(SAS) MPLS - Alcatel

7210 SERVICE ACCESS SWITCH
(SAS) MPLS
INSTALLATION GUIDE
December 2011
Document Part Number: 93-0257-01-11
*93-0245-01-11*
Copyright 2011 Alcatel-Lucent All rights reserved.
No portion of this document may be reproduced in any form or means without prior written permission from Alcatel-Lucent.
Information in this document is proprietary and confidential to Alcatel. The information in this document is subject to change. All
trademarks and registered trademarks are the property of the respective owners.
USA Requirements Only
Federal Communications Commission (FCC) Compliance Notice: Radio Frequency Notice
Note: This equipment has been tested and found to comply with the limits for a Class A digital device, pursuant to part 15 of the FCC Rules.
These limits are designed to provide reasonable protection against harmful interference when the equipment is operated in a commercial
environment. This equipment generates, uses, and can radiate radio frequency energy and, if not installed and used in accordance with the
instruction manual, may cause harmful interference to radio communications. Operation of this equipment in a residential area is likely to
cause harmful interference in which case the user will be required to correct the interference at his own expense.
Canadian Requirements Only
This Class A digital apparatus meets all requirements of the Canadian Interference-Causing Equipment Regulations.
Cet appareil numérique de la classe A respecte toutes les exigences du Réglement sur le matériel brouilleur du Canada.
Japan/Nippon Requirements Only
This is a Class A product. In a domestic environment this product may cause radio interference in which case the user may be required to
take adequate measures.
VCCI-A
Caution:
Use of controls or adjustments or performance of procedures other than those specified herein may result in hazardous laser
radiation exposure.
TABLE
OF
CONTENTS
Preface . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
7210 SAS-M Overview
7210 SAS-M Introduction and Features . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Switch Architecture . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Network Management Options . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Features . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Connectivity . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Hardware Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Ethernet Interfaces . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Management Port . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Console Port . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Alarm Interface Port. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Power Modules . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
DC power source failure detection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
USB Port . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Fan Tray . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
System LEDs and Buttons. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
System and Port LEDs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Port LEDs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
System Buttons and Switches . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
12
14
14
15
15
16
18
18
19
20
22
24
27
27
29
30
30
32
Installing the 7210 SAS-M
Site Preparation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Selecting a Site . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Ethernet Cabling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Equipment Checklist . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Installing Your Switch . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Rack Mounting. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Desktop or Shelf Mounting . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Grounding the Chassis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Connecting to a Power Source . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Connecting to AC Power . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Connecting to DC Power . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Connecting to the Console Port . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Warnings and Notes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Installation Preparation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Locking Mechanisms . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Installing SFP/XFPs. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Removing SFP/XFPs. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
34
34
34
35
36
36
38
39
41
41
42
44
46
47
47
48
48
Configuring the 7210 SAS-M
Diagnostics . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 50
Post Installation Status . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 50
Initializing the System and Downloading Software . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 51
7210 SAS-M Installation Guide
Page 3
Table of Contents
Booting a 7210 SAS-M in the Lab . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Booting a 7210 SAS-M using the image on Flash (with the image shipped by factory) . . . . . . . . .
Booting a 7210 SAS-M From the Network . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Using the Out-of-Band Ethernet Management port to boot 7210 from the nework: . . . . . . . . . . . .
Downloading the TiMOS Software to the Internal Flash. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Establishing Router Connections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Console Connection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Telnet Connection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Running Telnet . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
51
52
54
60
63
65
65
66
67
Troubleshooting
Diagnosing Switch Indicators . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Power and Cooling Problems . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Installation. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
In-Band Access. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
70
71
72
73
Appendix A: Specifications
Specifications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 76
Japan VCCI Class A Declaration. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 77
RoHS and WEEE. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 77
Appendix B: Pin Assignments
Management Port Pin Assignments . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 80
Console Port Pin Assignment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81
Appendix C: Alarm Pin Assignments
Alarm Port Pin Assignments . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 84
Page 4
7210 SAS-M Installation Guide
LIST
OF
TABLES
Preface
Table 1:
Information Symbols . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .10
7210 SAS-M Overview
Table 2:
Table 3:
Table 4:
Table 5:
Table 6:
Table 7:
Table 8:
Table 9:
Table 10:
Table 11:
7210 SAS-M Front Panel Features . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .16
7210 SAS-M 24F XFPand 7210 SAS-M 24F XFP ETR Front Panel Features . . . . . . . . . . . . . .17
Alarm Interface Port Pinouts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .20
Power Module LEDs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .22
Power Source Failure Detection Capability . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .25
7210 SAS-M System LEDs and Buttons . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .29
System and Port Status LEDs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .30
Port LEDs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .30
Port LED Key Descriptions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .31
Front Panel Buttons and Switches . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .32
Installing the 7210 SAS-M
Table 12:
Serial Cable Wiring . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .44
Configuring the 7210 SAS-M
Table 13:
Console Configuration Parameter Values . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .65
Troubleshooting
Table 14:
Troubleshooting . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .70
Appendix A: Specifications
Table 15:
7210 SAS-M Specifications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .76
Appendix B: Pin Assignments
Table 16:
Table 17:
10/100BASE-TX MDI and MDI-X Port Pinouts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .80
Serial Cable Wiring . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .81
Appendix C: Alarm Pin Assignments
Table 18:
Alarm Interface Port Pinouts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .84
7210 SAS-M Installation Guide
Page 5
List of Tables
Page 6
7750 SR-12
LIST
OF
FIGURES
7210 SAS-M Overview
Figure 1:
Figure 2:
Figure 3:
Figure 4:
Figure 5:
Figure 6:
Figure 7:
Figure 8:
Figure 9:
7210 SAS-M 24F Front Panel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .12
7210 SAS-M 24F 2XFP and 7210 SAS-M 24F 2XFP ETR Front Panel . . . . . . . . . . . . . . . . . . .13
7210 SAS-M 24F Front Panel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .16
7210 SAS-M 24F XFP and 7210 SAS-M 24F XFP ETR Front Panel . . . . . . . . . . . . . . . . . . . . .17
AC and DC Power Modules . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .22
Fan Tray . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .27
Removing and Replacing the Fan Tray and Air Filter . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .28
System LEDs and Buttons . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .29
SFP Port LEDs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .31
Installing the 7210 SAS-M
Figure 10:
Figure 11:
Figure 12:
Figure 13:
Figure 14:
Attaching the Brackets . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .36
Installing the Switch in a Rack . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .37
Attaching the Adhesive Feet . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .38
Connecting to a -48 VDC Power Source. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .43
Connecting to a +24 VDC Power Source . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .43
Configuring the 7210 SAS-M
Figure 15:
7210 SAS-M Boot Process . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .51
Troubleshooting
Appendix A: Specifications
Appendix B: Pin Assignments
Appendix C: Alarm Pin Assignments
Figure 16:
Figure 17:
DB-15 Alarm Connector . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .84
Alarm Input Connection Diagram . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .86
7210 SAS-M Installation Guide
Page 7
List of Figures
Page 8
7210 SAS-M Installation Guide
Preface
About This Manual
This guide provides site preparation recommendations, step-by-step procedures to rack mount the
Alcatel-Lucent 7210 Service Access Switch MPLS (SAS-M)® (i.e. 7210 SAS-M 24F, 7210 SASM 24F 2XFP, and 7210 SAS-M 24F 2XFP ETR), and instructions to install and configure the
TiMOS software.
This guide hereafter refers to all the variants (i.e. 7210 SAS-M 24F, 7210 SAS-M 24F 2XFP, and
7210 SAS-M 24F 2XFP ETR) as 7210 SAS-M. Any differences amongst the variants are called
out separately, as applicable.
Each 7210 SAS-M router is shipped with rack-mounting brackets, a console cable, power cord
(AC only), and rubber feet.
Warnings and Notes
Observe the warnings and notes to avoid injury or router damage during installation and
maintenance. Follow the safety procedures and guidelines when working with and near electrical
equipment. Warning statements and notes are provided in each chapter.
Audience
This guide is intended for network installers and system administrators who are responsible for
installing, configuring, or maintaining networks. This guide assumes you are familiar with
electronic and networking technologies.
7210 SAS-M Installation Guide
Page 9
Information Symbols
Table 1 describes symbols contained in this guide.
Table 1: Information Symbols
Symbol
Meaning
Description
Danger
This symbol warns that improper handling and installation could result in bodily
injury. An electric shock hazard could exist. Before you begin work on this
equipment, be aware of hazards involving electrical circuitry, networking
environments, and instigate accident prevention procedures.
Caution
This symbol warns that improper handling and installation could result in
equipment damage or loss of data.
Warning
This symbol warns that improper handling may reduce your component or
system performance.
Note
This symbol provides additional operational information.
Class 1 laser products are listed in the MDA installation guides. Only approved
Class 1 replaceable laser transceivers should be used with this product.
Class 1 Laser Product
Technical Support
If you purchased a service agreement for your 7210 SAS-M and related products from a distributor
or authorized reseller, contact the technical support staff for that distributor or reseller for
assistance. If you purchased an Alcatel-Lucent service agreement, contact technical assistance at:
Web:
Page 10
http://www1.alcatel-lucent.com/comps/pages/carrier_support.jhtml
7210 SAS-M Installation Guide
7210 SAS-M Overview
This chapter describes the 7210 SAS-M features and includes the following sections:
•
7210 SAS-M Introduction and Features on page 12
•
Switch Architecture on page 14
•
Features on page 15
•
Hardware Description on page 16
7210 SAS-M Installation Guide
Page 11
7210 SAS-M Introduction and Features
7210 SAS-M Introduction and Features
The 7210 SAS-M is a multilayer service-aware MPLS-capable switch. The switch is available as
two variants, as follows:
•
7210 SAS-M 24F with support for up to 24 100/1000 SFP ports
•
7210 SAS-M 24F 2XFP and 7210 SAS-M 24F 2XFP ETR with support for up to 24 100/
1000 SFP ports and up to 2 XFP (10G) ports
The 7210 SAS-M and its variants have one 10/100BASE-TX management port for dedicated
management access.
7210 SAS-M
Service Access Switch
24 SFP
Crit
SR72001A
Figure 1: 7210 SAS-M 24F Front Panel
The 7210 SAS-M 24F includes the following features:
• 24 100/1000 SFP ports
• One RJ-45 management port for firmware upgrade or system management
• One RJ-45 console (RS-232 interface) connector for device management
• Embedded SR OS
• Compact size: 1.5RU height, 19-inch rack-mountable metal enclosure, 10-inch depth (ETSI)
Page 12
7210 SAS-M Installation Guide
7210 SAS-M Overview
Crit
SR72029
Figure 2: 7210 SAS-M 24F 2XFP and 7210 SAS-M 24F 2XFP ETR Front Panel
The 7210 SAS-M 24F 2XFP and 7210 SAS-M 24F 2XFP ETR include the following features:
•
24 100/1000 SFP ports and 2 10G XFP ports
•
One RJ-45 management port for firmware upgrade or system management
•
One RJ-45 console (RS-232 interface) connector for device management
•
7210 SAS-M 24F 2XFP ETR version supports extended temperature range
•
Embedded SR OS
•
Compact size: 1.5RU height, 19-inch rack-mountable metal enclosure, 10-inch depth
(ETSI)
Note: Except for the labeling, the 7210 SAS-M 24F 2XFP and 7210 SAS-M 24F 2XFP ETR
chassis are identical in terms of front panel appearance.
7210 SAS-M Installation Guide
Page 13
Switch Architecture
Switch Architecture
The 7210 SAS-M employs a wire-speed, non-blocking switching fabric. This permits
simultaneous wire-speed transport of multiple packets at low latency on all ports. The switch also
features full-duplex capability on all ports, that effectively doubles the bandwidth of each
connection.
Network Management Options
This switch contains a comprehensive array of LEDs for at-a-glance monitoring of network and
port status. It also includes a management agent that enables you to configure or monitor your
switch using its CLI, or by using SNMP applications.
To manage the switch, you can make a direct connection to the console port (out-of-band Ethernet
management port) or you can manage it by using a network connection (in-band SFP or XFP
ports) using Telnet/SSH or SNMP-based network management software.
The management port provides a dedicated management channel that operates outside of the data
transport network. This makes it possible to reconfigure or troubleshoot the switch over either a
local or remote connection to the management port when access using the data channel is not
possible or deemed insecure.
Page 14
7210 SAS-M Installation Guide
7210 SAS-M Overview
Features
The 7210 SAS-M includes the following features:
•
Wire speed, non-blocking, service-aware MPLS switch
•
24 100/1000 SFP ports are available in 7210 SAS-M
•
2 10G XFP ports are available in 7210 SAS-M 24F 2XFP and 7210 SAS-M 24F 2XFP
ETR
•
7210 SAS-M 24F 2XFP ETR supports extended temperature range.
•
Powered by SR OS
•
Per-service quality of service (QoS) with up to eight levels of class-based queuing per port
•
Per-service OAM toolkit with IEEE 802.1ag, IEEE 802.3ah and local service mirroring
•
Supports NULL and Dot1Q access SAPs.
•
Dual homed connections uplinks to separate aggregation devices
•
Flexible deployment options with support for mesh and ring topologies
•
MEF 9 and MEF 14 certified platform
•
Managed by the 5620 SAM
•
Provides four isolated alarm inputs and two dry contacts that relay outputs through a
DB-15 interface on the front panel
•
Hot-swappable, redundant, load sharing AC or DC power and fan modules
Connectivity
The 7210 SAS-M includes the following connectivity features:
•
100/1000 fiber-optic SFP ports.
•
10G XFP ports on 7210 SAS-M 24F 2XFP and 7210 SAS-M 24F 2XFP ETR only
•
IEEE 802.3-2005 Ethernet, Fast Ethernet, Gigabit Ethernet, and Ten-Gigabit (only on
7210 SAS-M 24F 2XFP and 7210 SAS-M 24F 2XFP ETR) compliance ensures
compatibility with standards-based network cards and switches from any vendor.
7210 SAS-M Installation Guide
Page 15
Hardware Description
Hardware Description
1
2a
4
6
7
9
10
12
7210 SAS-M
Service Access Switch
24 SFP
Crit
2b
3
5
8
11
SR72001
Figure 3: 7210 SAS-M 24F Front Panel
Table 2: 7210 SAS-M Front Panel Features
Key
Page 16
Description
1
Ground and DC power connection
2
Power trays
Power tray one to fit power supply 2a
Power tray two to fit power supply 2b
3
LEDs
4
Alarm connector
5
USB port
6
Alarm cut off button
7
Reset button
8
Expansion slot
9
100/1000 SFP port LEDs
10
Management port
11
Console port
12
Fan tray
7210 SAS-M Installation Guide
7210 SAS-M Overview
1
2a
4
6
7
9
11
13
Crit
2b
3
5
8
10
12
SR72029A
Figure 4: 7210 SAS-M 24F XFP and 7210 SAS-M 24F XFP ETR Front Panel
Table 3: 7210 SAS-M 24F XFPand 7210 SAS-M 24F XFP ETR Front Panel Features
Key
Description
1
Ground and DC power connection
2
Power trays
Power tray one to fit power supply 2a
Power tray two to fit power supply 2b
3
LEDs
4
Alarm connector
5
USB port
6
Alarm cut off button
7
Reset button
8
Expansion slot
9
100/1000 SFP port LEDs
10
XFP ports
7210 SAS-M Installation Guide
Page 17
Hardware Description
Table 3: 7210 SAS-M 24F XFPand 7210 SAS-M 24F XFP ETR Front Panel Features
Key
Description
11
Management port
12
Console port
13
Fan tray
Ethernet Interfaces
The 7210 SAS-M provides 24 100/1000 SFP ports. Each port can be used for a direct connection
to a subscriber’s Customer Premises Equipment (CPE), or as an uplink to another aggregation
node. The 7210 SAS-M supports 10/100/1000 Base-T copper SFPs. In addition, the 7210 SAS-M
24F 2XFP and 7210 SAS-M 24F 2XFP ETR variants support 2 x 10G XFP ports. This port can
serve as a network uplink to another aggregation node or as a direction to a subscriber's CPE.
Management Port
The management port provides a dedicated management interface that is segregated from data
traffic crossing the other ports.
Page 18
7210 SAS-M Installation Guide
7210 SAS-M Overview
Console Port
The console port uses an RJ-45 connector with serial pinouts (see Table 12) that enables a
connection to a terminal for performing switch monitoring and configuration operations. The
terminal may be a PC or workstation that is running terminal emulation software, or a terminal
configured as a Data Terminal Equipment (DTE) connection. A null-modem wired serial cable is
supplied with the switch for connecting to this interface.
The serial port configuration requirements are as follows:
• Default Baud rate – 115200 bps
• Character Size – 8 Characters
• Parity – None
• Stop bit – One
• Data bits – 8
• Flow control – none
7210 SAS-M Installation Guide
Page 19
Hardware Description
Alarm Interface Port
The alarm interface port is a D-type 15-pin connector that supports a critical alarm output, a major
alarm output, and four alarm inputs. When your system has a critical or major alarm, the CPU will
drive the alarm relay to issue the alarm output and turn on the critical or major LED. If you push
the alarm cut off (ACO) button, the relay will be released but the LED will stay on until the alarm
is cleared.
The system signals the appropriate alarm output for the following events:
•
Fan failure - Critical alarm is raised.
•
On power supply failure - Critical alarm is raised. The critical alarm is cleared and a major
alarm is raised if the failed power supply is removed).
•
On power source failure - Critical alarm is generated and the system's status LED turns
amber in color and blinks.
•
Chassis temperature threshold exceeded - Major alarm is raised.
The system also supports four alarm inputs. The input voltage range is from 24V to 48V. If an
alarm input is active, the CPU will process it, output it to the CLI, and issue an SNMP trap. An
alarm input can also be configured to drive the appropriate alarm output pin. Please refer the
System Basics user guide for more details on configuring the alarm inputs.
See Table 4 for the alarm interface port pinouts.
Table 4: Alarm Interface Port Pinouts
Pin
Page 20
Name
Function
1
CRIT_ALARM_CNTR
Common contact for Critical alarm relay.
2
CRIT_ALARM_NO
Normally open during Critical alarm state.
3
MJR_ALARM_NC
Normally closed during Major alarm state.
4
N/C
N/C
5
ALARM_IN4_EXT_+
External alarm input 4 (external relay dry contact closure
to pin 12).
6
ALARM_IN3_EXT_+
External alarm input 3 (external relay dry contact closure
to pin 13).
7
ALARM_IN2_EXT_+
External alarm input 2 (external relay dry contact closure
to pin 14).
7210 SAS-M Installation Guide
7210 SAS-M Overview
Table 4: Alarm Interface Port Pinouts
Pin
Name
Function
8
ALARM_IN1_EXT_+
External alarm input 1 (external relay dry contact closure
to pin 15).
9
CRIT_ALARM_NC
Normally closed during Critical alarm state.
10
MJR_ALARM_CNTR
Common contact for Major alarm relay.
11
MJR_ALARM_NO
Normally open during Major alarm state.
12
ALARM_IN4_EXT_RTN
External alarm input 4 (external relay dry contact closure
from pin 5).
13
ALARM_IN3_EXT_RTN
External alarm input 3 (external relay dry contact closure
from pin 6).
14
ALARM_IN2_EXT_RTN
External alarm input 2 (external relay dry contact closure
from pin 7).
15
ALARM_IN1_EXT_RTN
External alarm input 1 (external relay dry contact closure
from pin 8).
RTN refers to the negative side of the floating external power supply. This power supply must not
be connected to chassis ground and should be 18-50 volts DC at 100 ma. Please refer to Appendix ,
“Appendix C: Alarm Pin Assignments,” on page 83 for further information.
7210 SAS-M Installation Guide
Page 21
Hardware Description
Power Modules
7210 SAS-M 24F 2XFP ETR variant provides three power module options: -48V, +24V and
universal AC. See Figure 5 for an illustration of the power modules.
For specifications on the power supply modules and external input power requirements, see
"Connecting to a Power Source" on page 41 and "Appendix A: Specifications" on page 75.
-48V
1
+24V ETR
2
3
SR72005
Figure 5: AC and DC Power Modules
Table 5: Power Module LEDs
LED
AC, -48V,+24, +12V
Page 22
Condition
Status
Green
DC or AC power is functioning normally.
Off
External power not connected or has failed.
7210 SAS-M Installation Guide
7210 SAS-M Overview
The -48V/+24V/AC LEDs on the left indicate the status of external power. The +12V LED on the
right indicates the status of the internal power conversion process.
Note: You must use AC and/or DC power supplies with your 7210 SAS-M. AC and DC power
supplies can be used simultaneously.
Note: The 7210 SAS-M 24F 2XFP ETR variant must use a power supply which supports
extended temperature range.
Note: The +24V DC power module must not be used simultaneously with the -48V DC power supply.
Note: The +24V DC power module is supported on the 7210 SAS-M 24F 2XFP ETR variant
chassis ONLY.
7210 SAS-M Installation Guide
Page 23
Hardware Description
DC power source failure detection
The 7210 platform provides capability to detect DC power source (-48V or +24V source) failure.
The 7210 chassis allows two DC power sources to be connected to the chassis. If the system
detects that the DC power source has failed, it raises a critical alarm (the Critical LED is lit and the
Critical Alarm output pin is triggered) and the system's status LED turns amber and blinks.. The
alarm is cleared if the DC power source is restored. There is no user configuration required to
enable this feature. The software enables this feature automatically by detecting the capability of
the hardware platform.
The system has two slots to plug in AC or DC power supplies. It associates the DC power supply
in top slot with power source feed #A (-48V or +24V Ret-A on the chassis) and DC power supply
in the bottom slot with power source feed #B (-48V or +24VRetB on the chassis). The system
detects the failure of power source feed #A only if the DC power supply is plugged into the top
slot. Similarly, the system detects the failure of power source feed #B only if the DC power supply
is plugged into the bottom slot. The trap message generated by the system indicates that there was
an input failure for the power supply associated with power input feed that failed.
Note: New traps needs to be explicitly enabled by the user and are suppressed by
default.
Notes: The power feeds are summed up internally before feeding the power supply units.
Hence, the DC power supply units will output power even if one of the power source feed is
available.
Note: Please check the release notes to know the software release that supports this feature.
Page 24
7210 SAS-M Installation Guide
7210 SAS-M Overview
The following table lists the conditions under which the system detects a power source failure.
Table 6: Power Source Failure Detection Capability
Power Feed
#A
(Available/
Failed)
Power Feed
#B
(Available/
Failed)
Power
Supply in
Top Slot
(PS1)
Power
Supply in
Bottom
Slot
(PS2)
Alarm
Generated
(Yes/No)
Available
Available
DC
DC
No
Available
Failed
DC
DC
Yes
PS2 input failure / PS2
output OK
Failed
Available
DC
DC
Yes
PS1 input failure / PS1
output OK
Failed
Failed
DC
DC
Available
Available
None
DC
No
Available
Failed
None
DC
Yes
PS2 input failure / PS2
output OK
Failed
Available
None
DC
No
Input failure / Not
detected
Failed
Failed
None
DC
Available
Available
DC
None
No
Available
Failed
DC
None
No
Input failure / Not
detected
Failed
Available
DC
None
Yes
PS1 input failure / PS1
output OK
Failed
Failed
DC
None
Available
Available
AC
DC
No
Available
Failed
AC
DC
Yes
PS2 input failure / PS2
output OK
Failed
Available
AC
DC
No
Input failure / Not
detected
Failed
Failed
AC
DC
Yes
PS2 input failure / PS2
output failure
Available
Available
DC
AC
No
7210 SAS-M Installation Guide
Notes
No power to system
No power to system
No power to system
Page 25
Hardware Description
Table 6: Power Source Failure Detection Capability
Page 26
Power Feed
#A
(Available/
Failed)
Power Feed
#B
(Available/
Failed)
Power
Supply in
Top Slot
(PS1)
Power
Supply in
Bottom
Slot
(PS2)
Alarm
Generated
(Yes/No)
Notes
Available
Failed
DC
AC
No
Input failure / Not
detected
Failed
Available
DC
AC
Yes
PS1 input failure / PS1
output OK
Failed
Failed
DC
AC
Yes
PS1 input failure / PS1
output OK
7210 SAS-M Installation Guide
7210 SAS-M Overview
USB Port
The USB port is reserved for future use.
Fan Tray
A hot-swappable fan tray on the right side of the front panel contains three fans that provide
cooling for the chassis. See Figure 6 for an illustration of the fan tray.
The fans are controlled by the system software, and their speed is set according to the
environmental temperature surrounding the switch. Allow at least three inches of clearance on the
side of the rack to ensure proper airflow intake cooling system. The fan trays must be in place
before the chassis is powered on.
SR72004
Figure 6: Fan Tray
7210 SAS-M Installation Guide
Page 27
Hardware Description
The fan tray also contains an air filter. The filter tray must always be installed while the chassis is
powered up. The air filter prevents large particles, debris, and dust from entering and circulating
through the system. Inspect your air filter monthly and clean it when accumulated dust is present.
To inspect and remove your air filter, see Figure 7 and perform the following steps:
Step 1
Loosen the captive screws on the fan tray (1).
Step 2
Carefully remove the fan tray from the router chassis and remove the air filter (2) to
inspect it and clean it if necessary.
Step 3
After inspecting and cleaning the air filter, replace it in the fan tray so that the edge of the
air filter is flush with the rear of the fan tray.
Step 4
Replace the fan tray and tighten the captive screws.
1
2
1
Figure 7: Removing and Replacing the Fan Tray and Air Filter
Page 28
7210 SAS-M Installation Guide
7210 SAS-M Overview
System LEDs and Buttons
The LEDs are located on the front panel and the power module trays. See Figure 8 for the location
of the system LEDs and buttons, Table 7 for key descriptions, and Table 8 for alarm descriptions.
2
3
4
5
7210 SAS-M
Service Access Switch
24 SFP
Crit
1
6
SR72025
Figure 8: System LEDs and Buttons
Table 7: 7210 SAS-M System LEDs and Buttons
Key
Description
1
Alarm LEDs and 10G port LEDs for 7210 SAS M 24F 2XFP
and 7210 SAS-M 24F 2XFP ETR only
2
Alarm Cut Off button
3
Reset button
4
100/1000 SFP port LEDs
5
Management port
6
Console port
7210 SAS-M Installation Guide
Page 29
Hardware Description
System and Port LEDs
Table 8: System and Port Status LEDs
LED
Condition
Status
Critical
Red
Indicates the presence of a new critical alarm.
Major
Amber
Indicates the presence of a new major alarm.
Fan
Off
Indicates that the fans are functioning properly.
Red
Indicates that one or more of the fans has failed, or that the fan
tray is not connected.
Note: The LED blinks shortly during the boot process.
Green
The system has completed boot phase and is running normally.
Note: The status LED turns amber and blinks on power source
failure.
Status
Port LEDs
The port LEDs are described in Table 9.
Table 9: Port LEDs
LED
SFP ports 1–24
XFP ports 25, 26
Condition
Status
Green
Port has a valid link.
Flashing Green
Flashing indicates activity on the port.
Off
The link is down.
Green
Port has a valid link.
Flashing Green
Flashing indicates activity on the port.
Off
The link is down.
See Figure 9 for an illustration of two ports and their corresponding LEDs. See Table 11 key
descriptions.
Page 30
7210 SAS-M Installation Guide
7210 SAS-M Overview
5
1
3
2
4
5
SR72007
Figure 9: SFP Port LEDs
Table 10: Port LED Key Descriptions
Key
Description
1
Reserved.
2
LED that indicates status for an odd-numbered port. Odd-numbered ports are in the
top row.
3
Reserved.
4
LED that indicates status for an even numbered port. Even-numbered ports are in the
bottom row.
5
SFP slots.
7210 SAS-M Installation Guide
Page 31
Hardware Description
System Buttons and Switches
See Table 11 for descriptions of front panel buttons and switches.
Table 11: Front Panel Buttons and Switches
Button/Switch
Power Module Switch
Page 32
Condition
Status
0
Standby mode if switch is connected to a power source.
1
AC or DC power is applied to the switch.
ACO (Alarm Cut Off)
Not pushed
Normal operating mode.
Reset (Recessed)
Not pushed
Normal operating mode. Push to reset hardware.
7210 SAS-M Installation Guide
Installing the 7210 SAS-M
This chapter describes site preparation and installation of your 7210 SAS-M and includes the
following sections:
•
Site Preparation on page 34
•
Installing Your Switch on page 36
7210 SAS-M Installation Guide
Page 33
Site Preparation
Site Preparation
Selecting a Site
Mount the 7210 SAS-M in a standard 19-inch equipment rack or on a flat surface. When you
mount your switch on a flat surface, ensure that the four rubber feet are installed on the bottom of
the box.
The site should be a weather-protected and temperature-controlled location, and should include the
following criteria:
•
Maintain site temperature within 0 to 50 ºC (32 to 122 ºF) and its humidity within 5% to
95%, non-condensing for the 7210 SAS-M. For the 7210 SAS-M 24F 2XFP ETR variant,
maintain site temperature within -40 to 65 ºC (-49 to 149 ºF).
•
Provide adequate space on the front and two sides of the unit to enable servicing and
proper air flow.
•
Ensure a secure environment in which only authorized and trained service personnel are
allowed to service the unit (IEC 60950 safety requirement).
Ethernet Cabling
To ensure proper operation when installing switches into a network, make sure that the cables are
suitable for 100/1000 fiber-optic or 10/100/1000Base-T copper operation, as appropriate. Make
sure your installation complies with the following guidelines:
Page 34
•
Cable type: Unshielded twisted pair (UTP) or shielded twisted pair (STP) cables with RJ45 connectors; Category 3 or better for 10BASE-T, Category 5 or better for 100BASE-TX,
and Category 5, 5e or 6 for 1000BASE-T.
•
Make sure your cables are not damaged and RJ-45 connectors are well connected.
•
Avoid installing copper cables close to strong electromagnetic fields generated by electric
generators, elevator engines, or similar heavy electric machines.
•
Make sure you only use SFPs and XFPs that are supported by Alcatel-Lucent.
7210 SAS-M Installation Guide
Installing the 7210 SAS-M
Equipment Checklist
After unpacking your switch, check the contents to make sure all the components are present.
Before installation, make sure you have all the necessary equipment.
7210 SAS-M Installation Guide
Page 35
Installing Your Switch
Installing Your Switch
Rack Mounting
If you plan to rack-mount your switch, make sure you have the following equipment available:
•
Four mounting screws for each device you plan to install in a rack (not included)
•
A screwdriver (Phillips or flathead, depending on the type of screws used)
To rack-mount your 7210 SAS-M:
Step 1
Attach the brackets to the device using the screws provided in the Bracket Mounting Kit.
See Figure 10.
SR72009
Figure 10: Attaching the Brackets
Step 2
Page 36
Mount the 7210 SAS-M in the rack, using four rack-mounting screws (not provided). See
Figure 11.
7210 SAS-M Installation Guide
Installing the 7210 SAS-M
SR72010
Figure 11: Installing the Switch in a Rack
Step 3
If you are installing a single switch, proceed to Grounding the Chassis on page 39.
Step 4
If installing multiple switches, mount them in the rack, one below the other, in any order.
7210 SAS-M Installation Guide
Page 37
Installing Your Switch
Desktop or Shelf Mounting
Step 1
Attach the four adhesive feet to the bottom of the first switch. See Figure 12.
SR72026
Figure 12: Attaching the Adhesive Feet
Page 38
Step 2
Set the device on a flat surface near an external power source, making sure there are at
least three inches of space on the front and sides for proper air flow.
Step 3
If you are installing a single switch, proceed to "Grounding the Chassis" on page 39.
Step 4
If you are installing multiple switches, attach four adhesive feet to each switch. Place each
device squarely on top of the one below, in any order.
7210 SAS-M Installation Guide
Installing the 7210 SAS-M
Grounding the Chassis
The router is suitable for installation as part of the Common Bonding Network (CBN) or an
Isolated Bonding Network (IBN). The router is suitable for installation in Network
Telecommunication Facilities or locations where the NEC applies.
Before powering on the switch, ground the switch to earth as described below.
Step 1
Ensure that the rack on which the switch is to be mounted is properly grounded.
Step 2
Ensure that you have made a suitable electrical connection to the grounding point on the
rack. Ensure that no paint or isolating surface treatment is present on the grounding point.
Step 3
Disconnect all power cables to the switch.
Step 4
The switch chassis is connected internally to 0 V. This circuit is connected to the doublehole grounding terminal on the rear of the switch (lower right corner) using Metric M4-.7
pitch screws and a Panduit LCCF8-14A-L or compatible ground lug. The surface area
around this terminal is not painted in order to provide for a good connection. Attach a #8
AWG stranded copper wire to the grounding terminal on the switch.
Step 5
Attach the grounding wire to the ground point on the rack.
CAUTION: The earth connection must not be removed unless all supply connections have been
disconnected.
Warning: Chassis ground cables are not included. Use only power cords that have a
grounding (earthing) path. Use only power cords that have a grounding (earthing) path. Main
grounding (earthing) connection points are through the IEC60320 appliance inlets. Grounding
(earthing) points on the rear of the equipment are for equipotential bonding only and are not
the safety grounding (earthing) points for the equipment. Lack of proper grounding (earthing)
of the equipment may result in a safety hazard and excessive electromagnetic emissions. See
Table 11 on page 47 for descriptions of common grounding-type (earthing) power supply
cords.
Warning: If you ground the equipment by a method other than those provided in this manual,
those means should be in compliance with all local wiring regulations and practices.
7210 SAS-M Installation Guide
Page 39
Installing Your Switch
Warning: To comply with the GR-1089-CORE, Issue 03, requirement R4-9 [31] standard for
electromagnetic compatibility and safety, all intra-building ports are specified for use with
shielded and grounded cables at both ends.
Warning: The intra-building port(s) of the equipment or sub-assembly is suitable for
connection to intrabuilding or unexposed wiring or cabling only. The intra-building port(s) of the
equipment or sub-assembly must not be metallically connected to interfaces that connect to
the Outside Plant (OSP) or its wiring. These interfaces are designed for use as intra-building
interfaces only (Type 2 or Type 4 ports as described in GR-1089-CORE, Issue 4) and require
isolation from the exposed OSP cabling. The addition of primary protectors is not sufficient
protection in order to connect these interfaces metallically to OSP wiring.
Warning: Bare conductors must be coated with an appropriate antioxidant compound before
crimp connections are made. All unplated connectors, braided strap, and bus bars must be
brought to a bright finish and then coated with an antioxidant before they are connected.
Warning: The equipment under test (EUT) is specified for DC-I power configurations. The
battery returns must remain isolated until they reach the main power bus.
Danger: Only electrical service personnel should perform wiring and cabling to the system.
Danger: All power to the equipment rack or cabinet should be disconnected before the
installation.
Danger: Power cable(s) must meet your local electric code requirements.
Danger: The power supply on/standby switch is not intended to be used as the chassis ON/
OFF switch. Unplug the power cord from the power source and disconnect the cord from the
receptacle on the power supply module to remove power.
Danger: An external circuit breaker no greater than 15A must be located within a readily
accessible distance of the equipment. This is intended as the disconnect device.
Page 40
7210 SAS-M Installation Guide
Installing the 7210 SAS-M
Connecting to a Power Source
This switch supports both AC and DC power supply modules.
Notes: The switch is designed to accept up to two AC or two DC power supplies. The switch also
accepts a single AC and single DC power supply.
Notes: The 7210 SAS-M 24F 2XFP ETR version must use the extended temperature range power
supplies.
Connecting to AC Power
Notes: In order to comply with the GR-1089 Lightning Criteria for Equipment Interfacing With AC
Power Ports, an external Surge Protective Device (Perma Power Model # PXD309) is intended to be
used at the AC input of the router.
To connect the switch to a power source:
Step 1
Verify that the external AC power supply has the following rating: 100-240VAC, 50/60
Hz, 2A.
Step 2
Make sure the AC power module is installed and powered OFF before you plug the power
cable into the AC power source.
Step 3
Check the power module LEDs as the switch is powered on to verify that the AC LED
indicating external power status is on, and that the +12V LED indicating internal power
conversion is on. If not, recheck the power supply and power cable connections at the
supply source and at the power module.
Step 4
A redundent AC power module may be hot swappable plugged in. However, for safety
precautions the main power cord should be connected after the AC power module is
installed.
Step 5
If you have installed both primary and redundant power supply modules, verify that the
LEDs on both modules are lit as indicated in the preceding step.
7210 SAS-M Installation Guide
Page 41
Installing Your Switch
Connecting to DC Power
The 7210 SAS-M chassis supports the -48V and +24V DC power modules. Hence, the steps below
are applicable for either the -48V or the +24V DC power modules.
Notes: Below the DC power entry block is an additional chassis ground point for attaching a
DC power chassis ground if required by local electrical codes. The ground point should be connected
with an M4 screw and a terminal lug as specified by local electrical codes.
Notes: Do NOT install BOTH the -48V and the +24V AC PEMs in the same chassis.
Notes: If a single power feed (either #A or #B) is connected to provide power to the system, it supplies power
to both the power supplies, if both of them plugged in. The DC power feeds, #A and #B, are internally bridged
using a diode.
To connect DC power:
Step 1
Before a VDC power supply module can be used, you must connect an external DC power
source to the DC power connection on the left side of the front panel (see Figure 1). The
external DC power supply must be between -36 to -72 VDC, and protected with a circuit
breaker.
WARNING:
Before wiring the DC plug or connecting power to the switch, ensure that power to the feed lines is
turned off at the supply circuit breaker or disconnected from the power bus.
Page 42
Step 2
To provide adequate circuit protection between the DC power supply and the switch, all
intermediate wiring and circuitry should be rated to carry a load at least two times the
maximum rating for this switch (see Appendix A: Specifications on page 75).
Step 3
The wiring between the DC power supply and the switch must be stranded copper wire
within the range of 16 to 20 AWG in accordance with local electrical codes.
Step 4
Connect the VDC power feed using the VDC input and RETA/B (return) lines for power
source A and B, respectively. Insert the wires into the DC input plug (using a small flattip screwdriver). Color code the wiring according to local standards to ensure that the
input power and ground lines can be easily distinguished.
7210 SAS-M Installation Guide
Installing the 7210 SAS-M
Figure 13 illustrates how to connect a -48 VDC power source to the chassis:
-48V (A)(Pin 1)
-48V
RTN
Return (A)(Pin 2)
7210SASdc_0015
Return (B)(Pin 4)
-48V (B)(Pin 3)
Figure 13: Connecting to a -48 VDC Power Source
Figure 14 illustrates how to connect a +24 VDC power source to the chassis:
Ground (A)(Pin 1)
+24V (A)(Pin 2)
7210SASdc_0014
+24V (B)(Pin 2)
Ground (B)(Pin 1)
Figure 14: Connecting to a +24 VDC Power Source
7210 SAS-M Installation Guide
Page 43
Installing Your Switch
WARNING:
If the power leads are plugged into the wrong holes, the power supply will not work properly and
may damage the switch.
Step 5
After the power source is tuned on, set the power button on the front of the power supply
module to the ON position (marked “— ').
Step 6
Check the LEDs on the power supply module as the switch is powered on to verify that
the -48V/+24V LED indicating external power status is on, and that the +12V LED
indicating internal power conversion is on. If not, recheck the power supply and power
cable connections at the supply source and at power supply module.
Step 7
If you have installed both a primary and redundant power supply module, verify that the
LEDs on both modules are lit as indicated in the preceding step.
Connecting to the Console Port
The RJ-45 serial port on the front panel is used to connect to the switch for out-of-band console
configuration. The on-board configuration program can be accessed from a terminal or a PC
running a terminal emulation program.
The pin assignments used to connect to the serial port are provided in Table 12.
Table 12: Serial Cable Wiring
Page 44
RJ45
Pin
Usage
RTS
1
Used as defined. Should be connected
NC
2
Not used. Should not be connected
TXD
3
Used as defined. Should be connected
GND
4
Used as defined. Should be connected
GND
5
Used as defined. Should be connected
RXD
6
Used as defined. Should be connected
NC
7
Not used. Should not be connected
CTS
8
Used as defined. Should be connected
7210 SAS-M Installation Guide
SFP/XFPS
In This Chapter
This chapter describes how to replace Small Form Factor Pluggable (SFP) transceivers on
MDA ports that support these devices.
•
Warnings and Notes on page 46
•
Installation Preparation on page 47
•
Locking Mechanisms on page 47
•
Installing SFP/XFPs on page 48
•
Removing SFP/XFPs on page 48
7210 SAS-M Installation Guide
Page 45
Warnings and Notes
Warnings and Notes
Danger:
• Fiber optic equipment can emit laser or infrared light that can injure your eyes. Never look into an
optical fiber or connector port. Always assume that fiber optic cables are connected to a light
source.
Caution:
• Make sure the plug is inserted while you install or remove the SFP. Only remove the plug when you
are ready to attach network cables.
• Electrostatic discharge (ESD) damage can occur if router components, including SFPs, are
mishandled. Always wear an ESD-preventive wrist or ankle strap and always connect an ESD strap
to the grounding plug on the front of the chassis.
• Always place router components on an anti-static surface.
• Avoid bending fiber optic cable beyond its minimum bend radius.
• Do not exceed the recommended minimum 1 1/2-inch (3.81 cm) bend radius for fiber optic cables.
Warning:
• Do not remove the dust cover on the connector until you are ready to install the SFP.
Always replace the the dust cover when the SFP is removed.
Notes:
• Discard SFPs according to all local laws and regulations.
• SFPs are keyed to prevent incorrect insertion.
Page 46
7210 SAS-M Installation Guide
Installation Preparation
Clean the connector before inserting it to prevent transfer of small particles and contamination of
the transceiver. Do not interchange SFP/XFPs from one port to another without first cleaning the
connectors.
To clean the connector, you can either:
•
Wipe the side and end of the ferrule with a lint-free alcohol-dampened cloth.
•
Blow dry the ferrule with compressed air and inspect for lint. Do not insert the compressed
air nozzle into the receptacle when blowing out.
Locking Mechanisms
Alcatel-Lucent SFP/XFPs can use different lock and release methods. Possible lock and release
mechanisms include:
•
Locking handle—A locking handle (lever) in the front of the SFP/XFP that you gently
raise or lower to insert or remove from the port.
•
Bail — A bar or wire latch in the front of the SFP/XFP that you pull down and outward to
release the module.
•
Tabs on the sides of the SFP/XFP that you press inward.
7210 SAS-M Installation Guide
Page 47
Installation Preparation
Installing SFP/XFPs
To install an SFP/XFP transceiver:
Step 1
Remove the SFP/XFP from its anti-static packaging.
Step 2
Holding the SFP/XFP by its sides, slide the unit into the port until it clicks into place.
Step 3
Remove the plug from the SFP/XFP optical bore when you are ready to attach the network
cable.
Removing SFP/XFPs
If you are removing an SFP/XFP, have a replacement SFP/XFP or slot plug, an anti-static mat, and
a safety cap for the SFP/XFP transceiver ready.
To remove an SFP/XFP:
Step 1
Disconnect the network cable from the optical connector.
Step 2
Pull the lever located in the front of the SFP/XFP with your thumb and forefinger. Slide
the connector out of the port.
Step 3
Place the SFP/XFP on an anti-static mat or in an electro-static bag.
Step 4
Install an SFP/XFP replacement or re-insert the plug.
Step 5
Connect the network cable or place a safety cap over the optical transceiver.
Note: Verify that the temperature ratings for the SFPs and XFPs match those of the intended
operating environment.
Page 48
7210 SAS-M Installation Guide
Configuring the 7210 SAS-M
This chapter describes how to configure your 7210 SAS-M and contains the following sections:
•
Diagnostics on page 50
•
Initializing the System and Downloading Software on page 51
•
Establishing Router Connections on page 65
7210 SAS-M Installation Guide
Page 49
Diagnostics
Diagnostics
Post Installation Status
After successfully installing the switch, ensure that the LEDs show the following state:
•
Critical: OFF
•
Major: OFF
•
Fan: OFF
•
Status: Steady GREEN
If any of the above LEDs shows a different state, press the Reset button and wait for a few seconds
to let the system boot.
Page 50
7210 SAS-M Installation Guide
Configuring the 7210 SAS-M
Initializing the System and Downloading Software
The 7210 SAS-M ships with bootloader and TiMOS in flash. When the system is powered up for
the first time, the bootloader will attempt an auto-init procedure (see the System Basics Guide for
more information). The auto-init can, however, be interrupted and the boot operation can be
controlled manually.
Note: By default, 7210 platforms attempt the autoinit procedure unless interrupted by user and
forced to use Timos available in the flash.
Booting a 7210 SAS-M in the Lab
There are several ways to boot the 7210 SAS-M from the network. User can choose to boot the
device using one of the following options:
•
Using the image shipped along with the box to boot the device
•
Using the network to load the image and boot the device
The following sections describe how to boot the device using either of the options listed above.
FTP
Server
SAS-M
Console Cable
Port: 24
IP Address: 10.135.4.172/24
Gateway: 10.135.4.1
IP Address:
10.10.170.22/24
OSSG325
Figure 15: 7210 SAS-M Boot Process
7210 SAS-M Installation Guide
Page 51
Initializing the System and Downloading Software
Booting a 7210 SAS-M using the image on Flash (with the image shipped by
factory)
You will need the following:
•
A PC with a serial port and Hyperterminal
•
Cable that connects the console port of SAS-M to the serial port of PC
Connect the 7210's console port to serial port of the PC and then power on the 7210. The system
will start booting up with messages on the console similar to those shown below. Follow the
procedure given below to boot the system with the image on the flash.
Resetting...OK
Alcatel-Lucent 7210 Boot ROM. Copyright 2009-2011 Alcatel-Lucent.
All rights reserved. All use is subject to applicable license agreements.
Testing ROM load area...done
Relocating code...Jumping to RAM
Performing second stage RAM test....passed
Board Serial Number is 'NS1111C0115'
Bootlog started for Version A-V-3.0.B5-85
Build V-3.0.B5-85 bootrom/mpc 7xxx
Built on Wed Apr 20 13:52:05 IST 2011 by builder in /builder/3.0B5/panos/main
?Attempting to load from file cf1:/boot.tim
Version L-3.0.B5-85, Wed Apr 20 14:13:38 IST 2011 by builder in /builder/3.0B5/panos/main
text:(4782384-->20108848) + data:(1084015-->3891872)
Starting at 0xb000000...
PCIe: Port 0 Link UP
Total Memory: 512MB Chassis Type: sas Card Type: badami_7210
TiMOS-L-3.0.B5-85 boot/mpc ALCATEL SAS-M 6F4T 7210 Copyright (c) 2000-2011 Alcatel-Lucent.
All rights reserved. All use subject to applicable license agreements.
Built on Wed Apr 20 14:13:38 IST 2011 by builder in /builder/3.0B5/panos/main
TiMOS BOOT LOADER
Time from clock is THU APR 21 11:03:21 2011 UTC
Switching serial output to sync mode... done
Since the switch does not ship with a BOF, it will show the default settings.
Looking for cf1:/bof.cfg ... not found
Could not find bof.cfg on any of the local drives.
Default Settings:
-----------------------------------------------------------------------------------------------Contents of Boot Options File on cf1:
#uplinkA Port Settings:
uplinkA-port 1/1/1
uplinkA-address 0
uplinkA-vlan 0
#uplinkB Port Settings:
uplinkB-port 1/1/2
uplinkB-address 0
uplinkB-vlan 0
Page 52
7210 SAS-M Installation Guide
Configuring the 7210 SAS-M
#System Settings:
wait 3
persist off
console-speed 115200
Hit a key within 2 seconds to change boot parameters...
Press any key.
Enter password to edit the Boot Options File
Or CTRL-D to exit the prompt
Password:
The default password is ‘password’.
You must supply some required Boot Options. At any prompt, you can type:
"restart" - restart the query mode.
"reboot" - reboot.
"exit" - boot with with existing values.
"diag" - enter the diag shell.
"reset" - reset the bof and reboot.
Press ENTER to begin, or 'flash' to enter firmware update...
Press Enter.
Software Location
----------------You must enter the URL of the TiMOS software.
The location can be on a Compact Flash device,
or on the network.
Here are some examples
cf1:/timos1.0R1
ftp://user:passwd@192.168.1.150/./timos1.0R1
tftp://192.168.1.150/./timos1.0R1
Software Image URL:
Enter the software URL. (For example, cf1:/both.tim)
At prompt above enter the location of the image. When the device ships from the
factory the image is typically available at cf1:/both.tim
Configuration File Location
--------------------------You must enter the location of configuration
file to be used by TiMOS. The file can be on
a Compact Flash device, or on the network.
Here are some examples
cf1:/config.cfg
ftp://user:passwd@192.168.1.150/./config.cfg
tftp://192.168.1.150/./config.cfg
No existing Config URL
Press ENTER, or type 'none' for no Config URL.
Config File URL:
Enter the location of the configuration file. Or none since you are booting for the first time. You
can skip all the remaining prompt that appear on the screen by pressing ‘ENTER’ until to get to the
following prompt
7210 SAS-M Installation Guide
Page 53
Initializing the System and Downloading Software
New Settings
-----------primary-image cf1\both.tim
primary-config cf1:\config.txt
#uplinkA Port Settings:
uplinkA-port 1/1/10
uplinkA-address 10.135.4.172/10
uplinkA-vlan 0
uplinkA-route 10.10.170.0/10 next-hop 10.135.4.1
#System Settings:
wait 3
persist off
console-speed 115200
Do you want to overwrite cf1:/bof.cfg with the new settings? (yes/no):
Type yes and press Enter. The 7210 SAS-M should boot now.
Primary image location: cf1:/both.tim
Loading image cf1:/both.tim
Version B-3.0.B5-85, Wed Apr 20 14:32:04 IST 2011 by builder in /builder/
3.0B5/panos/main
text:(25059814-->122242456) + data:(3179598-->18748616)
Executing TiMOS image at 0x100000
After the 7210 SAS-M boots up, you should see the following prompt:
All rights reserved. All use subject to applicable license agreements.
Built on Wed Apr 20 14:32:04 IST 2011 by builder in /builder/3.0B5/panos/
main
Login:
Note: The SYS LED will be Green when the device has successfully completed the boot
process and is running normally.
The default username and password are admin. Log into the 7210 SAS-M. To establish either
console connection or Telnet connection to the router after successful boot, please see Establishing
Router Connections on page 65.
Booting a 7210 SAS-M From the Network
There are several ways to boot the 7210 SAS-M from the network. User has options to use one of
the front panel ports (refered to as uplinkA and uplinkB in the display output shown below) or the
out-of-band ethernet management port (refered to as eth-mgmt port in the display output shown
below) to boot the 7210 SAS-M from the network. By default, the out-of-band ethernet
management port is disabled. User needs to enable it before using it for manual boot. The example
below shows how this can be done. The example described below shows how to boot the 7210
SAS using FTP servers and the manual boot process. For more information about booting your
7210 SAS, please refer to the System Basics Guide. Figure 13 shows the network diagram used in
Page 54
7210 SAS-M Installation Guide
Configuring the 7210 SAS-M
the example below. Additionally, you may want to store the TiMOS image on the internal flash if
you want to boot from the flash later.
You will need the following:
•
A FTP server
•
TiMOS image
•
A PC with a serial port and Hyperterminal
•
Cable that connects the console port of 7210 SAS-M to the serial port of PC
•
A network cable to connect the 7210 unit to the network
Prepare the set up as shown in the diagram above. Ensure that the console settings are set as shown
in Console Connection on page 65.
When you are done, power on the 7210 SAS-M.
Using the uplink port to boot 7210 from the network:
Resetting...OK
ø
Alcatel-Lucent 7210 Boot ROM. Copyright 2000-2009 Alcatel-Lucent.
All rights reserved. All use is subject to applicable license agreements.
Running POST tests from ROM
Testing ROM load area...done
Relocating code...Jumping to RAM
Performing second stage RAM test....passed
Board Serial Number is 'SN12345678'
Bootlog started for Version V-1.0.R1
Build V-1.0.R1 bootrom/mpc 7xxx
Built on Thu Jan 15 14:55:59 IST 2009 by builder in /builder/ws/panos/main
Since the router does not ship with a BOF, it will show the default settings.
Looking for cf1:/bof.cfg ... not found
Could not find bof.cfg on any of the local drives.
Default Settings:
-----------------------------------------------------------------------------------------------Contents of Boot Options File on cf1:
#eth-mgmt Port Settings:
eth-mgmt-disabled
#uplinkA Port Settings:
uplinkA-port
1/1/1
uplinkA-address
0
7210 SAS-M Installation Guide
Page 55
Initializing the System and Downloading Software
uplinkA-vlan
0
#uplinkB Port Settings:
uplinkB-port
1/1/2
uplinkB-address
0
uplinkB-vlan
0
#System Settings:
wait
3
persist
off
console-speed
115200
Hit a key within 2 seconds to change boot parameters...
Press any key.
Enter password to edit the Boot Options File
Or CTRL-D to exit the prompt
Password:
The default password is password.
You must supply some required Boot Options. At any prompt, you can type:
"restart" - restart the query mode.
"reboot" - reboot.
"exit" - boot with with existing values.
"reset" - reset the bof and reboot.
Press ENTER to begin, or 'flash' to enter firmware update...
Note: The restart command can be used at any time to start off at the beginning of the menu
options.
Press Enter.
Software Location
----------------You must enter the URL of the TiMOS software.
The location can be on a Compact Flash device,
or on the network.
Here are some examples
cf1:/timos1.1R1
ftp://user:passwd@192.168.1.150/./timos1.1R1
tftp://192.168.1.150/./timos1.1R1
Software Image URL:
Page 56
7210 SAS-M Installation Guide
Configuring the 7210 SAS-M
Enter the software URL. (For example,
ftp://<user>:<password>@10.10.170.22/./images/both.tim)
Configuration File Location
--------------------------You must enter the location of configuration
file to be used by TiMOS. The file can be on
a Compact Flash device, or on the network.
Here are some examples
cf1:/config.cfg
ftp://user:passwd@192.168.1.150/./config.cfg
tftp://192.168.1.150/./config.cfg
No existing Config URL
Press Enter, or type 'none' for no Config URL.
Config File URL:
Enter the location of the configuration file or none since you are booting for the first time.
Boot Interface Management
------------------------You specified a network location for either the
software or the configuration file. You need to,
configure either uplinkA or uplinkB ports.
You will be asked to configure the port number, IP address,
static routes, and VLAN Id for uplink ports.
uplinkA Port Setting
-------------------Existing uplinkA port settings are:
uplinkA-port
1/1/1
uplinkA-address 0
uplinkA-vlan
0
uplinkA port is configured for Boot Interface Management,
Press Enter to proceed with existing port settings
Or "disable" to disable the port for Boot Interface Management
Or "edit" to change the port settings:
Type edit.
Existing uplinkA port for Boot Interface Management is port 1/1/1.
Press Enter to keep it.
Enter the new uplinkA port number for Boot Interface Management:
7210 SAS-M Installation Guide
Page 57
Initializing the System and Downloading Software
Enter the port that it connected to the network (for example, 1/1/24).
You need to assign an IP address for this port.
The IP address should be entered in standard
dotted decimal form with a network length.
example: 192.168.1.169/24
Or type "0" to obtain IP address and static route
through DHCP. Existing IP address and static routes
will be deleted.
uplinkA port is configured to obtain IP address and static route through dhcp.
Press Enter to keep it.
Enter uplinkA port IP Address:
Enter the IP address and mask that the device should use (for example, 10.135.4.172/24).
Since the FTP server is on a different subnet, you will have to enter IP routing information:
You specified network locations which might require
static routes to reach. You will be asked to
enter static routes until all the locations become
reachable.
Static routes should be entered in the following format:
prefix/mask next-hop ip-address
example:
192.168.0.0/16 next-hop 192.168.1.254
Would you like to add a static route? (yes/no)
Type yes and press Enter.
Enter route:
Enter a static route to the FTP server's subnet (for example, 10.10.170.0/24 next-hop
10.135.4.1) at the prompt.
You need to configure the VLAN Id for this port
VLAN Id can be between 0 to 4094. To send out
packets with out any VLAN tags, type "null".
Existing VLAN Id for uplinkA port is VLAN Id 0.
Press Enter to keep it.
Enter the new VLAN Id for uplinkA port:
Press Enter if you want to send out untagged packets. Else, enter the VLAN tag.
uplinkB Port Setting
-------------------uplinkB port is disabled for Boot Interface Management,
Press ENTER to proceed with no uplinkB port settings
Or "enable" to enable the port for Boot Interface Management:
Page 58
7210 SAS-M Installation Guide
Configuring the 7210 SAS-M
Enter disable since we do not want the backup link.
Press Enter.
New Settings
-----------primary-image
ftp://*:*@10.10.170.22/./images/both.tim
primary-config
none
#uplinkA Port Settings:
uplinkA-port
1/1/24
uplinkA-address 10.135.4.172/24
uplinkA-vlan
0
uplinkA-route
10.10.170.0/24 next-hop 10.135.4.1
#System Settings:
wait
3
persist
off
console-speed
115200
Do you want to overwrite cf1:/bof.cfg with the new settings? (yes/no):
Type yes and press Enter.
The 7210 SAS-M should boot now.
Primary image location: ftp://*:*@10.10.170.22/./images/both.tim
Initializing uplinkA port using IP addr 10.135.4.172.
Loading image ftp://*:*@10.10.170.22/./images/both.tim
Version B-1.1.private, Wed Jul 15 17:18:37 IST 2009 by builder in /builder/ws/1.1B1/
main
text:(17446113-->76798004) + data:(2100172-->10874132)
Executing TiMOS image at 0x100000
…
After the 7210 SAS-M boots up, you should see the following prompt:
All rights reserved. All use subject to applicable license agreements.
Built on Wed Jul 15 17:18:37 IST 2009 by builder in /builder/ws/1.1B1/sultan
Login:
The default username and password are admin. Use it to log into the 7210 SAS-M.
Note: The status LED will be Green when the device has successfully completed the boot process
and is running normally. It is highly recommended that you change the default admin password to
prevent unauthorized access to the node.
7210 SAS-M Installation Guide
Page 59
Initializing the System and Downloading Software
Using the Out-of-Band Ethernet Management port to boot 7210 from the
nework:
Note: Use of this feature requires an upgrade of the bootloader software, to a version in which support
for Out-of-Band Management port is available. Please check the release notes for more information.
Follow the same procedure as used for a uplink port until the following prompt is
displayed. Use the following procedure to use the out-of-band ethernet management port
to boot 7210 from the network.
eth-mgmt Port Setting
-------------------The eth-mgmt port is disabled for Boot Interface Management Press ENTER to proceed with
no eth-mgmt port settings. Or "enable" to enable the port for Boot Interface Management: enable
At the above prompt enter 'enable' as shown to enable the use of out-of-band ethernet management
port for boot.
You need to assign an IP address for this port.
The IP address should be entered in standard
dotted decimal form with a network length.
example:
192.168.1.169/24
Enter eth-mgmt IP Address :
Enter the IP address and mask that the device should use (for example, 10.135.4.172/24).
Since the FTP server is on a different subnet, you will have to enter IP routing information using
the Out-of-Band Ethernet Management port to boot 7210 from the nework.
Network Configuration
--------------------Boot Interface Management
------------------------You specified a network location for either the
software or the configuration file. You need to
configure either eth-mgmt or uplinkA or uplinkB ports.
You will be asked to configure the port number, IP address,
static routes, and VLAN Id in case of uplink ports.
You specified network locations which might require
static routes to reach. You will be asked to
enter static routes until all the locations become
reachable.
Static routes should be entered in the following format:
prefix/mask next-hop ip-address
example:
192.168.0.0/16 next-hop 192.168.1.254
Would you like to add a static route? (yes/no) yes
Page 60
7210 SAS-M Installation Guide
Configuring the 7210 SAS-M
Enter ip route:
Enter a static route to the FTP server's subnet (for example, 10.10.170.0/24 next-hop 10.135.4.1) at
the prompt.
The device then prompts the user to configure the uplinkA and uplinkB port. Since we intend to
use the ethernet management port at the following prompts disable the use of uplink ports as
shown below.
uplinkA Port Setting
-------------------Existing uplinkA port settings are:
uplinkA-port
uplinkA-address
uplinkA-vlan
1/1/1
0
0
uplinkA port is configured for Boot Interface Management,
Press ENTER to proceed with existing port settings
Or "disable" to disable the port for Boot Interface Management
Or "edit" to change the port settings:
uplinkB Port Setting
-------------------Existing uplinkB port settings are:
uplinkB-port
uplinkB-address
uplinkB-vlan
1/1/2
0
0
uplinkB port is configured for Boot Interface Management,
Press ENTER to proceed with existing port settings
Or "disable" to disable the port for Boot Interface Management
Or "edit" to change the port settings:
uplinkB port will be disabled for Boot Interface Management
New Settings
-----------primary-image
ftp://*:*@10.10.170.22/./images/both.tim
#eth-mgmt Port Settings:
no eth-mgmt-disabled
eth-mgmt-address
10.135.25.97/24
eth-mgmt-route
10.135.0.0/16 next-hop 10.135.25.1
eth-mgmt-route
135.254.0.0/16 next-hop 10.135.25.1
eth-mgmt-autoneg
eth-mgmt-duplex
full
eth-mgmt-speed
100
#System Settings:
wait
3
persist
off
console-speed
115200
7210 SAS-M Installation Guide
Page 61
Initializing the System and Downloading Software
Do you want to overwrite cf1:/bof.cfg with the new settings? (yes/no): yes
Type yes and press Enter.
The 7210 SAS-M should boot now.
Successfully saved the new settings in cf1:/bof.cfg
Configuring Network with eth-mgmt Port Setting.....
No existing config file URL
Primary image location: ftp://*:*@10.10.170.22/./images/both.tim
Loading image ftp://*:*@10.10.170.22/./images/stu-hw/both.tim
Version B-2.0.B1-57, Tue Jul 13 23:24:58 IST 2010 by builder in /builder/2.0B1/panos/
main
text:(24285906-->114984824) + data:(2989128-->18305224)
Executing TiMOS image at 0x100000
.........
After the 7210 SAS-M boots up, you should see the following prompt:
All rights reserved. All use subject to applicable license agreements.
Built on Tue Jul 13 23:24:58 IST 2010 by builder in /builder/2.0B1/panos/main
Login:
The default username and password are admin. Use it to log into the device.
Note: The status LED will be Green when the device has successfully completed the boot process
and is running normally. It is highly recommended that you change the default admin password to
prevent unauthorized access to the node.
Page 62
7210 SAS-M Installation Guide
Configuring the 7210 SAS-M
Downloading the TiMOS Software to the Internal Flash
If you want to boot the 7210 SAS-M from the internal flash, you will have to copy the image there.
If you have used the uplinkA or uplinkB port to boot the 7210, use any of the network ports for IP
connectivity and follow the procedure given below to configure an IP interface and a route.
If you have used the out-of-band ethernet management port, then you do not need to configure the
IP interface. Instead jump to the step "Check IP connectivity" below and continue from there.
Change the mode of the connected port to network.
A:SN12# configure port 1/1/24
A:SN12>config>port#
A:SN12>config>port# ethernet mode network
A:SN12>config>port# no shutdown
A:SN12>config>port# exit
Configure an IP interface:
A:SN12# configure router
A:SN12>config>router# info
---------------------------------------------interface "in-band-mgmt" create
address 10.135.4.172/24
port 1/1/24
exit
---------------------------------------------A:SN12>config>router#
Configure a route to the FTP server.
A:SN12#configure router
A:SN12>config>router#
A:SN12>config>router# static-route 10.10.170.0/24 next-hop 10.135.4.1
A:SN12>config>router#
Check IP connectivity:
A:SN12# ping 10.10.170.22 source 10.135.4.172
PING 10.10.170.22 56 data bytes
64 bytes from 10.10.170.22: icmp_seq=1 ttl=251 time<1ms.
64 bytes from 10.10.170.22: icmp_seq=2 ttl=251 time<1ms.
64 bytes from 10.10.170.22: icmp_seq=3 ttl=251 time<1ms.
64 bytes from 10.10.170.22: icmp_seq=4 ttl=251 time<1ms.
64 bytes from 10.10.170.22: icmp_seq=5 ttl=251 time<1ms.
---- 10.10.170.22 PING Statistics ---5 packets transmitted, 5 packets received, 0.00% packet loss
round-trip min < 1ms, avg < 1ms, max < 1ms, stddev < 1ms
A:SN12#
7210 SAS-M Installation Guide
Page 63
Initializing the System and Downloading Software
Configure the primary-config in the BOF and save the config:
A:SN12# bof primary-config cf1:/config.txt
*A:SN12# bof save
Writing BOF to cf1:/bof.cfg
Saving BOF .... Completed.
A:SN12# admin save
Writing file to cf1:\config.txt
Saving configuration .... Completed.
A:SN12#
Copy the TiMOS image from the FTP server to the flash:/
A:SN12# system security source-address application ftp in-band-mgmt
A:SN12# file copy ftp://<user>:<passwd>@10.10.170.22/./images/both.tim cf1:/both.tim
Copying file ftp://<user>:<passwd>@10.10.170.22/./images/both.tim...
1 file copied.
A:SN12#
Configure the BOF to pick up the image from internal flash:
A:SN12# bof primary-image cf1:/both.tim
*A:SN12# bof save
Writing BOF to cf1:/bof.cfg
Saving BOF .... Completed.
A:SN12#
Reboot the 7210 SAS-M. The device will pick up both the image and the configuration from the
internal flash.
Page 64
7210 SAS-M Installation Guide
Configuring the 7210 SAS-M
Establishing Router Connections
Access your newly installed switch two ways:
•
Console Connection on page 65
•
Telnet Connection on page 66
Console Connection
To establish a console connection, you will need the following:
•
An ASCII terminal or a PC running terminal emulation software set to the parameters
shown in the table below
•
The included RJ-45 serial cable
Table 13: Console Configuration Parameter Values
Parameter
Value
Baud Rate
115,200
Data Bits
8
Parity
None
Stop Bits
1
Flow Control
None
To establish a console connection:
Step 1
Connect the terminal to the console port on the front panel using the serial cable.
Step 2
Power on the terminal.
Step 3
Establish the connection by pressing the Enter key a few times on your terminal
keyboard.
Step 4
At the router prompt, enter the login and password.
The default login is admin.
The default password is admin.
7210 SAS-M Installation Guide
Page 65
Establishing Router Connections
Telnet Connection
To access the router after a successful initialization with a Telnet connection from a PC or a
workstation, configure an in-band management interface using the Timos CLI. You can configure
an in-band management interface by configuring an IP interface on one of the ports configured in
network mode.
The following is a sample configuration for configuring an in-band management IP interface:
*A:7210SAS>config>router>info
interface "in-band-mgmt" create
address 10.10.10.25/24
port 1/1/24
exit
*A:7210SAS>config>router>
Telnet access provides the same options for user and administrator access as those available
through the console port.
To configure the 7210 SAS-M for Telnet access, you must have a device with Telnet client
software. The 7210 SAS-M must have a management IP interface configured with an IP address.
Before using the telnet client access you must enable telnet server on the 7210 by using the CLI
command:
*A: 7210SAS# configure system security telnet-server.
Each 7210 SAS-M is limited to a total of seven inbound/outbound Telnet or SSH sessions to
guarantee that either inbound or outbound sessions will be available.
MAC addresses are listed on a small label on the chassis. The MAC address also displays in the
show router arp command output.
Page 66
7210 SAS-M Installation Guide
Configuring the 7210 SAS-M
Running Telnet
Once the IP parameters are configured, you can access the CLI command line with a Telnet
connection. To establish a Telnet connection, run a Telnet program and issue the Telnet command,
followed by the IP address:
The following displays an example of a Telnet login:
C:\>telnet 10.10.10.25
Login: admin
Password: ########
ALA-1#
7210 SAS-M Installation Guide
Page 67
Establishing Router Connections
Page 68
7210 SAS-M Installation Guide
Troubleshooting
This chapter describes troubleshooting methods and procedures and includes the following
sections:
•
Diagnosing Switch Indicators on page 70
•
Power and Cooling Problems on page 71
•
Installation on page 72
•
In-Band Access on page 73
7210 SAS-M Installation Guide
Page 69
Diagnosing Switch Indicators
Diagnosing Switch Indicators
This switch can be easily monitored through panel indicators to identify problems.
Table 14 describes common problems you may encounter and possible solutions.
Table 14: Troubleshooting
Symptom
Possible Cause
Action
Power Module LED is
OFF +12 VDC or AC
Power outlet, power cord, or
power module may be defective.
• If using a DC power supply module, check the
connections between the switch and the
external DC power supply. If using an AC
power module, check connections between
the switch, the power cord, and the wall
outlet.
• Contact your dealer for assistance.
Power Module LED is
OFF +12 VDC
Power module may be defective.
• Internal power supply has failed. Contact your
local dealer for assistance.
Critical LED is RED
Critical alarm detected.
• One or more critical system alarm(s) have
occurred.
Major LED is RED
Major alarm detected.
• One or more major system alarm(s) have
occurred.
Fan LED is RED
Fan failure.
• One or more fans in the fan tray have failed.
Replace the fan tray.
Status LED is Off or
AMBER
Boot-up diagnostic program has
detected a problem.
• Power cycle the switch to try and clear the
condition.
• If the condition does not clear, contact your
local dealer for assistance.
Link LED is Off
Network cable or Ethernet device
attached to this port may be
defective.
• Verify that the switch and attached device are
powered on.
• Be sure the cable is plugged into both the
switch and corresponding device.
• Verify that the proper cable type is used and
its length does not exceed specified limits.
• Check the adapter on the attached device and
cable connections for possible defects.
Replace the defective adapter or cable if
necessary.
Management LED is
OFF
Page 70
7210 SAS-M Installation Guide
Troubleshooting
Power and Cooling Problems
If the power indicator does not turn on when the power cord is plugged in, you may
have a problem with your power outlet, power cord, or internal power supply.
However, if the unit powers off after running for a while, check for loose power
connections, power losses or surges at the power outlet, and verify that the fans on the
unit are unobstructed and running prior to shutdown.
7210 SAS-M Installation Guide
Page 71
Installation
Installation
Verify that all system components have been properly installed. If one or more
components appear to be malfunctioning (such as the power cord or network cabling),
test them in an alternate environment where you are sure that all the other components
are functioning properly.
Page 72
7210 SAS-M Installation Guide
Troubleshooting
In-Band Access
You can access the management agent in the switch from anywhere within the
attached network using Telnet or network management software tools. However, you
must first configure the switch with a valid IP address, subnet mask, and default
gateway.
If you have trouble establishing a link to the management agent, check to see if you
have a valid network connection. Then verify that you entered the correct IP address.
Also, be sure the port through which you are connecting to the switch has not been
disabled. If it has not been disabled, then check the network cabling that runs between
your remote location and the switch.
NOTE:
The management agent can accept up to seven simultaneous Telnet sessions. If the maximum
number of sessions already exists, an additional Telnet connection will not be able to log into the
system.
7210 SAS-M Installation Guide
Page 73
In-Band Access
Page 74
7210 SAS-M Installation Guide
Appendix A: Specifications
This appendix provides system specifications and includes the following sections:
•
Specifications on page 76
7210 SAS-M Installation Guide
Page 75
Specifications
Specifications
Table 15: 7210 SAS-M Specifications
Item
Width
Height
Depth
Physical dimensions
Size
17.17" (43.6 cm)
Weight
11 lbs. (5 kg)
2.64" (1.5RU) (6.7 cm)
9.96" (25.3 cm)
Environmental
Operating Temperature
For non-ETR variant: 0º C to 50º C (-32º F to 122º F) (standard) IEC
68-2-14
For ETR variant: -40º C to 65º C (-49º F to 149º F) (standard) IEC
68-2-14
Humidity
5% to 95% non-condensing
Vibration
IEC 68-2-36, IEC 68-2-6
Shock
IEC 68-2-29
Drop
IEC 68-2-32
Telcordia NEBS
Design to meet NEBS level 3
Input
Input voltage
-36VDC ~ -72VDC, Output: +12VDC
+20VDC ~ +28VDC, Output: +12VDC
100~240 V, 50~60 Hz, Output: +12VDC
Dual input power redundancy, with current sharing and hot-swap.
Maximum power
consumption
200 W
Typical power
consumption
80-100 W (depending
on configuration)
Safety, EMC and Immunity
Page 76
7210 SAS-M Installation Guide
Appendix A: Specifications
Table 15: 7210 SAS-M Specifications (Continued)
Item
Width
Height
Safety
CSA/NRTL (UL60950-1, CSA 22.2.No 60950-1)
CB
EMC
Europe CE Mark:
EN50081-1: EN55022 Class A
EN60555-2/3
North America:
FCC 47 CFR Part 15 Class A
ICES-003 Issue 4 Class A (Canada)
Japan: VCCI CISPR 22 Class A
Australia/New-Zeeland: C-Tick, CISPR 22 Class A
Immunity
EN50082-1, EN/IEC 61000-4-2/3/4/6/11
Depth
Japan VCCI Class A Declaration
This is a Class A product based on the standard of the Voluntary Control Council for
Interference by Information Technology Equipment (VCCI). If this equipment is used
in a domestic environment, radio disturbance may arise. When such trouble occurs,
the user may be required to take corrective actions.
RoHS and WEEE
Comply with European RoHS and WEEE requirements.
Comply with the Chinese RoHS legislations.
7210 SAS-M Installation Guide
Page 77
Specifications
Page 78
7210 SAS-M Installation Guide
Appendix B: Pin Assignments
This appendix contains pin assignments and includes the following sections:
•
Management Port Pin Assignments on page 80
•
Console Port Pin Assignment on page 81
7210 SAS-M Installation Guide
Page 79
Management Port Pin Assignments
Management Port Pin Assignments
Use unshielded twisted-pair (UTP) or shielded twisted-pair (STP) cable for RJ-45
connections and 100-ohm Category 3, 4, or 5 cable for 10 Mbps connections or 100ohm Category 5 cable for 100 Mbps connections. Make sure that the length of any
twisted-pair connection does not exceed 100 meters (328 feet).
The RJ-45 ports on the switch base unit support automatic MDI/MDI-X operation, so
you can use straight-through cables for all network connections to PCs or servers, or to
other switches or hubs. In straight-through cable, pins 1, 2, 3, and 6, at one end of the
cable, are connected straight through to pins 1, 2, 3, and 6 at the other end of the cable.
When using any RJ-45 port on these switches, you can use either straight-through or
crossover cable.
Table 16: 10/100BASE-TX MDI and MDI-X Port Pinouts
Pin
MDI Signal Name
MDI-X Signal Name
1
Transmit Data plus (TD+)
Receive Data plus (RD+)
2
Transmit Data minus (TD-)
Receive Data minus (RD-)
3
Receive Data plus (RD+)
Transmit Data plus (TD+)
6
Receive Data minus (RD-)
Transmit Data minus (TD-)
4, 5, 7, 8
Not used
Not used
NOTE:
• The “+” and “-” signs represent the polarity of the wires that make up each wire pair.
• Auto-negotiation must be enabled for automatic MDI/MDI-X pinout configuration.
Page 80
7210 SAS-M Installation Guide
Appendix B: Pin Assignments
Console Port Pin Assignment
The RJ-45 serial port on the front panel is used to connect to the switch for out-ofband console configuration. The on-board configuration program can be accessed
from a terminal or a PC running a terminal emulation program.
The pin assignments used to connect to the serial port are provided in Table 17.
Table 17: Serial Cable Wiring
RJ45
Pin
Usage
RTS
1
Used as defined. Should be connected
NC
2
Not used. Should not be connected
TXD
3
Used as defined. Should be connected
GND
4
Used as defined. Should be connected
GND
5
Used as defined. Should be connected
RXD
6
Used as defined. Should be connected
NC
7
Not used. Should not be connected
CTS
8
Used as defined. Should be connected
7210 SAS-M Installation Guide
Page 81
Console Port Pin Assignment
Page 82
7210 SAS-M Installation Guide
Appendix C: Alarm Pin
Assignments
This appendix contains pin assignments and includes the following sections:
•
Alarm Port Pin Assignments on page 84
7210 SAS-M Installation Guide
Page 83
Alarm Port Pin Assignments
Alarm Port Pin Assignments
The alarm interface port is a D-type 15-pin connector that supports a critical alarm
output, a major alarm output, and four alarm inputs. When your system has a critical or
major alarm, the CPU will drive the alarm relay to issue the alarm output and turn on
the critical or major LED. If you push the alarm cut off (ACO) button, the relay will be
released but the LED will stay on until the alarm is cleared.
Figure 16: DB-15 Alarm Connector
The system signals the appropriate alarm output for the following events:
•
Fan failure - Critical alarm is raised.
•
One Power Supply Failure - Critical alarm is raised. The critical alarm is
cleared and a major alarm is raised if the failed power supply is removed).
•
Chassis temperature threshold exceeded - Major alarm is raised.
The system also supports four alarm inputs. The input voltage range is from 24V to
48V. If an alarm input is active, the CPU will process it, output it to the CLI, and issue
an SNMP trap. An alarm input can also be configured to drive the appropriate alarm
output pin. Please refer the System Basics user guide for more details on configuring
the alarm inputs.
See Table 18 for the alarm interface port pinouts.
Table 18: Alarm Interface Port Pinouts
Pin
Page 84
Name
Function
1
CRIT_ALARM_CNTR
Common contact for Critical alarm relay.
2
CRIT_ALARM_NO
Normally open during Critical alarm state.
3
MJR_ALARM_NC
Normally closed during Major alarm state.
4
N/C
N/C
7210 SAS-M Installation Guide
Appendix C: Alarm Pin Assignments
Table 18: Alarm Interface Port Pinouts
Pin
Name
Function
5
ALARM_IN4_EXT_+
External alarm input 4 (external relay dry
contact closure to pin 12).
6
ALARM_IN3_EXT_+
External alarm input 3 (external relay dry
contact closure to pin 13).
7
ALARM_IN2_EXT_+
External alarm input 2 (external relay dry
contact closure to pin 14).
8
ALARM_IN1_EXT_+
External alarm input 1 (external relay dry
contact closure to pin 15).
9
CRIT_ALARM_NC
Normally closed during Critical alarm state.
10
MJR_ALARM_CNTR
Common contact for Major alarm relay.
11
MJR_ALARM_NO
Normally open during Major alarm state.
12
ALARM_IN4_EXT_RTN
External alarm input 4 (external relay dry
contact closure from pin 5).
13
ALARM_IN3_EXT_RTN
External alarm input 3 (external relay dry
contact closure from pin 6).
14
ALARM_IN2_EXT_RTN
External alarm input 2 (external relay dry
contact closure from pin 7).
15
ALARM_IN1_EXT_RTN
External alarm input 1 (external relay dry
contact closure from pin 8).
7210 SAS-M Installation Guide
Page 85
Alarm Port Pin Assignments
Figure 17: Alarm Input Connection Diagram
RTN refers to the negative side of the floating external power supply. This power
supply must not be connected to chassis ground and should be 18-50 volts DC at 100
ma.
Major and Critical alarm dry relay contact outputs are provided on pins 3,10,11 and
1,2,9. These reflect the major and critical alarms output by the box and can be
manually cleared by pressing the ACO button.
The 4 alarm inputs are customer configurable to monitor alarms provided by
additional equipment. These inputs require a separate DC power supply between 18-
Page 86
7210 SAS-M Installation Guide
Appendix C: Alarm Pin Assignments
50 volts at 100ma. The power supply outputs must be isolated from chassis ground,
for example do not connect the alarm power supply return to chassis or rack ground.
7210 SAS-M Installation Guide
Page 87
Alarm Port Pin Assignments
Page 88
7210 SAS-M Installation Guide