Installation of your new Fanuc T21iFL and T21iFL-PC2 can be smooth and rapid if preparations are made prior to the
delivery of your machine. Any questions regarding machine installation should be directed to our service
department for clarification. We hope this checklist will aid in a rapid installation of your new machine. NOTE: The
following must be completed prior to our service technician’s arrival to install your machine.
9
Power Requirements for your machine:
200/220v ± 10%, 3 phase, 15kVa 42 Amp
Proper voltage per machine specifications should be ready at machine site. Do NOT power up the machine. A
separate Earth Ground or Cold Water Pipe Ground is Required. (A Conduit-Type Ground Does Not
Provide Sufficient Noise Immunity). 440V-480v requires an external step-down transformer.
NOTE: A power source for options requiring 110v AC/Single Phase or 220V AC/Single Phase power will be
required in addition to the main power to the machine – options include programmable indexers (Haas,
Tsudakoma, Nikken), Oil Skimmers, etc.
9
Customer should furnish and have available the proper supply and types of lubricants required for machine
operation.
ITEM
CAPACITY
FLUID TYPE
Coolant
26 Gallons
Water Soluable, Synthetic
Way Lube
½ Gallon
Mobil Vactra #2
NOTE: You will need to have these fluids on hand prior to installation. Any questions, please contact our
Service Department.
9
Air lines should be routed to the machine location and operational for proper air pressure.
The machine requires a minimum pressure volume air supply of 4 CFM @ 71-135 PSI.
9
Machine location should be planned to allow enough room for access panels to be opened and serviced with
ease. A minimum of 36” clearance around the machine is required for operator/maintenance access.
9
Weight requirements should be checked to insure that the surface below the machine will have sufficient strength
for support and stability. The machine must be set on a solid, sound and stable, steel bar-reinforced concrete
slab poured directly on the grade. In general, the 6” concrete floor on industrial buildings is suitable for machine
placement. NOTE: Methods does NOT recommend vibration dampering pads under the machine level pads. As machine
settles or moves around, machine weight shifts and causes more problems in the rigidness of the machine cutting. If
vibration from other equipment will be present, an isolation foundation may be recommended.
9
The machine should be off loaded using a forklift with a capacity of at least 5,000#, and forks 8’ in length.
Upon arrival of your machine, unpack/uncrate and immediately check for visible damage.
SHIPPING WEIGHT
SHIPPING DIMENSIONS OF MACHINE
4,400# (Machine)
5’7" L x 7’2" W x 7’4" H (Robodrill Crate)
500# (Accessory)
5’1” L x 2’2” W x 2’3” H (Accessory Crate)
400# (optional PC2 Unit) 26.5” L x 44” W x 60.9” H (optional PC2 Unit)
1,000# (Opt Chip Conv)
12’ L x 3’4” W x 6’ H (Optional Chip Conveyor)
See attached for floor space requirements/dimensions.
9
Remove as much preservative from the machine as possible without having to power up (tables – slides,
pulleys, etc.). We recommend mineral spirits to clean. Apply oil when finished to prevent rust.
PLEASE FORWARD THIS TO THE APPROPRIATE PERSON. THANK YOU.
Fanuc RoboDrill
αT-21IFL, PC2
CNC Vertical Machining Center with APC
Pre-Installation Package (PIP)
Feb. 2006
Page 4 of 5
Fanuc RoboDrill
αT-21IFL, PC2
CNC Vertical Machining Center with APC
Pre-Installation Package (PIP)
Feb. 2006
Page 5 of 5