- Home
- Domestic appliances
- Climate control
- Nortec
- SE 50, 100, 175, 250, 375, 475, 675, 950, 1050
- User manual
- 72 Pages
Nortec SE 50, 100, 175, 250, 375, 475, 675, 950, 1050 Steam Exchange Humidifier Installation, Operation & Maintenance Guide
The Nortec SE Series Steam Exchange Humidifier is a completely new design based on leading edge technology. The SE is designed to provide clean atmospheric steam at an economical price.
advertisement
Assistant Bot
Need help? Our chatbot has already read the manual and is ready to assist you. Feel free to ask any questions about the device, but providing details will make the conversation more productive.
SE Series
Steam Exchange Humidifier
Installation,
Operation & Maintenance
Guide
IMPORTANT: Read and save this guide for future reference. This guide to be left with equipment owner.
2008-05-07
1720292-B
WARNING:
Improper installation, adjustment, alteration, service or maintenance can cause injury or property damage. For assistance or additional information consult a qualified installer or a service agency.
Table Of Contents
GENERAL 1
- RECEIVING & UNPACKING EQUIPMENT. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
MODEL CAPACITY & PHYSICAL DATA
FLOOR STAND
2-7
8
CEILING MOUNTING INSTALLATION
TYPICAL SE INSTALLATION DIAGRAM
SETC OUTDOOR DIMENSIONS
ROOF CURB DIMENSIONS
SE INDOOR INSTALLATION
12
13
9
10
11
- LOW VOLTAGE CONTROL WIRING . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
- STEAM CONDENSATE OUTLET . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
- AUXILIARY DRAIN OUTLET . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
- STEAM LINES AND CONDENSATE LINE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
- PRESSURIZED STEAM CONNECTIONS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
- STEAM SUPPLY PIPING . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
ACTUATOR INSTALLATION 19
- WHAT COMES WITH THE ACTUATOR . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19
- INSTALLATION INSTRUCTIONS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19
- PRE-LOADING INSTRUCTIONS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19
SETC OUTDOOR INSTALLATION 21
- MOUNTING . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
- PRESSURIZED STEAM SUPPLY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
- ELECTRICAL INSTALLATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
- FILL WATER SUPPLY LINE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
- DRAIN LINE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
- AUX DRAIN . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
- STEAM LINES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
OPERATION 23
INSPECTION AND START-UP PROCEDURE 24
- START UP PROCEDURE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24
- TAKING OUT OF OPERATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25
- SE INSPECTION CHECK LIST . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26-27
SCALE MANAGEMENT 28
- WATER QUALITY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28
MAINTENANCE 29
- CLEANING THE STAINLESS STEEL TANK & FLOAT CHAMBER . . . . . . . . . . . . . . . . . . 29
- ADJUSTMENTS/REPLACEMENTS OF COMPONENTS . . . . . . . . . . . . . . . . . . . . . . . . 30
- SERVICING THE UNIT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30
- TRANSFORMER REPLACEMENT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31
- FILL VALVE REPLACEMENT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31
- DRAIN PUMP REPLACEMENT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31
- FILL BOX REPLACEMENT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32
- REMOVAL OF HEAT EXCHANGER . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32
- SETC SETTINGS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33-34
- SETC LOGIC CONTROL BOARD . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 35
- KEYPAD DISPLAY MENU STRUCTURE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 36-41
- NORTEC TC CONTROLLER . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 42
- MANDATORY MAINTENANCE SCHEDULE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 53
- SETC INTERNAL WIRING DIAGRAM . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 54
- SEP INTERNAL WIRING DIAGRAM . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55
GENERAL
This installation guide has been designed to provide assistance when installing, mounting, and sizing a SE Series humidifier. Actual on site application may vary. Consult Walter Meier (Nortec)
Technical Services or your local Walter Meier (Nortec) representative.
RECEIVING & UNPACKING EQUIPMENT
1.
Check packing slip to ensure ALL material has been delivered.
2.
All material shortages are to be reported to
Walter Meier (Nortec) within 48 hours from receipt of goods. Walter Meier (Nortec) assumes no responsibility for any material shortages beyond this period.
3.
Inspect shipping boxes for damage and note on shipping waybill accordingly.
4.
After unpacking, inspect equipment for damage and if damage is found, notify the shipper promptly.
5.
All Walter Meier (Nortec) products are shipped on an F.O.B. factory basis. Any and all damage, breakage or loss claims are to be made directly to the shipping company.
DELIVERY
The standard delivery includes:
1.
Steam Exchange humidifier equipped with desired options.
2.
In a bag you will find:
- Manuals.
- Plastic adapter for potable, RO, DI or softened water connection.
- Steam hose for steam outlet with clamps.
3.
The SE Series comes complete with a telescopic stand mounted inside the unit legs.
Stand cross bracing is shipped with the unit.
(Optional on SE 50).
4.
Steam valve, actuator, and wye strainer.
5.
Desired accessories ordered.
GENERAL SPECIFICATIONS
The NORTEC SE Series humidifier is a completely new design based on leading edge technology. The
SE is designed to provide clean atmospheric steam at an economical price.
MODEL DESIGNATION
The unit specification label indicates the model of
Steam Exchange humidifier according to the following chart:
SE TC 100 OC
PRODUCT LINE
(Steam Exchange Humidifier)
TC = Total Controller c/w KEYPAD
P = Economical
Humidifier size
50
100
175
250
375
475
675
950
1050
Outdoor
- 1 -
MODEL CAPACITY & PHYSICAL DATA
Table #1
SETC/SEP
SE 50
SE 100
SE 175
SE 250
SE 375
SE 475
SE 675
SE 950
5 psi (34kpa)
17 (8)
33 (15)
45 (20)
77 (35)
105 (48)
161 (73)
200 (91)
386 (175)
7 psi (48kpa)
Operating Steam Pressure
10 psi (69 kpa)
Lbs/hr (kg/hr)
13 psi (90 kpa)
20 (9)
41 (19)
59 (27)
98 (44)
136 (62)
201 (91)
256 (116)
463 (210)
28 (13)
58 (26)
88 (40)
140 (64)
200 (91)
279 (127)
368 (167)
609 (276)
40 (18)
80 (36)
131 (59)
200 (91)
294 (133)
388 (176)
531 (241)
800 (363)
SE 1050 446 (202) 529 (240) 682 (309) 880 (399)
NOTE: Specification subject to change without notice. Rated capacity applies with no blowdown.
15 psi (103 kpa)
50 (23)
100 (45)
175 (79)
250 (113)
375 (170)
475 (215)
675 (306)
950 (431)
1050 (476)
.
- 2 -
1 13/16"
46.3mm
1 1/2"
3.8 cm
14 1/2"
36.9 cm
FASTENING POINTS
FOR CEILING MOUNT
7/8"
2.3 cm 8 3/4"
22.3 cm
12 13/16"
32.6 cm
RIGHT
POWER AND CONTROL
BOTTOM PORT
25 5/8"
65.1 cm
1 7/16"
3.7 cm
POWER AND CONTROL
2 1/4"
5.8 cm
20 5/8"
52.4 cm
FRONT
STEAM OUTLET
1 3/4" O.D TUBE
18 3/8"
46.7 cm
4 9/16"
11.6 cm
8 1/4"
21.0 cm
BOILER STEAM IN
1/2 NPT MALE
SUPPLY WATER
3/4 BSPP MALE OR
1/2 NPT MALE
1 9/16"
4.0 cm
2 11/16"
6.9 cm
1"
2.6 cm
8"
20.3 cm
10 5/16"
26.2 cm
16 3/4"
42.6 cm
1 1/16"
2.8 cm
1 3/8"
3.5 cm
7/8 TUBE, DRAIN
2 9/16"
6.5 cm
3/4 NPT MALE
CONDENSATE OUT
19 9/16"
49.7 cm
AUXILIARY DRAIN/
CONDENSATE RETURN
TO UNIT 1/2 NPT FEMALE
TOP
LEFT
RIGHT
REAR
FRONT
BOTTOM
SERVICE CLEARANCE
0”
0”
30"
0”
30"
0”
0 cm
0 cm
76 cm
0 cm
76 cm
0 cm
TECHNICAL DATA
Max. Rated Steam
Nominal @ 5 psi
Nominal @ 10 psi
Nominal @ 15 psi
Steam Valve CV
Supply Water Con.
Drain Water Connection
Aux. Drain Con.
Pressure Steam In
Steam Cond. Out
Atm. Steam Out
Weight Empty
Weight Full
56 lb/hr
3-17 lb/hr
6-28 lb/hr
10-50 lb/hr
SE 50
25.4 kg/hr
1.4-7.7 kg/hr
2.7- 12.7 kg/hr
4.5-22.6 kg/hr
2.2
½” NPT or ¾” BSPP male
0.825” (2.1 cm) tube
½” NPT female
½” NPT male
¾” NPT male
1 x 1.75 OD (4.5 cm)
125 lb
180 lb
57 kg
82 kg
- 3 -
Physical Data
SETC / SEP 50
3/27/06
TOP
13.9"
( 35.2cm )
STEAM OUTLET
5.5"
( 13.9cm )
20.8"
( 53cm )
31.6"
( 80.3cm )
4.0"
( 10.2cm )
21.0"
( 53.3cm )
40.2"
( 102.2cm )
TOP
LEFT
RIGHT
REAR
FRONT
BOTTOM
SERVICE CLEARANCE
36”
0”
30"
0”
91 cm
0 cm
76 cm
0 cm
30"
0”
76 cm
0 cm
44.5"
( 113.2cm )
CONTROL SIGNAL
3.5"
( 9cm )
1.5"
( 3.9cm )
FRONT
WATER INLET
PRESSURE
STEAM INLET
RIGHT SIDE
1.0"
( 2.5cm )
1.9"
( 4.83cm )
2.5"
( 6.4cm )
3.7"
( 9.47cm )
7.4"
( 18.92cm )
10.3"
( 26.2cm )
CONTROL PANEL
DRAIN
AUX. DRAIN
STEAM
CONDENSATE OUTLET
2.0"
( 5.1cm )
1.0"
( 2.5cm )
6.8"
( 17.18cm )
4.1"
( 10.3cm )
POWER SUPPLY
9.7"
( 24.6cm )
16.1"
( 40.8cm )
Technical data
Max.Rated Steam
Nominal @ 5psi
Nominal @10psi
Nominal @15psi
Steam Valve CV
Supply water con.
Drain water con.
Aux. drain con.
Pressure steam in.
Steam Cond. Out.
Atm. Steam Out.
Weight Empty
Weight Full
105 lb/hr
5-33 lb/hr
SE 100
48 kg/hr
2-15 kg/hr
9-58 lb/hr
15-100 lb/hr
4-26 kg/hr
7-45 kg/hr
2.8
0.5” NPT
180 lb/hr
7-45 lb/hr
13-88 lb/hr
26-175 lb/hr
SE 175
7.5
82 kg/hr
3-20 kg/hr
6-40 kg/hr
12-79 kg/hr
0.5” NPT
0.75” O.D. tube
0.5” NPT female
0.5” NPT
.75" NPT
0.75” O.D. tube
0.5” NPT female
0.5” NPT
.75" NPT
1 x 1.75” OD 1 x 4.4 cm OD 1 x 3.00” OD 1 x 7.62cm OD
267 lb 121 kg 267 lb 121kg
423 lb 192 kg 423 lb 192 kg
Physical Data
SETC 100 - 175
5/4/07
- 4 -
TOP
STEAM OUTLET
5.5"
( 13.9cm )
13.9"
( 35.2cm )
27.2"
( 69cm )
44.6"
( 113.3cm )
CONTROL SIGNAL
3.5"
( 9cm )
1.5"
( 3.9cm )
FRONT
PRESSURE
STEAM INLET
RIGHT SIDE
1.0"
( 2.6cm )
1.9"
( 4.8cm )
2.5"
( 6.4cm )
3.7"
( 9.5cm )
7.4"
( 18.9cm ) 10.3"
( 26.2cm )
31.6"
( 80.3cm )
4.0"
( 10.2cm )
21.0"
( 53.3cm )
40.2"
( 102.2cm )
TOP
LEFT
RIGHT
REAR
FRONT
BOTTOM
SERVICE CLEARANCE
36”
0”
91 cm
0 cm
30"
0”
30"
0”
76 cm
0 cm
76 cm
0 cm
WATER INLET
CONTROL PANEL
DRAIN
AUX. DRAIN
POWER SUPPLY
9.7"
( 24.6cm )
22.4"
( 56.8cm )
STEAM
CONDENSATE OUTLET
6.8"
( 17.2cm )
4.1"
( 10.3cm )
2.0"
( 5.1cm )
1.0"
( 2.5cm )
Technical data SE 250
Max.Rated Steam
Nominal @ 5psi
255 lb/hr
11-77 lb/hr
115 kg/hr
5-35 kg/hr
Nominal @10psi 21-140 lb/hr 10-64 kg/hr
Nominal @15psi 37-250 lb/hr 17-114 kg/hr
Steam Valve 12
Supply water con.
Drain water con.
0.5” NPT
0.75” O.D. tube
Aux. drain con.
Pressure steam in.
Steam Cond. Out.
Atm. Steam Out.
Weight Empty
Weight Full
0.5” NPT female
1 x 3” OD
355 lb
599 lb
1.0” NPT
.75” NPT
1 x 7.62 cm OD
161 kg
272 kg
380 lb/hr
15-105 lb/hr
30-200 lb/hr
56-375 lb/hr
SE 375
28
172 kg/hr
7-47 kg/hr
14-91 kg/hr
25-170 kg/hr
0.5” NPT
0.75” O.D. tube
0.5” NPT female
1” NPT
.75” NPT
1 x 4” OD
355 lb
599 lb
1 x 10.2cm OD
161 kg
272 kg
Physical Data
SETC 250 - 375
5/4/07
- 5 -
TOP
5.5"
( 13.9cm )
13.7"
( 34.9cm )
STEAM OUTLET
FRONT
42.7"
( 108.6cm )
31.6"
( 80.3cm )
CONTROL SIGNAL
4.0"
( 10.2cm )
21.0"
( 53.3cm )
40.2"
( 102.2cm )
3.5"
( 9cm )
1.5"
( 3.9cm )
WATER INLET
CONTROL PANEL
DRAIN
AUX. DRAIN
PRESSURE
STEAM INLET
9.7"
( 24.6cm )
POWER SUPPLY
21.9"
( 55.5cm )
38.0"
( 96.4cm )
2.5"
( 6.4cm )
RIGHT SIDE
1.0"
( 2.5cm )
1.9"
( 4.8cm )
3.7"
( 9.5cm )
7.4"
( 18.9cm ) 10.3"
( 26.2cm )
STEAM
CONDENSATE OUTLET
6.8"
( 17.2cm )
2.0"
( 5.1cm )
4.1"
( 10.3cm )
1.0"
( 2.5cm )
TOP
LEFT
RIGHT
REAR
FRONT
BOTTOM
SERVICE CLEARANCE
36”
30"
91 cm
76 cm
30"
0”
30"
0”
76 cm
0 cm
76 cm
0 cm
Technical data SE 475 SE 675
Max.Rated Steam 480 lb/hr 217 kg/hr 680 lb/hr
Nominal @ 5psi 24-161 lb/hr
Nominal @10psi 42-279 lb/hr
11-73 kg/hr
19-127kg/hr
30-200 lb/hr
55-368 lb/hr
Nominal @15psi 71-475 lb/hr 32-215 kg/hr 101-675 lb/hr
Steam Valve CV 20 28
308 kg/hr
14-91 kg/hr
25-167 kg/hr
46-306 kg/hr
Supply water con.
Drain water con.
0.5” NPT
0.75” O.D. tube
0.5” NPT
0.75” O.D. tube
Aux. drain con.
Pressure steam in.
Steam Cond. Out.
Atm. Steam Out.
Weight Empty
Weight Full
0.5” NPT female
1 x 4” OD
529 lb
992 lb
1.25 ” NPT
1.0” NPT
1 x 10.16cm OD
240 kg
450 kg
0.5” NPT female
1 x 4” OD
529 lb
992 lb
1.5” NPT
1.0” NPT
1 x 10.16cm OD
240 kg
450 kg
Physical Data
SETC 475 - 675
5/4/07
- 6 -
9.9"
( 25cm )
5.5"
( 13.9cm )
STEAM
OUTLETS
39.5"
( 100.2cm )
8.0"
( 20.3cm )
PRESSURE STEAM INLET
5.3"
( 13.6cm )
TOP
58.3"
( 148.2cm )
31.6"
( 80.3cm )
4.0"
( 10.2cm )
21.0"
( 53.3cm )
40.2"
( 102.2cm )
1.5"
( 3.9cm )
CONTROL SIGNAL
3.5"
( 9cm )
FRONT
WATER INLET
DRAIN
CONTROL PANEL
STEAM CONDENSATE
OUTLET
AUX. DRAIN
9.7"
( 24.6cm )
POWER SUPPLY
29.7"
( 75.3cm )
53.6"
( 136.1cm )
RIGHT SIDE
1.0"
( 2.5cm )
2.5"
( 6.4cm )
7.4"
( 18.9cm )
10.3"
( 26.2cm )
2.0"
( 5.1cm )
4.1"
( 10.3cm )
6.8"
( 17.2cm )
1.0"
( 2.5cm )
TOP
LEFT
RIGHT
REAR
FRONT
BOTTOM
SERVICE CLEARANCE
36”
30"
30"
0”
30"
0”
91 cm
76 cm
76 cm
0 cm
76 cm
0 cm
Technical data
Max.Rated Steam 960 lb/hr 435 kg/hr 1070 lb/hr
Nominal @ 5psi 58-386 lb/hr 26-175 kg/hr 67-446 lb/hr
Nominal @10psi 91-609 lb/hr 41-276 kg/hr 102-682 lb/hr
485 kg/hr
30-202 kg/hr
46-309 kg/hr
Nominal @15psi 142-950 lb/hr 64-430 kg/hr 158-1050 lb/hr 72-476 kg/hr
Steam Valve CV 40 65
Supply water con.
SE 950
0.5” NPT
SE 1050
0.5” NPT
Drain water con.
Aux. drain con.
Pressure steam in.
Steam Cond. Out.
Atm. Steam Out.
Weight Empty
Weight Full
0.75” O.D. tube
0.5” NPT female
2.0” NPT
1.25” NPT
0.75” O.D. tube
0.5” NPT female
2.5” NPT
1.25” NPT
2 x 4” OD 2 x 10.16cm OD 2 x 4” OD 2 x 10.16cm OD
703 lb
1384 lb
319 kg
628 kg
703 lb
1384 lb
319 kg
628 kg
Physical Data
SETC 950 - 1050
5/4/07
- 7 -
- 8 -
NOTES:
1. UNIT WEIGHT WITH WATER = 180 LB. THIS DOES NOT INCLUDE THE ADDITIONAL PLUMBING NEEDED
FOR CONNECTION. TOTAL WEIGHT MUST BE DETERMINED BY OTHERS.
2. STRUCTURAL CONSIDERATIONS ARE THE RESPONSIBILITY OF OTHERS.
3. PROPER MOUNTING MEANS, SUCH AS; THE SECURING OF FASTENERS OR OTHER JOINTS, IS THE
RESPONSIBILITY OF OTHERS.
4. UNIT CANNOT BE USED AS A STRUCTURAL MEMBER. NO OTHER COMPONENTS MAY BE ATTACHED TO
IT.
5. SERVICE ACCESS IS REQUIRED AT THE FRONT AND RIGHT SIDE OF THE UNIT. A MINIMUM OF
30” (76 cm) CLEARANCE IS NEEDED.
6. SIZES AND FEATURE LOCATIONS ARE TO BE DERIVED FROM THE UNIT DIMENSIONAL DRAWINGS OR
BY CONSULTING THE FACTORY.
SECURE RODS
TO STABLE STRUCTURE
UPPER BRACING BRACKET
RECOMMENDED
THREADED ROD
3/8" OR METRIC M10
SLIDE UNIT ONTO RODS
THROUGH HOLES PROVIDED
SLIDE FACTORY SUPPLIED
BOTTOM BRACKETS IN PLACE
IF USING FACTORY HARDWARE, RODS CAN
ONLY EXTEND 1" PAST THE BOTTOM OF THE CABINET
SECURE BRACKETS TO RODS. PROPER INSTALLATION MEANS MUST BE
USED TO ENSURE THAT THE ASSEMBLY DOES NOT DETACH
IF USING FACTORY DRIP PAN, FASTENING HARDWARE MUST BE CONCEALED
WITHIN THE PROFILE OF THE BOTTOM BRACKETS
ATTACH DRIP PAN. SECURE TO BOTTOM BRACKETS VIA END SCREW ATTACHMENT
DO NOT DRAIN UNIT INTO DRIP PAN. DO NOT ROUTE ANY OTHER FLUID TO DRIP PAN.
DRIP PAN IS NOT A STRUCTURAL MEMBER AND CANNOT BE USED TO SUPPORT OTHER ELEMENTS
1/2 NPT PLUMBING OR EQUIVALENT IS RECOMMENDED
TERMINATE AT DRAIN
- 9 -
SE 50
Ceiling Mounting Installation (Optional)
3/27/06
- 10 -
A
10”
(258mm)
*Required for
SETC Outdoor
475-1050
FRONT
RIGHT
CLEARANCE
ENVELOPE
30”
(76.2 cm)
*Cleaning Port for
SETC Outdoor 475-1050
Power and
Controls
TOP
NEMA RATED
JUNCTION BOX
(By Others)
Vent
Hood
Steam
Outlet(s)
Cleaning
Port
BACK
LEFT
FRONT
RIGHT
Model
SETC Outdoor 100
SETC Outdoor 175
SETC Outdoor 250
SETC Outdoor 375
SETC Outdoor 475
SETC Outdoor 675
SETC Outdoor 950
SETC Outdoor 1050 in
21.5
27.9
43.5
A cm
54.6
70.8
111
59.1
150
Shipped Operating
Weight Weight lbs kg lbs kg
267 121 423 192
355
529
703
161
240
319
599
992
1384
272
450
628
Steam Outlet
(O.D.) in cm
1x1.75
1x4.4
1x3 1x7.6
1x3 1x7.6
1x4 1x10.2
1x4 1x10.2
2x4 2x10.2
Pressure Steam
Inlet
NPT
0.5
0.75
1
1.5
1.25
1.5
2
2.5
Steam Condensate
Outlet
NPT
0.75
0.75
1
1.25
- 11 -
SETC Outdoor Dimensions
1/26/04
- 12 -
SE INDOOR INSTALLATION
LOCATING AND MOUNTING
SE Series humidifiers are designed to mount on an SE Stand (Included with all models) or floor. The clearance dimensions shown in this manual are for reference only and are the minimum required for maintenance of the humidifier. Local and National
Codes should be consulted prior to final location and installation of the humidifier. NORTEC cannot accept responsibility for installation code violations.
· Figure #1 shows the locations of all required connections to the Steam Exchange Humidifier.
Careful consideration should be given to all of these connections when choosing a location for the humidifier.
· For front and side clearance requirements (for access during installation, maintenance and troubleshooting), refer to pages 3 - 6.
· DO NOT locate humidifier any further than absolutely necessary from steam distributor location. Net output will be reduced as a result of heat loss through steam line. Also, increased static pressure (over 12" W.C.) will result in hot water going down the drain. Consult factory if this situation occurs.
· Where possible, mount humidifier at a height convenient for servicing.
· Ensure the humidifier is mounted level.
Figure #1
Primary Wiring to Humidifier
· Ambient temperature location for humidifier:
41ºF - 104ºF (5ºC - 40ºC).
· Relative humidity location for humidifiers:
5% rh - 80% rh.
· DO NOT mount humidifier on hot surfaces.
· DO NOT mount humidifiers in an area where freezing may occur.
· If humidifiers are mounted on roof, a properly ventilated, temperature controlled, (above freezing), weatherproof model should be used.
Consult your local representative for more information on NORTEC’s SETC Outdoor model.
· DO NOT mount humidifiers on vibrating surface.
Consult factory.
· The humidifier shall not be installed directly on carpeting, tile or other combustible material other than wood flooring.
· Some insulating materials may be combustible.
Prior to installing this appliance examine the area for insulating material. If this appliance is installed in an insulated space, it must be kept free and clear of insulating materials. If insulation is added after the appliance is installed, it will be necessary to examine the area again.
PRIMARY WIRING
All work concerning the electrical installation must be performed by qualified personnel.
- 13 -
ELECTRICAL
WARNING: The electrical parts inside the humidifier are very sensitive to electrostatic discharge.
Appropriate measures against electrostatic discharge
(ESD protection) must be taken when carrying out installation work.
· The humidifier should only be connected to primary power (main power) after all installation work has been completed.
· An external disconnect switch(by others) must be installed close to the unit to allow for power interruption during servicing and/or maintenance.
· Humidifiers require field wiring to primary voltage terminal blocks. Power requirement must be
110-120/1/60Vac, 15A or 20 A for SETC Outdoor
950 &1050 separately fused circuit, single phase.
Wiring can be fed through a 7/8" hole on the bottom or the top of the control compartment.
· When installed, the appliance must be electrically grounded in accordance with local codes or, in the absence of local codes, with the National
Electrical Code, ANSI/NFPA 70, and/or the CSA
C22.1 Electrical Code, if an external electrical source is utilized.
· External wiring sizes must be in accordance with
NEC and/or CEC and existing local electrical codes and by-laws.
LOW VOLTAGE CONTROL WIRING
(See Page 14 for details)
All SE models require at least one type of input control signal for unit operation. Refer to the sections below that detail the types of controls that can be used with each model.
Low voltage control terminal strips are provided in the electrical compartment. Refer to the specific control wiring diagram supplied with each unit.
Field wiring from humidistat to humidifier and between devices should be shielded 18 AWG or heavier and kept as short as possible.
Controls are available from NORTEC as accessories and can be ordered with the humidifier.
Controls by others may also be used as long as they meet the criteria noted below. The following is a summary of the common types of controls that may be used with NORTEC SE Humidifiers.
A – Wall or Duct Mounted Control On/Off
Humidistat: Wired to make on drop in humidity, break on rise to set point. Set to desired RH. Can be a make/break set of contacts from a Building
Management System.
B – Duct Mounted Safety High Limit On/Off
Humidistat: Wired to make on drop in humidity, break on rise to safety set point. Set to approximately 85%
RH as a safety to prevent saturation and wetting in the duct. Highly recommended for ducted applications.
C – Duct Mounted Safety Air Proving On/Off
Switch: Wired to make when sensing air flow, break when no air flow. Used as a safety to prevent saturation when there is no air flow. Highly recommended for ducted applications.
D – Wall or Duct Mounted Modulating Humidistat:
Provides a modulating signal to the unit that represents the output (up to 100%) required from the humidifier. Signal type can be changed in the field via dip switch settings on the logic control board. Refer to
SETC Setting section.
The SETC can accept a single or dual control signal. The SEP can only accept a single control signal:
0-20 mA
4-20 mA
0-10 VDC
2-10 VDC
0-5 VDC
1-5 VDC
ON/OFF
SETC
4-20 mA
0-10 VDC
ON/OFF
SEP
The unit must be ordered from the factory for the desired signal type and number of channels. If no signal type was specified, ON/OFF control signal will be set as default. When configured for 2-channel modulation the humidifier will generate steam only if both channels indicate a demand (see D). If both channels are demanding steam the humidifier will satisfy the lower demand signal.
- 14 -
SETC SERIES
EXTERNAL CONTROLS WIRING CONNECTIONS
LOW VOLTAGE TERMINAL STRIP
NOTE: This is a generic wiring diagram only. For specific wiring instructions, it is necessary to refer to the wiring diagram which is supplied with each unit.
WA R N I N G : F a i l u r e t o w i r e t h e c o n t r o l l e r i n a c c o r d a n c e w i t h t h e w i r i n g d i a g r a m t h a t w a s s u p p l i e d w i t h t h e u n i t c o u l d p e r m a n e n t l y d a m a g e t h e S E T C b o a r d . S u c h e r r o r s w i l l v o i d t h e u n i t w a r r a n t y.
Security Loop
EXTERNAL
1 2 3 4 5 6
INTERNAL
7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
EXTERNAL
INTERNAL
NOTE: If no On/Off Control is used then a field jumper must be connected across terminals 1 and 2 in order for the humidifier to operate.
Low Voltage Terminal Strip
1 & 2: Wire all on/off controls and safeties between these two terminals. If not used, jumper 1 & 2 for the unit to operate.
4: Modulating input to humidifier “A”.
5: Modulating input to humidifier “B”.
6: 10 Vdc output (20 mA max.) Can be used to simulate demand to unit..
8: When 24 Vac input received, the unit will initialize a full tank blowdown.
9: Safety interrupt (24 Vac).
10 & 11: Remote indication connection for humidifier “on” status indication.
12 & 13: Remote indication connection for humidifier “active” status.
14 & 15: Remote indication connection for service required indication.
16,17 & 18: Remote indication connection for fault indication.
19, 20 & 21: Modulating output and 24VAC power to actuator
SETC SERIES
External Controls Wiring Connections
09/16/2004
- 15 -
SEP SERIES
EXTERNAL CONTROLS WIRING CONNECTIONS
LOW VOLTAGE TERMINAL STRIP
NOTE: This is a generic wiring diagram only. For specific wiring instructions, it is necessary to refer to the wiring diagram which is supplied with each unit.
WA R N I N G : F a i l u r e t o w i r e t h e c o n t r o l l e r i n a c c o r d a n c e w i t h t h e w i r i n g d i a g r a m t h a t w a s s u p p l i e d w i t h t h e u n i t c o u l d p e r m a n e n t l y d a m a g e t h e S E P b o a r d . S u c h e r r o r s w i l l v o i d t h e u n i t w a r r a n t y.
Security Loop
EXTERNAL
1 2 3 4 5 6
INTERNAL
7 8 9 10 11 12
EXTERNAL
INTERNAL
NOTE: If no On/Off Control is used then a field jumper must be connected across terminals 1 and 2 in order for the humidifier to operate.
Low Voltage Terminal Strip
1 & 2: Wire all on/off controls and safeties between these two terminals. If not used, jumper 1 & 2 for the unit to operate.
4: Modulating input to humidifier
5, 6 & 7: Modulating output and 24VAC power to actuator
8, 9 & 10: Remote indication connection for fault indication.
SEP SERIES
External Controls Wiring Connections
09/16/2004
- 16 -
CONTROL INSTALLATION
· Mount any wall humidistat (control or high limit) over standard electrical box at height similar to typical thermostat. Any wall humidistat should be in location representative of overall space being humidified and not in path of blower pack or air supply grille. Do not mount on an outside wall where temperature fluctuations can affect control response. (Windows, sky lights, sinks, coffee machines, etc.)
· Mount duct humidistat in location representative of overall air humidity, usually in return duct. Do not mount it directly in front of steam distributor or in turbulent or mixing zone. Mount humidistat where air’s humidity and temperature are uniform and representative of spaces being humidified.
· Mount duct high limit humidistat downstream of steam distributors far enough that, under normal humidity and air flow conditions, steam will have been fully absorbed (typically at least 10 feet). It must be located to sense high humidity only when uniform and representative air is over-humidified or approaching saturation.
· Mount duct air-proving switch so that it is able to sense air flow or lack thereof it. Wire it to make when air flow is sensed and break when air flow fails.
· Check operation of all on/off controls before starting humidifier.
· Calibration of controls (on/off or modulation) in the field may be necessary due to shipping and handling. Verify humidistat accuracy before commissioning system.
PLUMBING
NOTE: All water supply and drain line connections should be installed in accordance with local plumbing codes.
WATER QUALITY
· The humidifier is intended to operate on cold water.
· DO NOT use a hot water source to supply the humidifier. Minerals will adhere more easily to surfaces and the fill valve’s small flow regulating orifice could become plugged.
· Consider using a water softener. Longer operating times between tank cleaning will be achieved with softened water.
· Reverse osmosis (RO) water can provide very long periods before cleaning is required since it is cleaner than softened water. Deionized (DI) water may be used with all models with the stainless steel water supply option. Consult your
NORTEC representative for a quote on a water treatment system.
FILL WATER SUPPLY LINE
· Each unit is supplied with an adapter for the fill valve (½”NPT ). The SE 50-675 has a fill rate of
10l/min (2.6 gpm) and the SE 950-1050 of
17l/min (4.5gpm). Size of piping is a minimum ½” copper, recommend ¾” up to within 4 feet of unit.
· Standard fill valves are sized for water pressure ranging from 30 to 80 psig (ideally 55 to 60 psig).
For other pressures, consult factory. This pressure should be measured at the humidifier if the water pressure is suspect.
· It is recommended to have a faucet installed close to the humidifier to allow quick filling of the system on initial start up. This can also be very useful for mandatory cleaning of the unit.
· ALWAYS supply and install a shut-off valve and union in the water supply line dedicated to the humidifier to facilitate servicing.
Figure #2
Installation
- 17 -
DRAIN LINE
· The humidifier is equipped with a ¾”O.D. drain outlet connection on the side of the humidifier. A vacuum break valve is installed internal to the unit on the drain line. The drain water line must be piped to a drain funnel to provide an air gap before connection to the building drainage system.
· The drain line should not end in a sink used frequently by personnel, or where plumbing codes prohibit it. Route to a floor drain or equivalent for safety reasons. Internal drain water tempering will ensure a maximum of 140ºF
(60ºC) exiting water temperature.
· Keep drain lines as short as possible. Keep drain lines sloped down, not level and not up since low spots in drain lines will accumulate sediment and cause backup. The drain line should be 1-1.5"
O.D. or larger. Consult local codes.
· When the drain pump is activated, the tank drains at a rate of 7-8 gal/min (18-20 l/min).
STEAM CONDENSATE OUTLET
MODEL OUTLET
SE 50, 100, 175, 250 and 375 ¾” NPT
SE 475, and 675 1” NPT
SE 950, and 1050 1 ¼” NPT
· The SE humidifier has a condensate return line connection for removal of the condensate formed in the heat exchange.
· Condensate line after the steam trap(s) must be atmospheric and lower than the traps at all times.
If required, a condensate pump (by others) can be used to return condensate to the humidifier.
AUXILIARY DRAIN OUTLET
· An auxiliary drain port is also provided on the side of the humidifier. It can be used to manually drain the unit, if required. The unit is shipped with this connection plugged. It is recommended to install a shut off valve on this line.
· The auxiliary drain port is used when the freeze protection option is required. Install a shut off valve on this line and pipe to the drain funnel.
The manual shut off valve must always be in the open position when the unit is operating but can be closed for servicing of the unit.
- 18 -
STEAM LINES AND CONDENSATE LINES
For steam line installation between the humidifier and distribution system, consult the distribution system installation manual. Steam Distributor Installation
Manual - Form #XX-231 and SAM-e, Short Absorption
Manifold - Form #XX-249.
The SE series of Steam Exchange humidifiers can develop steam pressures up to 12” w.c. to overcome duct and steam line pressures. An enclosed trap on the drain line prevents steam from going to drain.
Duct pressures above 12” will cause steam to exit through the drain line. Consult factory.
PRESSURIZED STEAM CONNECTIONS
Proper design and sizing of steam supply lines should be preformed by a qualified firm.
STEAM SUPPLY PIPING
The steam valve, actuator, wye strainer, and shut-off valve should be installed by a qualified technician.
Steam supply to the unit must be taken from the top of the supply main. Do not take from the sides or the bottom. The steam shut-off valve (supplied by others) should be installed on the supply line at the unit, followed by the wye strainer.
The steam valve and Actuator must be located as close as possible to the humidifier. Further than 6”
(15cm) away may result in lower output.
ACTUATOR INSTALLATION
WHAT COMES WITH THE ACTUATOR
1.
Jam Nut
2.
Lock Washer
3.
Stem Extension
4.
Connecting Pin
5.
Set Screw
Figure #3
Actuator Parts
3.
Thread the stem extension on to the valve stem making contact with the lock washer.
4.
Pre-load the actuator
PRE-LOADING INSTRUCTIONS
1.
Inserting the hex wrench as illustrated and cranking 1 ½ turns in the direction shown on the actuator. Lock it into position with the locking mechanism using a slotted screwdriver.
Figure #5
Pre-loading Instructions
INSTALLATION INSTRUCTIONS
1.
Thread jam nut on to the valve stem as far as it will go. At least ½” of the valve stem should extend above the nut.
2.
Place lock washer over the valve stem so it is seated on the jam nut.
Figure #4
Installation Instructions
2.
Install the actuator on the valve and tighten the mounting nut and raise the valve stem to the full up position.
Figure #6
Pre-loading Instructions
- 19 -
3.
Rotate the stem extension until it’s hole lines up with the hole in the shaft of the actuator.
4.
Insert connecting pin to secure stem extension and tighten jam nut against stem extension using 5/16” open-end wrench.
5.
Affix open/closed label to the indicator in the appropriate position.
6.
Insert set screw (packaged with actuator) into the most accessible side. Tighten with size 10
IP Torx bit to 20-25 lb-in.
7.
Apply power to the actuator and check the system operation (steam output) in relation to the control signal.
Figure #7
Pre-loading Instructions
- 20 -
SETC OUTDOOR
INSTALLATION
SETC Outdoor units come complete with internal ventilation (cooling) for the electronics, and optional heaters for freeze protection in cold climates.
All installations must conform with local building codes. NORTEC can not accept responsibility for installation code violations.
MOUNTING
· A typical rooftop installation is shown on page 19.
· The SETC Outdoor unit comes standard with cut-outs in the base to allow for lifting by a forklift.
When lifting by this method, ensure that the forks extend across the entire base to prevent tipping or damage to the unit.
· The enclosure also comes complete with four (4) removable lifting lugs fastened to the base. All four lugs must be utilized if moving the unit in this manner. Protect the cabinet from damage from the lifting cables/chains during lifting. The lifting lugs should be removed from the base once the unit has been correctly positioned on the curb mounting.
·
The SETC Outdoor models have a zero” clearance to combustibles. However, choose the location for the humidifier to allow for side and frontal clearances for access during installation, maintenance and servicing.
· The integral base of the SETC Outdoor model is designed to mount on a curb. The curb must be built to structurally support the entire weight of the humidifier when in operation.
· Ensure that the humidifier is mounted level.
·
The pan in the bottom of all outdoor models has a pipe chase for routing of services into the humidifier from below.
· It is not necessary to make the hole in the roof the same size as the curb. The curb drawing shows the location and size of the pipe chase required. The pipe chase should be sealed when the installation is complete to ensure positive or negative pressure from the building.
· The panels of the outdoor model have louvers to provide ventilation for the electronics and air for the combustion process. Locate the unit so that
- 21 louvered panels are a minimum of 10 ft (3m) from any mechanical exhaust outlet.
·
When mounted on the curb, the lowest air intake louvers must be a minimum of 12” (30.5cm) above any surface where snow or ice could accumulate. In areas where normal snow accumulation is higher, mount the unit accordingly.
·
Do not store or use gasoline or other flammable vapors and liquids in the vicinity of the humidifier.
PRESSURE STEAM SUPPLY
·
Steam Lines are to be routed through the pipe chase located on the floor of the unit.
·
The steam valve and actuator must be located as close as possible to the unit.
·
A wye strainer must be installed prior to the valve.
· Please refer to Actuator Installation Section.
ELECTRICAL INSTALLATION
· Power and control wiring is to be routed into the humidifier through the pipe chase in the base pan of the outdoor models located in the heat exchange area.
· Installation details for primary and low voltage control wiring are the same as for indoor units.
Figure #8
Electrical Disconnect Installation
Electrical
Disconnect
(by others)
Roof Curb
(by others)
Drain
Lines
Pressure Steam
Supply
Funnel
With Air Gap
Water
Supply
Manual
Shut-off
AHU
Steam Line
Steam Line
Roof Curb
(by others)
Electrical
Disconnect
(by others)
- 22 -
Typical SETC Outdoor Installation
· A field supplied NEMA rated disconnect switch must be mounted external to the SETC Outdoor unit to allow for power interruption during servicing and/or maintenance. A mounting plate, located on the front of each outdoor model above the electrical access door, is available for mounting of the disconnect switch. Two electrical conduits are provided for routing the primary wiring to the disconnect switch and then back inside the enclosure to the main power terminal strip. See Electrical Disconnect Installation
Figure for details.
FILL WATER SUPPLY LINE
· Each unit is supplied with a ½” NPT male connection to the fill valve. Refer to Installation
Figure for connection details. A minimum fill rate of 10 l/min (2.6 gpm) is required for the SE
100-675 and 17 l/min (4.5 gpm) for SE 950-1050.
Allowable pressure range is 30-80 psig.
· Always install a manual shut off within the building to allow isolation of the water to the unit.
A union must be installed on the fill line prior to the fill valve to allow for servicing.
· Heat trace fill line piping above rooftop from the pipe chase up to the fill valve.
DRAIN LINE
· SETC Outdoor units have an integrated 12” (30.5
cm) w.c. trap and vacuum break valve on the drain line.
·
Route the drain hose to a drain funnel in the building to provide an air gap before entering main building drain/sewage system.
· When the drain pump is activated, the tank drains at a rate of 18-20 l/min (7-8 gpm).
· Internal drain water tempering will ensure a maximum of 140 °F (60°C) during normal operation.
AUXILIARY DRAIN
· Standard SETC Outdoor units come with a capped ¾”NPT auxiliary drain connection at the bottom of the tank. It is recommended to install a manual shut-off valve on this connection and route to drain (provide an air gap).
· SETC Outdoor units equipped with a freeze protection package have a normally open drain valve mounted at the auxiliary drain connection and piping that terminates at the pipe chase in the base pan. This valve opens and will drain the contents of the tank in the event of a power failure. Install a manual shut off valve on this line and pipe to the drain funnel. This valve must always be left in the open position when in operation but can be closed for servicing of the unit.
· Drain pipe should be capable of withstanding
200
°F temperatures.
STEAM LINES
· The steam outlet connection is located at the back of the SETC Outdoor unit. Steam hose(s) and clamps are supplied with the unit and are intended to provide a flexible coupling outside of the unit to the building steam lines.
· SETC OUTDOOR models can develop steam pressures up to 12” (30.5 cm) w.c. to overcome duct and steam line pressures. Pressures above
12” (30.5 cm) w.c. will cause steam to exit through the drain line.
· Steam lines can be routed to an air handler on the roof or pipe chase (external to the unit) through the rooftop to enter the building.
·
All steam lines must be insulated to reduce losses.
· For steam line installation guidelines, consult the distribution system installation manual (Steam
Distributor Installation Manual Form #XX-231 and
SAM-e Short Absorption Manifold Form #XX-249
END OF SETC OUTDOOR
OPERATION
WATER MANAGEMENT
- 23 -
The SE Series is equipped with a unique float chamber water level monitoring device. Two magnetic floats measure 5 different water levels on the SETC models, and 2 different water levels on the SEP models for proper operation. The float chamber and board are located away from the boiling action to increase reading accuracy and reduce mineral build-up.
The float chamber is connected to the tank under the water level and above the water level to ensure equalization of pressure between the tank and float chamber. In addition, cooling water is introduced in
Pressure
Equalizer
Figure #9
Plumbing Connections
Float Chamber
Fill Chamber
Vacuum Break
Main Fill to System
Dual Fill Valve
Drain Outlet
Internal Trap
Drain Pump
Aux. Drain the float chamber to reduce scale build-up. The unit also includes an internal 1” air gap and a vacuum breaker to prevent siphoning effect.
On initial start-up, the solenoid operated fill valve fills the tank. The water level reaches the backup float first and then the main float. If the backup and main floats do not read the same water level during the operation of the unit, the unit will shut down on a fault.
The unit will continue to fill to the top yellow position.
The drain pump will then be energized to drain the water level down to just below the bottom red position and then the fill valve will energize again to fill the unit to the middle green position. During this time the software is performing a test on the fill valve and drain pump.
If a demand signal is present, the unit will then begin to open the steam valve. As the unit operates, the fill valve will be pulsed to maintain the water level between the yellow and green positions. During steam production the unit will also check if the floats and drain pump are operational by activating a drain sequence every 24 hours. (adjustable to time of day)
INSPECTION AND START UP
PROCEDURE
START-UP CHECKLIST
Before the SE humidifier is operated for the first time, a complete inspection must be performed to ensure that the installation and all water, pressure steam, atmospheric steam lines, and electrical connections to the humidifier conform to the guidelines
- 24 in this manual. Complete the checklist on pages 24 &
25 before commissioning the unit.
Qualified personnel must correct any deficiencies with the installation before commissioning takes place.
Prior to starting the humidifier, it is necessary to ensure that no dirt or dust has accumulated in the electronics compartment. A build up of dust on the electronics can cause overheating and early failure of the components.
FILLING THE SYSTEM
Before the SE unit will open the steam valve, it must be filled with water and the internal controller must have completed a self-test to verify that the water fill system, level controller, and drain pump are functioning correctly.
· Close the shut-off valve in the pressure steam supply line.
· Remove any demand signal to the unit.
· Open the shut-off valve in the water supply line.
· Switch the humidifier on.
· The fill valve will energize and the tank will begin to fill (fill time is approximately 10 to 30 minutes depending on the SE model). Once the float chamber has registered low water level, the unit will perform an internal test of the fill and drain system as described in the Water Management section.
· At the completion of the test, the float chamber will indicate middle float position (green LED) and the unit will go into standby mode until a demand signal is received.
STARTING THE HUMIDIFIER
Once the tank has been filled, the humidifier is ready to be put into operation.
· Verify that the inspection checklist has been completed and all deficiencies with the installation have been corrected.
· Open the shut-off valve in the pressure steam supply line.
· Open the shut-off valve in the water supply line.
· Ensure all external controls connected to the security loop are closed.
· Verify that the building demand signal is connected to the humidifier.
· Install and secure all cabinet service doors.
· Switch the humidifier on.
· At the completion of the float test, the humidifier will begin to open the steam valve and warm up the water.
· Depending on the system demand, the actuator will open or close to control the amount of steam injected into the heat exchangers.
· The water in the tank will heat up and begin to boil, delivering steam to the distribution system.
· During the boiling sequence the water fill valve will periodically activate to replenish water that has evaporated from the tank.
· Once the humidity requirements have been satisfied (demand drops below minimum %) the steam valve will be de-energized and will be shut off.
· The humidifier will go into standby mode until the next call for humidity.
TAKING OUT OF OPERATION
If it is required that the humidifier be taken out of operation (e.g. for service or end of season shut-down), proceed as follows:
· Remove the demand signal or open the security loop, allowing the steam valve to shut off.
· Switch the main power switch from On to Off and then to the Drain position. The drain pump will be energized and the tank will begin to drain.
· Once the tank has completely emptied, shut off the drain switch.
· Close the shut-off valve in the pressure steam supply line.
· Close the shut-off valve in the water supply line.
· Isolate the humidifier from the electrical power supply at the main disconnect switch.
- 25 -
SE INSPECTION CHECK LIST
HUMIDIFIER MOUNTING
£ Verify proper clearances around the unit
£ Humidifier mounted level
£ Humidifier properly secured to stand and stand bolted to floor
£ All service doors accessible
£ Roof curb sized correctly (Outdoor Model Only)
PRESSURE STEAM PIPING
£ Test joints for leaks
£ Manual shut-off valve installed prior to Steam Valve & Actuator
£ F&T Trap installed prior to Steam Valve & Actuator (by others)
ATMOSPHERIC STEAM or STEAM DISTRIBUTION LINES
£ Slope up 2” per 12”
£ Sloped back to drain
£ Slope down1/2” per 12”
£ Trapped 2” more than static duct pressure
Traps £ - Size _______________
Insulated
£
Length/Size _______________
90º Elbows £
45º Elbows £ qty: ______ qty: ______
Can condensate be trapped anywhere in the steam line? Yes £ No £
CONDESNATE LINES
£ Sloped back to drain
£ Trap is greater than 2” duct static pressure
£ Size of Trap ___________
SE Series Inspection Checklist
- 26 -
SUPPLY WATER LINE
£ Nortec supplied adapter installed on fill valve (1/2” NPT)
£ Manual shut off valve and union installed
£ Verified pressure (30-80 psig)
£ Water source of 10 L/min (2.6 gpm) for SE 100-675 or 17L/min (4.5 gpm) for
SE 950-1050
£ Leak tested
£ ½” dia. at max 4ft from the unit
DRAIN LINES
£ Air gap located within 3ft of the unit
£ Minimum drain line size of 1” – 1.5” in dia.
£ Downward slope
£ Tundish (funnel) installed to provide air gap
£ Temperature rating of piping
£ Hose connections tightened
£ Auxiliary drain piped with shut off valve to tundish
WATER QUALITY
Well Water £ City Water £ Softened Water £ RO/DI £ Water £
Conductivity:______ mmhos Hardness: ______ GPG Silica: ______ ppm
Chlorides: ______ ppm pH: ______
ELECTRICAL INSTALLATION
£ Comply with local regulations
£ Proper supply voltage (must match rating plate) and breaker size
£ Electrical disconnect switch close to humidifier
£ Cables properly affixed
£ Low voltage wiring & control signal(s) wired to correct terminals
£ Humidifier configured for correct control signal(s)
TYPE OF CONTROLS INSTALLED/LOCATION/WIRING/SETTING
£ High Limit ___________________________________________
£ Air Proving ___________________________________________
£ Modulation Control _____________________________________
£ On/Off Control ________________________________________
£ Controls by Nortec ____________________________________
£ Control by Others _____________________________________
SE Series Inspection Checklist
- 27 -
SCALE MANAGEMENT
The steam exchange humidifier will periodically
“blowdown” water from the tank to reduce the concentration of total dissolved solids that accumulate during long term operation.
Steam Exchange Humidifiers are shipped factory set with a blowdown of 25%. This setting ensures that scale build-up will be minimized for all water conditions.
Once the water conditions are known, the blowdown rate can be adjusted by software (SETC models) or by using dip switches on the logic control board (SEP models).
Another effective means of controlling the amount of scale in the tank is with the use of the Full Tank
Blowdown (FTBD) built into the software. When this feature is activated, the drain pump will be energized to drain the entire contents of the tank and then the tank will be refilled with fresh water, thus keeping the amount of total dissolved solids to a minimum. The feature can be programmed in the software to occur after a specific amount of operating time and can also be triggered by a signal sent to the humidifier from a building management system.
WATER QUALITY
Due to the wide range of water conditions found throughout North America it is important that the blowdown is set according to the local water conditions. By water conditions we are referring to the hardness of the water supplied to the humidifier. The hardness is measured in grains per gallon. It is also important to test for silica content. Silicates may cause foaming and contribute to scale buildup in the humidifier tank and float chamber.
If you are unaware of the hardness or silica content of your water supply, there are many “do it yourself” kits which can be purchased, or there are several companies that will perform the tests for a reasonable price. You can even contact your municipality for your water condition or order the
NORTEC water test kit.
Note: Water quality conditions resulting in component failures are not covered under
NORTEC’s standard warranty.
· Silica Test: Measured in ppm (parts per million)
Follow the directions with the kit. A high reading will
Figure #10
Site Water Test Kit P/N 1507214 decrease the performance of your system. The recommended operating range for silica is 0 ppm to
14 ppm. Note: A high silica content along with a high hardness content may increase the service intervals of the system . Consult the factory if this condition exists at the site.
· Hardness: Measured in gpg (grains per gallon).
Follow the instructions on each individually wrapped test strip and use the colour chart provided. The recommended operating range for hardness is 0 gpg to 12 gpg. Note: High hardness along with high silica may increase the service intervals of the system. Consult the factory if this condition exists at the site.
· pH: Follow the directions on the test strip bottle.
The recommended operating range for pH is 6.5
to 7.5 on the colour scale. Consult the factory if outside these parameters.
· Chlorides: Measured in ppm (parts per million).
Follow the directions on the test strip bottle. The recommended level for chlorides is not to exceed
25 ppm. High levels of chlorides will attack stainless steel. Add an in-line carbon filter that will remove up to 99% of the chlorides. Consult the factory for additional information if your water contain high levels of chlorides.
· Conductivity: Measured in micromhos. Follow the directions for the conductivity pen found inside the box. Multiply the digital reading by 1.5.
The recommended operating range for conductivity is 0 - 1500 micromhos. Consult the factory if you measure outside these parameters.
- 28 -
Technology
Water
Type
Water
Cond.
Range
Hardness
Range
Silica
Range
Alklin.
Range
Chlor.
Range
Steam
Exchange
Microm
-hos
GPG PPM pH PPM
Potable 0-1500 0-12 0-14 6.5-7.5 0-25
Treated 0-100 0-1 0-1 7-7.5
0-25
· NORTEC recommends performing a semi-annual water analysis to ensure optimal performance.
· The humidifier is intended to operate on cold potable tap water.
· DO NOT use a hot water source to supply the humidifier. Minerals will adhere more easily to surfaces and the fill valve's small flow regulating orifice could become plugged.
· Consider using a water softener. Longer operating times between tank cleaning will be reached on softened water.
· Reverse osmosis (RO) water can provide very long times before cleaning is required since it is cleaner than softened water. Deionized (DI) water may be used with all models.
· Consult your NORTEC representative for a quote on a water treatment system.
MAINTENANCE
To ensure proper performance and long operating life of the SE humidifier, a proper maintenance schedule should be followed. Since the amount and type of maintenance required is generally a result of how much the humidifier operates, all SE humidifiers monitor the amount of steam produced over time, and will indicate when service is required. All units come factory set with a service interval of 500 hours. This service interval can be adjusted through software
(SETC models) or by jumpers settings (SEP models) on the logic control board. Refer to the maintenance schedule for maintenance guidelines and intervals.
All maintenance work must be performed by experienced and trained personnel.
NOTE: Use only NORTEC original parts to replace damaged or defective components. Failure to do so may cause improper operation of the humidifier and will void warranty.
- 29 -
DRAINING THE TANK
During extended periods of inactivity such as offseason, it is advisable to drain the water from the tank.
On all models this is accomplished by switching the unit to “Drain”.
Do not remove the front or top clean out port on the tank until the unit is completely drained and cool.
The SETC model includes a pre-cleaning sequence feature. When activated (through the keypad), the unit will flush the humidifier, refill with cold water, and flush again reducing the scale accumulated at the bottom of the tank.
CLEANING THE STAINLESS STEEL TANK
& FLOAT CHAMBER
CAUTION: Water and scale may be hot enough to cause burns. Turn off humidifier and allow it to cool before cleaning.
It is recommended that the tank be cleaned at least once every season to maintain optimum operation. It may be necessary to increase the frequency of cleaning or increase the blowdown setting in areas of hard water or prolonged annual usage (see the “Blowdown Setting section of this manual).
Cleaning of the humidifier is mandatory and must be performed on a regular basis.
To reduce cleaning time, use the pre-cleaning sequence on the SETC model to help evacuate mineral debris from the unit. Check the controller operation to activate this feature.
The heat exchanger walls are usually self cleaning. The mineral build-up flakes off, due to the expansion and contraction and boiling action during on/off cycles, and settles to the bottom of the tank. The end block will have scale build-up. These surfaces must be cleaned at regular intervals.
Most cleaning will be done through the front door of the unit. Remove cabinet door on the left of the
LCD display using a Philips screwdriver. Remove the side tank port opening, by removing the 3/16” nuts (½” key or socket is needed).
Additional cleaning ports are available on the top of the SE 475/675 and SE 950/1050 models. To access these ports, remove the top cabinet panel using a Phillips screwdriver. Remove the top cleaning ports by removing the nuts.
Removal of the heat exchanger(s) is not necessary to clean the inside of the tank.
Scoop out loose scale with a small shovel such as those used for gardening. Once loose scale is removed, use a scraper such as a plastic windshield scraper to remove scale adhering to the tank or heat exchanger walls. DO NOT use a metal scraper that will scratch the stainless steel surfaces of the tank.
Once all large pieces of scale have been removed, vacuum the tank out with a shop vacuum, fill part way with water, and flush remaining sediment from the tank through the drain.
Due to the presence of polymer gaskets around the heat exchanger, do not use any harsh cleaning chemicals. Please consult NORTEC prior to using any chemicals. Once the lid has been replaced, fill the unit with water and examine for leaks.
Inspect the drain and fill lines assembly for scale build-up and if necessary, remove them from the humidifier for cleaning. If the blowdown assembly becomes blocked, scale build-up in the tank will be accelerated and damage to the humidifier could result.
The drain pump may be opened and cleaned. Consult
NORTEC for proper procedure.
Re-assemble the drain and blowdown if they were removed. Re-install tank top and side lids making sure tank cover gasket is intact. Do not over tighten nuts. If using a torque wrench do not exceed 50 in-lb ( 5 ft-lb).
Re-seal all cabinet lids.
Cleaning the float chamber is accomplished by removing the screws to access the floats and using a small brush to gently clean the scale from the floats and chamber. Ensure that floats are back in place and o-ring is properly seated before tightening screws on float chamber. Special attention must be used when removing or re-installing the float chamber. The switch board must be replaced into the same position as before cleaning and the tie-wrap must be used to hold the float chamber in position.
ADJUSTMENTS/REPLACEMENTS OF
COMPONENTS
NOTE: CONSULT FACTORY PRIOR TO THE
REPLACEMENT OF ANY COMPONENT.
DANGER - SHOCK HAZARD - Make sure electrical power to the appliance is disconnected to avoid potential serious injury or damage to components.
SERVICING THE UNIT
Caution: Disconnect power before servicing this appliance.
Caution: Label all wires prior to disconnection when servicing controls. Wiring errors can cause improper and dangerous operation.
Float Chamber Replacement (Figure #6)
1.
Drain the contents of the tank and then shut off electrical power and water supply to the humidifier.
2.
Remove the left front service access door.
3.
Remove the cable connection to the float board.
4.
Remove the hose clamps on the float chamber and remove all hoses (note the correct hose assignment).
5.
Squeeze both sides of the mounting bracket to release it from the slots in the support bracket behind the float chamber.
6.
Reverse the above sequence to install the new module.
7.
Leak test all water connections before re-commissioning the humidifier.
Figure #11
Float Chamber Removal
- 30 -
Transformer Replacement (Figure #12)
1.
Shut off electrical power to the appliance.
2.
Remove front access door.
3.
Disconnect wiring connections from transformer leads labeling as required.
4.
Remove screws (2) holding transformer.
5.
Reverse above procedure to re-install.
Figure #12
Transformer Detail
Figure #13
Fill Valve Detail
Fill Valve Replacement (Figure #13)
1.
Shut off electrical power and water supply to the humidifier.
2.
Remove the right side service access door.
3.
Remove all wiring connections to the fill valve.
4.
Remove the hose clamps on the fill valve outlets and remove hoses (note the correct hose assignment).
5.
Remove the 2 screws securing the fill valve to the cabinet and remove the valve.
6.
Reverse the above sequence to install the new module.
7.
Leak test all water connections before re-commissioning the humidifier.
Drain Pump Replacement (Figure #14)
1.
Drain the unit completely. If the pump is broken use the auxiliary drain out port.
2.
Shut off electrical power to the appliance.
3.
Remove front and right doors.
4.
Remove wiring connections to the pump.
5.
Remove hoses attached to the pump.
6.
Reverse above procedure to re-install.
NOTE: To avoid water spillage (some water will be left on the tank bottom after manual
Figure #14
Drain Pump Detail
- 31 -
draining) use shop vac to remove left over water.
Fill Box Replacement (Figure #15)
1.
Drain the contents of the tank and then shut off electrical power and water supply to the humidifier.
2.
Remove the right side service access door.
3.
Remove the hose clamps and remove all hoses.
4.
Undo the 2 nuts securing the fill box to the tank.
5.
Reverse the above sequence to install the new module.
6.
Leak test all water connections before re-commissioning the humidifier.
Figure #15
Fill Box Detail
Removal of Heat Exchanger
1.
Take the humidifier out of operation.
2.
Unlock and remove the right side panel(s).
3.
Unlock and remove the left and the right top panels.
4.
Free all piping of the respective heat exchanger.
5.
Unscrew the nuts on the heat exchanger and pull out the heat exchanger from the tank.
Re-installation is carried out in the reverse sequence. Replace all seals with new ones.
- 32 -
SETC MODELS
Faults are indicated with a fault message on the display of SETC models. Recovery from lockout requires resetting of the humidifier. This can be achieved by momentarily shutting off the power switch then turning it back on, or by pressing the reset button on the logic control board mounted inside the electrical cabinet.
A history of all faults is stored in memory of the software and can be viewed through the service level on the display. Refer to the keypad display menu structure at the end of the manual.
SEP MODELS
Faults are indicated on SEP models with blinking red lights. Check the LED sequence for the fault before shutting off the unit. Resetting the humidifier clears the fault. This can be achieved by shutting off the power switch, then turning it back on.
FAULT CONDITIONS
Fault F1- Humidifier no filling: Yellow LED
Flashes twice.
Probable Cause:
- Fill Valve not energizing
- Water supply interrupted
- Float level indication inoperable
- Tank leaking.
Fault F2 - Humidifier not draining: Yellow LED flashes once.
Probable Cause:
- Drain pump blocked
- Drain pump inoperable
- Float level indication inoperable
- Drain line restricted
Fault F3 - Float level inconsistent: Yellow LED flashes four times.
Probable Cause:
- Defective float level board
- Defective float chamber
SETC SETTINGS
3 DAY DRAIN
3 DAY DRAIN FUNCTION
Function Disabled
Function Enabled (Factory set)
SW3/7
OFF
ON
KEEP WARM/INDOOR FREEZE PROTECTION PACKAGE
3 DAY DRAIN FUNCTION
Function Enabled
Function Disabled (Factory set) - 3 day drain
SW5/7
ON
OFF
ANALOG CHANNEL 1
Input Range
0-10V input
0-5V input
2-10V input
1-5V input
0-20mA input
4-20mA input
ON/OFF + inst. jumper between 4 & 6
SW1/1
OFF
OFF
OFF
OFF
ON
ON
ON
ANALOG CHANNEL 2
Input Range
0-10V input
0-5V input
2-10V input
1-5V input
0-20mA input
4-20mA input
ON/OFF + inst. jumper between 4 & 6
SW1/2
OFF
OFF
OFF
OFF
ON
ON
ON
SW4/3
OFF
ON
OFF
ON
OFF
OFF
ON
SW4/1
OFF
ON
OFF
ON
OFF
OFF
ON
SW 4/4
OFF
OFF
ON
ON
OFF
ON
ON
SW 4/2
OFF
OFF
ON
ON
OFF
ON
ON
- 33 -
INPUT CHANNEL
DUAL CHANNEL FUNCTION
One Channel Input
Dual Channel Inputs
FULL TANK BLOWDOWN
FULL TANK BLOWDOWN FUNCTION
Disabled
Enabled (Factory set)
SW4/5
OFF
ON
TIME PROPORTIONING
TIME PROPORTIONING
Disabled (Factory set)
Enabled
SW4/7
OFF
ON
MAINTENANCE SHUTDOWN
MAINTENANCE SHUTDOWN FUNCTION
Unit will shutdown 72 hours after service time expired, by generating an error.
SW5/4
OFF
Unit will display warning but continues to operate. (Factory set) ON
SW5/8
OFF
ON
- 34 -
DIP Switch Settings
-35 -
SETC
Logic Control Board
INTRODUCTORY SCREEN
NORTEC SETC-250
VERSION X.XX
SYSTEM LOCKOUT
09.05.03 9:30
MENU
MENU
MAIN MENU
SYSTEM STATUS
SERVICE LEVEL
USER SETTINGS
USE THE
UP/DOWN
ARROWS
TO MOVE THE
POINTER TO
SELECT A
MENU ITEM.
TO OPEN THE
SELECTION,
PRESS THE ENTER
BUTTON.
- 36 -
Keypad Display Menu Structure
System Status 1
- 37 -
SYSTEM STATUS 2 of 2
- 38 -
- 39 -
- 40 -
- 41 -
NORTEC TC CONTROLLER
INTRODUCTORY SCREEN
NORTEC SETC 250
VERSION X.XX
SYSTEM LOCKOUT
06.07.03 9:30
Product name
NORTEC SETC (100-1050)
Version
The display will indicate the revision level of the control software
System
Depending on system activity, the display will toggle between LOCKOUT, ACTIVE or STANDBY.
Date/Time
The actual date and time will be displayed.
MAIN MENU
The main menu lists the available sub menus where system adjustments can be made. Some of the menus are password and jumper protected to
SYSTEM STATUS
SERVICE LEVEL
USER SETTINGS
block access by unauthorized personnel.
System status
Displays various system parameters as the user scrolls through the lists. For further details see specific section below.
Service Level: (password protected)
This section is specific to all service related activity. For further details see specific section below.
- 42 -
User Settings: (password protected)
This section allows the user to set parameters specific to their requirements. For further details see specific section below.
SYSTEM STATUS
SCREEN 1:
Status:
STATUS: LOCKOUT
DEMAND CHANNEL 1 0%
DEMAND CHANNEL 2 0%
CAPACITY LIMIT 0%
Displays the present status of the system.
Depending on system activity at the time, the field could display: lockout (security loop open), active (unit generating steam) or standby (security loop closed but no modulation demand signal).
Demand channel 1:
This field will display the modulation demand input on that channel.
Demand channel 2:
Field only visible if the unit is configured for dual modulation. This field will display the modulation demand input on that channel.
Capacity limit:
This field displays the user adjusted capacity limit set for the humidifier.
SCREEN 2:
System demand:
SCREEN 3:
Water level:
This field displays the present water level detected by the float system.
Fill valve:
WATER LEVEL:
FILL VALVE
X
[O/I]
DRAIN PUMP [O/I]
DRAIN COOL: SMART
This field displays status of fill valve, on, off, or pulsed.
Drain pump:
This field displays status of drain pump, on or off.
Drain cool:
This field displays the user (or factory default) setting.
OFF: fill will not activate when drain is activated.
ON: fill will activate whenever the drain activates.
hot.
SMART: fill will activate only when drain water is
DESGN PRSS.
VALVE OUTPUT
15.0 PSI
XXXLB
This field displays the total system demand as a percentage.
Valve output:
This field will display how much open the valve is in %.
- 43 -
SCREEN 4:
Service interval:
SERVICE INTERVAL
XXX HOURS
REMAINING XXX HOURS
START DATE: MM:DD:YY
This field displays the user (or factory default) setting for the humidifiers service reminder in steam hours.
Remaining:
This field displays the amount of time (steam hours) remaining before the next service is to be performed.
Start Date:
This field displays the date this service interval began.
SCREEN 5:
Security loop:
SECURITY LOOP [0/1]
TANK SENSORS [0/1]
This field displays the status of the security loop
(terminals 1 and 2 on LV terminal strip). If it is open the display will indicate “O”, if it is closed the display will indicate “I”.
Tank sensor
This field displays the status of the tank sensor input. If it is open the display will indicate “0”, if it is closed the display will indicate “1”. Closed indicates that the tank temperature is above 160ºF (70ºC).
This input is used for the “keep warm” feature and for activating the fill valve during blowdown cycles.
SCREEN 6:
3 day drain
3 DAY DRAIN
KEEP WARM
1
0
BLOWDOWN RATE XX%
FT BLOWDOWN 1
This field indicates if the feature has been selected
(0 = no, 1 = yes).
Keep warm
This field indicates if the feature has been selected
(0 = no, 1 = yes).
Blowdown rate:
This field displays the selected blowdown rate.
Full tank blowdown
This field indicates if the feature has been selected
(0 = no, 1 = yes).
- 44 -
SERVICE LEVEL
SERVICE INTERVAL
SERVICE HISTORY
FAULT HISTORY
TANK DRAIN
TANK PRE-CLEAN
BURNERS
SHORT CYCLE DELAY
The service level area is where service related tasks are performed. Below is a description of each field and what can be performed in them. When a parameter requires a change, press the two arrow key and enter the password
(0335). As long as you remain in this section, you will not need to enter the password more than once.
Service interval
SERVICE INTERVAL
SERVICE HISTORY
FAULT HISTORY
TANK DRAIN
TANK PRE-CLEAN
MAINTENANCE TIME
XXX HOURS
MAINTENANCE DUE
XXX HOURS
SERVICE INTERVAL
XXX HOURS
CLEAR REMINDER?
In this area the customer can set a service interval for humidifier MAINTENANCE.
MAINTENANCE TIME
XXX HOURS
This field displays the user selected MAINTENANCE time. To change the time selected enter the user code and adjust the time in SET MAINT. TIME (0-3000 hours, 0 = disabled).
MAINTENANCE DUE
XXX HOURS
This field displays the time remaining until the next service interval. To reset the MAINTENANCE due time, enter the user code and select CLEAR REMINDER?
Service history
SERVICE INTERVAL
SERVICE HISTORY
FAULT HISTORY
TANK DRAIN
TANK PRE-CLEAN
SERVICE HISTORY X/Y
STEAM HOURS XXXX
(DATE/TIME)
In this area the customer can view the history of service maintenance performed on the humidifier.
SERVICE HISTORY X/Y
The service history stores the last 10 service periods.
X = service occurrence, where 1 is the most recent.
Y = total number of recorded services (up to 10 maximum).
- 45 -
STEAM HOURS XXX
(DATE/TIME)
This field displays the steam hours and the date and time when the specific service (X) was performed.
Fault history
SERVICE INTERVAL
SERVICE HISTORY
FAULT HISTORY
TANK DRAIN
TANK PRE-CLEAN
FAULT HISTORY X/Y
(TYPE OF FAULT)
(DATE/TIME)
In this area the customer can view the history of recorded faults for the humidifier.
FAULT HISTORY X/Y
The fault history stores the last 54 system faults.
X = fault occurrence, where 1 is the most recent.
Y = total number of recorded faults (up to 54 maximum).
(type of fault) and (date/time)
A description of the fault type is displayed along with a date and time stamp when the fault occurred.
Tank Drain
SERVICE INTERVAL
SERVICE HISTORY
FAULT HISTORY
TANK DRAIN
TANK PRE-CLEAN
THIS WILL DRAIN
CONTENTS OF TANK
THIS WILL DRAIN
CONTENTS OF TANK
CONTINUE?
The tank drain feature, when activated, will activate the drain valve for a fixed period of time (depending on unit size).
To drain the tank press enter when CONTINUE is selected. During the tank drain cycle the display will indicate the tank is draining and the amount of time remaining on the cycle. To interrupt the cycle the unit must be switched off then on. Must enter service password to activate this function.
- 46 -
Tank Pre-Clean
The tank pre-clean feature when activated will activate the drain valve for a fixed period of time (depending on unit size). The fill valve will then activate, filling the tank partially with cold water. At the completion of the fill cycle the tank will once again drain.
This will help to flush out any accumulated minerals as well as cool the tank for the service personnel.
To pre-clean the tank press enter when CONTINUE is selected. During the tank pre-clean cycle the display will indicate the tank is draining and the amount of time remaining on the cycle. To interrupt the cycle the unit must be switched off then on. Must enter service password to activate this function.
User Settings
When a parameter requires a change, press the two arrow key and enter the password (0335). As long as you remain in this section, you will not need to enter the password more than once.
Date / Time Units
This field is used for modifying the Date, time and the units of measurement. The date and time are important parameters when features such as full tank blowdown are enabled.
DATE/TIME
WATER MANAGEMENT
CONTROL TYPE
CAPACITY LIMIT
- 47 -
Time (of day)
To set the time of day, highlight the selection then enter the user code (0335). Press enter. Use the UP/DOWN arrows to adjust the hours (24 hour format). Pressing enter saves the setting and indexes the display to minutes. Use the UP/DOWN arrows to adjust the minutes. Pressing enter saves the setting and returns the user to the previous menu.
Date
0335
CHANGE VALUE
XX:XX
DATE/TIME
LANGUAGE CONTROLS
WATER MANAGEMENT
CONTROL TYPE
CAPACITY LIMIT
1
TIME
DATE
HH:MM
MM.DD.YY
0335
CHANGE VALUE
MM.DD.YY
To set the date, highlight the selection then enter the user code (0335). Press enter. Use the UP/DOWN arrows to select the month. Pressing enter saves the setting and indexes the display to number of the month. Use the
UP/DOWN arrows to adjust the number. Pressing enter saves the setting and indexes the display to year. Use the
UP/DOWN arrows to adjust the year. Pressing enter saves the setting and returns the user to the previous menu.
Water Management
This section allows the user to set time based parameters and adjust water control parameters.
FTBD Hours
This section allows the user to set the frequency of full tank blowdowns (FTBD). FTBD’s drains and re-fills the entire contents of the humidifier after a preset accumulated operating time. Run time is measured in steam hours
(weighted run time hours), and can be adjusted from 0 hours (feature off) to 400 hours in 25 hour increments.
Once the FTBD time has expired, the controller will wait until the FTBD hour to initiate the cycle. This prevents random drains at times when they would be inconvenient.
- 48 -
FTBD Hour
DATE/TIME
WATER MANAGEMENT
CONTROL TYPE
CAPACITY LIMIT
C
FTBD HOURS
FTBD HOUR
XXX
XX
BLOWDOWN RATE XX%
FLOAT CHECK HH:MM
FILL CORRCTN XX%
DRAIN CORRCTN XX%
DRAIN COOL: ON
0335
FTBD HOUR
CHANGE VALVE XXX
Works in conjunction with FTBD hours.
Here the user sets the time of day (24 hour format) when they want the FTBD to execute. The time can be set to trigger the cycle during off hours, when the humidity requirements are minimal.
The time is adjusted in one-hour increments.
Blowdown Rate
DATE/TIME
WATER MANAGEMENT
CONTROL TYPE
CAPACITY LIMIT
FTBD HOURS
FTBD HOUR
XXX
XX
BLOWDOWN RATE XX%
FLOAT CHECK HH:MM
FILL CORRCTN XX%
DRAIN CORRCTN XX%
DRAIN COOL: ON
0335
BLOWDOWN RATE
CHANGE VALUE XX%
STEAM OUTPUT
This parameter adjusts the frequency of blowdown cycles.
Depending on water quality, the blowdown rate can be adjusted from 5% to 50%. The percentage is based on the steam production rate i.e. a 10% BD rate will drain 10 kg. of water for every 100 kg. of steam produced.
The higher the mineral content of the water the higher the BD rate should be set.
Float Check
DATE/TIME
WATER MANAGEMENT
CONTROL TYPE
CAPACITY LIMIT
FTBD HOURS
FTBD HOUR
XXX
XX
BLOWDOWN RATE XX%
FLOAT CHECK HH:MM
FILL CORRCTN XX%
DRAIN CORRCTN XX%
DRAIN COOL: ON
0335
FLOAT CHECK
CHANGE VALUE HH:MM
This parameter sets the time of day the controller will force a float check.
Float checks are important to ensure the water level detection system is operating correctly. The float check also tests the fill and drain system and will report any problems detected.
To set the time of day, highlight the selection then enter the user code (0335). Press enter. Use the UP/DOWN arrows to adjust the hours (24 hour format). Pressing enter saves the setting and indexes the display to minutes. Use the UP/DOWN arrows to adjust the minutes. Pressing enter saves the setting and returns the user to the previous menu.
- 49 -
Fill CORRCTN (correction)
Used for adjusting the fill rate. Adjustments to be made under factory direction only.
Drain CORRCTN (correction)
Used for adjusting the drain rate. Adjustments to be made under factory direction only.
Drain Cool
DATE/TIME
WATER MANAGEMENT
CONTROL TYPE
CAPACITY LIMIT
FTBD HOURS
FTBD HOUR
XXX
XX
BLOWDOWN RATE XX%
FLOAT CHECK HH:MM
FILL CORRCTN XX%
DRAIN CORRCTN XX%
DRAIN COOL: ON
0335
DRAIN COOL:
ON
OFF
SMART
The customer can select the type of drain water tempering they require (depending on local plumbing codes)
The customer can select ON, OFF, or SMART.
ON – whenever the drain valve is activated through software, the fill valve will automatically activate. This is the factory default setting, but is the most wasteful of water since it will activate even if the drain water is cool.
OFF – The drain water is never tempered. This can be used where plumbing codes permit. Some process waters are very expensive, so the customer may choose to temper the drain water through other means.
SMART – The humidifier has a tank sensor that communicates the water temperature to the controller. If the water is hot during drain cycles the fill valve will be activated. This is the most “water smart” of the settings.
Control Input
DATE/TIME
WATER MANAGEMENT
CONTROL TYPE
CAPACITY LIMIT
CONTROL TYPE
CONTROL INPUT
TRANSDUCER INPUT
0335
CONTROL TYPE
CONTROL INPUT
TRANSDUCER INPUT
This section is used for configuring the controller for a controller input or a transducer input.
To select control input, highlight the selection then enter the user code (0335). Press enter. Use the UP/DOWN arrows to select control input.
The controllers dip switches then determine the type (0-10 Vdc, 0-20 mA, etc.) of control signal to process.
- 50 -
Transducer Input
This section is used to configure the controller for transducer signals
In this section you can adjust the proportional, integral and derivative constants. There is also a PID learn algorithm which will tune the various PID constants for optimal performance.
Capacity Limit
In this section the customer can adjust the maximum output of the humidifier between 25-100%.
To adjust the maximum capacity, highlight the selection then enter the user code (0335). Press enter. Use the
UP/DOWN arrows to adjust the output between 25 and 100%.
- 51 -
FAULT AND WARNING LIST
SETC Fault (Warning)
Displayed
Description of Fault Troubleshooting
FAULT
DRAIN NOT
WORKING
DRAIN IS BLOCKED
There are many time windows in the GS software. If, during a drain cycle, the time window for the water level to drop is exceeded, this fault is generated
-Ensure that pump is being energized
-Check for blockage in all aspects of the drain system
-Float board defective
-Consult factory
FAULT
FLOAT CHECK
FAULT
ILLEGAL FLOAT
COMBINATION
FAULT
FILL VALVE ON
DETECTION
INCONSISTENT
FAULT
KEEP WARM TIME
OUT
TOO LONG TO
HEAT
FAULT (WARNING)
MAINTENANCE
TIME
HAS ELAPSED
Once every 24 hours (provided the unit is powered and in an operating or standby condition) the controller will test the water level detection circuit. If the test fails this fault is displayed
If the controller detects two or more float level readings, which are not expected (ex. Switch 1 and 3 ON or switch 1, 2, and 3 ON) this fault will be recorded.
The controller monitors the water level as it fills and drains. It expects to see the levels increase logically (1-2-3-4-5). If the water level increases and jumps a step (1-2-4-5) this fault will be generated. The same holds for water level decreasing.
During a keep warn cycle, if the tank temperature sensor does not open within a certain time window, this fault is generated.
-Ensure the proper operation of the fill valve and drain valve via the diagnostics screen
-Float board is defective
-Consult factory
-Miswired float board
-Defective float board
-Consult factory
-Float board defective
-Contact agent for replacement float board
-Ensure that the thank temperature sensor is connected
-Defective tank temperature switch
-Contact agent for replacement switch.
In the user menu the user sets the maintenance time. Once this time expires a warning is displayed. 72 hours later the warning changes to this fault. The maintenance time is measured in weighted operational hours.
With switch 5, #4 deactivated, this fault is enabled
-Perform tank cleaning and all other maintenance requirements outlined in the manual.
- 52 -
PARTS
Drain Lines
Tank
Float Chamber
Fill Lines
Drain Lines
Steam Traps
Wye Strainer
Condensate
Steam Valve’s
Boiler
30 DAYS after initial start-up
X
MANDATORY MAINTENANCE SCHEDULE
MID
X
End of
Season
X
X
WHAT NEEDS TO BE DONE?
REGULAR MAINTENANCE PREVENTATIVE MAINTENANCE
- Switch to drain and make sure water flows freely. Unit should be completely drained afer a maximum of 20 min.
- Adjust blow down times when required. Check that scale has not accumulated above 2”.
- Clean tank when required.
- Drill out tank nipples when required to ensure nipples are not blocked with scale.
- Clean tank.
X X
X
X
X
X
X
X
X
X
X
X
X
X
X
- Ensure floats move freely - Clean scale from float chamber and hose connecting to it.
- Inspect for leaks.
- Inspect for leaks at the drain pump, fill cup and float chamber.
-Clean to remove all deposits.
- If damaged replace trap seat if required
-Inspect for corrosion
-Check floats move freely
- Inspect for corrosion
- Clean strainer
- Check for leaks
- Clean
- Install new thermal disc if
-Check if orifices are not plugged
- Clean
- Replace any parts showing signs of wear
- Replace worn seals.
- Follow maintenance recommendations.
- Check valve seat
- Clean to remove all deposits.
- If damaged replace steam valve if required
- Putting out correct steam pressure
- Water test
- Follow manufacturer’s recommendations
- 53 -
- 54 -
- 55 -
- 56 -
Item #
SE Series Spare Parts List - Internals
Description Part #
101 Cover Plate, Clean-Out Port
102 Gasket, Tank Cover Plate
103 Fill Box
104 Vacuum Break Valve 1/2"npt
105 P-Trap
2523457
2524361
2526152
1505959
2526521
106 Heat Exchanger Gasket
Single 2524405
Dual 2524403
107 Dual Fill Valve 10.0 l/min & 0.35 l/min 1505759
108 Auxilliary Drain Termination
109 Steam Trap, 15psi
110 Heat Exchanger Replacement Kit
111
112
Drain Pump 24v 60 hz
Lower Mixing Box
1506925
1508849
Mini 2530901
Single 2530902
1502644
1506749
113 Tank Thermal sensor
114 Float Chamber
115 Float Chamber Mounting Bracket
116 Float Board
1506026
1115933
1113777
2511137
1
1
1
1
1
1
Quantity per unit
SE100 SE175 SE 250 SE 375 SE 475 SE 675 SE 950 SE1050
1 1 2 2 3 3
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
2
1
1
1
2
1
1
1
3
1
1
1
3
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
2
1
1
1
2
2
1
1
1
1
1
2
1
1
1
2
2
1
1
1
1
1
3
1
1
1
3
3
1
1
3
3
1
1
1
1
1
3
1
1
- 57 -
- 58 -
SE Series Spare Parts List - Cabinetry
SE100 SE175 SE 250 SE 375 SE 475 SE 675 SE 950 SE1050 Item # Description Part #
201 Service Door Assembly
Mini 2524439
Single 2524440
Double 2524441
Triple 2524458
202 Front Door Assembly 2528421
203 Recessed Handle 2523444
204 Transformer 24/16V 15VA 50/60 hz 1505760
205 Control Board
206 I/O Board (SETC units)
LED Board (SEP units)
207
SETC units 1508357
SEP units 1508577
1504760
Transformer, 120/24V, 150VA
Fuse for Transformer, 6.25 Amp
1508619
1504859
1505020
208a LCD Display Assembly b LCD Mounting Bracket c On-Off-Drain Switch
Slotted Wire Duct (not shown)
1507741
1506951
1453001
1506041
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1 order by length required
1
1
1
1
1
1
1
1
1
1
2
1
1
1
1
1
1
1
1
1
1
1
1
2
1
1
1
1
1
1
1
1
1
1
1
1
2
1
1
1
1
1
1
1
1
1
1
1
1
2
1
- 59 -
- 60 -
SE Spare Parts List - Internals
Item Description
1 Tank Replacement Kit, SE50
8
9
6
7
4
5
2
3
10
11
12
13
14
15
16
Gasket, Tank/H.E. Assembly, SE50
Heat Exchanger Replacement Kits, SE50
Gasket, Clean Out Port, SE50
Cover Plate Kit, Clean Out Port, SE50
Rail, Float Chamber Support, SE50
Bracket, Float Chamber Mount, SE50
F&T Trap Assembly, with Plumbing, SE50
Fill Box Assembly with Connections, SE50
Pump Drain, 24VDC, 60HZ (DPS 25-119)
P Trap Mount Assembly, SE50
P Trap Assembly, Complete, SE50
Termination Assembly with Connections, SE50
Auxiliary Drain Termination
Dual Fill Valve, 5.5L -.35 L/Min
Float Chamber Assembly, with Board and Connections, SE50
NOTE: Kits include fastening hardware such as nuts and washer assemblies will include hoses and clmaps for item 16, float board may be ordered seperatly p/n: 1114913
Part No.
2520458
1510179
2520460
1510180
2520461
2520241
2520240
1500181
2520235
1502644
2520137
1510187
2520236
1506925
1704234
2520239
SE 50
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
- 61 -
- 62 -
SE Spare Parts List - Cabinetry
4
5
2
3
SETC Electrical Components
Item
1
Description
Panel Assembly, Electrical Front, Cabinet SE50
6
Not Shown
I/O Board, GS-SE Series
SETC Logic Board Assembly
Transforner 24/16V, 15VA
SETC, Display-Keypad Assembly, SE50
Bracket, Assembly, Key Pad Mount, Cabinet, SE50
Wire Harness SETC
Part No.
2520268
1504760
1508357
1505760
2520274
2520272
2520808
1
1
1
1
1
1
SE 50
1
SEP Electrical Components
Item
1
Description
Panel Assembly, Electrical Front, Cabinet SE50
4
5
2
3
Not Shown
SEP Display / Keypad Assembly, SE50
Bracket, Assembly, Key Pad Mount, Cabinet, SE50
SEP Control Board
SEP, Led Board Assembly
Wire Harness SEP
5
6
3
4
1
2
SE50 Spare Parts List - Cabinetry
Item Description
Panel Assembly, Electrical Front, Cabinet SE50
I/O Board, GS-SE Series
7
Not Shown
SETC Logic Board Assembly
Transforner 24/16V, 15VA
SETC, Display-Keypad Assembly, SE50
Bracket, Assembly, Key Pad Mount, Cabinet, SE50
Pipe Plug, 1/2 NPT
Fuse For Transformer
Part No.
2520268
2520279
2520272
1508577
1508619
1508352
Part No.
2520267
2520267
2520270
2520313
2520271
2520281
1507043
1505020
1
1
1
1
1
SE 50
1
1
1
1
1
1
1
SE 50
1
1
- 63 -
THIS PAGE INTENTIONALLY LEFT BLANK
THIS PAGE INTENTIONALLY LEFT BLANK
THIS PAGE INTENTIONALLY LEFT BLANK
LIMITED WARRANTY
Walter Meier Inc. and/or Walter Meier Ltd. (hereinafter collectively referred to as THE COMPANY), warrant for a period of two years from date of shipment, that THE COMPANY's manufactured and assembled products, not otherwise expressly warranted, are free from defects in material and workmanship. No warranty is made against corrosion, deterioration, or suitability of substituted materials used as a result of compliance with government regulations.
THE COMPANY's obligations and liabilities under this warranty are limited to furnishing replacement parts to the customer, F.O.B. THE COMPANY's factory, providing the defective part(s) is returned freight prepaid by the customer. Parts used for repairs are warranted for the balance of the term of the warranty on the original humidifier or 90 days, whichever is longer.
The warranties set forth herein are in lieu of all other warranties expressed or implied by law. No liability whatsoever shall be attached to THE COMPANY until said products have been paid for in full and then said liability shall be limited to the original purchase price for the product. Any further warranty must be in writing, signed by an officer of THE COMPANY.
THE COMPANY's limited warranty on accessories, not of Walter Meier’s manufacture, such as controls, humidistats, pumps, etc. is limited to the warranty of the original equipment manufacturer from date of original shipment of humidifier.
THE COMPANY makes no warranty and assumes no liability unless the equipment is installed in strict accordance with a copy of the catalog and installation manual in effect at the date of purchase and by a contractor approved by THE COMPANY to install such equipment.
THE COMPANY makes no warranty and assumes no liability whatsoever for consequential damage or damage resulting directly from misapplication, incorrect sizing or lack of proper MAINTENANCE of the equipment.
THE COMPANY retains the right to change the design, specification and performance criteria of its products without notice or obligation.
E65185
Walter Meier (Climate USA) Inc.
826 Proctor Avenue, Ogdensburg, New York 13669
Walter Meier (Climate Canada) Ltd.
2740 Fenton Road, Ottawa, Ontario K1T3T7
Tel: 866 NORTEC 1 Fax: 613 822 7964 [email protected]
www.humidity.com
advertisement
Key Features
- Economical operation
- Clean atmospheric steam
- Easy installation
- Reliable operation
- Low maintenance