C3060
INSTALLATION INSTRUCTIONS
UNIVERSAL WELDED 4-LINK FRAME KIT
PARTS LIST
1) Welded Subframe 4) 4-Link Tubes
4) 4-Link Axle Brackets 1) Driveshaft Loop
1) Coil-Over Spring Kit 1) Bolt-On Diagonal Link Kit
1) Lower Shock Mount Kit* 4) 3/4"-16 Locknuts
8) 3/4"-16 Bolts 8) 3/4"-16 Locknuts
2) 5/16"-18 x 1-3/4" Bolts 2) 5/16"-18 Locknuts
Magnum Series Shocks or Coil Spring Mount Kit
* Magnum Series Shock equipped Frame Kits only.
Read all instructions completely before beginning the installation. The following suggestions will help to
ensure a quality installation.
- All welding should be done using either the MIG or TIG process. A welding machine rated at 130
amps or higher should be used to ensure adequate weld penetration. All of the supplied components
are made from mild steel unless otherwise noted.
- Select a clean, flat and level work area where the vehicle can remain undisturbed until final
completion. The car cannot be moved once the rear frame and floor pan has been taken out.
- Trial fit all of the components several times, checking and re-checking all dimensions.
- Tack weld everything and double-check all your measurements before final welding.
- These instructions are only a guide to a correct installation. Certain applications may differ (Full
Frame vs. Unibody, etc.) but the basic concepts used in chassis construction remain the same.
- Keep a fire extinguisher handy at all times during the construction process. Cutting torches, grinders
and welding sparks can spark fires at any time.
- Cover all windows and gauges with cardboard to protect them from grinder sparks.
- This kit requires the installation of at least an 8-Point Roll Bar. We highly recommend that a
10-Point Roll Cage be installed. Both 8-Point and 10-Point kits are available from Competition
Engineering.
For Technical Assistance, call Competition Engineering's Tech Line at
(203) 458-0542, 8:30am-5:00pm Eastern Time
COMPETITION ENGINEERING
80 Carter Drive • P.O. Box 1470 • Guilford, CT 06437
Phone: (203) 453-5200 • Fax: (203) 453-6906
Visit Us At www.competitionengineering.com
Visit Us At www.competitionengineering.com
Rev. D
C3060INST
032415 4-Link Frame Kit installation Instructions cont. Page 2 of 14
TABLE OF CONTENTS
I. Tool List
II. Disassembly and Set-up
III. Subframe Installation
IV. Axle Bracket Installation
V. Lower Shock Mount Installation
VI. Housing Installation and Set-up
VII. Diagonal Link Set-up
VIII. Final Welding
IX. Shock Assembly
X. Final Assembly
XI. Adjustments and Tuning Tips
XI. Build Sheet
XII. Diagrams
I. TOOL LIST
- Power Reciprocating Saw to remove floor pan and cut subframe to length.
- Body Grinder with coarse wheel to remove paint and rust.
- MIG or TIG welder with 130 amp minimum rating.
- Protective Face Shield for grinding and welding.
- Sheetmetal Shears to modify or remove interior panels.
- Tape Measure, Plumb Bob, Angle Finder, 3ft Level, Chalkline, Framing Square & Marking Pen.
- 4 Jack Stands and Floor Jack to support vehicle
- Cutting Torch to modify full framed chassis.
For a professional looking installation we highly recommend the following materials and tools:
- Thin cardboard to cover the windows. This protects the glass from welding and grinder sparks.
- Plasma Cutter for cleaner cuts when removing sheetmetal and frame components.
Installation Instructions 4-Link Frame Kit cont. Page 3 of 14
II. DISASSEMBLY AND SET-UP
1. Before beginning the installation, you must choose a place to work on the vehicle where it will not be
disturbed until it is completed. The chosen area should be level, clean and preferably a solid surface,
such as concrete.
2. At this time, remove all components that will be in the way of the removal and installation process.
Items such as seats, carpet, wiring, door panels, gas tank, rear bumper and the deck lid should be
taken off.
3. Take time now to cover all exposed glass with cardboard and tape. Also cover any gauges or radios
to prevent damage from sparks.
4. Measure the wheelbase of the vehicle from the front spindle centerline to the rear axle centerline.
Make sure that the front wheels are pointing straightforward. Mark this information down on the
supplied build sheet at the back of this booklet.
5. Determine the desired ride height of the rear of the car. Measure from the floor to the bottom of the
rearmost portion of the rocker box. Mark this dimension on the build sheet.
NOTE: Check your sanctioning body's guidelines concerning minimum ride heights.
6. Jack up the front and rear of the vehicle to a comfortable working height (approximately 24").
Support the vehicle under the front frame and the body in the rear using, as many jack stands as
necessary to prevent the body from drooping when the rear frame is removed. A good location for
the rear jack stands is under the rocker boxes, near the wheel opening.
7. Level the car using a 3-ft carpenter's level front to back and side to side. Take your time doing this,
as this will determine how the subframe is finally located within the body shell. Use metal shims
between the jack stands and the body/chassis to obtain proper level. It is recommended that braces
be fabricated to support the rear tail panel of the vehicle. These can be made from 2"x4" lumber and
mounted through the rear bumper bolt holes.
8. Remove the rear tires from the car.
9. Using the plumb bob, drop a point onto the floor from the front spindle center on each side of the car.
Mark this point on the floor with the marking pen. Repeat this process to locate the front of the axle
tube, marking the point on the floor.
10. Snap a chalkline between the two front spindle marks and the two rear axle marks. Using a straight
edge and the marking pen, trace over the chalkline onto the shop floor, making the lines permanent.
11. Measure the diameter of the axle housing tube and divide it by 2. Write this dimension on the build
sheet. Make a line; using this dimension, behind the line made for the axle housing. This is your rear
axle centerline.
12. Measure from the front spindle line to the rear axle centerline and compare this dimension to the one
on the build sheet. Note any differences.
4-Link Frame Kit installation Instructions cont. Page 4 of 14
13. Using the plumb bob, locate and mark the axle centerline onto the body with the marking pen. This
will provide you with a quick reference when checking if the car has moved during construction. We
highly recommend that you drop points onto the floor from fixed positions on the body to reference
its position relative to the new chassis. Door to rocker pinch welds and front suspension brackets
are the best places to use for reference points. Make sure you mark and circle the points so you
can find them easily.
14. With all the critical dimensions taken, you may now remove the axle housing and any other
unnecessary suspension components.
15. Determine the centerline of the vehicle and mark its location on the shop floor. This can be done as
follows:
a. Measure the distance from one front spindle centerline to the other. Divide by 2. Write this
dimension on the build sheet. Also mark this point on the line marked between the front spindle
centerlines.
b. Drop a point from the inside of each rear frame rail onto the axle centerline. Measure between
these points and divide by 2. Mark this point on the axle centerline and on the build sheet.
c. Stretch a chalkline between the two marks made in steps a & b. Snapping a line between these
points gives you the chassis centerline.
d. Using a straightedge, make this line permanent by tracing over it with the marking pen.
16. Next we will determine the offset of the drivetrain. Most cars, but not all, have on-center drivetrains.
You can figure this out as follows:
a. Measure from the center of the transmission tailshaft to the inside of the front frame rails on both
sides.
b. Subtract one side's dimension from the other. The result will be the drivetrain offset.
c. Mark this point on the proper side of the chassis centerline in two places. Snap a chalkline
between the two points and trace it with the straightedge and the marking pen. This line will be
the centerline for the pinion. Write this dimension on the build sheet.
17. With the rear of the car down to the bare frame, determine where you want to cut the floor.
a. Measure forward from the rear axle centerline, along the chassis centerline, a distance of
26-7/8". Mark this location on the floor. Using the framing square, extend a line 90 from the
chassis centerline at this point. Do this on both sides of the line extending it to approximately 30"
per side.
b. Hold the string of the plumb bob against the floor pan over the line you just made on the floor.
Center the point of the plumb bob over the line. Mark the location of the string on the floor pan.
Do this in several locations across the floor pan, following the line on the floor.
c. Using a sharp punch or chisel, punch up through the floor pan on the marks you made from under
the car.
d. Working from inside the car, connect the punch marks made through the floor pan with a marking
pen and the straight edge. This will make the cut line for the front of the subframe crossmember.
Extend this line so that it ends at the weld seam of the floor pan and the rocker box.
e. Cut out the floor pan using this line as a guide.
f. Remove all floor pan and trunk sheetmetal from this cut line back leaving the rear tail panel and
package tray intact. Also remove the wheelwells being careful not to damage the quarter panel
sheetmetal in the process.
4-Link Frame Kit installation Instructions cont. Page 5 of 14
18. With the floor pan removed, you can now cut off the unwanted section of the frame. Only cut what is
necessary to clear the new subframe installation and your wheel/tire combination. Leave enough of
the frame on full framed cars to allow for additional bracing between the old and new frames. Unibody cars will have to connect the existing front subframe to the new rear subframe by way of a
weld-in subframe connector. These are available from Competition Engineering.
19. With all the sheetmetal and frame removed, check that you have selected the proper width
subframe by doing the following:
a. Position the wheels and tires that you intend to use under the body of the car. Use concrete
blocks or milk crates to position them at the desired ride height.
b. The sidewall of the tire should be a minimum of 1" from the wheelwell lip. The tire should be
centered on the axle centerline.
c. Measure from the inside tire bulge of one wheel to the inside tire bulge of the other wheel.
Subtract two inches to this dimension. This is your frame rail width. Write this dimension on the
build sheet.
Note: The wider you can make your frame rails, the better. Wider frame rails provide better top end
stability and make it easier to mount your shocks and other brackets.
III. SUBFRAME INSTALLATION
1. Trimming the crossmember:
a. Measure the distance between rocker boxes right behind the cut line made earlier. Divide this
dimension by 2 and mark it on the build sheet.
b. Locate the center of the crossmember that is welded to the new subframe. Mark it with the
pen. This is the line that will correspond with the chassis centerline. If you have an offset
drivetrain, the line will match up with the drivetrain offset line.
c. Make a template to match the contour of the rocker panel where the 2"x3" crossmember will
mount.
d. If you have no drivetrain offset, measure the distance determined in step a. on each side of
the crossmember. If you do have drivetrain offset, make sure to subtract the offset from one
side and add it to the other. Example: Rocker-to-rocker dimension = 50", Drivetrain offset = 1"
to the passenger side, 50"2=25" per side, 25"-1"=24" passenger side crossmember length,
25"+1"= 26" driver side length. The centerline of the crossmember should remain inline with
the drivetrain centerline.
e. Using the template, trim the ends of the crossmember to the desired length.
2. Determining frame rail length:
a. With the location and ride height of the front crossmember determined, measure from the face
of the crossmember to the intended mounting location of the rear of the subframe. This
location will be located somewhere on the rear body panel. Write this dimension on the build
sheet. As shipped, the length of the subframe from the face of the crossmember to the end of
the top rail is 69".
b. Determine the desired height location of the rail ends on the body panel. As shipped, the top
of the frame rail ends are 14-3/4" above the top of the front crossmember. Measure from the
floor to the desired mounting point on the rear body panel. Write this dimension on the build
sheet.
Note: With the crossmember at the recommended 8" ride height, the bottom of the frame rail is
26" above the floor.
4-Link Frame Kit installation Instructions cont. Page 6 of 14
c. To determine the proper length of the frame rails, subtract the as-shipped length (69") from
the dimension determined in step a. Write this dimension on the build sheet.
d. Cut the frame rails to the proper length at this time.
3. With the help of a friend, position the new subframe under the body. Align the centerline mark on the
crossmember with the chassis centerline on the floor. Support the subframe in place with jack stands
and wood bracing. Trim the rails as necessary to ensure a snug fit.
4. Level the subframe side-to-side and front-to-back using the 3ft level. Draw a line 2" behind the
previously-made front crossmember line. Using the carpenter's square, check to see if the
crossmember line is perpendicular to the chassis centerline.
5. Drop plumb bob points off the back of the crossmember down to the line on the floor. Adjust the
position of the subframe until it aligns perfectly with the new line on the floor.
6. When the crossmember and the chassis centerline are aligned, tack the ends of the crossmember to
the rocker boxes.
7. It may be necessary to fabricate reinforcing brackets from the rear body panel to the subframe for
strength. Do not weld in one continuous bead when attaching the rear of the subframe to the body
panel. Severe warpage and burn through will result. Instead weld in 1/2" long beads, alternating from
rail to rail, giving time for the metal to cool sufficiently. Remember to tack weld the subframe in place
first. Final welding will be done at the completion of the project.
8. You may now install your subframe connectors, tying them into the front of the new crossmember.
For full frame cars we recommend adding diagonal bracing from the stock frame to the front of the
new crossmember.
With the subframe tacked in place, we will now move on to modifying the axle housing.
IV. AXLE BRACKET INSTALLATION
1. Using the plasma cutter or cutting torch, remove all existing factory brackets from the axle
housing you intend to use. Be careful not to add too much heat to the housing, as it will warp the
tubes, causing problems later.
2. Remove the housing ends as close to the welds as possible using a bandsaw or abrasive chop
saw.
3. Measure the distance between the front chassis brackets and write this dimension on the build
sheet.
4. Assemble the 4-link axle brackets using your rod ends as spacers.
5. Slide the axle housing brackets onto the axle tubes so that the flat edge of the brackets face
forward and the link mounting holes closest to the axle-mounting hole are on top.
6. Align the brackets so that they are equally spaced from the pinion centerline for centered
drivelines. For offset drivelines, make sure you offset the pinion the same amount as the
driveline.
7. Tack weld the brackets so that they are 90 to the pinion. Place tacks in three places around
each bracket to ensure that the do not move.
V. LOWER SHOCK MOUNT INSTALLATION
Subframe kits that have the Magnum Series coil-over shocks also include a separate lower shock mount
kit. Coil spring mount equipped kits have the lower shock mount packaged with the coil spring mount kit.
The installation procedure is the same for both.
1. Assemble the lower mounting brackets to the axle brackets using one right hand bracket and one left
hand bracket per side. (See Diagram) Use the provided 3/8"-16 bolts and locknuts to attach them.
Do not tighten completely at this time. Mount these brackets in the middle of the axle brackets to
allow for up or down ride height adjustment.
4-Link Frame Kit installation Instructions cont. Page 7 of 14
2. Measure the center-to-center distance between the upper shock mount brackets located on the
subframe. Write this dimension on the build sheet.
3. The lower axle brackets should be mounted equally distant and perpendicular to the pinion centerline
at the dimension determined in the previous step. Make sure that they are parallel to each other.
4. With everything in place, tack weld the brackets to the axle tubes. Re-check the mounting dimension
and that the brackets are square to the pinion.
VI. HOUSING INSTALLATION
1. Assemble the 4-link tubes with the rod ends of your choice. Thread the jam nuts onto the rod ends
so that approximately 1" of thread is showing. Thread the rod ends into the link tubes and adjust
them equally to achieve a distance of 21" center to center.
2. Using a floor jack, slide the housing under the newly installed subframe.
3. Install the link tube assemblies into the chassis and axle brackets using the supplied 3/4" hardware.
DO NOT INSTALL THE PASSENGER SIDE UPPER BAR AT THIS TIME.
4. Swing the housing upward so that the distance between the upper and lower shock mounting holes
is 13-3/4". Support the housing with the floor jack.
5. Check your wheelbase on each side using the dimension from the build sheet for reference. If the
wheelbase needs to be adjusted, rotate the lower 4-link bars to achieve the correct dimension. Once
the correct measurement has been reached, tighten the jam nuts.
6. Using an angle finder, check the pinion angle by placing it against the mounting surface of the center
section (Mopar 8-3/4" and 9" Ford) or the rear cover surface (10&12 Bolt GM, Dana, Ford 8.8 etc.).
7. Rotate the driver's side upper 4-link bar to achieve 1-2 downward pinion angle. Lock the jam nuts
in place.
8. Install the passenger side upper bar at this time. This bar should be installed so that the bolts slide in
without resistance. Do not force the bolts or move the housing to get them to fit. Instead, rotate the
link to achieve the proper length.
NOTE: Forcing the bolts into place will cause the chassis to be pre-loaded. This will cause problems
later down the road when it comes time to tune the chassis.
9. Re-check the wheelbase on each side, adjust as necessary. If you make changes to the wheelbase,
be sure to check the pinion angle and the pre-load bar.
10. Label the mounting locations of the link tubes using masking tape and a marking pen. This will
ensure that they go back in the right place.
VII. DIAGONAL LINK SET-UP
1. Remove the lower bolt located on the driver's side chassis bracket.
2. Slide the bolt through one of the supplied link brackets and replace it into its mounting hole. The ears
of the bracket should be facing the driveshaft and be parallel to the ground. Re-install the nut on to
the bolt, but do not tighten.
3. Repeat this process for the passenger side lower hole located on the axle bracket.
4. Thread the left-hand jam nut onto the left-hand rod end. Thread it approximately 3/4 of the way up
the rod end threads. Repeat this process for the right hand rod end.
5. Install the rod ends into the link brackets with the supplied 1/2"-20 bolts.
6. With the threaded portions of the rod ends facing each other, measure the distance from one jam nut
to the other. This will be the finished length of the tube. Write this dimension on the build sheet.
4-Link Frame Kit installation Instructions cont. Page 8 of 14
7. Cut the tube to match the dimension. Make sure that you cut off material from the right hand
threaded end of the tube. Re-tap the cut end of the tube with a 1/2"-20 right-hand thread tap. This
tap size can be purchased from any hardware store.
8. Remove the rod ends from the brackets and thread them into the end of the tubes. We highly
recommend using anti-seize compound on the threads to eliminate galling and thread damage.
9. Install the bar assembly into the mounting brackets.
10. Using the plumb bob, locate the pinion centerline directly over the chassis centerline. This can be
accomplished by rotating the diagonal link in either direction to shift the housing in the proper
direction. Tighten the jam nuts at this time.
11. Remove the 4-link tubes as well as the diagonal link at this time.
VIII. FINAL WELDING
Now that everything is fitted and in place you can begin the final welding process. We will begin with the
welding of the subframe, then the axle housing and ending with the roll bar. Remember to take your
time. If a tack weld breaks, re-tack it before proceeding. Alternate your welds from one end of the part to
the other. This will prevent twisting and excessive movement of the welded part. When welding on the
axle housing, the use of an alignment bar is highly recommended.
NOTE: WE HIGHLY RECOMMEND THAT YOU INSTALL YOUR ROLL BAR OR ROLL CAGE AT THIS
TIME TO ELIMINATE SHIFTING OF THE SUBFRAME.
1. With the rear housing moved out of the way, begin to add secondary tacks to all the areas that are to
be welded. Place the tacks in locations that will be the beginning and end of a weld bead. This will
ensure a cleaner looking weld.
2. With all the secondary tack welds in place, begin to weld the subframe to the car. Weld each end of
the crossmember first, then proceed to the rear of the frame rails. Next, weld the subframe
connectors to the face of the crossmember and then to the front subframe.
3. Weld the floor pan to the front of the crossmember using a stitch technique to eliminate burn through.
4. Prepare the rear axle housing for final welding.
5. Insert the alignment bar through the housing using bushings in the axle tubes and center section to
hold the bar centered within the housing.
6. Weld the brackets to the axle tubes using the same alternating weld technique to minimize warpage.
Allow the welds to cool periodically, this will also help to reduce warpage.
7. With the brackets welded completely, install your choice of housing ends at this time. Remember to
keep the alignment bar in the housing during the installation of the housing ends. The bar should be
left in until the housing is completely cool.
IX. SHOCK ASSEMBLY
The following instructions cover the assembly and installation of the Magnum Series Coil-Over Shocks
and the Coil Spring Mount Kit.
Magnum Series Coil-Over Shock Assembly:
1. Clamp the lower mounting loop in a large vise. (Use of soft vise jaws is recommended to protect the
aluminum housing from scratches etc.)
2. Screw the aluminum spring seat and jam nut down to the last thread, NO FURTHER. Now is a good
time to lubricate the threads of the shock body with an anti-seize lubricant.
3. Pull the piston rod all the way out and slide the bump stop down. Check the jam nut under the upper
bearing housing making sure it is secure.
4-Link Frame Kit installation Instructions cont. Page 9 of 14
4. Slide the spring over the shock body. Slip the spring cap in place, making sure that it is set in the
spring squarely. The spring rate selected for your application will determine how difficult they will be
to install.
5. Adjust the spring seat up until the spring is compressed 1 inch shorter than the free height of the
spring, i.e. 12-inch spring would be compressed to 11 inches. This preloads the springs prior to
mounting on the vehicle. (Make sure that the spring cap is aligned properly under the upper bearing
mount)
6. Bearing Installation:
a. Test fit the bearings in both ends of the shock. Bearings may start easier on one side than the
other.
b. Clean the outer bearing race with solvent and apply thread-locking compound to the outer
bearing race and the bore surface of the bearing mount.
c. Assemble by inserting the bearing in a twisting motion. Install the snap rings on both sides of the
bearing. (In some cases it may be necessary to press the bearings into the mount.)
Coil Spring Shock Mount Kit Assembly:
1. Place the rear housing in its proper position and at the correct ride height.
2. Mount the lower shock brackets to the weld-on axle brackets using the supplied 3/8"-16 hardware.
3. Install the spring and the spring perches on the top and bottom of the coil-over spring. Slide the
spring assembly over the shock absorber and over the upper and lower mounting tabs. Fasten in
place using the supplied 1/2" bolts. Tighten the 1/2" bolts to 65-ft/lbs and the 3/8" bolts to 40-ft/lbs.
X. FINAL ASSEMBLY
1. With the subframe securely welded to the car and the axle housing welded complete; begin to reassemble the rear suspension.
a. Slide the housing assembly under the chassis and locate it in place using your marks on the floor.
b. Install the assembled 4-link bars into the appropriate holes in the chassis and axle brackets.
Remember the lower links go in the bottom holes of the chassis and axle brackets and the top
links go in the top holes on the axle brackets and the middle holes on the top of the chassis
brackets. Do not put the passenger side upper bar in at this time. Make sure that you put the
labeled bars in their correct positions.
2. Install the diagonal link in position but do not tighten the jam nuts at this time. Make sure that the
mounting brackets are parallel to the shop floor.
3. Mount the assembled Magnum Series Shocks into the upper and lower shock mount brackets using
the supplied 1/2"-20 x 2-1/2" bolts and locknuts.
4. Slide the driveshaft hoop over the welded stubs on the crossmember. Drill through the center of each
hoop leg approximately 1" from the end using an 11/32" drill bit. Install the supplied 5/16"-18 x 1-3/4"
bolts and locknuts.
XI. ADJUSTMENTS AND TUNING TIPS
The following procedure should be done with the vehicle's weight resting on the housing. Support the
axle housing with jack stands.
1. Adjust the coil-over spring seat up or down to reach the desired shock ride height. Shock ride height
is the distance from the center of the top-mounting loop to the center of the bottom-mounting loop. If
you have selected the proper spring rate, you should be able to adjust the spring seat up or down
approximately 1/2" to get into the recommended ride height. If you cannot achieve the shock ride
height recommended, a softer or stiffer spring may be required.
4-Link Frame Kit installation Instructions cont. Page 10 of 14
2. Check the vehicle ride height using the calculation found on your build sheet. Vehicle ride height
should be changed if the car sits higher or lower than desired. With the chassis supported with jack
stands, unbolt the adjustable lower shock mount brackets and move the housing up or down to get
the vehicle ride height you are looking to achieve. When this is accomplished, place the vehicle's
weight back on the axle housing supporting it with jack stands.
3. Using the plumb bob check the alignment of the housing in relation to the centerlines on the floor.
Rotate the diagonal link in either direction to center the housing under the chassis. Lock the jam nuts
when you are finished.
4. Check the wheelbase on each side of the car using the dimensions on your build sheet. Adjust the
lower bars to achieve the correct dimension.
5. Adjust the pinion angle by turning the driver's side upper bar so that the angle finder reads 1-2
downward angle.
6. Install the passenger side upper bar so that the mounting bolts slide through the brackets without
resistance. Do not force the bolts. Lengthen or shorten the link bar to allow the bolts to go through.
7. Tighten all jam nuts and mounting bolts.
8. The installation of your 4-link Subframe Kit is now complete. At this time you can install your
fenderwells and tinwork as well as your axles, center section and wheels.
TUNING TIPS
Magnum Series Shock Adjustment:
1. Competition Engineering Magnum Series Coil-Over Shocks have 12 damping settings. There are 4
clicks per revolution of the knob. The knob will rotate 3 times. Do not adjust past the 12th click. Base
settings to start testing with are 3-5 clicks for bracket racing and 4-7 clicks for Pro Tree racing.
THESE ARE BASELINE SETTINGS. NOTE: DO NOT FORCE THE ADJUSTER KNOB. DO NOT
USE PLIERS OR ANY OTHER TOOLS ON THE ADJUSTER KNOB. DO NOT EXCEED 12 CLICKS
UNDER ANY CIRCUMSTANCES. THIS COULD DAMAGE THE IDLER PIN AND CAUSE THE
SHOCK NOT TO ADJUST. THIS WILL VOID ALL WARRANTIES.
2. The ride height can be adjusted by raising the chassis and supporting it with jack stands. With the
rear axle housing supported by a floor jack, raise or lower the axle mounting brackets the desired
amount.
CAUTION: NEVER ATTEMPT TO MAKE A SUSPENSION ADJUSTMENT WITHOUT FIRST
SUPPORTING THE CAR WITH JACK STANDS.
Coil Spring Mount Adjustment:
1. With the shock removed from the vehicle, compress it fully.
2. Rotate the top of the shock until you feel the internal adjuster engage.
3. Rotate the shock in a clockwise direction, listening for three distinct clicks. There will be one loud
click followed by two softer clicks. This will repeat three times around the shock. The loud click is the
"R" or regular setting, the first soft click is the "F" or firm setting and the second soft click is the "XF"
or extra firm setting.
4. Re-install the shock after the desired adjustment has been set.
- - If the car pulls to the right on launch, you can shorten the passenger side upper bar up to one
wrench flat at a time. If more than two wrench flats are added you should look for signs of
suspension binding or flex.
If you run into trouble while tuning always go back to your baseline set-up. Keep your build sheet in a
place where it won't get lost and refer to it when making changes.
4-Link Frame Kit installation Instructions cont. - - - - - Page 11 of 14
Change one thing at a time and try it before changing something else. Too often racers change
several things at once not knowing what thing made the car run better or worse. Keep a log of all
changes.
Lowering the instant center (the imaginary intersection point of the top and bottom bars) will reduce
weight transfer and soften the hit on the tires.
Raising the instant center will increase weight transfer and hit the tires harder.
Always check the pinion angle when relocating the links on the brackets. Strive to keep 1-2
downward pinion angle.
Check your mounting bolts before each race making sure they are tight. Keep your rod ends clean
and oiled. Take the suspension apart each year to clean and re-oil the rod ends. Look for mechanical
bind as well as bent or cracked brackets and welds.
4-Link Frame Kit installation Instructions cont. Page 12 of 14
BUILD SHEET
Driver's Side Wheelbase =______ Passenger Side Wheelbase =______
Desired Ride Height = _______ Axle Housing Diameter / 2 = _______
Front Spindle Center to Center / 2 =_____ Rear Framerail to Framerail / 2 = _____
Drivetrain Offset = ______ New Framerail Width = _______
Rocker Box to Rocker Box / 2 =______ New Framerail Length = ______
Floor to Rear Body Panel Mounting Point = _____
Amount to Cut Off Frame Rail = 69"- New Framerail Length = ______
Distance Between the Front Chassis Brackets (Inside to Inside) = ________
Center to Center Distance Upper Shock Mounts = _______
Diagonal Link Length = ______ Tire Size =_______________
Pinion Angle = _______ Rear Spring Installed Height =_______
Spring Rate, Rear = _______ Shock Valve Setting =______________
RIDE HEIGHT FORMULA
DR-(TD/2) =____ (HD height difference), AJ-RJ =____ (CH construction height)
CH-HD =____ AMOUNT TO RAISE OR LOWER SHOCK MOUNTS FOR CORRECT RIDE HEIGHT
VEHICLE WEIGHT SPECIFICATIONS
Total Weight =________
Front Weight =________
Rear Weight = ________
LF
RF
LR
RR
Left Front Weight =________
Right Front Weight =_________
Left Rear Weight =_________
Right Rear Weight =_________
% of Weight, Front (LF+RF/Total x 100)=__________
% of Weight, Rear (LR+RR/Total x 100)=__________
Floor Centerline Diagram