Installation and maintenance instructions
For the competent person
Installation and maintenance instructions
ecoTEC plus
VU
GB, IE
Publisher/manufacturer
Vaillant GmbH
Berghauser Str. 40 D-42859 Remscheid
Tel. +49 21 91 18‑0 Fax +49 21 91 18‑28 10
[email protected] www.vaillant.de
Contents
Contents
7.12
Checking the leak-tightness of the flue gas
system and for flue gas recirculation ................... 16
1
Safety .................................................................... 3
7.13
Checking function and leak-tightness.................. 16
1.1
Action-related warnings ......................................... 3
7.14
Checking the heating mode ................................. 16
1.2
Intended use ......................................................... 3
8
1.3
General safety information .................................... 3
Adapting the unit to the heating
installation.......................................................... 16
1.4
Regulations (directives, laws, standards) .............. 5
8.1
Burner anti-cycling time ....................................... 17
2
Notes on the documentation .............................. 6
9
Handing the product over to the operator ...... 17
2.1
Observing other applicable documents ................. 6
10
Inspection and maintenance ............................ 17
2.2
Storing documents................................................. 6
10.1
2.3
Applicability of the instructions .............................. 6
Observing inspection and maintenance
intervals ............................................................... 17
3
Product description............................................. 6
10.2
Procuring spare parts .......................................... 17
3.1
Serial number ........................................................ 6
10.3
Removing the gas-air mixture unit....................... 17
3.2
Information on the identification plate.................... 6
10.4
Cleaning the heat exchanger............................... 18
3.3
CE label ................................................................. 6
10.5
Checking the burner ............................................ 18
3.4
Functional elements............................................... 7
10.6
Checking the ignition electrode ........................... 18
4
Installation............................................................ 7
10.7
Cleaning the condensate siphon ......................... 19
4.1
Transporting the unit.............................................. 7
10.8
Installing the gas-air mixture unit ......................... 19
4.2
Unpacking the product........................................... 7
10.9
Draining the product ............................................ 19
4.3
Checking the scope of delivery.............................. 7
10.10
Completing inspection and maintenance work .... 19
4.4
Dimensions ............................................................ 8
11
Troubleshooting ................................................ 19
4.5
Minimum clearances.............................................. 8
11.1
Rectifying faults ................................................... 19
4.6
Clearance from combustible components ............. 8
11.2
Calling up the fault memory ................................. 19
4.7
Using the installation template............................... 8
11.3
Deleting the fault memory.................................... 19
4.8
Wall-mounting the product..................................... 8
11.4
Preparing the repair work .................................... 19
4.9
Removing/installing the front casing...................... 9
11.5
Replacing defective components......................... 19
4.10
Removing/installing the side section ..................... 9
5
Installation............................................................ 9
5.1
Preparing for installation ........................................ 9
5.2
Connecting the heating flow and heating
return ................................................................... 10
5.3
Gas connection.................................................... 10
5.4
Connecting the condensate drain pipework ........ 10
5.5
Installing the air/flue pipe ..................................... 11
5.6
Electrical installation ............................................ 11
6
Operation............................................................ 12
6.1
Operating concept ............................................... 12
6.2
Calling up the installer level ................................. 12
6.3
Live Monitor (status codes) ................................. 12
7
Start-up ............................................................... 13
7.1
Carrying out the initial start-up............................. 13
7.2
Running the installation assistants ...................... 13
7.3
Restarting the installation assistants ................... 14
7.4
Test programmes................................................. 14
7.5
11.6
Completing repair work........................................ 21
12
Decommissioning the product ......................... 21
13
Customer service............................................... 21
Appendix ............................................................................ 22
A
Inspection and maintenance work –
Overview............................................................. 22
B
Installer level – Overview .................................. 22
C
Overview of diagnostics codes ........................ 25
D
Status codes – Overview .................................. 28
E
Overview of fault codes .................................... 29
F
Connection diagram .......................................... 31
G
Connection diagram, 30 kW.............................. 32
H
Opening in the flue pipe.................................... 33
H.1
Positioning of the opening of a fan-supported
flue gas pipe ........................................................ 33
H.2
Text from BS 5440-1 on fan-supported flue
gas pipes ............................................................. 34
H.3
Opening of the flue pipe below eaves and
balconies.............................................................. 34
Checking the factory setting ................................ 14
I
Commissioning Checklist................................. 35
7.6
Checking and treating the heating water/filling
and supplementary water .................................... 14
J
Technical data.................................................... 39
Index ................................................................................... 43
7.7
Switching on the product ..................................... 15
7.8
Filling the condensate siphon .............................. 15
7.9
Checking the gas connection pressure (gas
flow pressure) ...................................................... 15
7.10
Checking the CO₂ content ................................... 16
7.11
Setting the CO₂ content ....................................... 16
2
Installation and maintenance instructions ecoTEC plus 0020200871_00
Safety 1
1
1.1
Safety
Action-related warnings
Classification of action-related warnings
The action-related warnings are classified in
accordance with the severity of the possible
danger using the following warning signs and
signal words:
Warning symbols and signal words
Danger!
Imminent danger to life or risk of
severe personal injury
Danger!
Risk of death from electric shock
Warning.
Risk of minor personal injury
Caution.
Risk of material or environmental
damage
1.2
Intended use
Any other use that is not specified in these
instructions, or use beyond that specified in
this document shall be considered improper
use. Any direct commercial or industrial use
is also deemed to be improper.
Caution.
Improper use of any kind is prohibited.
1.3
General safety information
1.3.1 Required personnel qualifications
Improper work carried out on the product
may cause material damage to the complete
installation and, as a consequence, may even
cause personal injury.
▶ You should therefore only work on the
product if you are an authorised competent
person.
▶ Carry out all work using the technology
currently available.
1.3.2 Risk of injury during transport due
to a high product weight.
There is a risk of injury or death to the user or
others, or of damage to the product and other
property in the event of improper use or use
for which it is not intended.
▶ Make sure that the product is transported
by at least two people.
The product is intended as a heat generator
for closed heating installations and for hot
water generation.
What to do if you smell gas in the building:
The products referred to in these instructions
must only be installed and operated in conjunction with the flue pipe accessories listed
in other applicable documents.
Exceptions: For C63 and B23P installation
types, follow the specifications in these instructions.
Intended use includes the following:
– observance of accompanying operating,
installation and servicing instructions for
the product and any other system components
– installing and fitting the product in accordance with the product and system approval
– compliance with all inspection and maintenance conditions listed in the instructions.
Intended use also covers installation in accordance with the IP class.
0020200871_00 ecoTEC plus Installation and maintenance instructions
1.3.3 Risk of death from escaping gas
▶ Avoid rooms that smell of gas.
▶ If possible, open doors and windows fully
and ensure adequate ventilation.
▶ Do not use naked flames (e.g. lighters,
matches).
▶ Do not smoke.
▶ Do not use any electrical switches, mains
plugs, doorbells, telephones or other communication systems in the building.
▶ If it is safe to do so, close the emergency
control valve or the main isolator.
▶ If possible, close the gas isolator cock on
the product.
▶ Warn other occupants in the building by
yelling or banging on doors or walls.
▶ Leave the building immediately and ensure
that others do not enter the building.
▶ Notify the gas supply company or National
Grid Transco +44 (0) 800 111999 by telephone from outside of the building.
3
1 Safety
1.3.4 Risk of death from escaping flue
gas
If you operate the product with an empty condensate siphon, flue gas may escape into the
room air.
▶ Wait for at least 3 minutes until the condensers have discharged.
▶ Check that there is no voltage.
1.3.9 Risk of death due to lack of safety
devices
▶ In order to operate the product, ensure that
The schematic drawings included in this docthe condensate siphon is always full.
ument do not show all safety devices required for correct installation.
1.3.5 Risk of death due to blocked or
leaking flue gas routes
▶ Install the necessary safety devices in the
system.
Installation errors, damage, tampering, unauthorised installation sites or similar can cause ▶ Observe the applicable national and international laws, standards and guidelines.
flue gas to escape and result in a risk of poisoning.
1.3.10 Risk of poisoning caused by
What to do if you smell flue gas in the propinsufficient supply of combustion
erty:
air
▶ Open all accessible doors and windows
Conditions: Open-flued operation
fully to provide ventilation.
▶ Switch off the product.
▶ Ensure that the air supply to the product's
▶ Check the flue gas routes in the product
installation room is permanently unobstrucand the flue gas diversions.
ted and sufficient in accordance with the
relevant ventilation requirements.
1.3.6 Risk of poisoning and burns caused
by escaping hot flue gases
1.3.11 Risk of death due to cabinet-type
casing
▶ Only operate the product if the air/flue pipe
has been completely installed.
▶ With the exception of short periods for
testing purposes, only operate the product
when the front casing is installed and
closed.
Cabinet-type casing can give rise to dangerous situations when used on a product which
is operated with an open flue.
1.3.7 Risk of death due to explosive and
flammable materials
1.3.12 Risk of corrosion damage due to
unsuitable combustion and room
air
▶ Do not use or store explosive or flammable
materials (e.g. petrol, paper, paint) in the
installation room of the product.
1.3.8 Risk of death from electric shock
There is a risk of death from electric shock if
you touch live components.
Before commencing work on the product:
▶ Disconnect the product from the power
supply by switching off all power supplies
(electrical partition with a contact opening
of at least 3 mm, e.g. fuse or line protection switch).
▶ Secure against being switched back on
again.
4
▶ Ensure that the product is supplied with
sufficient combustion air.
Sprays, solvents, chlorinated cleaning
agents, paint, adhesives, ammonia compounds, dust or similar substances may lead
to corrosion on the product and in the air/flue
pipe.
▶ Ensure that the supply of combustion air is
always free of fluorine, chlorine, sulphur,
dust, etc.
▶ Ensure that no chemical substances are
stored at the installation site.
▶ Ensure that the combustion air is not
routed through chimneys which have
previously been used with floor-standing
oil-fired boilers, or with other boilers,
Installation and maintenance instructions ecoTEC plus 0020200871_00
Safety 1
which could cause soot to build up in the
chimney.
▶ If you are installing the product in
hairdressing salons, painter's or joiner's
workshops, cleaning businesses or similar
locations, choose a separate installation
room in which a combustion air supply is
ensured that is technically free of chemical
substances.
1.3.13 Risk of material damage caused by
frost
▶ Do not install the product in rooms prone
to frost.
1.3.14 Risk of being burned or scalded by
hot components
▶ Only carry out work on these components
once they have cooled down.
1.3.15 Risk of material damage caused by
using an unsuitable tool
▶ Use the correct tool to tighten or loosen
screw connections.
1.4
Regulations (directives, laws,
standards)
▶ Observe the national regulations, standards, guidelines and laws.
0020200871_00 ecoTEC plus Installation and maintenance instructions
5
2 Notes on the documentation
2
Notes on the documentation
2.1
▶
Observing other applicable documents
You must observe all the operating and installation instructions included with the system components.
2.2
▶
Storing documents
Pass these instructions and all other applicable documents on to the system operator.
2.3
Applicability of the instructions
These instructions apply only to:
Product article number
Information on the
identification plate
Meaning
Type: Xx3(x)
Permissible flue gas connections
PMS
Maximum water pressure in heating
mode
PMW
Maximum water pressure in hot water
handling mode
V/Hz
Electric connection
W
Max. electrical power consumption
IP
Level of protection
Heating mode
Pn
Nominal heat output range in heating
mode
Article number
Gas Council
Number
Pnc
Nominal heat output range in heating
mode (condensing technology)
VU 126/6-5 OV (H-GB)
ecoTEC plus
0010015669
41-044-71
P
Nominal heat output range in hot water
handling mode
VU 156/6-5 OV (H-GB)
ecoTEC plus
0010015670
41-044-72
Qn
Nominal heating load range in heating
mode
VU 186/6-5 OV (H-GB)
ecoTEC plus
0010015671
41-044-73
Qnw
Nominal heating load range in hot water
handling mode
VU 246/6-5 OV (H-GB)
ecoTEC plus
0010015672
41-044-74
Tmax.
Max. flow temperature
VU 306/6-5 OV (H-GB)
ecoTEC plus
0010015673
41-044-75
3
3.1
NOx class for the product
Code (DSN)
Specific product code
→ "CE label" section
Product description
Read the instructions.
Serial number
The serial number is located on a plate behind the front flap.
The plate is in a plastic fish plate. You can also display the
serial number in the display.
3.2
NOx
Information on the identification plate
→ "Recycling and disposal" section
GC no.
3.3
Gas council number
CE label
The identification plate is mounted on the underside of the
product in the factory.
The identification plate keeps record of the country in which
the product is to be installed.
Information on the
identification plate
Meaning
Barcode with serial number
Serial number
For quality control purposes; 3rd and 4th
digits = year of production
For quality control purposes; 5th and 6th
digits = week of production
For identification purposes; 7th to 16th
digits = product article number
For quality control purposes; 17th to 20th
digits = place of manufacture
ecoTEC plus
Product description
2H, G20 - 20 mbar
(2 kPa)
Factory setting for type of gas and gas
connection pressure
Cat.
Approved gas category
Condensing technology
Efficiency class of the boiler in accordance with EC Directive 92/42/EEC
6
The CE label shows that the products comply with the basic
requirements of the applicable directives as stated on the
identification plate.
The declaration of conformity can be viewed at the manufacturer's site.
Installation and maintenance instructions ecoTEC plus 0020200871_00
Installation 4
3.4
▶
▶
Functional elements
▶
▶
1
2
3
4.2
1.
2.
Unpacking the product
Remove the product from its box.
Remove the protective film from all of the product's
components.
4
4.3
5
▶
6
4.3.1
7
8
9
1
Gas-air mixture unit
6
Heat exchanger
2
Flue pipe
7
Air intake pipe
3
Flue gas analysis point
8
Condensate siphon
4
Gas valve
9
Electronics box
5
Ignition transformer
4
Installation
4.1
▶
Lift the box using the straps provided.
Use safe lifting techniques – keep your back straight and
bend your legs at the knee.
Hold the load as close as possible to your body.
If the unit is being lifted by two persons, ensure your
movements are coordinated during lifting.
If required, get somebody to assist you in this.
Checking the scope of delivery
Check that the scope of delivery is complete and intact.
Scope of delivery
Number
Description
1
Heat generator
1
Hanging bracket
1
Gas isolator cock
1
Gas pipe
1
Condensate drain hose
1
Installation template
1
Enclosed documentation
Transporting the unit
Important: With regard to the regulations of 1992 concerning the manual handling of loads, the unit exceeds the
weight that can be lifted by a single person.
4.1.1
▶
▶
▶
▶
▶
Hold the load as close as possible to your body. Avoid
rotational movements. Instead, reposition your feet.
If the unit is being lifted by two persons, ensure your
movements are coordinated during lifting.
Avoid bending your upper body – do not lean forwards or
to the side.
Wear suitable non-slip protective gloves in order to protect your hands against sharp edges. Ensure that you are
carrying the load securely.
If required, get somebody to assist you in this.
4.1.2
▶
General
Unloading the box from the delivery van
It is recommended that two people lift the unit together.
0020200871_00 ecoTEC plus Installation and maintenance instructions
7
4 Installation
4.4
Dimensions
4.5
Minimum clearances
A
1
2
112
C
71
375
33,5
D
3
78
B
183,5
C
4
602
Minimum clearance
4.6
A
150 mm
B
150 mm
C
5 mm
D
600 mm
Clearance from combustible components
It is not necessary to maintain a clearance between the
product and components made of combustible materials.
4.7
▶
32,5
4.8
Using the installation template
Use the installation template to ascertain the locations at
which you need to drill holes and make breakthroughs.
Wall-mounting the product
220
B
150
A
5
1
Condensate discharge
4
Heating flow
2
Gas connection
5
Flue pipe connection
3
Heating return
1.
2.
Check whether the wall has sufficient load-bearing capacity to bear the operational weight of the product.
Check if the supplied fixing material may be used for
the wall.
Conditions: The load-bearing capacity of the wall is sufficient, The fixing
material may be used for the wall
▶
Wall-mount the product as described.
Conditions: The load-bearing capacity of the wall is not sufficient
▶
8
Ensure that wall-mounting apparatus on-site has a sufficient load-bearing capacity. Use individual stands or
primary walling, for example.
Installation and maintenance instructions ecoTEC plus 0020200871_00
Installation 5
▶
Do not wall-mount the product if you cannot provide
wall-mounting apparatus with a sufficient load-bearing
capacity.
Note
If there is sufficient lateral clearance (at least
70 mm), you can remove the side section to facilitate maintenance or repair work.
Conditions: The fixing material may not be used for the wall
▶
Wall-mount the product as described using the permitted
fixing material provided on-site.
4.9
Removing/installing the front casing
4.9.1
Removing the front casing
D
D
E
A
C
B
B
1.
2.
A
C
1.
2.
3.
4.
Undo the two screws (1).
Gently press the front casing backwards in the centre
and pull it downwards on the lower edge so that the
retaining clip is released.
Pull the front casing forwards at the bottom edge.
Lift the front casing upwards from the retainers.
4.9.2
1.
2.
3.
4.10
Installing the front casing
Place the front casing on the upper retainer.
Press the front casing onto the product so that the retainer bracket clicks into place.
Secure the front casing by tightening both screws.
Removing/installing the side section
4.10.1 Removing the side section
Caution.
Risk of material damage caused by mechanical deformation.
Removing both side sections may cause
mechanical distortion in the product, which
may cause damage to the piping, for example, and potentially result in leaks.
▶
Always remove only one side section –
never both side sections at the same time.
0020200871_00 ecoTEC plus Installation and maintenance instructions
3.
Tilt the electronics box forward.
Hold on to the side section so that it cannot fall, and
unscrew both screws, one from the top and one from
the bottom.
Tilt the side section to the outside and take it out towards the top.
4.10.2 Installing the side section
1.
2.
3.
4.
5
5.1
Push the side section into the recesses in the back wall.
Tilt the side section towards the product.
Screw the two screws into the side section, one at the
top and one at the bottom.
Fold up the electronics box.
Installation
Preparing for installation
Danger!
Risk of scalding and/or damage due to
incorrect installation leading to escaping
water.
Stresses in the supply line can cause leaks.
▶
Make sure there is no voltage in the supply lines when they are installed.
Caution.
Risk of damage caused by corrosion.
If non-diffusion-tight plastic pipes are used in
the heating installation, this may cause air to
enter the heating water and corrosion of the
heat generation circuit and the boiler.
9
5 Installation
▶
If using non-diffusion-tight plastic pipes
in the heating installation, separate the
system by installing an external heat exchanger between the boiler and the heating installation.
5.3
Gas connection
1
Caution.
Risk of material damage due to heat transfer during soldering.
▶
Do not solder the connection pieces if
the connection pieces are screwed to the
service valves.
Caution.
Risk of damage caused by incorrect gas
installation.
1.
2.
3.
5.4
Establish the gas connection (1) in accordance with the
applicable standards.
Purge the gas line before start-up.
Check whether the connections (→ Page 16) are leaktight.
Connecting the condensate drain pipework
Excess test pressure or operating pressure
may cause damage to the gas valve.
▶
▶
▶
▶
5.2
Check the leak-tightness of the gas valve
using a maximum pressure of 1.1 kPa
(110 mbar).
Flush the heating installation thoroughly prior to installation.
Make sure that the existing gas meter is capable of
passing the rate of gas supply required.
Install the following components:
– Drain cocks at the lowest points of the heating installation
– A heating pump in the heating flow
– A bypass that is at least 1.5 m away from the product
– A stop cock in the gas line
1
2
Connecting the heating flow and heating
return
2
▶
▶
▶
1
▶
1
1.
2.
3.
10
Heating return connection
2
Note
The condensate drain pipework must have a
continuous fall (45 mm per metre) and should
whenever possible terminate at a suitable
drain point within the heated envelope of the
building that will remain frost free under long
periods of low external temperatures.
Heating flow connection
Establish the heating connections in accordance with
the applicable standards.
Purge the gas line before start-up.
Check whether the connections (→ Page 16) are leaktight.
Follow the instructions listed here and observe directives
and local regulations on condensate discharge.
Use PVC or another material that is suitable for draining
the non-neutralised condensate.
If it cannot be guaranteed that the materials the drain
lines are made from are suitable, install a system for
neutralising the condensate.
Ensure that the connection between the condensate
drain pipework and the drain hose is not air-tight.
▶
During installation remove all burs from inside of cut pipe
work and avoid excessive adhesive which may trap small
pockets of water close to the pipe wall which can freeze
and build into a larger ice plug.
Installation and maintenance instructions ecoTEC plus 0020200871_00
Installation 5
▶
As with other pipe work insulate the condensate discharge pipe to minimise any risk of freezing and beware
when crossing cavities that the fall is maintained and the
pipe sleeved.
5.6.2
You can find further information in BS 6789: "Specification
for installing and maintaining gas-fired boilers with a nominal
heat loading less than 70 kW".
5.5
Cable route
230V
Installing the air/flue pipe
Caution.
Risk of poisoning due to escaping flue
gas.
24V / eBus
Mineral-oil-based greases can damage the
seals.
▶
1.
2.
Instead of grease, use only water or commercially available soft soap to aid installation.
You can find out which air/flue pipes may be used by
consulting the enclosed air/flue pipe installation manual.
Install the flue gas pipe in accordance with the installation instructions that are included in the scope of delivery for the air/flue pipe.
5.6
1
24-V eBUS cable route
2
230-V eBUS cable
route
5.6.3
30 mm max.
Electrical installation
Danger!
Risk of death from electric shock!
The mains connection terminals L and N remain live even if the product is switched off:
▶
▶
5.6.1
Carrying out the wiring
Switch off the power supply.
Secure the power supply against being
switched on again.
1.
Shorten the connection cables to the appropriate
lengths to prevent them from causing damage inside
the electronics box.
2.
3.
Screw the plug to the connection cable.
Plug the plug into the slot provided on the PCB.
5.6.4
Establishing the power supply
1
Opening the electronics box
A
B
B
1.
2.
3.
▶
Follow the instructions in the specified sequence.
0020200871_00 ecoTEC plus Installation and maintenance instructions
Observe all valid regulations.
Ensure that the rated mains voltage is 230 V.
Set up a fixed connection and install a partition with a
contact opening of at least 3 mm (e.g. fuses or power
switches).
11
6 Operation
4.
5.
6.
Provide one common electricity supply for the boiler
and for the corresponding controller:
– Power supply: Single-phase, 230 V, 50 Hz
– Fuse protection: ≤ 3 A
Open the electronics box. (→ Page 11)
Observe the routing of the power supply cable (1) in the
electronics box in order to guarantee the strain relief.
3.
Connect the individual components depending on the
type of installation.
Conditions: If installing a multi-circuit controller.
▶
Change the pump's operating mode d.18 from Eco (intermittently operating pump) to Comfort (continuously
operating pump).
L N
RT
≤ 30 mm
≤ 30 mm
Conditions: When connecting a controller (230 V).
X1
230V~
L N
▶
▶
4.
6
6.1
7.
8.
9.
Carry out the wiring. (→ Page 11)
Close the electronics box.
Make sure that access to the mains connection is always available and is not covered or blocked.
5.6.5
Connecting controllers to the electronic
system
6.2
Burner
off
RT
24V =
RT
BUS
- +
BUS
X106
B.off
3.
1
2
3
+
BUS
Operation
Operating concept
Installer level – Overview (→ Page 22)
2.
–
Connect the controller to the main plug.
Remove the bridge from the plug 24V=RT.
Close the electronics box.
An overview of the reading and setting options for the installer level is included in the table in the appendix.
24 V BUS
24V=
RT
X1
230V~
The operating concept and the read-off and setting facilities
of the operator level are described in the operating instructions.
1.
Burner
off
RT
6.3
Calling up the installer level
Only call up the installer level if you are a competent
person.
Navigate to Menu → Installer level and confirm by
pressing
.
Set the value 17 (code) and confirm by pressing
.
Live Monitor (status codes)
Menu → Live Monitor
Status codes in the display provide information on the product's current operating status.
X2
X22
Status codes – Overview (→ Page 28)
X41
4
1
2
1.
2.
12
Safety thermostat for
floor-standing heating
24 V controller
3
4
eBUS controller or radio
receiver unit
Outside temperature
sensor, wired
Open the electronics box. (→ Page 11)
Carry out the wiring. (→ Page 11)
Installation and maintenance instructions ecoTEC plus 0020200871_00
Start-up 7
7
Start-up
7.1
7.2.3
1.
Carrying out the initial start-up
Initial start-up must be carried out by a customer service
technician or an authorised competent person using the firstcommissioning-checklist. The first-commissioning-checklist
in the appendix (→ Page 35) of the installation instructions
must be filled out and stored carefully along with the unit's
documentation.
▶
▶
Carry out the initial start-up using the first-commissioning-checklist in the appendix.
Fill out and sign the first-commissioning-checklist.
2.
Unlike in the Check programs menu, to purge the system, start check programme P.00 by pressing
or
.
If you need to change the circuit that is to be purged,
press
.
7.2.4
1.
2.
Purging
Target flow temperature, hot water
temperature
To set the target flow temperature and hot water temperature, use
and
.
Press
to confirm this setting.
Conditions: Water hardness: > 3.57 mol/m³, Product with connected cylin-
7.2
Running the installation assistants
der
The installation assistant is displayed whenever the product
is switched on until it has been successfully completed.
It provides direct access to the most important check
programmes and configuration settings for starting up the
product.
Danger!
Risk of death from Legionella.
Legionella multiply at temperatures below
60 °C.
▶ Ensure that the operator is familiar with
all of the Anti-legionella measures in order to comply with the applicable regulations regarding legionella prevention.
To recheck and reset the most important system parameters,
call up the Appliance config..
Menu → Installer level Appliance config.
The settings options for more complex systems can be found
in the Diagnostics menu.
▶
Menu → Installer level Diagnostics menu
▶
Press
◁
to confirm installation assistant start-up.
All heating and hot water requests are blocked whilst
the installation assistant is active.
Note
If you do not confirm the launch of the installation assistant within 10 seconds of switching
the system on, the basic display reappears.
▶
7.2.1
▶
▶
7.2.5
7.2.6
in each
Language
2.
Note
This setting can be retroactively changed in
the Diagnostics menu using D.026, D.027
and D.028.
Set the required language.
To confirm the set language and to avoid unintentionally
changing it, press
twice to confirm this.
▶
▶
Press and hold
and
at the same time.
Also briefly press
.
Press and hold
and
until the display shows the
language setting option.
Select the required language.
Press
twice to confirm this change.
7.2.2
Filling mode
Filling mode (check programme P.06) is activated automatically in the installation assistant for as long as the filling mode
appears on the display.
0020200871_00 ecoTEC plus Installation and maintenance instructions
Auxiliary relay and multi-functional module
If you have connected additional components to the
product, assign these components to the individual relays.
In each case, confirm by pressing
.
If you have unintentionally set a language that you do not
understand, proceed as follows to change it:
▶
▶
▶
Heating partial load
The heating partial load of the product is set to Auto at the
factory. The product independently determines the optimum
heating output depending on the current heat demand of
the system. You can retroactively change the setting in the
Diagnostics menu under D.000.
1.
To access the next point, confirm by pressing
case.
Set the hot water temperature.
– Water temperature: ≤ 50 ℃
7.2.7
▶
If required, store your telephone number in the Appliance config. (max. 16 digits/no blank spaces). The operator can view the telephone number.
7.2.8
▶
Contact data
Ending the installation assistant
Once you have run through the installation assistant successfully, confirm by pressing
.
◁
The installation assistant will close and will not launch
again when the product is next switched on.
13
7 Start-up
7.3
Restarting the installation assistants
Menu → Installer level → Start inst. assistant
You can restart the installation assistant at any time by calling it up in the menu.
7.4
Test programmes
Menu → Installer level Test programs
As well as the installation assistants, you can also call up
the following test programmes for start-up, service and
troubleshooting.
–
–
–
Check programs
Function menu
Electronics self-test
7.5
Check the information about the type of gas indicated on
the identification plate and compare this with the type of
gas available at the installation location.
Conditions: The product design is not compatible with the local gas
Ensure that oxygen cannot get into the heating water.
(→ Page 16)
Checking the filling and supplementary water
▶
Before filling the system, measure the hardness of the
filling and supplementary water.
Treating the filling and supplementary water
▶
Observe all applicable national regulations and technical
standards when treating the filling and supplementary
water.
Provided the national regulations and technical standards
do not stipulate more stringent requirements, the following
applies:
You must treat the heating water in the following cases:
–
Checking the factory setting
The product's combustion has been factory tested and is
preset for operation with the gas group indicated on the identification plate.
▶
▶
–
–
If the entire filling and supplementary water quantity during the operating life of the system exceeds three times
the nominal volume of the heating installation, or
If the guideline values listed in the following table are not
met, or
if the pH value of the heating water is less than 6.5 or
more than 8.5.
group
▶
Do not start up the product.
Conditions: The product design is compatible with the local gas group
▶
7.6
Proceed as described below.
Checking and treating the heating
water/filling and supplementary water
Caution.
Risk of material damage due to poor-quality heating water
▶
▶
Ensure that the heating water is of sufficient quality.
Before filling or topping up the system, check the quality
of the heating water.
Checking the quality of the heating water
▶
▶
▶
▶
▶
▶
▶
Remove a little water from the heating circuit.
Check the appearance of the heating water.
If you ascertain that it contains sedimentary materials,
you must desludge the system.
Use a magnetic rod to check whether it contains magnetite (iron oxide).
If you ascertain that it contains magnetite, clean the system and apply suitable corrosion-protection measures, or
fit a magnet filter.
Check the pH value of the removed water at 25 °C.
If the value is below 6.5 or above 8.5, clean the system
and treat the heating water.
1)
Total
heating
output
kW
Water hardness at specific system volume
> 50 l/kW
ppm
ppm
ppm
CaCO₃ mol/m³ CaCO₃ mol/m³ CaCO₃ mol/m³
< 50
< 300
<3
200
2
2
0.02
> 50
to ≤ 200
200
2
150
1.5
2
0.02
> 200
to ≤ 600
150
1.5
2
0.02
2
0.02
> 600
2
0.02
2
0.02
2
0.02
1) Nominal capacity in litres/heating output; in the case of multiboiler systems, the smallest single heating output is to be used.
Caution.
The use of unsuitable heating water may
cause aluminium corrosion and a resulting lack of leak-tightness.
In contrast to steel, grey cast iron or copper,
for example, aluminium reacts with alkaline
heating water (pH value > 8.5) to produce
substantial corrosion.
▶
When using aluminium, make sure that
the pH value of the heating water is
between 6.5 and a maximum of 8.5.
Caution.
Risk of material damage if the heating
water is treated with unsuitable additives.
Unsuitable additives may cause changes in
the components, noises in heating mode and
possibly subsequent damage.
▶
14
> 20 l/kW
≤ 50 l/kW
≤ 20 l/kW
Do not use any unsuitable frost and corrosion protection agents, biocides or sealants.
Installation and maintenance instructions ecoTEC plus 0020200871_00
Start-up 7
No incompatibility with our products has been detected to
date with proper use of the following additives.
▶
Note
Check whether the float is present in the
condensate siphon.
When using additives, follow the manufacturer's instructions without exception.
We accept no liability for the compatibility of any additive or
its effectiveness in the rest of the heating system.
5.
Additives for cleaning measures (subsequent
flushing required)
7.9
–
–
–
1.
Fernox F3
Sentinel X 300
Sentinel X 400
Clip the lower section of the siphon (1) into the upper
section of the siphon (2).
Checking the gas connection pressure (gas
flow pressure)
Close the gas isolator cock.
Additives intended to remain permanently in the
system
–
–
–
–
Fernox F1
Fernox F2
Sentinel X 100
Sentinel X 200
1
Additives for frost protection intended to remain
permanently in the system
–
–
Fernox Antifreeze Alphi 11
Sentinel X 500
▶
If you have used the above-mentioned additives, inform
the operator about the measures that are required.
Inform the operator about the measures required for frost
protection.
▶
7.7
▶
7.8
Switching on the product
2
Switch on the product via the main switch installed onsite.
Filling the condensate siphon
2.
3.
4.
5.
6.
2
Use a screwdriver to undo the sealing screw on the
measuring connection (1) of the gas valve.
Connect a pressure gauge (2) to the measuring nipple
(1).
Open the gas isolator cock.
Start up the product with the check programme P.01.
Measure the gas connection pressure against atmospheric pressure.
Permissible connection pressure
C
A
Great Britain
B
1
3
1.
2.
3.
4.
7.
8.
9.
10.
11.
12.
Natural gas
G20
1.7
… 2.5 kPa
(17.0
… 25.0 mbar)
Decommission the product.
Close the gas isolator cock.
Remove the pressure gauge.
Tighten the screw on the measuring nipple (1).
Open the gas isolator cock.
Check the measuring nipple for gas tightness.
Unclip the lower section of the siphon (1) from the upper section of the siphon (2).
Remove the float (3).
Fill the lower section of the siphon with water up to
10 mm below the upper edge of the condensate drain
pipework.
Re-insert the float (3).
0020200871_00 ecoTEC plus Installation and maintenance instructions
15
8 Adapting the unit to the heating installation
5.
Conditions: Gas connection pressure not in the permissible range
Caution.
Risk of material damage and operating
faults caused by incorrect gas connection pressure.
If the gas connection pressure lies outside
the permissible range, this can cause operating faults in and damage to the product.
▶ Do not make any adjustments to the
product.
▶ Do not start up the product.
For liquid gas only: Only perform the adjustment in
small increments (approx. 1/16 turn), and wait approx.
one minute after each adjustment until the value stabilises.
If an adjustment is not possible in the specified adjustment range, you must not start up the product.
If this is the case, inform Vaillant Customer Service.
Secure the covering cap.
Install the front casing. (→ Page 9)
6.
7.
8.
9.
7.12
1.
▶
▶
If you are unable to remedy the fault, contact the gas
supply company.
Close the gas isolator cock.
7.10
1.
2.
3.
4.
Start up the product with the check programme P.01.
Wait at least five minutes until the product reaches its
operating temperature.
Measure the CO₂ content at the flue gas analysis point.
Compare the measured value with the corresponding
value in the table.
Settings
Unit
G20
natural
gas
CO₂ after 5 minutes in full load mode
with front casing closed
Vol.–%
CO₂ after 5 minutes in full load mode
with front casing removed
Vol.–%
9.0 ± 1.0
Set for Wobbe index W₀
kWh/m³
15
CO in full load mode
9.2 ± 1.0
≤ 250
ppm
≤ 0.0031
CO/CO₂
5.
Set the CO₂ content as required. (→ Page 16)
7.11
Check that the flue gas system is intact, in accordance
with British Gas TB 200.
If the flue gas system is longer than 2 m, we urgently
recommend that you test the system for flue gas recirculation as described below.
Use the air analysis point (1) to check for flue gas recirculation.
Use the flue gas measuring instrument.
If you discover CO or CO2 in the fresh air, search for a
leak in the flue gas system or for the flue gas recirculation.
Eliminate the damage.
Repeat the above-mentioned test to determine if the
fresh air contains CO or CO2.
If you cannot eliminate the damage, you must not start
up the boiler.
2.
3.
Checking the CO₂ content
Checking the leak-tightness of the flue gas
system and for flue gas recirculation
4.
5.
6.
7.
8.
7.13
Checking function and leak-tightness
Before you hand the product over to the operator:
▶
▶
▶
Check the gas line, the flue gas installation, the heating
installation and the hot water pipes for leaks.
Check that the air/flue pipe and condensate drain pipework have been installed correctly.
Check that the front casing has been installed correctly.
7.14
Setting the CO₂ content
1
1.
2.
3.
4.
5.
Checking the heating mode
Activate the heating mode on the user interface.
Turn all thermostatic radiator valves on the radiators
until they are fully open.
Allow the product to operate for at least 15 minutes.
Purge the heating installation.
Call up the Live Monitor.
– Menu → Live Monitor
Status codes – Overview (→ Page 28)
◁
1.
2.
3.
4.
16
If the product is working correctly, the display shows
S.04.
Remove the yellow sticker.
Remove the blue covering cap (1).
Use an Allen key to turn the bolt in order to set the CO₂
content (value with front casing removed).
8
◁
◁
You can reset/change the system parameters using the following menu points:
Turning to the right decreases the value.
Turning to the left increases the value.
For natural gas only: Only perform the adjustment in
increments of a 1/8 turn and wait approx. one minute
after each adjustment until the value stabilises.
Adapting the unit to the heating
installation
Menu → Installer level → Start inst. assistant
You can restart and run through the installation assistant at
any time.
Installation and maintenance instructions ecoTEC plus 0020200871_00
Handing the product over to the operator 9
Menu → Installer level Appliance config.
10
You can set/change the most important system parameters
in the Appliance config. menu point.
10.1
Menu → Installer level Diagnostics menu
You can set/change additional system parameters in the
Diagnostics menu point.
▶
You can find an overview of all the system parameters in the
"Installer level – Overview" table in the appendix.
Installer level – Overview (→ Page 22)
8.1
Burner anti-cycling time
To prevent frequent switching on and off of the burner and
thus prevent energy losses, an electronic restart lockout
is activated for a specific period each time the burner is
switched off. The burner anti-cycling time is only active for
the heating mode. Hot water handling mode during a burner
anti-cycling time does not affect the time function element.
8.1.1
▶
Set the burner anti-cycling time via the diagnostics code.
Overview of diagnostics codes (→ Page 25)
8.1.2
▶
▶
▶
▶
▶
▶
▶
Procuring spare parts
The original components of the product were also certified
as part of the declaration of conformity. If you do not use certified Vaillant original spare parts for maintenance or repair
work, this voids the conformity of the product. We therefore
strongly recommend that you fit Vaillant genuine spare parts.
Information about available Vaillant original spare parts is
available by contacting the contact address provided on the
reverse of this document.
▶
If you require spare parts for maintenance or repair work,
use only Vaillant genuine spare parts.
10.3
Removing the gas-air mixture unit
Note
The gas-air mixture unit consists of three main
components:
Resetting the remaining burner anti-cycling
time
– Ventilator
– Gas valve
is shown in the display.
Handing the product over to the
operator
Observing inspection and maintenance
intervals
Adhere to the minimum inspection and maintenance intervals. The inspection may require maintenance to be
carried out earlier, depending on the results.
Inspection and maintenance work – Overview
(→ Page 22)
10.2
Press and hold the fault clearance key for more than
three seconds.
◁
9
Setting the burner anti-cycling time
Inspection and maintenance
– Burner cover
1.
2.
3.
Switch off the product via the main switch.
Close the gas isolator cock.
Remove the front casing. (→ Page 9)
When you have finished the installation, attach the sticker
supplied (in the operator's language) to the product
cover.
Explain to the operator how the safety devices work and
where they are located.
Inform the operator how to handle the product.
In particular, draw attention to the safety information
which the operator must follow.
Inform the operator of the necessity to have the product
maintained on a regular basis.
Instruct the operator about measures taken to ensure the
supply of combustion air and flue gas pipe.
A
1
B
4.
0020200871_00 ecoTEC plus Installation and maintenance instructions
Remove the air intake pipe (1).
17
10 Inspection and maintenance
10.4
2
1.
2.
Cleaning the heat exchanger
Check the heat exchanger for damage and dirt.
If required, clean and replace the heat exchanger.
A
1
B
3
3.
Protect the folded down electronics box against sprayed
water.
Clean the ribs of the heat exchanger (1) with water.
4.
◁
The water runs out via the condensate tray.
C
10.5
▶
5.
6.
Checking the burner
Check the surface of the burner for damage. If you see
any damage, replace the burner.
10.6
Push the clip (2) upwards.
Remove the flue pipe (3).
Checking the ignition electrode
3
4
5
2
1
B
D
1.
2.
3.
C
4.
5.
A
7.
8.
9.
Remove the plugs from the gas valve.
Remove the gas-air mixture unit.
Remove both burner seals from the burner cover.
6.
Disconnect the connection (2) and the earthing cable
(1).
Remove the fixing screws (3).
Carefully remove the electrode from the combustion
chamber.
Check that the electrode ends (4) are undamaged.
Check the electrode distance.
– Clearance for the ignition electrodes: 3.5 … 4.5 mm
Make sure that the seal (5) is free from damage.
▽
If necessary, replace the seal.
1
10. Remove the burner (4).
18
Installation and maintenance instructions ecoTEC plus 0020200871_00
Troubleshooting 11
10.7
Cleaning the condensate siphon
11
Troubleshooting
11.1
▶
2
Rectifying faults
If fault codes (F.XX) are present, refer to the table in the
appendix for advice or use the check programme(s).
Overview of fault codes (→ Page 29)
Installer level – Overview (→ Page 22)
If several faults occur at the same time, the display shows
the corresponding fault messages for two seconds each in
alternation.
A
B
▶
▶
1
3
11.2
2.
3.
4.
Unclip the lower section of the siphon (1) from the upper section of the siphon (2).
Remove the float (3).
Flush out the lower section of the siphon with water.
Reinsert the float (3).
Navigate to the Fault list menu.
◁
▶
1.
2.
11.4
5.
10.8
1.
2.
3.
4.
5.
10.9
1.
2.
3.
Clip the lower section of the siphon (1) into the upper
section of the siphon (2).
Installing the gas-air mixture unit
Install the burner.
Install two new burner seals in the burner cover.
Install the gas-air mixture unit.
Install the flue pipe.
Install the air intake pipe.
Draining the product
Close the service valves of the product.
Start check programme P.06.
Open the drain valves.
10.10 Completing inspection and maintenance
work
1.
2.
Check the gas connection pressure (gas flow pressure).
(→ Page 15)
Check the CO₂ content. (→ Page 16)
1.
2.
3.
4.
5.
6.
7.
8.
9.
11.5
or
to call up individual fault messages.
Deleting the fault memory
Navigate to the Fault list menu.
Press
twice to delete the fault list.
Preparing the repair work
Decommission the product.
Disconnect the product from the power mains.
Remove the front casing.
Close the gas isolator cock.
Close the service valves in the heating flow and in the
heating return.
Close the service valve in the cold water pipe.
Drain the product if you want to replace water-bearing
components of the product.
Make sure that water does not drip on live components
(e.g. the electronics box).
Use only new seals.
Replacing defective components
11.5.1 Replacing the burner
1.
2.
3.
4.
5.
0020200871_00 ecoTEC plus Installation and maintenance instructions
The display shows the number of faults that have
occurred, the fault numbers and the corresponding
plain text display.
Press
11.3
Note
Check whether the float is present in the
condensate siphon.
Calling up the fault memory
The last 10 fault messages are stored in the fault memory.
▶
1.
Press and hold the fault clearance key for more than
three seconds.
If you are unable to clear the fault code and it reappears
despite several fault clearance attempts, contact customer service.
Remove the gas-air mixture unit. (→ Page 17)
Remove the burner seal.
Remove the burner.
Install the new burner complete with new seal on the
heat exchanger.
Install the gas-air mixture unit. (→ Page 19)
19
11 Troubleshooting
11.5.2 Replacing the gas-air mixture unit
1.
2.
Remove the gas-air mixture unit. (→ Page 17)
Install the new gas-air mixture (→ Page 19).
11.5.3 Replacing the heat exchanger
1.
2.
B
3
A
Remove the side section. (→ Page 9)
Remove the gas-air mixture unit. (→ Page 17)
4
A
6.
7.
Undo the clip underneath the condensate tray (4).
Undo the two screws (3).
C
A
B
1
5
2
C
E
B
8.
Lift the heat exchanger up slightly and remove it together with the condensate tray.
9. Remove the ignition transformer (5).
10. Replace all the seals.
11. Install the new heat exchanger in reverse order.
D
3.
4.
11.5.4 Replacing the main PCB
Remove the flow pipe (1).
Remove the return pipe (2).
C
B
C
D
B
A
A
5.
Remove the gas pipe.
A
1.
2.
3.
4.
20
Open the electronics box. (→ Page 11)
Pull all of the plugs out from the PCB.
Undo the clips on the PCB.
Remove the PCB.
Installation and maintenance instructions ecoTEC plus 0020200871_00
Decommissioning the product 12
5.
Install the new PCB in such a way that it clicks into the
groove at the bottom and into the clip at the top.
Plug in the PCB plugs.
Close the electronics box.
6.
7.
11.5.5 Replacing the PCB for the user interface
D
C
C
B
A
A
1.
2.
3.
4.
5.
Open the electronics box. (→ Page 11)
Pull the plug out of the PCB.
Undo the clips on the PCB.
Remove the PCB.
Install the new PCB in such a way that it clicks into the
groove at the bottom and into the clip at the top.
Plug in the PCB plug.
Close the electronics box.
6.
7.
11.6
▶
12
▶
▶
▶
▶
▶
13
Completing repair work
Check that the product functions correctly and is leaktight (→ Page 16).
Decommissioning the product
Switch off the product.
Disconnect the product from the power mains.
Close the gas isolator cock.
Close the cold water stop valve.
Drain the product. (→ Page 19)
Customer service
To ensure regular servicing, it is strongly recommended
that arrangements are made for a Maintenance Agreement.
Please contact Vaillant Service Solutions for further details.
Vaillant Service Solutions: 03 30 100‑31 43
0020200871_00 ecoTEC plus Installation and maintenance instructions
21
Appendix
Setting level
Values
Min.
Max.
Unit
Increment, select, explanation
Default
setting
Installer level → Test programs → Check programs →
P.00 Purging
–
–
–
Yes, No
–
P.01 Maximum load
–
–
–
Yes, No
–
P.02 Minimum load
–
–
–
Yes, No
–
P.04 Heating partial load
–
–
–
Yes, No
–
P.06 Filling mode
–
–
–
Yes, No
–
Installer level → Test programs → Function menu →
T.02 3-way valve
–
–
–
On, Off
–
T.03 Fan
–
–
–
On, Off
–
T.04 Cyl. charging pump
–
–
–
On, Off
–
T.05 Circulation pump
–
–
–
On, Off
–
T.06 External pump
–
–
–
On, Off
–
T.08 Burner
–
–
–
On, Off
–
–
Installer level → Test programs → Electronics self-test →
–
–
–
Yes, No
–
–
–
Deutsch, English, Français, Italiano, Dansk,
Nederlands, Castellano, Türkce, Magyar,
Pусский, Українськa, Svenska, Norsk, Polski, Čeština, Hrvatski, Slovenčina, Română,
Slovenščina, Português, Srpski
Flow temp. setpoint
30
75
℃
1
–
DHW temperature
30
60
℃
1
Product with connected domestic hot water cylinder
–
Auxiliary relay
1
10
–
1 = Circulation pump
2 = External pump
3 = Cylinder charging pump
4 = Extractor hood
5 = External solenoid valve
6 = External fault message
7 = Solar pump (not active)
8 = eBUS remote control (not active)
9 = Legionella protection pump (not active)
10 = Solar valve (not active)
2
Accessory relay 1
1
10
–
1 = Circulation pump
2 = External pump
3 = Cylinder charging pump
4 = Extractor hood
5 = External solenoid valve
6 = External fault message
7 = Solar pump (not active)
8 = eBUS remote control (not active)
9 = Legionella protection pump (not active)
10 = Solar valve (not active)
2
Self-test
Installer level → Appliance config. →
Language
English
¹Fault lists are only displayed, and can only be deleted, if faults have occurred.
0020200871_00 ecoTEC plus Installation and maintenance instructions
23
Appendix
Setting level
Values
Unit
Min.
Max.
Accessory relay 2
1
10
–
Heating partial load
–
–
kW
Phone
number
–
–
Contact data
Default setting
Increment, select, explanation
1 = Circulation pump
2 = External pump
3 = Cylinder charging pump
4 = Extractor hood
5 = External solenoid valve
6 = External fault message
7 = Solar pump (not active)
8 = eBUS remote control (not active)
9 = Legionella protection pump (not active)
10 = Solar valve (not active)
Default
setting
2
Partial load only, full load only, auto
Auto
–
0–9
Auto
–
–
On, Off
Current value
–
–
Installer level → Diagnostics menu →
D.XXX - D.XXX
–
–
Installer level → Start ins. assistant →
Language
–
–
–
Deutsch, English, Français, Italiano, Dansk,
Nederlands, Castellano, Türkce, Magyar,
Pусский, Українськa, Svenska, Norsk, Polski, Čeština, Hrvatski, Slovenčina, Română,
Slovenščina, Português, Srpski
Filling mode: 3-way valve is in midposition
0
2
–
0 = Normal operating mode
1 = Mid-position (parallel operation)
2 = Permanent heating mode position
–
Purge programme
–
–
–
Automatic adaptive purging of the heating circuit
and hot water circuit
Not active
Active
–
Flow temp. setpoint
30
75
℃
1
–
DHW temperature
35
60
℃
1
Product with hot water generation
–
Auxiliary relay
1
10
–
1 = Circulation pump
2 = External pump
3 = Cylinder charging pump
4 = Extractor hood
5 = External solenoid valve
6 = External fault message
7 = Solar pump (not active)
8 = eBUS remote control (not active)
9 = Legionella protection pump (not active)
10 = Solar valve (not active)
2
Accessory relay 1
1
10
–
1 = Circulation pump
2 = External pump
3 = Cylinder charging pump
4 = Extractor hood
5 = External solenoid valve
6 = External fault message
7 = Solar pump (not active)
8 = eBUS remote control (not active)
9 = Legionella protection pump (not active)
10 = Solar valve (not active)
2
English
¹Fault lists are only displayed, and can only be deleted, if faults have occurred.
24
Installation and maintenance instructions ecoTEC plus 0020200871_00
Appendix
Setting level
Values
Accessory relay 2
Contact data
Min.
Max.
1
10
Unit
–
–
Phone number
–
End the installation assistant?
–
–
Default
setting
Increment, select, explanation
1 = Circulation pump
2 = External pump
3 = Cylinder charging pump
4 = Extractor hood
5 = External solenoid valve
6 = External fault message
7 = Solar pump (not active)
8 = eBUS remote control (not active)
9 = Legionella protection pump (not active)
10 = Solar valve (not active)
2
0-9
–
Yes, No
–
¹Fault lists are only displayed, and can only be deleted, if faults have occurred.
C
Overview of diagnostics codes
Setting level
Values
Unit
Increment, select, explanation
Min.
Max.
d.00 Heating maximum output
–
–
kW
The maximum heating output varies
depending on the product.
→ Section "Technical data"
d.01 Pump overrun in heating
mode
1
60
min
d.02 Burner anti-cycling time
in heating mode
2
60
d.04 Water temperature in the
cylinder
d.05 Determined heating flow
set target temperature
Current value
Current value
Default setting
Own setting
→ Section
"Technical
data"
Adjustable
1
5
Adjustable
min
1
20
Adjustable
℃
–
–
Not
adjustable
℃
–
–
Not
adjustable
d.07 Set target temperature
for the domestic hot water
cylinder
Current value
℃
–
–
Not
adjustable
d.08 Status of the 230 V thermostat
Current value
–
0 = Room thermostat open (no heat
requirement)
1 = Room thermostat closed (heat
requirement)
–
Not
adjustable
d.09 Heating flow set target
temperature that is set on the
eBUS room thermostat
Current value
–
–
–
Not
adjustable
d.10 Status of the internal
pump in the heating circuit
Current value
–
off / on
–
Not
adjustable
d.11 Status of the heating circuit's shunt pump
Current value
–
off / on
–
Not
adjustable
d.13 Status of the hot water
circuit's circulation pump
Current value
–
off / on
–
Not
adjustable
d.16 Status of the 24 V room
thermostat
Current value
–
off = Heating off
on = Heating on
–
Not
adjustable
–
off = Flow temperature
on = Return temperature (adjustment
for underfloor heating. If you have activated the return temperature control,
the automatic heating output determination function is not active.)
0
Adjustable
d.17 Heating control
–
–
0020200871_00 ecoTEC plus Installation and maintenance instructions
25
Appendix
Setting level
Values
Unit
Increment, select, explanation
Default setting
Own setting
Min.
Max.
d.18 Pump overrun operating
mode
1
3
–
1 = Comfort (continuously operating
pump)
3 = Eco (intermittent pump mode –
for the dissipation of the residual heat
after hot water generation at an extremely low heat demand)
1
Adjustable
d.20 Maximum hot water set
target temperature
50
60
℃
1
50
Adjustable
d.23 Status of the heating demand
Current value
–
off = Heating off (Summer mode)
on = Heating on
–
Not
adjustable
d.24 Status of the pressure
monitor
0
1
–
off = Not switched
on = Switched
–
Not
adjustable
d.25 Status of the requirement
to reheat the cylinder or for
the hot water warm start from
the eBUS thermostat
Current value
–
off = Function deactivated
on = Function activated
–
Not
adjustable
d.27 Function of relay 1 (multifunctional module)
1
10
–
1 = Circulation pump
2 = External pump
3 = Cylinder charging pump
4 = Extractor hood
5 = External solenoid valve
6 = External fault message
7 = Solar pump (omitted)
8 = eBUS remote control
9 = Legionella protection pump
10 = Solar valve
1
Adjustable
d.28 Function of relay 2 (multifunctional module)
1
10
–
1 = Circulation pump
2 = External pump
3 = Cylinder charging pump
4 = Extractor hood
5 = External solenoid valve
6 = External fault message
7 = Solar pump (omitted)
8 = eBUS remote control
9 = Legionella protection pump
10 = Solar valve
2
Adjustable
d.31 Automatic filling device
0
2
–
0 = Manual
1 = Semi-automatic
2 = Automatic
0
Adjustable
d.33 Fan speed target value
Current value
rpm
Fan speed = Display value x 100
–
Not
adjustable
d.34 Value for the fan speed
Current value
rpm
Fan speed = Display value x 100
–
Not
adjustable
d.40 Heating flow temperature
Current value
℃
–
–
Not
adjustable
d.41 Heating return temperature
Current value
℃
–
–
Not
adjustable
d.43 Heating curve
0.2
4
d.45 Value for the base point
of the heating curve
15
30
d.47 Outside temperature
Current value
–
0.1
1.2
Adjustable
–
1
20
Adjustable
℃
–
–
Not
adjustable
d.50 Correction of the minimum fan speed
0
3000
rpm
1
Fan speed = Display value x 10
600
Adjustable
d.51 Correction of the maximum fan speed
-2500
0
rpm
1
Fan speed = Display value x 10
-1000
Adjustable
26
Installation and maintenance instructions ecoTEC plus 0020200871_00
Appendix
Setting level
Values
Unit
Increment, select, explanation
Default setting
Own setting
Min.
Max.
0
3
–
0 = Boiler's Legionella protection
function deactivated
3 = Hot water activated (target value
min. 60 °C)
0
Adjustable
d.60 Number of blocks by the
temperature sensor
Current value
–
–
–
Not
adjustable
d.61 Number of successful
ignitions
Current value
–
–
–
Not
adjustable
–
1
0
Adjustable
d.58 Solar circuit reheating
d.62 Night set-back
0
30
d.64 Average burner ignition
time
Current value
s
–
–
Not
adjustable
d.65 Maximum burner ignition
time
Current value
s
–
–
Not
adjustable
d.66 Activation of the warm
start function for hot water
–
–
off = Function deactivated
on = Function activated
1
Adjustable
d.67 Remaining burner anticycling time (setting under
d.02)
Current value
min
–
–
Not
adjustable
d.68 Number of unsuccessful
ignitions at 1st attempt
Current value
–
–
–
Not
adjustable
d.69 Number of unsuccessful
ignitions at 2nd attempt
Current value
–
–
–
Not
adjustable
–
d.71 Maximum heating flow set
target temperature
45
80
℃
1
75
Adjustable
d.75 Maximum cylinder reheating time
20
90
min
1
45
Adjustable
–
–
kW
1
→ Section "Technical data"
–
Adjustable
50
80
d.77 Max. cylinder reheating
d.78 DHW max. flow temperature
℃
1
–
Adjustable
d.80 Running time in heating
mode
Current value
h
–
–
Not
adjustable
d.81 Running time in DHW
mode
Current value
h
–
–
Not
adjustable
d.82 Number of burner ignitions in heating mode
Current value
–
Number of ignitions = Display value x
100
–
Not
adjustable
d.83 Number of burner ignitions in DHW mode
Current value
–
Number of ignitions = Display value x
100
–
Not
adjustable
Number of hours = Display value x 10
300
Not
adjustable
1
→ Section "Technical data"
–
Adjustable
–
off = Not connected
on = Connected
–
Not
adjustable
d.84 Maintenance in
0
3000
h
d.85 Increase in the min. output (heating and DHW mode)
–
–
kW
d.90 Status of the eBUS room
thermostat
Current value
d.93 Setting the product code
0
99
–
1
–
Adjustable
d.94 Delete fault list
0
1
–
off = No
on = Yes
–
Adjustable
d.95 Software versions
–
–
–
1 = Main PCB
2 = Interface PCB
–
Adjustable
d.96 Reset to factory setting
–
–
–
0 = No
1 = Yes
–
Adjustable
10
75
℃
1
10
Adjustable
d.128 Heating minimum target
value
0020200871_00 ecoTEC plus Installation and maintenance instructions
27
Appendix
Setting level
Values
d.129 Hot water minimum target value
Min.
Max.
35
(combination
unit)
45
(pure
boiler)
60
Unit
℃
Increment, select, explanation
1
Default setting
35
Own setting
Adjustable
Status codes – Overview
D
Status code
Meaning
Displays in heating mode
S. 0
Heating mode: No requirement
S.01
Heating mode: Advance fan operation
S.02
Heating mode: Pump pre-run
S.03
Heating mode: Burner ignition
S.04
Heating mode: Burner on
S.05
Heating mode: Pump/fan overrun
S.06
Heating mode: Fan overrun
S.07
Heating mode: Pump overrun
S.08
Heating mode: Temporary shutdown after heating procedure
Display in hot water handling mode with cylinder
S.20
Hot water handling mode: Requirement
S.21
Hot water handling mode: Advance fan operation
S.22
Hot water handling mode: Pump pre-run
S.23
Hot water handling mode: Burner ignition
S.24
DHW mode: Burner on
S.25
DHW mode: Pump/fan overrun
S.26
DHW mode: Fan overrun
S.27
DHW mode: Pump overrun
S.28
Hot water handling mode: Temporary shutdown of the burner
S.30
Room thermostat is blocking heating mode.
S.31
No heating demand: Summer mode, eBUS controller, waiting period
S.32
Fan waiting time: Fan speed outside of the tolerance values
S.34
Frost protection active
S.39
Underfloor heating contact open
S.42
Flue non-return flap closed
S.46
Frost protection mode (Comfort): Minimum load
S.53
Product in waiting period/operation block function due to low water pressure (flow/return spread too large)
S.54
Waiting period: Low water pressure in the circuit (flow/return spread too large)
S.88
Product purging active
S.91
Maintenance: Demo mode
S.96
Automatic test programme: Return temperature sensor, heating demands blocked.
S.98
Automatic test programme: Return temperature sensor, heating demands blocked.
S.99
Internal automatic test programmes
S.108
Purging the combustion chamber, fan in operation
S.109
Product's standby mode activated
Other displays
28
Installation and maintenance instructions ecoTEC plus 0020200871_00
Appendix
E
Overview of fault codes
Code
Meaning
Cause
F.00
Flow temperature sensor interruption
NTC plug not plugged in or has come loose, multiple plug on the PCB
not plugged in correctly, interruption in cable harness, NTC defective
F.01
Return temperature sensor interruption
NTC plug not plugged in or has come loose, multiple plug on the PCB
not plugged in correctly, interruption in cable harness, NTC defective
F.10
Flow NTC short circuit
NTC defective, short circuit in cable harness, cable/casing
F.11
Return NTC short circuit
NTC defective, short circuit in cable harness, cable/casing
F.13
Warm start sensor/cylinder sensor short circuit
NTC defective, short circuit in cable harness, cable/casing
F.22
Safety switch-off: Low water pressure
No or insufficient water in the product, water pressure sensor defective,
cable to pump or water pressure sensor loose/not connected/defective
F.23
Safety switch-off: Temperature difference too
great
Pump blocked, insufficient pump output, air in product, flow and return
NTC connected the wrong way round
F.24
Safety switch-off: Temperature rise too fast
Pump blocked, insufficient pump output, air in product, system pressure
too low, non-return valve blocked/incorrectly installed
F.25
Safety switch-off: Flue gas temperature too high
Break in plug connection for optional flue gas safety temperature limiter
(STB), break in cable harness
F.27
Safety switch-off: Flame simulation
Moisture on the electronics, electronics (flame monitor) defective, gas
solenoid valve leaking
F.28
Failure during start-up: Ignition unsuccessful
Gas meter defective or gas pressure monitor has triggered, air in gas,
gas flow pressure too low, thermal isolator device (TAE) has triggered,
condensate duct blocked, incorrect gas restrictor, incorrect spare part
gas valve, fault on the gas valve, multiple plug on PCB incorrectly
plugged in, break in cable harness, ignition system (ignition transformer,
ignition cable, ignition plug, ignition electrode) defective, ionisation
current interrupted (cable, electrode), incorrect earthing of product,
electronics defective
F.29
Failure during operation: Re-ignition unsuccessful
Gas supply temporarily stopped, flue gas recirculation, condensate duct
blocked, defective earthing of product, ignition transformer has spark
failure
F.32
Fan fault
Plug on fan not correctly plugged in, multiple plug on PCB not correctly
plugged in, break in cable harness, fan blocked, Hall sensor defective,
electronics defective
F.49
Fault: eBUS
Short circuit on eBUS, eBUS overload or two power supplies with different polarities on the eBUS
F.61
Fault: Gas valve regulation
–
–
–
Short circuit/short to earth in cable harness for the gas valve
Gas valve defective (coils shorted to earth)
Electronics defective
F.62
Fault: Gas valve switch-off delay
–
–
–
–
Delayed shutdown of gas valve
Delayed extinguishing of flame signal
Gas valve leaking
Electronics defective
F.63
Fault: EEPROM
Electronics defective
F.64
Fault: Electronics/NTC
Flow or return NTC short circuited, electronics defective
F.65
Fault: Electronics temp.
Electronics overheating due to external influences, electronics defective
F.67
Fault: Electronics/flame
Implausible flame signal, electronics defective
F.68
Fault: Unstable flame signal
Air in gas, gas flow pressure too low, incorrect air ratio, condensate
duct blocked, incorrect gas restrictor, ionisation flow interruption (cable,
electrode), flue gas recirculation, condensate duct
F.70
Invalid device specific number (DSN)
If spare parts fitted: Display and PCB replaced at same time and DSN
not reset, incorrect or missing output range coding resistance
F.71
Flow NTC fault
Flow temperature sensor signalling constant value:
–
–
F.72
Flow/return NTC fault
Flow temperature sensor incorrectly positioned at supply pipe
Flow temperature sensor defective
Flow/return NTC temperature difference too great → flow and/or return
temperature sensor defective
0020200871_00 ecoTEC plus Installation and maintenance instructions
29
Appendix
Code
Meaning
Cause
F.73
Water pressure sensor signal in the wrong range
(too low)
Interruption/short circuit of water pressure sensor, interruption/short
circuit to GND in supply line to water pressure sensor or water pressure
sensor defective
F.74
Water pressure sensor signal outside correct
range (too high)
Line to water pressure sensor has a short circuit to 5 V/24 V or internal
fault in the water pressure sensor
F.75
Fault: No pressure change detection when starting pump
Water pressure sensor and/or pump defective, air in the heating installation, insufficient water in the product; check adjustable bypass, connect
external expansion vessel to the return
F.76
Overheating protection on primary heat exchanger has responded
Cable or cable connections for safety fuse in primary heat exchanger or
primary heat exchanger defective
F.77
Fault: Flue non-return flap/condensate pump
No response from flue non-return flap or condensate pump defective
F.83
Fault: Flow and/or return temperature sensor
temperature change
When the burner starts, the temperature change registered at the flow
and/or return temperature sensor is non-existent or too small.
–
–
Insufficient water in product
Flow or return temperature sensor not in correct position at pipe
F.85
Fault: Flow and return temperature sensors
incorrectly installed
The flow and/or return temperature sensors have been installed on the
same pipe/incorrect pipe
F.87
Ignition transformer not connected
Ignition transformer plug not plugged in or has come loose, multiple
plug on the PCB not plugged in correctly, interruption in cable harness,
electronics defective
F.88
Gas valve not connected
Gas valve plug not plugged in or has come loose, multiple plug on the
PCB not plugged in correctly, interruption in cable harness, electronics
defective
F.89
Incorrect pump detected
Unsuitable pump connected, PWM plug not plugged in or has come
loose, multiple plug on the PCB not plugged in correctly, interruption in
cable harness, electronics defective
con
No communication with the PCB
Communication fault between display and PCB in the electronics box
30
Installation and maintenance instructions ecoTEC plus 0020200871_00
Appendix
F
Connection diagram
X51
2
X51
Burner off
X106
3
1
X51
X32
X35
Burner
off
24V=
RT
–
13
5
6
5
24V
4
15
3
16
1
2
3
4
1
9
M
6
5
1
X22
X20
4
X20
+
BUS
X41
X40
X106
X51
eBUS
24V
7
230V~
X14
X30
L
N
8
X21
X21
X1
X1
L
N
L
9
N
10
11
RT
230V~
X12
RT
X14
L
N
L
N
X12
1
Main PCB
7
Gas valve
2
Interface PCB
8
Monitoring electrode
3
Control system
9
Room thermostat
4
Temperature sensor in the heating flow
10
Main power supply
5
Temperature sensor in the heating return
11
Ignition electrode
6
Fan
0020200871_00 ecoTEC plus Installation and maintenance instructions
31
Appendix
G
Connection diagram, 30 kW
X51
2
X51
Burner off
X106
3
1
X51
X32
X35
Burner
off
24V=
RT
–
13
5
6
5
24V
4
15
3
16
1
2
3
4
1
9
M
6
5
1
X22
X20
4
X20
+
BUS
X41
X40
X106
X51
eBUS
24V
7
230V~
X14
X30
L
N
8
X21
X21
X1
X1
L
N
L
9
N
10
X12
1
Main PCB
7
Gas valve
2
Interface PCB
8
Monitoring electrode
3
Control system
9
Room thermostat
4
Temperature sensor in the heating flow
10
Main power supply
5
Temperature sensor in the heating return
11
Ignition electrode
6
Fan
32
11
RT
230V~
X12
RT
X14
L
N
L
N
Installation and maintenance instructions ecoTEC plus 0020200871_00
Appendix
H
Opening in the flue pipe
P
I
Q
Q
T
Q
S
Q
R
F
Q
D, E
G
O
C
A
I
M
B
L
N
N
H
H
M
J
K
H.1
Positioning of the opening of a fan-supported flue gas pipe
Installation site
Minimum dimensions
A
Directly below an opening, air bricks, opening windows, etc., that can be opened.
300 mm
B
Above an opening, air bricks, opening windows, etc., that can be opened.
300 mm
C
Horizontally to an opening, air bricks, opening windows, etc., that can be opened.
300 mm
D
Below temperature-sensitive building components, e.g. plastic gutters, down pipes or wastewater
pipes
75 mm
E
Below eaves
200 mm
F
Below balconies or car port roofs
200 mm
G
From vertical wastewater pipes or down pipes
150 mm
H
From external or internal corners
200 mm
I
Above floors, roofs or balconies
300 mm
J
From a surface facing a terminal
600 mm
K
From a terminal facing a terminal
1,200 mm
L
From an opening in the car port (e.g. door, window) which leads into the dwelling
1,200 mm
M
Vertical from a terminal on the same wall
1,500 mm
N
Horizontal from a terminal on the same wall
300 mm
O
From the wall on which the terminal has been installed
0 mm
P
From a vertical structure on the roof
N/A
Q
Above the roof area
300 mm
R
Horizontal from adjacent windows on pitched or flat roofs
600 mm
S
Above adjacent windows on pitched or flat roofs
600 mm
T
Below adjacent windows on pitched or flat roofs
2,000 mm
0020200871_00 ecoTEC plus Installation and maintenance instructions
33
Appendix
H.2
Text from BS 5440-1 on fan-supported flue gas pipes
BS 5440–1: It is recommended that the fanned flue gas system terminal is positioned as follows:
–
–
–
–
At least 2 m from an opening in the building directly opposite, and
So that the combustion products are not discharged directly across a property boundary.
Dimensions D, E, F and G: These clearances may be reduced to 25 mm without affecting the performance of the boiler.
In order to ensure that the condensate vapour plume does not damage adjacent surfaces, the terminal should be extended as shown.
Dimension H: This clearance may be reduced to 25 mm without adversely affecting the performance of the boiler. However, in order to ensure that the condensate vapour plume does not damage adjacent surfaces, a clearance of 300 mm is
preferred. For IE, recommendations are given in the current issue of the IS 813.
H.3
Opening of the flue pipe below eaves and balconies
Balcony/eaves
Gutter
Adequately secured
air/flue gas pipe
34
The flue pipe must
protrude beyond any overhang
Installation and maintenance instructions ecoTEC plus 0020200871_00
Appendix
I
Commissioning Checklist
Benchmark Commissioning and
Servicing Section
It is a requirement that the boiler is installed and commissioned to the
completed in full.
www.centralheating.co.uk
© Heating and Hotwater Industry Council (HHIC)
0020200871_00 ecoTEC plus Installation and maintenance instructions
35
Appendix
GAS BOILER SYSTEM COMMISSIONING CHECKLIST
This Commissioning Checklist is to be completed in full by the competent person who commissioned the boiler as a means of demonstrating
compliance with the appropriate Building Regulations and then handed to the customer to keep for future reference.
CONTROLS
Optimum start control
Fitted
Fitted
Fitted
Fitted
ALL SYSTEMS
Yes
Yes
CENTRAL HEATING MODE
OR
mbar
mbar
OR
COMBINATION BOILERS ONLY
Yes
Yes
DOMESTIC HOT WATER MODE
OR
mbar OR
mbar
Yes
Temperature
CONDENSING BOILERS ONLY
Yes
ALL INSTALLATIONS
AND
²
Ratio
AND
²
Ratio
Yes
Yes
Yes
Yes
36
Installation and maintenance instructions ecoTEC plus 0020200871_00
Appendix
SERVICE RECORD
It is recommended that your heating system is serviced regularly and that the appropriate Service Interval Record is completed.
Service Provider
SERVICE 01
SERVICE 02
AND
AND
²%
²%
SERVICE 03
AND
AND
²%
²%
SERVICE 04
AND
AND
²%
²%
SERVICE 05
AND
AND
²%
²%
SERVICE 06
AND
AND
²%
²%
SERVICE 07
AND
AND
²%
²%
SERVICE 08
AND
AND
²%
²%
SERVICE 09
AND
AND
²%
²%
SERVICE 10
AND
AND
²%
²%
0020200871_00 ecoTEC plus Installation and maintenance instructions
AND
AND
²%
²%
37
Appendix
PRIOR TO CO AND COMBUSTION RATIO CHECK
The boiler manufacturer’s installation instructions should have been followed, gas type verified and gas
supply pressure/rate checked as required prior to commissioning.
As part of the installation process, especially where a flue has been fitted by persons other than the
boiler installer, visually check the integrity of the whole flue system to confirm that all components are
correctly assembled, fixed and supported. Check that manufacturer’s max. flue lengths have not been
exceeded and all guidance has been followed (e.g. Gas Safe Technical Bulletin TB008).
The flue gas analyser should be of the correct type, as specified by BS 7967
Prior to its use, the flue gas analyser should have been maintained and calibrated as specified by the
manufacturer. The installer must have the relevant competence for use of the analyser.
Check and zero the analyser IN FRESH AIR as per analyser manufacturer’s instructions.
NOTE
THE AIR GAS RATIO VALVE IS FACTORY
SET AND MUST NOT BE ADJUSTED
DURING COMMISSIONING UNLESS THIS
ACTION IS RECOMMENDED FOLLOWING
CONTACT WITH THE MANUFACTURER.
If any such adjustment is recommended and
further checking of the boiler is required the
installer/service engineer must be competent
to carry out this work and to use the flue gas
analyser accordingly.
If the boiler requires conversion to operate with
a different gas family (e.g. conversion from
natural gas to LPG) separate guidance will be
provided by the boiler manufacturer
SET BOILER TO MAXIMUM RATE
In accordance with boiler instructions, set boiler to operate at max. rate
(full load condition). Allow sufficient time for combustion to stabilise.
NOTE - Do not insert analyser probe during this period to avoid
possible “flooding” of sensor.
CARRY OUT FLUE INTEGRITY CHECK USING ANALYSER
Insert analyser probe into air inlet test point and allow readings to stabilise.
NOTE - where no air inlet test point is provided then a flue integrity check
with the analyser is not possible. The installer should verify that flue
integrity has been visually checked in accordance with the “Prior to
CO and combustion ratio check” box above before proceeding to the
“Check CO and combustion ratio at maximum rate” stage below.
VERIFY FLUE INTEGRITY
Analyser readings indicate that combustion products
and inlet air must be mixing. Further investigation of
the flue is therefore required.
Check that flue components are assembled, fixed
and supported as per boiler/flue manufacturer’s
instructions.
Check that flue and flue terminal are not obstructed.
NO
Is
O2 • 20.6%
and
CO2 < 0.2%
YES
Is
O2 • 20.6%
and
CO2 < 0.2%
YES
NO
TURN OFF APPLIANCE AND CALL
MANUFACTURER’S TECHNICAL HELPLINE
FOR ADVICE.
THE APPLIANCE MUST NOT BE
COMMISSIONED UNTIL PROBLEMS ARE
IDENTIFIED AND RESOLVED.
CHECK CO AND COMBUSTION RATIO AT MAX. RATE
With boiler still set at maximum rate, insert analyser probe into flue gas
sampling point. Allow readings to stabilise before recording.
NOTE - If no flue gas sampling point is present and the correct procedure is
not specified in the manual, consult boiler manufacturer for guidance.
NO
Check all seals around the appliance burner,
internal flue seals, door and case seals.
Rectify where necessary.
Is
CO less than
335ppm
and
CO/CO2 ratio less
than 0.004
Is
CO less than
350ppm and
CO/CO2 ratio
less than 0.004
YES
YES
SET BOILER TO MINIMUM RATE
In accordance with boiler instructions, set boiler to operate at minimum rate (to
minimum load condition). Allow sufficient time for combustion to stabilise.
NOTE - If manufacturer’s instructions do not specify how to set boiler to minimum
rate contact Technical Helpline for advice.
NO
CHECK CO AND COMBUSTION RATIO AT MINIMUM RATE
With boiler still set at minimum rate, insert analyser probe into flue gas sampling
point. Allow readings to stabilise before recording.
NOTE - If no flue gas sampling point is present and the correct procedure is not
specified in the manual, consult boiler manufacturer for guidance.
TURN OFF APPLIANCE AND CALL
MANUFACTURER’S TECHNICAL HELPLINE
FOR ADVICE.
THE APPLIANCE MUST NOT BE
COMMISSIONED UNTIL PROBLEMS ARE
IDENTIFIED AND RESOLVED. IF
COMMISSIONING CANNOT BE FULLY
COMPLETED, THE APPLIANCE MUST BE
DISCONNECTED FROM THE GAS SUPPLY IN
ACCORDANCE WITH THE GSIUR.
NOTE: Check and record CO and combustion ratio
at both max. and min. rate before contacting the
manufacturer.
38
NO
Is
CO less than
350ppm and
CO/CO2 ratio
less than 0.004
YES
BOILER IS OPERATING SATISFACTORILY
no further actions required.
Ensure test points are capped, boiler case is correctly replaced and
all other commissioning procedures are completed.
Complete Benchmark Checklist, recording CO and combustion ratio
readings as required.
Installation and maintenance instructions ecoTEC plus 0020200871_00
Appendix
J
Technical data
Technical data – Heating
VU 126/6-5 OV (HGB) ecoTEC plus
VU 156/6-5 OV (HGB) ecoTEC plus
VU 186/6-5 OV (HGB) ecoTEC plus
VU 246/6-5 OV (HGB) ecoTEC plus
Max. flow temperature adjustment
range (default setting: 75 °C)
10 … 80 ℃
10 … 80 ℃
10 … 80 ℃
10 … 80 ℃
Maximum permissible pressure
0.3 MPa
(3.0 bar)
0.3 MPa
(3.0 bar)
0.3 MPa
(3.0 bar)
0.3 MPa
(3.0 bar)
Nominal water flow (ΔT = 20 K)
530 l/h
655 l/h
788 l/h
1,059 l/h
Nominal water flow (ΔT = 30 K)
353 l/h
436 l/h
525 l/h
706 l/h
Approximate value for the
condensate volume (pH value
between 3.5 and 4.0) at 50/30 °C
1.23 l/h
1.53 l/h
1.84 l/h
2.47 l/h
VU 306/6-5 OV (HGB) ecoTEC plus
Max. flow temperature adjustment
range (default setting: 75 °C)
10 … 80 ℃
Maximum permissible pressure
0.3 MPa
(3.0 bar)
Nominal water flow (ΔT = 20 K)
1,313 l/h
Nominal water flow (ΔT = 30 K)
876 l/h
Approximate value for the
condensate volume (pH value
between 3.5 and 4.0) at 50/30 °C
3.06 l/h
Technical data – G20 power/loading G20
VU 126/6-5 OV (HGB) ecoTEC plus
VU 156/6-5 OV (HGB) ecoTEC plus
VU 186/6-5 OV (HGB) ecoTEC plus
VU 246/6-5 OV (HGB) ecoTEC plus
Maximum heat output
12 kW
15 kW
18 kW
24 kW
Effective output range (P)
at 40/30 °C
4.8 … 13.0 kW
4.8 … 16.2 kW
5.3 … 19.5 kW
6.5 … 26.2 kW
Effective output range (P)
at 50/30 °C
4.7 … 12.8 kW
4.7 … 15.9 kW
5.2 … 19.1 kW
6.3 … 25.7 kW
Effective output range (P)
at 80/60 °C
4.5 … 12.3 kW
4.5 … 15.2 kW
5.0 … 18.3 kW
6.1 … 24.6 kW
Domestic hot water heat
output (P)
4.4 … 18.0 kW
4.4 … 18.0 kW
5.0 … 25.2 kW
6.0 … 30.0 kW
Maximum heat input –
heating (Q max.)
12.3 kW
15.3 kW
18.4 kW
24.7 kW
Minimum heat input – heating (Q min.)
5.0 kW
4.5 kW
5.0 kW
6.1 kW
Maximum heat input – hot
water (Q max.)
18.4 kW
18.4 kW
25.7 kW
30.6 kW
Minimum heat input – hot
water (Q min.)
4.5 kW
4.5 kW
5.1 kW
6.1 kW
VU 306/6-5 OV (HGB) ecoTEC plus
Maximum heat output
30 kW
Effective output range (P)
at 40/30 °C
7.6 … 32.4 kW
Effective output range (P)
at 50/30 °C
7.5 … 31.8 kW
Effective output range (P)
at 80/60 °C
7.2 … 30.5 kW
Domestic hot water heat
output (P)
7.1 … 35.0 kW
0020200871_00 ecoTEC plus Installation and maintenance instructions
39
Appendix
VU 306/6-5 OV (HGB) ecoTEC plus
Maximum heat input –
heating (Q max.)
30.6 kW
Minimum heat input – heating (Q min.)
7.2 kW
Maximum heat input – hot
water (Q max.)
35.7 kW
Minimum heat input – hot
water (Q min.)
7.2 kW
Technical data – General
VU 126/6-5 OV (HGB) ecoTEC plus
VU 156/6-5 OV (HGB) ecoTEC plus
VU 186/6-5 OV (HGB) ecoTEC plus
VU 246/6-5 OV (HGB) ecoTEC plus
Gas category
I2H
I2H
I2H
I2H
Diameter of the gas pipe
1/2 inch
1/2 inch
1/2 inch
1/2 inch
Diameter of the heating connections
3/4 inch
3/4 inch
3/4 inch
3/4 inch
Expansion relief valve connector
(min.)
15 mm
15 mm
15 mm
15 mm
Condensate drain pipework (min.)
21.5 mm
21.5 mm
21.5 mm
21.5 mm
G20 gas supply pressure
2.0 kPa
2.0 kPa
2.0 kPa
2.0 kPa
Gas flow at P max. – hot water
(G20)
1.9 m³/h
1.9 m³/h
2.7 m³/h
3.2 m³/h
Gas flow at P max. – heating mode
(G20)
1.3 m³/h
1.6 m³/h
1.9 m³/h
2.6 m³/h
Gas flow at P min. (G20)
0.480 m³/h
0.480 m³/h
0.533 m³/h
0.646 m³/h
CE number (PIN)
CE-0063CP3646
CE-0063CP3646
CE-0063CP3646
CE-0063CP3646
Flue gas mass rate in heating
mode at P min.
2.08 g/s
2.08 g/s
2.31 g/s
2.80 g/s
Flue gas mass rate in heating
mode at P max.
5.5 g/s
6.9 g/s
8.3 g/s
11.1 g/s
Flue gas mass rate in hot water
handling mode at P max.
8.3 g/s
8.3 g/s
11.6 g/s
13.8 g/s
Flue gas temperature (80 °C/60 °C)
at P max.
55 ℃
55 ℃
60 ℃
77 ℃
Flue gas temperature (80 °C/60 °C)
at P min.
55 ℃
55 ℃
55 ℃
55 ℃
Flue gas temperature (50 °C/30 °C)
at P max.
43 ℃
48 ℃
51 ℃
60 ℃
Flue gas temperature (50 °C/30 °C)
at P min.
32 ℃
32 ℃
34 ℃
35 ℃
Flue gas temperature in hot water
handling mode
71 ℃
71 ℃
69 ℃
68 ℃
Flue gas temperature when overheating
105 ℃
105 ℃
105 ℃
95 ℃
Released system types
C13, C33, C43, C53
C13, C33, C43, C53
C13, C33, C43, C53
C13, C33, C43, C53
Nominal efficiency at 80/60 °C
99.6 %
99.6 %
99.6 %
99.6 %
Nominal efficiency at 50/30 °C
104.0 %
104.0 %
104.0 %
104.0 %
Nominal efficiency at 40/30 °C
106.0 %
106.0 %
106.0 %
106.0 %
Nominal efficiency in partial load
operation (30%) at 40/30 °C
108.5 %
108.5 %
108.5 %
108.5 %
NOx class
5
5
5
5
Product dimensions, width
375 mm
375 mm
375 mm
375 mm
Product dimensions, depth
280 mm
280 mm
280 mm
280 mm
Product dimensions, height
600 mm
600 mm
600 mm
600 mm
40
Installation and maintenance instructions ecoTEC plus 0020200871_00
Appendix
VU 126/6-5 OV (HGB) ecoTEC plus
VU 156/6-5 OV (HGB) ecoTEC plus
VU 186/6-5 OV (HGB) ecoTEC plus
VU 246/6-5 OV (HGB) ecoTEC plus
Net weight
23 kg
23 kg
23 kg
23 kg
Weight when filled with water
27 kg
27 kg
27 kg
28 kg
VU 306/6-5 OV (HGB) ecoTEC plus
Gas category
I2H
Diameter of the gas pipe
1/2 inch
Diameter of the heating connections
3/4 inch
Expansion relief valve connector
(min.)
15 mm
Condensate drain pipework (min.)
21.5 mm
G20 gas supply pressure
2.0 kPa
Gas flow at P max. – hot water
(G20)
3.8 m³/h
Gas flow at P max. – heating mode
(G20)
3.2 m³/h
Gas flow at P min. (G20)
0.762 m³/h
CE number (PIN)
CE-0063CP3646
Flue gas mass rate in heating
mode at P min.
3.30 g/s
Flue gas mass rate in heating
mode at P max.
13.8 g/s
Flue gas mass rate in hot water
handling mode at P max.
16.1 g/s
Flue gas temperature (80 °C/60 °C)
at P max.
86 ℃
Flue gas temperature (80 °C/60 °C)
at P min.
56 ℃
Flue gas temperature (50 °C/30 °C)
at P max.
60 ℃
Flue gas temperature (50 °C/30 °C)
at P min.
37 ℃
Flue gas temperature in hot water
handling mode
75 ℃
Flue gas temperature when overheating
104 ℃
Released system types
C13, C33, C43, C53
Nominal efficiency at 80/60 °C
99.6 %
Nominal efficiency at 50/30 °C
104.0 %
Nominal efficiency at 40/30 °C
106.0 %
Nominal efficiency in partial load
operation (30%) at 40/30 °C
108.5 %
NOx class
5
Product dimensions, width
375 mm
Product dimensions, depth
280 mm
Product dimensions, height
600 mm
Net weight
23 kg
Weight when filled with water
28 kg
0020200871_00 ecoTEC plus Installation and maintenance instructions
41
Appendix
Technical data – Electrics
VU 126/6-5 OV (HGB) ecoTEC plus
Electric connection
VU 156/6-5 OV (HGB) ecoTEC plus
VU 186/6-5 OV (HGB) ecoTEC plus
VU 246/6-5 OV (HGB) ecoTEC plus
230 V / 50 Hz
230 V / 50 Hz
230 V / 50 Hz
230 V / 50 Hz
T2/2A, 250V
T2/2A, 250V
T2/2A, 250V
T2/2A, 250V
Max. electrical power consumption
65 W
65 W
66 W
75 W
Standby electrical power consumption
2W
2W
2W
2W
IPX4D
IPX4D
IPX4D
IPX4D
Built-in fuse (slow-blow)
Level of protection
VU 306/6-5 OV (HGB) ecoTEC plus
Electric connection
Built-in fuse (slow-blow)
230 V / 50 Hz
T2/2A, 250V
Max. electrical power consumption
60 W
Standby electrical power consumption
2W
Level of protection
42
IPX4D
Installation and maintenance instructions ecoTEC plus 0020200871_00
Index
Index
A
Air index setting................................................................... 16
Air/flue pipe ......................................................................... 11
Air/flue pipe, installed ............................................................ 4
Article number ....................................................................... 6
Auxiliary relay ...................................................................... 13
B
Burner anti-cycling time....................................................... 17
C
Calling up the fault memory................................................. 19
CE label ................................................................................. 6
Check programmes ............................................................. 14
Checking the burner ............................................................ 18
Checking the CO₂ content ................................................... 16
Cleaning the condensate siphon ......................................... 19
Cleaning the heat exchanger .............................................. 18
Combustion air ...................................................................... 4
Completing inspection work ................................................ 19
Completing maintenance work ............................................ 19
Completing repair work ....................................................... 21
Completing, repair work ...................................................... 21
Condensate drain pipework................................................. 10
Contact details..................................................................... 13
Controller............................................................................. 12
Corrosion............................................................................... 4
D
Decommissioning ................................................................ 21
Decommissioning the product ............................................. 21
Documents ............................................................................ 6
Draining the product ............................................................ 19
E
Electricity ............................................................................... 4
Ending, installation assistant ............................................... 13
F
Fault codes.................................................................... 19, 29
Filling mode ......................................................................... 13
Filling the condensate siphon.............................................. 15
Flue gas route ....................................................................... 4
Front casing, closed .............................................................. 4
Frost ...................................................................................... 5
H
Handing over to the operator............................................... 17
Heating partial load ............................................................. 13
Hot water temperature......................................................... 13
I
Identification plate ................................................................. 6
If you smell gas ..................................................................... 3
Inspection work ............................................................. 17, 22
Installation assistant, ending ............................................... 13
Installation assistants, restarting ......................................... 14
Installation site....................................................................... 4
Installer level, calling up ...................................................... 12
Installing the front casing....................................................... 9
Installing the side section ...................................................... 9
Intended use.......................................................................... 3
L
Language ............................................................................ 13
M
Mains connection ................................................................ 11
Maintenance work ......................................................... 17, 22
0020200871_00 ecoTEC plus Installation and maintenance instructions
Minimum clearance ............................................................... 8
Multi-functional module ....................................................... 13
O
Operating concept ............................................................... 12
P
Power supply....................................................................... 11
Preparing the repair work .................................................... 19
Preparing, repair work ......................................................... 19
R
Regulations ........................................................................... 5
Removing the air intake pipe............................................... 17
Removing the burner........................................................... 17
Removing the flue pipe........................................................ 17
Removing the gas-air mixture unit....................................... 17
Removing the side section .................................................... 9
Replacing the burner ........................................................... 19
Replacing the heat exchanger............................................. 20
Replacing the main PCB ..................................................... 20
Resetting the burner anti-cycling time ................................. 17
S
Safety device......................................................................... 4
Schematic drawing ................................................................ 4
Serial number ........................................................................ 6
Setting the burner anti-cycling time ..................................... 17
Setting the CO₂ content....................................................... 16
Spare parts.......................................................................... 17
Starting, installation assistants ............................................ 14
Status codes........................................................................ 12
Supply of combustion air ....................................................... 4
Switching on the product ..................................................... 15
T
Target feed temperature...................................................... 13
Telephone number, competent person ............................... 13
Test programmes ................................................................ 14
Tool ....................................................................................... 5
Transport ............................................................................... 3
Transporting .......................................................................... 7
Treating the heating water .................................................. 14
U
Unloading the box ................................................................. 7
Unpacking the product .......................................................... 7
User interface, replacing the PCB ....................................... 21
V
Voltage .................................................................................. 4
W
Wall-mounting the product .................................................... 8
Weight ................................................................................... 8
43
0020200871
0020200871_00B5 22.06.2015
Vaillant Ltd.
Nottingham Road Belper Derbyshire DE56 1JT
Telephone 03 30 100‑34 61 Telephone (renewables) 02 07 022‑09 28
Vaillant Service Solutions 03 30 100‑31 43 Spares Technical Enquiries 177 359 66 15
[email protected][email protected]
www.vaillant.co.uk
© These instructions, or parts thereof, are protected by copyright and may be reproduced or distributed only with
the manufacturer's written consent.

advertisement

Was this manual useful for you? Yes No
Thank you for your participation!

* Your assessment is very important for improving the workof artificial intelligence, which forms the content of this project

Related manuals

Download PDF

advertisement