EPRI Feasibility Study for an Integrated Gasification Combined Cycle Facility at a Texas Site

Feasibility Study for an Integrated Gasification
Combined Cycle Facility at a Texas Site
1014510
Feasibility Study for an Integrated
Gasification Combined Cycle
Facility at a Texas Site
1014510
Technical Update, October 2006
Cosponsor
CPS Energy
145 Navarro
San Antonio, TX 78296
Project Manager
J. Kosub
EPRI Project Manager
G. Booras
ELECTRIC POWER RESEARCH INSTITUTE
3420 Hillview Avenue, Palo Alto, California 94304-1338
▪ PO Box 10412, Palo Alto, California 94303-0813 ▪ USA
800.313.3774
▪ 650.855.2121 ▪ [email protected] ▪ www.epri.com
DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITIES
THIS DOCUMENT WAS PREPARED BY THE ORGANIZATION(S) NAMED BELOW AS AN
ACCOUNT OF WORK SPONSORED OR COSPONSORED BY THE ELECTRIC POWER RESEARCH
INSTITUTE, INC. (EPRI). NEITHER EPRI, ANY MEMBER OF EPRI, ANY COSPONSOR, THE
ORGANIZATION(S) BELOW, NOR ANY PERSON ACTING ON BEHALF OF ANY OF THEM:
(A) MAKES ANY WARRANTY OR REPRESENTATION WHATSOEVER, EXPRESS OR IMPLIED, (I)
WITH RESPECT TO THE USE OF ANY INFORMATION, APPARATUS, METHOD, PROCESS, OR
SIMILAR ITEM DISCLOSED IN THIS DOCUMENT, INCLUDING MERCHANTABILITY AND FITNESS
FOR A PARTICULAR PURPOSE, OR (II) THAT SUCH USE DOES NOT INFRINGE ON OR
INTERFERE WITH PRIVATELY OWNED RIGHTS, INCLUDING ANY PARTY'S INTELLECTUAL
PROPERTY, OR (III) THAT THIS DOCUMENT IS SUITABLE TO ANY PARTICULAR USER'S
CIRCUMSTANCE; OR
(B) ASSUMES RESPONSIBILITY FOR ANY DAMAGES OR OTHER LIABILITY WHATSOEVER
(INCLUDING ANY CONSEQUENTIAL DAMAGES, EVEN IF EPRI OR ANY EPRI REPRESENTATIVE
HAS BEEN ADVISED OF THE POSSIBILITY OF SUCH DAMAGES) RESULTING FROM YOUR
SELECTION OR USE OF THIS DOCUMENT OR ANY INFORMATION, APPARATUS, METHOD,
PROCESS, OR SIMILAR ITEM DISCLOSED IN THIS DOCUMENT.
ORGANIZATION(S) THAT PREPARED THIS DOCUMENT
Burns & McDonnell Engineering Co. Inc.
This is an EPRI Technical Update report. A Technical Update report is intended as an informal report of continuing research, a meeting, or a topical study. It is not a final EPRI technical report.
NOTE
For further information about EPRI, call the EPRI Customer Assistance Center at 800.313.3774 or e-mail [email protected]
Electric Power Research Institute and EPRI are registered service marks of the Electric Power
Research Institute, Inc.
Copyright © 2006 Electric Power Research Institute, Inc. All rights reserved.
CITATIONS
This report was prepared by
Burns & McDonnell
9400 Ward Parkway
Kansas City, MO 64114
Principal Investigator
J. Schwarz
This report describes research sponsored by the Electric Power Research Institute (EPRI) and
CPS Energy.
This publication is a corporate document that should be cited in the literature in the following manner:
Feasibility Study for an Integrated Gasification Combined Cycle Facility at a Texas Site. EPRI,
Palo Alto, CA: 2006. 1014510. iii
PRODUCT DESCRIPTION
Interest in integrated gasification combined cycle technology (IGCC) has grown sharply since the passage of the Energy Policy Act in 2005. Many new projects are being planned since the
AEP and Duke 600 MW IGCC plants were announced nearly two years ago. This report compares the cost and performance of IGCC with a supercritical pulverized coal plant (SCPC) based on lower rank PRB coal. The IGCC options included 100% PRB and 50/50 PRB/petcoke cases. The addition of CO
2
capture equipment was also evaluated as a retrofit for the 100% PRB
IGCC and SCPC facilities.
Results and Findings
The net plant heat rates for the IGCC and SCPC plants without CO
2
capture are similar, with the
100% PRB IGCC case having a slightly worse heat rate while the PRB/petcoke blend IGCC case has a slightly better heat rate than the PRB-fired SCPC. IGCC has an advantage in terms of SO
2
,
PM
10
, and mercury emissions, with NO x
emissions being similar for both technologies. SCR was not included for the IGCC unit due to concerns that ammonium bisulfate (ABS) deposits could plug the finned heat transfer surfaces of the HRSG downstream of the SCR. In addition, IGCC technology consumes less water than SCPC technology.
The capital costs for the IGCC cases are approximately 20% higher than the cost for the SCPC case. There is about a 2.5% capital cost savings for the 50/50 PRB/petcoke IGCC over the 100%
PRB IGCC due to the higher heating value of the blended fuel (lower water and ash contents).
The 100% PRB SCPC unit has the lowest busbar cost of all alternatives.
The installation of CO
2
capture equipment as a retrofit for both of these technologies results in a very significant decrease in plant output. The IGCC net plant output decreases by approximately
25% and the SCPC decrease in output is 29%. Likewise, the net plant heat rate of the facilities also increases by approximately 39% for the IGCC and 41% for the SCPC. Water consumption is also increased by approximately 23% for IGCC and 34% for SCPC.
All of these factors result in an increase of the levelized busbar cost by approximately 45% for the IGCC and 58% for the SCPC post CO
2
capture. SCPC technology still provides the lowest busbar cost after CO
2
capture retrofit, although by less of a gap than pre-CO
2
capture. The avoided cost of CO
2
capture is less for an IGCC implying that IGCC technology is the more economical choice for retrofit of CO
2
capture technology.
Challenges and Objectives
The Shell gasification process chosen for this application utilizes a dry-feed system, which has advantages over slurry-feed gasification processes for low rank coal (for the non-CO
2
capture case). However, the Shell gasification process produces syngas with higher concentrations of
CO and less H
2
than would be produced by a slurry-feed gasifier. When adding CO
2
capture v
equipment to the Shell gasification process, more steam is required to convert the CO to CO
2
and
H
2 than would be required for a slurry-feed gasifier. This results in less steam available to the steam turbine, which equates to less plant output for the CO
2
capture case than may be seen if using a slurry-feed gasifier. If the objective of the Owner is to capture CO
2
, then a slurry-feed gasifier may be a better choice than a dry-feed gasifier. Another option would be a water quench version of the Shell gasifier, which would require some additional development.
Applications, Values, and Use
In recent years, several factors have caused the cost of power projects to increase at a higher rate than in years past. The world demand for many commodities has increased sharply, resulted in a
100-300% cost increase for some commodities including steel (in particular stainless or high alloy steel), concrete, copper, oil, and nickel. The compounding effect of labor productivity, high labor rate escalation, commodity cost escalation, risk mitigation, and contractor markups results in much higher project costs for both IGCC and SCPC than may have been anticipated one or two years ago. It is important that owners who are planning to add new generation have access to the most recent cost and performance estimates.
EPRI Perspective
This is the first EPRI study performed that evaluates CO
2
capture as a retrofit to existing IGCC and SCPC units. Other EPRI studies have evaluated CO
2
capture on new units specifically designed for and incorporating CO
2
capture from the start. Additionally, this is the first detailed study performed by EPRI that evaluates IGCC and PC technology with CO
2
capture when using a lower rank, higher moisture PRB coal. Other detailed studies performed by EPRI focused primarily on higher rank bituminous coals (using slurry-fed gasifiers), where IGCC has been shown to provide a more distinct advantage.
Approach
Burns & McDonnell was engaged by CPS Energy and EPRI to perform a feasibility study for a nominal 550 MW (net) IGCC facility to be located at a greenfield Texas Gulf Coast location.
The IGCC options were based on the use of Shell coal gasification technology with GE 7FB gas turbines. EPRI’s in-house computer model was used to estimate the performance of the Shell coal gasification process for both fuels. UOP’s SELEXOL system was used as the basis for the
IGCC CO
2
capture technology and Fluor’s Econamine FG Plus
SM
system was used for SCPC CO
2 capture technology. This report provides screening level capital cost, performance, operations and maintenance costs, availability factors, and emission rates for the two IGCC alternatives.
The capital costs include many site and owner-specific items that are not normally included in
EPRI’s Technical Assessment Guide (TAG
®
).
Keywords
Integrated Gasification Combined Cycle
Pulverized Coal
CO
2
Capture
PRB Coal vi
CONTENTS
vii
viii
ix
13 CO
2
IGCC CO
2
IGCC Modifications for CO
2
Capture ..............................................................................13-4
IGCC Impacts from CO
2
Capture....................................................................................13-5
x
IGCC Performance – CO
2
Capture ............................................................................13-5
IGCC Capital Cost – CO
2
Capture .............................................................................13-7
IGCC Operations and Maintenance – CO
2
Capture...................................................13-7
IGCC Emissions – CO
2
Capture ................................................................................13-9
IGCC Pre-Investment Options for CO
2
Capture.......................................................13-10
SCPC CO
2
SCPC Modifications for CO
2
Capture ...........................................................................13-12
SCPC Impacts from CO
2
Capture.................................................................................13-13
SCPC Performance – CO
2
Capture .........................................................................13-13
SCPC Capital Cost – CO
2
Capture ..........................................................................13-14
SCPC Operations and Maintenance – CO
2
Capture................................................13-15
SCPC Emissions – CO
2
Capture .............................................................................13-17
SCPC Pre-Investment Options for CO
2
Capture......................................................13-17
CO
2
H SYSTEM OF INTERNATIONAL UNITS CONVERSION TABLE ......................................... H-1
xi
LIST OF FIGURES
Figure 13-1 CO
2
Storage Supply Curve for North America ......................................................13-3
Error! No table of figures entries found xiii
LIST OF TABLES
Table 11-1 550 MW (Net) SCPC Capital Cost Estimate Summary (2006 US Dollars) ............11-3
Table 13-1 CO
2
Table 13-2 IGCC Performance Impacts from CO
2
Capture .....................................................13-6
Table 13-3 IGCC Capital Cost Additions for CO
2
Capture Retrofit...........................................13-7
Table 13-4 IGCC O&M Impacts from CO
2
Capture..................................................................13-8
Table 13-5 IGCC Emissions Impacts from CO
2
Capture .........................................................13-9
Table 13-6 SCPC Performance Impacts from CO
2
Capture ..................................................13-14
Table 13-7 SCPC Capital Cost Additions for CO
2
Capture Retrofit........................................13-15
Table 13-8 SCPC O&M Impacts from CO
2
Capture...............................................................13-16
Table 13-9 SCPC Emissions Impacts from CO
2
Capture ......................................................13-17
xv
ACRONYMS, ABBREVIATIONS, AND SYMBOLS
10
6 million
$/MMBtu dollars per million British thermal unit
ALPC Air Liquide Process and Construction
Btu/kWh
British unit
British thermal unit(s) per kilowatt-hour
CO
2
DCS distributed control system
Plus
SM
(Fluor CO
2
capture system)
EPRI Electric Power Research Institute
H
2
H
2
H
2
generator (transformer)
gas generator
hydrogen xvii
HRSG
HVAC
higher value heat recovery steam generator heating, ventilation, and air conditioning
lower value
LTGC
LTSA low temperature gas cooling long term service agreement
low
3 m cubic meters
motor center
N
2
nitrogen
Air Standards
NFPA National Fire Protection Association
NH
3
ammonia
NO x nitrous oxide ppmv ppmvd
power module ppmvd @ 15% O
2 part(s) per million by volume part(s) per million by volume (dry) part(s) per million by volume (dry) corrected to 15% oxygen
SO
2
SO
3
steam generator xviii
TGTU tail gas treatment unit xix
CERTIFICATION PAGE
Electric Power Research Institute & CPS Energy
Feasibility Study for an Integrated Combined Cycle Facility at a Texas Site
DOCUMENT DESCRIPTION
Report/Appendices Findings of IGCC Feasibility Study
CERTIFICATION(S)
NUMBER
221 xxi
1
EXECUTIVE SUMMARY
Overview
Integrated gasification combined cycle (IGCC) technology has been the source of much interest in the world of advanced coal-fired generation. IGCC technology provides a bridge between the two mature technologies of coal gasification and combined cycle technology by producing a medium-Btu value syngas from coal or other solid fuel and firing it in a modified conventional gas turbine as part of a combined cycle application.
Burns & McDonnell was engaged by CPS Energy (Owner) and EPRI to perform a feasibility study for IGCC technology to be located at a greenfield Texas Gulf Coast location.
IGCC Options
Due to the availability of petroleum coke (petcoke) and PRB coal in the area, two IGCC options were evaluated:
Option 1 – 100% PRB
Option 2 – 50% PRB / 50% Petcoke (% by weight)
For this evaluation, a 2x1 (two gas turbine/HRSG trains and 1 steam turbine) configuration was selected. The IGCC facility consists of the following major equipment:
• 1 high-pressure air separation unit (ASU) with 2x50% main air compressors and nitrogen compressors, utilizing a portion of air extracted from the gas turbine compressors at lower ambient temperatures (air-side integration).
• 2 Shell gasifiers.
• 1 SELEXOL
TM
acid gas removal (AGR) system.
• 2 sulfur recovery units (SRU).
• 1 tail gas treating unit (TGTU).
• 2 General Electric (GE) 7FB gas turbine generators (GTG).
1-1
Executive Summary
• 2 heat recovery steam generators (HRSG).
• 1 steam turbine generator (STG).
• Balance of plant (BOP).
Deliverables
This report provides screening level capital cost, performance, operations and maintenance
(O&M) costs, availability factors, and emission rates for the two IGCC alternatives defined above. As a part of creating this information Burns & McDonnell also generated process flow diagrams, layout drawings, water mass balances, and electrical one-line diagrams.
Another objective of this study was to compare IGCC technology to supercritical pulverized coal
(SCPC) technology using steam conditions of 3500 psig/1050°F/1050°F. Therefore capital cost, performance, O&M costs, availability factors, and emission rates were also developed for a
SCPC Unit firing 100% PRB coal with a net output of 550 MW. This information was used to create a 20-year levelized busbar cost to determine the overall cost of generation for the three alternatives.
The addition of CO
2
capture equipment was also evaluated as a retrofit for the 100% PRB IGCC and SCPC facilities. UOP’s SELEXOL system was used as the basis for the IGCC CO
2
capture technology and Fluor’s Econamine FG Plus
SM
system was used for SCPC CO
2
capture technology. Capital cost, performance, O&M, and emission rates were developed and used to calculate a 20-year levelized busbar cost for both technologies.
Results
A summary table is provided in Table 1-1 and Table 1-2.
1-2
Executive Summary
Table 1-1
Executive Summary Table (Table 1 of 2)
Case
Fuel
PRB (% wt.)
Petcoke (% wt.)
PRB (% heat input)
Petcoke (% heat input)
HHV (Btu/lb)
Capital Cost (2006 USD)
EPC Capital Cost
Owner's Costs
Total Project Cost
EPC Capital Cost, $/kW (73°F Ambient)
Total Project Cost, $/kW (73°F Ambient)
Performance
43°F Dry Bulb, 40°F Wet Bulb
Gross Plant Output, MW
Auxiliary Load, MW
Net Plant Output, MW
Net Plant Heat Rate, Btu/kWh (HHV)
73°F Dry Bulb, 69°F Wet Bulb
Gross Plant Output, MW
Auxiliary Load, MW
Net Plant Output, MW
Net Plant Heat Rate, Btu/kWh (HHV)
93°F Dry Bulb, 77°F Wet Bulb
Gross Plant Output, MW
Auxiliary Load, MW
Net Plant Output, MW
Net Plant Heat Rate, Btu/kWh (HHV)
O&M Cost (2006 USD)
Fixed O&M, $/kW-yr
Variable O&M, $/MWh
Total O&M Cost, $/Year (85% CF)
Availability Factor
100% PRB
100%
0%
100%
0%
8,156
$1,318,980,000
$155,240,000
$1,474,220,000
$2,390
$2,670
736.6
137.4
599.2
9,090
709.9
156.8
553.0
9,220
681.5
153.2
528.4
9,350
$25.19
$5.95
$38,426,700
85%
Base Cases
IGCC
50% PRB / 50% Petcoke
50%
50%
36%
64%
11,194
$1,287,540,000
$139,500,000
$1,427,040,000
$2,330
$2,580
734.2
137.2
597.0
8,950
711.1
158.0
553.0
9,070
682.6
154.5
528.2
9,210
$25.19
$5.66
$37,245,400
85%
SCPC
100% PRB
100%
0%
100%
0%
8,156
$1,072,580,000
$129,760,000
$1,202,340,000
$1,950
$2,190
623.3
65.4
557.8
9,030
614.5
64.5
550.0
9,150
613.2
64.4
548.8
9,170
$20.68
$4.60
$30,209,800
90%
CO
2
Capture Cases
IGCC
100% PRB IGCC
SCPC
100% PRB
100%
0%
100%
0%
8,156
100%
0%
100%
0%
8,156
$179,220,000 (Note 1)
$17,960,000 (Note 1)
$197,180,000 (Note 1)
$3,630 (Note 1)
$4,040 (Note 1)
Not Evaluated
Not Evaluated
Not Evaluated
Not Evaluated
630.1
216.8
413.3
12,800
Not Evaluated
Not Evaluated
Not Evaluated
Not Evaluated
$34.74
$8.55
$40,661,400
Not Evaluated
$269,430,000 (Note 1)
$26,570,000 (Note 1)
$296,000,000 (Note 1)
$3,440 (Note 1)
$3,840 (Note 1)
Not Evaluated
Not Evaluated
Not Evaluated
Not Evaluated
521.4
131.6
389.8
12,910
Not Evaluated
Not Evaluated
Not Evaluated
Not Evaluated
$31.19
$6.97
$32,563,000
Not Evaluated
Economic Analysis
Capacity Factor
20-year levelized busbar cost, $/MWh (2006 Real $)
Avoided CO
2
Cost, $/Mt CO
2
avoided
85%
$45.03
N/A
85%
$40.89
N/A
85%
$39.28
N/A
N/A
$65.41
$26.28
N/A
$62.00
$29.64
Notes:
1) CO
2
Capture capital costs are based on retrofit of the existing IGCC or PC facilities as provided in the base case alternatives. $/kW values reflect total installed cost to date (including original costs provided in the base case) divided by net plant output with CO2 capture.
1-3
Executive Summary
Table 1-2
Executive Summary Table (Table 2 of 2)
Case
NO x
Emissions lb/MMBtu (HHV) ppmvd @ 15% O
2 lb/MWh (net)
SO
2
Emissions lb/MMBtu (HHV) lb/MWh (net)
PM
10
Emissions (front half) lb/MMBtu (HHV) lb/MWh (net)
CO lb/MMBtu (HHV) ppmvd lb/MWh (net)
CO
2 lb/MMBtu (HHV) lb/MWh (net)
Hg
% Removal lb/TBtu (HHV) lb/MWh (net)
100% PRB
0.063
15
0.581
0.019
0.173
0.007
0.065
0.037
25
0.337
215
1,985
90%
0.778
7.17E-06
IGCC
Base Cases
50% PRB / 50% Petcoke
0.062
15
0.562
0.023
0.210
0.007
0.065
0.036
25
0.337
213
1,934
90%
0.496
4.50E-06
SCPC
100% PRB
0.050
N/A
0.458
0.060
0.549
0.015
0.137
0.150
N/A
1.373
215
1,967
70%
2.315
2.12E-05
IGCC
CO
2
Capture Cases
100% PRB IGCC
0.061
15
0.781
0.004
0.051
0.007
0.090
0.035 (Note 1)
25 (Note 1)
0.448 (Note 1)
22
276
90%
0.778
9.96E-06
SCPC
100% PRB
0.045
N/A
0.581
0.0003
0.003
0.015
0.194
0.150
N/A
1.937
22
278
70%
2.315
2.99E-05
Plant Cooling Requirements, MMBtu/hr (@ 73°F)
Steam Cycle Cooling Requirement, MMBtu/hr
BOP Auxiliary Cooling Requirement, MMBtu/hr
Total Plant Makeup Water Requirement
GPM (@ 73°F)
Acre-ft/year (@ 85% CF)
2,141
1,480
661
4,980
6,830
2,179
1,480
699
5,231
7,170
2,490
2,300
190
5,800
7,950
2,101
1,120
981
6,147
8,430
3,330
1,354
1,976
7,757
10,640
Notes:
1) GE is currently in the process of developing tools to accurately predict CO emissions for high hydrogen fuels. It is estimated that CO emissions will be less than shown for IGCC CO
2
capture technology, however to what extent is unknown at this time.
1-4
Executive Summary
The capital costs are based on mid-2006 overnight EPC costs. Escalation through a commercial operation date (COD) is not included. Additionally, sales tax, interest during construction, financing fees, and transmission lines or upgrades are not included in the capital cost estimates.
As can be seen SCPC technology provides the lowest capital cost, best efficiency, and lowest
O&M when comparing the two 100% PRB options. Additionally, the 100% PRB SCPC unit has the lowest busbar cost of all alternatives.
The heat rate for the fuel blended IGCC case is slightly better than 100% PRB SCPC technology
(with the exception of the 93°F case); however firing petcoke in a PC unit is also possible, although not specifically evaluated for this report. Petcoke firing in a conventional PC boiler is typically limited to approximately 20% (by heat input) due to the low volatiles present in the fuel which can create flame stability issues. Firing 20% petcoke in the PC boiler will result in approximately 1% improvement in heat rate over that shown for the PC unit, thus closing the gap, if not eliminating any performance benefit of the IGCC.
IGCC has an advantage in terms of SO
2
, PM
10
, and mercury emissions, however using the emissions allowance costs provided in Chapter 8, these lower emissions are not enough to overcome the capital cost and performance differences between the technologies.
The IGCC evaluated has higher NO x
emission rates than for the SCPC unit. This is because an
SCR was not included for the IGCC unit due to concerns that ammonium bisulfate (ABS) deposits could plug and corrode the heat transfer surfaces of the HRSG downstream of the SCR.
Additionally, if an SCR were used, a larger AGR and SRU would be required to lower the sulfur content of the syngas (to reduce particulate formation from the excess ammonia with SO
2
/SO
3
in the flue gas) resulting in increased capital cost. For these reasons, an SCR was not included; however subsequent evaluations should be performed to evaluate the cost/benefit/technological risk tradeoff. If an SCR were used, NO x
emissions could be reduced to levels below that provided for the SCPC unit.
IGCC technology consumes less water than SCPC technology. This is primarily due to the steam turbine output of the IGCC being less than half that of the SCPC unit. Although the steam condenser duty is less for the IGCC, the auxiliary cooling requirements of the IGCC are higher than the SCPC unit (primarily due to the ASU cooling requirement), resulting in about a 15% overall lower cooling tower duty and water consumption.
The installation of CO
2
capture equipment as a retrofit for both of these technologies results in a very significant decrease in plant output. The IGCC net plant output decreases by approximately
25% and the SCPC decrease in output is 29%. Likewise, the net plant heat rate of the facilities also increases by approximately 39% for the IGCC and 41% for the SCPC. Water consumption is also increased by approximately 23% for IGCC and 34% for SCPC.
All of these factors result in an increase of the 20-year levelized busbar cost by approximately
45% for the IGCC and 58% for the SCPC post CO
2
capture. SCPC technology still provides the lowest busbar cost after CO
2
capture retrofit, although by less of a gap than pre-CO
2
capture.
The avoided cost of CO
2
capture is less for an IGCC implying that IGCC technology is the more economical choice for retrofit of CO
2
capture technology (if you owned both an existing IGCC
1-5
Executive Summary
plant and SCPC plant and were going to retrofit only one, you would choose the IGCC), however the lower initial capital cost (pre-capture) of SCPC technology still results in an overall lower busbar cost for SCPC technology.
This is the first EPRI study performed that evaluates CO
2
capture as a retrofit to existing IGCC and SCPC units. Other EPRI studies have evaluated CO
2
capture on new units specifically designed for and incorporating CO
2
capture from the start vs. new units that are not designed with CO
2
capture in mind. This study attempts to answer the question of what are the impacts from adding CO
2
capture to an existing SCPC or IGCC plant at a later date.
The Shell gasification process chosen for this application utilizes a dry-feed system, which has advantages over slurry-feed gasification processes for low rank coal (for the non-CO
2
capture case). The Shell gasifiers produce syngas with higher concentrations of CO and less H
2
than would be produced by a slurry-feed gasifier. When adding CO
2
capture equipment to the Shell gasification process, more steam is required to convert the CO to CO
2
and H
2 than would be required for a slurry-feed gasifier. This results in less steam available to the steam turbine, which equates to less plant output for the CO
2
capture case than may be seen if using a slurryfeed gasifier. If the objective of the Owner is to capture CO
2
, then a slurry-feed gasifier may be a better choice than a dry-feed gasifier.
Additionally, this is the first detailed study performed by EPRI that evaluates IGCC and PC technology with CO
2
capture when using a lower rank, higher moisture PRB coal. Other detailed studies performed by EPRI focused primarily on higher rank bituminous coals (using slurry-feed gasifiers), where IGCC has been shown to provide a more distinct advantage.
The performance information provided by UOP and Fluor for the CO
2
capture equipment is different from data obtained for other recently published studies. A resolution of the differences is outside the scope of this project, however it is anticipated that the differences are related to the
CO
2
purity that was specified for this project. It should be noted that none of the technologies
(IGCC, SCPC, or CO
2
capture) evaluated in this study were optimized to provide the best costto-benefit ratio (i.e. lowest busbar cost). The designs used as the basis for this evaluation are just one of many possible configurations that should be further optimized in the future.
Changes in market conditions, improvements in IGCC technology, different fuel specifications, or CO
2
purity specifications could be enough to swing the economics in favor of IGCC.
Therefore, it is recommended that utilities consider IGCC technology for future generation needs. However, based on the results and design basis used in this study, SCPC provides the lowest busbar cost of the three alternatives at this time.
Current Market Conditions
In recent years, several factors have caused the cost of power projects to increase at a higher rate than in years past. Specifically in the Gulf Coast area, the destruction of Hurricane Katrina has resulted in a large labor demand for reconstruction efforts. In order to meet labor requirements, much of the construction labor force has been pulled from out of state, resulting in a construction labor shortage across the country (in an industry that was already in high demand). The high demand for qualified labor has resulted in “job-hopping” for many workers. The result is that
1-6
Executive Summary
labor productivity has been very poor compared to that of just a few years ago, yet the cost of construction labor is increasing at a rapid rate.
In addition to Hurricane Katrina rebuilding projects, engineering firms and construction contractors are very busy with new power generation projects and air pollution control projects designed to clean up SO
2
and NO x
emissions from older coal-fired units. This increased demand results in increased contingency, overhead, and profit levels for contractors. Some clients have even had challenges finding qualified contractors that are willing to bid on their projects.
Beyond labor issues, the world demand for many commodities has also increased sharply, due in large part to China’s economic growth. This high demand has resulted in a 100-300% cost increase for some commodities including steel (in particular stainless or high alloy steel), concrete, copper, oil, and nickel resulting in increased equipment costs and vendor markups.
The compounding effect of labor productivity, high labor rate escalation, commodity cost escalation, risk mitigation, and contractor markups results in much higher project costs than may have been anticipated one or two years ago.
Limitations and Qualifications
The estimates and projections prepared by Burns & McDonnell relating to construction costs, performance, and O&M are based on our experience, qualifications, and judgment as a professional consultant. Since Burns & McDonnell has no control over weather, cost, and availability of labor, materials, and equipment, labor productivity, unavoidable delays, economic conditions, government regulations and laws (including interpretation thereof), competitive bidding and market conditions or other factors affecting such estimates or projections, Burns &
McDonnell does not guarantee that actual rates, costs, performance, etc., will not vary from the estimates and projections prepared herein.
1-7
2
INTRODUCTION
Background
CPS Energy, located in San Antonio, Texas, is the nation’s largest municipally owned energy company providing both electricity and natural gas to its customers. In December of 2005, CPS
Energy agreed to fund an IGCC study, as part of a settlement during the air permitting process for a new pulverized coal plant. Under the terms of the agreement, the IGCC study scope compares SCPC and IGCC technologies at a generic site in Texas. CPS Energy also agreed to make the report available to the public. This study provides typical decision support input for a power plant investment decision for a generic municipally-owned utility. The study includes generic investment decision information such as, cost of capital, forecasted fuel costs, etc. The study does not include competitive, sensitive CPS Energy power plant investment decision information.
CPS Energy contacted Burns & McDonnell to perform a technical and economic feasibility study for a nominal 550 MW 2x1 IGCC unit.
Objectives
The primary objectives of this study were to provide screening-level information for use in evaluating a 2x1 IGCC facility to be located at a generic Texas Gulf Coast site. This information consists primarily of capital cost, performance, and O&M cost estimates.
To achieve these objectives, Burns & McDonnell provided a conceptual design for the facility, consisting of preliminary process design, overall plant heat balances, preliminary process flow diagrams, preliminary electrical one-line diagrams, and preliminary site layout drawings. This information was then used to establish the plant preliminary capital cost estimate.
Once the conceptual design information was produced, IGCC technology was compared to conventional coal fired SCPC technology in a pro forma economic analysis to determine which technology resulted in the lowest busbar cost of the facility.
Additionally, the impacts of adding CO
2
capture as a retrofit to the IGCC and SCPC technologies were evaluated. The impacts for performance, capital cost, O&M, emissions, and levelized busbar cost were determined.
If any of the technologies presented in this report are of interest to the Owner, it is recommended this feasibility study be followed up with more detailed studies to further define the project and
2-1
Introduction
to tailor the information for a specific site. These follow-on studies should include gasifier and gas turbine manufacturer involvement.
Status of the Technology
Conventional combined cycle technology is a proven technology that has been used for many years in the power industry. Similarly, gasification technology is a proven technology that has been used extensively in the chemical industry to produce products such as ammonia and hydrogen. IGCC technology combines these two proven technologies by producing a medium-
Btu value syngas from coal or other solid fuel (petcoke) and firing it in a modified conventional gas turbine as part of a combined cycle application.
When combining these two technologies, high levels of integration between the two processes are often required to increase plant efficiency and to make IGCC competitive with other coalfired electric power generation technologies. This integration is created by using heat exchangers to capture heat produced in the gasification process and utilizing it to increase the output and efficiency of the steam cycle, yet at the same time increasing the complexity of the plant.
IGCC projects generally utilize conventional equipment (gas turbines, heat exchangers, compressors), that when combined with the complexity of integration into an IGCC facility, has led to less than desirable availability factors and forced outage rates in the past. It has generally been the failure of this “conventional” equipment that has lead to the poor reliability and availability of the existing IGCC facilities. It is anticipated that advancements in IGCC design and increased IGCC operational experience are expected to improve availability and lower the forced outage rates for IGCC technology.
Development of the IGCC technology truly commenced in the 1970’s during the energy crisis.
Research and development during this timeframe led to the construction of the Texaco Cool
Water facility in California, and the LGTI facility in Louisiana. Both of these facilities have been decommissioned. Experiences and lessons learned from these facilities were brought forward during the 1990’s with the development of the Polk and the Wabash IGCC facilities.
Ongoing operation of these two facilities in the United States and the Buggenum and Puertollano facilities in Europe continue to help improve the future generation of IGCC facilities.
Selection of Gasification Technology
Burns & McDonnell was requested to perform a cursory evaluation of the gasification technologies available, and select a technology to be used as a basis for this study. Focus was given only to the major technologies that currently have commercial IGCC offerings in the
United States. This consists of GE, ConocoPhillips, and Shell gasification technologies.
GE and ConocoPhillips use slurry-feed gasifiers, whereas Shell uses a dry-feed gasifier. Slurryfeed gasifiers typically work well on high rank bituminous coals. When utilizing PRB as a feedstock, however, the slurry has a lower concentration due to the high inherent moisture content of the PRB coal. As a result of feeding less dense slurry to the gasifier, the cold gas
2-2
Introduction
efficiency decreases and oxygen consumption increases, typically resulting in decreased performance.
GE has several gasifiers operating in the United States and worldwide. The GE gasification technology is an oxygen-blown slurry-feed entrained flow gasifier. Most of the operating GE gasifiers are the quench design. Their IGCC offering is the radiant design intended to maximize the steam production for power generation. The GE gasification process works well on bituminous coal and/or petcoke, and they are currently working on a design for PRB, with the intention of having a commercial offering toward the end of 2006. GE was approached about participating in this study, and due to their current workload, declined to participate.
ConocoPhillips has an operating, full commercial scale gasifier at the Wabash IGCC facility.
Their process is a 2-stage oxygen-blown slurry-feed entrained flow gasifier. At the LGTI IGCC facility, which was decommissioned in 1995, ConocoPhillips gasified over 3.7 million tons of
PRB. ConocoPhillips was also approached about participating in this study, and due to their current workload, declined to participate.
Shell currently has three coal gasifiers operating worldwide. Two started up this year in China and the Shell gasifier is used at the NUON IGCC facility in the Netherlands. Eleven other Shell coal gasifiers are currently under construction in China. The Shell coal gasification process is an oxygen-blown dry-feed entrained flow gasifier that is suitable for PRB gasification. The dryfeed system of the Shell gasifier also likely provides some performance benefits over slurry-feed gasifiers when designing for low-rank coals such as PRB. Shell was approached about participating in the study and also declined to participate directly, but agreed to allow EPRI to perform modeling of their gasification system and supply the results to Burns & McDonnell.
Based on the likely performance benefits associated with the Shell process for PRB coal, it was agreed that the Shell gasification process would be used as the basis for this evaluation.
It should be noted that all of the gasification technologies described above perform differently and have different O&M requirements. The GE and ConocoPhillips gasifiers are refractory lined, whereas the Shell gasifier has a steam tube membrane wall. The refractory lined gasifiers require a periodic replacement of the refractory due to wear in the high slag flow areas, whereas the membrane wall tubes require little maintenance. Also, the Shell process is a dry-feed, versus slurry-feed for the GE and ConocoPhillips processes. Due to the higher concentrations of water, the syngas from the GE and ConocoPhillips gasifiers has higher concentrations of CO
2
and H
2 and the syngas from the Shell process has a higher concentration of CO.
Project Experience
Table 2-1 shows the current and previous IGCC facilities that were developed in the United
States and in Europe. All of the United States facilities were developed with funding assistance from the Department of Energy.
2-3
Introduction
Table 2-1
IGCC Facilities – Past and Current
Facility
Puertollano
Polk
County
Wabash
River
Buggenum
Pinon Pine
LGTI
Cool Water
Owner
Capacity
(MW)
Commercial
Operation
Date
Gasifier
Manufacturer
Status
Elcogas 321 1998 Prenflo Operating
Tampa
Electric
252 1996 GE Operating
PSI Energy 262 1995 Conoco Phillips Operating
NUON 254 1994 Shell Operating
Sierra
Pacific
Dow
Chemical
Texaco 125 1984 GE Decommissioned
Fuel experience
Within the United States, relatively little IGCC experience exists with PRB as the feedstock. As noted previously, between 1987 and 1995, the LGTI facility gasified over 3.7 million tons of
PRB. This represents the majority of the United States operating experience with PRB gasification.
There has been significant operating experience with petcoke. Petcoke lends itself well to gasification due to the higher heating content, low moisture, and low ash. However, petcoke does have significantly higher sulfur content. Due to the trace metals in the petcoke, either a fluxant or coal needs to be blended with the petcoke to enable the ash to flow out of the slagging gasifiers. Currently, the fuel for the Polk IGCC facility is a blend of coal and petcoke, and petcoke is being utilized at the Wabash IGCC facility.
Shell has processed both PRB coal and petcoke during the early 1990s at a 250 tpd demonstration plant at Shell’s Deer Park, TX refinery. Shell has reported a cold gas efficiency of 78.0% with 99.7% carbon conversion and 99.9% sulfur capture during 297 hours of tests on
PRB and 78.9% cold gas efficiency with 99.5% carbon conversion and 99.8% sulfur capture during 169 hours of operations on petcoke.
Technical Approach and Data Sources
As noted above, the Shell coal gasification process was selected for this study. EPRI provided the gasifier yield and thermal performance for the gasification plant (up to the wash column inlet). Burns & McDonnell performed the preliminary design of the low temperature gas cooling and scrubbing section, COS/HCN catalyst section, AGR, SRUs, TGTU, power block, and balance of plant. The following vendors were used to provide additional information:
• UOP provided an equipment list and performance information for the SELEXOL unit.
2-4
Introduction
• Air Liquide Process and Construction (ALPC) provided cost and performance information for the ASU.
• Sud-Chemie provided cost and performance information for the COS/HCN catalyst.
• NUCON provided cost and performance information for the mercury removal bed.
• Fluor provided cost, performance, and emissions information for the Econamine FG Plus
Plant (EFG+) for SCPC CO
2
capture.
The information provided herein does not represent a thorough performance or cost optimization.
Further optimizations (capital cost investment vs. performance, emissions, or O&M benefits) can be performed that would likely improve the busbar cost of all technologies (SCPC, IGCC, and
CO
2
capture).
2-5
3
STUDY CRITERIA
Site Selection
The site for this project is based on a generic greenfield site located in the Texas Gulf Coast.
The ambient conditions used as the design basis of this study are the 2% dry bulb (dry bulb temperature is exceeded 2% of the year), average dry bulb, and 95% dry bulb (dry bulb temperature is exceeded 95% of the year)
The ambient conditions are as follows:
• 2% Dry Bulb: 93°F with coincident wet bulb temperature of 77°F.
• Average Dry Bulb: 73°F with coincident wet bulb temperature of 69°F.
• 95% Dry Bulb: 43°F with coincident wet bulb temperature of 40°F.
The finished grade of the site is assumed to be 100 ft. Additional assumptions about the site can be found in Chapter 7.0
Gas Turbine Selection
The gas turbines selected as the basis for this project are GE 7FB gas turbines. EPRI and Burns
& McDonnell have access to more readily available information for GE’s 7FB gas turbines than from other manufacturers. Also, GE has much experience with syngas operation, having accumulated over 300,000 hours of operation on syngas; however GE has no operating experience with firing syngas in the 7FB. Although GE has this significant syngas operating experience, other gas turbine manufacturers are able to offer similar gas turbines that should result in a comparable result.
Fuel Selection
PRB fuel is currently utilized by several utilities in Texas. This low-sulfur coal has proven to be an economical choice for generation in Texas.
Additionally, petcoke, a byproduct of the refining process, has proven to be an economical fuel alternative for other generating facilities across the nation. Refineries are typically eager to
3-1
Study Criteria
remove this byproduct from their site; therefore petcoke is relatively inexpensive from the refinery. The expense of petcoke is dictated by transportation costs from the refinery to the power plant. The prospect of petcoke firing is typically limited by the following factors:
1) Projects planning to fire petcoke are typically located near refineries that produce coke as a byproduct.
2) The quantity of petcoke is typically only available in sufficient quantities to supply a part of the overall heat input to a large power facility.
3) Firing 100% petcoke in a PC unit is only achievable using a special down-fired boiler.
Conventional designed PC units are limited to approximately 20% petcoke firing due to the low volatiles in the coal.
Therefore, petcoke is typically blended with other fuels when used in large scale power generation.
Because this project is located in the Texas Gulf Coast, petcoke should be available as an alternate fuel source from nearby refineries. Therefore, two independent IGCC options were evaluated for this project:
• Option 1 – 100% PRB Coal
• Option 2 – 50% PRB Coal / 50% Petcoke (% by weight)
Fuel analyses are provided in Table 3-1.
3-2
Study Criteria
Table 3-1
Fuel Analyses
PRB (% wt.)
Petcoke (% wt.)
PRB (% heat input)
Petcoke (% heat input)
HHV (Btu/lb)
Proximate Analysis (% wt.)
Moisture
Volatile Matter
Fixed Carbon
Ash
Ultimate Analysis (% wt.)
Carbon
Hydrogen
Nitrogen
Chlorine
Sulfur
Oxygen
Ash
Moisture
Total
Mercury (ppm)
Ash Fusion Temperatures
Reducing Atmosphere
Initial Deformation
Softening
Hemispherical
Fluid
Oxidizing Atmosphere
Initial Deformation
Softening
Hemispherical
Fluid
100% PRB
100%
0%
100%
0%
8,156
30.24
31.39
33.05
5.32
48.18
3.31
0.70
0.01
0.37
11.87
5.32
30.24
100.00
0.091
2150°F
2170°F
2190°F
2210°F
2220°F
2240°F
2260°F
2280°F
100% Petcoke
0%
100%
0%
100%
14,231
4.83
10.60
84.44
0.13
83.62
3.02
0.85
0.01
6.60
0.94
0.13
4.83
100.00
0.05
2800+°F
2800+°F
2800+°F
2800+°F
2,505°F
2,597°F
2,610°F
2,611°F
50% PRB / 50% Petcoke
50%
50%
36.40%
63.60%
11,194
17.53
21.00
58.74
2.73
65.88
3.17
0.78
0.01
3.49
6.41
2.73
17.53
100.00
0.07
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
Plant Capacity Selection
The largest IGCC facility that has been constructed in the United States is a 1x1 (one gasification/gas turbine/HRSG train and one steam turbine). Currently, 2x1 IGCC technology is the primary focus of IGCC development by both manufacturers and developers due to improved economies of scale. It is possible to improve the economies of scale of an IGCC facility further by adding an additional gasification/gas turbine/HRSG train (3x1 facility). However due to a general aversion to risk in the industry, it is unlikely that a 3x1 IGCC facility will be developed until 2x1 IGCC technology has been proven successfully in the United States. Therefore, a 2x1
IGCC facility is the basis of this study.
3-3
Study Criteria
The plant capacity for this project is dictated by the capacity of the gas turbines coupled with the available energy that can be recovered from the gas turbine and gasification process. For this project, the 2x1 IGCC facility has a nominal net plant output of 550 MW.
Capacity Factor and Availability Factor Targets
Capacity Factor (CF) is defined as the actual MWh produced in a year divided by the maximum possible MWh produced in a year. Generally, capacity factors for units are dictated by economic issues. Lower production cost technologies operate at base load (capacity factors above 70%), whereas higher production cost technologies tend to operate as “peaker” plants or for serving an intermediate load (operating throughout the day and ramping down at night).
The large capital and operating expenditure (yet lower fuel cost) of a coal plant are typically only justified by operating the unit at base load. Due to the increase of natural gas prices and limited base load resources, capacity factors of conventional PC plants are typically at 85% or higher.
The O&M estimates and economic evaluation provided in this study assume a capacity factor of
85%, with a 100% load factor (operating 85% of the time at full load and off-line the other 15% of the time).
The Availability Factor (AF) is defined as the sum of service hours and reserved shut down hours divided by the total hours per year. Essentially, it is the percentage of hours in a year that the plant is available to operate.
Some IGCC facilities have been evaluated with a spare gasifier to increase availability factors and allow increased operational flexibility. It was decided that the increased operating and capital expenses of the spare gasifier are not justified for this project at this time. The resulting availability factor is approximately 85% for the IGCC technologies evaluated.
Additional information on plant availability factors can be found in Chapter 9.0.
3-4
4
PROCESS DESCRIPTION
Gasification System Description
For this report, the Gasification System refers to all of the equipment required to make syngas.
This includes the ASU, gasifiers, slag handling, candle filters, wash towers, COS/HCN hydrolysis, mercury removal, syngas cooling and condensation, AGR, SRUs, tail gas treatment, sour water stripping, and syngas saturation. Process flow diagrams are included in Appendix A for reference. A block flow diagram is provided in Figure 4-1.
Figure 4-1
Gasification Block Flow Diagram
Air Separation Unit (ASU)
Atmospheric air is dried and then cryogenically distilled in the ASU to produce 95% oxygen and several nitrogen steams. The air separation unit selected for this study is a high-pressure ASU, meaning that the columns all operate at a higher pressure than a conventional low-pressure ASU.
The selection of an HP or LP ASU depends primarily on the amount of nitrogen required under
4-1
Process Description
pressure vs. the oxygen requirement. Because of the large nitrogen requirement, the primary benefit of the HP ASU is the reduced power requirement for N
2
compression.
The majority of the oxygen produced in the ASU is supplied at high pressure (780 psia) for use in the gasifiers. A small amount of low pressure oxygen is used as the oxidant in the SRU.
Uses for the nitrogen streams are as follows:
• High pressure (1089 psia) N
2
with 0.1% O
2
is used for conveying the fuel into the gasifier and other purposes in the gasification block.
• Medium pressure (480 psia) N
2
with 2% O
2
is used as diluent in the gas turbines for NO x control.
• Low pressure (140 psia) N
2
with 2% O
2
is used for regeneration of the molecular sieve driers and miscellaneous purges.
Cryogenic pumps are used to supply the high pressure nitrogen and oxygen streams to the gasifier. The cryogenic pumps were chosen because of their lower auxiliary power consumption and lower cost than gas compression. Additionally, pumping liquid O
2
is generally viewed to be safer than compression of gaseous O
2
. The high-pressure liquid oxygen and nitrogen are then vaporized prior to the gasifier. The medium pressure and low pressure nitrogen streams are pressurized by nitrogen compressors.
The ASU scope includes storage of high-pressure, high-purity nitrogen equivalent to 12 hours of production in liquid form. Additionally, 20 minutes of production as gas is available at pressure to provide nitrogen during the period of time that back-up liquid vaporization comes on line.
The back-up system is to be designed to deliver high pressure nitrogen within 10 minutes after being activated.
The material balances around the ASU for the 100% PRB cases (43°F and 93°F) are provided in
Table 4-1, which are used to set the design requirements of the ASU. Since very little difference exists between the ASU for the 100% PRB case and the 50% PRB / 50% petcoke case, the same
ASU design was used for both options. Additionally, Figure 4-2 provides a block flow diagram for a generic ASU.
4-2
Process Description
Table 4-1
ASU Material Balances
Stream
H2O
O2
N2
Ar
Total
% O2
Temp, F
Pres. psia
Total lb/hr
Case 93F PRB Coal
<------------------------------------Nitrogen Product Streams----------------------------->
Total Air In Total Dry Air O2 Product Conveying HP To Process LP Misc Sieve Regen. Remaining N2 to GT Ambient Air GT Air lb-moles/hr lb-moles/hr lb-moles/hr lb-moles/hr lb-moles/hr lb-moles/hr
1,390 1 1,392
11,057 11 11,068 11,068 10,383 2 lb-moles/hr lb-moles/hr lb-moles/hr lb-moles/hr lb-moles/hr
1,392
2 187 490 677
41,211
492
54,150
20.4%
41
0
54
20.4%
41,252
492
54,204
20.4%
41,252
492
52,812
21.0%
164
383
10,930
95.0%
1,930
1.9
1,934
0.1%
4
4,000
4.1
4,008
0.1%
1,555
1.6
1,559
0.1%
9,164
9
9,360
2.0%
24,439
93
25,021
2.0%
33,603
102
35,773
1.9%
93
15
1,552,965
810
218
1,547 1,554,511 1,529,437
382
760
352,142
280
1068
54,206
280
1068
112,353
56
140
43,692
56
140
263,066
56
140
703,991
453
290
992,132
Stream
H2O
O2
N2
Ar
Total
% O2
Temp, F
Pres. psia
Total lb/hr
Ambient Air GT Air Total Air In Total Dry Air O2 Product Conveying HP To Process LP Misc Sieve Regen. Remaining N2 to GT lb-moles/hr lb-moles/hr lb-moles/hr lb-moles/hr lb-moles/hr lb-moles/hr lb-moles/hr lb-moles/hr lb-moles/hr lb-moles/hr lb-moles/hr
253 168 422 422
7,281
27,138
323
34,996
20.8%
4,854
18,092
216
23,330
20.8%
12,135
45,230
539
58,326
20.8%
12,135
45,230
539
57,904
21.0%
11,360
179
419
11,958
95.0%
2
1,930
1.9
1,934
0.1%
4
4,000
4.1
4,008
0.1%
2
1,555
1.6
1,559
0.1%
187
9,164
9
9,360
2.0%
580
28,402
103
29,085
2.0%
767
37,566
113
38,867
2.0%
93
15
1,010,697
810
218
673,785 1,684,482 1,676,887
Case 43F PRB Coal
<------------------------------------Nitrogen Product Streams----------------------------->
382
760
385,263
280
1068
54,206
280
1068
112,353
56
140
43,692
56
140
263,066
56
140
453
290
818,321 1,088,982
Note: The air provided by the GTG (stream 2) is cooled to ambient temperature by heat exchange with steam cycle condensate and auxiliary cooling water prior to being sent to the ASU. The N
2
to the gas turbine (stream 11) is heated from ~350°F at the discharge of the final stage of compression to 453°F using IP boiler feedwater as the heat source prior to the gas turbine.
The following major equipment items are included:
• Main air compressor and booster air compressor (2 trains x 50%).
• Nitrogen compressor (2 x 50%).
• Cryogenic oxygen pumps (2 x 100%).
• Cryogenic nitrogen pumps (2 x 100%) for high pressure N
2.
• Cold box.
• Switching valves, driers and regeneration heater.
• MV and LV Switchgear and MCC.
• Transformers from 13.8 KV.
• Liquid N
2
storage and associated backup vaporizer.
• Electrical / control room.
• Commissioning spares.
4-3
Process Description
Figure 4-2
Generic ASU Process Flow Diagram
Additionally, heat exchangers are provided to cool the extracted air from the gas turbine to ambient temperature prior to the ASU and to heat the nitrogen from the ASU to the gas turbine.
These costs are not included in the ASU cost provided by ALPC, however they are included in the BOP costs.
Gasifiers
The gasification plant for this project is comprised of two Shell oxygen-blown entrained-flow gasifiers, each capable of supplying enough syngas for operation of one gas turbine at full load.
Each gasification train is comprised of coal milling and drying equipment, coal pressurization lockhopper, high pressure oxygen and coal feed systems, gasifier vessel, slag removal system, syngas cooling, syngas recycle compressor, and particulate removal systems.
The Shell gasifier uses a dry-coal feed system. This system requires the feedstock moisture content to be reduced to approximately 5% prior to injection to the gasifier. Therefore, coal drying equipment is required which utilizes syngas (or natural gas during startup) to drive off the excess moisture in the fuel. The coal dryer is combined with the coal milling equipment in a vertical roller mill which pulverizes the coal to the required consistency. The dried and pulverized coal is raised above the gasifier operating pressure in a set of lockhoppers and conveyed to the gasifier using high pressure nitrogen. PRB fuel is highly reactive and has a high potential for spontaneous combustion; consequently the oxygen concentration in the milling/drying and coal feeding systems is minimized via the injection of nitrogen at various locations. A detailed evaluation of the operation of the coal dryer relative the PRB fuel was not performed.
4-4
Process Description
The fuel and high pressure oxygen react in the gasifier at high temperatures (2,700 ºF) and approximately 560 psia to produce syngas. The gasifier, operating in an oxygen deficient
(reducing) atmosphere, is designed to operate at conditions suitable to promote reactions which produce a synthesis gas (syngas) and slag. The syngas produced in the gasifiers is rich in hydrogen, carbon monoxide, and water. There are also lesser amounts of several components including carbon dioxide, hydrogen sulfide, carbonyl sulfide, methane, argon, and nitrogen.
The gasifier vessel walls are cooled using water-wall membranes that produce medium-pressure
(MP) steam at approximately 650 psia. The syngas is quenched by recycle of cooled, particulate-free syngas to ~1,700°F. The syngas then passes to the syngas cooler which also uses medium pressure feedwater as a cooling medium. Heat from the syngas is transferred to the feedwater resulting in the generation of medium pressure saturated steam that is transferred to the HRSG in the power block for superheating and re-introduced to the steam turbine as “hot reheat” steam. After being partially cooled in the syngas cooler, the syngas passes through a candle filter to remove entrained solids from the syngas. Additionally the syngas is passed through a water wash scrubber which is primarily used to remove fine particulate, chlorides, and any other water-soluble compounds (see Syngas Wash Towers section below).
Alternatively, HP steam can be generated in the syngas cooler, however this greatly increases the cost of the syngas cooler and associated piping (alloy materials vs. carbon steel), resulting in
~$60-$70 million increase in total project cost. Shell claims that the use of HP steam generation in the syngas cooler can result in a 1.5% improvement in IGCC efficiency; however this option was viewed as cost prohibitive at this stage of the project. It is recommended that this option be evaluated in more detail at a later developmental stage of the project.
Gasifier Performance Estimate by EPRI
EPRI used its internal IGCC modeling tool, which uses a Gibbs Free Energy Minimization approach to estimating gasifier product composition and temperature. EPRI relied heavily on the performance data Shell published in a 2004 Gasification Technologies Conference paper to set the inputs for the gasifier model. That paper presented performance estimates for the Shell coal gasification process on a generic Powder River Basin coal and on a 50/50 mixture of PRB and petcoke. One difference between the Shell design premises and those used by EPRI was the purity of the oxygen feed stream. Shell assumed it was 99 v% O
2
, while EPRI chose 95 v% as several engineering studies have shown that to be the optimal value for IGCCs producing power only.
A summary of the main inputs and outputs from the gasifier performance model at the 43°F ambient condition is provided in Table 4-2.
4-5
Process Description
Table 4-2
Summary of Gasifier Modeling Results
100% PRB
Model Inputs
O
2
/coal feed ratio (95v% O
2
) lb/lb-coal
1
0.771
Steam/coal lb/lb-coal
1
0.034
N
2
/coal lb/lb-coal
1
0.110
Syngas Exit Pressure psia 574
Heat Flux to Gasifier Wall
Carbon Conversion
Model Results
%coal HHV
%
0.6
99.5
Syngas Exit Temperature ºF
Gasifier Wall Steam Production MMBtu/hr
Syngas Exit Composition
CH
4
CO
CO
2
COS
H
2
H
2
H
2
HCN
NH
3
N
2
AR
%vol
%vol
%vol
%vol
O
2
Feed Rate
Steam Feed Rate lb/hr lb/hr
2732
32.7
59.91
0.013
0.005
0.97
377,816
16,688
50% PRB / 50%
Petcoke
0.881
0.104
0.107
574
1.4
99.0
2913
74.8
64.85
0.110
0.011
1.02
364,983
42,939
N
2
for Coal Conveying
Coal Feed Rate
Coal Feed Rate
2 lb/hr lb/hr
MMBtu/hr
Unquenched Syngas Flow Rate lb/hr
54,069
490,171
5,444.3
901,760
Syngas Production Rate
2
MMBtu/hr 4,561.7
Flyslag (overhead) Production lb/hr 10,084
44,371
414,125
5,340.7
850,367
4,453.4
6,185
Slag (bottom) Production
Cold Gas Efficiency lb/hr
3
%
26,900
83.8
9,866
83.4
1
As fed coal basis (dried to 5 wt% H
2
O)
2
HHV basis
3
As fed coal HHV basis only, energy value of feed steam and dryer fuel not included
Slag Handling
Slag formed in the coal gasification process flows to the bottom of the gasifier. This slag is quenched in a slag bath that is located within the gasifier vessel. Water is circulated through the slag bath to recover the heat from the slag. The hot slag water is cooled with a heat exchanger.
The cooled slag settles to a slag accumulator and lockhopper vessel. Once the slag has settled to the lockhopper vessel, the valves between the slag accumulator and lockhopper vessel are closed.
The lockhopper provides a transition between the pressurized gasifier and the atmospheric slag dewatering system. Once isolated from the gasifier, the lockhopper is depressurized and the
4-6
Process Description
valves are opened at the outlet of the lockhopper vessel. The slag and water mixture are then discharged to the slag dewatering system. This lockhopper system operates in batch mode continually to remove slag from the gasifier as it is accumulated.
The slag from the outlet of the lockhopper is dewatered using a submerged scraper conveyor.
The slag slurry water from the bottom of the submerged scraper conveyor is pumped to a clarifier where the clean slag slurry water is recycled to the lockhopper and the fines are collected and re-injected into the gasifier. The coarse slag from the outlet of the submerged scraper conveyor is conveyed to a slag storage pile. The coarse slag can then be landfilled or sold to market. The glassy, inert slag produced in the Shell gasifier is very low in carbon content which makes the slag attractive for sale.
Fly Ash System
After the syngas cooler, the syngas passes through first a cyclone and then ceramic candle filters that remove particulate matter (flyash) from the syngas. Similar to removing the slag from the gasifier, the flyash is removed from the cyclone and candle filter vessels with a batch process using lockhoppers. The coarse flyash that was removed by the cyclone can be recycled to the coal mill if it contains a significant amount of unconverted carbon. Otherwise, the coarse flyash along with the finer flyash collected by the candle filters is temporarily stored on site and either landfilled or sold to cement manufacturers or to other markets for flyash.
Syngas Wash Towers
Raw syngas flows from the candle filter to the syngas wash towers where the syngas is washed with water. The purpose of the water wash is twofold: 1) to recover any particulates that pass through the candle filters and 2) to recover chlorides that dissolve in the wash water and remove them from the system at concentration less than 300 ppm (to avoid corrosion of the carbon steel tower and piping). The wash water is primarily fresh demineralized water to which recycled water streams from the saturator water circulation loop (a purge stream) and the sour water stripper bottoms are added.
The water streams from the bottom of the syngas wash towers flow to a common system consisting of several operations:
• The first step is a flash at 7 psia. Liquid from the flash is cooled with make-up demineralized water used for syngas saturation before being filtered and sent to the cooling tower as makeup water.
• Solids recovered from the filtration mentioned above (particulates not removed by the candle filters) are sent to the coal pile. The amount of solids is estimated at only 110 lb/day.
• Vapor from the 7 psia flash is condensed under vacuum using an air cooler.
• Liquid condensed in the air cooler is separated from the small amount of vapor and is pumped to the sour water stripper.
4-7
Process Description
• Vacuum conditions in the condensate drum are maintained by a steam jet ejector. Effluent from the ejector flows to the sour water stripper.
This design was generated by Burns & McDonnell in absence of detailed design information by
Shell and does not represent Shell’s standard syngas scrubbing and sour water treatment design.
It is recommended that the design of this system be evaluated in detail in conjunction with Shell at a later development stage of the project.
The syngas wash system consists of the following equipment:
• Syngas wash tower (one tower for each of two parallel trains).
• Recovered water flash drum (one common drum for two parallel trains).
• Recovered wash water pumps (one common pump with a full spare for two parallel trains).
• Recovered wash water exchanger (one common exchanger for two parallel trains).
• Recovered wash water filters (one common filter with a full spare for two parallel trains).
• Flashed water condenser (one common air cooler for two parallel trains).
• Flash water condensate drum (one common drum for two parallel trains).
• Flashed water steam ejector (one common ejector for two parallel trains).
• Flashed water condensate pumps (one common pump with a full spare for two parallel trains).
Washed syngas flows to the COS/HCN hydrolysis reactors.
COS / HCN Hydrolysis
The syngas contains trace amounts of carbonyl sulfide (COS) and hydrogen cyanide (HCN) and relatively large amounts of both H
2
and H
2
O. Hydrolysis of COS is required because the AGR removal step (SELEXOL) only removes about 50% of the COS fed to AGR. The quantity of
COS present in the raw syngas is such that if not hydrolyzed the concentration of COS alone in the feed to the gas turbines would be 60 ppmv for the 100% PRB case and 480 ppmv for the 50%
PRB / 50% petcoke case compared to the required 30 ppmv level for COS plus H
2
S. The use of catalytic hydrolysis reduces the contribution of COS in the gas turbine feed gas to 1 ppmv and 5 ppmv for the 100% PRB and 50% PRB / 50% petcoke cases, respectively.
Hydrolysis of HCN occurs simultaneously with COS and effectively removes the HCN from the
GTG feed gas. Removal of HCN, which is a form of fuel-bound nitrogen, results in less NO x emissions from the gas turbines. The same catalyst is appropriate for both hydrolysis steps.
The COS and HCN are hydrolyzed according to the following reactions:
COS + H
2
O Æ H
2
S + CO
2
4-8
Process Description
COS + H
2
Æ H
2
S + CO
HCN + 2 H
2
O Æ NH
3
+ H
2
+CO
2
Sud-Chemie provided operating conditions that are expected to result in COS and HCN conversions greater than 99%.
Unconverted H
2
S along with other components in the tail gas from the TGTU are recycled and mixed with the syngas just upstream of the feed / effluent exchanger associated with the hydrolysis reactor. The feed gas to hydrolysis is further heated with high-pressure boiler feedwater just prior to entering the hydrolysis reactor to raise the temperature to the required level.
The COS and HCN Hydrolysis system consists of the following equipment:
• Hydrolysis interchanger (one exchanger for each of two parallel trains).
• Hydrolysis reactor (one reactor for each of two parallel trains).
After passing through the hydrolysis reactor, the syngas flows to syngas cooling and condensation.
Syngas Cooling and Condensation
The syngas is cooled prior to flowing to mercury removal in a set of three heat exchangers:
• Sweet syngas from AGR provides the heat sink for the first stage.
• Condensate from the surface condenser of the steam turbine provides the heat sink for the second stage.
• Cooling water provides the heat sink for the third stage.
Water condensed from the syngas is separated from the syngas and flows to the sour water stripper. Part of the condensate is recirculated to a point just upstream of the first stage of condensation to assure that the stream entering the condenser is partially liquid.
Primary equipment items included:
• Syngas interchanger (one exchanger for each of two parallel trains).
• First stage syngas condenser (one exchanger for each of two parallel trains).
• Second stage syngas condenser (one exchanger for each of two parallel trains).
• Water knockout drum (one drum for each of two parallel trains).
• Sour water pumps (one pump plus a full spare for each of two parallel trains).
4-9
Process Description
Mercury Removal
It is important that the temperature of the feed gas to mercury removal be above the dew point in order to avoid contamination of the carbon bed with condensed water. For this reason the saturated syngas from syngas cooling and condensation is heated to approximately 5°F above the dew point prior to flowing to the mercury removal beds.
Adsorbent beds are used to remove mercury from the syngas. One bed is provided for each train.
Information from NUCON was used as the basis for the study. A mercury removal of 90% or greater is expected. This adsorbent is an activated carbon made from coal.
The mercury removal system consists of the following equipment:
• Mercury removal preheater (one exchanger for each of two parallel trains).
• Mercury adsorbent bed (one vessel for each of two parallel trains).
• Mercury removal aftercooler (one exchanger for each of two parallel trains).
After passing through the mercury removal beds the syngas is cooled with cooling water prior to flowing to AGR.
Acid Gas Removal (AGR)
UOP’s SELEXOL AGR system is generally considered to be the standard for acid gas recovery from IGCC syngas. However, it was felt that the relatively modest sweet syngas sulfur specification (30 ppmv) and the low sulfur content of the PRB-only feed case might allow the use of other technologies. Amine treating was one technology considered. After discussion with
UOP it was determined that the 30 ppmv specification benefits both the SELEXOL and amine processes, and that for the operating pressure of this study SELEXOL will at least be competitive with, if not preferred to, amine absorption. Further, the use of SELEXOL lends itself to future
CO
2
capture while amine treating does not. As a result of this analysis, amine treating was eliminated from further consideration for this study.
Another technology considered for the PRB-only, non-capture case was Sulferox. It was initially anticipated that the small sulfur recovery capacity needed (25 LTPD) would permit the use of a
Sulferox unit or similar redox technology in place of a SELEXOL AGR with Claus SRU and
SCOT-type TGTU. However, discussions with one vendor suggested that the best use of the redox unit would be as a replacement for the Claus/SCOT units. In this case the SELEXOL unit is still needed for acid gas removal. Another disadvantage of redox sulfur recovery is the relatively poor quality of sulfur product and additional handling and drying steps needed.
SELEXOL was subsequently chosen as the AGR technology for both the PRB-only and PRB-
PETCOKE cases for this study.
The SELEXOL solvent is a mixture of dimethyl ethers of polyethylene glycol. SELEXOL is a physical solvent, as compared to amines that form chemical complexes and require more energy to regenerate. SELEXOL solvent is chemically inert and is not subject to the same corrosion and degradation problems as amines.
4-10
Process Description
SELEXOL solvent has a higher affinity for H
2
S than CO
2
. This allows a SELEXOL system to achieve a very high rejection of H
2
S from the syngas, to meet the specification of less than 30 ppm of H
2
S + COS in the treated syngas, while allowing a controlled “slip” of CO
2
depending on the design requirements. Slip is defined as the percentage of CO
2
that leaves the system with the sweet syngas compared to the CO
2
in the feed to SELEXOL. CO
2
slip sets the concentration of
H
2
S in the acid gas product from the SELEXOL unit. Very high acid gas concentrations (greater than 50% H
2
S) require large, costly equipment and solvent circulation rates. Very low concentrations (less than about 25% for an oxygen-blown SRU that is also burning sour water stripper gas) complicate downstream SRU design and operation.
For each of the feed cases, UOP was asked to provide SELEXOL unit material balances and equipment lists for 25% and 50% H
2
S acid gas products. The information provided by UOP was evaluated and, based on this evaluation, acid gas concentrations of 25% and 50% H
2
S were selected for the PRB and PRB-PETCOKE cases, respectively. Although these are not completely optimized selections, they are believed to give reasonable estimates of capital and operating costs for the two cases.
SELEXOL consists of absorber and stripper towers, stripper reboiler, rich/lean solvent exchanger and flash drums typical for such systems. A simplified process flow diagram for SELEXOL is presented in Figure 4-3.
4-11
Process Description
Figure 4-3
SELEXOL Process Flow Diagram
The lean SELEXOL solvent is chilled using refrigeration to optimize the solvent circulation rate and energy input. Low pressure steam is used to supply heat to the stripper reboiler.
Primary equipment items included:
(Note: The AGR unit is a single train serving both gasifier trains.)
• H
2
S absorber.
• H
2
S stripper with reboiler, condenser, reflux drum and pumps.
• Rich flash coolers and drum.
• Lean / rich exchanger.
• Lean solvent chiller.
• Rich flash compressor.
• Refrigeration package.
4-12
Process Description
Sulfur Recovery and Tail Gas Treating
A block flow diagram of the SRUs and TGTU is shown in Figure 4-4. Acid gases from the AGR unit and from the sour water stripper (SWS) unit are treated in two parallel Claus SRUs to destroy hydrogen sulfide and ammonia. Tail gas from the two SRUs is combined and fed to a single TGTU to convert residual sulfur dioxide from the Claus process back to hydrogen sulfide before it is compressed and recycled to the COS Hydrolysis sections of the gas cooling trains.
To minimize the volume of recycle gas all of the oxygen required for SRU operation is supplied at 95% purity by the ASU. A thermal oxidizer is included to handle vent streams from the sulfur pits and truck/rail loading facilities.
Figure 4-4
Block Flow Diagram – Sulfur Recovery and Tail Gas Treating
Approximately 96% of the sulfur in the acid gas feeds is recovered in one pass through the
SRUs. By recycling the remaining hydrogen sulfide back through the gas cooling trains overall sulfur recovery from the syngas streams is increased to over 99%.
Sulfur Recovery Units (SRU)
Hydrogen sulfide is destroyed to form sulfur byproduct in Claus-technology SRUs. H
2 converted to sulfur according to the Claus reaction:
S is
2H
2
S + SO
2
↔ (3/n)S n
+ 2H
2
O
Sulfur dioxide is generated by reacting part of the H
2 thermal reactor:
S in the acid gas feed with oxygen in a
H
2
S + 1.5O
2
↔ SO
2
+ H
2
O
4-13
Process Description
The 2:1 mixture of SO
2
and H
2
S is then passed through a series of catalytic reactor stages to facilitate the Claus reaction. Sulfur is removed after each step by condensing it out of the vapor phase.
Sour water stripper gas is also fed to the SRUs for the purpose of ammonia destruction.
Ammonia is destroyed in the thermal reactor by either combustion or dissociation:
2NH
3
+ 1.5O
2
↔ N
2
+ 3H
2
O
2NH
3
• N
2
+ 3H
2
To destroy ammonia, the thermal reactor must operate above 2300-2400°F. For the 100% PRB case, the AGR acid gas feed contains only 25% hydrogen sulfide. As a result the heat content of the stream is very low. Part of the AGR acid gas stream must be bypassed around the thermal reactor and the remaining AGR acid gas must be preheated to achieve the high temperature needed for ammonia destruction. This is referred to as a split-flow SRU, and is a common application of the technology. For the 50% PRB / 50% petcoke, the AGR acid gas feed contains
50% hydrogen sulfide. The heat content of the stream is high enough to produce the necessary temperature without bypassing or preheating.
Waste heat boilers downstream of the thermal reactors produce saturated 600 psia steam. Part of the steam is used to heat the feeds to the catalytic reactor stages. The remainder is exported to the steam cycle for power generation. Each SRU has three stages of sulfur condensation, reheat and catalytic reaction. Low-level steam is produced in the sulfur condensers and exported to the steam cycle.
Tail gas from the final sulfur condenser goes to the Tail Gas Treating Unit. Elemental sulfur produced by the SRU is collected in a sulfur pit (sump). From there, the sulfur is pumped to the railcar loadout facility for transportation off-site.
Two 50% SRU trains are included in the estimate. Primary equipment items included for the
SRU trains are:
• AGR acid gas knockout drum (one for each train).
• AGR acid gas knockout drum pumps (one operating pump with one full spare for each train).
• AGR feed heater (PRB-only case, one for each train).
• Sour water stripper acid gas knockout drum (one for each train).
• Sour water stripper acid gas knockout drum pumps (one operating pump with one full spare for each train).
• Combustion air startup blower (one for each train).
• Thermal reactor and acid gas burner (one for each train).
• Waste heat boiler (one for each train).
• Sulfur condenser (one for each train).
4-14
Process Description
• Reheat exchangers (three for each train).
• Catalytic reactor vessel (one vessel with three compartments for each train).
• Final sulfur condenser (one for each train).
• Low-pressure steam condenser (one for each train).
• Sulfur pit (one for each train).
• Sulfur transfer pumps (one operating pump with one full spare for each train).
• Sulfur railcar loadout facility.
Tail Gas Treating Unit (TGTU)
The TGTU for this study consists of a catalyzed hydrogenation reaction step that converts residual sulfur dioxide back to hydrogen sulfide, followed by gas cooling. There is normally ample hydrogen and carbon monoxide present in the SRU tail gas for the reduction reaction.
However, if additional hydrogen is needed to feed the tail gas reactor, syngas can be added upstream of the reactor.
The tail gas reaction is:
SO
2
+ 3H
2
↔ H
2
S + 2H
2
O
Gas cooling includes a waste heat steam generator followed by direct contact with water in a packed quench tower. The small amount of water condensed in the quench tower is exported to the sour water stripper unit.
The amine absorber and regenerator that are typically attached to TGTUs for hydrogen sulfide recovery are not required in this service, since the tail gas is recycled to the gas cooling trains.
This eliminates a source of H
2
S/SO
2
emissions and improves recovery of carbon monoxide and hydrogen for power generation.
A single TGTU services both SRUs. The TGTU consists of the following equipment:
• Tail gas feed heater.
• Tail gas hydrogenation reactor.
• TGTU waste heat boiler.
• Quench tower.
• Quench water pumps (one operating pump with one full spare).
• Quench water air cooler.
• Quench water trim cooler.
4-15
Process Description
Tail Gas Compression
Multistage reciprocating compressors are required to boost treated tail gas to the pressure required for recycle to the gas cooling trains. Two full-capacity compressors with interstage knockout drums are provided for reliability.
A net production of carbonyl sulfide is anticipated through the SRUs and TGTU due to reactions of sulfur compounds with carbon monoxide and carbon dioxide. As a result, the tail gas must be recycled to a point upstream of the COS hydrolysis section. A small quantity of sour water is created as the tail gas is compressed. This water is exported to the sour water stripper unit.
Thermal Oxidizer
Purging of sulfur pit vapor spaces and vent recovery from sulfur loading operations will create vent streams containing mixtures of air and hydrogen sulfide. These vent streams are incinerated in the thermal oxidizer.
Sour Water Stripping
The sour water stripper receives feed from four sources:
• Vapor from the steam jet ejector associated with the system for handling the bottoms stream from the water wash towers.
• Condensate from the 7 psia flash of the bottoms stream from the water wash towers.
• Sour water from the knockout drums associated with syngas cooling and condensing.
• Sour water from the TGTU associated with sulfur recovery.
Water from the bottom of the sour water stripper joins the demineralized water and saturator purge water streams and flows to the top of the water wash towers. A pump-around loop with an air cooler provides condensing at the top of the sour water stripper. Low pressure steam serves as the heat source for the reboiler of the sour water stripper. Gas containing primarily H
2
S and ammonia, with lesser amounts of CO and H
2
, from the top of the sour water stripper is sent to the
SRU.
Primary equipment items included in the sour water stripper are:
• Sour water feed/effluent exchanger (one common exchanger for two parallel trains).
• Sour water stripper (one common tower for two parallel trains).
• Sour water pump around pumps (one common pump with a full spare for two parallel trains).
• Sour water pump around cooler (one common air cooler for two parallel trains).
• Sour water reboiler (one common exchanger for two parallel trains).
4-16
Process Description
Syngas Saturation
Sweet syngas from the AGR, after exchanging heat with the sour syngas in the first condensing stage, flows to the syngas saturators. The purpose of the saturators is to add vaporized water to the syngas to bring the moisture content to 16.5 mole % for NO x
reduction, which also results in additional mass flow through the turbine section (i.e. more power). The wet syngas is further preheated with high-pressure (HP) boiler feedwater to raise the temperature to 405°F before serving as fuel for the gas turbines.
Demineralized water, after heat exchange with the recovered water from the water wash towers, is fed to the circulating loops of the syngas saturators in amounts required to achieve the desired moisture content of the syngas. A small purge stream from the circulating loops joins the other water streams that flow to the top of the water wash towers. This avoids buildup of any components in the water that do not vaporize.
Water in the circulation loops is heated with HP boiler feedwater as required to maintain the level in the bottom of the syngas saturators, thus assuring that the water added to the loop is vaporized and added to the syngas.
Primary equipment included for syngas saturation is as follows:
• Syngas saturator (one tower for each of two parallel trains).
• Saturator heater (one exchanger for each of two parallel trains).
• Saturator circulation pumps (one pump plus a spare for each of two parallel trains).
• Sweet syngas heater (one exchanger for each of two parallel trains)
After passing through the syngas saturators, the syngas is ready for use in the power block.
Power Block Description
The power block of the IGCC consists of the gas turbines, HRSGs, steam turbine, condenser, and interconnecting pipe, pumps, etc. as required for the power production duty. The power block of an IGCC is very similar to that of a standard combined cycle.
Gas Turbines
The Project consists of two GE PG7251FB (7FB) gas turbines rated at 232 MW each on syngas.
Like a conventional combined cycle or gas turbine plant, ambient conditions (in particular compressor inlet temperature) can greatly affect the performance of an IGCC facility. A gas turbine is a constant volume machine, therefore, lower compressor inlet temperatures result in greater air density, which results in more power output and decreased heat rate. Similarly, higher ambient temperatures result in lower air density, which results in lower output and higher heat rate.
4-17
Process Description
Because of the low heating value of the syngas, the fuel mass flow through the gas turbine is significantly higher than a standard natural gas fired turbine (approximately 4 times greater).
This additional mass flow, coupled with the additional nitrogen mass flow for NO x
control, increases the gas turbine output over that of a conventional gas turbine firing natural gas. This causes the gas turbine to reach its shaft limit at a higher ambient temperature than it typically would. Therefore, the gas turbine output must be limited to avoid exceeding the shaft limit of the turbine (232 MW for the 7FB). This is accomplished by extracting a portion of the air from the compressor section of the gas turbine for gas turbine compressor inlet temperatures (CIT) below ~70°F. This compressed air is utilized in the ASU, which reduces the additional auxiliary load of compression required by the ASU compression system. At CITs above ~70°F, the air density is low enough that the total mass flow through the turbine does not result in sufficient
MW to exceed the shaft limit of the gas turbine. Thus air extraction from the compressor section of the gas turbine is not available for ASU use at CITs above ~70°F. Exporting of air from the
GTG to the ASU is referred to as air-side integration.
Since air-side integration improves the efficiency of the IGCC facility, it is beneficial to export as much air as possible to the ASU. Therefore, 85% effective evaporative cooling is included on the inlet to each gas turbine to lower the compressor inlet temperature, resulting in improved mass flow available for the turbine and the ASU.
Alternatively, inlet air chilling could be used to further reduce the CIT. Inlet air chilling has a higher capital cost than evaporative cooling and may not be economically justified since this equipment will not be fully utilized for a significant portion of the year. It is recommended that further studies regarding inlet air cooling methods and tradeoffs be pursued.
Heat Recovery Steam Generators (HRSG)
Two HRSGs are utilized to capture the gas turbine exhaust heat. Triple pressure, naturalcirculation HRSGs are utilized to preheat feedwater, generate steam, and superheat both the steam generated within the HRSG and the saturated steam from the gasification process. The
HRSGs also utilize a reheat section to further increase steam cycle efficiency.
Alternatively, two-pressure HRSGs could be utilized in lieu of three-pressure HRSGs, thus eliminating the LP evaporator and superheater sections of the HRSG. The loss of the LP section would result in reduced steam flow to the STG (i.e. less output), however since very little LP steam is being generated in the HRSG (particularly for the 100% PRB cases), this increased capital (approximately $5 million), may not be justified. Alternatively, a large amount of LP steam is generated in the CO
2
capture case (Chapter 13), which is of great benefit in that scenario. Further analysis into the use of a two-pressure HRSG should be performed in the future.
Steam Turbine
The total steam is expanded in a steam turbine to generate power. The steam turbine consists of three turbine sections (HP, IP, LP), utilizing a dual down flow LP turbine exhaust. The steam from the low pressure turbine exhaust is condensed by the heat rejection system.
4-18
Process Description
The design pressure is 1905 psia with 1050°F main steam and hot reheat temperatures. The turbine will drive a hydrogen-cooled electric generator.
Steam Condenser
The water-cooled steam condenser will be a single, rectangular shell, single pressure, split waterbox, two pass steam condenser. The water-cooled condenser will include an air removal section and baffled steam inlet connections for the 100% steam turbine bypass. Air removal from the condenser’s upper portion will be via two full capacity vacuum pumps. To dissipate the energy in the condensing steam, a circulating water system will supply cooling water from the wet cooling tower to the water-cooled steam condenser. The steam condenser is designed with a
5°F terminal temperature difference (TTD) and a 17°F range at the 73°F ambient condition.
Steam System
The steam system transports main steam (HP), reheat steam, intermediate pressure (IP) steam and low pressure (LP) steam between the HRSGs and steam turbine. A steam turbine bypass system is included to accommodate the steam generated by the HRSG during start-up of the gas turbine before steam turbine admission, as well as during a full-load steam turbine trip.
Condensate System
The condensate system delivers condensate via two, 100% capacity vertical, condensate pumps.
These pumps transport condensate from the steam condenser hotwell, through the gland steam condenser to the low pressure HRSG drum.
Feedwater System
The feedwater system provides feedwater to the HP and IP HRSG economizers, gasifier and syngas cooler via two 100% capacity, HP/IP boiler feed pumps per HRSG. This system also supplies desuperheating water requirements for the HRSGs and steam turbine bypass system.
Natural Gas System
The natural gas system provides pipeline quality natural gas to the gasifier and auxiliary boiler for startup and the gas turbine for backup fuel. It is assumed that the natural gas is available at the site boundary at sufficient pressure (~570 psig) to avoid the need for compressors.
4-19
Process Description
Balance of Plant
Coal Handling
Fuel delivery to the site is accomplished by rail. A rotary car dumper is provided for unloading of the coal. The coal handling system provides for the stackout, storage, and reclaim of the solid fuel for this project. Outdoor storage is assumed at this stage of the project. Layout drawings provided in Appendix B help to illustrate these systems.
100% PRB Option
The coal handling system unloads the coal with a rotary car dumper and conveys the coal with a stockout conveyor to the stockout pile. From the stockout pile, coal is moved with mobile equipment to long term storage or to the reclaim system. The reclaim system consists of a hopper, belt feeder, reclaim tunnel, and dust collection. The reclaim system supplies the coal to the inlet of the coal drying and milling equipment supplied with the gasifier.
Because PRB is shipped long distances, 60 days of long term PRB storage is provided to lessen the possibility of fuel interruption.
50% PRB / 50% Petcoke Option
The coal handing system for the fuel blend case is similar in concept to the 100% PRB option.
The stockout conveyor has an intermediate transfer tower that allows for stockout into one of two piles. Weight feeders on the reclaim system allows for accurate blending of the fuel prior to the coal drying and milling equipment. Each fuel has its own stockout pile and reclaim system.
Similar to the 100% PRB option, 60 days of long term PRB storage is included. Petcoke is produced locally, thus reducing the potential for supply interruption, thus only 30 days of petcoke storage is provided.
Cooling System
Cooling for the condenser, ASU, and other auxiliary cooling loads is accomplished by a multicell, counter flow, mechanical draft, wet cooling tower. Circulating water is transported between the water-cooled steam condenser and cooling tower by two 60% capacity circulating water pumps. Additionally, two 60% capacity auxiliary cooling water pumps are used to supply auxiliary cooling water to the ASU, and other auxiliary cooling loads.
The cooling system is designed with a 2°F recirculation allowance and an 11°F approach (wet bulb minus cold water temperature).
4-20
Process Description
Auxiliary Boiler
A natural gas fired package boiler (approximately 200,000 lb/hr @ 150 psig) is included for preheat of the gasification area heat exchangers and providing steam to the critical systems during plant startup. Since this system is only required during startup sequence procedure, it is anticipated to be used less than 200 hours per year.
Buildings
The IGCC facility has the following major buildings:
• Administration and control room building.
• Water treatment building.
• Warehouse.
• Auxiliary boiler.
• Yard maintenance building.
• Cooling tower chemical building.
Water Treatment
Water mass balances are provided in Appendix C. Consumptive water uses include potable/sanitary water, plant service water, demineralized water, cooling tower make-up, and fire water. Raw water for the site is based on the wells with water quality shown in Table 4-3.
4-21
Process Description
Table 4-3
Assumed Raw Water Quality
Data Type Data Units
uS/cm
2
Specific Conductance 607
Hardness 224 mg/L as CaCO
3
Calcium
Magnesium
Sodium
Potassium
Chloride
Sulfate
72
11
44
0
26
15 mg/L as Ca mg/L as Mg mg/L as Na mg/L as K mg/L as Cl mg/L as SO
4
Silica pH
Fluoride
Total Alkalinity
36 mg/L as SiO
2
7.5
0.4
mg/L as Fl
189 meq/L as CaCO
3
Raw water supply and wastewater discharge requirements (on a local, state, and federal level) vary greatly from location to location. Once more information is known about that anticipated project site, additional studies should be performed to verify raw water availability and wastewater discharge viability for the project. These issues have the potential to greatly impact the cost and performance of the project.
Raw Water/Service Water
Raw water from the on-site wells is routed to an on-site raw water storage pond that stores 30 days of raw water. This storage pond may not be required if a highly reliable source of water is available, however most Owners of large coal generating stations are incorporating some amount of raw water storage to hedge against potential shortfalls in water availability. From the raw water pond, the water is routed to the raw water treatment where the majority of suspended solids, iron, and manganese will be removed by filtration and sodium hypochlorite injection prior to entering the service water storage tank (which also serves as the firewater storage tank).
Service water uses include coal pile dust suppression, gasifier slag quenching, pump seals, equipment wash water, fire water, and other miscellaneous sources.
The raw water also serves as the major source cooling tower make-up (along with demineralizer reject, and Gasifier and HRSG blowdown). The cooling tower requires water treatment chemistry and blowdown to prevent scale and biological formation and corrosion on piping and heat transfer surfaces.
4-22
Process Description
Demineralized Water
Raw water is routed to the demineralizer system that consists of reverse osmosis and electrodeionization (EDI) equipment designed to produce high purity water for various uses in the gasifier and HRSG. Reject from this system is routed to the cooling tower as an additional make-up source. The demineralized water is stored in a demineralized water storage tank.
Wastewater
Blowdown from the cooling tower, coal pile wastewater, reject from the raw water treatment, and clean effluent from the plant drains are routed to a common wastewater collection pond prior to discharge to a nearby river.
Sanitary Drains
Plant sanitary drains are routed to an on-site septic system.
Flare
A flare system is included to burn off syngas produced the by gasifier during startup or in the event of a unit trip or pressure excursion. The flare is located at a safe distance (600 ft. radius) from accessible areas. A perimeter fence is placed around the flare to prevent people and animals from approaching the flare.
A 200 ft. tall guyed flare with a 60 in. flare tip is provided in the estimate. A knockout drum and pumps are included upstream of the flare.
Fire Protection
Fire protection water is supplied from the raw water storage tank with an electric motor driven fire pump, a diesel engine driven fire pump and an electric motor-driven jockey pump. Fire protection and detection systems will be in accordance with NFPA requirements. A fire water loop with sectionalizing valves is included around the plant. Automatic and semi-automatic fire protection systems employing detection and extinguishing equipment and hose stations are included for the generator step-up transformers, steam turbine lube oil system, cooling tower, buildings, Gasification Systems, and coal handling and storage. Fire hydrants, monitors, and fire extinguishers will be strategically positioned throughout the plant for coverage of fuel conditioning equipment, cooling tower fan deck, steam turbine, gas turbine, and gasificationrelated areas. The gas turbine fire protection system is supplied with the equipment. The fire detection system will provide detection throughout the plant and annunciation in the main plant control room.
4-23
Process Description
Plant Drains
The plant drains system collects liquid waste (non-sanitary) from plant areas and equipment and transfers the waste to the wastewater treatment system. This system includes sumps and two
100% capacity pumps for each sump. Equipment drains will be located adjacent to all equipment requiring intermittent or continuous drainage during operation or shutdown. Plant drains with potential oil contamination will be drained to the oil-water separator.
Electrical Systems
The electrical systems for the IGCC facility consist of the auxiliary power supply, generator feed, switchyard, essential AC and DC power supply, and freeze protection systems.
Auxiliary Power Supply
The auxiliary power system provides electric power for all systems in the plant.
The power distribution for the power block and gasifier plant is supplied from the main 13.8kV distribution switchgear. The main 13.8kV distribution switchgear is supplied from two plant auxiliary power transformers that are connected to the low side of the gas turbine GSU transformers that are connected to the 345kV substation.
The main 13.8kV distribution switchgear supplies the following 4.16kV switchgear lineups located in the power block and throughout the plant. Each of the 4.16kV buses is located in a power control module (PCM) placed in the vicinity of the loads.
• Power block switchgear A.
• Power block switchgear B.
• Coal handling switchgear.
• Gasification switchgear.
• Balance of plant bus.
• Sulfur & slag bus.
Each of the 4.16kV switchgear lineups supplies multiple station service transformers that supply
480V load centers arranged in a main-tie-main configuration. The load centers supply the 480V motor and non-motor loads. The 480V motor loads are supplied from motor control centers
(MCC) that are connected to the 480V load centers. The 480V load centers and 480V MCCs are located in the PCM buildings along with the 4.16kV switchgear lineup. The station service transformers are located outside the PCM buildings. The small power loads are supplied from
120/240-volt utility panels located in the PCM.
4-24
Process Description
The power distribution for the ASU is supplied from the ASU 13.8kV distribution switchgear.
The ASU 13.8kV distribution switchgear is supplied from two auxiliary power transformers that are connected to a single overhead line from the 345kV substation. Each auxiliary power transformer connects to a 13.8kV switchgear bus that supplies the ASU compressor motors and a
13.8kV to 480V station service transformer. The station service transformers connect to 480V switchgear buses that are interconnected with tie breakers.
A plant emergency generator is connected to the 4160 volt bus. The natural gas engine-generator is sized to start and operate the emergency loads of the facility.
Generator and Excitation
The generator system provides power from the gas turbine and steam turbine generators to the generator step-up transformer.
The generator system consists of the following:
• Auxiliary transformer.
• Isolated phase bus.
• Generator step-up transformer.
• Protection devices.
• Wiring, instrumentation, and controls.
The excitation system provides controlled DC power to the generator field. The exciter system consists of the following:
• Power potential transformer (PPT) that is connected to the generator terminals with an isolated phase bus tap. The power potential transformer steps down the generator voltage for use by the exciter.
• Static exciter system supplied by the turbine manufacturer. The exciter systems convert the AC power for the PPT to a DC power source applied to the generator rotor to establish the generator field. The system controls the generator field current to regulate the generator terminal voltage, power factor, or VAR flow.
Switchyard
The switchyard configuration is a three-bay breaker-and-a-half arrangement consisting of 9 breakers. The switchyard has dedicated positions for each generator step-up transformer, two incoming transmission lines, and on-site transmission to the ASU.
4-25
Process Description
The high-voltage equipment is rated for 345kV nominal operating voltage.
Essential AC and DC Power Supply
The essential AC and DC power system provides highly reliable power to such essential low power loads as DCS, logic systems, annunciators, events recorder, data loggers and computers, communications equipment, intercommunications systems and emergency lighting. Essential power for the gas turbine and its auxiliaries is provided by gas turbine manufacturer as part of the gas turbine package.
Separate plant uninterruptible power supply (UPS) systems are provided for the power block and
Gasification System. The equipment for the essential power supply consists of:
• DC chargers and batteries.
• Operator terminals.
• DC switchboard.
• Single phase UPS.
• Electrolytic capacitors.
• Wire, instrumentation, and controls.
Freeze Protection
The freeze protection system maintains temperature above the freezing point in piping and equipment. The freeze protection system consists of
• Heat tracing cable.
• Voltage monitors.
• Thermostats.
• Contactors.
• Control cabinets.
4-26
5
TERMINAL POINTS
General
The following terminal points identify the termination points or interfaces for those services or facilities, which extend beyond the scope of the work included in this report.
Site Access
Site access roads shown on the layout drawings in Appendix B are included in the capital cost estimate. Any roads or road upgrades to the site are not included in the estimate.
Rail Siding
The capital cost estimate includes a 5 mile rail siding to the site plus the track shown on the layout drawings in Appendix B. It is assumed that all large equipment is delivered to the site via rail. Heavy haul costs are included to offload the equipment from the rail to the foundations.
Modifications to any existing rail or road infrastructure are not included.
Sanitary Waste
Sanitary waste is disposed of in an on-site septic system.
Natural Gas
The capital cost estimate includes one mile of 12 in. natural gas pipeline to the site for startup and backup fuel. Additionally, Burns & McDonnell’s estimate includes natural gas metering and pressure regulation equipment. It is assumed that natural gas will be supplied by others at sufficient pressure (~570 psig), temperature, quality, and flow to meet the requirements of the
IGCC facility without the need for natural gas compression or dew point heating.
Raw Water Supply
Raw water is assumed to be available through on-site wells. The capital cost estimate includes the well water system. If well water is unavailable or other sources of water are required to supplement the well water supply, the costs of these items are by others.
5-1
Terminal Points
Wastewater Discharge
Wastewater is assumed to be discharged to a river through a wastewater pipeline 5 miles in length after being treated in the on-site wastewater treatment pond. The capital cost estimate includes the cost of the wastewater pipeline and on-site wastewater treatment pond. Any other means of wastewater discharge is outside the scope of this estimate.
Electrical Interface
The project capital cost estimate includes the electrical interconnection costs up to and including the plant switchyard. Transmission lines to the site or transmission upgrades are by others.
5-2
6
IGCC PERFORMANCE ESTIMATES
Performance Estimate Assumptions
The following assumptions are used as the basis for the performance estimates:
• Output and heat rate estimates are at new and clean conditions.
• An 85% effective evaporative cooler is included and is on for the 93°F case.
• Performance is based on an elevation of 100 ft.
• Performance is based on the fuel analysis provided in Table 3-1.
• Gas turbine performance and Shell gasification performance estimated by EPRI without vendor involvement.
• Steam turbine consists of three turbine sections (HP, IP, LP) with a dual down flow exhaust. The design throttle conditions are 1905 psia with 1050°F main steam and hot reheat temperatures.
• Air-side integration is used to supplement air flow to the ASU when the gas turbine has reached its shaft limit (for CIT below ~70°F).
• Performance is based on a wet cooling tower.
Performance Estimate Results
The results of the performance analysis are provided in Table 6-1. Heat balance diagrams containing additional information are provided in Appendix F.
6-1
IGCC Performance Estimates
Table 6-1
IGCC Performance Summary
Ambient Dry Bulb Temperature, °F
Ambient Wet Bulb Temperature, °F
Elevation, ft.
Evaporative Cooling, On/Off
Coal Heat Input, MMBtu/hr (LHV)
Coal Heat Input, MMBtu/hr (HHV)
Gas Turbine Gross Output, MW (each)
Gas Turbine Gross Output, MW (total)
Steam Turbine Gross Output, MW
Gross Plant Output, MW
Auxiliary Load
Power Block, MW
Material Handling, MW
Air Separation Unit, MW
Gasifier, MW
CO
2
Compression
Syngas Treatment, MW
Total Plant Auxiliary Load, MW
Net Plant Output, MW
Net Plant Heat Rate, Btu/kWh (LHV)
Net Plant Heat Rate, Btu/kWh (HHV)
Plant Cooling Requirements, MMBtu/hr (Total)
Steam Cycle Cooling Requirement, MMBtu/hr
BOP Auxiliary Cooling Requirement, MMBtu/hr
Total Makeup Water Requirement
GPM
Acre-ft/year (@ 85% CF)
599.2
8,390
9,090
2,155
1,550
605
22.5
6.3
101.3
2.3
0.0
5.0
137.4
43
40
100
Off
5,026
5,447
232.0
464.0
272.6
736.6
4,390
6,830
100% PRB
73
69
100
Off
4,705
5,099
224.9
449.7
260.1
709.9
553.0
8,510
9,220
2,141
1,480
661
22.0
5.9
122.1
2.1
0.0
4.7
156.8
4,980
6,830
528.4
8,630
9,350
2,159
1,450
709
21.8
5.8
119.1
2.0
0.0
4.5
153.2
93
77
100
On
4,559
4,940
215.6
431.2
250.4
681.5
5,580
6,830
597.0
8,560
8,950
2,185
1,540
645
22.0
4.5
101.1
2.2
0.0
7.4
137.2
43
40
100
Off
5,113
5,343
232.0
464.0
270.1
734.2
50% PRB / 50% Petcoke
73
69
100
Off
4,800
5,016
226.3
452.7
258.4
711.1
93
77
100
On
4,655
4,864
217.0
433.9
248.7
682.6
4,619
7,170
553.0
8,680
9,070
2,179
1,480
699
21.9
4.3
122.9
2.1
0.0
6.9
158.0
5,231
7,170
528.2
8,810
9,210
2,206
1,460
746
21.6
4.1
120.0
2.0
0.0
6.7
154.5
5,800
7,170
The power block auxiliary load includes gas turbine auxiliary loads, steam turbine auxiliary loads, power block pumping loads, transformer losses, iso-phase bus losses, and miscellaneous
BOP auxiliary loads (lighting, HVAC, air compression, etc.). Additionally, the power block auxiliary loads include the cooling water pumps and cooling tower that provide the cooling loads for the entire facility.
Material handling auxiliary loads include the loads associated with coal conveying and coal milling and drying equipment.
Air separation unit auxiliary loads include the main air compressor, booster air compressor, cold box, nitrogen compression, cryogenic pumping, and miscellaneous ASU auxiliary loads.
Gasifier auxiliary loads include recycle quench gas compressor loads and slag handling loads.
Syngas treatment auxiliary loads include AGR, SRU, TGTU, and miscellaneous process loads.
6-2
7
IGCC CAPITAL COST ESTIMATES
Capital Cost Estimate Assumptions
• All estimates are “screening level” in nature and do not reflect guaranteed costs (+/- approximately 30%).
• Project is based on a greenfield site.
• Project cost is based on the terminal points as defined in Chapter 5.0.
• It is assumed that 10 ft. of cut is required for half the site area and 10 ft. of fill is required for the other half of the site area. Other areas may require more cut and fill, however an average cut/fill of 10 ft. is assumed. Additionally, it is assumed there are no existing structures, underground utilities, or hazardous materials on site.
• Project costs are based on a preliminary site layout drawings included in Appendix B.
• Project costs are based on preliminary electrical one-line diagrams included in Appendix
D.
• Preliminary foundation design is based on the assumption that shallow, mat-type foundations will be sufficient for all minor foundations. Major structures such as the gas turbines, HRSGs, steam turbine, step up transformers, gasifiers, and the major equipment for the ASU, AGR, SRU, TGTU, and coal reclaim are assumed to require piling.
• The steam turbine, gas turbines, and HRSGs are located outdoors.
• Sufficient area to receive, assemble, and temporarily store construction materials is available.
• The design fuel is based on the information provided in Table 3-1.
• An on-site landfill is included for disposal of flyash and slag. The capital cost estimate includes the initial 5-year cell. The ongoing cost of closing current cells and the addition of future cells is covered in the landfill cost ($/ton) used in the O&M estimate.
• Cooling is achieved through the use of conventional wet cooling towers.
7-1
IGCC Capital Cost Estimates
• Construction costs are based on an engineer, procure and construct (EPC) contracting philosophy. The Owner would have an EPC contract with a single “Global EPC” contractor. It is assumed the Global EPC contractor will contract the ASU, gasification, and syngas treatment as separate EPC contracts (under the Global EPC). The Global
EPC contractor is responsible for integration of the construction and design aspects of all
EPC contractors and assumes overall risk for schedule, performance, and capital cost.
• Labor rates are based on prevailing wage rates and productivity factors for the Texas Gulf
Coast. Labor rates include a $9/hour per diem to account for non-local labor (assumed
90% outside 50 miles).
• All capital cost estimates are in mid-2006 dollars and do not include escalation through the COD, sales tax, interest during construction, financing fees or transmission lines/upgrades.
Indirect Construction Costs (Included in EPC Cost)
The following project indirect costs are included in the EPC capital cost estimate:
• Construction water and power.
• Performance testing and CEMS/stack emissions testing (where applicable).
• Initial fills and consumables, preoperational testing, startup, startup management, and calibration.
• Construction/startup technical service.
• Heavy haul
• Site surveys and studies.
• Engineering and construction management.
• Construction testing.
• Operator training.
• Startup spare parts.
• Performance and payment bond.
• EPC contingency.
• EPC Fee.
7-2
IGCC Capital Cost Estimates
Owner Indirect Costs
In addition to the estimated EPC costs, an estimate of anticipated Owner’s costs was also provided. The Owner’s costs included in the estimate are as follows:
• Project development costs.
• Owner project management and project engineering (including startup).
• Owner’s operations personnel prior to COD.
• Owner’s construction management.
• Owner’s engineer.
• Permitting and licensing fees.
• Land (1,500 acres for accommodation of future expansion to 3 x 550 MW units).
• Political concessions / area development allowance.
• Startup consumables, including fuel.
• Credit for test power sales.
• Initial fuel inventory (60 days PRB, 30 days petcoke).
• Builder’s risk insurance.
• Site security.
• Owner’s legal costs.
• Operating spare parts.
• Permanent plant equipment and furnishings.
• Owner’s contingency (5% of entire project cost).
7-3
IGCC Capital Cost Estimates
Costs not included
The costs not included in the capital costs estimates include, but are not limited to the following:
• Escalation through COD is not included. The EPC and Owner’s costs provided are in overnight 2006 US dollars. This cost does not represent the cost of an EPC contract signed today. It represents the cost of the project assuming zero time value of money.
Additional escalation needs to be applied by the Owner as a part of the Owner’s
Integrated Resource Plan to determine when the project would fit into the generation needs of the Owner.
• Sales Tax is not included. Because sales tax requirements differ greatly depending on location (even within a state), sales tax has been excluded from this estimate. In some instances, emissions controls equipment have been known to be tax exempt, so it is possible that a large part of the IGCC facility may be tax exempt, if not all. Additionally, some municipalities or utilities are tax exempt. If this project proceeds and a site is chosen, it is recommended that a detailed investigation into sales tax be pursued at that time.
• Interest during construction is not included in the capital cost estimates provided herein.
Since the estimates provided are in overnight 2006 US dollars, applying interest during construction is not feasible. However, interest during construction costs are a very significant project cost that must included separately once a desired COD is determined, which will increase the overall capital cost of the project. Interest during construction is included in the 20-year levelized busbar cost ($/MWh) discussed in Chapter 12.
• Financing fees are not included in the capital cost estimates provided herein. However, financing fees are included in the 20-year levelized busbar cost ($/MWh) discussed in
Chapter 12.
• Transmission lines to or from the site are not included. Additionally, transmission upgrades, if required, are not included.
Capital Cost Results
The estimated capital costs for the project are provided in Table 7-1. Additional cost detail can be found in Appendix E.
7-4
IGCC Capital Cost Estimates
Table 7-1
IGCC Capital Cost Estimate Summary (2006 US Dollars)
Procurement
Gas Turbines
Steam Turbine
HRSGs
Other Mechanical
Electrical
Water & Chemical Treatment
Structural
Construction
Furnish and Erect
Material Handling
Air Separation Unit and N2 Storage
Gasification
Syngas Treatment
GTG/STG/HRSG Erection
Civil / Structural Construction
Mechanical Construction
Electrical Construction
EPC Contractor Indirect Costs
Construction Indirects
Construction Management
Pre-operational startup and testing
Other
Project Indirects
Project Management and Engineering
EPC Contingency
EPC Fee
Other
Total EPC Contractor Cost (2006 US $)
Owner Indirect Costs
Owner's Engineer
Permitting and Licensing Fees
Land
Initial Fuel Inventory
Operating Spare Parts
Permanent Plant Equipment and Furnishings
Builder's Risk Insurance
Owner Contingency
Other
Total Owner's Cost (2006 US $)
Total Project Cost (2006 US $)
Total EPC Contractor Cost (2006 US $), $/kW (73°F)
Total Project Cost (2006 US $), $/kW (73°F)
550 MW (Net) IGCC
100% PRB
550 MW (Net) IGCC 50%
PRB / 50% Petcoke
$ 86,000,000 $ 86,000,000
$ 22,950,000 $ 22,950,000
$ 28,080,000 $ 28,080,000
$ 46,720,000 $ 47,220,000
$ 47,820,000 $ 50,320,000
$ 2,380,000 $ 2,380,000
$ 1,600,000 $ 1,600,000
$ 36,660,000 $ 44,300,000
$ 102,400,000 $ 102,400,000
$ 354,310,000 $ 306,360,000
$ 149,990,000 $ 158,150,000
$ 20,730,000 $ 20,730,000
$ 94,740,000 $ 96,290,000
$ 42,070,000 $ 42,070,000
$ 23,030,000 $ 23,480,000
$ 24,710,000 $ 24,710,000
$ 8,230,000 $ 8,230,000
$ 4,790,000 $ 4,790,000
$ 40,000,000 $ 40,000,000
$ 57,100,000 $ 55,740,000
$ 119,910,000 $ 117,050,000
$ 4,760,000 $ 4,690,000
$ 1,318,980,000 $ 1,287,540,000
$ 23,000,000 $ 23,000,000
$ 2,910,000 $ 2,910,000
$ 7,500,000 $ 7,500,000
$ 10,930,000 $ 6,190,000
$ 10,060,000 $ 10,120,000
$ 4,600,000 $ 4,600,000
$ 5,940,000 $ 5,790,000
$ 70,200,000 $ 67,950,000
$ 20,100,000 $ 11,440,000
$ 155,240,000 $ 139,500,000
$ 1,474,220,000 $ 1,427,040,000
$ 2,390 $ 2,330
$ 2,670 $ 2,580
7-5
8
IGCC OPERATIONS AND MAINTENANCE
O&M Assumptions
The following describes the methodology and major assumptions used in the development of the
O&M estimate.
• Fixed costs include such items as plant staffing, office and administration, training, safety, contract staff, annual inspections, standby power energy costs and other miscellaneous fixed costs.
• Variable costs include such items as gas turbine, steam turbine, HRSG, gasifier, and syngas treatment scheduled maintenance, water treatment, wastewater disposal, consumables, landfill costs, balance of plant equipment maintenance and replacements, unplanned maintenance activities, and estimated emissions allowance costs.
• Emissions allowance costs are included in the variable O&M at $3,000/ton of NO x
,
$1,000/ton of SO
2
, and $20,000/lb of mercury, based on input from CPS Energy.
• Costs are shown in 2006 US dollars.
• 85% capacity factor (7446 hrs/year at 100% load).
• 2 cold starts per year.
• Additional staff is required above that of a PC unit due to the additional process-related equipment associated with an IGCC project. 126 full time operations and maintenance personnel have been assumed.
• The gas turbine major maintenance costs are based on Long Term Service Agreement
(LTSA) contracts with GE executed for similar equipment.
• Other fixed and variable O&M estimates are based on information obtained by Burns &
McDonnell from plant operators of similar installations.
• Raw water is available at zero cost (other than treatment costs) and wastewater is discharged to a river at zero costs (other than treatment costs)
8-1
IGCC Operations and Maintenance
• Flyash (the amount not recycled to the gasifier) and slag are landfilled on-site at a cost of
$11.29/ton. This cost includes the ongoing cost of closing old landfill cells and expanding the landfill in the future.
• Sulfur produced in the SRU is assumed to be sold at zero cost, thus avoiding any disposal cost.
O&M Exclusions
The costs not included in the O&M estimates include, but are not limited to the following:
• Property taxes.
• Insurance (included in economic analysis).
• Fuel and fuel supply costs (included in economic analysis).
• Initial spare parts (included in capital cost estimate).
O&M Results
The estimated O&M costs for the project are provided in Table 8-1. Additional O&M cost detail can be found in Appendix G.
8-2
IGCC Operations and Maintenance
Table 8-1
IGCC O&M Summary (2006 US Dollars)
100% PRB 50% PRB / 50%
Petcoke
Fixed O&M
Labor, $/yr
Office and Admin, $/yr
Major Inspections, $/yr
Standby Power Energy Costs, $/yr
Other Fixed O&M, $/yr
Fixed O&M, $/yr
Variable O&M (85% CF)
Emissions Allowance Costs, $/yr
NO x
Emissions Allowance Cost
SO
2
Emissions Allowance Cost
Hg Emissions Allowance Cost
Major Maintenance Costs, $/yr
Steam Turbine / Generator Overhaul
HRSG Major Replacements
Gasifier Replacements
Candle Filter Major Replacements
Gas Turbine Major Replacements
Syngas Treatment Major Replacements
Air Separation Unit Major Replacements
Mercury Carbon Bed Replacements
HCN/COS Hydrolysis Catalyst Replacements
Shift Catalyst Replacements
Demin System Replacements
Water Treatment, $/yr
Fly Ash & Slag Disposal
Other Variable O&M, $/yr
Variable O&M, $/yr (85% CF)
Fixed O&M, $/kW-yr
Variable O&M, $/MWh
Total O&M Cost, $/Year (85% CF)
$ 11,835,700 $ 11,835,700
$ 118,400 $ 118,400
$ 400,000 $ 400,000
$ 98,600 $ 98,600
$ 1,479,500 $ 1,479,500
$ 13,932,200 $ 13,932,200
$ 3,588,300 $ 3,472,900
$ 360,700 $ 429,400
$ 590,000 $ 370,600
$ 260,400 $ 260,400
$ 200,000 $ 200,000
$ 885,800 $ 765,900
$ 300,000 $ 300,000
$ 8,148,700 $ 8,148,700
$ 375,000 $ 395,000
$ 275,000 $ 275,000
$ 530,300 $ 530,300
$ 640,000 $ 640,000
$ - $ -
$ 3,600 $ 3,600
$ 1,479,100 $ 1,523,700
$ 1,560,200 $ 642,100
$ 5,297,400 $ 5,355,600
$ 24,494,500 $ 23,313,200
$ 25.19 $ 25.19
$ 5.95 $ 5.66
$ 38,426,700 $ 37,245,400
8-3
9
IGCC AVAILABILITY
General
Some IGCC facilities have been evaluated with a spare gasifier to increase availability factors and allow increased operational flexibility. It is anticipated that adding a spare gasifier train will improve the availability factor of the IGCC facility by approximately 5 percentage points. The spare gasifier is typically operated in hot-standby mode which requires natural gas (or syngas if available) to maintain the metal temperatures within the gasification system. This significantly reduces gasifier startup time in the event that one of the gasifiers is forced off-line. The benefits of the spare gasifier, however, come at a large operating and capital expense (approximately 20% capital cost increase). For these reasons, a spare gasifier was not considered for this project.
Assumptions and Clarifications
Plant availability factors are typically determined from historical data of existing plants, which is often a good predictor for the future. Since IGCC technology is relatively new, published availability information is difficult to obtain.
The availability factor is a measure of the amount of the year that the plant or unit is available to operate and produce electricity. It includes the effect of both planned and forced outages.
Past data from existing IGCCs has indicated availability factors of 83-85% for designs that do not utilize a spare gasifier. These existing facilities had first year availabilities of approximately
75%, followed by 80% in the second year, followed by 83-85% in the third year and thereafter.
It is expected that improvements in gasifier designs will improve availability factors from previous generation designs.
Availability Factor
For this assessment, an 85% availability factor is assumed for both IGCC options.
The availability factor of an IGCC facility will depend heavily on the structure of the O&M programs and how well they are executed. The most effective IGCC facilities are those that commit to and follow well organized plans.
As previously noted, the membrane wall design of the Shell gasifier will experience less frequent maintenance than the GE and ConocoPhillips refractory lined gasifiers. Refractory lined
9-1
IGCC Availability
gasifiers will require periodic refractory replacement (perhaps every two years). This results in a lower planned outage rate for the Shell gasifier, and therefore a higher availability factor.
9-2
10
IGCC EMISSIONS ESTIMATES
General
The emissions evaluated for this IGCC study are NO x
, SO
2
, PM
10
, CO, CO
2
, and mercury. The actual emissions limits and emissions control technology required for a facility are dictated by the air permitting process. The emission rates herein are used to provide the basis of the capital cost, performance, and O&M costs. Actual permitted rates may vary from the emission rates shown below.
CO
2
capture was not considered for the two base case options; however Chapter 13 provides additional information regarding the impact to the capital cost, performance, and CO
2
emissions from the addition of CO
2
capture equipment at a later date.
For purposes of this study, it is assumed the project is located in an attainment area for National
Ambient Air Quality Standards (NAAQS) Pollutants as set by the Environmental Protection
Agency (EPA).
For SO
2
control, the AGR process selected for the basis of this project is SELEXOL. The AGR is sized to achieve a total sulfur content of 30 ppmv in the syngas to the gas turbines (for the non-
CO
2
capture cases). High levels of sulfur removal are accomplished by first passing the syngas through a COS hydrolysis reactor prior to the SELEXOL scrubber to convert small amounts of
COS in the syngas to H
2
S.
NO x
control is achieved through the use of nitrogen injection and syngas saturation into the gas turbine. The nitrogen acts as a diluent (similar to water injection) to control the flame temperature which is a major source of NO x
. Additionally fuel-bound nitrogen is effectively eliminated by the removal of HCN and NH
3
in the syngas cleanup system.
An SCR was not included at this phase of the project. Some of the ammonia utilized in an SCR will react with SO
3
in the exhaust gas to form ammonium bisulfate (ABS) that may plug the heat transfer surfaces in the HRSG. If an SCR were to be used, the sulfur level in the syngas would have to be reduced to approximately 15 ppmv to minimize the potential for ABS formation which would increase the cost of the AGR and SRU. Therefore, the capital cost of the project would increase. Also, the net plant output will be reduced due to the reduction in GTG output
(caused by increased exhaust pressure loss) and the additional steam and auxiliary power requirements of the AGR and SRU. The benefit is that NO x
emissions will be reduced from 15 ppmvd @ 15% O
2
(from the output of the gas turbines) to approximately 3.5 ppmvd @ 15% O
2
, however particulate emissions will increase. At $3,000/ ton for NO x
emissions allowances costs
(see Table 8-1), the yearly savings provided by the addition of an SCR may make it an attractive
10-1
IGCC Emissions Estimates
option provided that the technical issues can be overcome. At this stage, SCR was not included due to the technical issues stated above; however additional studies regarding the use of an SCR should be performed in the future.
Particulate control for this project is achieved using candle filters and a water wash scrubber to remove the particulate from the syngas. Beyond the syngas particulate control, there is no additional post-combustion particulate control required.
CO is controlled by the gas turbine combustion system. Additional CO removal is not included.
Mercury control is achieved by using activated carbon adsorbent beds to remove mercury from the syngas prior to combustion and is capable of removing 90+% of the entrained mercury.
The resulting emission rates are shown in Table 10-1.
Table 10-1
IGCC Target Emission Rates
100% PRB 50% PRB / 50%
Petcoke
NO x lb/MMBtu (HHV) ppmvd @ 15% O
2 lb/MWh (net)
SO
2
0.063
15
0.581
0.062
15
0.562
lb/MMBtu (HHV) lb/MWh (net)
PM
10 lb/MMBtu (HHV)
1 lb/MWh (net)
1
CO lb/MMBtu (HHV) ppmvd lb/MWh (net)
CO
2
0.019
0.173
0.007
0.065
0.037
25
0.337
0.023
0.210
0.007
0.065
0.036
25
0.337
lb/MMBtu (HHV) lb/MWh (net)
Hg
% Removal lb/TBtu (HHV) lb/MWh (net)
215
1,985
90%
0.778
7.17E-06
213
1,934
90%
0.496
4.50E-06
1) Particulate matter emissions rate is for front half only excluding back half condensables, for the concentration of particulate matter less than 10 microns in diameter
10-2
11
SUPERCRITICAL PC ESTIMATES
General
In order to compare IGCC to SCPC technology, Burns & McDonnell estimated the capital costs, performance, O&M, and availability factor of a 550 MW (net) SCPC unit with steam conditions of 3500 psig/1050°F/1050°F. For this assessment, only a 100% PRB fired SCPC was evaluated.
Although much more effort was put into developing IGCC cost estimates than the SCPC estimate for this study, Burns & McDonnell believes the accuracy of the SCPC costs to be equal in accuracy, if not greater than those provided for the IGCC estimates. This is largely due to
Burns & McDonnell involvement with other SCPC projects that have been constructed in recent years and the fact that IGCC definitive cost data with vendor input is not available or is considered confidential at this time.
SCPC Capital Cost Assumptions
The majority of the assumptions and exclusions discussed in Chapter 7.0 are applicable to the
SCPC capital cost estimates. Additional assumptions are as follows.
• Wet flue gas desulfurization (FGD) is assumed for SO
2
control, and SCR for NO x
control, and a baghouse for particulate control.
• The physical size of the wet FGD is increased beyond that required at this stage to accommodate additional future SO
2
removal as may be required by future environmental regulations. Based on the Fluor EFG+ CO
2
capture system (discussed in Chapter 13), approximately 98% SO
2
removal is required in the FGD, which is higher than currently required. The design capability for future SO
2
removal is integrated into the design of the
FGD system absorber by adding additional height to the absorber tower and by allocating space for installation of additional recirculation pumps and spray headers that could be added in the future should it be necessary to minimize SO
2
concentrations entering the
CO
2
capture system. It is estimated that the provision of this additional space within the absorber tower would increase the initial installed cost of the FGD system by about
$5,000,000, which is included in the capital cost estimate.
• Preliminary foundation design is based on the assumption that shallow, mat-type foundations will be sufficient for all minor foundations. Major structures such as the boiler, steam turbine, APC equipment, coal reclaim, and step up transformers are assumed to require piling.
11-1
Supercritical PC Estimates
• The boiler, steam turbine, and air pollution control equipment are located outdoors.
• The design fuel is based on 100% PRB fuel as provided in Table 3-1.
• An on-site landfill is included for disposal of flyash, bottom ash, and scrubber sludge.
The capital cost estimate includes the initial 5-year cell. The ongoing cost of closing current cells and the addition of future cells is covered in the landfill cost ($/ton) used in the O&M estimate.
SCPC Capital Cost Results
The estimated capital costs for the project are provided in Table 11-1. Additional capital cost detail can be found in Appendix E.
11-2
Supercritical PC Estimates
Table 11-1
550 MW (Net) SCPC Capital Cost Estimate Summary (2006 US Dollars)
Procurement
Boiler/AQC
Steam Turbine
Other Mechanical
Electrical
Water & Chemical Treatment
Structural
Construction
Furnish and Erect
Material Handling
Chimney
Boiler/AQC/STG Erection
Civil / Structural Construction
Mechanical Construction
Electrical Construction
EPC Contractor Indirect Costs
Construction Indirects
Construction Management
Pre-operational startup and testing
Other
Project Indirects
Project Management and Engineering
EPC Contingency
EPC Fee
Other
Total EPC Contractor Cost (2006 US $)
Owner Indirect Costs
Owner's Engineer
Permitting and Licensing Fees
Land
Initial Fuel Inventory
Operating Spare Parts
Permanent Plant Equipment and Furnishings
Builder's Risk Insurance
Owner Contingency
Other
Total Owner's Cost (2006 US $)
Total Project Cost (2006 US $)
Total EPC Contractor Cost (2006 US $), $/kW (73°F)
Total Project Cost (2006 US $), $/kW (73°F)
550 MW (Net) SCPC
100% PRB
$ 182,630,000
$ 40,040,000
$ 48,370,000
$ 35,270,000
$ 4,560,000
$ 1,970,000
$ 46,530,000
$ 15,000,000
$ 171,210,000
$ 156,650,000
$ 85,310,000
$ 61,350,000
$ 24,710,000
$ 8,790,000
$ 4,500,000
$ 38,120,000
$ 46,430,000
$ 97,510,000
$ 3,630,000
$ 1,072,580,000
$ 20,000,000
$ 2,910,000
$ 7,500,000
$ 10,690,000
$ 5,750,000
$ 5,780,000
$ 4,830,000
$ 57,250,000
$ 15,050,000
$ 129,760,000
$ 1,202,340,000
$ 1,950
$ 2,190
11-3
Supercritical PC Estimates
SCPC Performance Assumptions
The majority of the assumptions discussed in Chapter 6 are applicable to the SCPC performance estimates. Additional assumptions are as follows.
• Performance is based on the 100% PRB fuel as provided in Table 3-1.
• Steam turbine consists of four turbine sections (HP, IP, and 2 LP) with a two dual down flow exhausts. The design throttle conditions are 3500 psia with 1050°F main steam and hot reheat temperatures.
• Performance is based on a wet cooling tower, wet scrubber, and baghouse.
SCPC Performance Estimate Results
The results of the performance analysis are provided in Table 11-2.
Table 11-2
550 MW (Net) SCPC Performance Summary
100% PRB
Ambient Dry Bulb Temperature, °F
Ambient Wet Bulb Temperature, °F
Elevation, ft.
Coal Heat Input, MMBtu/hr (LHV)
Coal Heat Input, MMBtu/hr (HHV)
Gross Plant Output, MW
Total Plant Auxiliary Load, MW
Net Plant Output, MW
Net Plant Heat Rate, Btu/kWh (LHV)
Net Plant Heat Rate, Btu/kWh (HHV)
Plant Cooling Requirements, MMBtu/hr (Total)
Steam Cycle Cooling Requirement, MMBtu/hr
BOP Auxiliary Cooling Requirement, MMBtu/hr
Total Makeup Water Requirement
GPM
Acre-ft/year (@ 85% CF)
43
40
100
4,648
5,037
623.3
65.4
557.8
8,333
9,030
2,490
2,300
190
5,120
7,950
73
69
100
4,644
5,033
614.5
64.5
550.0
8,444
9,150
2,490
2,300
190
5,800
7,950
6,430
7,950
93
77
100
4,644
5,033
613.2
64.4
548.8
8,462
9,170
2,490
2,300
190
11-4
Supercritical PC Estimates
SCPC O&M Cost Assumptions
The majority of the assumptions discussed in Chapter 8 are applicable to the SCPC O&M estimates. Additional assumptions are as follows:
• 103 full time operations and maintenance personnel.
• Flyash, bottom ash, and scrubber sludge are landfilled on-site at a cost of $11.29/ton.
This cost includes the ongoing cost of closing old landfill cells and expanding the landfill in the future.
• Delivered limestone for wet scrubbing is based on $18/ton.
• Delivered ammonia for SCR use is based on $658/ton for 19% aqueous solution.
SCPC O&M Exclusions
The costs not included in the O&M estimates include, but are not limited to the following:
• Property taxes.
• Insurance (included in economic analysis).
• Fuel and fuel supply costs (included in economic analysis).
• Initial spare parts (included in capital cost estimate).
SCPC O&M Results
The estimated O&M costs for the project are provided in Table 11-3. Additional O&M cost detail can be found in Appendix G.
11-5
Supercritical PC Estimates
Table 11-3
550 MW (Net) SCPC O&M Summary (2006 US Dollars)
100% PRB
Fixed O&M
Labor, $/yr
Office and Admin, $/yr
Major Inspections, $/yr
Standby Power Energy Costs, $/yr
Other Fixed O&M, $/yr
Fixed O&M, $/yr
Variable O&M (85% CF)
Emissions Allowance Costs, $/yr
NO x
Emissions Allowance Cost
SO
2
Emissions Allowance Cost
Hg Emissions Allowance Cost
Major Maintenance Costs, $/yr
Steam Turbine / Generator Overhaul
Steam Generator Major Replacements
Baghouse Bag Replacement
SCR Catalyst Replacement
Demin System Replacements
Water Treatment, $/yr
Consumables/Disposal, $/yr
Limestone Consumption
SCR Ammonia (Anhydrous)
Scrubber Sludge Disposal
Fly Ash Disposal
Bottom Ash (Sales) / Disposal
Other Chemical Costs
Other Variable O&M, $/yr
Variable O&M, $/yr (85% CF)
Fixed O&M, $/kW-yr
Variable O&M, $/MWh
Total O&M Cost, $/Year (85% CF)
$ 9,687,800
$ 96,900
$ 280,000
$ 98,600
$ 1,211,000
$ 11,374,300
$ 2,810,100
$ 1,127,900
$ 1,734,700
$ 339,200
$ 893,900
$ 253,400
$ 312,000
$ 4,300
$ 1,759,500
$ 524,700
$ 1,041,800
$ 634,700
$ 1,412,600
$ 351,900
$ -
$ 5,634,800
$ 18,835,500
$ 20.68
$ 4.60
$ 30,209,800
SCPC Emission Rates
A wet scrubber is assumed for SO
2
control, an SCR for NO x
control, and a baghouse for particulate control.
11-6
Supercritical PC Estimates
The use of SCR is a proven technology on PC units. ABS formation is not as much of a concern on a PC unit as for an IGCC unit. In a PC unit, maximum ammonia slip is designed to be less than 2 ppmvd at the end of a specified operating period (2-3 years). This means the average slip over that period is significantly less. Much of the remaining ammonia after the catalyst is absorbed in the flyash. ABS formation will typically occur in the air preheaters if slip exceeds this maximum point. Additionally, the heat transfer surfaces (except for the air heater) are located upstream of the SCR in a PC boiler, thus limiting downstream cold areas where the ABS can collect. The HRSG, however, has HP, IP, and LP heat transfer surface downstream of the
SCR, which can become plugged with the ABS particulate.
Ammonia salt formation is not as much of a concern on a PC unit as for an IGCC unit. In a PC unit much of the remaining ammonia after the catalyst is absorbed in the flyash, thus ammonia salt formation is limited primarily to that formed in the catalyst while in the presence of ammonia. Additionally, the heat transfer surfaces (except for the air heater) are located upstream of the SCR in a PC boiler, thus limiting downstream cold areas where the ammonia salts can collect. An HRSG, however, has HP, IP, and LP heat transfer surface downstream of the SCR, which can become plugged with the ammonia salts.
Approximately 70% mercury removal has been shown with the combination of an SCR, wet scrubber, and baghouse alone. Additional mercury control can be achieved through the use of halogenated carbon injection or activated carbon injection into the flue gas stream. This was not considered for this assessment due to the small amount of test data that is currently available and the potential for contamination of flyash and gypsum.
The estimated emission rates for the SCPC Unit are provided in Table 11-4.
11-7
Supercritical PC Estimates
Table 11-4
500 MW (Net) SCPC Emissions Estimates
100% PRB
NO x lb/MMBtu (HHV) lb/MWh (net)
SO
2 lb/MMBtu (HHV) lb/MWh (net)
PM
10 lb/MMBtu (HHV)
1 lb/MWh (net)
1
CO lb/MMBtu (HHV) lb/MWh (net)
CO
2
0.050
0.458
0.060
0.549
0.015
0.137
0.150
1.373
lb/MMBtu (HHV) lb/MWh (net)
Hg
% Removal lb/TBtu (HHV) lb/MWh (net)
215
1,967
70%
2.315
2.12E-05
1) Particulate matter emissions rate is for front half only excluding back half condensables, for the concentration of particulate matter less than 10 microns in diameter
Availability Factor
Historic data for SCPC units in the United States is typically from much earlier vintage units
(1970’s). Since the 1980’s, the majority of SCPC units have been installed in Europe and Asia.
Development of high strength materials has helped to minimize the thermal stresses that caused problems in early units. Additionally, the development of Distributed Control Systems (DCS) has helped make a complex starting sequence much easier to control and minimize tube overheating due to lack of fluid. Additionally, newer units use a particle separator placed into the fluid process during startup to minimize solid particle carryover, which causes erosion of the turbine blades. Therefore, many of the early problems experienced with SCPC units have been corrected.
Historically, an availability factor for subcritical PC units in the United States has been 87%.
Newer supercritical units located overseas have maintained availability factor equal to newer subcritical units at approximately 90% or greater. It is estimated that a new SCPC unit will have an availability factor of approximately 90%.
11-8
12
ECONOMIC ANALYSIS
General
A pro forma economic analysis was prepared for the three solid fuel alternatives: an IGCC unit utilizing 100% PRB coal, an IGCC unit utilizing 50% PRB coal and 50% petcoke, and a SCPC unit firing 100% PRB. A 20-year economic analysis was developed based on the estimated capital costs, performance, fuel costs, and operating costs of each alternative. A 20-year levelized busbar cost in real dollars was determined for each alternative using a revenue requirements analysis of debt service (including principal and interest), fixed O&M, variable
O&M, and fuel. The economic analysis was conducted on a real basis, and therefore, the analysis does not include escalation for fuel or O&M.
The economic analysis assumes a debt term of 30 years. However, the busbar cost presented is a levelized value for the first 20 years of the Project. There is not a significant difference in the levelized busbar cost when comparing 20-year and 30-year project periods
Other EPRI reports and published papers have assumed a 30-year constant dollar busbar analysis based on typical investor owned utility (IOU) financial assumptions. A municipal utility has access to lower cost financing, through both lower interest rates and higher leverage factors.
Additionally, municipal utilities do not have income tax liability, nor an equity financing component, which typically requires a larger rate of return compared to debt financing. As a result, municipal utilities often have a lower cost of capital compared to typical IOU financing.
Burns & McDonnell estimated capital recovery costs based on debt service payments rather than depreciation and interest. The annual capital recovery costs are equal to the cash flow requirements for debt service payments for both principal and interest associated with 100% debt financing of the project capital expenditures.
Assumptions
The following provides the assumptions utilized in the pro forma economic analysis.
•
Capital Cost Estimates: Table 7-1 and Chapter 11
•
Fuel Cost Assumptions:
PRB Coal Cost (Delivered, 2005$) $1.65/MMBtu
12-1
Economic Analysis
Petcoke Cost (Delivered, 2005$)
Fuel Cost Escalation
•
Operating Assumptions:
Heat Rate Performance
Overall Capacity Factor
$1.14/MMBtu
Excluded (real basis)
Table 6-1 and Chapter 11
85%
IGCC Unit
•
Financing Assumptions:
Permanent Financing Term
Capital Structure
Permanent Financing Fees
Minimum Debt Service Coverage Ratio
Debt Service Reserve Fund
•
Economic Assumptions:
O&M Inflation
•
O&M Cost Assumptions:
Fixed O&M Costs
12-2
50% PRB coal, 50% petcoke
3.0%
30 years
Debt – 100%, Equity – 0%
0.50%
1.00%
1.00
50% of annual debt service funded at financial closing
Excluded (real basis)
Table 8-1 and Chapter 11
Variable O&M Costs
Emissions Allowances
Insurance
Property Taxes
Economic Analysis
Table 8-1 and Chapter 11
Included in Variable O&M
0.05% of capital cost
Exempt
Economic Analysis
The economic pro forma analyses were used to determine the levelized busbar cost of power in real dollars for each alternative. Figure 12-1 presents a graph of the resulting levelized busbar power costs in real dollars for the solid fuel-fired alternatives over a 20 year planning period covering 2006 through 2025. Figure 12-1 was developed by preparing a project pro forma model for each of the alternatives under consideration. The levelized busbar cost in real dollars represents the fixed energy cost in 2006 US dollars that would be equivalent to the busbar cost over 20 years. The economic analysis does not include escalation for fuel and O&M costs.
$50.00
$45.00
$40.00
$35.00
$30.00
$25.00
$20.00
$15.00
$10.00
$5.00
$0.00
Supercritical PC
IGCC - 50% PRB / 50% Pet Coke
IGCC - 100% PRB
Figure 12-1
20-Year Levelized Busbar Cost (2006 US Dollars)
Alternative
$39.28
$40.89
$45.03
12-3
Economic Analysis
Figure 12-2 presents a breakout of the components for the 20-year levelized busbar cost in real dollars for the alternatives in 2006 US dollars.
$50.00
$45.00
$40.89
$45.03
$39.28
$40.00
$35.00
$30.00
$25.00
$20.00
$15.00
$10.00
$5.00
$0.00
$15.10
$4.66
$2.91
$16.62
$12.02
$5.71
$3.54
$19.62
$15.21
$6.01
$3.54
$20.27
Fuel Costs
Variable O&M
Fixed O&M
Debt Service
Supercritical PC IGCC - 50% PRB / 50% Pet
Coke
Alternatives
IGCC - 100% PRB
Figure 12-2
Breakout of 20-Year Levelized Busbar Cost (2006 US Dollars)
The SCPC unit is the lowest cost alternative. Since the SCPC unit is less capital intensive than the two IGCC alternatives, the debt service component for the PC unit is considerably lower, as shown in Figure 12-2. Additionally, the SCPC unit has lower operational and maintenance costs, both variable and fixed, compared to the IGCC alternatives, providing a lower overall project cost.
The IGCC alternative utilizing a fuel blend of PRB coal and petcoke has a lower cost than the
IGCC alternative utilizing only PRB coal, and is only slightly higher than the SCPC alternative.
The IGCC alternative using coal and petcoke has a slightly lower capital cost than the IGCC alternative utilizing 100% coal, therefore the debt service requirements for both IGCC alternatives is nearly equivalent. However, the blended fuel option has a significantly lower heat rate and delivered fuel cost, therefore lowering the project busbar cost relative to the IGCC alternative utilizing 100% coal. The ability to use an opportunity fuel, such as petcoke, allows the overall levelized busbar cost of the IGCC technology to be lower compared to strictly using
PRB coal.
12-4
Economic Analysis
Sensitivity Analysis
A sensitivity analysis was preformed for all three alternatives under the following cases:
•
•
Interest Rate
•
± 0.5 percentage point
•
Coal Fuel Cost
•
± 10%
The ranges shown above not intended to imply the accuracy of the estimates, but the resulting change in busbar cost for the range shown. It is possible that the capital cost, interest rate, fuel cost, capacity factor, and O&M cost may vary by a larger amount than shown above.
The results of the sensitivity analysis are presented in the tornado diagram in Figures 12-3 through 12-5. The sensitivity analysis results are presented in 2006 US dollars. A tornado diagram illustrates the range of results for each sensitivity case and its impact on the levelized busbar cost in real dollars, and ranks the results from greatest impact to least impact.
Capital Cost -/+ 10%
$37.62
$40.94
Fuel Cost -/+ 10%
Interest Rate -/+ 0.5%
Capacity Factor +/- 5%
$37.77
$38.03
$38.35
$40.80
$40.60
$40.31
O&M Cost -/+ 10%
$38.53
$37.6
2
$38
.1
7
$38.7
3
Figure 12-3
Sensitivity Analysis – SCPC Unit – 100% PRB Coal
$3
9.
84
$4
0.
39
$4
0.
94
$40.03
12-5
Economic Analysis
Capital Cost -/+ 10%
Interest Rate -/+ 0.5%
$38.93
$39.42
Fuel Cost -/+ 10%
Capacity Factor +/- 5%
$39.69
$39.79
$42.10
$42.11
O&M Cost -/+ 10%
$39.97
$38.9
3
$39
.5
9
$40.2
4
Figure 12-4
Sensitivity Analysis – IGCC – 50% PRB Coal / 50% Petcoke
Capital Cost -/+ 10%
$43.01
$4
1.
55
$4
2.
20
$4
2.
86
$41.82
$47.06
Interest Rate -/+ 0.5%
$43.51
$46.64
Fuel Cost -/+ 10%
Capacity Factor +/- 5%
$43.51
$43.90
O&M Cost -/+ 10%
$44.08
$43.0
1
$43
.6
8
Figure 12-5
Sensitivity Analysis – IGCC – 100% PRB Coal
$44.3
6
$4
5.
71
$4
6.
39
$4
7.
06
$42.86
$42.45
$46.56
$46.29
$45.99
12-6
Economic Analysis
The sensitivity analysis indicates that capital cost is the most significant factor affecting the economics of the IGCC alternatives and the SCPC unit. Additionally, the interest rate and fuel cost have the next most significant affects. Since the pro forma analyses assume the project alternatives are financed with 100% debt, changes in the capital cost and interest rate have a significant affect on the economics of the project, due to the large portion of debt service. The cost of fuel is the largest ongoing cost to the project; therefore significant changes in the cost of fuel will affect the economics of the project.
Solid fuel generation resources are capital intensive, and have a construction period that is approximately four years in duration. This results in more capital risk due to interest costs, labor availability and costs, and general inflation. The primary tradeoff for these higher capital risks with a solid fuel generation resource is the long-term stability of solid fuel prices which has few competing uses relative to natural gas that is used by almost all economic sectors including residential heating.
12-7
13
CO
2
CAPTURE
General
As a part of this study, Burns & McDonnell was tasked with determining the approximate impacts to performance, cost, O&M, emissions, and levelized busbar cost for the 100% PRB
IGCC and 100% PRB SCPC units from adding CO
2
capture systems. For this assessment, it was assumed that the plants are existing units with cost and operating characteristics as defined in previous chapters. The CO
2
capture systems are added as a plant retrofit at a later date.
A CO
2
capture rate of 90% was targeted for both the IGCC and SCPC technologies. For this assessment, it was assumed the CO
2
would be compressed into a common carrier CO
2
pipeline.
The pipeline may serve many purposes including:
• Storage in depleted/disused oil and gas fields.
• Enhanced Oil Recovery (EOR) combined with CO
2
storage.
• Enhanced coal bed methane recovery (ECBM) combined with CO
2
storage.
• Storage in deep saline aquifers/formations (DSF) – both open and closed structures.
The assumed common carrier pipeline pressure is 2,000 psig. The cost of the CO
2
pipeline and/or storage is not included in the estimates.
Table 13-1 provides the assumed CO
2
purity required for the common carrier pipeline.
13-1
CO2 Capture
Table 13-1
CO
2
Purity Specification
SUBSTANCE
CO
2
N
2
Hydrocarbons
H
2
O
b
O
2
H
2
S
CO
Glycol
Temperature
Pressure
LIMIT
95%
4%
5%
-40 °C (-40 °F)
100 ppm
25 ppm
0.1%
174 lit/10
6 m
3
(0.3 gal/MMcf)
50 °C (120 °F) d
13,800 kPa
(2,000 psig)
MAX OR
MIN
Min
Max
Max
Max
Max
Max
Max
Max
Max
Normal
REASON
MMP concern a
MMP concern
MMP concern
Corrosion
Corrosion
Safety
C
Safety
Operations
Materials
Materials a
Minimum miscible pressure concern because the application of the CO
2
is potentially for EOR. b
Dew point: < -40 °F c
Based on limiting H
2
S partial pressure to 0.3 kPa, above which the pipeline will be classified for sour service. d
There will also be a lower limit associated with potential failure of the pipeline but this is not relevant to most of the North American pipelines because of their location.
The potential for CO
2
sales exists, which could help offset the costs associated with CO
2
capture.
In 2005 EPRI evaluated the potential CO
2
sales costs for the CO
2
storage options listed above
(Building the Cost Curve for CO
2
Storage: North American Sector, EPRI, Palo Alto, CA: 2005.
Report No. 1010167). As a part of this 2005 study, cost curves for each storage option were developed by compiling data on geological reservoirs for CO
2
storage and determining the technical storage capacity of these reservoirs. These data, along with baseline study data on CO
2 sources, were then analyzed within a purpose-built techno-economic model based upon geographic information system (GIS) technology. The mapping capability of the GIS allowed the presentation of the data base information at both regional and continental scales. The computational portion of the model calculated the distance between each source and accessible candidate storage reservoir and compared characteristics such as CO
2
flow rate, remaining storage capacity, depth, and other injection parameters, to estimate the cost for CO
2
transmission and storage for each source and reservoir pair. The overall costs for CO
2
storage in the USA were modeled to be effectively capped at about $12-15/Mt CO
2
, with important yet limited resource available below $0/Mt CO
2
.
The results of the previous EPRI study are summarized in Figure 13-1.
13-2
CO2 Capture
Figure 13-1
CO
2
Storage Supply Curve for North America
For purposes of this study, any revenue or cost associated with CO
2
disposal were not considered. It is assumed that the captured CO
2
is disposed at zero cost.
If a dedicated pipeline for EOR or other designated purpose were to be used rather than the common carrier pipeline assumed for this report, the design of the CO
2
capture systems could be significantly different which may produce different results.
There are many legal and regulatory aspects with regard to CO
2
storage that have not been evaluated for this study.
The capital cost, O&M, and performance assumptions provided in previous sections are applicable for the CO
2
capture cases.
IGCC CO
2
Capture
CO
2
capture in an IGCC facility is accomplished by removing the CO
2
and water from the syngas prior to combustion. This is achieved by first shifting the syngas to convert CO to CO
2
and H
2
by the addition of water-gas shift reactors. The CO
2
is then absorbed in the AGR unit, resulting in a hydrogen rich fuel. For the purposes of this analysis, SELEXOL was used as the solvent for CO
2 removal (SELEXOL is discussed in greater detail in Chapter 4).
CO
2
capture for an IGCC facility has not been proven commercially, however CO
2
capture has been proven commercially at the Dakota Gasification Company’s Great Plains Synfuels Plant, which sends compressed CO
2
through a pipeline for Enhanced Oil Recovery (EOR).
13-3
CO2 Capture
IGCC Modifications for CO
2
Capture
For this study, all major modifications for CO
2
capture are downstream of the gasification block.
These modifications include:
• Replacement of the COS/HCN hydrolysis reactor with two stages of sour shift reaction to convert carbon monoxide to CO
2
.
• Additions to the syngas cooling train to incorporate the shift reactors.
• Additions to the SELEXOL AGR to recover CO
2
as a separate byproduct.
• Addition of a single CO
2
compressor, consisting of four multi-stage centrifugal compressor cases with intercoolers and CO
2
product cooler, is included to deliver CO
2
at 2,000 psig to the pipeline. Heat recovery from CO
2
compression is not included at this stage, but should be evaluated in the future.
The acid gas composition from the SELEXOL unit to the Sulfur Recovery Units was set at 25%
H
2
S as in the non-capture case. The SRU/TGTU design is therefore identical to the non-capture case.
Process flow diagrams for the modified syngas flow train are included in Appendix A. Original equipment that is reused is highlighted in yellow.
Sour Shift
The COS/HCN reactor included in the non-capture case is replaced with two stages of sour shift reaction. The shift reaction converts approximately 95% of the carbon monoxide to CO
2, generating hydrogen fuel as a byproduct. The shift reaction is
CO + H
2
O Æ H
2
+ CO
2
The reactors operate with 1.3 moles of steam feed per mole of dry gas (or 2.1 mole of H
2
O per mole of CO). IP steam is added upstream of the reactors to replace steam consumed in the reaction. The balance is generated by heating and vaporizing process water.
Cobalt-molybdenum sour shift catalyst is a good COS/HCN hydrolysis catalyst. Both COS and
HCN are almost entirely hydrolyzed in the reactors, eliminating the need for a separate reactor.
Since each mole of CO is replaced with a mole of H
2
, the available syngas chemical energy
(MMBtu/hr) on an HHV basis actually increases slightly from the un-shifted syngas due to H
2 having a higher HHV heating value than CO. However, since CO does not form water as a byproduct of combustion, the LHV and HHV heating value of CO are identical. Therefore, the
LHV energy of the shifted syngas (MMBtu/hr) decreases by approximately 9.7%.
13-4
CO2 Capture
Syngas Cooling and Condensation
The exothermic shift reaction and the addition of steam to facilitate the reaction significantly increase the heat load on the syngas cooling train. Several new heat exchangers are required to remove this heat. The additional heat is used to preheat the shift feed and to generate part of the steam feed to the reactors.
Due to the number of heat exchangers and additional pressure drop through the AGR, some increase in the gasifier pressure is required to maintain the needed pressure at the inlet of the gas turbines. This increase can be minimized by appropriate design of the exchangers and is believed to be within the design allowance of the gasifier.
Acid Gas Removal (AGR)
The number of moles, and therefore the volumetric flow rate, of syngas feeding the AGR is about 60% higher than in the non-capture case. Although most of the original non-capture equipment (towers, large heat exchangers and refrigeration equipment) can be reused, significant additions are required to handle the additional volumetric flow and to separate CO
2
as a separate byproduct.
The following new equipment is required:
• H
2
S absorber (in parallel to original absorber).
• H
2
S stripper with reboiler, condenser, reflux drum, and pumps (in parallel to original stripper).
• H
2
S concentrator (common to both H
2
S absorber/stripper trains).
• Rich solvent pumps to feed H
2
S absorber bottoms to the H
2
S concentrator.
• New rich flash compressor and coolers to replace original units.
• CO
2
absorber.
• Loaded solvent pumps to feed H
2
S absorbers.
• Solvent regeneration flash drum system (4 drums with CO
2
recycle compressor and CO
2 vacuum compressor.
• Semi-lean solvent pumps and chiller to feed cold regenerated solvent to CO
2
absorber.
• Refrigeration package.
IGCC Impacts from CO
2
Capture
IGCC Performance – CO
2
Capture
The shift reaction results in a high hydrogen content fuel with a higher heating value (Btu/lb) than for the standard syngas cases. This results in less mass flow through the gas turbines and
13-5
CO2 Capture
less gas turbine power as a result. Additionally, more steam is required for the AGR and a large quantity of IP steam (450,000 lb/hr) is required for the water-gas shift reaction resulting in substantially less steam turbine output.
The auxiliary load of the facility also increases substantially due to the CO
2
compression
(approximately 37.1 MW) and the increased auxiliary loads of the AGR. The net result is approximately a 25% reduction in net plant output and a 39% increase in net plant heat rate.
The cooling load of the facility decreases since a large portion of the steam is extracted for the
AGR and water-gas shift reaction. However due to the large amount of steam leaving the cycle, the plant makeup requirement has increased by approximately 23%.
Table 13-2 illustrates the impact of CO
2
capture on the IGCC facility.
Table 13-2
IGCC Performance Impacts from CO
2
Capture
Ambient Dry Bulb Temperature, °F
Ambient Wet Bulb Temperature, °F
Elevation, ft.
Evaporative Cooling, On/Off
Coal Heat Input, MMBtu/hr (LHV)
Coal Heat Input, MMBtu/hr (HHV)
Gas Turbine Gross Output, MW (each)
Gas Turbine Gross Output, MW (total)
Steam Turbine Gross Output, MW
Gross Plant Output, MW
Auxiliary Load
Power Block, MW
Material Handling, MW
Air Separation Unit, MW
Gasifier, MW
CO
2
Compression
Syngas Treatment, MW
Total Plant Auxiliary Load, MW
Net Plant Output, MW
Net Plant Heat Rate, Btu/kWh (LHV)
Net Plant Heat Rate, Btu/kWh (HHV)
Plant Cooling Requirements, MMBtu/hr (Total)
Steam Cycle Cooling Requirement, MMBtu/hr
BOP Auxiliary Cooling Requirement, MMBtu/hr
Total Makeup Water Requirement
GPM
Acre-ft/year (@ 85% CF)
553.0
8,510
9,220
2,141
1,480
661
22.0
5.9
122.1
2.1
0.0
4.7
156.8
Base Case
(100% PRB)
73
69
100
Off
4,705
5,099
224.9
449.7
260.1
709.9
CO
2
Capture
(100% PRB)
73
69
100
Off
4,883
5,291
213.8
427.5
202.6
630.1
4,980
6,830
6,147
8,430
413.3
11,810
12,800
2,101
1,120
981
22.0
6.2
123.4
2.2
37.1
26.0
216.8
13-6
CO2 Capture
IGCC Capital Cost – CO
2
Capture
In addition to the revised AGR costs, syngas treatment costs, and CO
2
compression costs, the demineralized water treatment and storage system must be upgraded due to the 450,000 lb/hr of
IP steam being used for the water-gas shift reaction.
For the CO
2
capture case, much more heat load (approximately 300 MMBtu) is transferred to the condensate (See heat exchanger SGT-HTX-110 in Appendix A). This results in significantly more LP steam production than in the Base Case. The LP superheater provided in the Base Case
HRSG is undersized to superheat this amount of steam. Therefore, $2,000,000 in HRSG modifications are required to increase the size of the HRSG LP superheaters.
The additional capital cost estimated for CO
2
capture retrofit is shown in Table 13-3. The capital cost is provided in overnight mid-2006 US dollars.
Table 13-3
IGCC Capital Cost Additions for CO
2
Capture Retrofit
Installed Costs
AGR and Syngas Treatment Modifications
CO
2
Compressors
Additional Demineralized Water Treatment & Storage
HRSG LP Superheater Modifications
Total EPC Retrofit Cost (2006 US $)
Owner's Costs
Total Retrofit Cost (2006 US $)
$ 156,620,000
$ 16,600,000
$ 4,000,000
$ 2,000,000
$ 179,220,000
$ 17,960,000
$ 197,180,000
Total EPC Plant Costs (Including Base Case)
Total Project Costs (Including Base Case)
$ 1,498,200,000
$ 1,671,400,000
Total EPC Contractor Cost (2006 US $), $/kW (73°F)
Total Project Cost (2006 US $), $/kW (73°F)
$ 3,630
$ 4,040
The cost of the CO
2
pipeline and/or storage is not included in the estimates.
IGCC Operations and Maintenance – CO
2
Capture
Due to the increased size and role of the AGR for the CO
2
capture case, it is assumed that an additional control room operator is required for each shift, resulting in a plant staff of 130.
Other impacts to O&M are minimal from a $/year perspective, however due to the reduced output of the facility, the O&M increases greatly on a $/kW-yr and $/MWh basis.
The CO
2
that is captured is assumed to be sold to the common carrier pipeline at zero cost.
13-7
CO2 Capture
The O&M for the IGCC facility with and without CO
2
capture is provided in Table 13-4.
Table 13-4
IGCC O&M Impacts from CO
2
Capture
Base Case
(100% PRB)
CO
2
Capture
(100% PRB)
Fixed O&M
Labor, $/yr
Office and Admin, $/yr
Major Inspections, $/yr
Standby Power Energy Costs, $/yr
Other Fixed O&M, $/yr
Fixed O&M, $/yr
Variable O&M (85% CF)
Emissions Allowance Costs, $/yr
NO x
Emissions Allowance Cost
SO
2
Emissions Allowance Cost
Hg Emissions Allowance Cost
Major Maintenance Costs, $/yr
Steam Turbine / Generator Overhaul
HRSG Major Replacements
Gasifier Replacements
Candle Filter Major Replacements
Gas Turbine Major Replacements
Syngas Treatment Major Replacements
Air Separation Unit Major Replacements
Mercury Carbon Bed Replacements
HCN/COS Hydrolysis Catalyst Replacements
Shift Catalyst Replacements
Demin System Replacements
Water Treatment, $/yr
Fly Ash & Slag Disposal
Other Variable O&M, $/yr
Variable O&M, $/yr (85% CF)
Fixed O&M, $/kW-yr
Variable O&M, $/MWh
Total O&M Cost, $/Year (85% CF)
$ 11,835,700 $ 12,209,200
$ 118,400 $ 122,100
$ 400,000 $ 400,000
$ 98,600 $ 98,600
$ 1,479,500 $ 1,526,200
$ 13,932,200 $ 14,356,100
$ 3,588,300 $ 3,604,800
$ 360,700 $ 78,800
$ 590,000 $ 612,000
$ 260,400 $ 260,400
$ 200,000 $ 200,000
$ 885,800 $ 885,800
$ 300,000 $ 300,000
$ 8,148,700 $ 8,148,700
$ 375,000 $ 587,500
$ 275,000 $ 275,000
$ 530,300 $ 530,300
$ 640,000 $ -
$ - $ 1,020,000
$ 3,600 $ 20,100
$ 1,479,100 $ 2,066,800
$ 1,560,200 $ 1,560,200
$ 5,297,400 $ 6,154,900
$ 24,494,500 $ 26,305,300
$ 25.19 $ 34.74
$ 5.95 $ 8.55
$ 38,426,700 $ 40,661,400
13-8
CO2 Capture
IGCC Emissions – CO
2
Capture
CO
2
emissions are reduced by 90% in the SELEXOL unit. In order to meet the CO provided in Table 13-1, 25 ppm H
2
S is required at the outlet of the H
2
2
purity spec
S absorber. From the H
2
S absorber, the low H
2
S content syngas is then passed through a CO
2 absorber where the CO
2
is stripped off. Because the low H
2
S content syngas is again exposed to the SELEXOL solvent in the CO2 stripper, the sulfur content of the syngas is reduced significantly (approximately 1 ppm
COS and 1 ppm H
2
S), resulting in a reduction of SO
2
emissions (ton/yr) by approximately 80%.
The resulting emission rates are shown in Table 13-5.
Table 13-5
IGCC Emissions Impacts from CO
2
Capture
Base Case
(100% PRB)
CO
2
Capture
(100% PRB)
NO x lb/MMBtu (HHV) ppmvd @ 15% O
2 lb/MWh (net)
SO
2 lb/MMBtu (HHV) lb/MWh (net)
PM
10 lb/MMBtu (HHV)
1 lb/MWh (net)
1
CO lb/MMBtu (HHV) ppmvd lb/MWh (net)
CO
2 lb/MMBtu (HHV) lb/MWh (net)
Hg
% Removal lb/TBtu (HHV) lb/MWh (net)
0.063
15
0.581
0.019
0.173
0.007
0.065
0.037
25
0.337
215
1,985
90%
0.778
7.17E-06
0.061
15
0.781
0.004
0.051
0.007
0.090
0.035 (Note 2)
25 (Note 2)
0.448 (Note 2)
22
276
90%
0.778
9.96E-06
1) Particulate matter emissions rate is for front half only excluding back half condensables, for the concentration of particulate matter less than 10 microns in diameter
2) GE is currently in the process of developing tools to accurately predict CO emissions for high hydrogen fuels. It is estimated that CO emissions will be less than shown for IGCC technology, however to what extent is unknown at this time.
13-9
CO2 Capture
IGCC Pre-Investment Options for CO
2
Capture
This study was performed with minimal pre-investment for CO
2
capture equipment other than allowing space for future expansion and including SELEXOL in the base case (which may be the
AGR of choice without consideration for CO
2
capture as discussed in Chapter 4). Other options for pre-investment include:
• Design syngas cooler with a hotter exit temperature, resulting in more water being vaporized in the syngas scrubber and decreasing steam demand upstream of the water-gas shift. This results in lower cost of the syngas cooler and better CO
2
capture performance, however it also results in higher heat rate during non-capture operation.
• Supplemental duct firing can be added to the HRSG to make up for loss of steam turbine output.
• Increase size of initial gasification block to allow for additional syngas production to increase output for CO
2
capture cases (in particular the cold ambient conditions which are limited on syngas).
SCPC CO
2
Capture
Unlike IGCC technology, SCPC technology utilizes post-combustion capture of CO
2
using chemical absorption, also capable of achieving 90% removal efficiencies. Different technologies are available that use various solvents. Mitsubishi Heavy Industries (MHI) utilizes a tertiary amine solvent called KS-1; additionally ammonia-based technology is being developed that utilizes aqueous ammonium carbonate to capture CO
2
as ammonium bicarbonate.
The technology evaluated for this study is based on Fluor’s Econamine FG Plus
SM
(EFG+) CO
2 capture technology, which is based on a formulation of monoethanolamine (MEA) and proprietary additives for operation in high O
2
content gas and for corrosion resistance. A block flow diagram provided by Fluor is provided in Figure 13-2.
13-10
CO2 Capture
Figure 13-2
Fluor EFG+ Block Flow Diagram
The purpose of the EFG+ plant is to recover 90% of the carbon dioxide from the flue gas of the existing the FGD. The plant consists of an Absorption section and a Stripper section. This results in a plant with a total capacity of 11,697 ton/day (100% CO
2
basis).
The EFG+ plant battery limit for the flue gas feed is at the exit of the FGD. All of the flue gas from the FGD is routed to the EFG+ plant thus resulting in a zero flow of gas through the existing stacks to the atmosphere. The flue gas enters the Flue Gas Conditioning Unit (FGCU) where the gas is cooled by a circulating water stream, and the sulfur content of the gas is lowered from 7 ppmv to 1 ppmv. By lowering the gas temperature, much of the water vapor contained in the flue gas is condensed and separated from the feed gas before entering the Absorber.
The cooled, overhead gas from the FGCU is routed by a Blower to the Absorber. The flue gas enters the bottom of the Absorber and flows upwards counter current to the circulating solvent.
The solvent reacts chemically to remove the carbon dioxide in the feed gas. Residue gas, consisting mainly of nitrogen and oxygen, is vented through the top of the Absorber.
13-11
CO2 Capture
The rich solvent, containing absorbed carbon dioxide from the Absorber, is routed to the
Stripper. The rich solvent enters the Stripper and flows down counter current to stripping stream, which removes carbon dioxide from the rich solvent. Heat for stripping is supplied by low pressure steam via the Reboiler. Lean solvent from the Stripper is routed back to the
Absorber. The overhead vapor from the Stripper is routed to the Product CO
2
Compressor.
To maintain the highest possible absorption capacity of the solvent, contaminants, such as heat stable salts, are continuously removed in the Reclaimer.
EFG+ technology has not been proven commercially for a full scale PC unit, however commercial experience exists for capturing CO
2
from natural gas and fuel oil fired units, primarily for use in the food industry, EOR, and urea plants. Two demo plants have been constructed in Japan firing LPG and an oil/coal mixture. Additionally, Fluor is currently developing two demonstration plants that will fire coal and natural gas.
SCPC Modifications for CO
2
Capture
The Econamine FG Plus (EFG+) process for CO
2
capture requires that the level of SO
2
in the flue gas be minimized. Any SO
2
entering the EFG+ CO
2
absorber will react with the MEA solvent resulting in formation of waste salts that must be purged from the system. Therefore, approximately 7 ppm (approximately 98% removal with PRB fuel) SO
2
is required at the inlet to
Fluor’s flue gas conditioning system. To the extent that the SO
2
entering the EFG+ process is greater than about 1 ppm, it must be reduced to that level within the EFG+ process upstream of the CO
2
absorber. The EFG+ process accomplishes this reduction by scrubbing the flue gas with sodium hydroxide (NaOH).
In order to provide 7 ppm inlet SO
2
to the EFG+ process as described above, additional FGD SO
2 removal capacity must be installed in the wet FGD. Since the FGD system was initially designed with a space allocation for future SO
2
/CO
2
control, new internal spray headers and the recycle pumps can be installed at this time to reduce the overall inlet SO
2
to the 7 ppm required.
The installed cost for the FGD internals and recycle pumps is approximately $2.5 million.
Because this analysis is performed from a retrofit standpoint, the following modifications to the existing SCPC unit are required. All major modifications for CO
2
capture are downstream of the existing wet FGD. These include:
• Addition of wet FGD upgrades described above.
• Addition of Fluor EFG+ System.
• Addition of a single CO
2
compressor, consisting of four multi-stage centrifugal compressor cases with intercoolers and product cooler, is included to deliver CO
2
at 2,000 psig to the pipeline. Heat recovery from CO
2
compression is not included at this stage, but should be evaluated in the future.
• Although the steam turbine condenser duty is less than before, the EFG+ system requires approximately 1,730 MMBtu/hr of auxiliary cooling, resulting in the need for additional cooling capacity. This is accomplished by the addition of a new cooling tower and circulating water system.
13-12
CO2 Capture
SCPC Impacts from CO
2
Capture
SCPC Performance – CO
2
Capture
The SCPC performance adjustments for CO
2
capture are as follows:
• Approximately 1.4 million lb/hr of saturated LP steam (45 psig) is required by the EFG+
Reboiler. Steam is taken from the IP steam turbine exhaust to supply this steam. This extraction is approximately 40% of the flow from the IP turbine exhaust, which reduces the steam turbine output by approximately 93 MW. The remaining steam through the steam turbine is sufficient for providing adequate blade cooling.
• Additionally, the EFG+ system has an auxiliary load of approximately 19 MW.
• The additional cooling capacity auxiliary load discussed above is estimated at 3.5 MW.
• Approximately 42.6 MW of CO
2
compression is required to compress the CO
2
to 2,000 psig.
• Approximately 2 MW for addition of new FGD recycle pumps.
The net result is approximately a 29% reduction in net plant output and a 41% increase in net plant heat rate.
Due to the large auxiliary cooling requirement of the EFG+ system, the plant makeup water requirement increased by approximately 34%.
The resulting performance is show in Table 13-6, both pre and post-CO
2
capture.
13-13
CO2 Capture
Table 13-6
SCPC Performance Impacts from CO
2
Capture
Ambient Dry Bulb Temperature, °F
Ambient Wet Bulb Temperature, °F
Elevation, ft.
Coal Heat Input, MMBtu/hr (LHV)
Coal Heat Input, MMBtu/hr (HHV)
Gross Plant Output, MW
Total Plant Auxiliary Load, MW
Net Plant Output, MW
Net Plant Heat Rate, Btu/kWh (LHV)
Net Plant Heat Rate, Btu/kWh (HHV)
Plant Cooling Requirements, MMBtu/hr (Total)
Steam Cycle Cooling Requirement, MMBtu/hr
BOP Auxiliary Cooling Requirement, MMBtu/hr
Total Makeup Water Requirement
GPM
Acre-ft/year (@ 85% CF)
Base Case
(100% PRB)
73
69
100
CO
2
Capture
(100% PRB)
73
69
100
4,644
5,033
614.5
64.5
550.0
8,440
9,150
2,490
2,300
190
4,644
5,033
521.4
131.6
389.8
11,910
12,910
3,330
1,354
1,976
5,800
7,950
7,757
10,640
SCPC Capital Cost – CO
2
Capture
The additional capital cost encountered once CO
2
capture equipment is installed is shown in
Table 13-7. The capital cost is provided in overnight mid-2006 US dollars.
13-14
CO2 Capture
Table 13-7
SCPC Capital Cost Additions for CO
2
Capture Retrofit
Installed Costs
Fluor Econamine FG+ System
CO
2
Compressors
FGD Modifications to Obtain 98% SO
2
Removal
Additional Cooling Capacity
Total EPC Retrofit Cost (2006 US $)
Owner's Costs
Total Retrofit Cost (2006 US $)
Total EPC Plant Costs (Including Base Case)
Total Project Costs (Including Base Case)
Total EPC Contractor Cost (2006 US $), $/kW (73°F)
Total Project Cost (2006 US $), $/kW (73°F)
The cost of the CO
2
pipeline is not included in the estimates.
$ 243,000,000
$ 17,530,000
$ 2,500,000
$ 6,400,000
$ 269,430,000
$ 26,570,000
$ 296,000,000
$ 1,342,010,000
$ 1,498,340,000
$ 3,440
$ 3,840
SCPC Operations and Maintenance – CO
2
Capture
Based on input from Fluor, an additional control room operator and field operator are required
(per shift), resulting in a plant staff of 111.
Other impacts to O&M are minimal from a $/year perspective, however due to the reduced output of the facility, the O&M increases greatly on a $/kW-yr and $/MWh basis.
The CO
2
that is captured is assumed to be sold to the common carrier pipeline at zero cost.
The O&M for the SCPC facility with and without CO
2
capture is provided in Table 13-8.
13-15
CO2 Capture
Table 13-8
SCPC O&M Impacts from CO
2
Capture
Fixed O&M
Labor, $/yr
Office and Admin, $/yr
Major Inspections, $/yr
Standby Power Energy Costs, $/yr
Other Fixed O&M, $/yr
Fixed O&M, $/yr
Variable O&M (85% CF)
Emissions Allowance Costs, $/yr
NO x
Emissions Allowance Cost
SO
2
Emissions Allowance Cost
Hg Emissions Allowance Cost
Major Maintenance Costs, $/yr
Steam Turbine / Generator Overhaul
Steam Generator Major Replacements
Baghouse Bag Replacement
SCR Catalyst Replacement
Demin System Replacements
Water Treatment, $/yr
Consumables/Disposal, $/yr
Limestone Consumption
SCR Ammonia (Anhydrous)
Scrubber Sludge Disposal
Fly Ash Disposal
Bottom Ash (Sales) / Disposal
Other Chemical Costs
Other Variable O&M, $/yr
Variable O&M, $/yr (85% CF)
Fixed O&M, $/kW-yr
Variable O&M, $/MWh
Total O&M Cost, $/Year (85% CF)
Base Case
(100% PRB)
CO
2
Capture
(100% PRB)
$ 9,687,800 $ 10,434,900
$ 96,900 $ 104,300
$ 280,000 $ 280,000
$ 98,600 $ 98,600
$ 1,211,000 $ 1,304,400
$ 11,374,300 $ 12,222,200
$ 2,810,100 $ 2,529,400
$ 1,127,900 $ 4,800
$ 1,734,700 $ 1,734,900
$ 339,200 $ 339,200
$ 893,900 $ 893,900
$ 253,400 $ 253,400
$ 312,000 $ 312,000
$ 4,300 $ 4,300
$ 1,759,500 $ 2,372,900
$ 524,700 $ 551,200
$ 1,041,800 $ 1,042,000
$ 634,700 $ 666,800
$ 1,412,600 $ 1,412,800
$ 351,900 $ 351,900
$ - $ 2,236,500
$ 5,634,800 $ 5,634,800
$ 18,835,500 $ 20,340,800
$ 20.68 $ 31.19
$ 4.60 $ 6.97
$ 30,209,800 $ 32,563,000
13-16
CO2 Capture
SCPC Emissions – CO
2
Capture
In addition to removing 90% of CO
2
emissions, the outlet SO
2
from the EFG+ Absorber is reduced to approximately 0.1 ppm (99.9+% removal) and NO x
emissions are reduced by approximately 10%. The resulting emission rates are shown in Table 13-9. Additionally, these reduced emissions are reflected in the O&M costs provided in Table 13-8.
Table 13-9
SCPC Emissions Impacts from CO
2
Capture
Base Case
(100% PRB)
CO
2
Capture
(100% PRB)
NO x lb/MMBtu (HHV) lb/MWh (net)
SO
2 lb/MMBtu (HHV) lb/MWh (net)
PM
10 lb/MMBtu (HHV)
1 lb/MWh (net)
1
CO lb/MMBtu (HHV) lb/MWh (net)
CO
2 lb/MMBtu (HHV) lb/MWh (net)
Hg
% Removal lb/TBtu (HHV) lb/MWh (net)
0.050
0.458
0.060
0.549
0.015
0.137
0.150
1.373
215
1,967
70%
2.315
2.12E-05
0.045
0.581
0.0003
0.003
0.015
0.194
0.150
1.937
22
278
70%
2.315
2.99E-05
1) Particulate matter emissions rate is for front half only excluding back half condensables, for the concentration of particulate matter less than
10 microns in diameter
SCPC Pre-Investment Options for CO
2
Capture
This study was performed with minimal pre-investment in CO
2
capture equipment. The only pre-investments made were the increase in FGD absorber size, allowing expansion of the FGD to achieve 7 ppm SO
2
in the future for the CO
2
capture case and the plot space allocation for future
CO
2
capture equipment. Other options for pre-investment that should be further evaluated in the future are as follows:
13-17
CO2 Capture
• The use of a deaerating condenser in lieu of a standard deaerator arrangement (open feedwater heater) allows for boiler feedwater to be routed to the CO
2
compressor interstages, providing reduced compressor auxiliary load and less steam extraction from the steam cycle.
• Increasing the size of the wet FGD to reduce SO
2
emissions to 1 ppm (instead of 7 ppm assumed for this evaluation). This would eliminate the need for the sodium hydroxide scrubber currently included in Fluor’s scope. Although achieving this low of an SO
2 emission with a wet FGD is typically cost prohibitive, it is likely more cost effective that the use of the sodium hydroxide scrubber. It should be noted that obtaining SO
2 guarantees of 1 ppm from FGD vendors is not likely at this stage.
• Other multi-pollutant flue gas clean-up systems such as J-Power’s ReACT
TM
system
(utilizing regenerated activated carbon) and Powerspan’s ECO
®
system (utilizing electrocatalytic oxidation) may provide emissions requirements more acceptable for SCPC CO
2 capture technology without the need for major modifications.
CO
2
Capture Economics
A 20-year levelized busbar cost analysis was performed using the same assumptions as provided in Chapter 12. The resulting busbar costs are provided in Table 13-10.
Table 13-10
CO2 Capture Busbar Costs
Base Case
(100% PRB)
CO
2
Capture
(100% PRB)
% Increase
IGCC 20-year levelized busbar cost (2006 Real $)
SCPC 20-year levelized busbar cost (2006 Real $)
$45.03
$39.28
$65.41
$62.00
45%
58%
The avoided CO
2
cost can be determined by dividing the differential busbar cost between the capture and non-capture cases by the differential metric tons/MWh between the capture and noncapture cases.
The resulting avoided CO
2
costs are as follows:
• IGCC
$26.28 / Mt CO
2
avoided
• SCPC
$29.64 / Mt CO
2
avoided
The results indicate that adding CO
2
capture to an existing IGCC is a more efficient means of reducing CO
2
emissions than adding CO
2
capture equipment to an existing SCPC facility; however the initial busbar cost difference (pre-CO
2
capture) between the two technologies still results in PC technology having the lowest post-capture busbar cost.
13-18
CO2 Capture
A brief analysis was performed to determine what CO
2
emissions allowance cost ($/Mt) would be required to justify the expense of the addition of CO
2
capture to both technologies (assuming
CO
2
is sold at zero cost). Approximately $30/Mt for SCPC technology and $26/Mt for IGCC technology were determined to be the break-even points. An allowance cost above these figures may justify the additional expense of installing CO
2
capture equipment. Additionally, any CO
2 sales above zero cost ($/Mt) would reduce the breakeven point accordingly.
13-19
14
OTHER CONSIDERATIONS
Byproduct Sales
The two major byproducts from the IGCC process are slag and sulfur. The slag coming off of the bottom of the gasifier is vitrified, has low bulk density, high shear strength, and good leachability characteristics. As such, IGCC slag has the ability to be utilized as a feedstock to a number of different industries.
Identified markets for IGCC slag include:
• Construction structural backfill
• Asphalt paving aggregate
• Portland cement aggregate
• Asphalt shingle roofing granules
• Pipe bedding material
• Blasting grit
• Mineral filler
• Road drainage media
• Water filtering medium
• Water-jet cutting
The sulfur in the syngas is removed in the AGR and then generally either sent to a Claus unit to convert it to elemental sulfur or to a sulfuric acid plant for to make sulfuric acid. The sulfur or sulfuric acid is also utilized in a number of industries, including asphalt, and agriculture.
A smaller potential by-product is the flyash. The flyash produced by the Shell gasifier has very low carbon content and therefore has attractive qualities for use in cement manufacturing.
Co-Production
One advantage of the IGCC technology is the capability of producing a variety of chemicals in addition to the production of electricity, especially during the times of the year when it may not be economically attractive to produce power.
The properties of the syngas produced by the coal gasification process can be adjusted to allow a range of hydrogen to carbon monoxide molar rations, and stand alone gasification plants have been operating for years with refinery waste streams to produce syngas for chemical production.
Various options for downstream integration correspond to a range of value added products.
Figure 14-1 identifies some of the possible products resulting from coal gasification.
14-1
Other Considerations
Power
Generation
Coal
Gasification
Synthesis Gas
Methanol
- Acetate products
- Acetic Acid
- Ethylene / Propylene
Figure 14-1
Products from Syngas
Fisher-Tropes
Liquids
- Gasoline
- Diesel
- Jet Fuel
Hydrogen
-Ammonia
-Fertilizers
- Urea
Synthetic
Natural Gas
CO
2
- Enhanced oil recovery
Plant Degradation
Plant degradation has not been included in the performance estimates or economic analysis. It should be noted that gas turbine degradation (and consequently steam turbine performance reduction) can be significant over time. This may result in 4-5% average degradation over the life of the plant depending on frequency of water wash and gas turbine maintenance (compared to ~2% for a PC Unit).
Lignite Gasification
Another potential lower cost feedstock for an IGCC in Texas would be lignite. While lignite is an abundant resource in Texas, the combination of its high ash content and high moisture content, makes it unattractive to be transported to power plants. Instead, lignite-based power plants are typically located at the “mine mouth”. In the present study, the site location is not near a lignite resource and therefore lignite was not evaluated as a fuel.
However, if a mine-mouth site was used, it might be an economic option. Mine-mouth lignite’s lower fuel cost must be balanced against some undesirable impacts on the IGCC design.
Compared to PRB coal, Texas lignite has more ash, more sulfur, and more moisture. Each of these has a negative impact on thermal efficiency while increasing the capital cost of the design.
Since the Shell gasification technology, a dry coal-feed gasifier, is used here, lignite may be used and still produce plant efficiency in the upper 30’s. The off-set is the increase in coal drying energy required. The use of coal drying processes that utilize low level energy, such as the RWE
Vapour Compression cycle, may make use of the abundant low-level energy in the IGCC cycle that is currently going unused. The use of lignite in slurry-feed gasifiers will likely result in energy penalties too severe to produce economic benefits, even at low fuel costs.
14-2
15
SUMMARY
A summary of the information provided in previous chapters is provided in Table 15-1 and Table
15-2.
15-1
Summary
Table 15-1
Summary Table (1 of 2)
Case
Fuel
PRB (% wt.)
Petcoke (% wt.)
PRB (% heat input)
Petcoke (% heat input)
HHV (Btu/lb)
Capital Cost (2006 USD)
EPC Capital Cost
Owner's Costs
Total Project Cost
EPC Capital Cost, $/kW (73°F Ambient)
Total Project Cost, $/kW (73°F Ambient)
Performance
43°F Dry Bulb, 40°F Wet Bulb
Gross Plant Output, MW
Auxiliary Load, MW
Net Plant Output, MW
Net Plant Heat Rate, Btu/kWh (HHV)
73°F Dry Bulb, 69°F Wet Bulb
Gross Plant Output, MW
Auxiliary Load, MW
Net Plant Output, MW
Net Plant Heat Rate, Btu/kWh (HHV)
93°F Dry Bulb, 77°F Wet Bulb
Gross Plant Output, MW
Auxiliary Load, MW
Net Plant Output, MW
Net Plant Heat Rate, Btu/kWh (HHV)
O&M Cost (2006 USD)
Fixed O&M, $/kW-yr
Variable O&M, $/MWh
Total O&M Cost, $/Year (85% CF)
100% PRB
100%
0%
100%
0%
8,156
$1,318,980,000
$155,240,000
$1,474,220,000
$2,390
$2,670
736.6
137.4
599.2
9,090
709.9
156.8
553.0
9,220
681.5
153.2
528.4
9,350
Base Cases
IGCC
50% PRB / 50% Petcoke
50%
50%
36%
64%
11,194
$1,287,540,000
$139,500,000
$1,427,040,000
$2,330
$2,580
734.2
137.2
597.0
8,950
711.1
158.0
553.0
9,070
682.6
154.5
528.2
9,210
SCPC
100% PRB
100%
0%
100%
0%
8,156
$1,072,580,000
$129,760,000
$1,202,340,000
$1,950
$2,190
623.3
65.4
557.8
9,030
614.5
64.5
550.0
9,150
613.2
64.4
548.8
9,170
CO
2
Capture Cases
IGCC
100% PRB IGCC
SCPC
100% PRB
100%
0%
100%
0%
8,156
$179,220,000 (Note 1)
$17,960,000 (Note 1)
$197,180,000 (Note 1)
$3,630 (Note 1)
$4,040 (Note 1)
Not Evaluated
Not Evaluated
Not Evaluated
Not Evaluated
630.1
216.8
413.3
12,800
Not Evaluated
Not Evaluated
Not Evaluated
Not Evaluated
100%
0%
100%
0%
8,156
$269,430,000 (Note 1)
$26,570,000 (Note 1)
$296,000,000 (Note 1)
$3,440 (Note 1)
$3,840 (Note 1)
Not Evaluated
Not Evaluated
Not Evaluated
Not Evaluated
521.4
131.6
389.8
12,910
Not Evaluated
Not Evaluated
Not Evaluated
Not Evaluated
$25.19
$5.95
$38,426,700
$25.19
$5.66
$37,245,400
$20.68
$4.60
$30,209,800
$34.74
$8.55
$40,661,400
$31.19
$6.97
$32,563,000
Availability Factor 85% 85% 90% Not Evaluated Not Evaluated
Economic Analysis
Capacity Factor
20-year levelized busbar cost, $/MWh (2006 Real $)
Avoided CO
2
Cost, $/Mt CO
2
avoided
85%
$45.03
N/A
85%
$40.89
N/A
85%
$39.28
N/A
N/A
$65.41
$26.28
N/A
$62.00
$29.64
Notes:
1) CO
2
Capture capital costs are based on retrofit of the existing IGCC or PC facilities as provided in the base case alternatives. $/kW values reflect total installed cost to date (including original costs provided in the base case) divided by net plant output with CO2 capture.
15-2
Summary
Table 15-2
Summary Table (2 of 2)
Case
NO x
Emissions lb/MMBtu (HHV) ppmvd @ 15% O
2 lb/MWh (net)
SO
2
Emissions lb/MMBtu (HHV) lb/MWh (net)
PM
10
Emissions (front half) lb/MMBtu (HHV) lb/MWh (net)
CO lb/MMBtu (HHV) ppmvd lb/MWh (net)
CO
2 lb/MMBtu (HHV) lb/MWh (net)
Hg
% Removal lb/TBtu (HHV) lb/MWh (net)
100% PRB
0.063
15
0.581
0.019
0.173
0.007
0.065
0.037
25
0.337
215
1,985
90%
0.778
7.17E-06
Base Cases
IGCC
50% PRB / 50% Petcoke
0.062
15
0.562
0.023
0.210
0.007
0.065
0.036
25
0.337
213
1,934
90%
0.496
4.50E-06
SCPC
100% PRB
0.050
N/A
0.458
0.060
0.549
0.015
0.137
0.150
N/A
1.373
215
1,967
70%
2.315
2.12E-05
CO
2
Capture Cases
IGCC
100% PRB IGCC
SCPC
100% PRB
0.061
15
0.781
0.004
0.051
0.007
0.090
0.035 (Note 1)
25 (Note 1)
0.448 (Note 1)
22
276
90%
0.778
9.96E-06
0.045
N/A
0.581
0.0003
0.003
0.015
0.194
0.150
N/A
1.937
22
278
70%
2.315
2.99E-05
Plant Cooling Requirements, MMBtu/hr (@ 73°F)
Steam Cycle Cooling Requirement, MMBtu/hr
2,141
1,480
661
2,179
1,480
699
2,490
2,300
190
2,101
1,120
981
3,330
1,354
1,976 BOP Auxiliary Cooling Requirement, MMBtu/hr
Total Plant Makeup Water Requirement
GPM (@ 73°F)
Acre-ft/year (@ 85% CF)
4,980
6,830
5,231
7,170
5,800
7,950
6,147
8,430
7,757
10,640
Notes:
1) GE is currently in the process of developing tools to accurately predict CO emissions for high hydrogen fuels. It is estimated that CO emissions will be less than shown for IGCC CO
2
capture technology, however to what extent is unknown at this time.
15-3
Summary
Of the three alternatives evaluated, SCPC technology provides the lowest busbar cost based on this analysis. SCPC technology provides a $5.75/MWh (approximately 13%) lower busbar cost than a comparable IGCC unit when operating on 100% PRB fuel. The 100% PRB SCPC also provides a $1.61/MWh (approximately 4%) lower busbar cost than the IGCC operating on 50%
PRB / 50% petcoke. Of the two IGCC alternatives, the fuel blend case provides the lowest busbar cost, provided that a long-term petcoke supply that meets plant specifications can be found for the project at a reasonable cost.
The SCPC Unit provides a lower capital cost, lower O&M, better performance, and higher availability factor than the IGCC. Although the heat rate for the 50% PRB / 50% petcoke IGCC option is better than the 100% PRB SCPC option (except at 93°F ambient), this difference could likely be overcome by specifying a fuel blend for the SCPC option.
IGCC has an advantage in terms of SO
2
, PM
10
, and mercury emissions, however using the emissions allowance costs provided in Chapter 8, these lower emissions are not enough to overcome the disadvantages discussed above.
In an effort to reduce greenhouse gases, some form of CO
2 legislation may be passed in the future. At this point in time, it is uncertain what form this legislation will take, but it is logical to assume that CO
2 regulations would provide an incentive for CO
2
reduction from power plants.
The installation of CO
2
capture equipment as a retrofit for both of these technologies results in a very significant decrease in net plant output, a significant increase in net plant heat rate, and a significant increase in water consumption. All of these factors result in an increase of the 20year levelized busbar cost by approximately 45% for the IGCC and 58% for the SCPC post CO
2 capture.
SCPC technology still provides the lowest busbar cost after CO
2
capture retrofit, although by less of a gap than pre-CO
2
capture. The avoided cost of CO
2
capture is less for an IGCC implying that IGCC technology is the more economical choice for retrofit of CO
2
capture technology, however the lower initial capital cost (pre-capture) of SCPC technology still results in an overall lower busbar cost for SCPC technology.
It is recommended that additional studies be performed if IGCC, SCPC, or CO
2
capture technology is of interest to the Owner:
• SCR for IGCC technology.
• Two-pressure vs. three-pressure HRSG for IGCC technology.
• Other multi-pollutant flue gas clean-up systems such as J-Power’s ReACT system and
Powerspan’s ECO system for SCPC technology.
• More efficient steam cycle for SCPC technology.
15-4
Summary
• Inlet air cooling methods (chilling vs. evaporative cooling) in conjunction with evaluation of air-side integration for IGCC technology.
• IGCC and SCPC CO
2
capture pre-investment options.
• Other SCPC CO
2
capture technologies such as MHI’s KS-1 process.
• Evaluation of gasifiers from other manufacturers that that may be better suited for CO
2 capture.
• Heat recovery from CO
2
compression.
• Raw water availability study, which may result in different water treatment requirements.
• More detailed studies incorporating gasifier and gas turbine vendor involvement.
Changes in market conditions, improvements in IGCC technology, different fuel specifications, or CO
2
purity specifications could be enough to swing the economics in favor of IGCC.
Therefore it is recommended that utilities consider IGCC technology for future generation needs.
15-5
A
PROCESS FLOW DIAGRAMS
A-1
DEMINERALIZED
WATER
100
611
102
GCT-PFD-2
SYNGAS SATURATOR
MAKEUP
103
SYNGAS FROM
GASIFIER
SYNGAS
COOLER
605
504
SATURATOR PURGE
GCT-PFD-2
GCT-PFD-2
SOUR WATER
STRIPPER PURGE
HP BFW
40-1&2-SGT-TNK-001
SYNGAS WASH
TOWERS
105
101
TO RECOVERED WATER
FLASH DRUM
GCT-PFD-2
104
NOTES:
1.
2.
CONDENSATE
CONDENSATE
CIRC. WATER
CIRC. WATER
204
HP BFW
201
40-1&2-SGT-HTX-003
HYDROLYSIS
PREHEATERS
107
40-1&2-SGT-HTX-002
HYDROLYSIS
INTERCHANGERS
205
40-1&2-SGT-TNK-004
COS/HCN HYDROLYSIS
REACTORS
NO. DATE BY REVISION
A 6/7/06 JAJ INTERNAL REVIEW
B 6/16/06 JAJ INTERNAL REVIEW
C 7/24/06 JAJ INTERNAL REVIEW
D 7/31/06 JAJ INTERNAL REVIEW
E 8/11/06 JAJ FINAL
206
OXYGEN
TO SRU
FROM SOUR
WATER STRIPPER
GCT-PFD-2
301
403
SYNGAS TO
SATURATOR
GCT-PFD-2
40-1&2-SGT-HTX-004
SYNGAS
INTERCHANGERS
302
401
400
402
IP STEAM
SYNGAS TO
COAL/COKE DRYING
313
310
502
303
304
40-1&2-SGT-TNK-005
WATER KNOCKOUT
DRUMS
40-1&2-SGT-HTX-005
FIRST STAGE
SYNGAS CONDENSORS
40-1&2-SGT-HTX-006
SECOND STAGE
SYNGAS CONDENSORS
306
305
40-1&2-SGT-PMP-001A/B
SOUR WATER PUMPS
SELEXOL
AGR
307
40-1&2-SGT-HTX-001
MERCURY REMOVAL
PREHEATERS
308
309
SRU / TGTU
IP BFW
IP STEAM CONDENSATE
316
IP BFW
312
314
CIRC. WATER
SULFUR
40-1&2-SGT-TNK-002
MERCURY ABSORBENT
BEDS
315
GCT-PFD-2
SOUR WATER
TO EFFLUENT
HEAT EXCHANGER
40-1&2-SGT-HTX-015
MERCURY REMOVAL
AFTERCOOLERS
311
HP STEAM
HP BFW
LP STEAM
CONDENSATE
SW TO SOUR
WATER STRIPPER
GCT-PFD-2 date
07-JUN-06 designed
T_McCALL detailed checked
CPS / EPRI IGCC FEASIBILITY
STUDY
PROCESS FLOW DIAGRAM
GAS COOLING AND TREATMENT
project contract
42127 drawing rev
GCT-PFD-1 E
SYNGAS FROM
INTERCHANGERS
GCT-PFD-1
DEMINERALIZED
WATER
GCT-PFD-1
403
611
FROM SYNGAS
WASH TOWERS
GCT-PFD-1
104
40-0-SGT-HTX-013
FLASHED WATER
CONDENSER
705
701
702
40-0-SGT-TNK-008
RECOVERED WATER
FLASH DRUM
703
40-0-SGT-HTX-012
RECOVERED WASH
WATER EXCHANGER
40-0-SGT-PMP-005A/B
RECOVERED WASH
WATER PUMPS
IP STEAM
707
706
40-0-SGT-JET-1
FLASHED WATER
STEAM EJECTOR
708
704
40-0-SGT-FLT-001
RECOVERED WASH
WATER FILTER
712
TO COOLING TOWER
711
SOLIDS TO
LANDFILL
610
SW FROM
TGTU
GCT-PFD-1
311
40-0-SGT-TNK-009
FLASH WATER
CONDENSATE DRUM
TO SYNGAS
WASH TOWER
GCT-PFD-1
504
FROM SOUR
WATER PUMPS
GCT-PFD-1
308
709
40-0-SGT-PMP-006A/B
FLASHED WATER
CONDENSATE PUMP
710
40-0-SGT-HTX-009
SOUR WATER
FEED / EFFLUENT
EXCHANGER
501
503
40-0-SGT-TNK-007
SOUR WATER
STRIPPER
40-0-SGT-PMP-004A/B
SOUR WATER STRIPPER
BOTTOM PUMPS
40-1&2-SGT-HTX-007
SWEET SYNGAS
HEATER
601
HP BFW
HP BFW
602
SYNGAS TO
GAS TURBINES
608
40-1&2-SGT-TNK-006
SYNGAS SATURATOR
HP BFW
607
HP BFW
40-1&2-SGT-HTX-008
SATURATOR
HEATER
603
604
40-1&2-SGT-PMP-002A/B
SATURATOR CIRCULATION
PUMPS
606
605
SATURATOR PURGE
TO SYNGAS WASH
TOWER
GCT-PFD-1
NO. DATE BY REVISION
A 6/7/06 JAJ INTERNAL REVIEW
B 6/16/06 JAJ INTERNAL REVIEW
C 7/24/06 JAJ INTERNAL REVIEW
D 7/31/06 JAJ INTERNAL REVIEW
E 8/11/06 JAJ FINAL
502
506
505
40-0-SGT-PMP-003A/B
SOUR WATER PUMP
AROUND PUMPS
40-0-SGT-HTX-011
SOUR WATER
REBOILER
LP STEAM
CONDENSATE
40-0-SGT-HTX-010
SOUR WATER PUMP
AROUND COOLER
TO SULFUR
RECOVERY UNIT
GCT-PFD-1 date
07-JUN-06 designed
T_McCALL detailed checked
JAJ
CPS / EPRI IGCC FEASIBILITY
STUDY
PROCESS FLOW DIAGRAM
GAS COOLING AND TREATMENT
project contract
42127 drawing rev
GCT-PFD-2 E
TAIL GAS
FROM TGTU
DEMINERALIZED
WATER
SATURATOR
PURGE
GCT-PFD-4
SOUR WATER
STRIPPER PURGE
GCT-PFD-4
100
605
SYNGAS FROM
GASIFIER
102
IP STEAM
504
103
SYNGAS
COOLER
40-1&2-SGT-TNK-001
SYNGAS WASH
TOWERS
101
105
316
SW TO SOUR
WATER STRIPPER
40-1&2-SGT-PMP-101A/B
KNOCKOUT WATER PUMPS
207
321
201
405
106
208
2
40-1&2-SGT-HTX-103
ND STAGE SOUR GAS
SHIFT OUTLET
INTERCHANGERS
202
40-1&2-SGT-HTX-101
1
ST
STAGE SOUR GAS
SHIFT INLET
INTERCHANGERS
209
203
204
HP BFW
HP BFW
40-1&2-SGT-HTX-120
1
ST
STAGE SOUR GAS
SHIFT PREHEATERS
TO RECOVERED WATER
FLASH DRUM
GCT-PFD-4
104
40-1&2-SGT-TNK-103
WATER FLASH
DRUMS
322
206
40-1&2-SGT-TNK-101
1
ST
STAGE SOUR GAS
SHIFT REACTORS
2
40-1&2-SGT-TNK-102
ND STAGE SOUR GAS
SHIFT REACTORS
HP BFW
319
320
40-1&2-SGT-HTX-114
RECYCLE STEAM
GENERATORS
HP BFW
205
318
40-1&2-SGT-HTX-102
1
ST
STAGE SOUR GAS
SHIFT OUTLET
INTERCHANGERS
401
40-0-SGT-HTX-012
WASTEWATER
INTERCHANGER
317
309
315
323
306
40-1&2-SGT-HTX-109
5
TH
SOUR GAS
CONDENSERS
311
308
40-1&2-SGT-TNK-005
WATER KNOCKOUT
DRUMS
CONDENSATE
307
40-1&2-SGT-HTX-110
6
TH
SOUR GAS
CONDENSERS
CIRC. WATER
40-1&2-SGT-HTX-111
7
TH
SOUR GAS
CONDENSERS
312
40-1&2-SGT-TNK-002
MERCURY ADSORBENT
BEDS
313
40-1&2-SGT-HTX-015
MERCURY REMOVAL
AFERCOOLERS
CIRC. WATER
314
CIRC. WATER
400
614
SELEXOL
AGR
40-1&2-SGT-HTX-104
SATURATOR HEATERS
301
302
40-1&2-SGT-HTX-105
1
ST
SOUR GAS
CONDENSERS
303
40-1&2-SGT-HTX-106
2
ND
SOUR GAS
CONDENSERS
304
40-1&2-SGT-HTX-107
3
RD
SOUR GAS
CONDENSERS
305
40-1&2-SGT-HTX-108
4
TH
SOUR GAS
CONDENSERS
406 407
40-0-SGT-CMP-101A/B/C/D
CO2 COMPRESSOR
W / INTERCOOLERS
404
414
OXYGEN
TO SRU
OXYGEN
615
609
607
611
DEMIN. WATER
TO HTX-012
608
606
RECIRC WATER
TO SATURATOR
RECIRC WATER
FROM SATURATOR
GCT-PFD-4
SYNGAS TO
SATURATOR
GCT-PFD-4
403
616
HP NITROGEN TO
SATURATOR.
610
DEMIN. WATER
FROM HTX-012
SRU / TGTU
417
402
613
413
HP NITROGEN
SYNGAS TO
COAL/COKE DRYING
CO2 TO PIPELINE
SULFUR
405
TAIL GAS TO
SHIFT REACTORS
GCT-PFD-3
416
SW TO SOUR
WATER STRIPPER
NO. DATE BY REVISION
A 6/7/06 JAJ INTERNAL REVIEW
B 8/11/06 JAJ INTERNAL REVIEW
C 8/28/06 JAJ INTERNAL REVIEW
D 9/14/06 TMA FINAL
- DENOTES ORIGINAL EQUIPMENT
REUSED FOR CO2 CAPTURE.
date
07-JUN-06 designed
T_McCALL detailed checked
CPS / EPRI IGCC FEASIBILITY
STUDY
PROCESS FLOW DIAGRAM
GAS COOLING AND TREATMENT - CO2 CAPTURE
project contract
42127 drawing rev
HP NITROGEN
FROM HTX-106
RECIRC WATER
FROM HTX-104
GCT-PFD-3
SYNGAS FROM
INTERCHANGERS
GCT-PFD-3
DEMIN. WATER
GCT-PFD-3
616
608
403
611
FROM SYNGAS
WASH TOWERS
GCT-PFD-3
DEMIN. WATER
TO HTX-108
GCT-PFD-3
104
610
701
702
40-0-SGT-TNK-008
RECOVERED WATER
FLASH DRUM
703
40-0-SGT-HTX-012
RECOVERED WASH
WATER EXCHANGER
704
40-1&2-SGT-FLT-101A/B
WASH WATER FILTERS
712
TO COOLING TOWER
711
SOLIDS TO
COAL PILE
40-0-SGT-HTX-013
FLASHED WATER
CONDENSER
705
IP STEAM
40-1&2-SGT-PMP-005A/B
RECOVERED WASH
WATER PUMPS
40-0-SGT-JET-1
FLASHED WATER
STEAM EJECTOR
707
706
708
SW FROM
TGTU
GCT-PFD-3
416
40-0-SGT-TNK-009
FLASH WATER
CONDENSATE DRUM
TO SYNGAS
WASH TOWER
GCT-PFD-3
504
SOUR WATER
FROM TNK-005
310
709
40-0-SGT-PMP-006A/B
FLASHED WATER
CONDENSATE PUMP
710
40-0-SGT-HTX-009
SOUR WATER
FEED / EFFLUENT
EXCHANGER
501
503
40-0-SGT-TNK-007
SOUR WATER
STRIPPER
40-0-SGT-PMP-004A/B
SOUR WATER STRIPPER
BOTTOM PUMPS
601
40-1&2-SGT-TNK-006
SYNGAS SATURATORS
HP BFW
602
40-1&2-SGT-HTX-006
SWEET SYNGAS
HEATERS
SYNGAS TO
GAS TURBINES
HP BFW
603
502
604
40-1&2-SGT-PMP-002A/B
SATURATOR CIRCULATION
PUMPS
506
505
40-0-SGT-PMP-003A/B
SOUR WATER PUMP
AROUND PUMPS
40-0-SGT-HTX-011
SOUR WATER
REBOILER
LP STEAM
CONDENSATE
606
605
40-0-SGT-HTX-010
SOUR WATER PUMP
AROUND COOLER
RECIRC WATER
TO HTX-104
GCT-PFD-3
SAT. PURGE TO
WASH TOWER
GCT-PFD-3
TO SULFUR
RECOVERY UNIT
GCT-PFD-3
NO. DATE BY REVISION
A 9/14/06 TMA FINAL date
07-JUN-06 designed
T_McCALL detailed checked
JAJ
CPS / EPRI IGCC FEASIBILITY
STUDY
PROCESS FLOW DIAGRAM
GAS COOLING AND TREATMENT
project contract
42127 drawing rev
SYNGAS TREATING AREA
43F PRB
Table 1
Component Balance
9/14/2006
Project No: 42127
Stream Number
Stream Description
Overall Properties
Pressure, psia
Temperature, °F
Mass Flow, lb/hr
Mole Flow, lbmole/hr
Component lb-moles/hr
NH3
N2
O2
NO2
SO2
AR
Sulfur
CH4
CO
CO2
COS
H2
H2O
H2S
HCN
Vapor Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, ACFM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
Liquid Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, USGPM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
100
Total Makeup
Demineralized
Water
101
Raw Syngas
102
Demin Water to
Wash Tower
103
Water to Wash
Tower
104
Wash Tower
Bottoms Stream
105
Wash Tower
Overhead Vapor
107
Hydrolysis
Reactor Feed
(prior to preheat)
201
Hydrolysis
Reactor Feed
(after preheat)
204
Hydrolysis
Reactor Feed
14,147
254,865
510
62.30
0.684
1.031
0.363
18.0
---
---
---
---
---
---
---
---
60
100
254,865
14,147
0.0
14,147.3
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
---
---
---
---
---
---
---
---
42,556
901,724
12,945
1.16
0.023
0.347
0.039
21.19
540
450
901,724
42,556
8.3
25,497.0
1,133.3
5.5
11,397.9
1,758.4
71.5
2.0
1.9
2,268.0
0.0
0.0
0.0
412.5
0.0
500
100
117,000
6,495
0.0
6,494.6
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
6,495
117,000
234
62.35
0.680
1.030
0.363
18.0
---
---
---
---
---
---
---
---
11,311
203,773
414
61.42
0.485
1.032
0.376
18.0
---
---
---
---
---
---
---
---
480
135
203,773
11,311
0.0
11,310.9
0.0
0.0
0.0
0.0
0.0
0.0
0.1
0.0
0.0
0.0
0.0
0.0
0.0
520
280
172,170
9,555
1.1
9,549.5
0.3
0.1
0.0
2.1
1.2
0.0
0.4
0.2
0.0
0.0
0.0
0.0
0.0
9,555
172,170
375
57.22
0.199
1.076
0.397
18.0
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
44,588
943,246
11,026
1.43
0.020
0.351
0.032
21.15
519
260
943,246
44,588
8.3
25,506.6
1,341.0
5.5
11,440.3
3,522.5
74.6
1.9
1.6
2,273.3
0.0
0.0
0.0
412.5
0.0
---
---
---
---
---
---
---
---
44,313
933,327
10,955
1.42
0.020
0.352
0.033
21.06
519
260
933,327
44,313
8.3
25,495.0
1,132.2
5.5
11,396.8
3,519.9
71.2
1.9
1.6
2,267.8
0.0
0.0
0.0
412.5
0.0
---
---
---
---
---
---
---
---
44,588
943,246
12,499
1.26
0.021
0.350
0.035
21.15
518
350
943,246
44,588
8.3
25,506.6
1,341.0
5.5
11,440.3
3,522.5
74.6
1.9
1.6
2,273.3
0.0
0.0
0.0
412.5
0.0
517
425
943,246
44,588
8.3
25,506.6
1,341.0
5.5
11,440.3
3,522.5
74.6
1.9
1.6
2,273.3
0.0
0.0
0.0
412.5
0.0
---
---
---
---
---
---
---
---
44,588
943,246
13,721
1.15
0.023
0.351
0.038
21.15
Material Balance SGT PRB 25% H2S 16 Sep.xls Mat Bal Page 1 of 7
SYNGAS TREATING AREA
43F PRB
Table 1
Component Balance
9/14/2006
Project No: 42127
Stream Number
Stream Description
Overall Properties
Pressure, psia
Temperature, °F
Mass Flow, lb/hr
Mole Flow, lbmole/hr
Component lb-moles/hr
NH3
N2
O2
NO2
SO2
AR
Sulfur
CH4
CO
CO2
COS
H2
H2O
H2S
HCN
Vapor Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, ACFM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
Liquid Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, USGPM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
205
Hyfdrolysis
Reactor Effluent
206
Hydrolysis
Reactor Effluent
(after heat exchange)
301
Sour Syngas to
Interchanger
302
Sour Syngas from Interchanger
303
Syngas from First
Stage
Condensation
304
Syngas from
Second Stage
Condensation
305
Syngas to
Mercury Removal
Preheat
306
Sour Water from
Sour Syngas
Condensation
307
Sour Water
Recycle to
Syngas
Condensation
---
---
---
---
---
---
---
---
44,588
943,246
13,995
1.12
0.023
0.351
0.038
21.15
507
425
943,246
44,588
8.3
25,506.6
1,348.0
0.3
11,442.1
3,513.6
79.9
0.0
3.4
2,273.3
0.0
0.0
0.0
412.5
0.0
---
---
---
---
---
---
---
---
44,588
943,246
12,551
1.25
0.021
0.350
0.035
21.15
506
335
943,246
44,588
8.3
25,506.6
1,348.0
0.3
11,442.1
3,513.6
79.9
0.0
3.4
2,273.3
0.0
0.0
0.0
412.5
0.0
506
273
963,246
45,698
8.3
25,506.6
1,348.4
0.3
11,442.1
4,621.9
79.9
0.0
4.1
2,273.4
0.0
0.0
0.0
412.5
0.0
64
1,153
3
57.44
0.205
1.072
0.397
18.0
45,634
962,092
11,754
1.36
0.020
0.354
0.033
21.08
44,031
933,209
11,017
1.41
0.019
0.349
0.032
21.19
1,667
30,036
64
58.19
0.230
1.061
0.397
18.0
505
248
963,246
45,698
8.3
25,506.6
1,348.4
0.3
11,442.1
4,621.9
79.9
0.0
4.1
2,273.4
0.0
0.0
0.0
412.5
0.0
502
110
963,246
45,698
8.3
25,506.6
1,348.4
0.3
11,442.1
4,621.9
79.9
0.0
4.1
2,273.4
0.0
0.0
0.0
412.5
0.0
41,210
882,362
8,353
1.76
0.017
0.340
0.028
21.41
4,487
80,884
162
62.07
0.652
1.030
0.367
18.0
---
---
---
---
---
---
---
---
41,176
881,735
8,209
1.79
0.017
0.340
0.028
21.41
501
100
881,735
41,176
8.3
25,506.4
1,346.8
0.3
11,442.1
104.9
79.6
0.0
1.4
2,273.3
0.0
0.0
0.0
412.5
0.0
41,176
881,735
8,209
1.79
0.017
0.340
0.028
21.41
4,522
81,511
163
62.33
0.718
1.029
0.363
18.0
501
100
963,246
45,698
8.3
25,506.6
1,348.4
0.3
11,442.1
4,621.9
79.9
0.0
4.1
2,273.4
0.0
0.0
0.0
412.5
0.0
1,110
20,000
40
62.33
0.718
1.029
0.363
18.0
---
---
---
---
---
---
---
---
521
100
20,000
1,110
0.0
1,108.3
0.1
0.0
0.0
0.0
0.4
0.0
0.6
0.0
0.0
0.0
0.0
0.0
0.0
4,522
81,511
163
62.33
0.718
1.029
0.363
18.0
0
0
0
1.79
0.017
0.340
0.028
21.41
501
100
81,511
4,522
0.1
4,517.0
0.3
0.0
0.0
0.2
1.6
0.0
2.6
0.1
0.0
0.0
0.0
0.0
0.0
Material Balance SGT PRB 25% H2S 16 Sep.xls Mat Bal Page 2 of 7
SYNGAS TREATING AREA
43F PRB
Table 1
Component Balance
9/14/2006
Project No: 42127
Stream Number
Stream Description
Overall Properties
Pressure, psia
Temperature, °F
Mass Flow, lb/hr
Mole Flow, lbmole/hr
Component lb-moles/hr
NH3
N2
O2
NO2
SO2
AR
Sulfur
CH4
CO
CO2
COS
H2
H2O
H2S
HCN
Vapor Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, ACFM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
Liquid Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, USGPM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
308
Sour Water to
Elluent Heat
Exchange
309
Sour Gas to
Sulrur Recovery
Unit (SRU)
310
Recycle Gas from SRU
311
Sour Water from
Tail Gas Treating
(TGTU) to Sour
Water Stripper
312
Sulfur Product
313
Oxygen to SRU
314
Syngas to
Mercury Removal
315
Syngas from
Mercury Removal
316
Syngas to AGR
---
---
---
---
---
---
---
---
315
10,316
784
0.22
0.016
0.242
0.014
32.70
40
100
10,316
315
0.0
14.3
0.0
0.0
0.0
1.9
0.0
0.0
127.5
80.8
0.1
12.1
0.0
78.6
0.0
3,412
61,511
123
62.33
0.718
1.029
0.363
18.0
0
0
0
1.79
0.017
0.340
0.028
21.41
519
100
61,511
3,412
0.1
3,408.7
0.2
0.0
0.0
0.1
1.2
0.0
2.0
0.1
0.0
0.0
0.0
0.0
0.0
---
---
---
---
---
---
---
---
275
9,919
65
2.54
0.023
0.278
0.024
36.02
556
303
9,919
275
0.0
5.5
0.0
0.0
0.0
0.0
0.0
0.0
11.6
208.8
0.0
43.5
2.6
3.4
0.0
66
104
1,155
64
0
0
0
0.06
0.009
1.354
0.086
5.17
64
1,155
2
62.18
0.651
1.031
0.365
18.0
0.0
0.0
0.0
0.0
0.0
64.1
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
100
100
2,293
72
---
---
---
---
---
---
---
---
32.1
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
71.5
100
100
1,568
49
49
1,568
49
0.53
0.022
0.223
0.016
31.80
---
---
---
---
---
---
---
---
0.0
13.2
46.8
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
500
105
881,735
41,176
---
---
---
---
---
---
---
---
41,176
881,735
8,303
1.77
0.017
0.340
0.028
21.41
8.3
25,506.4
1,346.8
0.3
11,442.1
104.9
79.6
0.0
1.4
2,273.3
0.0
0.0
0.0
412.5
0.0
---
---
---
---
---
---
---
---
41,176
881,735
8,336
1.76
0.017
0.340
0.028
21.41
498
105
881,735
41,176
8.3
25,506.4
1,346.8
0.3
11,442.1
104.9
79.6
0.0
1.4
2,273.3
0.0
0.0
0.0
412.5
0.0
497
100
881,735
41,176
8.3
25,506.4
1,346.8
0.3
11,442.1
104.9
79.6
0.0
1.4
2,273.3
0.0
0.0
0.0
412.5
0.0
---
---
---
---
---
---
---
---
41,176
881,735
8,275
1.78
0.017
0.340
0.028
21.41
Material Balance SGT PRB 25% H2S 16 Sep.xls Mat Bal Page 3 of 7
SYNGAS TREATING AREA
43F PRB
Table 1
Component Balance
9/14/2006
Project No: 42127
Stream Number
Stream Description
Overall Properties
Pressure, psia
Temperature, °F
Mass Flow, lb/hr
Mole Flow, lbmole/hr
Component lb-moles/hr
NH3
N2
O2
NO2
SO2
AR
Sulfur
CH4
CO
CO2
COS
H2
H2O
H2S
HCN
Vapor Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, ACFM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
Liquid Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, USGPM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
400
Sweet Syngas from Selexol
401
Sweet Syngas to
Syngas
Interchanger
402
Sweet Syngas to
Coal Drying
403
Sweet Syngas to
Saturator
501
Primary Sour
Water Stripper
Feed
502
Sopur Water
Stripper
Overhead Vapor to SRU
503
Recovered Water from Sour Water
Stripper to heat exchange
504
Recovered Water from Sour Water
Stripper to Wash
Tower
505
Pump Around from SWS to Air
Cooler
---
---
---
---
---
---
---
---
38,138
813,369
7,776
1.74
0.017
0.341
0.028
21.33
490
100
813,369
38,138
7.7
23,688.3
1,181.7
0.1
10,668.5
97.9
0.9
0.0
1.3
2,108.5
0.0
0.0
0.0
383.3
0.0
---
---
---
---
---
---
---
---
40,860
871,419
8,331
1.74
0.017
0.341
0.028
21.33
490
100
871,419
40,860
8.3
25,378.9
1,266.0
0.2
11,430.0
104.9
1.0
0.0
1.4
2,259.0
0.0
0.0
0.0
410.6
0.0
---
---
---
---
---
---
---
---
2,722
58,050
555
1.74
0.017
0.341
0.028
21.33
490
100
58,050
2,722
0.6
1,690.6
84.3
0.0
761.4
7.0
0.1
0.0
0.1
150.5
0.0
0.0
0.0
27.4
0.0
489
227
813,369
38,138
7.7
23,688.3
1,181.7
0.1
10,668.5
97.9
0.9
0.0
1.3
2,108.5
0.0
0.0
0.0
383.3
0.0
---
---
---
---
---
---
---
---
38,138
813,369
9,639
1.41
0.020
0.338
0.033
21.33
3,412
61,511
129
59.59
0.301
1.044
0.392
18.0
---
---
---
---
---
---
---
---
500
200
61,511
3,412
0.1
3,408.7
0.2
0.0
0.0
0.1
1.2
0.0
2.0
0.1
0.0
0.0
0.0
0.0
0.0
30
184
292
12
---
---
---
---
---
---
---
---
12
292
46
0.11
0.013
0.341
0.019
24.29
2.2
0.2
0.0
0.0
0.0
0.0
0.0
1.2
3.2
0.5
0.1
0.0
2.2
2.4
0.0
4,517
81,367
175
58.05
0.224
1.064
0.397
18.0
---
---
---
---
---
---
---
---
481
253
81,367
4,517
0.0
4,516.5
0.0
0.0
0.0
0.0
0.0
0.0
0.1
0.0
0.0
0.0
0.0
0.0
0.0
4,517
81,367
168
60.22
0.345
1.040
0.388
18.0
---
---
---
---
---
---
---
---
480
203
81,367
4,517
0.0
4,516.5
0.0
0.0
0.0
0.0
0.0
0.0
0.1
0.0
0.0
0.0
0.0
0.0
0.0
4,517
81,367
168
60.22
0.345
1.040
0.388
18.0
---
---
---
---
---
---
---
---
480
178
81,367
4,517
0.0
4,516.5
0.0
0.0
0.0
0.0
0.0
0.0
0.1
0.0
0.0
0.0
0.0
0.0
0.0
Material Balance SGT PRB 25% H2S 16 Sep.xls Mat Bal Page 4 of 7
SYNGAS TREATING AREA
43F PRB
Table 1
Component Balance
9/14/2006
Project No: 42127
Stream Number
Stream Description
Overall Properties
Pressure, psia
Temperature, °F
Mass Flow, lb/hr
Mole Flow, lbmole/hr
Component lb-moles/hr
NH3
N2
O2
NO2
SO2
AR
Sulfur
CH4
CO
CO2
COS
H2
H2O
H2S
HCN
Vapor Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, ACFM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
Liquid Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, USGPM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
506
Pump Around from Air Cooler to
SWS
601
Saturator
Overhead Vapor
602
Syngas to Gas
Turbines
603
Saturator
Bottoms Liquid
604
Saturator
Bottoms Pump
Discharge
605
Saturator Liquid
Purge to Wash
Tower
606
Saturetor Bottms
Circulation after
Purge
607
Saturator
Circulation Liquid after Make-up
608
Saturator
Circulation Liquid after Satiratpr
Heater
4,517
81,367
168
60.22
0.345
1.040
0.388
18.0
---
---
---
---
---
---
---
---
480
178
81,367
4,517
0.0
4,516.5
0.0
0.0
0.0
0.0
0.0
0.0
0.1
0.0
0.0
0.0
0.0
0.0
0.0
480
303
947,014
45,557
7.7
23,688.2
45,557
947,014
12,805
1.23
0.020
0.365
0.033
20.79
---
---
---
---
---
---
---
---
1,181.6
0.1
10,668.5
7,517.7
0.9
0.0
0.0
2,108.5
0.0
0.0
0.0
383.3
0.0
479
405
947,014
45,557
7.7
23,688.2
1,181.6
0.1
10,668.5
7,517.7
0.9
0.0
0.0
2,108.5
0.0
0.0
0.0
383.3
0.0
45,557
947,014
14,659
1.08
0.021
0.365
0.036
20.79
---
---
---
---
---
---
---
---
481
223
1,125,907
62,483
4.1
62,459.2
0.0
0.0
0.0
8.2
9.4
0.0
---
---
---
---
---
---
---
---
62,483
1,125,907
2,382
58.93
0.262
1.052
0.395
18.0
1.3
0.9
0.0
0.0
0.0
0.0
0.0
516
223
1,125,907
62,483
---
---
---
---
---
---
---
---
62,483
1,125,907
2,382
58.93
0.262
1.052
0.395
18.0
0.0
8.2
9.4
0.0
4.1
62,459.2
0.0
0.0
1.3
0.9
0.0
0.0
0.0
0.0
0.0
300
5,406
11
58.93
0.262
1.052
0.395
18.0
---
---
---
---
---
---
---
---
516
223
5,406
300
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
299.9
0.0
0.0
0.0
0.0
0.0
0.0
516
223
1,120,501
62,183
4.1
62,159.3
0.0
0.0
0.0
8.1
9.3
0.0
1.3
0.9
0.0
0.0
0.0
0.0
0.0
500
217
1,258,366
69,836
4.1
69,812.0
0.0
0.0
0.0
8.1
9.3
0.0
1.3
0.9
0.0
0.0
0.0
0.0
0.0
490
335
1,258,366
69,836
4.1
69,812.0
0.0
0.0
0.0
8.1
9.3
0.0
1.3
0.9
0.0
0.0
0.0
0.0
0.0
---
---
---
---
---
---
---
---
62,183
1,120,501
2,371
58.93
0.262
1.052
0.395
18.0
---
---
---
---
---
---
---
---
69,836
1,258,366
2,654
59.11
0.271
1.050
0.394
18.0
69,836
1,258,366
2,830
55.43
0.160
1.111
0.394
18.0
---
---
---
---
---
---
---
---
Material Balance SGT PRB 25% H2S 16 Sep.xls Mat Bal Page 5 of 7
SYNGAS TREATING AREA
43F PRB
Table 1
Component Balance
9/14/2006
Project No: 42127
Stream Number
Stream Description
Overall Properties
Pressure, psia
Temperature, °F
Mass Flow, lb/hr
Mole Flow, lbmole/hr
Component lb-moles/hr
NH3
N2
O2
NO2
SO2
AR
Sulfur
CH4
CO
CO2
COS
H2
H2O
H2S
HCN
Vapor Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, ACFM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
Liquid Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, USGPM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
610
Demin Water
Make-up to
Saturator (after heat exchange)
611
Demin Water
Make-up to
Saturator (before heat exchange)
701
Flashed Vapor from Wash
Tower Bottoms
Flash
702
Flashed Liquid from Wash
Tower Bottoms
Flash
703
Recovered Wash
Water from Flash
704
Cooled
Recovered Water from Flash
705
Recovered Wash
Water from Flash after Air Cooler
706
Vapors to Jet
Ejector
707
Steam to Jet
Ejector
500
165
137,865
7,653
7,653
137,865
284
60.58
0.379
1.037
0.385
18.0
---
---
---
---
---
---
---
---
0.0
7,652.7
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
500
100
137,865
7,653
7,653
137,865
276
62.35
0.680
1.030
0.363
18.0
---
---
---
---
---
---
---
---
0.0
7,652.7
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
7
177
19,082
1,057
---
---
---
---
---
---
---
---
1,057
19,082
17,105
0.02
0.009
0.451
0.013
18.05
1.1
1,051.8
0.3
0.1
0.0
2.1
1.2
0.0
0.3
0.2
0.0
0.0
0.0
0.0
0.0
7
177
153,088
8,498
0
0
0
0.02
0.009
0.451
0.013
18.05
8,498
153,088
317
60.19
0.349
1.041
0.387
18.0
0.0
8,497.6
0.0
0.0
0.0
0.0
0.0
0.0
0.1
0.0
0.0
0.0
0.0
0.0
0.0
62
177
153,088
8,498
8,498
153,088
317
60.19
0.349
1.041
0.387
18.0
---
---
---
---
---
---
---
---
0.0
8,497.6
0.0
0.0
0.0
0.0
0.0
0.0
0.1
0.0
0.0
0.0
0.0
0.0
0.0
62
118
153,088
8,498
8,498
153,088
309
61.81
0.565
1.032
0.370
18.0
---
---
---
---
---
---
---
---
0.0
8,497.6
0.0
0.0
0.0
0.0
0.0
0.0
0.1
0.0
0.0
0.0
0.0
0.0
0.0
1,047
18,855
39
60.92
0.426
1.036
0.381
18.0
10
227
165
0.02
0.011
0.363
0.018
21.75
7
150
19,082
1,057
1.1
1,051.8
0.3
0.1
0.0
2.1
1.2
0.0
0.3
0.2
0.0
0.0
0.0
0.0
0.0
7
150
227
10
10
227
165
0.02
0.011
0.363
0.018
21.75
---
---
---
---
---
---
---
---
0.0
2.1
1.1
0.0
1.1
5.6
0.2
0.0
0.0
0.2
0.0
0.0
0.0
0.0
0.0
615
491
500
28
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
27.8
0.0
0.0
0.0
0.0
0.0
0.0
---
---
---
---
---
---
---
---
28
500
6
1.29
0.018
0.580
0.029
18.02
Material Balance SGT PRB 25% H2S 16 Sep.xls Mat Bal Page 6 of 7
SYNGAS TREATING AREA
43F PRB
Table 1
Component Balance
Stream Number
Stream Description
Overall Properties
Pressure, psia
Temperature, °F
Mass Flow, lb/hr
Mole Flow, lbmole/hr
Component lb-moles/hr
NH3
N2
O2
NO2
SO2
AR
Sulfur
CH4
CO
CO2
COS
H2
H2O
H2S
HCN
Vapor Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, ACFM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
Liquid Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, USGPM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
708
Jet Ejector
Effluent Vapor to
SWS
709
Condensate
Recovered from
Vacuum Flash
710
Recovered
Condensate to
SWS
711
Solids from
Candle Filers
Recovered in
Wash Tower
712
Recovered Wash
Water to
Disposal
7
326
727
38
---
---
---
---
---
---
---
---
38
727
776
0.02
0.012
0.433
0.019
19.04
0.0
0.2
0.0
0.0
0.0
0.0
0.0
1.1
33.4
0.2
0.0
0.0
2.1
1.1
0.0
1,047
18,855
39
60.92
0.426
1.036
0.381
18.0
0
0
0
0.02
0.011
0.363
0.018
21.75
7
150
18,855
1,047
0.0
1,046.2
0.0
0.1
0.0
0.0
0.0
0.0
0.3
0.0
0.0
0.0
0.0
0.0
0.0
1,047
18,855
39
60.93
0.426
1.036
0.381
18.0
---
---
---
---
---
---
---
---
47
150
18,855
1,047
0.0
1,046.2
0.0
0.1
0.0
0.0
0.0
0.0
0.3
0.0
0.0
0.0
0.0
0.0
0.0
Approximately
110 lb/day of solids will be removed by the filters and sent to the coal pile.
8,498
153,088
309
61.81
0.565
1.032
0.370
18.0
---
---
---
---
---
---
---
---
62
118
153,088
8,498
0.0
8,497.6
0.0
0.0
0.0
0.0
0.0
0.0
0.1
0.0
0.0
0.0
0.0
0.0
0.0
Material Balance SGT PRB 25% H2S 16 Sep.xls Mat Bal Page 7 of 7
9/14/2006
Project No: 42127
SYNGAS TREATING AREA
43F PRB + PETCOKE
Table 1
Component Balance
9/14/2006
Project No: 42127
Stream Number
Stream Description
Overall Properties
Pressure, psia
Temperature, °F
Mass Flow, lb/hr
Mole Flow, lbmole/hr
Component lb-moles/hr
NH3
N2
O2
NO2
SO2
AR
Sulfur
CH4
CO
CO2
COS
H2
H2O
H2S
HCN
Vapor Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, ACFM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
Liquid Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, USGPM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
100
Total Makeup
Demineralized
Water
101
Raw Syngas
102
Demin Water to
Wash Tower
103
Water to Wash
Tower
104
Wash Tower
Bottoms Stream
105
Wash Tower
Overhead Vapor
107
Hydrolysis
Reactor Feed
(prior to preheat)
201
Hydrolysis
Reactor Feed
(after preheat)
204
Hydrolysis
Reactor Feed
13,955
251,395
503
62.30
0.684
1.031
0.363
18.0
---
---
---
---
---
---
---
---
60
100
251,395
13,955
0.0
13,954.7
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
---
---
---
---
---
---
---
---
39,203
850,323
11,948
1.19
0.024
0.335
0.038
21.69
540
450
850,323
39,203
7.2
25,424.2
430.6
43.0
9,891.7
646.0
476.1
4.6
1.5
1,880.1
0.0
0.0
0.0
398.0
0.0
500
100
117,000
6,495
0.0
6,494.6
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
6,495
117,000
234
62.35
0.680
1.030
0.363
18.0
---
---
---
---
---
---
---
---
10,110
182,132
369
61.56
0.508
1.032
0.374
18.0
---
---
---
---
---
---
---
---
480
130
182,132
10,110
0.0
10,109.7
0.0
0.0
0.0
0.0
0.0
0.0
0.2
0.0
0.0
0.0
0.0
0.0
0.0
510
266
146,731
8,142
0.8
8,137.2
1.5
0.3
0.0
1.7
0.4
0.0
0.4
0.1
0.0
0.0
0.0
0.0
0.0
8,142
146,731
317
57.64
0.211
1.069
0.397
18.0
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
41,858
909,315
10,365
1.46
0.020
0.340
0.031
21.72
509
246
909,315
41,858
7.2
25,436.1
923.5
43.0
10,030.0
2,624.8
492.5
4.3
1.3
1,897.8
0.0
0.0
0.0
398.0
0.0
---
---
---
---
---
---
---
---
41,171
885,724
10,183
1.45
0.020
0.342
0.031
21.51
509
245
885,724
41,171
7.2
25,422.6
430.2
43.0
9,890.9
2,618.5
474.6
4.3
1.3
1,880.0
0.0
0.0
0.0
398.0
0.0
---
---
---
---
---
---
---
---
41,858
909,315
11,982
1.26
0.022
0.339
0.034
21.72
508
350
909,315
41,858
7.2
25,436.1
923.5
43.0
10,030.0
2,624.8
492.5
4.3
1.3
1,897.8
0.0
0.0
0.0
398.0
0.0
507
425
909,315
41,858
7.2
25,436.1
923.5
43.0
10,030.0
2,624.8
492.5
4.3
1.3
1,897.8
0.0
0.0
0.0
398.0
0.0
---
---
---
---
---
---
---
---
41,858
909,315
13,149
1.15
0.023
0.340
0.037
21.72
Material Balance SGT PRB + PETOCKE 50% H2S 16 Sep.xls Mat Bal Page 1 of 7
SYNGAS TREATING AREA
43F PRB + PETCOKE
Table 1
Component Balance
9/14/2006
Project No: 42127
Stream Number
Stream Description
Overall Properties
Pressure, psia
Temperature, °F
Mass Flow, lb/hr
Mole Flow, lbmole/hr
Component lb-moles/hr
NH3
N2
O2
NO2
SO2
AR
Sulfur
CH4
CO
CO2
COS
H2
H2O
H2S
HCN
Vapor Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, ACFM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
Liquid Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, USGPM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
205
Hyfdrolysis
Reactor Effluent
206
Hydrolysis
Reactor Effluent
(after heat exchange)
301
Sour Syngas to
Interchanger
302
Sour Syngas from Interchanger
303
Syngas from First
Stage
Condensation
304
Syngas from
Second Stage
Condensation
305
Syngas to
Mercury Removal
Preheat
306
Sour Water from
Sour Syngas
Condensation
307
Sour Water
Recycle to
Syngas
Condensation
---
---
---
---
---
---
---
---
41,858
909,315
13,238
1.14
0.023
0.340
0.037
21.72
505
427
909,315
41,858
7.2
25,436.1
968.5
2.1
10,034.3
2,575.6
533.3
0.1
5.5
1,897.8
0.0
0.0
0.0
398.0
0.0
---
---
---
---
---
---
---
---
41,858
909,315
11,671
1.30
0.021
0.339
0.033
21.72
504
324
909,315
41,858
7.2
25,436.1
968.5
2.1
10,034.3
2,575.6
533.3
0.1
5.5
1,897.8
0.0
0.0
0.0
398.0
0.0
504
261
929,315
42,968
7.2
25,436.1
968.8
2.1
10,034.3
3,682.7
533.8
0.1
6.7
1,897.8
0.0
0.0
0.0
398.0
0.0
129
2,331
5
57.80
0.216
1.066
0.397
18.0
42,838
926,984
10,908
1.42
0.020
0.343
0.031
21.64
41,875
909,616
10,442
1.45
0.020
0.340
0.031
21.72
1,093
19,699
42
58.33
0.236
1.059
0.396
18.0
503
243
929,315
42,968
7.2
25,436.1
968.8
2.1
10,034.3
3,682.7
533.8
0.1
6.7
1,897.8
0.0
0.0
0.0
398.0
0.0
500
110
929,315
42,968
7.2
25,436.1
968.8
2.1
10,034.3
3,682.7
533.8
0.1
6.7
1,897.8
0.0
0.0
0.0
398.0
0.0
39,413
865,222
8,014
1.80
0.018
0.332
0.027
21.95
3,555
64,093
129
62.04
0.650
1.029
0.367
18.0
---
---
---
---
---
---
---
---
39,379
864,614
7,875
1.83
0.017
0.332
0.027
21.96
499
100
864,614
39,379
7.2
25,436.0
967.9
2.1
10,034.2
101.1
532.1
0.1
2.7
1,897.7
0.0
0.0
0.0
398.0
0.0
39,379
864,614
7,875
1.83
0.017
0.332
0.027
21.96
3,589
64,701
129
62.30
0.716
1.029
0.363
18.0
499
100
929,315
42,968
7.2
25,436.1
968.8
2.1
10,034.3
3,682.7
533.8
0.1
6.7
1,897.8
0.0
0.0
0.0
398.0
0.0
1,109
20,000
40
62.31
0.716
1.029
0.363
18.0
---
---
---
---
---
---
---
---
519
100
20,000
1,109
0.0
1,107.1
0.5
0.0
0.0
0.0
0.3
0.0
1.2
0.0
0.0
0.0
0.0
0.0
0.0
3,589
64,701
129
62.30
0.716
1.029
0.363
18.0
0
0
0
1.83
0.017
0.332
0.027
21.96
499
100
64,701
3,589
0.0
3,581.6
1.7
0.0
0.0
0.2
1.0
0.0
4.0
0.1
0.0
0.0
0.0
0.0
0.0
Material Balance SGT PRB + PETOCKE 50% H2S 16 Sep.xls Mat Bal Page 2 of 7
SYNGAS TREATING AREA
43F PRB + PETCOKE
Table 1
Component Balance
9/14/2006
Project No: 42127
Stream Number
Stream Description
Overall Properties
Pressure, psia
Temperature, °F
Mass Flow, lb/hr
Mole Flow, lbmole/hr
Component lb-moles/hr
NH3
N2
O2
NO2
SO2
AR
Sulfur
CH4
CO
CO2
COS
H2
H2O
H2S
HCN
Vapor Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, ACFM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
Liquid Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, USGPM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
308
Sour Water to
Elluent Heat
Exchange
309
Sour Gas to
Sulrur Recovery
Unit (SRU)
310
Recycle Gas from SRU
311
Sour Water from
Tail Gas Treating
(TGTU) to Sour
Water Stripper
312
Sulfur Product
313
Oxygen to SRU
314
Syngas to
Mercury Removal
315
Syngas from
Mercury Removal
316
Syngas to AGR
---
---
---
---
---
---
---
---
1,072
39,244
2,648
0.25
0.014
0.233
0.011
36.61
40
100
39,244
1,072
0.0
12.0
0.0
0.0
0.0
1.8
0.0
0.0
127.2
387.1
1.7
10.6
0.0
531.5
0.0
2,479
44,701
89
62.30
0.716
1.029
0.363
18.0
0
0
0
1.83
0.017
0.332
0.027
21.96
519
100
44,701
2,479
0.0
2,474.5
1.2
0.0
0.0
0.1
0.7
0.0
2.8
0.0
0.0
0.0
0.0
0.0
0.0
556
303
23,591
688
688
23,591
163
2.41
0.023
0.287
0.027
34.29
---
---
---
---
---
---
---
---
0.0
13.5
493.3
0.0
139.1
6.3
17.9
0.0
0.0
17.8
0.0
0.0
0.0
0.0
0.0
66
104
1,155
64
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
64.1
0.0
0.0
0.0
0.0
0.0
0.0
64
1,155
2
62.18
0.651
1.031
0.365
18.0
0
0
0
0.06
0.009
1.354
0.086
5.17
---
---
---
---
---
---
---
---
100
100
15,263
476
0.0
0.0
0.0
0.0
0.0
0.0
476.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
32.1
---
---
---
---
---
---
---
---
39,376
864,568
7,965
1.81
0.017
0.332
0.027
21.96
498
105
864,568
39,376
7.2
25,436.0
967.9
2.1
10,034.2
101.1
532.1
0.1
0.0
1,897.7
0.0
0.0
0.0
398.0
0.0
---
---
---
---
---
---
---
---
232
7,387
231
0.53
0.022
0.223
0.016
31.80
100
100
7,387
232
0.0
13.2
220.7
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
---
---
---
---
---
---
---
---
39,376
864,568
7,981
1.81
0.017
0.332
0.027
21.96
497
105
864,568
39,376
7.2
25,436.0
967.9
2.1
10,034.2
101.1
532.1
0.1
0.0
1,897.7
0.0
0.0
0.0
398.0
0.0
496
100
864,568
39,376
7.2
25,436.0
967.9
2.1
10,034.2
101.1
532.1
0.1
0.0
1,897.7
0.0
0.0
0.0
398.0
0.0
---
---
---
---
---
---
---
---
39,376
864,568
7,922
1.82
0.017
0.332
0.027
21.96
Material Balance SGT PRB + PETOCKE 50% H2S 16 Sep.xls Mat Bal Page 3 of 7
SYNGAS TREATING AREA
43F PRB + PETCOKE
Table 1
Component Balance
9/14/2006
Project No: 42127
Stream Number
Stream Description
Overall Properties
Pressure, psia
Temperature, °F
Mass Flow, lb/hr
Mole Flow, lbmole/hr
Component lb-moles/hr
NH3
N2
O2
NO2
SO2
AR
Sulfur
CH4
CO
CO2
COS
H2
H2O
H2S
HCN
Vapor Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, ACFM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
Liquid Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, USGPM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
400
Sweet Syngas from Selexol
401
Sweet Syngas to
Syngas
Interchanger
402
Sweet Syngas to
Coal Drying
403
Sweet Syngas to
Saturator
501
Primary Sour
Water Stripper
Feed
502
Sopur Water
Stripper
Overhead Vapor to SRU
503
Recovered Water from Sour Water
Stripper to heat exchange
504
Recovered Water from Sour Water
Stripper to Wash
Tower
505
Pump Around from SWS to Air
Cooler
2
35
0
62.35
0.680
1.029
0.363
18.0
37,160
800,681
7,583
1.76
0.017
0.336
0.027
21.55
490
100
800,717
37,162
7.0
24,554.2
563.4
0.4
9,724.7
98.1
0.5
0.1
0.0
1,829.6
0.0
0.0
0.0
384.4
0.0
2
36
0
62.35
0.680
1.029
0.363
18.0
38,302
825,287
7,816
1.76
0.017
0.336
0.027
21.55
490
100
825,324
38,304
7.2
25,308.8
580.7
0.4
10,023.6
101.1
0.5
0.1
0.0
1,885.8
0.0
0.0
0.0
396.2
0.0
---
---
---
---
---
---
---
---
37,162
800,717
8,750
1.53
0.019
0.333
0.030
21.55
489
181
800,717
37,162
7.0
24,554.2
563.4
0.4
9,724.7
98.1
0.5
0.1
0.0
1,829.6
0.0
0.0
0.0
384.4
0.0
0
1
0
62.35
0.680
1.029
0.363
18.0
1,142
24,606
233
1.76
0.017
0.336
0.027
21.55
490
100
24,607
1,142
0.0
56.2
0.0
0.0
0.0
11.8
0.0
0.2
754.6
17.3
0.0
298.9
3.0
0.0
0.0
2,479
44,701
94
59.56
0.301
1.044
0.392
18.0
---
---
---
---
---
---
---
---
498
200
44,701
2,479
0.0
2,474.5
1.2
0.0
0.0
0.1
0.7
0.0
2.8
0.0
0.0
0.0
0.0
0.0
0.0
30
169
296
12
---
---
---
---
---
---
---
---
12
296
45
0.11
0.013
0.336
0.017
24.70
2.9
0.2
0.0
0.0
0.0
0.0
0.0
0.8
2.3
2.7
0.3
0.0
1.8
1.1
0.0
3,315
59,727
128
58.05
0.224
1.064
0.397
18.0
---
---
---
---
---
---
---
---
481
253
59,727
3,315
0.0
3,315.2
0.0
0.0
0.0
0.0
0.0
0.0
0.1
0.0
0.0
0.0
0.0
0.0
0.0
3,315
59,727
124
60.20
0.343
1.040
0.388
18.0
---
---
---
---
---
---
---
---
480
203
59,727
3,315
0.0
3,315.2
0.0
0.0
0.0
0.0
0.0
0.0
0.1
0.0
0.0
0.0
0.0
0.0
0.0
3,315
59,727
124
60.20
0.343
1.040
0.388
18.0
---
---
---
---
---
---
---
---
480
179
59,727
3,315
0.0
3,315.2
0.0
0.0
0.0
0.0
0.0
0.0
0.1
0.0
0.0
0.0
0.0
0.0
0.0
Material Balance SGT PRB + PETOCKE 50% H2S 16 Sep.xls Mat Bal Page 4 of 7
SYNGAS TREATING AREA
43F PRB + PETCOKE
Table 1
Component Balance
9/14/2006
Project No: 42127
Stream Number
Stream Description
Overall Properties
Pressure, psia
Temperature, °F
Mass Flow, lb/hr
Mole Flow, lbmole/hr
Component lb-moles/hr
NH3
N2
O2
NO2
SO2
AR
Sulfur
CH4
CO
CO2
COS
H2
H2O
H2S
HCN
Vapor Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, ACFM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
Liquid Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, USGPM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
506
Pump Around from Air Cooler to
SWS
601
Saturator
Overhead Vapor
602
Syngas to Gas
Turbines
603
Saturator
Bottoms Liquid
604
Saturator
Bottoms Pump
Discharge
605
Saturator Liquid
Purge to Wash
Tower
606
Saturetor Bottms
Circulation after
Purge
607
Saturator
Circulation Liquid after Make-up
608
Saturator
Circulation Liquid after Saturator
Heater
3,315
59,727
124
60.20
0.343
1.040
0.388
18.0
---
---
---
---
---
---
---
---
480
179
59,727
3,315
0.0
3,315.2
0.0
0.0
0.0
0.0
0.0
0.0
0.1
0.0
0.0
0.0
0.0
0.0
0.0
480
303
930,842
44,386
7.0
24,554.2
44,386
930,842
12,479
1.24
0.020
0.360
0.032
20.97
---
---
---
---
---
---
---
---
563.4
0.4
9,724.7
7,321.3
0.5
0.1
0.0
1,829.6
0.0
0.0
0.0
384.4
0.0
479
405
930,842
44,386
7.0
24,554.2
563.4
0.4
9,724.7
7,321.3
0.5
0.1
0.0
1,829.6
0.0
0.0
0.0
384.4
0.0
44,386
930,842
14,286
1.09
0.022
0.359
0.035
20.97
---
---
---
---
---
---
---
---
481
215
1,117,687
62,033
3.5
62,016.0
0.0
0.1
0.0
8.0
4.7
0.0
---
---
---
---
---
---
---
---
62,033
1,117,687
2,355
59.16
0.274
1.049
0.394
18.0
0.0
0.8
0.0
0.0
0.0
0.0
0.0
516
215
1,117,687
62,033
---
---
---
---
---
---
---
---
62,033
1,117,687
2,355
59.17
0.274
1.049
0.394
18.0
0.0
8.0
4.7
0.0
3.5
62,016.0
0.0
0.1
0.0
0.8
0.0
0.0
0.0
0.0
0.0
300
5,405
11
59.17
0.274
1.049
0.394
18.0
---
---
---
---
---
---
---
---
516
215
5,405
300
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
299.9
0.0
0.0
0.0
0.0
0.0
0.0
516
215
1,112,282
61,733
3.5
61,716.0
0.0
0.1
0.0
8.0
4.7
0.0
0.0
0.8
0.0
0.0
0.0
0.0
0.0
500
209
1,246,677
69,193
3.5
69,176.2
0.0
0.1
0.0
8.0
4.7
0.0
0.0
0.8
0.0
0.0
0.0
0.0
0.0
490
335
1,246,677
69,193
3.5
69,176.2
0.0
0.1
0.0
8.0
4.7
0.0
0.0
0.8
0.0
0.0
0.0
0.0
0.0
---
---
---
---
---
---
---
---
61,733
1,112,282
2,344
59.17
0.274
1.049
0.394
18.0
---
---
---
---
---
---
---
---
69,193
1,246,677
2,619
59.34
0.284
1.047
0.393
18.0
69,193
1,246,677
2,804
55.43
0.160
1.111
0.394
18.0
---
---
---
---
---
---
---
---
Material Balance SGT PRB + PETOCKE 50% H2S 16 Sep.xls Mat Bal Page 5 of 7
SYNGAS TREATING AREA
43F PRB + PETCOKE
Table 1
Component Balance
9/14/2006
Project No: 42127
Stream Number
Stream Description
Overall Properties
Pressure, psia
Temperature, °F
Mass Flow, lb/hr
Mole Flow, lbmole/hr
Component lb-moles/hr
NH3
N2
O2
NO2
SO2
AR
Sulfur
CH4
CO
CO2
COS
H2
H2O
H2S
HCN
Vapor Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, ACFM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
Liquid Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, USGPM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
610
Demin Water
Make-up to
Saturator (after heat exchange)
611
Demin Water
Make-up to
Saturator (before heat exchange)
701
Flashed Vapor from Wash
Tower Bottoms
Flash
702
Flashed Liquid from Wash
Tower Bottoms
Flash
703
Recovered Wash
Water from Flash
704
Cooled
Recovered Water from Flash
705
Recovered Wash
Water from Flash after Air Cooler
706
Vapors to Jet
Ejector
707
Steam to Jet
Ejector
500
158
134,395
7,460
7,460
134,395
276
60.79
0.400
1.036
0.383
18.0
---
---
---
---
---
---
---
---
0.0
7,460.1
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
500
100
134,395
7,460
7,460
134,395
269
62.35
0.680
1.030
0.363
18.0
---
---
---
---
---
---
---
---
0.0
7,460.1
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
7
177
14,128
782
---
---
---
---
---
---
---
---
782
14,128
12,649
0.02
0.009
0.450
0.013
18.07
0.2
0.1
0.0
0.0
0.0
0.0
0.0
0.8
776.7
1.5
0.3
0.0
1.7
0.4
0.0
7
177
132,603
7,361
0
0
0
0.02
0.009
0.450
0.013
18.07
7,361
132,603
275
60.19
0.350
1.041
0.387
18.0
0.0
7,360.5
0.0
0.0
0.0
0.0
0.0
0.0
0.1
0.0
0.0
0.0
0.0
0.0
0.0
62
177
132,603
7,361
7,361
132,603
275
60.20
0.349
1.041
0.387
18.0
---
---
---
---
---
---
---
---
0.0
7,360.5
0.0
0.0
0.0
0.0
0.0
0.0
0.1
0.0
0.0
0.0
0.0
0.0
0.0
62
118
132,603
7,361
7,361
132,603
267
61.81
0.565
1.032
0.370
18.0
---
---
---
---
---
---
---
---
0.0
7,360.5
0.0
0.0
0.0
0.0
0.0
0.0
0.1
0.0
0.0
0.0
0.0
0.0
0.0
772
13,904
28
60.91
0.426
1.036
0.381
18.0
10
224
158
0.02
0.011
0.355
0.016
22.29
7
150
14,128
782
0.2
0.1
0.0
0.0
0.0
0.0
0.0
0.8
776.7
1.5
0.3
0.0
1.7
0.4
0.0
7
150
224
10
10
224
158
0.02
0.011
0.355
0.016
22.29
---
---
---
---
---
---
---
---
0.0
1.7
0.4
0.0
0.8
5.4
1.5
0.1
0.0
0.1
0.0
0.0
0.0
0.0
0.0
615
491
500
28
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
27.8
0.0
0.0
0.0
0.0
0.0
0.0
---
---
---
---
---
---
---
---
28
500
6
1.29
0.018
0.580
0.029
18.02
Material Balance SGT PRB + PETOCKE 50% H2S 16 Sep.xls Mat Bal Page 6 of 7
SYNGAS TREATING AREA
43F PRB + PETCOKE
Table 1
Component Balance
Stream Number
Stream Description
Overall Properties
Pressure, psia
Temperature, °F
Mass Flow, lb/hr
Mole Flow, lbmole/hr
Component lb-moles/hr
NH3
N2
O2
NO2
SO2
AR
Sulfur
CH4
CO
CO2
COS
H2
H2O
H2S
HCN
Vapor Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, ACFM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
Liquid Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, USGPM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
708
Jet Ejector
Effluent Vapor to
SWS
709
Condensate
Recovered from
Vacuum Flash
710
Recovered
Condensate to
SWS
711
Solids from
Candle Filers
Recovered in
Wash Tower
712
Recovered Wash
Water to
Disposal
7
327
724
38
---
---
---
---
---
---
---
---
38
724
770
0.02
0.012
0.431
0.018
19.15
0.0
0.1
0.0
0.0
0.0
0.0
0.0
0.8
33.2
1.5
0.1
0.0
1.7
0.4
0.0
772
13,904
28
60.91
0.426
1.036
0.381
18.0
0
0
0
0.02
0.011
0.355
0.016
22.29
7
150
13,904
772
0.2
0.0
0.0
0.0
0.0
0.0
0.0
0.0
771.3
0.0
0.1
0.0
0.0
0.0
0.0
772
13,904
28
60.92
0.426
1.036
0.381
18.0
---
---
---
---
---
---
---
---
47
150
13,904
772
0.2
0.0
0.0
0.0
0.0
0.0
0.0
0.0
771.3
0.0
0.1
0.0
0.0
0.0
0.0
Approximately
110 lb/day of solids will be removed by the filters and sent to the coal pile.
7,361
132,603
267
61.81
0.565
1.032
0.370
18.0
---
---
---
---
---
---
---
---
62
118
132,603
7,361
0.0
7,360.5
0.0
0.0
0.0
0.0
0.0
0.0
0.1
0.0
0.0
0.0
0.0
0.0
0.0
Material Balance SGT PRB + PETOCKE 50% H2S 16 Sep.xls Mat Bal Page 7 of 7
9/14/2006
Project No: 42127
SYNGAS TREATING AREA
43F PRB CO2 CAPTURE CASE
Table 1
Component Balance
9/15/2006
Project No: 42127
Stream Number
Stream Description
Overall Properties
Pressure, psia
Temperature, °F
Mass Flow, lb/hr
Mole Flow, lbmole/hr
HCN
NH3
N2
O2
NO2
SO2
AR
Sulfur
Component lb-moles/hr
CH4
CO
CO2
COS
H2
H2O
H2S
Vapor Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, ACFM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
Liquid Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, USGPM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
100
Total Makeup
Demineralized
Water
101
Raw Syngas
102
Demin Water to
Wash Tower
103
Water to Wash
Tower
104
Wash Tower
Bottoms Stream
105
Wash Tower
Overhead Vapor
106
Preheated Wash
Tower Overhead
Vapor
201
IP Steam to Sour
Gas Shift
202
Sour Gas Shift
Feed to
Interchangers
HTX-101
203
Sour Gas Shift
Feed to
Preheater HTX-
120
---
---
---
---
---
---
---
---
60
100
246,266
13,670
0.0
13,670.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
540
450
901,381
42,540
8.3
25,486.7
1,133.3
5.5
11,393.3
1,757.7
71.5
2.0
1.9
2,267.1
0.0
0.0
0.0
412.3
0.0
42,540
901,381
12,940
1.16
0.023
0.347
0.039
21.19
13,670
246,266
493
62.30
0.684
1.031
0.363
18.0
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
530
100
104,848
5,820
0.0
5,820.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
---
---
---
---
---
---
---
---
31
139
204,243
11,337
0.1
11,337.1
0.0
0.0
0.0
0.0
0.0
0.0
0.1
0.0
0.0
0.0
0.0
0.0
0.0
---
---
---
---
---
---
---
---
531
281
172,687
9,583
1.2
9,577.9
0.3
0.1
0.0
2.1
1.2
0.0
0.4
0.2
0.0
0.0
0.0
0.0
0.0
530
261
932,937
44,293
8.3
25,484.5
1,132.2
5.5
11,392.2
3,516.9
71.2
1.9
1.6
2,266.9
0.0
0.0
0.0
412.3
0.0
44,293
932,937
10,740
1.45
0.020
0.352
0.033
21.06
529
359
932,937
44,293
8.3
25,484.5
1,132.2
5.5
11,392.2
3,516.9
71.2
1.9
1.6
2,266.9
0.0
0.0
0.0
412.3
0.0
44,293
932,937
12,298
1.26
0.021
0.351
0.036
21.06
599
488
450,378
25,000
0.0
25,000.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
529
417
1,849,109
94,586
8.3
25,496.2
1,540.8
5.5
11,437.0
53,316.8
76.5
1.9
17.7
2,272.9
0.0
0.0
0.0
412.3
0.0
528
496
1,849,109
94,586
8.3
25,496.2
1,540.8
5.5
11,437.0
53,316.8
76.5
1.9
17.7
2,272.9
0.0
0.0
0.0
412.3
0.0
25,000
450,378
5,999
1.25
0.018
0.577
0.029
18.02
94,586
1,849,109
26,333
1.17
0.018
0.442
0.030
19.55
94,586
1,849,109
29,278
1.05
0.019
0.438
0.032
19.55
5,820
104,848
210
62.35
0.680
1.030
0.363
18.0
11,337
204,243
416
61.25
0.468
1.034
0.377
18.0
9,583
172,687
376
57.19
0.198
1.076
0.397
18.0
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
Material Balance SGT PRB CO2 Capture 15 Sep TMA Mat Bal Page 1 of 9
SYNGAS TREATING AREA
43F PRB CO2 CAPTURE CASE
Table 1
Component Balance
9/15/2006
Project No: 42127
Stream Number
Stream Description
Overall Properties
Pressure, psia
Temperature, °F
Mass Flow, lb/hr
Mole Flow, lbmole/hr
HCN
NH3
N2
O2
NO2
SO2
AR
Sulfur
Component lb-moles/hr
CH4
CO
CO2
COS
H2
H2O
H2S
Vapor Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, ACFM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
Liquid Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, USGPM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
204
1st Stage Sour
Gas Shift Inlet
205
1st Stage Sour
Gas Shift Outlet
206
2nd Stage Sour
Gas Shift Inlet
207
2nd Stage Sour
Gas Shift Outlet to HTX-103
208
Shifted Syngas to Interchanger
HTX-101
209
Shifted Syngas to
Condensing
Train
301
Sour Syngas from Saturator
Heater
302
Sour Syngas from 1st Stage
Condenser
303
Sour Syngas from 2nd Stage
Condenser
304
Sour Syngas from 3rd Stage
Condenser
---
---
---
---
---
---
---
---
527
572
1,849,109
94,586
8.3
25,496.2
1,540.8
5.5
11,437.0
53,316.8
76.5
1.9
17.7
2,272.9
0.0
0.0
0.0
412.3
0.0
517
962
1,849,110
94,589
8.3
5,403.7
21,639.7
0.9
31,534.3
33,216.0
81.0
0.0
19.6
2,272.9
0.0
0.0
0.0
412.3
0.0
516
550
1,849,110
94,589
8.3
5,403.7
21,639.7
0.9
31,534.3
33,216.0
81.0
0.0
19.6
2,272.9
0.0
0.0
0.0
412.3
0.0
506
629
1,849,110
94,589
8.3
1,383.2
25,660.8
0.3
35,555.5
29,194.9
81.7
0.0
19.6
2,272.9
0.0
0.0
0.0
412.3
0.0
505
591
1,849,110
94,589
8.3
1,383.2
25,660.8
0.3
35,555.5
29,194.9
81.7
0.0
19.6
2,272.9
0.0
0.0
0.0
412.3
0.0
504
514
1,849,110
94,589
8.3
1,383.2
25,660.8
0.3
35,555.5
29,194.9
81.7
0.0
19.6
2,272.9
0.0
0.0
0.0
412.3
0.0
503
368
1,849,110
94,589
8.3
1,383.2
25,660.8
0.3
35,555.5
29,194.9
81.7
0.0
19.6
2,272.9
0.0
0.0
0.0
412.3
0.0
502
342
1,849,110
94,589
8.3
1,383.2
25,660.8
0.3
35,555.5
29,194.9
81.7
0.0
19.6
2,272.9
0.0
0.0
0.0
412.3
0.0
501
335
1,849,110
94,589
8.3
1,383.2
25,660.8
0.3
35,555.5
29,194.9
81.7
0.0
19.6
2,272.9
0.0
0.0
0.0
412.3
0.0
500
334
1,849,110
94,589
8.3
1,383.2
25,660.8
0.3
35,555.5
29,194.9
81.7
0.0
19.6
2,272.9
0.0
0.0
0.0
412.3
0.0
94,586
1,849,109
32,056
0.96
0.021
0.438
0.034
19.55
94,589
1,849,110
46,535
0.66
0.027
0.469
0.065
19.55
94,589
1,849,110
32,572
0.95
0.021
0.449
0.048
19.55
94,589
1,849,110
36,115
0.85
0.023
0.455
0.055
19.55
94,589
1,849,110
34,840
0.88
0.022
0.453
0.054
19.55
94,589
1,849,110
32,154
0.96
0.021
0.449
0.050
19.55
94,589
1,849,110
26,939
1.14
0.018
0.446
0.044
19.55
89,275
1,753,210
24,709
1.18
0.018
0.441
0.044
19.64
86,611
1,705,117
23,863
1.19
0.018
0.439
0.044
19.69
86,381
1,700,966
23,830
1.19
0.018
0.438
0.044
19.69
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
5,314
95,900
217
55.18
0.090
1.115
0.394
18.0
7,979
143,993
324
55.42
0.090
1.110
0.395
18.0
8,209
148,144
333
55.44
0.090
1.109
0.395
18.0
Material Balance SGT PRB CO2 Capture 15 Sep TMA Mat Bal Page 2 of 9
SYNGAS TREATING AREA
43F PRB CO2 CAPTURE CASE
Table 1
Component Balance
9/15/2006
Project No: 42127
Stream Number
Stream Description
Overall Properties
Pressure, psia
Temperature, °F
Mass Flow, lb/hr
Mole Flow, lbmole/hr
HCN
NH3
N2
O2
NO2
SO2
AR
Sulfur
Component lb-moles/hr
CH4
CO
CO2
COS
H2
H2O
H2S
Vapor Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, ACFM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
Liquid Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, USGPM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
305
Sour Syngas from 4th Stage
Condenser
306
Sour Syngas from 5th Stage
Condenser
307
Sour Syngas from 6th Stage
Condenser
308
Sour Syngas from 7th Stage
Condenser
309
Water from
Syngas Knockout
Drum
310
Sour Water
Stripper Feed
311
Syngas to
Interchanger
HTX-109
312
Syngas to
Mercury Removal
313
Syngas from
Mercury Removal
314
Syngas To Acid
Gas Removal
499
330
1,849,110
94,589
8.3
1,383.2
25,660.8
0.3
35,555.5
29,194.9
81.7
0.0
19.6
2,272.9
0.0
0.0
0.0
412.3
0.0
498
330
1,849,110
94,589
8.3
1,383.2
25,660.8
0.3
35,555.5
29,194.9
81.7
0.0
19.6
2,272.9
0.0
0.0
0.0
412.3
0.0
497
200
1,849,110
94,589
8.3
1,383.2
25,660.8
0.3
35,555.5
29,194.9
81.7
0.0
19.6
2,272.9
0.0
0.0
0.0
412.3
0.0
496
100
1,849,110
94,589
8.3
1,383.2
25,660.8
0.3
35,555.5
29,194.9
81.7
0.0
19.6
2,272.9
0.0
0.0
0.0
412.3
0.0
85,128
1,678,342
23,446
1.19
0.018
0.437
0.045
19.72
84,970
1,675,505
23,436
1.19
0.018
0.437
0.045
19.72
67,226
1,354,669
15,731
1.44
0.017
0.411
0.045
20.15
65,418
1,320,283
12,876
1.71
0.015
0.407
0.040
20.18
---
---
---
---
---
---
---
---
496
100
704,916
38,885
0.0
0.1
169.5
0.0
1.2
38,691.7
1.7
0.0
20.2
0.5
0.0
0.0
0.0
0.0
0.0
9,462
170,768
383
55.57
0.090
1.106
0.395
18.0
9,619
173,605
389
55.59
0.089
1.106
0.395
18.0
27,363
494,440
1,034
59.62
0.300
1.042
0.391
18.1
29,171
528,827
1,056
62.43
0.710
1.023
0.360
18.1
38,885
704,916
1,408
62.43
0.710
1.023
0.360
18.1
4,131
74,886
150
62.43
0.710
1.023
0.360
18.1
---
---
---
---
---
---
---
---
496
100
74,886
4,131
0.0
0.0
18.0
0.0
0.1
4,110.4
0.2
0.0
2.1
0.1
0.0
0.0
0.0
0.0
0.0
496
114
1,319,923
65,459
8.3
1,383.2
25,491.8
0.3
35,554.3
255.4
79.9
0.0
0.7
2,272.5
0.0
0.0
0.0
412.3
0.0
495
120
1,319,923
65,459
8.3
1,383.2
25,491.8
0.3
35,554.3
255.4
79.9
0.0
0.7
2,272.5
0.0
0.0
0.0
412.3
0.0
493
120
1,319,923
65,459
8.3
1,383.2
25,491.8
0.3
35,554.3
255.4
79.9
0.0
0.7
2,272.5
0.0
0.0
0.0
412.3
0.0
492
100
1,319,923
65,459
8.3
1,383.2
25,491.8
0.3
35,554.3
255.4
79.9
0.0
0.7
2,272.5
0.0
0.0
0.0
412.3
0.0
65,459
1,319,923
13,251
1.66
0.016
0.407
0.041
20.16
65,459
1,319,923
13,420
1.64
0.016
0.407
0.041
20.16
65,459
1,319,923
13,474
1.63
0.016
0.407
0.041
20.16
65,374
1,318,393
12,975
1.69
0.015
0.407
0.040
20.17
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
84
1,531
3
62.44
0.711
1.023
0.360
18.1
Material Balance SGT PRB CO2 Capture 15 Sep TMA Mat Bal Page 3 of 9
SYNGAS TREATING AREA
43F PRB CO2 CAPTURE CASE
Table 1
Component Balance
9/15/2006
Project No: 42127
Stream Number
Stream Description
Overall Properties
Pressure, psia
Temperature, °F
Mass Flow, lb/hr
Mole Flow, lbmole/hr
HCN
NH3
N2
O2
NO2
SO2
AR
Sulfur
Component lb-moles/hr
CH4
CO
CO2
COS
H2
H2O
H2S
Vapor Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, ACFM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
Liquid Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, USGPM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
315
Recycle Water
Pump Suction
316
Recycle Water to
Interchanger
HTX-012
317
Recycle Water to
1st Stage
Condenser
318
Recycle Water to
Shift Outlet
Interchanger
HTX-102
319
Recycle Water to
Steam Generator
HTX-114
320
Recycle Water to
Flash Drum
321
Flash Steam to
Sour Shift
Reactors
322
Water Flash
Drum Purge
323
Recycle TGTU
Tail Gas
400
Sweet Syngas from AGR
---
---
---
---
---
---
---
---
496
100
630,030
34,754
0.0
0.1
151.5
0.0
1.1
34,581.3
1.6
0.0
18.1
0.4
0.0
0.0
0.0
0.0
0.0
---
---
---
---
---
---
---
---
536
100
630,010
34,754
0.0
0.1
150.6
0.0
1.1
34,584.8
1.6
0.0
15.4
0.4
0.0
0.0
0.0
0.0
0.0
34,754
630,030
1,258
62.43
0.710
1.023
0.360
18.1
34,754
630,010
1,258
62.43
0.710
1.023
0.360
18.1
---
---
---
---
---
---
---
---
535
198
630,010
34,754
0.0
0.1
150.6
0.0
1.1
34,584.8
1.6
0.0
15.4
0.4
0.0
0.0
0.0
0.0
0.0
39
1,372
10
2.37
0.019
0.300
0.019
35.58
534
351
630,010
34,754
0.0
0.1
150.6
0.0
1.1
34,584.8
1.6
0.0
15.4
0.4
0.0
0.0
0.0
0.0
0.0
533
474
630,010
34,754
0.0
0.1
150.6
0.0
1.1
34,584.8
1.6
0.0
15.4
0.4
0.0
0.0
0.0
0.0
0.0
19,008
346,319
5,134
1.12
0.014
0.557
0.025
18.22
532
474
630,010
34,754
0.0
0.1
150.6
0.0
1.1
34,584.8
1.6
0.0
15.4
0.4
0.0
0.0
0.0
0.0
0.0
25,000
454,280
6,765
1.12
0.014
0.558
0.025
18.17
532
474
454,280
25,000
0.0
0.1
150.2
0.0
1.1
24,832.6
1.5
0.0
14.1
0.4
0.0
0.0
0.0
0.0
0.0
25,000
454,280
6,765
1.12
0.014
0.558
0.025
18.17
0
0
0
1.12
0.014
0.558
0.025
18.17
532
474
175,730
9,754
0.0
9,752.2
0.0
0.0
0.0
0.0
0.4
0.0
1.3
0.0
0.0
0.0
0.0
0.0
0.0
---
---
---
---
---
---
---
---
531
151
175,730
9,754
0.0
9,752.2
0.0
0.0
0.0
0.0
0.4
0.0
1.3
0.0
0.0
0.0
0.0
0.0
0.0
482
131
272,797
41,973
8.2
1,376.2
1,019.7
0.1
35,461.8
229.8
0.0
0.0
0.0
3,442.6
24.0
0.0
0.0
410.5
0.0
41,973
272,797
9,283
0.49
0.011
1.071
0.080
6.50
34,754
630,010
1,315
59.74
0.305
1.038
0.389
18.1
34,715
628,638
1,428
54.89
0.090
1.120
0.391
18.1
15,746
283,691
708
49.97
0.109
1.295
0.359
18.0
9,754
175,730
438
49.97
0.109
1.295
0.359
18.0
---
---
---
---
---
---
---
---
9,754
175,730
438
49.97
0.109
1.295
0.359
18.0
9,754
175,730
359
60.98
0.423
1.034
0.381
18.0
---
---
---
---
---
---
---
---
Material Balance SGT PRB CO2 Capture 15 Sep TMA Mat Bal Page 4 of 9
SYNGAS TREATING AREA
43F PRB CO2 CAPTURE CASE
Table 1
Component Balance
9/15/2006
Project No: 42127
Stream Number
Stream Description
401
Syngas to 2nd
Stage Condenser
402
Syngas to
Coal/Coke Drying
403
Syngas to
Saturator
404
AGR Acid Gas to
Sulfur Recovery
405
Recycle TGTU
Tail Gas
406
LP CO2 to
Compressor
407
MP CO2 to
Compressor
413
Compressed
CO2 to Pipeline
414
Oxygen to SRU
416
TGTU Sour
Water Purge
Overall Properties
Pressure, psia
Temperature, °F
Mass Flow, lb/hr
Mole Flow, lbmole/hr
HCN
NH3
N2
O2
NO2
SO2
AR
Sulfur
Component lb-moles/hr
CH4
CO
CO2
COS
H2
H2O
H2S
Vapor Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, ACFM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
Liquid Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, USGPM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
---
---
---
---
---
---
---
---
482
131
254,794
39,203
7.7
1,285.4
952.4
0.1
33,121.5
214.7
0.0
0.0
0.0
3,215.4
22.4
0.0
0.0
383.4
0.0
39,203
254,794
8,670
0.49
0.011
1.071
0.080
6.50
---
---
---
---
---
---
---
---
481
305
254,794
39,203
7.7
1,285.4
952.4
0.1
33,121.5
214.7
0.0
0.0
0.0
3,215.4
22.4
0.0
0.0
383.4
0.0
39,203
254,794
11,259
0.38
0.013
1.078
0.097
6.50
---
---
---
---
---
---
---
---
2,770
18,003
613
0.49
0.011
1.071
0.080
6.50
482
131
18,003
2,770
0.5
90.8
67.3
0.0
2,340.3
15.2
0.0
0.0
0.0
227.2
1.6
0.0
0.0
27.1
0.0
25
457
0.9
63.21
1.183
1.026
0.337
18.1
301
12,434
353
0.59
0.013
0.221
0.009
41.26
75
50
12,891
327
0.7
0.6
0.0
0.0
0.0
0.0
0.0
0.0
0.0
220.2
0.0
0.0
25.5
79.5
0.0
---
---
---
---
---
---
---
---
292
10,667
69
2.57
0.023
0.276
0.024
36.48
556
303
10,667
292
0.0
5.5
0.0
0.0
0.0
0.0
0.0
0.0
11.6
225.8
0.0
43.5
2.6
3.4
0.0
17.7
41
352,422
8,038
0.0
2.3
8,003.1
0.1
30.5
0.0
0.1
0.0
0.0
1.7
0.0
0.0
0.0
0.6
0.0
8,038
352,422
40,368
0.15
0.014
0.207
0.009
43.84
75
50
715,524
16,321
0.0
4.6
16,248.7
0.1
61.9
0.0
0.3
0.0
0.0
3.5
0.0
0.0
0.0
1.2
0.0
2000
294
1,067,947
24,359
0.1
6.9
24,251.8
0.2
92.4
0.0
0.4
0.0
0.0
5.3
0.0
0.0
0.0
1.9
0.0
16,321
715,524
19,174
0.62
0.014
0.213
0.009
43.84
24,359
1,067,947
1,329
13.39
0.028
0.340
0.022
43.84
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
100
100
1,602
49
0.0
0.0
46.6
2.5
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
---
---
---
---
---
---
---
---
49
1,602
49
0.55
0.021
0.220
0.015
32.70
66
104
576
32
32
576
1.2
62.19
0.651
1.030
0.365
18.0
---
---
---
---
---
---
---
---
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
32.0
0.0
0.0
0.0
0.0
0.0
0.0
Material Balance SGT PRB CO2 Capture 15 Sep TMA Mat Bal Page 5 of 9
SYNGAS TREATING AREA
43F PRB CO2 CAPTURE CASE
Table 1
Component Balance
9/15/2006
Project No: 42127
Stream Number
Stream Description
Overall Properties
Pressure, psia
Temperature, °F
Mass Flow, lb/hr
Mole Flow, lbmole/hr
HCN
NH3
N2
O2
NO2
SO2
AR
Sulfur
Component lb-moles/hr
CH4
CO
CO2
COS
H2
H2O
H2S
Vapor Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, ACFM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
Liquid Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, USGPM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
417
Molten Sulfur
501
Heated Sour
Water Stripper
Feed
502
Sour Water
Stripper Gas to
SRU
503
Stripper Bottoms to Feed/Effluent
Exchanger
504
Cooled Stripper
Bottoms to
Syngas Wash
Tower
505
Stripper
Pumparound to
Cooler
506
Stripper
Pumparound
Return
601
Syngas Saturator
Overhead Vapor
602
Diluted Syngas to
Combustion
Turbines
603
Saturator
Bottoms Stream
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
100
260
2,405
75
0.0
0.0
0.0
0.0
0.0
0.0
75.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
4,131
74,886
156
59.66
0.299
1.039
0.389
18.1
0
0
0
2.74
0.020
0.276
0.020
36.45
496
200
74,886
4,131
0.0
0.0
18.0
0.0
0.1
4,110.4
0.2
0.0
2.1
0.1
0.0
0.0
0.0
0.0
0.0
30
185
1,152
36
36
1,152
136
0.14
0.014
0.277
0.015
32.25
---
---
---
---
---
---
---
---
0.0
2.1
19.2
0.0
1.3
10.0
0.4
0.1
2.3
0.2
0.0
0.0
0.0
0.0
0.0
---
---
---
---
---
---
---
---
31
252
94,151
5,226
0.0
5,226.1
0.0
0.0
0.0
0.0
0.0
0.0
0.1
0.0
0.0
0.0
0.0
0.0
0.0
5,226
94,151
202
57.98
0.225
1.065
0.397
18.0
31
174
94,151
5,226
---
---
---
---
---
---
---
---
0.0
5,226.1
0.0
0.0
0.0
0.0
0.0
0.0
0.1
0.0
0.0
0.0
0.0
0.0
0.0
5,226
94,151
195
60.27
0.356
1.040
0.387
18.0
30
233
81,284
4,515
---
---
---
---
---
---
---
---
4,515
81,284
175
58.06
0.227
1.061
0.393
18.0
0.0
4,454.0
0.0
0.4
0.0
0.0
0.2
0.0
60.2
0.0
0.0
0.0
0.0
0.0
0.0
25
182
81,284
4,515
---
---
---
---
---
---
---
---
4,515
81,284
170
59.57
0.343
1.045
0.386
18.0
0.0
4,454.0
0.0
0.4
0.0
0.0
0.2
0.0
60.2
0.0
0.0
0.0
0.0
0.0
0.0
480
306
390,691
46,747
7.7
1,284.8
952.4
0.1
33,122.1
7,759.2
0.0
0.0
0.0
3,215.4
22.4
0.0
0.0
383.4
0.0
46,747
390,691
13,284
0.49
0.013
0.877
0.078
8.36
---
---
---
---
---
---
---
---
479
405
627,987
55,194
7.7
1,284.8
952.4
0.1
33,122.1
7,759.2
0.0
0.0
0.0
11,493.4
191.4
0.0
0.0
383.4
0.0
481
242
1,199,289
66,573
15.9
66,548.0
0.0
0.0
0.0
0.5
7.5
0.0
0.0
1.5
0.0
0.0
0.0
0.0
0.0
55,194
627,987
17,847
0.59
0.016
0.646
0.070
11.38
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
---
66,573
1,199,289
2,562
58.35
0.237
1.059
0.396
18.0
Material Balance SGT PRB CO2 Capture 15 Sep TMA Mat Bal Page 6 of 9
SYNGAS TREATING AREA
43F PRB CO2 CAPTURE CASE
Table 1
Component Balance
9/15/2006
Project No: 42127
Stream Number
Stream Description
Overall Properties
Pressure, psia
Temperature, °F
Mass Flow, lb/hr
Mole Flow, lbmole/hr
HCN
NH3
N2
O2
NO2
SO2
AR
Sulfur
Component lb-moles/hr
CH4
CO
CO2
COS
H2
H2O
H2S
Vapor Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, ACFM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
Liquid Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, USGPM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
604
Saturator Btms
Pump Discharge
605
Saturator Purge to Syngas Wash
Tower
606
Saturator
Recirculation
Water
607
Saturator
Recirc/Makeup to
Heater HTX-104
608
Hot Recirculation
Water to Top of
Saturator
609
Heated Saturator
Makeup Water
610
Saturator
Makeup Water to
4th Stage
Condenser
611
Saturator
Makeup Water to
HTX-012
613
Nitrogen to AGR and Syngas
Dilution
614
Nitrogen to AGR
---
---
---
---
---
---
---
---
540
242
1,199,289
66,573
15.9
66,548.0
0.0
0.0
0.0
0.5
7.5
0.0
0.0
1.5
0.0
0.0
0.0
0.0
0.0
66,573
1,199,289
2,562
58.36
0.237
1.059
0.396
18.0
540
242
5,404
300
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.1
299.9
0.0
0.0
0.0
0.0
0.0
0.0
540
242
1,193,885
66,273
15.8
66,248.1
0.0
0.0
0.0
0.5
7.5
0.0
0.0
1.4
0.0
0.0
0.0
0.0
0.0
529
250
1,335,304
74,123
15.8
74,098.1
0.0
0.0
0.0
0.5
7.5
0.0
0.0
1.4
0.0
0.0
0.0
0.0
0.0
528
334
1,335,304
74,123
15.8
74,098.1
0.0
0.0
0.0
0.5
7.5
0.0
0.0
1.4
0.0
0.0
0.0
0.0
0.0
---
---
---
---
---
---
---
---
300
5,404
12
58.36
0.237
1.059
0.396
18.0
---
---
---
---
---
---
---
---
66,273
1,193,885
2,550
58.36
0.237
1.059
0.396
18.0
---
---
---
---
---
---
---
---
74,123
1,335,304
2,864
58.13
0.228
1.062
0.397
18.0
---
---
---
---
---
---
---
---
74,123
1,335,304
3,001
55.48
0.161
1.110
0.394
18.0
528
334
1,335,304
74,123
---
---
---
---
---
---
---
---
15.8
74,098.1
0.0
0.0
0.0
0.5
7.5
0.0
74,123
1,335,304
3,001
55.48
0.161
1.110
0.394
18.0
0.0
1.4
0.0
0.0
0.0
0.0
0.0
530
162
141,419
7,850
---
---
---
---
---
---
---
---
291
0.0
7,850.0
0.0
0.0
0.0
0.0
0.0
0.0
7,850
141,419
60.69
0.389
1.036
0.384
18.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
530
100
141,419
7,850
---
---
---
---
---
---
---
---
283
18.0
0.0
7,850.0
0.0
0.0
0.0
0.0
0.0
0.0
7,850
141,419
62.35
0.680
1.030
0.363
0.0
0.0
0.0
0.0
0.0
0.0
0.0
500
237
271,008
9,647
2,416
1.87
0.023
0.260
0.019
28.09
---
---
---
---
---
---
---
---
0.0
9,454.0
192.9
0.0
0.0
0.0
0.0
9,647
271,008
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
---
---
---
---
---
---
---
---
1,200
33,711
301
1.87
0.023
0.260
0.019
28.09
500
237
33,711
1,200
0.0
1,176.0
24.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
Material Balance SGT PRB CO2 Capture 15 Sep TMA Mat Bal Page 7 of 9
SYNGAS TREATING AREA
43F PRB CO2 CAPTURE CASE
Table 1
Component Balance
9/15/2006
Project No: 42127
Stream Number
Stream Description
Overall Properties
Pressure, psia
Temperature, °F
Mass Flow, lb/hr
Mole Flow, lbmole/hr
HCN
NH3
N2
O2
NO2
SO2
AR
Sulfur
Component lb-moles/hr
CH4
CO
CO2
COS
H2
H2O
H2S
Vapor Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, ACFM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
Liquid Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, USGPM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
615
Dilution Nitrogen to 3rd Stage
Condenser
616
Hot Dilution
Nitrogen
701
Flash Vapor from
Wash Tower
Bottoms Flash
702
Flash Liquid from
Wash Tower
Bottoms Flash
703
Recovered Wash
Water from Flash
704
Cooled
Recovered Water from Flash
705
Cooled Flash
Vapor
706
Vapors to Jet
Ejector
707
Steam to Jet
Ejector
708
Jet Ejector
Effluent Vapor to
Sour Water
Stripper
500
237
237,297
8,447
---
---
---
---
---
---
---
---
8,447
237,297
2,115
1.87
0.023
0.260
0.019
28.09
0.0
8,278.0
168.9
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
499
306
237,297
8,447
---
---
---
---
---
---
---
---
8,447
237,297
2,337
1.69
0.024
0.260
0.020
28.09
0.0
8,278.0
168.9
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
7
177
19,341
1,071
---
---
---
---
---
---
---
---
1,071
19,341
17,337
0.02
0.009
0.451
0.013
18.05
1.2
1,066.0
0.3
0.1
0.0
2.1
1.2
0.0
0.3
0.2
0.0
0.0
0.0
0.0
0.0
7
177
153,346
8,512
8,512
153,346
318
60.19
0.349
1.041
0.387
18.0
0
0
0
0.02
0.009
0.451
0.013
18.05
0.0
8,511.9
0.0
0.0
0.0
0.0
0.0
0.0
0.1
0.0
0.0
0.0
0.0
0.0
0.0
62
177
153,346
8,512
8,512
153,346
318
60.19
0.349
1.041
0.387
18.0
---
---
---
---
---
---
---
---
0.0
8,511.9
0.0
0.0
0.0
0.0
0.0
0.0
0.1
0.0
0.0
0.0
0.0
0.0
0.0
57
120
153,346
8,512
8,512
153,346
310
61.75
0.555
1.032
0.371
18.0
---
---
---
---
---
---
---
---
0.0
8,511.9
0.0
0.0
0.0
0.0
0.0
0.0
0.1
0.0
0.0
0.0
0.0
0.0
0.0
7
150
19,341
1,071
1,061
19,110
39
60.92
0.426
1.036
0.381
18.0
11
231
164
0.02
0.012
0.362
0.018
21.78
1.2
1,066.0
0.3
0.1
0.0
2.1
1.2
0.0
0.3
0.2
0.0
0.0
0.0
0.0
0.0
7
150
231
11
11
231
164
0.02
0.012
0.362
0.018
21.78
---
---
---
---
---
---
---
---
0.0
2.1
1.2
0.0
1.2
5.6
0.2
0.0
0.0
0.2
0.0
0.0
0.0
0.0
0.0
615
491
500
28
28
500
6
1.29
0.018
0.580
0.029
18.02
---
---
---
---
---
---
---
---
0.0
0.0
0.0
0.0
0.0
27.8
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
7
325
731
38
0.0
0.2
0.0
0.0
0.0
0.0
0.0
1.2
33.4
0.2
0.0
0.0
2.1
1.2
0.0
---
---
---
---
---
---
---
---
38
731
767
0.02
0.012
0.433
0.019
19.06
Material Balance SGT PRB CO2 Capture 15 Sep TMA Mat Bal Page 8 of 9
SYNGAS TREATING AREA
43F PRB CO2 CAPTURE CASE
Table 1
Component Balance
Stream Number
Stream Description
Overall Properties
Pressure, psia
Temperature, °F
Mass Flow, lb/hr
Mole Flow, lbmole/hr
HCN
NH3
N2
O2
NO2
SO2
AR
Sulfur
Component lb-moles/hr
CH4
CO
CO2
COS
H2
H2O
H2S
Vapor Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, ACFM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
Liquid Phase Properties
Mole Flow, lbmole/hr
Mass Flow, lb/hr
Actual Volumetric Flow, USGPM
Density, lb/ft3
Viscosity, cP
Heat Capacity, Btu/lb-F
Thermal Conductivity, Btu/hr-ft-F
Molecular Weight
709
Vacuum Flash
Condensate
710
Vacuum Flash
Condensate to
Sour Water
Stripper
711
Particulate Solids
Removed from
Wash Tower
Bottoms
712
Recovered Wash
Water
1,061
19,110
39
60.92
0.426
1.036
0.381
18.0
0
0
0
0.02
0.012
0.362
0.018
21.78
7
150
19,110
1,061
0.0
1,060.4
0.0
0.1
0.0
0.0
0.0
0.0
0.3
0.0
0.0
0.0
0.0
0.0
0.0
1,061
19,110
39
60.93
0.426
1.036
0.381
18.0
---
---
---
---
---
---
---
---
47
150
19,110
1,061
0.0
1,060.4
0.0
0.1
0.0
0.0
0.0
0.0
0.3
0.0
0.0
0.0
0.0
0.0
0.0
Approximately
110 lb/day is removed from the Wash Tower
Bottoms stream.
---
---
---
---
---
---
---
---
1,061
19,110
39
60.93
0.426
1.036
0.381
18.0
1,061
19,110
39
60.93
0.426
1.036
0.381
18.0
---
---
---
---
---
---
---
---
47
150
19,110
1,061
0.0
1,060.4
0.0
0.1
0.0
0.0
0.0
0.0
0.3
0.0
0.0
0.0
0.0
0.0
0.0
Material Balance SGT PRB CO2 Capture 15 Sep TMA Mat Bal Page 9 of 9
9/15/2006
Project No: 42127
B
SITE LAYOUT DRAWINGS
B-1
CURRENT
FUTURE
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
KEY NOTES:
1
26
CONTROL ROOM/ADMIN. BLDG.
2
3
GAS TURBINE
HEAT RECOVERY STEAM GENERATOR
4
5
STEAM TURBINE
COOLING TOWER
6 GASIFICATION
7
8
AIR SEPARATION PLANT
ACID GAS SEPARATION
10
11
12
13
9 GAS CLEANUP
SULFUR PRODUCTION
SLAG HANDLING
WASTE WATER TREATMENT
14
15
16
17
WATER TREATMENT
WAREHOUSE
SULFUR LOAD-OUT SIDING
ROTARY DUMPER
COAL STOCKOUT
18
19
COAL CONVEYOR
COAL PILE (60 DAYS)
20 COAL GRINDING AND DRYING
21 YARD MAINTENANCE BLDG.
22 PLANT PARKING
23 SWITCHYARD
24 CONSTRUCTION OFFICES
25 CONSTRUCTION PARKING
26 SLAG & FINES LANDFILL
27 WASTE WATER POND
28 GAS METERING STATION
29 ACCESS SPUR
30 LOOP TRACK
31 FLARE
32 AUXILIARY BOILER
33 TAIL GAS TREATMENT UNIT
34 WATER STORAGE POND (30 DAYS)
35 SULFUR LOADOUT
300’ 0’ 300’
SCALE IN FEET
600’
26
12
27
34
13
29
15
33
35
11
8
9
10
7
20
6
6
32
21
18
3
4
5
17
1
2
14
22
23
24
25
28
31
19
294.75’
16
30
PROPERTY LINE no.
date by ckd description date
JUNE 12, 2006 designed
R. SEDLACEK detailed
R. SEDLACEK checked
K
L
550MW (NET) 2X1 IGCC UNIT 1 OF 3
OPTION 1 - 100% PRB project
42127 drawing
SK-CS1 contract sheet file of rev.
sheets
M
I
J
G
H
E
F
C
D
A
B
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
CURRENT
FUTURE
KEY NOTES:
1
26
CONTROL ROOM/ADMIN. BLDG.
2 GAS TURBINE
3 HEAT RECOVERY STEAM GENERATOR
4 STEAM TURBINE
5 COOLING TOWER
6 GASIFICATION
7 AIR SEPARATION PLANT
8 ACID GAS SEPARATION
9 GAS CLEANUP
10
11
SULFUR PRODUCTION
SLAG HANDLING
WASTE WATER TREATMENT 12
13
14
15
WATER TREATMENT
WAREHOUSE
SULFUR LOAD-OUT SIDING
ROTARY DUMPER 16
17
18
19
COAL STOCKOUT
COAL CONVEYORS
COAL PILE (60 DAYS)
20 COAL GRINDING AND DRYING
21 YARD MAINTENANCE BLDG.
22 PLANT PARKING
23 SWITCHYARD
24 CONSTRUCTION OFFICES
25 CONSTRUCTION PARKING
26 SLAG & FINES LANDFILL
27 WASTE WATER POND
28 GAS METERING STATION
29 ACCESS SPUR
30 LOOP TRACK
31 FLARE
32 AUXILIARY BOILER
33 TAIL GAS TREATMENT UNIT
34 WATER STORAGE POND (30 DAYS)
35 SULFUR LOADOUT
36 PET COKE PILE (30 DAYS)
300’ 0’ 300’
SCALE IN FEET
600’
26
12
27
34
13
29
15
33
35
11
8
9
10
7
20
6
6
32
21
18
3
4
5
17
1
2
14
22
23
24
25
28
31
36
19
294.75’
16
30
PROPERTY LINE no.
date by ckd description date
JUNE 12, 2006 designed
R. SEDLACEK detailed
R. SEDLACEK checked
K
L
550MW (NET) 2X1 IGCC UNIT 1 OF 3
OPTION 2 - 50% PRB/50% PET COKE project
42127 drawing
SK-CS2 contract sheet file of rev.
sheets
M
I
J
G
H
E
F
C
D
A
B
C
WATER MASS BALANCE DIAGRAMS
C-1
no. | date | by | chd | description
A | 6/23/06 | mab | |
B | 6/29/06 | mab | bdh |
Initial Issue
Revise Raw H
2
O
Raw Water
Influent
4,391
(2,194,622)
A
AJ
Potable
Water
Treatment
AK
On-site Septic
System
3
(1,499)
3
(1,499)
Cartridge
Filtration
B
9
(4,498)
4,379
(2,188,624)
C
D
90
(44,982)
Service
Water
Storage
E
16
(7,997)
Coal
Storage
Area
F
16
(7,997)
4,289
(2,143,642)
K
3,597
(1,797,781)
N
74
(36,985)
G
I
Sour Water
Condensate Recycle
54
(26,989)
H
20
(9,996)
Slag Quench
(Non-recoverable)
AF
Syngas
Treatment
L
692
(345,862)
M
Demineralizer
System
(RO/EDI)
Non-recoverable
Losses
199
(99,460)
8
(3,998)
AE
44
(21,991)
O
234
(116,953)
AA
Demineralized
Water
Storage
493
(246,401)
38
(18,992)
P
Oil/Water
Separator
Syngas Saturation
(Non-Recoverable)
188
(93,962)
AC
33
(16,493)
7
(3,499)
R
J
20
(9,996)
Syngas Burner
(Non-Recoverable)
AG
Non-recoverable
Losses
278
(138,944)
AB
3,796
(1,897,241)
S
Gasifier Units
AI
Condenser
Q
HRSG Units
20
(9,996)
18
(8,996)
AD
12
(5,998)
11
(5,498)
T
Process
Wastewater
Storage
U
3,808
(1,903,238)
AH
4,097
(2,047,681)
Evaporation &
Drift
Cooling
Tower
V
3,135
(1,566,873)
NOTES:
1. FLOWS ARE SHOWN IN GALLONS PER MIN
ROUNDED TO THE NEAREST GALLON.
2. FLOWS ARE BASED ON AVERAGE DAILY
CONDITIONS.
3. FLOWS IN PARENTHESIS SHOWN IN POUNDS
PER HOUR ROUNDED TO THE NEAREST
POUND.
W
36
(17,993)
962
(480,808)
X date
6/29/2006 designed
M. Boyd detailed
M. Boyd checked
B. Hansen
Y
998
(498,800)
1,007
(503,299)
Z
Wastewater
Discharge to
Outfall
PRELIMINARY
550 MW (net) IGCC
Gulf Coast, Texas
Water Balance Diagram
100% PRB @ 43 F Ambient Dry
Bulb Temp. & 40 F Ambient Wet Bulb Temp.
project
42127 drawing
WMB-1.1
contract
---
rev.
B sheet file
1 of 2 sheets
42127 CPS IGCC WMB Rev B.xls
no. | date | by | chd | description
A | 6/23/06 | mab | |
B | 6/29/06 | mab | bdh |
Initial Issue
Revise Raw H
2
O
Raw Water
Influent
4,983
(2,490,503)
A
AJ
Potable
Water
Treatment
AK
On-site Septic
System
3
(1,499)
3
(1,499)
Cartridge
Filtration
B
11
(5,498)
4,969
(2,483,506)
C
D
90
(44,982)
Service
Water
Storage
E
16
(7,997)
Coal
Storage
Area
F
16
(7,997)
4,879
(2,438,524)
K
4,208
(2,103,158)
N
74
(36,985)
G
I
Sour Water
Condensate Recycle
54
(26,989)
H
20
(9,996)
Slag Quench
(Non-recoverable)
AF
Syngas
Treatment
L
671
(335,366)
M
Demineralizer
System
(RO/EDI)
Non-recoverable
Losses
193
(96,461)
7
(3,499)
AE
44
(21,991)
O
234
(116,953)
AA
Demineralized
Water
Storage
478
(238,904)
36
(17,993)
P
Oil/Water
Separator
Syngas Saturation
(Non-Recoverable)
177
(88,465)
AC
31
(15,494)
7
(3,499)
R
J
20
(9,996)
Syngas Burner
(Non-Recoverable)
AG
Non-recoverable
Losses
278
(138,944)
AB
4,401
(2,199,620)
S
Gasifier Units
AI
Condenser
Q
HRSG Units
18
(8,996)
18
(8,996)
AD
11
(5,498)
11
(5,498)
T
Process
Wastewater
Storage
U
4,412
(2,205,118)
AH
4,701
(2,349,560)
Evaporation &
Drift
Cooling
Tower
V
3,595
(1,796,781)
NOTES:
1. FLOWS ARE SHOWN IN GALLONS PER MIN
ROUNDED TO THE NEAREST GALLON.
2. FLOWS ARE BASED ON AVERAGE DAILY
CONDITIONS.
3. FLOWS IN PARENTHESIS SHOWN IN POUNDS
PER HOUR ROUNDED TO THE NEAREST
POUND.
W
36
(17,993)
1,106
(552,779)
X date
6/29/2006 designed
M. Boyd detailed
M. Boyd checked
B. Hansen
Y
1,142
(570,772)
1,153
(576,269)
Z
Wastewater
Discharge to
Outfall
PRELIMINARY
550 MW (net) IGCC
Gulf Coast, Texas
Water Balance Diagram
100 % PRB @ 73 F Ambient Dry
Bulb Temp. & 69 F Ambient Wet Bulb Temp.
project
42127 drawing
WMB-1.2
contract
---
rev.
B sheet file
1 of 2 sheets
42127 CPS IGCC WMB Rev B.xls
no. | date | by | chd | description
A | 6/23/06 | mab | |
B | 6/29/06 | mab | bdh |
Initial Issue
Revise Raw H
2
O
Raw Water
Influent
5,580
(2,788,884)
A
AJ
Potable
Water
Treatment
AK
On-site Septic
System
3
(1,499)
3
(1,499)
Cartridge
Filtration
B
12
(5,998)
5,565
(2,781,387)
C
D
90
(44,982)
Service
Water
Storage
E
16
(7,997)
Coal
Storage
Area
F
16
(7,997)
5,475
(2,736,405)
K
4,814
(2,406,037)
N
74
(36,985)
G
I
Sour Water
Condensate Recycle
54
(26,989)
H
20
(9,996)
Slag Quench
(Non-recoverable)
AF
Syngas
Treatment
L
661
(330,368)
M
Demineralizer
System
(RO/EDI)
Non-recoverable
Losses
190
(94,962)
7
(3,499)
AE
44
(21,991)
O
234
(116,953)
AA
Demineralized
Water
Storage
471
(235,406)
36
(17,993)
P
Oil/Water
Separator
Syngas Saturation
(Non-Recoverable)
171
(85,466)
AC
30
(14,994)
7
(3,499)
R
J
20
(9,996)
Syngas Burner
(Non-Recoverable)
AG
Non-recoverable
Losses
278
(138,944)
AB
5,004
(2,500,999)
S
Gasifier Units
AI
Condenser
Q
HRSG Units
18
(8,996)
18
(8,996)
AD
11
(5,498)
11
(5,498)
T
Process
Wastewater
Storage
U
5,015
(2,506,497)
AH
5,304
(2,650,939)
Evaporation &
Drift
Cooling
Tower
V
4,055
(2,026,689)
NOTES:
1. FLOWS ARE SHOWN IN GALLONS PER MIN
ROUNDED TO THE NEAREST GALLON.
2. FLOWS ARE BASED ON AVERAGE DAILY
CONDITIONS.
3. FLOWS IN PARENTHESIS SHOWN IN POUNDS
PER HOUR ROUNDED TO THE NEAREST
POUND.
W
36
(17,993)
1,249
(624,250)
X date
6/29/2006 designed
M. Boyd detailed
M. Boyd checked
B. Hansen
Y
1,285
(642,243)
1,297
(648,241)
Z
Wastewater
Discharge to
Outfall
PRELIMINARY
550 MW (net) IGCC
Gulf Coast, Texas
Water Balance Diagram
100% PRB @ 93 Ambient Dry
Bulb Temp. & 77 F Ambient Wet Bulb Temp.
project
42127 drawing
WMB-1.3
contract
---
rev.
B sheet file
1 of 2 sheets
42127 CPS IGCC WMB Rev B.xls
no. | date | by | chd | description
A | 6/23/06 | mab | |
B | 6/29/06 | mab | bdh |
Initial Issue
Revise Raw H
2
O
Raw Water
Influent
4,619
(2,308,576)
A
AJ
Potable
Water
Treatment
AK
On-site Septic
System
3
(1,499)
3
(1,499)
Cartridge
Filtration
B
10
(4,998)
4,606
(2,302,079)
C
D
90
(44,982)
Service
Water
Storage
E
16
(7,997)
Coal
Storage
Area
F
16
(7,997)
4,516
(2,257,097)
K
3,689
(1,843,762)
N
74
(36,985)
G
I
Sour Water
Condensate Recycle
54
(26,989)
H
20
(9,996)
Slag Quench
(Non-recoverable)
AF
Syngas
Treatment
L
827
(413,335)
M
Demineralizer
System
(RO/EDI)
Non-recoverable
Losses
238
(118,952)
8
(3,998)
AE
44
(21,991)
O
234
(116,953)
AA
Demineralized
Water
Storage
589
(294,382)
38
(18,992)
P
Oil/Water
Separator
Syngas Saturation
(Non-Recoverable)
231
(115,454)
AC
86
(42,983)
7
(3,499)
R
J
20
(9,996)
Syngas Burner
(Non-Recoverable)
AG
Non-recoverable
Losses
278
(138,944)
AB
3,927
(1,962,715)
S
Gasifier Units
AI
Condenser
Q
HRSG Units
20
(9,996)
18
(8,996)
AD
12
(5,998)
11
(5,498)
T
Process
Wastewater
Storage
U
3,939
(1,968,712)
AH
4,228
(2,113,154)
Evaporation &
Drift
Cooling
Tower
V
3,235
(1,616,853)
NOTES:
1. FLOWS ARE SHOWN IN GALLONS PER MIN
ROUNDED TO THE NEAREST GALLON.
2. FLOWS ARE BASED ON AVERAGE DAILY
CONDITIONS.
3. FLOWS IN PARENTHESIS SHOWN IN POUNDS
PER HOUR ROUNDED TO THE NEAREST
POUND.
W
36
(17,993)
993
(496,301)
X date
6/29/2006 designed
M. Boyd detailed
M. Boyd checked
B. Hansen
Y
1,029
(514,294)
1,039
(519,292)
Z
Wastewater
Discharge to
Outfall
PRELIMINARY
550 MW (net) IGCC
Gulf Coast, Texas
Water Balance Diagram
50% PRB / 50% Pet Coke @ 43 F Ambient Dry
Bulb Temp. & 40F Ambient Wet Bulb Temp.
project
42127 drawing
WMB-2.1
contract
---
rev.
B sheet file
1 of 2 sheets
42127 CPS IGCC WMB Rev B.xls
no. | date | by | chd | description
A | 6/23/06 | mab | |
B | 6/29/06 | mab | bdh |
Initial Issue
Revise Raw H
2
O
Raw Water
Influent
5,231
(2,614,454)
A
AJ
Potable
Water
Treatment
AK
On-site Septic
System
3
(1,499)
3
(1,499)
Cartridge
Filtration
B
11
(5,498)
5,217
(2,607,457)
C
D
90
(44,982)
Service
Water
Storage
E
16
(7,997)
Coal
Storage
Area
F
16
(7,997)
5,127
(2,562,475)
K
4,328
(2,163,134)
N
74
(36,985)
G
I
Sour Water
Condensate Recycle
54
(26,989)
H
20
(9,996)
Slag Quench
(Non-recoverable)
AF
Syngas
Treatment
L
799
(399,340)
M
Demineralizer
System
(RO/EDI)
Non-recoverable
Losses
230
(114,954)
8
(3,998)
AE
44
(21,991)
O
234
(116,953)
AA
Demineralized
Water
Storage
569
(284,386)
37
(18,493)
P
Oil/Water
Separator
Syngas Saturation
(Non-Recoverable)
217
(108,457)
AC
81
(40,484)
7
(3,499)
R
J
20
(9,996)
Syngas Burner
(Non-Recoverable)
AG
Non-recoverable
Losses
278
(138,944)
AB
4,558
(2,278,088)
S
Gasifier Units
AI
Condenser
Q
HRSG Units
19
(9,496)
18
(8,996)
AD
11
(5,498)
11
(5,498)
T
Process
Wastewater
Storage
U
4,569
(2,283,586)
AH
4,858
(2,428,028)
Evaporation &
Drift
Cooling
Tower
V
3,715
(1,856,757)
NOTES:
1. FLOWS ARE SHOWN IN GALLONS PER MIN
ROUNDED TO THE NEAREST GALLON.
2. FLOWS ARE BASED ON AVERAGE DAILY
CONDITIONS.
3. FLOWS IN PARENTHESIS SHOWN IN POUNDS
PER HOUR ROUNDED TO THE NEAREST
POUND.
W
36
(17,993)
1,143
(571,271)
X date
6/29/2006 designed
M. Boyd detailed
M. Boyd checked
B. Hansen
Y
1,179
(589,264)
1,190
(594,762)
Z
Wastewater
Discharge to
Outfall
PRELIMINARY
550 MW (net) IGCC
Gulf Coast, Texas
Water Balance Diagram
50% PRB / 50% Pet Coke @ 73 F Ambient Dry
Bulb Temp. & 69 F Ambient Wet Bulb Temp.
project
42127 drawing
WMB-2.2
contract
---
rev.
B sheet file
1 of 2 sheets
42127 CPS IGCC WMB Rev B.xls
no. | date | by | chd | description
A | 6/23/06 | mab | |
B | 6/29/06 | mab | bdh |
Initial Issue
Revise Raw H
2
O
Raw Water
Influent
5,800
(2,898,840)
A
AJ
Potable
Water
Treatment
AK
On-site Septic
System
3
(1,499)
3
(1,499)
Cartridge
Filtration
B
12
(5,998)
5,785
(2,891,343)
C
D
90
(44,982)
Service
Water
Storage
E
16
(7,997)
Coal
Storage
Area
F
16
(7,997)
5,695
(2,846,361)
K
4,910
(2,454,018)
N
74
(36,985)
G
I
Sour Water
Condensate Recycle
54
(26,989)
H
20
(9,996)
Slag Quench
(Non-recoverable)
AF
Syngas
Treatment
L
785
(392,343)
M
Demineralizer
System
(RO/EDI)
Non-recoverable
Losses
226
(112,955)
7
(3,499)
AE
44
(21,991)
O
234
(116,953)
AA
Demineralized
Water
Storage
559
(279,388)
36
(17,993)
P
Oil/Water
Separator
Syngas Saturation
(Non-Recoverable)
211
(105,458)
AC
78
(38,984)
7
(3,499)
R
J
20
(9,996)
Syngas Burner
(Non-Recoverable)
AG
Non-recoverable
Losses
278
(138,944)
AB
5,136
(2,566,973)
S
Gasifier Units
AI
Condenser
Q
HRSG Units
18
(8,996)
18
(8,996)
AD
11
(5,498)
11
(5,498)
T
Process
Wastewater
Storage
U
5,147
(2,572,471)
AH
5,436
(2,716,913)
Evaporation &
Drift
Cooling
Tower
V
4,155
(2,076,669)
NOTES:
1. FLOWS ARE SHOWN IN GALLONS PER MIN
ROUNDED TO THE NEAREST GALLON.
2. FLOWS ARE BASED ON AVERAGE DAILY
CONDITIONS.
3. FLOWS IN PARENTHESIS SHOWN IN POUNDS
PER HOUR ROUNDED TO THE NEAREST
POUND.
W
36
(17,993)
1,281
(640,244)
X date
6/29/2006 designed
M. Boyd detailed
M. Boyd checked
B. Hansen
Y
1,317
(658,237)
1,329
(664,234)
Z
Wastewater
Discharge to
Outfall
PRELIMINARY
550 MW (net) IGCC
Gulf Coast, Texas
Water Balance Diagram
50% PRB / 50% Pet Coke @ 93 F Ambient Dry
Bulb Temp. & 77 F Ambient Wet Bulb Temp.
project
42127 drawing
WMB-2.3
contract
---
rev.
B sheet file
1 of 2 sheets
42127 CPS IGCC WMB Rev B.xls
AC
AD
AG
AH
AA
AB
V
Z
AJ
AK
Flow Path
A Water Supply
B
D
E
H
Filter Reject to Outfall
Service Water
Flow Description
Service Water for Coal Storage
Service Water to Slag Quench
P
T
M
O
Demin. Reject
Demin Storage Influent
Condenser Influent
HRSG Blowdown
CT Evaporation & Drift
Wastewater w/ Filter Reject to Outfall
Demin Water to Syngas Scrubber
Syngas Scrubber Effluent
Demin Water for Syngas Saturation
Gasifier Blowdown
Water for Syngas Burner
Combined CT Make-up
Raw Water Influent to Potable Water Treatment
Effluent to on-site Septic System
PRB
73°F
Flowrate
(GPM)
3595
1153
234
278
193
478
36
11
4983
11
90
16
54
177
11
31
4701
3
3
43°F
Flowrate
(GPM)
3135
1007
234
278
199
493
38
11
4391
9
90
16
54
188
12
33
4097
3
3
93°F
Flowrate
(GPM)
4055
1297
234
278
190
471
36
11
5580
12
90
16
54
171
11
30
5304
3
3
50-50 PRB-Petcoke
43°F
Flowrate
(GPM)
73°F
Flowrate
(GPM)
93°F
Flowrate
(GPM)
3235
1039
234
278
238
589
38
11
4619
10
90
16
54
231
12
86
4228
3
3
3715
1190
234
278
230
569
37
11
5231
11
90
16
54
217
11
81
4858
3
3
4155
1329
234
278
226
559
36
11
5800
12
90
16
54
211
11
78
5436
3
3
D
ELECTRICAL ONE-LINE DIAGRAMS
D-1
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
LINE #2 LINE #1 no.
date by
A
08/04/06 RDM ckd
description
ISSUED FOR
APPROVAL
A
B
192/256/320MVA
345-22kV
153/204/255MVA
345-22kV
153/204/255MVA
345-22kV
STG
320MVA
22KV
CTG 2
255MVA
22KV
45/60/75
22-13.8KV
CTG 1
255MVA
22KV
45/60/75
22-13.8KV
120MVA
345-13.8kV
120MVA
345-13.8kV
G
H
60MVA
345-13.8kV
40,000
MAC
COMPR. 1
12,000 40,000
BAC
COMPR. 1
NITROGEN
AIR
COMPR. 1
60MVA
345-13.8kV
2000/2666KVA
13,800-480V
40,000
MAC
COMPR. 2
12,000 40,000
BAC
COMPR. 2
NITROGEN
AIR
COMPR. 2
2000/2666KVA
13,800-480V
15/20MVA
13,800-4160V
2000/2666KVA
13,800-480V
15/20MVA
13,800-4160V
15/20MVA
13,800-4160V
15/20MVA
13,800-4160V
E
EE004
TO SULFUR &
SLAG SWGR
K
EE013
TO BOP
SWGR
A
EE002
C
EE003
TO GASIFICATION
SWGR
TO COAL
HANDLING SWGR
I
EE006
TO POWER
BLOCK SWGR B
G
EE005
TO POWER
BLOCK SWGR A
15/20MVA
13,800-4160V
15/20MVA
13,800-4160V
15/20MVA
13,800-4160V
2000/2666KVA
13,800-480V
15/20MVA
13,800-4160V
J
H
EE005
TO POWER
BLOCK SWGR A
J
EE006
TO POWER
BLOCK SWGR B
D
EE003
TO COAL
HANDLING SWGR
B
EE002
TO GASIFICATION
SWGR
L
EE013
TO BOP
SWGR
F
EE004
TO SULFUR &
SLAG SWGR date
JUNE 28, 2006 designed
R. MAHALEY detailed
V. VERMILLION checked
--
K
L
EPRI / CPS IGCC STUDY
OVERALL
ONE-LINE DIAGRAM contract project drawing
42127
EE001 sheet of file
42127EE001.DGN
rev.
A sheets
M
I
M:\EPRI-CPS\42127\CAD\ELEC\ONE-LINES\42127EE001.DGN 8-03-2006 15:23 V_VERMIL
E
F
C
D
1 2 3 4 5
A
EE001
6 7 8 9
13,800 GASIFICATION SWGR
10 11
B
EE001
12 13 14 15 16 17
1250
13.8KV
GASIFICATION
LOADS A
2000/2666KVA
13,800-480V
M
480V
GASIFICATION MCCs
1250
13.8KV
GASIFICATION
LOADS B
2000/2666KVA
13,800-480V
N
480V
GASIFICATION MCCs no.
date by
A
08/04/06 RDM ckd
description
ISSUED FOR
APPROVAL
C
D
A
B
G
H
E
F date
JUNE 28, 2006 designed
R. MAHALEY detailed
V. VERMILLION checked
--
K
L
EPRI / CPS IGCC STUDY
GASIFICATION
13.8KV SWGR project drawing
42127
EE002 sheet of file
42127EE002.DGN
contract
rev.
A sheets
M
I
J
M:\EPRI-CPS\42127\CAD\ELEC\ONE-LINES\42127EE002.DGN 8-03-2006 15:25 V_VERMIL
1 2 3 4 5
C
EE001
6 7 8 9 10 11 12 13
D
EE001
14 15 16 17
4160V COAL HANDLING SWGR
2000
GRINDING
MILL 1
2000/2666KVA
4160-480V
250
RECLAIM
CONV.
250
STOCKOUT
CONV.
P
EE009
COAL HANDLING
& GRINDING
MCC A
480V COAL HANDLING SWGR
2000/2666KVA
4160-480V
2000
GRINDING
MILL 2
150
RECLAIM DUST
COLLECTION
200
UNLDG.
CONV.
Q
150
TRANSFER
CONVEYOR
OTHER COAL
HANDLING & GRINDING no.
date by
A
08/04/06 RDM ckd
description
ISSUED FOR
APPROVAL
C
D
A
B
G
H
E
F date
JUNE 28, 2006 designed
R. MAHALEY detailed
V. VERMILLION checked
--
K
L
EPRI / CPS IGCC STUDY
COAL HANDLING
4160V SWGR project drawing
42127
EE003 sheet of file
42127EE003.DGN
contract
rev.
A sheets
M
I
J
M:\EPRI-CPS\42127\CAD\ELEC\ONE-LINES\42127EE003.DGN 8-03-2006 15:30 V_VERMIL
1 2 3 4 5 6
E
EE001
7 8 9 10 11 12 13 14
F
EE001
15 16 17
4160V SULFUR & SLAG SWGR
2000/2666KVA
4160-480V
4160V
SULFUR & SLAG
LOADS 1A
R
TO SLAG & SULFUR
480V MCCs
2000/2666KVA
4160-480V
4160V
SULFUR & SLAG
LOADS 1B
S
TO SLAG & SULFUR
480V MCCs no.
date by
A
08/04/06 RDM ckd
description
ISSUED FOR
APPROVAL
C
D
A
B
G
H
E
F date
JUNE 28, 2006 designed
R. MAHALEY detailed
V. VEMILLION checked
--
K
L
EPRI / CPS IGCC STUDY
SULFUR & SLAG
4160V SWGR project drawing
42127
EE004 sheet of file
42127EE004.DGN
contract
rev.
A sheets
M
I
J
M:\EPRI-CPS\42127\CAD\ELEC\ONE-LINES\42127EE004.DGN 8-03-2006 15:37 V_VERMIL
1 2
G
EE001
3 4 5 6 7 8 9 10 11 12 13 14 15 16
H
EE001
17
4160V POWER BLOCK SWGR. A
2500
CIRC.
WATER
PUMP
CTG 1
STATION SERVICE
TRANSF. 1A
2000/2666KVA
4160-480V
350
WELL
PP1A
750
CTG 1
ATOMIZING
AIR
2500
HP/IP
FEEDWATER
PUMP 2A
2500
HP/IP
FEEDWATER
PUMP 1A
1000
AUX. COOLING
WATER PUMP 1A
BB
PWR BLK
MCC
GG
CTG 2
MCC
DD
CTG 1
MCC
200
CTG 1
WATER
INJ PP
480V POWER BLOCK SWGR. A
EE
CTG 1
MCC
CC
EMERGENCY
MCCs
HH
CTG 2
MCC
JJ
STG
MCC
2500
HP/IP
FEEDWATER
PUMP 1B
2500
HP/IP
FEEDWATER
PUMP 2B
750
CTG 2
ATOMIZING
AIR
350
WELL
PP1B
500
CONDENSATE
PUMP
1000
AUX. COOLING
WATER PUMP 1B
EMERGENCY
GENERATOR
CTG 2
STATION SERVICE
TRANSF. 2A
2000/2666KVA
4160-480V
FF
CTG 1
MCC
II
CTG 2
MCC
200
CTG 2
WATER
INJ PP no.
date by
A 08/04/06 RDM ckd
description
ISSUED FOR
APPROVAL date
JUNE 28, 2006 designed
R. MAHALEY detailed
V. VERMILLION checked
--
K
L
EPRI / CPS IGCC STUDY
POWER BLOCK
SWITCHGEAR A project drawing
42127
EE005 sheet of file
42127EE005.DGN
contract
rev.
A sheets
M
G
H
E
F
I
J
C
D
A
B
M:\EPRI-CPS\42127\CAD\ELEC\ONE-LINES\42127EE005.DGN 8-03-2006 15:39 V_VERMIL
1 2
I
EE001
3 4 5 6 7 8 9 10 11 12 13 14 15 16
J
EE001
17
4160V POWER BLOCK SWGR B
PP
COOLING
TOWER
MCC 18
CTG 1
STATION SERVICE
TRANSF. 1B
2000/2666KVA
4160-480V
1000
CLOSED
COOLING
WATER
PUMP 1A
750
CTG 1
ATOMIZING
AIR
2500
CIRCULATING
WATER
PUMP 1C
500
CONDENSATE
PUMP 1A
MM
HRSG 1
MCC
KK
STG 1A
MCC
480V SWGR. B
500
CONDENSATE
PUMP 1B
2500 1000
CIRCULATING
WATER
PUMP 1B
CLOSED
COOLING WATER
PUMP 1B
350
WELL
PP1C
COOLING
TOWER
MCC 28
NN
HRSG 2
MCC
LL
STG 1B
MCC
CTG 2
STATION SERVICE
TRANSF. 2B
2000/2666KVA
4160-480V no.
date by
A
08/04/06 RDM ckd
description
ISSUED FOR
APPROVAL
C
D
A
B
G
H
E
F date
JUNE 28, 2006 designed
R. MAHALEY detailed
V. VERMILLION checked
--
K
L
EPRI / CPS IGCC STUDY
POWER BLOCK
SWITCHGEAR B project drawing
42127
EE006 sheet of file
42127EE006.DGN
contract
rev.
A sheets
M
I
J
M:\EPRI-CPS\42127\CAD\ELEC\ONE-LINES\42127EE006.DGN 8-03-2006 15:43 V_VERMIL
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
K
EE001
L
EE001
1
RR
WATER TREATMENT
MCC
CONTROL RM/
ADMIN BLDG
PNL
3
BOP MCC A
40A
5
FLARE KO DRUM PUMP
30
CONDENSATE TRANSFER
PUMP 1
WELL PUMP
HOUSE #1 PANEL
480-208/120V
30KVA 3 PH,
DRY TYPE
WAREHOUSE
PNL
FIRE PUMP
SKID
BOP MCC B
3
3A
1
40A
30
CONDENSATE TRANSFER
PUMP 2
25
WELL PUMP 4
POTABLE WATER
10WWW-PMP4
WELL PUMP
HOUSE #2 PANEL
480-208/120V
30KVA 3 PH,
DRY TYPE
NOTES:
1.
FOR GENERAL SYMBOLS AND LEGENDS, REFER TO DWG. E001.
2.
NEMA 1 ENCLOSURE.
3.
INCOMING MAIN POWER CABLES ARE TOP ENTRY.
no.
date by
A
08/04/06 RDM ckd
description
ISSUED FOR
APPROVAL
C
D
A
B
G
H
E
F date
JUNE 28, 2006 designed
R. MAHALEY detailed
V. VERMILLION checked
--
K
L
EPRI / CPS IGCC STUDY
BALANCE OF PLANT
480V SWITCHGEAR & MCC project drawing
42127
EE007 sheet of file
42127EE007.DGN
contract
rev.
A sheets
M
I
J
M:\EPRI-CPS\42127\CAD\ELEC\ONE-LINES\42127EE007.DGN 8-03-2006 16:04 V_VERMIL
E
CAPITAL COST DETAIL
E-1
Burns McDonnell
Confidential
EPRI/CPS - 2x1 7FB IGCC Cost Estimate Summary - 100% PRB
Project Desc:
Project #:
550 MW (Net) 2x1 7FB IGCC - 100% PRB
42127
Account /
Contract
Description
100
101
102
103
104
105
106
107
108
109
FLA
110
111
112
112A
113
114
115
116
117
118
127
128
129
130
131
1201
1202
121
122
123
124
125
126
PROCUREMENT
Major Equipment
Gas Turbine - Generator
Steam Turbine - Generator
Steam Generator / Heat Recovery Steam Generator
Flue Gas Desulfurization System
Particulate Removal (Baghouse or Precip)
SCR / CO Catalyst
Bypass Stack
Stack
Surface Condenser & Air Removal Equipment
Cooling Tower
Flare
Mechanical Procurement
Boiler Feed Pumps
Condensate Pumps
Circulating Water Pumps
Aux Cooling Water Pumps
Miscellaneous Pumps
Compressed Air Equipment
Deaerator
Closed Feedwater Heaters
Auxiliary Boiler
Heat Exchangers
Electrical & Control Procurement
GSU Transformers
Auxiliary Transformers
Generator Breakers
Iso Phase Bus Duct
Small (480 V & 5 kV) Power Transformers
Emergency Diesel Generator
Medium Voltage Metal-Clad Switchgear
480 V Switchgear & Transformers
480 V Motor Control Center
Electrical Control Boards
Battery & UPS System
Freeze Protection System
Relay & Metering Panels
Client:
Estimate By:
EPRI / CPS Energy
J. Schwarz
Material
Dollars Manhours
Labor
Dollars
Subcontract
Dollars
Date:
Revision:
Subcontract
Indirect $
0
07/20/06
Total
Dollars
86,000,000
22,950,840
28,080,000
-
-
-
-
-
4,138,000
-
-
-
-
3,169,814
367,500
819,052
649,251
250,000
330,000
-
-
1,896,000
-
-
-
18,000,000
4,160,000
1,200,000
5,390,000
-
-
7,915,000
6,905,000
-
-
620,000
-
1,075,000
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
10,133,333
6,102,434
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
$ 86,000,000
$ 22,950,840
$ 28,080,000
$ -
$ -
$ -
$ -
$ -
$ 4,138,000
$ 10,133,333
$ 6,102,434
$ -
$ -
$ 3,169,814
$ 367,500
$ 819,052
$ 649,251
$ 250,000
$ 330,000
$ -
$ -
$ 1,896,000
$ -
$ -
$ -
$ 18,000,000
$ 4,160,000
$ 1,200,000
$ 5,390,000
$ -
$ -
$ 7,915,000
$ 6,905,000
$ -
$ -
$ 620,000
$ -
$ 1,075,000
1 of 5 CPS 2x1 7FB IGCC - 100% PRB (working) R0.xls
Burns McDonnell
Confidential
Account /
Contract
Description
160
161
162
163
170
171
172
173
174
180
181
182
183
190
191
192
145
146
147
150
151
152
153
154
155
156
157
158
135
136
137
140
141
142
143
144
195
196
197
Distributed Control System
Continuous Emission Monitors
Instrumentation
Natural Gas Equipment Procurement
Gas Compressors
Fuel Gas Filter/Separator
Fuel Gas Dewpoint Heater
Fuel Gas Efficiency Heater
Fuel Flow Measurement / Monitoring Equipment
Material Handling
Coal Handling Equipment
Ash Handling Equipment
Limestone / Lime Handling Equipment
Water Treatment & Chemical Storage
Raw Water Treatment
RO/EDI or Demineralizer
Condensate Polisher
Chemical Feed Equipment (Boiler Cycle)
Ammonia Supply & Storage
CO
2
Supply & Storage
Chemical Feed Equipment
Sample Analysis Panel
Wastewater Treatment Equipment
Misc Mechanical
Critical Pipe
Balance of Plant Pipe
Pipe Supports
Circulating Water Pipe
High Pressure Valves
Low Pressure Valves
Large Butterfly Valves (>24")
Control Valves
Steam Turbine Bypass Valves
Shop Fabricated Tanks
Oil/Water Separator
Closed Cooling Water Heat Exchanger
Piping Specials
Fire Protection
Fire Protection System
Fire Pumps
Flammable/Combustible Storage Enclosure
Structural Procurement
Bridge Crane
Structural Steel
Fixators
EPRI/CPS - 2x1 7FB IGCC Cost Estimate Summary - 100% PRB
Material
Labor
Manhours
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Dollars
-
1,366,075
572,900
611,725
-
-
-
214,864
-
-
-
-
-
59,000
-
-
-
-
982,500
754,000
-
146,462
-
20,000
270,000
200,000
12,000
-
-
7,425,524
-
532,000
3,591,000
165,000
1,151,500
300,000
626,360
630,000
205,000
58,000
2,228,100
165,500
-
-
1,357,960
216,300
-
-
-
-
1,485,138
117,000
Dollars
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Subcontract Subcontract
Indirect $
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Dollars
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
31,600,000
5,000,000
-
-
-
-
-
-
-
-
-
Total
Dollars
$ -
$ 1,366,075
$ 572,900
$ 611,725
$ -
$ -
$ -
$ 214,864
$ -
$ -
$ -
$ -
$ -
$ 31,659,000
$ 5,000,000
$ -
$ -
$ -
$ 982,500
$ 754,000
$ -
$ 146,462
$ -
$ 20,000
$ 270,000
$ 200,000
$ 12,000
$ -
$ -
$ 7,425,524
$ -
$ 532,000
$ 3,591,000
$ 165,000
$ 1,151,500
$ 300,000
$ 626,360
$ 630,000
$ 205,000
$ 58,000
$ 2,228,100
$ 165,500
$ -
$ -
$ 1,357,960
$ 216,300
$ -
$ -
$ -
$ -
$ 1,485,138
$ 117,000
2 of 5 CPS 2x1 7FB IGCC - 100% PRB (working) R0.xls
EPRI/CPS - 2x1 7FB IGCC Cost Estimate Summary - 100% PRB
Burns McDonnell
Confidential
ASU
GAS
SGT
200
201
202
203
204
205
206
210
211
212
213
214
215
216
220
221
222
223
290
291
299
2301
2310
231
232
260
2401
2402
2403
2404
2405
2406
2407
2408
CONSTRUCTION
Material
Manhours
-
-
Labor
Dollars
-
-
Subcontract Subcontract Total
Account /
Contract
Description
Sub-EPC Packages
Air Separation Unit and N2 Storage
Dollars
-
-
Gasification -
Syngas Treatment
-
-
-
-
-
-
-
-
-
-
-
Major Equipment Erection
Combustion Turbine Generator Erection
Steam Turbine - Generator Erection
Steam Generator / HRSG Erection
FGD System Erection
Particulate Removal (Baghouse or Precip) Erection
SCR / CO Catalyst Erection
Chimney
Civil / Structural Construction
Site Preparation
Piling
Substructures
Underground Utilities
Yard Structures
Foundations
Railroad
Structural Steel
Power Plant Structures
Pre-engineered Buildings
Sanitary Drains / Treatment
Final Painting
Final Paving, Landscaping & Cleanup
Demolition
Mechanical Construction
Misc Mechanical Equipment Erection
Below Grade Piping
Above Grade Piping
Insulation and Lagging
Field Erected Tanks
-
7,488
-
-
-
-
-
-
-
-
3,154,045
-
-
-
-
4,068,872
-
338,331
-
-
-
-
988,000
486,405
-
-
-
-
373,650
6,475,923
760,000
-
Electrical Construction
Electrical Equipment Erection
Wire / Cable
Grounding
Raceway
Lighting
Heat Tracing
Instrumentation
-
-
250,000
2,223,970
57,124
Switchyard -
-
-
230,285
-
-
-
-
3,324,536
1,458,605
8,825,957
-
-
-
-
-
-
12,717,757
-
-
-
-
8,601,390
-
1,097,378
-
-
-
-
840,172
72,487
-
-
-
2,904,083
3,288,263
10,986,993
1,656,923
-
-
-
3,179,171
2,167,145
-
650,680
-
-
430,586
-
-
-
-
72,651
31,875
165,750
-
-
-
-
-
-
297,345
-
-
-
-
188,696
-
24,831
-
-
-
-
18,896
1,695
-
-
-
63,463
73,953
247,098
36,210
-
-
-
69,459
47,350
-
14,216
-
-
9,410
-
-
-
Dollars
-
-
Indirect $
-
-
-
102,400,000
354,306,139
149,993,742
-
17,000
-
500,000
-
-
-
-
-
-
40,313,746
3,301,520
-
-
-
189,900
10,040,500
-
6,783,360
-
-
-
1,170,000
389,928
-
-
-
-
1,071,134
1,373,690
765,000
2,260,000
-
-
-
-
-
-
-
-
10,000
10,890,000
-
-
-
-
-
-
-
-
1,773,346
778,037
4,045,792
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
182,817
-
-
-
-
1,549,071
1,805,122
6,031,409
773,415
-
-
-
1,097,335
1,405,157
-
281,909
-
-
156,067
-
-
-
Dollars
$ -
$ -
$
$
-
-
$ 102,400,000
$ 354,306,139
$ 149,993,742
$ -
$ -
$ 5,122,369
$ 2,236,642
$ 13,371,748
$ -
$ -
$ -
$ -
$ -
$ -
$ 56,185,548
$ 3,301,520
$ -
$ -
$ -
$ 12,860,162
$ 10,040,500
$ 1,435,708
$ 6,783,360
$ -
$ -
$ -
$ 3,180,990
$ 948,819
$ -
$ -
$ -
$ 4,453,154
$ 6,538,169
$ 24,868,015
$ 3,955,338
$ 2,260,000
$ -
$ -
$ 4,526,506
$ 5,796,271
$ -
$ 1,162,874
$ -
$ -
$ 653,777
$ 10,890,000
$ -
$ -
3 of 5 CPS 2x1 7FB IGCC - 100% PRB (working) R0.xls
Burns McDonnell
Confidential
Account /
Contract
Description
5000
5001
5002
5003
5004
5005
5006
5012
5007
5008
5009
5010
5011
5050
5051
5052
5053
5064
5054
5055
5056
5057
5058
5059
5060
EPC CONTRACTOR INDIRECT COSTS
Construction Indirects
Construction Management
Field Office Expense
Temporary Facilities
Temporary Utilities
Construction Equipment / Operators
Heavy Haul
Small Tools & Consumables
Labor Per Diem & Benefits
Site Services
Construction Testing
Preoperational Testing, Startup, & Calibration
Safety
Miscellaneous Construction Indirects
Project Indirects
Site Surveys/Studies
Performance Testing
Project Management & Engineering
Training
Warranty
Operating Spare Parts
Project Insurance
Project Bonds
Escalation
Sales Tax
EPC Contingency
EPC Fee
TOTAL EPC PROJECT COST
EPRI/CPS - 2x1 7FB IGCC Cost Estimate Summary - 100% PRB
Material
Labor
Subcontract Subcontract
Dollars Manhours Dollars Dollars Indirect $
-
-
-
-
-
-
-
-
-
-
-
-
-
146,400
-
-
-
-
-
-
40,000,000
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
1,530
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
70,011
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
24,714,000
-
-
2,954,590
-
1,331,911
-
-
-
500,000
8,016,000
-
-
-
-
700,000
600,000
-
500,000
-
-
-
2,961,450
-
-
57,099,042
119,907,989
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Total
Dollars
$ -
$ -
$ -
$ 24,714,000
$ -
$ -
$ 2,954,590
$ -
$ 1,331,911
$ -
$ -
$ -
$ 500,000
$ 8,232,411
$ -
$ -
$ -
$ -
$ 700,000
$ 600,000
$ 40,000,000
$ 500,000
$ -
$ -
$ -
$ 2,961,450
$ -
$ -
$ 57,099,042
$ 119,907,989
278,939,856 1,364,428 62,272,136 957,896,409 19,879,477 1,318,987,878
4 of 5 CPS 2x1 7FB IGCC - 100% PRB (working) R0.xls
Burns McDonnell
Confidential
EPRI/CPS - 2x1 7FB IGCC Cost Estimate Summary - 100% PRB
6008
6009
6010
6011
6012
6013
6014
6015
6000
6001
6002
6003
6004
6005
6006
6007
6016
6017
6018
6019
6020
6021
6022
Material
Account /
Contract
Description
Owner Indirects
Project Development
Owner Personnel
Owners OE
Owners Legal Council
Owner Startup Engineering
Permitting & License Fees
Land
Water Rights
Political Concessions / Area Development Fees / Labor Camps
Startup/Testing
Initial Fuel Inventory
Site Surveys/Studies
Site Security
Transmission Interconnection / Upgrades
Operating Spare Parts
Permanent Plant Equipment & Furnishings
Builder's Risk Insurance
Escalation Owner's Indirects
Sales Tax & Duties
Owner Contingency
Financing Fees
Interest During Construction
Dollars
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
10,055,869
4,600,000
-
-
-
-
-
-
Manhours
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Labor
Dollars
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Subcontract
Dollars
-
-
3,000,000
7,200,000
23,000,000
2,000,000
-
2,910,000
7,500,000
-
1,000,000
5,186,487
10,927,224
-
1,728,000
-
-
-
5,935,445
-
-
70,201,545
-
-
Subcontract
Indirect $
Total
Dollars
$ -
$ -
$ 3,000,000
$ 7,200,000
$ 23,000,000
$ 2,000,000
$ -
$ 2,910,000
$ 7,500,000
$ -
$ 1,000,000
$ 5,186,487
$ 10,927,224
$ -
$ 1,728,000
$ -
$ 10,055,869
$ 4,600,000
$ 5,935,445
$ -
$ -
$ 70,201,545
$ -
$ -
TOTAL OWNER COST
TOTAL EPC PROJECT COST
TOTAL OWNER'S COST
PROJECT TOTAL
14,655,869 140,588,702 155,244,571
$ 278,939,856
$ 14,655,869
1,364,428
-
$ 62,272,136 $ 957,896,409
$ 140,588,702
$ 19,879,477 $ 1,318,987,878
$ 155,244,571
$ 293,595,725 1,364,428 $ 62,272,136 $ 1,098,485,111 $ 19,879,477 $ 1,474,232,449
5 of 5 CPS 2x1 7FB IGCC - 100% PRB (working) R0.xls
EPRI/CPS - 2x1 7FB IGCC Cost Estimate Summary - 50% PRB / 50% Pet Coke
Project Desc:
Project #:
550 MW (Net) 2x1 7FB IGCC - 50% PRB/50% Petcoke
42127
Account /
Contract
Description
100
101
102
103
104
105
106
107
108
109
FLA
110
111
112
112A
113
114
115
116
117
118
127
128
129
130
131
1201
1202
121
122
123
124
125
126
PROCUREMENT
Major Equipment
Gas Turbine - Generator
Steam Turbine - Generator
Steam Generator / Heat Recovery Steam Generator
Flue Gas Desulfurization System
Particulate Removal (Baghouse or Precip)
SCR / CO Catalyst
Bypass Stack
Stack
Surface Condenser & Air Removal Equipment
Cooling Tower
Flare
Mechanical Procurement
Boiler Feed Pumps
Condensate Pumps
Circulating Water Pumps
Aux Cooling Water Pumps
Miscellaneous Pumps
Compressed Air Equipment
Deaerator
Closed Feedwater Heaters
Auxiliary Boiler
Heat Exchangers
Electrical & Control Procurement
GSU Transformers
Auxiliary Transformers
Generator Breakers
Iso Phase Bus Duct
Small (480 V & 5 kV) Power Transformers
Emergency Diesel Generator
Medium Voltage Metal-Clad Switchgear
480 V Switchgear & Transformers
480 V Motor Control Center
Electrical Control Boards
Battery & UPS System
Freeze Protection System
Relay & Metering Panels
Client:
Estimate By:
EPRI / CPS Energy
J. Schwarz
Material
Dollars Manhours
Labor
Dollars
Subcontract
Dollars
Date:
Revision:
Subcontract
Indirect $
0
07/20/06
Total
Dollars
86,000,000
22,950,840
28,080,000
-
-
-
-
-
4,138,000
-
-
-
-
3,169,814
367,500
819,052
649,251
250,000
330,000
-
-
1,896,000
-
-
-
18,000,000
4,160,000
1,200,000
5,820,000
-
-
8,465,000
8,355,000
-
-
620,000
-
1,075,000
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
10,133,333
6,102,434
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
$ 86,000,000
$ 22,950,840
$ 28,080,000
$ -
$ -
$ -
$ -
$ -
$ 4,138,000
$ 10,133,333
$ 6,102,434
$ -
$ -
$ 3,169,814
$ 367,500
$ 819,052
$ 649,251
$ 250,000
$ 330,000
$ -
$ -
$ 1,896,000
$ -
$ -
$ -
$ 18,000,000
$ 4,160,000
$ 1,200,000
$ 5,820,000
$ -
$ -
$ 8,465,000
$ 8,355,000
$ -
$ -
$ 620,000
$ -
$ 1,075,000
Burns McDonnell
Confidential
1 of 5 CPS 2x1 7FB IGCC - 50% PRB - 50% Pet Coke (working) R0.xls
Account /
Contract
Description
160
161
162
163
170
171
172
173
174
180
181
182
183
190
191
192
145
146
147
150
151
152
153
154
155
156
157
158
135
136
137
140
141
142
143
144
195
196
197
Distributed Control System
Continuous Emission Monitors
Instrumentation
Natural Gas Equipment Procurement
Gas Compressors
Fuel Gas Filter/Separator
Fuel Gas Dewpoint Heater
Fuel Gas Efficiency Heater
Fuel Flow Measurement / Monitoring Equipment
Material Handling
Coal Handling Equipment
Ash Handling Equipment
Limestone / Lime Handling Equipment
Water Treatment & Chemical Storage
Raw Water Treatment
RO/EDI or Demineralizer
Condensate Polisher
Chemical Feed Equipment (Boiler Cycle)
Ammonia Supply & Storage
CO
2
Supply & Storage
Chemical Feed Equipment
Sample Analysis Panel
Wastewater Treatment Equipment
Misc Mechanical
Critical Pipe
Balance of Plant Pipe
Pipe Supports
Circulating Water Pipe
High Pressure Valves
Low Pressure Valves
Large Butterfly Valves (>24")
Control Valves
Steam Turbine Bypass Valves
Shop Fabricated Tanks
Oil/Water Separator
Closed Cooling Water Heat Exchanger
Piping Specials
Fire Protection
Fire Protection System
Fire Pumps
Flammable/Combustible Storage Enclosure
Structural Procurement
Bridge Crane
Structural Steel
Fixators
Burns McDonnell
Confidential
EPRI/CPS - 2x1 7FB IGCC Cost Estimate Summary - 50% PRB / 50% Pet Coke
Material
Labor
Manhours
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Dollars
-
1,391,075
572,900
662,725
-
-
-
214,864
-
-
-
-
-
118,000
-
-
-
-
982,500
754,000
-
146,462
-
20,000
270,000
200,000
12,000
-
-
7,425,524
-
532,000
3,591,000
165,000
1,151,500
300,000
626,360
630,000
205,000
58,000
2,228,100
165,500
-
-
1,857,960
216,300
-
-
-
-
1,485,138
117,000
Dollars
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Subcontract Subcontract
Indirect $
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Dollars
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
41,100,000
3,077,861
-
-
-
-
-
-
-
-
-
Total
Dollars
$ -
$ 1,391,075
$ 572,900
$ 662,725
$ -
$ -
$ -
$ 214,864
$ -
$ -
$ -
$ -
$ -
$ 41,218,000
$ 3,077,861
$ -
$ -
$ -
$ 982,500
$ 754,000
$ -
$ 146,462
$ -
$ 20,000
$ 270,000
$ 200,000
$ 12,000
$ -
$ -
$ 7,425,524
$ -
$ 532,000
$ 3,591,000
$ 165,000
$ 1,151,500
$ 300,000
$ 626,360
$ 630,000
$ 205,000
$ 58,000
$ 2,228,100
$ 165,500
$ -
$ -
$ 1,857,960
$ 216,300
$ -
$ -
$ -
$ -
$ 1,485,138
$ 117,000
2 of 5 CPS 2x1 7FB IGCC - 50% PRB - 50% Pet Coke (working) R0.xls
Account /
Contract
Description
200
201
202
203
204
205
206
210
211
212
213
214
215
216
220
221
222
223
290
291
299
ASU
GAS
SGT
2301
2310
231
232
260
2401
2402
2403
2404
2405
2406
2407
2408
CONSTRUCTION
Sub-EPC Packages
Air Separation Unit and N2 Storage
Gasification
Syngas Treatment
Major Equipment Erection
Combustion Turbine Generator Erection
Steam Turbine - Generator Erection
Steam Generator / HRSG Erection
FGD System Erection
Particulate Removal (Baghouse or Precip) Erection
SCR / CO Catalyst Erection
Chimney
Civil / Structural Construction
Site Preparation
Piling
Substructures
Underground Utilities
Yard Structures
Foundations
Railroad
Structural Steel
Power Plant Structures
Pre-engineered Buildings
Sanitary Drains / Treatment
Final Painting
Final Paving, Landscaping & Cleanup
Demolition
Mechanical Construction
Misc Mechanical Equipment Erection
Below Grade Piping
Above Grade Piping
Insulation and Lagging
Field Erected Tanks
Electrical Construction
Electrical Equipment Erection
Wire / Cable
Grounding
Raceway
Lighting
Heat Tracing
Instrumentation
Switchyard
Burns McDonnell
Confidential
EPRI/CPS - 2x1 7FB IGCC Cost Estimate Summary - 50% PRB / 50% Pet Coke
Material
Labor
Subcontract Subcontract Total
Dollars
-
-
-
-
-
-
Manhours
-
-
-
-
-
-
Dollars
-
-
-
-
-
-
-
7,488
-
-
-
-
-
-
-
-
3,121,355
-
-
-
-
4,417,676
-
338,331
-
-
-
-
988,000
486,405
-
-
-
-
373,650
6,475,923
760,000
-
-
-
250,000
2,223,970
-
230,285
-
-
57,124
-
-
-
-
3,324,536
1,458,605
8,825,957
-
-
-
-
-
-
12,678,548
-
-
-
-
9,966,627
-
1,097,378
-
-
-
-
840,172
72,487
-
-
-
2,904,083
3,288,263
10,986,993
1,656,923
-
-
-
3,479,360
2,167,145
-
650,680
-
-
464,542
-
-
-
-
72,651
31,875
165,750
-
-
-
-
-
-
296,428
-
-
-
-
218,646
-
24,831
-
-
-
-
18,896
1,695
-
-
-
63,463
73,953
247,098
36,210
-
-
-
76,018
47,350
-
14,216
-
-
10,152
-
-
-
Dollars
-
-
Indirect $
-
-
-
102,400,000
306,357,314
158,147,910
-
17,000
-
500,000
-
-
-
-
-
-
40,009,951
3,499,160
-
-
-
204,460
10,040,500
-
6,783,360
-
-
-
1,170,000
389,928
-
-
-
-
1,071,134
1,373,690
765,000
2,260,000
-
-
-
-
-
-
-
-
20,000
10,890,000
-
-
-
-
-
-
-
-
1,773,346
778,037
4,045,792
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
182,817
-
-
-
-
1,549,071
1,805,122
6,031,409
773,415
-
-
-
1,193,395
1,405,157
-
281,909
-
-
166,933
-
-
-
Dollars
$ -
$ -
$
$
-
-
$ 102,400,000
$ 306,357,314
$ 158,147,910
$ -
$ -
$ 5,122,369
$ 2,236,642
$ 13,371,748
$ -
$ -
$ -
$ -
$ -
$ -
$ 55,809,853
$ 3,499,160
$ -
$ -
$ -
$ 14,588,763
$ 10,040,500
$ 1,435,708
$ 6,783,360
$ -
$ -
$ -
$ 3,180,990
$ 948,819
$ -
$ -
$ -
$ 4,453,154
$ 6,538,169
$ 24,868,015
$ 3,955,338
$ 2,260,000
$ -
$ -
$ 4,922,755
$ 5,796,271
$ -
$ 1,162,874
$ -
$ -
$ 708,598
$ 10,890,000
$ -
$ -
3 of 5 CPS 2x1 7FB IGCC - 50% PRB - 50% Pet Coke (working) R0.xls
Account /
Contract
Description
5000
5001
5002
5003
5004
5005
5006
5012
5007
5008
5009
5010
5011
5050
5051
5052
5053
5064
5054
5055
5056
5057
5058
5059
5060
EPC CONTRACTOR INDIRECT COSTS
Construction Indirects
Construction Management
Field Office Expense
Temporary Facilities
Temporary Utilities
Construction Equipment / Operators
Heavy Haul
Small Tools & Consumables
Labor Per Diem & Benefits
Site Services
Construction Testing
Preoperational Testing, Startup, & Calibration
Safety
Miscellaneous Construction Indirects
Project Indirects
Site Surveys/Studies
Performance Testing
Project Management & Engineering
Training
Warranty
Operating Spare Parts
Project Insurance
Project Bonds
Escalation
Sales Tax
EPC Contingency
EPC Fee
TOTAL EPC PROJECT COST
EPRI/CPS - 2x1 7FB IGCC Cost Estimate Summary - 50% PRB / 50% Pet Coke
Material
Labor
Subcontract Subcontract
Dollars Manhours Dollars Dollars Indirect $
-
-
-
-
-
-
-
-
-
-
-
-
-
146,400
-
-
-
-
-
-
40,000,000
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
1,530
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
70,011
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
24,714,000
-
-
2,954,590
-
1,331,911
-
-
-
500,000
8,016,000
-
-
-
-
700,000
600,000
-
500,000
-
-
-
2,890,860
-
-
55,738,004
117,049,808
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Total
Dollars
$ -
$ -
$ -
$ 24,714,000
$ -
$ -
$ 2,954,590
$ -
$ 1,331,911
$ -
$ -
$ -
$ 500,000
$ 8,232,411
$ -
$ -
$ -
$ -
$ 700,000
$ 600,000
$ 40,000,000
$ 500,000
$ -
$ -
$ -
$ 2,890,860
$ -
$ -
$ 55,738,004
$ 117,049,808
282,320,970 1,400,762 63,932,307 921,308,208 19,986,403 1,287,547,889
Burns McDonnell
Confidential
4 of 5 CPS 2x1 7FB IGCC - 50% PRB - 50% Pet Coke (working) R0.xls
EPRI/CPS - 2x1 7FB IGCC Cost Estimate Summary - 50% PRB / 50% Pet Coke
Account /
Contract
Description
6008
6009
6010
6011
6012
6013
6014
6015
6000
6001
6002
6003
6004
6005
6006
6007
6016
6017
6018
6019
6020
6021
6022
Owner Indirects
Project Development
Owner Personnel
Owners OE
Owners Legal Council
Owner Startup Engineering
Permitting & License Fees
Land
Water Rights
Political Concessions / Area Development Fees / Labor Camps
Startup/Testing
Initial Fuel Inventory
Site Surveys/Studies
Site Security
Transmission Interconnection / Upgrades
Operating Spare Parts
Permanent Plant Equipment & Furnishings
Builder's Risk Insurance
Escalation Owner's Indirects
Sales Tax & Duties
Owner Contingency
Financing Fees
Interest During Construction
TOTAL OWNER COST
TOTAL EPC PROJECT COST
TOTAL OWNER'S COST
PROJECT TOTAL
Material
Labor
Dollars
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
10,123,491
4,600,000
-
-
-
-
-
-
Manhours
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Dollars
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Subcontract
Dollars
-
-
3,000,000
7,200,000
23,000,000
2,000,000
-
2,910,000
7,500,000
-
1,000,000
(3,499,854)
6,191,274
-
1,728,000
-
-
-
5,793,965
-
-
67,954,738
-
-
Subcontract
Indirect $
Total
Dollars
$ -
$ -
$ 3,000,000
$ 7,200,000
$ 23,000,000
$ 2,000,000
$ -
$ 2,910,000
$ 7,500,000
$ -
$ 1,000,000
$ (3,499,854)
$ 6,191,274
$ -
$ 1,728,000
$ -
$ 10,123,491
$ 4,600,000
$ 5,793,965
$ -
$ -
$ 67,954,738
$ -
$ -
14,723,491 124,778,124 139,501,616
$ 282,320,970
$ 14,723,491
1,400,762
-
$ 63,932,307
$ -
$ 921,308,208
$ 124,778,124
$ 19,986,403
$ -
$ 1,287,547,889
$ 139,501,616
$ 297,044,462 1,400,762 $ 63,932,307 $ 1,046,086,333 $ 19,986,403 $ 1,427,049,505
Burns McDonnell
Confidential
5 of 5 CPS 2x1 7FB IGCC - 50% PRB - 50% Pet Coke (working) R0.xls
Burns McDonnell
Confidential
EPRI/CPS - 550 MW Supercritical PC Cost Estimate Summary - 100% PRB
Project Desc:
Project #:
550 MW (Net) Supercritical PC - 100% PRB
42127
Client:
Estimate By:
Account /
Contract
Description
Material
Dollars
EPRI / CPS Energy
J. Schwarz
Manhours
Labor
Dollars
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
127
128
129
130
131
1201
1202
121
122
123
124
125
126
PROCUREMENT
Major Equipment
Gas Turbine - Generator
Steam Turbine - Generator
Steam Generator / Heat Recovery Steam Generator
Flue Gas Desulfurization System
Particulate Removal (Baghouse or Precip)
SCR / CO Catalyst
Bypass Stack
Stack
Surface Condenser & Air Removal Equipment
Cooling Tower
Mechanical Procurement
Boiler Feed Pumps
Condensate Pumps
Circulating Water Pumps
Miscellaneous Pumps
Compressed Air Equipment
Deaerator
Closed Feedwater Heaters
Auxiliary Boiler
Heat Exchangers
Electrical & Control Procurement
GSU Transformers
Auxiliary Transformers
Generator Breakers
Iso Phase Bus Duct
Small (480 V & 5 kV) Power Transformers
Emergency Diesel Generator
Medium Voltage Metal-Clad Switchgear
480 V Switchgear & Transformers
480 V Motor Control Center
Electrical Control Boards
Battery & UPS System
Freeze Protection System
Relay & Metering Panels
Subcontract
Dollars
Date:
Revision:
Subcontract
Indirect $
0
07/20/06
Total
Dollars
-
40,043,000
182,631,579
-
-
-
-
-
5,800,000
-
-
-
3,275,768
420,000
1,300,000
800,600
990,000
362,887
2,854,904
-
270,000
-
-
9,450,000
3,100,000
-
2,035,000
-
-
6,295,000
3,965,000
1,785,000
115,836
1,105,000
-
405,000
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
10,000,000
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
$ -
$ 40,043,000
$ 182,631,579
$ -
$ -
$ -
$ -
$ -
$ 5,800,000
$ 10,000,000
$ -
$ -
$ 3,275,768
$ 420,000
$ 1,300,000
$ 800,600
$ 990,000
$ 362,887
$ 2,854,904
$ -
$ 270,000
$ -
$ -
$ 9,450,000
$ 3,100,000
$ -
$ 2,035,000
$ -
$ -
$ 6,295,000
$ 3,965,000
$ 1,785,000
$ 115,836
$ 1,105,000
$ -
$ 405,000
1 of 5 550MW Super PC Cost Estimate - Greenfield.xls
Burns McDonnell
Confidential
Account /
Contract
Description
135
136
137
140
141
142
143
144
160
161
162
163
170
171
172
173
174
180
181
182
183
190
191
192
195
196
197
145
146
147
150
151
152
153
154
155
156
157
158
Distributed Control System
Continuous Emission Monitors
Instrumentation
Natural Gas Equipment Procurement
Gas Compressors
Fuel Gas Filter/Separator
Fuel Gas Dewpoint Heater
Fuel Gas Efficiency Heater
Fuel Flow Measurement / Monitoring Equipment
Material Handling
Coal Handling Equipment
Ash Handling Equipment
Limestone Handling Equipment
Water Treatment & Chemical Storage
Raw Water Treatment
RO/EDI or Demineralizer
Condensate Polisher
Chemical Feed Equipment (Boiler Cycle)
Ammonia Supply & Storage
CO2 Supply & Storage
Chemical Feed Equipment (Cooling Tower)
Sample Analysis Panel
Wastewater Treatment Equipment
Misc Mechanical
Critical Pipe
Balance of Plant Pipe
Pipe Supports
Circulating Water Pipe
High Pressure Valves
Low Pressure Valves
Large Butterfly Valves (>24")
Control Valves
Steam Turbine Bypass Valves
Shop Fabricated Tanks
Oil/Water Separator
Closed Cooling Water Heat Exchanger
Piping Specials
Fire Protection
Fire Protection System
Fire Pumps
Flammable/Combustible Storage Enclosure
Structural Procurement
Bridge Crane
Structural Steel
Fixators
EPRI/CPS - 550 MW Supercritical PC Cost Estimate Summary - 100% PRB
Material
Labor
Manhours
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Dollars
-
6,857,723
-
542,190
3,195,000
1,633,159
3,287,242
-
792,000
1,266,411
206,000
101,500
-
1,584,920
-
-
-
325,000
-
-
-
-
1,967,360
-
-
5,301,000
600,000
1,108,310
-
-
-
-
-
-
-
-
-
-
-
-
-
-
792,500
754,000
2,225,309
190,000
301,899
30,200
-
250,000
12,000
-
Dollars
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Subcontract Subcontract
Indirect $
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Dollars
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
2,500,000
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
32,000,000
10,630,000
3,899,000
-
-
-
-
-
-
-
-
-
-
-
-
Total
Dollars
$ -
$ 5,301,000
$ 600,000
$ 1,108,310
$ -
$ -
$ -
$ -
$ -
$ -
$ -
$ -
$ -
$ 32,000,000
$ 10,630,000
$ 3,899,000
$ -
$ -
$ 792,500
$ 754,000
$ 2,225,309
$ 190,000
$ 301,899
$ 30,200
$ -
$ 250,000
$ 12,000
$ -
$ -
$ 6,857,723
$ -
$ 542,190
$ 3,195,000
$ 1,633,159
$ 3,287,242
$ -
$ 792,000
$ 1,266,411
$ 206,000
$ 101,500
$ -
$ 1,584,920
$ -
$ -
$ 2,500,000
$ 325,000
$ -
$ -
$ -
$ -
$ 1,967,360
$ -
2 of 5 550MW Super PC Cost Estimate - Greenfield.xls
Burns McDonnell
Confidential
EPRI/CPS - 550 MW Supercritical PC Cost Estimate Summary - 100% PRB
200
201
202
203
204
205
206
210
211
212
213
214
215
216
220
221
222
223
290
291
299
2301
2310
231
232
260
2401
2402
2403
2404
2405
2406
2407
2408
Material
Account /
Contract
Description
Dollars
CONSTRUCTION
-
-
Major Equipment Erection
Combustion Turbine Generator Erection
Steam Turbine - Generator Erection
Steam Generator / HRSG Erection
FGD System Erection
Particulate Removal (Baghouse or Precip) Erection
SCR / CO Catalyst Erection
Chimney
Civil / Structural Construction
Site Preparation
Piling
Substructures
Underground Utilities
Yard Structures
Foundations
Railroad
Structural Steel
Power Plant Structures
Pre-engineered Buildings
Sanitary Drains / Treatment
Final Painting
Final Paving, Landscaping & Cleanup
Demolition
Mechanical Construction
Misc Mechanical Equipment Erection
Below Grade Piping
Above Grade Piping
Insulation and Lagging
Field Erected Tanks
-
-
-
-
-
-
-
-
-
-
-
3,208,315
-
-
-
-
10,409,116
-
1,172,632
12,544,401
-
-
-
520,000
886,405
-
-
-
-
457,718
19,432,376
781,708
Electrical Construction
Electrical Equipment Erection
Wire / Cable
Grounding
Raceway
Lighting
Heat Tracing
Instrumentation
-
-
-
-
6,627,351
345,613
1,788,353
311,520
700,000
Switchyard -
-
-
-
Labor
Subcontract Subcontract
Dollars
-
-
-
-
-
4,091,681
-
-
-
-
-
-
-
15,065,704
-
-
-
-
20,694,597
-
2,286,786
8,614,204
-
-
-
546,580
104,192
-
-
-
6,883,668
2,854,928
27,741,082
5,410,223
-
-
-
3,117,057
17,426,660
944,212
9,538,073
799,429
470,570
682,463
-
-
-
Manhours
-
-
-
-
-
83,105
-
-
-
-
-
-
-
335,390
-
-
-
-
491,846
-
47,801
180,063
-
-
-
9,945
2,320
-
-
-
131,127
52,729
504,760
116,243
-
-
-
63,342
354,129
19,187
193,824
16,245
9,563
13,868
-
-
-
Indirect $
-
-
-
-
-
2,028,498
-
-
-
-
-
-
-
1,827,402
-
-
-
-
3,110,371
-
345,942
2,115,861
-
-
-
106,658
99,060
-
-
-
3,200,676
1,287,064
12,320,685
2,837,370
-
-
-
997,458
7,697,284
412,744
3,624,456
355,504
374,582
218,388
-
-
-
Dollars
-
-
-
-
-
720,000
164,368,421
-
-
-
15,000,000
-
-
40,392,509
10,000,000
-
-
-
-
10,040,500
70,000
10,556,140
-
-
-
1,500,000
435,928
-
-
-
600,000
-
-
-
1,499,100
-
-
83,100
-
-
-
-
-
-
4,840,000
-
-
Total
Dollars
$ -
$ -
$ -
$ -
$ -
$ 6,840,179
$ 164,368,421
$ -
$ -
$ -
$ 15,000,000
$ -
$ -
$ 60,493,929
$ 10,000,000
$ -
$ -
$ -
$ 34,214,084
$ 10,040,500
$ 3,875,360
$ 33,830,606
$ -
$ -
$ -
$ 2,673,238
$ 1,525,585
$ -
$ -
$ -
$ 10,684,344
$ 4,599,709
$ 59,494,143
$ 9,029,301
$ 1,499,100
$ -
$ -
$ 4,197,616
$ 31,751,294
$ 1,702,569
$ 14,950,883
$ 1,466,452
$ 1,545,152
$ 900,852
$ 4,840,000
$ -
$ -
3 of 5 550MW Super PC Cost Estimate - Greenfield.xls
Burns McDonnell
Confidential
Account /
Contract
Description
5000
5001
5002
5003
5004
5005
5006
5007
5008
5009
5010
5011
5050
5051
5052
5053
5054
5055
5056
5057
5058
5059
5060
EPC CONTRACTOR INDIRECT COSTS
Construction Indirects
Construction Management
Field Office Expense
Temporary Facilities
Temporary Utilities
Construction Equipment / Operators
Heavy Haul
Small Tools & Consumables
Site Services
Construction Testing
Preoperational Testing, Startup, & Calibration
Safety
Miscellaneous Construction Indirects
Project Indirects
Site Surveys/Studies
Performance Testing
Project Management & Engineering
Training
Operating Spare Parts
Project Insurance
Project Bonds
Escalation
Sales Tax
EPC Contingency
EPC Fee
TOTAL EPC PROJECT COST
EPRI/CPS - 550 MW Supercritical PC Cost Estimate Summary - 100% PRB
Material
Dollars
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Labor
Manhours
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Dollars
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Subcontract Subcontract
Dollars Indirect $
-
-
-
24,712,644
-
-
2,754,590
-
1,250,000
-
-
500,000
8,786,000
-
-
-
-
700,000
300,000
38,115,000
225,000
-
-
2,408,182
-
-
46,431,601
97,506,363
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Total
Dollars
$ -
$ -
$ -
$ 24,712,644
$ -
$ -
$ 2,754,590
$ -
$ 1,250,000
$ -
$ -
$ 500,000
$ 8,786,000
$ -
$ -
$ -
$ -
$ 700,000
$ 300,000
$ 38,115,000
$ 225,000
$ -
$ -
$ 2,408,182
$ -
$ -
$ 46,431,601
$ 97,506,363
359,513,804 2,625,486 127,272,110 542,824,078 42,960,002 1,072,569,994
4 of 5 550MW Super PC Cost Estimate - Greenfield.xls
Burns McDonnell
Confidential
EPRI/CPS - 550 MW Supercritical PC Cost Estimate Summary - 100% PRB
6008
6009
6010
6011
6012
6013
6014
6015
6000
6001
6002
6003
6004
6005
6006
6007
6016
6017
6018
6019
6020
6021
6022
Material
Account /
Contract
Description
Owner Indirects
Project Development
Owner Operations Personnel
Owners OE
Owners Legal Council
Owner Startup Engineering
Permitting & License Fees
Land
Water Rights
Political Concessions / Area Development Fees / Labor Camps
Startup/Testing
Initial Fuel Inventory
Site Surveys/Studies
Site Security
Transmission Interconnection / Upgrades
Operating Spare Parts
Permanent Plant Equipment & Furnishings
Builder's Risk Insurance
Escalation Owner's Indirects
Sales Tax & Duties
Owner Contingency
Financing Fees
Interest During Construction
Dollars
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
5,752,221
5,780,000
-
-
-
-
-
-
Manhours
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Labor
Dollars
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Subcontract
Dollars
-
-
2,000,000
7,200,000
20,000,000
2,000,000
-
2,910,000
7,500,000
-
1,000,000
1,114,760
10,692,000
-
1,728,000
-
-
-
4,826,565
-
-
57,253,677
-
-
Subcontract
Indirect $
Total
Dollars
$ -
$ -
$ 2,000,000
$ 7,200,000
$ 20,000,000
$ 2,000,000
$ -
$ 2,910,000
$ 7,500,000
$ -
$ 1,000,000
$ 1,114,760
$ 10,692,000
$ -
$ 1,728,000
$ -
$ 5,752,221
$ 5,780,000
$ 4,826,565
$ -
$ -
$ 57,253,677
$ -
$ -
TOTAL OWNER COST
TOTAL EPC PROJECT COST
TOTAL OWNER'S COST
PROJECT TOTAL
11,532,221 118,225,002 129,757,223
$ 359,513,804
$ 11,532,221
2,625,486
-
$ 127,272,110
$ -
$ 542,824,078
$ 118,225,002
$ 42,960,002
$ -
$ 1,072,569,994
$ 129,757,223
$ 371,046,025 2,625,486 $ 127,272,110 $ 661,049,080 $ 42,960,002 $ 1,202,327,217
5 of 5 550MW Super PC Cost Estimate - Greenfield.xls
F
HEAT BALANCE DIAGRAMS
F-1
LEGEND
M- Mass Flow, pph
T- Temperature, F
P- Pressure, psia
H- Enthalpy, Btu/lb
SYNGAS
M
Fuel Gas
Heater
405 T
N
COMP
TURB
COMPONENTS IN THE HRSG BELOW DO NOT REPRESENT THE
ACTUAL LAYOUT OF THE HRSG. ARRANGEMENT IS SCHEMATIC ONLY.
C
K
D
M
G
A
D C B
G
B A
279 T
FROM HRSG 2
FROM HRSG 2
716,664
1,030
1,903
1,497
M
T
P
H
1,652,990
1,026
575
1,533
P
H
M
T
HPST IPST
672,307
724
634
1,363
P
H
M
T
TO HRSG 2
E
Stream
A
B
C
D
E
F
G
L
IGCC Process Requirements
SRU and TGTU LP Steam Production
Hg Removal Preheater & Diluent N
2
Heater
Syngas Cooler and SRU IP Steam Production
TGTU HP Steam Requirements
Selexol and ASU IP Steam
ASU, Selexol, Sour Water Reboiler Water
Consumption
HCN Hydrolysis Preheater and Saturator Pump
Around Heater
Flow Out (lb/hr)
1,223
160,767
494,039
1,272
58,872
26,370
312,172
4,381
630
109
655
M
T
P
H
Process Duty
(MMBtu/hr)
1.11
H
14.25
404.1
2.05
52.1
25.4
97.4
358,332
1,038
2,001
1,499
P
H
M
T
826,495
1,031
588
1,535
P
H
M
T
J
LPST
I
1630276 M
90 T
1.42 in HgA
1559 MMBTU/hr
L
F
FROM HRSG 2
H
K
Aux Cooling Water Return
70,866,496
75
M
T
COOLING TOWER 2267 MMBTU/hr
70,866,496
65
Aux Cooling Water Supply
M
T
BFP
E F
GSC
I
ST LEAKS
N
TO HRSG 2
Syngas Condensing
& GTG Air Cooling
205 MMBTU/hr
1,800,033
213
182
M
T
H
PERFORMANCE SUMMARY
DRY BULB TEMP, °F
WET BULB TEMP, °F
RELATIVE HUMIDITY, %
ELEVATION, FT
GTG1 OUTPUT, kW
GTG2 OUTPUT, kW
STG OUTPUT, kW
GROSS PLANT OUTPUT, kW
POWER BLOCK AUX LOAD, kW
GASIFICATION BLOCK AUX POWER, kW
TOTAL AUX POWER, kW
GTG1 HEAT RATE, BTU/kWh (HHV)
GTG1 HEAT CONS, MMBTU/h (HHV)
GTG2 HEAT RATE, BTU/kWh (HHV)
GTG2 HEAT CONS, MMBTU/h (HHV)
TOTAL COAL HEAT INPUT, MMBtu/h (HHV)
NET PLANT OUTPUT, kW
NET PLANT HEAT RATE, BTU/kWh (HHV)
NET CYCLE EFFICIENCY
EPRI / CPS Energy
2x1 7FB IGCC - Shell Gasification Process
BMCD PROJECT 42127
DATE
7/21/2006
HEAT BALANCE DIAGRAM
100% PRB @ 43DB
DESIGNED: J. SCHWARZ
MODEL REV.
0
43
40
78%
100
9,369
2,174
9,369
2,174
5,444
599,224
9,085
38%
232,009
232,009
272,581
736,599
22,465
114,911
137,376
LEGEND
M- Mass Flow, pph
T- Temperature, F
P- Pressure, psia
H- Enthalpy, Btu/lb
SYNGAS
M
Fuel Gas
Heater
405 T
N
COMP
TURB
COMPONENTS IN THE HRSG BELOW DO NOT REPRESENT THE
ACTUAL LAYOUT OF THE HRSG. ARRANGEMENT IS SCHEMATIC ONLY.
C
K
D
M
G
A
D C B
G
B A
245 T
FROM HRSG 2
FROM HRSG 2
710,964
1,053
1,904
1,511
M
T
P
H
1,562,644
1,053
550
1,548
P
H
M
T
HPST IPST
667,745
732
607
1,369
P
H
M
T
TO HRSG 2
E
Stream
A
B
C
D
E
F
G
L
IGCC Process Requirements
SRU and TGTU LP Steam Production
Hg Removal Preheater & Diluent N
2
Heater
Syngas Cooler and SRU IP Steam Production
TGTU HP Steam Requirements
Selexol and ASU IP Steam
ASU, Selexol, Sour Water Reboiler Water
Consumption
HCN Hydrolysis Preheater and Saturator Pump
Around Heater
Flow Out (lb/hr)
1,118
151,738
452,803
1,192
55,337
26,370
296,062
1,118
653
83
655
M
T
P
H
Process Duty
(MMBtu/hr)
1.04
H
13.35
378.2
1.91
50.1
25.4
91.3
355,475
1,060
2,003
1,513
P
H
M
T
781,322
1,058
562
1,551
P
H
M
T
J
LPST
I
1536088 M
104 T
2.18 in HgA
1471 MMBTU/hr
L
F
FROM HRSG 2
H
K
Aux Cooling Water Return
70,866,496
75
M
T
COOLING TOWER 2130 MMBTU/hr
70,866,496
65
Aux Cooling Water Supply
M
T
BFP
E F
GSC
I
ST LEAKS
N
TO HRSG 2
Syngas Condensing
& GTG Air Cooling
91 MMBTU/hr
1,698,067
165
133
M
T
H
PERFORMANCE SUMMARY
DRY BULB TEMP, °F
WET BULB TEMP, °F
RELATIVE HUMIDITY, %
ELEVATION, FT
GTG1 OUTPUT, kW
GTG2 OUTPUT, kW
STG OUTPUT, kW
GROSS PLANT OUTPUT, kW
POWER BLOCK AUX LOAD, kW
GASIFICATION BLOCK AUX POWER, kW
TOTAL AUX POWER, kW
GTG1 HEAT RATE, BTU/kWh (HHV)
GTG1 HEAT CONS, MMBTU/h (HHV)
GTG2 HEAT RATE, BTU/kWh (HHV)
GTG2 HEAT CONS, MMBTU/h (HHV)
TOTAL COAL HEAT INPUT, MMBtu/h (HHV)
NET PLANT OUTPUT, kW
NET PLANT HEAT RATE, BTU/kWh (HHV)
NET CYCLE EFFICIENCY
EPRI / CPS Energy
2x1 7FB IGCC - Shell Gasification Process
BMCD PROJECT 42127
DATE
7/21/2006
HEAT BALANCE DIAGRAM
100% PRB @ 73DB
DESIGNED: J. SCHWARZ
MODEL REV.
0
73
69
82%
100
9,057
2,037
9,057
2,037
5,100
553,059
9,222
37%
224,869
224,869
260,134
709,872
21,952
134,861
156,813
LEGEND
M- Mass Flow, pph
T- Temperature, F
P- Pressure, psia
H- Enthalpy, Btu/lb
SYNGAS
M
Fuel Gas
Heater
405 T
N
COMP
TURB
COMPONENTS IN THE HRSG BELOW DO NOT REPRESENT THE
ACTUAL LAYOUT OF THE HRSG. ARRANGEMENT IS SCHEMATIC ONLY.
C
K
D
M
G
A
D C B
G
B A
247 T
FROM HRSG 2
FROM HRSG 2
691,351
1,050
1,853
1,511
M
T
P
H
1,531,861
1,052
539
1,548
P
H
M
T
HPST IPST
649,198
731
594
1,369
P
H
M
T
TO HRSG 2
E
Stream
A
B
C
D
E
F
G
L
IGCC Process Requirements
SRU and TGTU LP Steam Production
Hg Removal Preheater & Diluent N
2
Heater
Syngas Cooler and SRU IP Steam Production
TGTU HP Steam Requirements
Selexol and ASU IP Steam
ASU, Selexol, Sour Water Reboiler Water
Consumption
HCN Hydrolysis Preheater and Saturator Pump
Around Heater
Flow Out (lb/hr)
1,087
146,920
438,696
1,154
53,707
26,370
291,102
1,087
649
82
650
M
T
P
H
Process Duty
(MMBtu/hr)
1.01
H
12.93
366.3
1.86
48.7
25.4
88.4
345,697
1,057
1,948
1,512
P
H
M
T
765,930
1,056
551
1,550
P
H
M
T
J
LPST
I
1505624 M
109 T
2.53 in HgA
1448 MMBTU/hr
L
F
FROM HRSG 2
H
K
Aux Cooling Water Return
70,866,496
75
M
T
COOLING TOWER 2156 MMBTU/hr
70,866,496
65
Aux Cooling Water Supply
M
T
BFP
E F
GSC
I
ST LEAKS
N
TO HRSG 2
Syngas Condensing
& GTG Air Cooling
88 MMBTU/hr
1,663,191
169
137
M
T
H
PERFORMANCE SUMMARY
DRY BULB TEMP, °F
WET BULB TEMP, °F
RELATIVE HUMIDITY, %
ELEVATION, FT
GTG1 OUTPUT, kW
GTG2 OUTPUT, kW
STG OUTPUT, kW
GROSS PLANT OUTPUT, kW
POWER BLOCK AUX LOAD, kW
GASIFICATION BLOCK AUX POWER, kW
TOTAL AUX POWER, kW
GTG1 HEAT RATE, BTU/kWh (HHV)
GTG1 HEAT CONS, MMBTU/h (HHV)
GTG2 HEAT RATE, BTU/kWh (HHV)
GTG2 HEAT CONS, MMBTU/h (HHV)
TOTAL COAL HEAT INPUT, MMBtu/h (HHV)
NET PLANT OUTPUT, kW
NET PLANT HEAT RATE, BTU/kWh (HHV)
NET CYCLE EFFICIENCY
EPRI / CPS Energy
2x1 7FB IGCC - Shell Gasification Process
BMCD PROJECT 42127
DATE
7/21/2006
HEAT BALANCE DIAGRAM
100% PRB @ 93DB
DESIGNED: J. SCHWARZ
MODEL REV.
0
93
77
49%
100
9,149
1,972
9,149
1,972
4,940
528,398
9,348
37%
215,584
215,584
250,374
681,542
21,763
131,381
153,144
LEGEND
M- Mass Flow, pph
T- Temperature, F
P- Pressure, psia
H- Enthalpy, Btu/lb
SYNGAS
M
Fuel Gas
Heater
405 T
N
COMP
TURB
COMPONENTS IN THE HRSG BELOW DO NOT REPRESENT THE
ACTUAL LAYOUT OF THE HRSG. ARRANGEMENT IS SCHEMATIC ONLY.
C
K
D
M
G
A
D C B
G
B A
267 T
FROM HRSG 2
FROM HRSG 2
701,666
1,031
1,903
1,497
M
T
P
H
1,632,862
1,030
570
1,535
P
H
M
T
HPST IPST
657,519
721
627
1,362
P
H
M
T
TO HRSG 2
E
Stream
A
B
C
D
E
F
G
L
IGCC Process Requirements
SRU and TGTU LP Steam Production
Hg Removal Preheater & Diluent N
2
Heater
Syngas Cooler and SRU IP Steam Production
TGTU HP Steam Requirements
Selexol and ASU IP Steam
ASU, Selexol, Sour Water Reboiler Water
Consumption
HCN Hydrolysis Preheater and Saturator Pump
Around Heater
Flow Out (lb/hr)
6,007
161,899
501,323
4,175
95,654
26,370
311,661
27,822
493
86
652
M
T
P
H
Process Duty
(MMBtu/hr)
5.52
H
14.25
417.9
6.71
86.0
25.4
96.5
350,827
1,038
2,002
1,499
P
H
M
T
816,431
1,034
582
1,537
P
H
M
T
J
LPST
I
1624996 M
89 T
1.37 in HgA
1556 MMBTU/hr
L
F
FROM HRSG 2
H
K
Aux Cooling Water Return
70,866,496
75
M
T
COOLING TOWER 2186 MMBTU/hr
70,866,496
65
Aux Cooling Water Supply
M
T
BFP
E F
GSC
I
ST LEAKS
N
TO HRSG 2
Syngas Condensing
& GTG Air Cooling
196 MMBTU/hr
1,848,329
208
177
M
T
H
PERFORMANCE SUMMARY
DRY BULB TEMP, °F
WET BULB TEMP, °F
RELATIVE HUMIDITY, %
ELEVATION, FT
GTG1 OUTPUT, kW
GTG2 OUTPUT, kW
STG OUTPUT, kW
GROSS PLANT OUTPUT, kW
POWER BLOCK AUX LOAD, kW
GASIFICATION BLOCK AUX POWER, kW
TOTAL AUX POWER, kW
GTG1 HEAT RATE, BTU/kWh (HHV)
GTG1 HEAT CONS, MMBTU/h (HHV)
GTG2 HEAT RATE, BTU/kWh (HHV)
GTG2 HEAT CONS, MMBTU/h (HHV)
TOTAL COAL HEAT INPUT, MMBtu/h (HHV)
NET PLANT OUTPUT, kW
NET PLANT HEAT RATE, BTU/kWh (HHV)
NET CYCLE EFFICIENCY
EPRI / CPS Energy
2x1 7FB IGCC - Shell Gasification Process
BMCD PROJECT 42127
DATE
7/21/2006
HEAT BALANCE DIAGRAM
50% PRB 50% PET COKE @ 43DB
DESIGNED: J. SCHWARZ
MODEL REV.
0
43
40
78%
100
9,319
2,162
9,319
2,162
5,341
596,993
8,946
38%
232,018
232,018
270,141
734,177
22,026
115,159
137,185
LEGEND
M- Mass Flow, pph
T- Temperature, F
P- Pressure, psia
H- Enthalpy, Btu/lb
SYNGAS
M
Fuel Gas
Heater
405 T
N
COMP
TURB
COMPONENTS IN THE HRSG BELOW DO NOT REPRESENT THE
ACTUAL LAYOUT OF THE HRSG. ARRANGEMENT IS SCHEMATIC ONLY.
C
K
D
M
G
A
D C B
G
B A
237 T
FROM HRSG 2
FROM HRSG 2
698,492
1,053
1,904
1,511
M
T
P
H
1,552,656
1,057
550
1,550
P
H
M
T
HPST IPST
655,324
731
605
1,369
P
H
M
T
TO HRSG 2
E
Stream
A
B
C
D
E
F
G
L
IGCC Process Requirements
SRU and TGTU LP Steam Production
Hg Removal Preheater & Diluent N
2
Heater
Syngas Cooler and SRU IP Steam Production
TGTU HP Steam Requirements
Selexol and ASU IP Steam
ASU, Selexol, Sour Water Reboiler Water
Consumption
HCN Hydrolysis Preheater and Saturator Pump
Around Heater
Flow Out (lb/hr)
5,512
152,890
462,743
3,921
90,058
26,370
296,225
18,499
537
83
652
M
T
P
H
Process Duty
(MMBtu/hr)
5.18
H
13.38
392.5
6.28
81.4
25.4
90.7
349,246
1,061
2,004
1,513
P
H
M
T
776,328
1,061
561
1,552
P
H
M
T
J
LPST
I
1531101 M
104 T
2.18 in HgA
1467 MMBTU/hr
L
F
FROM HRSG 2
H
K
Aux Cooling Water Return
70,866,496
75
M
T
COOLING TOWER 2164 MMBTU/hr
70,866,496
65
Aux Cooling Water Supply
M
T
BFP
E F
GSC
I
ST LEAKS
N
TO HRSG 2
Syngas Condensing
& GTG Air Cooling
83 MMBTU/hr
1,741,828
163
131
M
T
H
PERFORMANCE SUMMARY
DRY BULB TEMP, °F
WET BULB TEMP, °F
RELATIVE HUMIDITY, %
ELEVATION, FT
GTG1 OUTPUT, kW
GTG2 OUTPUT, kW
STG OUTPUT, kW
GROSS PLANT OUTPUT, kW
POWER BLOCK AUX LOAD, kW
GASIFICATION BLOCK AUX POWER, kW
TOTAL AUX POWER, kW
GTG1 HEAT RATE, BTU/kWh (HHV)
GTG1 HEAT CONS, MMBTU/h (HHV)
GTG2 HEAT RATE, BTU/kWh (HHV)
GTG2 HEAT CONS, MMBTU/h (HHV)
TOTAL COAL HEAT INPUT, MMBtu/h (HHV)
NET PLANT OUTPUT, kW
NET PLANT HEAT RATE, BTU/kWh (HHV)
NET CYCLE EFFICIENCY
EPRI / CPS Energy
2x1 7FB IGCC - Shell Gasification Process
BMCD PROJECT 42127
DATE
7/21/2006
HEAT BALANCE DIAGRAM
50% PRB 50% PET COKE @ 73DB
DESIGNED: J. SCHWARZ
MODEL REV.
0
73
69
82%
100
8,971
2,030
8,971
2,030
5,016
553,022
9,070
38%
226,335
226,335
258,397
711,067
21,867
136,178
158,045
LEGEND
M- Mass Flow, pph
T- Temperature, F
P- Pressure, psia
H- Enthalpy, Btu/lb
SYNGAS
M
Fuel Gas
Heater
405 T
N
COMP
TURB
COMPONENTS IN THE HRSG BELOW DO NOT REPRESENT THE
ACTUAL LAYOUT OF THE HRSG. ARRANGEMENT IS SCHEMATIC ONLY.
C
K
D
M
G
A
D C B
G
B A
238 T
FROM HRSG 2
FROM HRSG 2
672,327
1,050
1,835
1,511
M
T
P
H
1,527,907
1,052
540
1,548
P
H
M
T
HPST IPST
630,470
733
593
1,371
P
H
M
T
TO HRSG 2
E
Stream
A
B
C
D
E
F
G
L
IGCC Process Requirements
SRU and TGTU LP Steam Production
Hg Removal Preheater & Diluent N
2
Heater
Syngas Cooler and SRU IP Steam Production
TGTU HP Steam Requirements
Selexol and ASU IP Steam
ASU, Selexol, Sour Water Reboiler Water
Consumption
HCN Hydrolysis Preheater and Saturator Pump
Around Heater
Flow Out (lb/hr)
5,355
148,275
449,026
3,802
87,441
26,370
292,901
18,876
527
81
646
M
T
P
H
Process Duty
(MMBtu/hr)
5.03
H
12.98
380.6
6.12
79.1
25.4
87.9
336,158
1,057
1,932
1,513
P
H
M
T
763,953
1,056
551
1,550
P
H
M
T
J
LPST
I
1508008 M
109 T
2.52 in HgA
1450 MMBTU/hr
L
F
FROM HRSG 2
H
K
Aux Cooling Water Return
70,866,496
75
M
T
COOLING TOWER 2195 MMBTU/hr
70,866,496
65
Aux Cooling Water Supply
M
T
BFP
E F
GSC
I
ST LEAKS
N
TO HRSG 2
Syngas Condensing
& GTG Air Cooling
80 MMBTU/hr
1,713,230
166
135
M
T
H
PERFORMANCE SUMMARY
DRY BULB TEMP, °F
WET BULB TEMP, °F
RELATIVE HUMIDITY, %
ELEVATION, FT
GTG1 OUTPUT, kW
GTG2 OUTPUT, kW
STG OUTPUT, kW
GROSS PLANT OUTPUT, kW
POWER BLOCK AUX LOAD, kW
GASIFICATION BLOCK AUX POWER, kW
TOTAL AUX POWER, kW
GTG1 HEAT RATE, BTU/kWh (HHV)
GTG1 HEAT CONS, MMBTU/h (HHV)
GTG2 HEAT RATE, BTU/kWh (HHV)
GTG2 HEAT CONS, MMBTU/h (HHV)
TOTAL COAL HEAT INPUT, MMBtu/h (HHV)
NET PLANT OUTPUT, kW
NET PLANT HEAT RATE, BTU/kWh (HHV)
NET CYCLE EFFICIENCY
EPRI / CPS Energy
2x1 7FB IGCC - Shell Gasification Process
BMCD PROJECT 42127
DATE
7/21/2006
HEAT BALANCE DIAGRAM
50% PRB 50% PET COKE @ 93DB
DESIGNED: J. SCHWARZ
MODEL REV.
0
93
77
49%
100
9,075
1,969
9,075
1,969
4,864
528,165
9,209
37%
216,963
216,963
248,701
682,628
21,649
132,813
154,462
G
O&M COST DETAIL
G-1
IGCC O&M.XLS Rev 3 1/28/05
Operating Assumptions
Greenfield \ Brownfield
Basis Year
Plant Capacity Factor
Hours per Year
Number of Gasifiers
Number of Steam Turbines
Boiler Output, (Net kW Each)
Normal Operation
Gross Gas Turbine Output, kW (Each)
Gross Steam Turbine Output, kW (Each)
Auxiliary Load, %
Margin, %
Net Unit Output, kW
Net Unit Heat Rate, Btu/kWh
Unit Fuel Consumption, MMBtu/hr
Net Facility Output, kW (Avg Ambient Conditions)
Net Facility Heat Rate, Btu/kWh
Net Annual Output, MWh (Total Facility)
Annual Fuel Consumption, MMBtu (Total Facility)
Coal Type
Boiler Technology
Type of Boiler
Type of Feedwater Pump Drive
Type of NOx Control
Type of SO2 Control
Type of Particulate Control
Type of Mercury Control
Cooling Tower Materials of Construction
Type of Sidestream Treatment
Fly Ash Disposal
Slag Disposal
EPRI / CPS Energy
2x1 7FB IGCC
Operations and Maintenance Estimates
BMcD Project: 42127
2x1 7FB IGCC - 100% PRB
Greenfield
2006
85.0%
7446
2
1
250,000
2x1 7FB IGCC - 50% PRB / 50%
Pet Coke
Greenfield
2006
85.0%
7446
2
1
250,000
224,869
260,134
22.09%
0.00%
553,072
9,220
5,100
226,335
258,397
22.23%
0.00%
553,022
9,069
5,015
553,072
9,220
553,022
9,069
4,118,174
37,971,622
4,117,804
37,343,289
EPRI UDBS PRB 50% PRB / 50% Pet Coke (by wt%)
IGCC
Subcritical
Motor
N2 Injection
Selexol
N/A
IGCC
Subcritical
Motor
N2 Injection
Selexol
N/A
Carbon Bed
Fiberglass
None
Landfill
Landfill
Carbon Bed
Fiberglass
None
Landfill
Landfill
Page 1 of 6 BURNS MCDONNELL
IGCC O&M.XLS Rev 3 1/28/05
Operating Assumptions
Fixed O&M
Labor
# of People
Average Salary
Total Labor
Office & Admin
Other Fixed O&M
Employee Expenses \ Training
Contract Labor
Environmental Expenses
Safety Expenses
Buildings, Grounds, and Painting
Other Supplies & Expenses
Communication
Control Room \ Lab Expenses
Annual Steam Turbine Inspections
Annual Gasifier Inspections
Annual Syngas Cooling and Treatment Inspections
Start-up power demand charge
$/kW-Mo kW
Water supply demand charge
$/acre-ft acre-ft
Water discharge demand charge
$/acre-ft acre-ft
Standby Power Energy Costs
$/kWh kWh
Standby Power Service Fee
$/Month
Months
Property Taxes & Insurance
Total Fixed O&M Annual Cost
EPRI / CPS Energy
2x1 7FB IGCC
Operations and Maintenance Estimates
BMcD Project: 42127
2x1 7FB IGCC - 100% PRB
2x1 7FB IGCC - 50% PRB / 50%
Pet Coke
126 People
$93,934/ Person
$ 11,835,700
126 People
$93,934/ Person
$ 11,835,700
$ 118,400
$ 1,479,500
$ 118,400
$ 1,479,500
$ 100,000
$ 100,000
$ 200,000
$ 100,000
$ 100,000
$ 200,000
$ -
8,000
$ -
8,000
$ $ -
6,832
$ -
7,172
$ -
1,581 1,632
$ 98,600 $ 98,600
3,942,000
$ -
3,942,000
$ -
12
By Owner
$ 13,932,200
12
By Owner
Page 2 of 6 BURNS MCDONNELL
IGCC O&M.XLS Rev 3 1/28/05
EPRI / CPS Energy
2x1 7FB IGCC
Operations and Maintenance Estimates
BMcD Project: 42127
2x1 7FB IGCC - 100% PRB
2x1 7FB IGCC - 50% PRB / 50%
Pet Coke Operating Assumptions
Emissions Allowance Costs - Included in Variable O&M
Emissions Rates
NOx , lb/MMBtu
SOx , lb/MMBtu
CO2, lb/MMBtu
HG, lb/MMBtu
Emissions - TPY
NOx , TPY
SOx , TPY
CO2, TPY
HG, lb/year
Emissions Allowance Costs
NOx Allowance, $/ton-yr
SOx Allowance, $/ton-yr
CO2 Allowance, $/ton-yr
HG Allowance, $/lb-yr
Total Emissions Allowance Costs, $/yr
NOx Allowance Cost
SOx Allowance Cost
CO2 Allowance Cost
HG Allowance Cost
Total Annual Emissions Allowance Costs
0.063
0.019
215
7.769E-07
0.062
0.023
213
4.962E-07
1,196
361
4,086,517
29.50
1,158
429
3,980,767
18.53
$3,000
$1,000
$0
$20,000
$3,000
$1,000
$0
$20,000
$ 3,588,300
$ 360,700
$ -
$ 590,000
$ 4,539,000
$ 3,472,900
$ 429,400
$ -
$ 370,600
Page 3 of 6 BURNS MCDONNELL
IGCC O&M.XLS Rev 3 1/28/05
Operating Assumptions
Major Maintenance Costs - Included in Variable O&M
Steam Turbine / Generator Overhaul
Operating Hours
$/Turbine Hour
HRSG Major Replacements
$/Boiler - Yr
# of Boilers
Gasifier Major Replacements
$/Replacement
Replacement Interval, years
Candle Filter Major Replacements
$/Replacement
Replacement Interval, years
Gas Turbine Major Replacements
$/Replacement
$/Gas Turbine Hour
Syngas Treatment Major Replacements
$/Replacement
Replacement Interval, years
Air Separation Unit
$/Replacement
Replacement Interval, years
Mercury Carbon Bed Replacements
$/Replacement
Replacement Interval, years
COS Hydrolysis Catalyst
$/Catalyst
Catalyst Life, years
HCN Hydrolysis Catalyst
$/Catalyst
Catalyst Life, years
Shift Catalyst
$/Catalyst
Catalyst Life, years
Demin Water Treatment System Replacements
Total Annual Major Maintenance Costs
EPRI / CPS Energy
2x1 7FB IGCC
Operations and Maintenance Estimates
BMcD Project: 42127
2x1 7FB IGCC - 100% PRB
2x1 7FB IGCC - 50% PRB / 50%
Pet Coke
$ 260,400
7446
$ 35
$ 260,400
7446
$ 35
$ 200,000
$100,000
2
$ 200,000
$100,000
2
$ 885,800
$885,765
1
$ 765,900
$765,893
1
$ 300,000
$1,500,000
5
$ 300,000
$1,500,000
5
$ 8,148,685
$885,765
547
$ 8,148,685
$765,893
547
$ 375,000
$375,000
1
$ 395,000
$395,000
1
$ 275,000
$275,000
1
$ 275,000
$275,000
1
$ 530,300
$1,060,666
2
$ 530,300
$1,060,666
2
$ 320,000
$960,000
3
$ 320,000
$960,000
3
$ 320,000
$960,000
3
$ 320,000
$960,000
3
$ -
$0
3
$ -
$0
3
$ 3,600 $ 3,600
$ 11,618,785
Page 4 of 6 BURNS MCDONNELL
IGCC O&M.XLS Rev 3 1/28/05
EPRI / CPS Energy
2x1 7FB IGCC
Operations and Maintenance Estimates
BMcD Project: 42127
2x1 7FB IGCC - 100% PRB
2x1 7FB IGCC - 50% PRB / 50%
Pet Coke Operating Assumptions
Other Variable O&M
Water Consumption, MMGal/yr
Raw Water Makeup, MMGal/yr
Raw Water Makeup Treatment, MMGal/yr
Zero Liquid Discharge Treatment, MMGal/yr
Potable Water, MMGal/yr
Wastewater Discharge, MMGal/yr
Cooling Tower Makeup, MMGal/yr
Demin Water Makeup Treatment, MMGal/yr
Boiler Treatment Makeup Treatment, MMGal/yr
Water Consumable \ Treatment Costs, $/kGal
Raw Water, $/kGal
Raw Water Makeup Treatment, $/kGal
Zero Liquid Discharge Treatment, $/kGal
Potable Water, $/kGal
Wastewater Discharge, $/kGal
Cooling Tower Makeup, $/kGal
Demin Water Treatment, $/kGal
Boiler Treatment Chemicals, $/kGal
Total Water Related Costs
Raw Water
Raw Water Make-up Treatment
Zero Liquid Discharge Treatment Chemicals
Potable Water
Water Discharge
Cooling Tower Treatment Chemicals
Demin Water Treatment
Boiler Treatment Chemicals
Maintenance & Consumables (lube oil, nitrogen, hydrogen, etc.)
ZLD System General Maintenance
Membrane Replacements, $/yr
General Maintenance, $/yr
Water Treatment System General Maintenance, $/yr
Cooling Tower System General Maintenance, $/unit-yr
Other Variable O&M (Electronics, Controls, BOP Electrical, Steam Generators, Misc.)
2,226
2,226
0
1
515.11
2,100
38
20
$0.04
$0.01
$0.00
$1.00
$0.05
$0.55
$1.05
$7.4500
$ 92,000
$ 11,100
$ -
$ 1,500
$ 25,800
$ 1,159,300
$ 39,700
$ 149,700
$ 96,500
$ 11,700
$ -
$ 1,500
$ 26,600
$ 1,198,000
$ 39,700
$ 149,700
$0.04
$0.01
$0.00
$1.00
$0.05
$0.55
$1.05
$7.4500
2,337
2,337
0
1
531.64
2,170
38
20
$0
$60,100
$45,100
$5,192,238
$0
$60,100
$44,800
$5,250,717
Page 5 of 6 BURNS MCDONNELL
IGCC O&M.XLS Rev 3 1/28/05
Operating Assumptions
Other Variable O&M - (Cont.)
Consumable Consumption \ Disposal Rates
SCR Ammonia (Anhydrous), TPY
Sulfur, TPY
Fly Ash / Slag Sales, TPY
Fly Ash / Slag Disposal, TPY
Consumable \ Disposal Unit Costs
SCR Ammonia (Anhydrous), $/ton
Sulfur, $/ton
Fly Ash / Slag Sales, $/ton
Fly Ash / Slag Disposal, $/ton
Total Consumable \ Disposal Costs
SCR Ammonia (Anhydrous)
Sulfur Sales / Disposal
Fly Ash / Slag Sales
Fly Ash / Slag Disposal
Total Other Variable O&M
Total Fixed O&M Cost
$/year
$/kW-yr
Total Variable O&M Cost
$/year
$/MWh
EPRI / CPS Energy
2x1 7FB IGCC
Operations and Maintenance Estimates
BMcD Project: 42127
2x1 7FB IGCC - 100% PRB
2x1 7FB IGCC - 50% PRB / 50%
Pet Coke
0
8,390
0
138,213
$657.89
$0.00
$0.00
$11.29
$ -
$ -
$ -
$ 1,560,200
$ -
$ -
$ -
$ 642,100
$ 8,336,738
0
58,728
0
56,884
$657.89
$0.00
$0.00
$11.29
$ 13,932,200
$ 25.19
$ 13,932,200
$ 25.19
$ 24,494,523
$ 5.95
$ 23,313,202
$ 5.66
Page 6 of 6 BURNS MCDONNELL
PC Unit O&M_r1 (working).XLS Rev 3 1/28/05
Operating Assumptions
Greenfield \ Brownfield
Basis Year
Plant Capacity Factor
Hours per Year
Number of Boilers
Number of Steam Turbines
Boiler Output, (Net kW Each)
Steam Turbine Output, (Net kW Each)
Net Facility Output, kW
Normal Operation
Gross Steam Turbine Output, kW (Each)
Gross Steam Turbine Heat Rate
Auxiliary Load, %
Margin, %
Net Unit Output, kW
Net Unit Heat Rate, Btu/kWh
Unit Fuel Consumption, MMBtu/hr
Net Facility Output, kW (Avg Ambient Conditions)
Net Facility Heat Rate, Btu/kWh
Net Annual Output, MWh (Total Facility)
Annual Fuel Consumption, MMBtu (Total Facility)
Coal Type
Boiler Technology
Type of Boiler
Type of Feedwater Pump Drive
Type of NOx Control
Type of SO2 Control
Type of Particulate Control
Type of Mercury Control
Cooling Tower Materials of Construction
Type of Sidestream Treatment
Fly Ash Disposal
Gypsum Disposal
Bottom Ash Disposal
EPRI / CPS Energy
550 MW Supercritical PC - 100% PRB
Operations and Maintenance Estimates
BMcD Project: 42127
550 PC-Wet Tower / Wet Scrubber - Greenfield
Greenfield
2006
85.0%
7446
550,000
550,000
1
1
550,000
614,525
6,986
10.50%
0.00%
550,000
9,149
5,032
550,000
9,149
4,095,300
37,468,109
EPRI UDBS PRB
Pulverized Coal
Supercritical
Motor
SCR
Wet
Fabric Filter
Fabric Filter / Wet Scrubber
Fiberglass
None
Landfill
Landfill
Landfill
Page 1 of 5 BURNS MCDONNELL
PC Unit O&M_r1 (working).XLS Rev 3 1/28/05
Operating Assumptions
Fixed O&M
Labor
# of People
Average Salary
Total Labor
Office & Admin
Other Fixed O&M
Employee Expenses \ Training
Contract Labor
Environmental Expenses
Safety Expenses
Buildings, Grounds, and Painting
Other Supplies & Expenses
Communication
Control Room \ Lab Expenses
Annual Steam Turbine Inspections
Annual Boiler Inspections
Annual APC Inspections
Start-up power demand charge
$/kW-Mo kW
Water supply demand charge
$/acre-ft acre-ft
Water discharge demand charge
$/acre-ft acre-ft
Standby Power Energy Costs
$/kWh kWh
Standby Power Service Fee
$/Month
Months
Property Taxes & Insurance
Total Fixed O&M Annual Cost
EPRI / CPS Energy
550 MW Supercritical PC - 100% PRB
Operations and Maintenance Estimates
BMcD Project: 42127
550 PC-Wet Tower / Wet Scrubber - Greenfield
103 People
$94,056/ Person
$ 9,687,800
$ 96,900
$ 1,211,000
$ 100,000
$ 80,000
$ 100,000
$ -
-
64,200
$ -
-
7,541
$ -
-
1,632
$ 98,600
0.025
3,942,000
$ -
-
12
By Owner
Page 2 of 5 BURNS MCDONNELL
PC Unit O&M_r1 (working).XLS Rev 3 1/28/05
EPRI / CPS Energy
550 MW Supercritical PC - 100% PRB
Operations and Maintenance Estimates
BMcD Project: 42127
Operating Assumptions
Emissions Allowance Costs - Included in Variable O&M
Emissions Rates
NOx , lb/MMBtu
SOx , lb/MMBtu
CO2, lb/MMBtu
HG, lb/MMBtu
Emissions - TPY
NOx , TPY
SOx , TPY
CO2, TPY
HG, lb/year
Emissions Allowance Costs
NOx Allowance, $/ton-yr
SOx Allowance, $/ton-yr
CO2 Allowance, $/ton-yr
HG Allowance, $/lb-yr
Total Emissions Allowance Costs, $/yr
NOx Allowance Cost
SOx Allowance Cost
CO2 Allowance Cost
HG Allowance Cost
Total Annual Emissions Allowance Costs
Major Maintenance Costs - Included in Variable O&M
Steam Turbine / Generator Overhaul
Operating Hours
$/Turbine Hour
Steam Generator Major Replacements
$/Boiler - Yr
# of Boilers
Baghouse Bag Replacement
$/Replacement
Replacement Interval, years
SCR Catalyst Replacement
$/Catalyst
Catalyst Life, years
Demin Water Treatment System Replacements
Total Annual Major Maintenance Costs
550 PC-Wet Tower / Wet Scrubber - Greenfield
0.050
0.060
213.5
2.315E-06
937
1,128
3,998,878
86.73
$3,000
$1,000
$0
$20,000
$ 2,810,100
$ 1,127,900
$ -
$ 1,734,700
$ 339,200
7446
$ 46
$ 893,900
$893,900
1
$ 253,400
$1,266,900
5
$ 312,000
$936,100
3
$ 4,300
Page 3 of 5 BURNS MCDONNELL
PC Unit O&M_r1 (working).XLS Rev 3 1/28/05
EPRI / CPS Energy
550 MW Supercritical PC - 100% PRB
Operations and Maintenance Estimates
BMcD Project: 42127
Operating Assumptions
Other Variable O&M
Water Consumption, MMGal/yr
Raw Water Makeup, MMGal/yr
Raw Water Makeup Treatment, MMGal/yr
Zero Liquid Discharge Treatment, MMGal/yr
Potable Water, MMGal/yr
Wastewater Discharge, MMGal/yr
Cooling Tower Makeup, MMGal/yr
Demin Water Makeup Treatment, MMGal/yr
Boiler Treatment Makeup Treatment, MMGal/yr
Water Consumable \ Treatment Costs, $/kGal
Raw Water, $/kGal
Raw Water Makeup Treatment, $/kGal
Zero Liquid Discharge Treatment, $/kGal
Potable Water, $/kGal
Wastewater Discharge, $/kGal
Cooling Tower Makeup, $/kGal
Demin Water Treatment, $/kGal
Boiler Treatment Chemicals, $/kGal
Total Water Related Costs
Raw Water
Raw Water Make-up Treatment
Zero Liquid Discharge Treatment Chemicals
Potable Water
Water Discharge
Cooling Tower Treatment Chemicals
Demin Water Treatment
Boiler Treatment Chemicals
Maintenance & Consumables (lube oil, nitrogen, hydrogen, etc.)
ZLD System General Maintenance
Membrane Replacements, $/yr
General Maintenance, $/yr
SCR System General Maintenance
General Maintenance, $./unit-yr
Scrubber System General Maintenance
Absorber, Dewatering & Accessories, $/unit-yr
Limestone Preparation, $/yr
Water Treatment System General Maintenance, $/yr
Cooling Tower System General Maintenance, $/unit-yr
Other Variable O&M (Electronics, Controls, BOP Electrical, Steam Generators, Misc.)
550 PC-Wet Tower / Wet Scrubber - Greenfield
$ 101,500
$ 12,300
$ -
$ 1,500
$ 26,600
$ 1,393,400
$ 63,600
$ 160,600
$0.041
$0.005
$0.000
$1.000
$0.050
$0.642
$1.050
$3.730
2,457
2,457
0
1
532
2,170
61
43
$0
$64,200
$120,700
$342,400
$59,800
$47,700
$5,000,000
Page 4 of 5 BURNS MCDONNELL
PC Unit O&M_r1 (working).XLS Rev 3 1/28/05
Operating Assumptions
Other Variable O&M - (Cont.)
Consumable Consumption \ Disposal Rates
Lime Consumption, TPY
Limestone Consumption, TPY
SCR Ammonia (Anhydrous), TPY
Halogenated Carbon Injection, TPY
Scrubber Sludge (Sales) / Disposal, TPY
Fly Ash Sales, TPY
Fly Ash Disposal, TPY
Bottom Ash (Sales) / Disposal, TPY
Consumable \ Disposal Unit Costs
Lime Consumption, $/ton
Limestone Consumption, $/ton
SCR Ammonia (Anhydrous), $/ton
Halogenated Carbon Injection, $/ton
Scrubber Sludge (Sales) / Disposal, $/ton
Fly Ash Sales, $/ton
Fly Ash Disposal, $/ton
Bottom Ash (Sales) / Disposal, $/ton
Total Consumable \ Disposal Costs
Lime Consumption
Limestone Consumption
SCR Ammonia (Anhydrous)
Halogenated Carbon Injection
Scrubber Sludge (Sales) / Disposal
Fly Ash Sales
Fly Ash Disposal
Bottom Ash (Sales) / Disposal
Total Other Variable O&M
Total Fixed O&M Cost
$/year
$/kW-yr
Total Variable O&M Cost
$/year
$/MWh
EPRI / CPS Energy
550 MW Supercritical PC - 100% PRB
Operations and Maintenance Estimates
BMcD Project: 42127
550 PC-Wet Tower / Wet Scrubber - Greenfield
-
29,150
1,584
0
56,228
0
125,137
31,172
$86.00
$18.00
$658
$1,545
$11.29
$0.00
$11.29
$11.29
$ -
$ 524,700
$ 1,041,800
-
$ 634,700
$ -
$ 1,412,600
$ 351,900
$ 11,374,300
$ 20.68
$ 18,835,500
$ 4.60
Page 5 of 5 BURNS MCDONNELL
H
SYSTEM OF INTERNATIONAL UNITS CONVERSION
TABLE
The heat and material balances included in this report are shown in British (English) units. The following table can be used for conversion to SI units.
British Unit
P, absolute pressure, psia, multiply by 6.895 x10
-3
°F, temperature, (F minus 32) divided by 1.8
H, enthalpy, Btu/lb, multiply H by 2.3260
W, total mass flow, lb/h, multiply W by 0.4536
Heat rate, Btu/kWh, multiply Btu/kWh by 1.0551
Air emissions, lb/MMBtu, multiply by 429.9
Flow, gal/minute, multiply by 0.06309
= MPa (megapascals)
=
°C (Centigrade)
= kJ/kg (kilojoules/kilogram)
= kg/h (kilogram/hour)
= kJ/kWh (kilojoules/kilowatt-hour)
= kg/GJ (kilogram/gigajoule)
= l/s (liters/second)
H-1
Export Control Restrictions
Access to and use of EPRI Intellectual Property is granted with the specific understanding and requirement that responsibility for ensuring full compliance with all applicable U.S. and foreign export laws and regulations is being undertaken by you and your company. This includes an obligation to ensure that any individual receiving access hereunder who is not a U.S. citizen or permanent U.S. resident is permitted access under applicable U.S. and foreign export laws and regulations. In the event you are uncertain whether you or your company may lawfully obtain access to this EPRI Intellectual Property, you acknowledge that it is your obligation to consult with your company’s legal counsel to determine whether this access is lawful. Although EPRI may make available on a case-by-case basis an informal assessment of the applicable U.S. export classification for specific EPRI Intellectual Property, you and your company acknowledge that this assessment is solely for informational purposes and not for reliance purposes. You and your company acknowledge that it is still the obligation of you and your company to make your own assessment of the applicable U.S. export classification and ensure compliance accordingly. You and your company understand and acknowledge your obligations to make a prompt report to EPRI and the appropriate authorities regarding any access to or use of EPRI Intellectual Property hereunder that may be in violation of applicable U.S. or foreign export laws or regulations.
The Electric Power Research Institute (EPRI)
The Electric Power Research Institute (EPRI), with major locations in Palo Alto, California, and Charlotte,
North Carolina, was established in 1973 as an independent, nonprofit center for public interest energy and environmental research. EPRI brings together members, participants, the Institute’s scientists and engineers, and other leading experts to work collaboratively on solutions to the challenges of electric power. These solutions span nearly every area of electricity generation, delivery, and use, including health, safety, and environment. EPRI’s members represent over 90% of the electricity generated in the
United States. International participation represents nearly 15% of EPRI’s total research, development, and demonstration program.
Together…Shaping the Future of Electricity
© 2006 Electric Power Research Institute (EPRI), Inc. All rights reserved. Electric Power Research Institute and EPRI are registered service marks of the Electric Power Research Institute, Inc.
Printed on recycled paper in the United States of America
ELECTRIC POWER RESEARCH INSTITUTE
3420 Hillview Avenue, Palo Alto, California 94304-1338 • PO Box 10412, Palo Alto, California 94303-0813 • USA
800.313.3774 • 650.855.2121 • [email protected] • www.epri.com
1014510
* Your assessment is very important for improving the work of artificial intelligence, which forms the content of this project