advertisement
R3 and R5 installation manual
TM
TM
ROTARY
SWING GATE
OPERATOR
CENTURION SYSTEMS has been manufacturing automatic gate systems since 1987, and is committed to providing reliable, cost effective solutions in the field of access automation.
CENTURION strives to give service and backup second to none. Our engineers are available to give sales support, installation training, and answers to technical or installation problems.
The equipment is installed worldwide and is available through a network of distributors.
CENTURION is an ISO 9001 registered company, continually looking at updating its products in line with world trends to ensure that its products will provide customer satisfaction.
Further information is available on our web site www.centsys.co.za
© CENTURION SYSTEMS (PTY) LTD 2002.
Centurion Systems (Pty) Ltd. reserves the right to make changes to the products described in this manual without notice and without obligation of Centurion Systems (Pty) Ltd. to notify any persons of any such revisions or changes. Additionally, Centurion Systems (Pty) Ltd. makes no representations or warranties with respect to this manual.
No part of this document may be copied, stored in a retrieval system or transmitted in any form or by any means electronic, mechanical, optical or photographic, without the express prior written consent of Centurion Systems (Pty) Ltd.
Page 2
Declaration of Conformity . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
Important Safety Instructions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
Fast Track . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
General Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
Specifications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
Product Identification . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
Required Tools & Equipment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
Site Considerations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
Cabling Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
Operator Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
Pedestal Mount Features . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
Wall Mount Features . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
Locate the Operator Position . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
Where to Position the Operator. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
Mount Gate Bracket . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
Route Cables & Secure Motor Mounting . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
Fasten Gearbox in Position. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
Determine Drive Arm Length . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
Fit the Drive Arm . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24
Set the Connecting Arm . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24
Electrical Set-up . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
Connect all Wiring. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
Set Up the Gate Origin/s. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
Get into Programming Mode . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28
Select either Master or Slave Motor Setup. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
Set the Gate Limits . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
Setting Additional Features (Optional) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30
Controller Features . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32
Set-Up Troubleshooting Guide . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 35
Fault Finding Guide. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37
Procedure to Programme Controller Back to Factory Default Settings . . . . . . . . . . . . . . . . . . . . . . . . 43
Manual Release Mechanism . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 43
Normal Operation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 43
Determine Gate Swing Angle . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 44
Description of Terminal Function . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45
LED Indicator Lights . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 46
CP75 Controller Functions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 47
CP75 Controller Connections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 48
CP75 Trigger Connections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 49
CP84ER5V01 Charger Connection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 50
PSUx Power Connection. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 50
Installation Handover . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 51
Page 3
Manufacturer: Centurion Systems (Pty) Ltd
Unit 13 Northlands Production Park Epsom Avenue
Northriding Randburg Johannesburg 2196
Declares that the product:
Product Name: R3/R5 Swing Gate Operator
Product Options: All variants
Conforms with the following specifications:
Safety: IEC 60355-1:1991 & Am1:1994 & Am2:1999
Emissions:
Immunity:
CISPR 22 CLASS B: RADIATED EMISSIONS - 30MHZ TO 1000MHZ
CISPR 22 CLASS B: CONDUCTED EMISSIONS - 150MHZ TO 30MHZ
IEC 61000-4-2 - ELECTROSTATIC DISCHARGE
IEC 61000-4-3 - RADIATED IMMUNITY - 80MHZ TO 1000MHZ
IEC 61000-4-4 - ELECTRICAL FAST TRANSIENTS / BURST
IEC 61000-4-5 - SURGE IMMUNITY TEST
IEC 61000-4-6 - CONDUCTED IMMUNITY - 150KHZ TO 80MHZ
IEC 61000-4-11 - VOLTAGE DIPS AND INTERRUPTION
Standard to which conformity is declared:
IEC 60355-1:1991 & Am1: 1994 & Am2: 1999
IEC 1000-6-3 & IEC 1000-6-1: Generic Emission and Immunity
Signed at North Riding, South Africa on March 24, 2004
Ian Rozowsky
Research & Development Director
Page 4
ATTENTION
To ensure the safety of people, it is important that you read all the following instructions. Incorrect installation or incorrect use of the product could cause serious harm to people.
The installer, being either professional or DIY, is the last person on the site that can ensure that the operator is safely installed, and that the whole system can be operated safely.
WARNINGS FOR THE INSTALLER
1. CAREFULLY READ AND FOLLOW ALL INSTRUCTIONS before beginning to install the product.
13. Never short circuit the battery and do not try to recharge the batteries with power supply units other than that supplied with the product, or by Centurion Systems.
2. This appliance is not intended for use by persons
(including children) with reduced physical, sensory or mental capabilities, or lack of experience and knowledge, unless they have been given supervision or instruction concerning use of the appliance* by a person responsible for their safety.
3. All installation, repair, and service work to this product must be done by a suitably qualified person.
14. Make sure that the earthing system is correctly constructed, and that all metal parts of the system are suitably earthed.
15. Safety devices must be fitted to the installation to guard against mechanical movement risks such as crushing, dragging and shearing.
16. It is recommended that at least one warning indicator light be fitted to every system.
4. Do not activate your gate opener unless you can see it and can determine that its area of travel is clear of people, pets, or other obstructions.
17. Always fit the warning signs visibly to the inside and outside of the gate.
5. NO ONE MAY CROSS THE PATH OF A MOVING GATE.
Always keep people and objects away from the gate and its area of travel.
18. The installer must explain and demonstrate the manual operation of the gate in case of an emergency, and must hand the User/Warnings guide over to the user.
6. NEVER LET CHILDREN OPERATE OR PLAY WITH THE
GATE CONTROLS, and do not allow children or pets near the gate area.
19. Explain these safety instructions to all persons authorized to use this gate, and be sure that they understand the hazards associated with automated gates.
7. Secure all easily accessed gate opener controls in order to prevent unauthorized use of the gate.
8. Do not in any way modify the components of the automated system.
20. Do not leave packing materials (plastic, polystyrene, etc.) within reach of children as such materials are potential sources of danger.
21. Dispose of all waste products like packaging materials, worn out batteries, etc, according to local regulations.
9. Do not install the equipment in an explosive atmosphere: the presence of inflammable gas or fumes is a serious danger to safety.
22. Always check the obstruction detection system, and safety devices for correct operation.
10. Before attempting any work on the system, cut electrical power and disconnect the batteries.
23. Centurion Systems does not accept any liability caused by improper use of the product, or for use other than that for which the automated system was intended.
11. The mains power supply of the automated system must be fitted with an all-pole switch with contact opening distance of 3mm or greater. Use of a 5A thermal breaker with allpole circuit break is recommended.
12. Make sure that an earth leakage circuit breaker with a threshold of 30mA is fitted upstream of the system.
24. This product was designed and built strictly for the use indicated in this documentation. Any other use, not
* expressly indicated here, could compromise the good condition/operation of the product and/or be a source of danger.
Appliance should be product described in manual
WARNING
MOVING GATE CAN CAUSE
SERIOUS INJURY OR DEATH
KEEP CLEAR. GATE MAY MOVE AT
ANY TIME. DO NOT ALLOW
CHILDREN TO PLAY IN AREA OR
OPERATE GATE .
Page 5
These abbreviated instructions are for the experienced installer who needs a checklist to get a standard installation up and running in the minimum of time.
Detailed installation features and functions are referred to later in this manual.
Step 6
Step 7
Step 8
Step 9
Step 10
Step 11
Step 1
Step 2
Step 3
Step 4
Step 5
Mechanical Setup
Action
Read and understand all safety instructions
Gather required tools and equipment.
Heed necessary site considerations.
Check cabling requirements.
Select appropriate mounting configuration
Mount the gate bracket in position.
Route cables & secure motor mounting
Fasten gearbox in position
Determine drive arm length
Fit drive arm
Set connecting arm
Page 5
Page 12
Page 13
Page 14
Page 15
Page 22
Page 22
Page 23
Page 23
Page 24
Page 24
Page 6
Step 1
Step 2
Step 3
Step 4
Step 5
Step 6
Step 7
Step 8
Step 9
Electrical Setup
Action
Read and understand all safety instructions
Connect all wiring:
Set the gate origin:
Release the manual override and close the gate(s)
Use origin tool and line up marks
Open gate ½ way and unscrew the manual release mechanism.
Get into programming mode:
Remove all power.
Fit the SET link.
Reapply power.
Select master or slave set-up:
Press and hold TEST, release after 1 flash of L1.
Press and hold TEST, release after 1 or 2 flashes
(1=master, 2=slave).
Set the gate limits:
Press and hold TEST until gate is closed, release.
Press and hold TEST until gate is open, release.
Press and release TEST.
(The MASTER gate will close and open to pedestrian. The SLAVE gate will close slightly).
Set additional features: (If required)
Exit programming mode:
Remove the SET link.
Perform installation hand over
Page 5
Page 27
Page 27
Page 28
Page 29
Page 29
Page 30
Page 51
Page 7
The R3 & R5 rotary swing gate systems are designed to open and close swing gates. The CP75 controller is capable of handling both single and double swing gates and offers many features to suit almost any application.
Detailed specifications for the R3 & R5 motors are shown in the figure below and the table alongside.
The unit employs a battery driven DC motor for low duty domestic applications, which provides automatic backup protection in the event of a power failure. The unit can also be fitted with a high duty power supply in addition to the battery to allow for more frequent operation of the gate.
The R3 & R5 operators are fitted with an internal electronic limit switch system, which provides reliable and accurate positioning of the gate. This system allows the operator to smoothly slow the gate down at the fully open or closed positions.
A fail-safe and highly reliable collision sensing system is built into the controller, which will cause the motor to stop while the gate is opening, and stop and reverse when closing if a gate is obstructed in any way. (The collision sensitivity will be reduced during the endpoints of sinusoidal motion).
Gate movement is transmitted to the gate by means of articulated arms. The length of both the drive arm and the connecting arm is easily adjusted to give maximum installation flexibility.
Specifications
Figure 1 Overall Dimensions
Page 8
SPECIFICATION
Input Voltage*
AC Current draw (with C84E Battery Charger)
DC Motor Voltage
DC Current draw (Max)
Maximum solenoid lock current draw
Output shaft rotational speed
Maximum output torque
R3 R5
220V AC ±10% 50Hz 220V AC ±10% 50Hz
120mA 120mA
12V
30A
2A
3.5 rpm
95Nm
12V
35A
2A
2.6 rpm
250Nm
Mass of master motor kit (excluding pedestal or wall bracket)
Mass of slave motor kit (excluding pedestal or wall bracket)
Maximum number of operations per day (Average):
Light industrial, with 10A power pack (PSU)
Domestic, with 1A Battery Charger (CP84E)
Maximum number of continuous operations
Typical time to open/close a gate
(For standard pedestal in recommended position)
14.4kg
12.9kg
100
20
20
10 seconds
15,5kg
14,0kg
250
20
100
13 seconds
No. of operations on a 7A/H battery (should the mains power fail)
Limit switches
Collision sensitivity
±20
Sealed optical counter Sealed optical counter with origin switch with origin switch
Electronic adjustable
±20
Electronic adjustable
Temperature range
Housing protection
Control card (single or double motor)
Corrosion protection (baseplate and arms)
*Other voltages are available
-20º to +50ºC
IP55
CP75
-20º to +50ºC
IP55
CP75
Zinc passivation with Zinc passivation with
lacquer impregnation lacquer impregnation
Page 9
SPECIFICATION (continued)
Maximum gate length & mass for Installation:
Standard Inward Opening or Limited Space Installation
Maximum wind speeds for which the operator will open the gate:
Gate Length:
R3 - Max. Allowable Leaf Mass:
R3: For a 1,8m high gate, 25% coverage#:
R3: For a 1,8m high gate, 100% coverage#:
1,5m
400kg
75km/h
37km/h
2,0m
400kg
54km/h
27km/h
R5 - Max. Allowable Leaf Mass:
R5: For a 1,8m high gate, 25% coverage#:
R5: For a 1,8m high gate, 100% coverage#:
600kg
127km/h
64km/h
Perpendicular or Parallel Wall Mount & Outward Opening
Maximum wind speed for which the operator will open the gate
Gate Length:
R3 - Max. Allowable Leaf Mass:
R3: For a 1,8m high gate, 25% coverage#:
R3: For a 1,8m high gate, 100% coverage#:
1,5m
400kg
50km/h
25km/h
600kg
93km/h
46km/h
2,0m
300kg
34km/h
17km/h
2,5m
320kg
44km/h
22km/h
510kg
74km/h
37km/h
3,0m
225kg
38km/h
19km/h
360kg
64km/h
32km/h
3,5m
160kg
34km/h
17km/h
260kg
56km/h
28km/h
R5 - Max Allowable Leaf Mass:
R5: For a 1,8m high gate, 25% coverage#:
R5: For a 1,8m high gate, 100% coverage#:
600kg
89km/h
44km/h
600kg
63km/h
31km/h
-Electric lock recommended;# -When installed in recommended positions, and collision sensitivity set to LOW.
The actual components supplied may vary depending on the model purchased.
1
1. R3/R5 Linkage Hardware Kit
2. Connecting Arm
3. Drive Arm
4. End Cap
5. Drive Arm Clamp
6. Wedge
7. M10 Washer
8. M12x65 Bolt
9. Clevis Pin
10. Gate Bracket
11. Padlock with key
Figure 2 Linkage Hardware Kit
Page 10
1. Baseplate
2.* Battery (7 A/H)
3. Geared DC Motor
4.* Master Controller (CP75)
5. Slave Interface Card (CP75B)
6.* Controller Enclosure
7. Gearbox
8.* Charger (CP84ER5V01)
9.* Enclosure Uprights
10. Warning Decal
11. Wall Mount Bracket (Version 2)
12. Pedestal (Version 2)
† Pedestal and wall mount installations require different connecting arms. Be sure to use the correct connecting arm for the particular installation type.
* Not fitted to a slave motor in a double leaf gate system.
Figure 3 Product Identification
Page 11
Electric
Drilling
Machine
Spanners
22mm
17mm
13mm
Screw Drivers
3.5mm Flat
Crimping Tool and Pin Lugs Hammer
G-Clamp
Pick
Side Cutters
Pliers / Side
Measuring Tape
10mm Allen Key
9mm Allen Key
Masonry Bits - 6mm
20mm For Wall Mount Bracket
Steel Bits 8,5mm/5,0mm/4,0mm
Hacksaw
Not Normally Required
Spade
Level
Figure 4 Required Tools and Equipment
Plumb Bob
Soldering Iron
Welding
Machine
Page 12
Install the gate operator only if:
1. It will not pose a hazard to the public.
2. There is sufficient clearance to a roadway and/or public thoroughfares.
3. The installation will meet all municipal and/or local authority requirements once completed.
4. The gate mass, length and application is within the operator specifications (see page 9).
5. The gate is in good working order, meaning:
That it moves freely.
Does not move on its own if left in any position.
6. It can be installed to have sufficient clearance between moving parts when opening and closing to reduce the risk of personal injury and entrapment.
7. Pushbuttons or key switches, when required, can be positioned so that the gate is in line of sight of the operator.
General considerations for the installation:
1. Always recommend the fitment of additional safety equipment such as safety edges and safety beams, for additional protection against entrapment or other mechanical risks.
2. Check that there is enough ground clearance below the motor to enable assembly of the drive arm clamps (see page 21).
3. Check that no pipes or electrical cables are in the way of the intended installation.
4. Check that enough space is available for the gate operator with the gate in the required open position.
5. Check for loose sandy soil if installing foundations, as the soil condition may require a larger foundation.
6. Check the strength of the mounting pillar in the case of a wall mount installation.
7. If the swing gate leaf is longer than 2.5m for a wall mount installation, or 3.5m for pedestal-mount installations, ensure that a lock can be fitted.
8. Never fit the operator on the outside of the gate, where the public has access to it. (Follow the instructions for an outward opening swing gate, if required.)
Page 13
Mains isolator switch
To dwelling
LEGEND
1. 220V AC mains cable via mains isolator
2 switch (3 core LNE 0,5mm )*†,
4. Radio receiver cable (3 core 0,5mm
2 multistranded).
Or
Low voltage 16V AC battery charger
2 supply (2 core 1,5mm )†.
2. Intercom cable (n1 + 6 core) to house.
3. Slave motor cable (if required) (3 core
2 2
2,5mm + 3 core 0,5mm multistranded).
5. Pedestrian key switch (if required) (2
2 core 0,5mm multistranded).
6. Infrared beams or safety edge (if
2 required) (3 core 0,5mm multistranded)
7. Intercom cable (n2+2 core 0,5mm
2 multistranded) to gate station.
n1 = number of cores required by intercom.
n2 = number of cores required by intercom.
Figure 5 Cabling Requirements
Page 14
Pedestal Mount Installation
(R3 and R5 operators)
Wall Mount Installation
(R3 operators only)
Figure 6 Basic Installation Options
Pedestal Mount Features
Secure locking with no need for gate end stops.
Can be used on both inward and outward opening gates and on installations where space is limited.
Provides the smoothest gate motion.
Provides very secure locking and high security.
Where a gate leaf width exceeds 3.0m a gate lock is recommended for security.
Installation is independent of the size and strength of gate pillar.
Products required per gate leaf automation:
1 x R3 or R5 operator.
1 x R3 or R5 long linkage hardware kit
(which includes drive arm, connecting arm,
fasteners and bracket).
1 x Pedestal.
Wall Mount Features
Very compact installation.
Requires a pillar strong enough to support the operator and potential loading if the gate is forced.
Where a gate leaf width exceeds 2.5m a gate lock is recommended for optimum security.
The operator may be mounted parallel or perpendicular to the pillar, whichever is best suited for the installation.
Perpendicular installations are recommended since it inherently provides better locking and greater security.
Products required per gate leaf automation:
1 x R3 or R5 operator.
1 x R3 or R5 long linkage hardware kit
(which includes drive arm, connecting arm, fasteners and bracket)
1 x Wall mount bracket.
NOTE: Ensure that you use a LONG connecting arm for this type of installation.
NOTE: Ensure that you use a SHORT connecting arm for this type of installation.
Locate the Operator Position
1. Swing the gate to the required open position and estimate the swing angle of the gate using the angle diagrams in Fig.7 to 11. Alternatively determine the gate swing angle by following the procedure detailed on page 44.
Page 15
PEDESTAL POSITIONING FOR
STANDARD INSTALLATION
(SMOOTHEST MOVEMENT, BEST LOCKING)
E
50mm #
A #
Pedestal
C b
GATE LEAF IN CLOSED POSITION
GA
TE LEAF IN OPEN POSITION
Gate opening angle
0
o
BE SURE TO USE A ‘LONG’ CONNECTING ARM
FOR THIS INSTALLATION TYPE.
120 o
110 o
100 o
90 o
80 o 70 o
60 o b
Gate Opening
Angle (Degrees)
A #
Gate Centre to
Pedestal Centre
B
Hinge Centre to
Pedestal Centre
C
Hinge Centre to
Gate Bracket
E
Pedestal to edge of motor
110
60
70
80
90
100
110
120
350 to 610 (370)
320 to 600 (340)
240 to 530 (260)
200 to 450 (220)
210 to 400 (230)
250 to 440 (330)
280 to 440 (300)
550 to 790 (750)
550 to 790 (750)
550 to 790 (750)
550 to 740 (700)
500 to 740 (700)
450 to 640 (600)
300 to 490 (450)
650 to 700 (700)
650 to 700 (700)
650 to 700 (700)
650 to 700 (700)
600 to 650 (650)
500 to 610 (610)
500 to 570 (570)
Ensure that the gate does not exceed the relevant specifications on page 9.
Recommended values are shown in bold type.
All dimensions shown are indicated in millimetres.
All recommended values will result in gates with similar opening times.
224
191
153
110
122
130
130
© Centurion Systems (Pty) Ltd.
Figure 7 Pedestal Positioning for Standard Installations
Page 16
PEDESTAL POSITIONING FOR
INSTALLATIONS WITH LIMITED SPACE
BE SURE TO USE A ‘LONG’ CONNECTING
ARM FOR THIS INSTALLATION TYPE.
b
Gate Opening
Angle (Degrees)
A #
Gate Centre to
Pedestal Centre
B
Hinge Centre to
Pedestal Centre
C
Hinge Centre to
Gate Bracket
D
Drive Arm
Length
60
70
80
90
100
110
120
190 to 390 (190)
190 to 380 (190)
180 to 370 (180)
170 to 360 (170)
210 to 400 (210)
250 to 440 (250)
280 to 420 (280)
800 to 890 (850)
750 to 890 (850)
750 to 840 (800)
700 to 840 (800)
550 to 840 (800)
450 to 640 (600)
350 to 540 (500)
800 (800) 475 (419)
700 to 750 (750) 500 (444)
650 to 700 (700) 500 (461)
600 to 650 (650) 500 (459)
550 to 610 (610) 500 (464)
500 to 590 (590) 500 (487)
500 to 570 (570) 500 (496)
Ensure that the gate does not exceed the relevant specifications on page 9.
Recommended values are shown in bold type.
All dimensions shown are indicated in millimetres.
All recommended values will result in gates with similar opening times.
E
Edge of Motor to
Pedestal Centre
224
191
153
110
122
130
130
F
Gate Centre to Wall
414
381
333
280
332
380
410
© Centurion Systems (Pty) Ltd.
Figure 8 Pedestal Positioning for Installations with Limited Space
Page 17
PEDESTAL POSITIONING FOR OUTWARD OPENING GATES
It is recommended to fit end stops in the open position of the gate to reduce gate movement when open.
120 o
110 o 100 o 90 o
80 o
70 o
60 o
BE SURE TO USE A ‘LONG’ CONNECTING ARM
FOR THIS INSTALLATION TYPE.
b
Gate Opening
Angle (Degrees)
60
70
80
90
100
110
120
A #
Gate Edge or
Hinge Point to
Shaft Centre
240 to 530 (250)
150 to 440 (160)
100 to 400 (120)
100 to 400 (120)
100 to 400 (120)
100 to 380 (120)
100 to 260 (120)
B
Hinge Centre to
Shaft Centre
600 to 660 (640)
580 to 640 (620)
560 to 660 (580)
520 to 640 (580)
440 to 660 (580)
360 to 620 (400)
340 to 580 (480)
C
Hinge Centre to
Gate Bracket
500 (500)
500(500)
500 to 550 (550)
550 to 600 (600)
550 to 600 (600)
550 to 600 (600)
550 to 650 (650)
Ensure that the gate does not exceed the relevant specifications on page 9.
Recommended values are shown in bold type.
All dimensions shown are indicated in millimetres.
All recommended values will result in gates with similar opening times.
Gate opening angle
0 o
© Centurion Systems (Pty) Ltd.
Figure 9 Pedestal Positioning for Outward Opening Gates
Page 18
PERPENDICULAR WALL MOUNT
FOR INSTALLATIONS WHERE
Wall Mount
Bracket
A
#
C
FOR INSTALLATIONS WHERE THE
GATE OPENS MORE THAN 90 O
Wall Mount
Bracket
A
#
90 o
C
b
GATE LEAF IN CLOSED POSITION
b
GATE LEAF IN CLOSED POSITION
50mm
#
D
50mm
# b
Gate Opening
Angle (Degrees)
60
70
80
90
100
110
120
A #
Gate Centre to
Bracket Centre
140 to 180 (140)
180 to 220 (180)
180 to 260 (180)
170 to 350 (210)
230 to 370 (270)
290 to 400 (330)
340 to 410 (380)
B
Hinge Centre to
Mounting Face
50 to 220 (180)
50 to 220 (180)
50 to 220 (140)
50 to 220 (140)
50 to 220 (180)
50 to 140 (80)
50 to 140 (80)
C
Hinge Centre to
Gate Bracket
(700)
(700)
(700)
(700)
(700)
(700)
(610)
Ensure that the gate does not exceed the relevant specifications on page9.
Recommended values are shown in bold type.
All dimensions shown are indicated in millimetres.
All recommended values will result in gates with similar opening times.
D
Drive Arm
Length
(250)
(300)
(350)
(420)
(480)
(500)
(500)
110
Gate opening angle
0
o
#The minimum value will ensure a clearance of 30mm if the gate is 50mm thick
BE SURE TO USE A ‘SHORT’
CONNECTING ARM FOR THIS
INSTALLATION TYPE.
120 o
110 o
100 o
90 o
80 o
60 o
70 o
© Centurion Systems (Pty) Ltd.
Figure 10 Determining Wall Bracket Position for Perpendicular Wall Mount
Page 19
PARALLEL WALL MOUNT
FOR INSTALLATIONS WHERE
THE GATE OPENS LESS THAN 90 O
FOR INSTALLATIONS WHERE THE
GATE OPENS MORE THAN 90 O b
Gate Opening
Angle (Degrees)
60
70
80
90
100
110
120
A #
Gate Centre to
Bracket Centre
310 to 330 (310)
350 to 370 (350)
350 to 410 (350)
340 to 500 (380)
370 to 500 (400)
390 to 490 (430)
400 to 460 (440)
B
Hinge Centre to
Mounting Face
220 to 380 (340)
220 to 380 (340)
220 to 380 (300)
220 to 380 (300)
220 to 380 (340)
220 to 300 (240)
220 to 300 (240)
C
Hinge Centre to
Gate Bracket
(700)
(700)
(700)
(700)
(700)
(700)
(610)
D
Drive Arm
Length
(250)
(300)
(350)
(420)
(480)
(500)
(500)
Ensure that the gate does not exceed the relevant specifications on page 9.
Recommended values are shown in bold type.
All dimensions shown are indicated in millimetres.
All recommended values will result in gates with similar opening times.
Gate opening angle
0
o
#The minimum value will ensure a clearance of 30mm if the gate is 50mm thick
BE SURE TO USE A ‘SHORT’
CONNECTING ARM FOR THIS
INSTALLATION TYPE.
120 o
110 o
100 o
90 o
80 o 70 o
60 o
© Centurion Systems (Pty) Ltd.
Figure 11 Determining Wall Bracket Position for Parallel Wall Mount
Page 20
Gate
Bracket
300mm²
Cabling
Pedestal
Concrete
GATE & WALL BRACKET LOCATION FOR VERTICAL WALL MOUNT INSTALLATION
Wall Bracket
Gate Bracket
C (See Fig. 10 to 11)
Figure 12 Determine the Position of the Gate Bracket and Pedestal or Wall Bracket
Page 21
2. Determine a suitable position for the pedestal or wall mount bracket using the swing angle and dimensions A and B as found in the tables in Fig 7 to 11. (Values given in BOLD indicate the recommended dimensions). Before finalising the position of the pedestal or wall bracket, see points 5 & 6 below.
If it is not possible to find a suitable position within the given A and B dimensions, then contact your local Centurion Systems sales office.
3. Determine the vertical height of the pedestal or wall bracket to be 37mm above the gate bracket as in
Fig. 12.
4. If installing a pedestal, prepare a square hole for the pedestal foundation according to Fig. 12 at the predetermined position.
Mount Gate Bracket
5. Locate a suitable place for mounting the gate bracket according to dimension "C" as shown in Fig. 12
By positioning the gate bracket further from the hinge (increasing the "C" value), it would:
increase the time it takes to open the gate (make it slower), improve the gates locking and security properties.
(The A dimension does not affect the opening time or other properties of the gate.)
6. Determine the height of the bracket above ground by taking into account drive arm clearance and ground clearance for the padlock. (See Fig. 12). Once correctly located, weld or screw the gate bracket to the gate using the two M4 screws provided.
Route Cables & Secure Motor Mounting
7. Route cables as determined in the cabling plan (Fig. 5), making sure that all cables protrude at least
400mm above the pedestal mounting plate or wall mount bracket as shown in Fig. 13.
400mm
400mm
Pedestal
Figure 13 Pedestal Adaptor Plate Assembly
Page 22
Wall Bracket
Cables must protrude at least 400mm beyond the top of the pedestal adaptor plate or wall bracket.
8. Securely concrete the pedestal into position making sure that it is vertical, and at the correct height relative to the gate bracket, as shown in Fig. 12. Allow concrete sufficient time to cure.
In the case of a wall mount installation, securely fix the wall mount bracket in the determined position to the wall or pillar using four M12 Rawl bolts.
Fasten Gearbox in Position
9. Fasten the motor onto the pedestal adaptor plate or wall bracket, as shown in Fig. 14, using the M8 bolts and spring washers as supplied.
Wall Mount
Bracket
Pedestal
Figure 14 Secure Gearbox to Pedestal Adaptor or Wall Mount Bracket
Determine Drive Arm Length
10. Depending on the particular installation type, determine the drive arm length as follows:
For Standard Pedestal & Outward Opening Gates:
Measure dimensions L (long) and S (short) as in Fig. 15 and calculate the drive arm length D as shown in Fig. 15. DO NOT CUT THE DRIVE ARM TO THIS LENGTH. Cut the drive arm at least 50mm longer than D. The cut length is therefore = D +50mm. (See Fig. 16)
For Pedestal Mounted Installations With Limited Space:
From the tables on Fig. 8, determine the drive arm length D, and select the boldface value if the motor is mounted in the recommended. DO NOT CUT THE DRIVE ARM TO THIS LENGTH. Cut the drive arm at least 50mm longer than D. The cut length is therefore = D + 50mm (see Fig. 16)
Assemble the drive arm and connecting arm as in steps 11 to 18 and check the gate operation
• If the drive arm interferes with the gate or,
• If the ball joint on the drive arm is more than 30mm from the obstructing wall, then,
Shorten the drive arm by 25mm and repeat the process until the gate operates smoothly.
Page 23
Gate leaf in Closed Position
L
S
Gate leaf in Open Position
Example: If L = 934 and S = 333 then D = 934 - 333
2
= 601
2 therefore D (drive arm length) = 300.5mm
(Do NOT cut the drive arm to this length allow an extra 50mm i.e. cut drive arm D = 350mm. See Fig. 16)
The easiest way of measuring L and S is to hold the zero mark of the tape measure on the middle of the output shaft, and then to read off
L and S at the gate bracket.
Figure 15 Determining Drive Arm Length for Standard Pedestal & Outward Opening Gates
For Parallel and Perpendicular Wall Mount
Installations:
Determine the drive arm length (D) from
Figures 10 and 11. DO NOT CUT THE DRIVE
ARM TO THIS LENGTH. Cut the drive arm at least 50mm longer than D. The cut length therefore = D + 50mm (see Fig. 16)
Fit the Drive Arm
11. Once the drive arm has been cut to length, regardless of installation type, put the gearbox into manual mode (See Page 43)
12. Fit the drive arm and connecting arm assembly to the motor output shaft as in Fig. 20, using the supplied M10 or M12 bolt and washer (Check that the flats on the shaft and clamp line up before tightening up the bolt.)
Set the Connecting Arm
13. Prepare the connecting arm for installation, by moving the inner tube to the retracted position
(see Fig. 17). Turn the inner tube clockwise
D + 50
D
(see Fig 7 or 9 and 10)
Connecting Arm
Drive Arm
Figure 16 Adjust Drive Arm length
Page 24
Inner tube
1
Twist anti-clockwise to loosen.
Outer tube
Retract inner tube completely
Apply each of the warning decals to both the inward and outward faces of the gate frame.
Twist clockwise until ski-pole lock starts to tighten
Figure 17 Prepare Connecting Arm For Installation Figure 18 Apply warning decals to gate until the ski-pole lock starts to tighten. Do not over tighten, as that will make the final adjustment more difficult.
14. Open the gate, and possibly swing the drive arm slightly, until the connecting arm can be fitted into the gate bracket using the clevis pin
(see Fig. 19)
Clevis Pin
15. Using the gate as a lever, slowly close the gate to extend the connecting arm. When the gate is completely closed, the hinge points of the connecting and drive arms must be
in a straight line (see Fig. 22).
Connecting Arm
16. In a double leaf gate system, ensure that both gates are correctly aligned in the closed position.
17. Carefully unhook the connecting arm from the gate bracket making sure it's length is not altered. Hand tighten the connecting arm skipole lock and reconnect it to the gate bracket.
Bush
Gate Bracket
Figure 19 Fit Connecting Arm to Gate Bracket
18. Manually operate the gate leaf and check that it opens sufficiently.
If the gate opens too little, lengthen the drive arm by 10mm and readjust t he connecting arm by restarting from step 14.
Page 25
2
19. Once a satisfactory gate opening has been achieved, the connecting arm must be fully tightened:
Disconnect the connecting arm from the gate bracket. Remove the bushes from the front end of the connecting arm. Using a large screwdriver or similar lever, tighten the ski-pole lock using halfturns until it is as tight as possible and aligned with the gate bracket. Replace the bushes and reconnect the connecting arm to the gate as shown in Fig. 19.
20. Apply the two warning decals supplied to the inward and outward facing sides of the gate frame about 1.2m above ground at the non-hinged end of the gate.
R3 R5
Clamp
Drive Arm
Wedge
M12 Washer
M12 Bolt
Clamp
Drive Arm
Wedge
M12 Washer
M12 Bolt
Figure 20 Assemble Clamp to Drive Arm (R3 only) Figure 21 Assemble Clamp to Drive Arm (R5 only)
Gate closed and aligned
GATE LEAF IN CLOSED POSITION
NB. Hinge points must be in a straight line when gates are closed
Close gate to extend the connecting arm
Drive Arm
Clamp
Connecting Arm
Drive Arm
Figure 22 Align Gates
Page 26
WARNING
1. Always check that the circuit breaker in the electrical panel is in the
OFF position, and that all high voltage circuits (more than 42.4V) are completely isolated from the mains supply before doing any work.
2. Ensure that all low voltage systems (Less than 42.4V) are suitably protected from damage, by disconnecting all sources of power such as chargers and batteries before doing any work.
3. All electrical work must be carried out according to the requirements of all applicable local electrical codes. (It is recommended that a licensed electrical contractor perform such work.)
Connect all wiring
1. Connect all cables as required to the control card and battery charger, according to the wiring diagrams on page 48 & 49.
2. Check that the battery charger is plugged into the controller board as shown in Fig. 23
3. Check that the power source link is in the STD position when using a standard CP84ER5V01 charger, or PSU position for PSUx power supply driven installations. See Fig. 24
Battery Charger Connector
Power Source Link
Bridge pins 1 & 2 for PSU power supply.
Bridge pins 2 & 3 for standard R5V01 charger power supply.
Figure 23 CP75 Controller Battery Charger Connector Figure 24 CP75 Power Source Link
Set up the gate origin/s
4. With both the master and slave gates still in manual mode, move both gates to the closed position.
5. Flip over the controller enclosure. Open the override dust cover as shown in Fig. 31, and remove the origin tool from its storage position (see Fig. 25).
6. Insert the origin setup tool into the release mechanism with a twist action, until the tool is snugly seated (see Fig. 26).
7. Now turn the origin setup tool, until the arrow on the set-up tool lines up with the mark on the release mechanism cover as in Fig. 27 (Take care to line it up with the correct mark.)
Page 27
Setup Tool
Manual Release
Mechanism
Figure 26 Fit Setup Tool into Release Mechanism
Figure 25 Setup tool in stored position
8. Repeat the procedure for the other motor in a double swing system.
9. Return the origin tool to its storage position on the upright pillar and close the override dust cover.
10. With the gates still in manual mode, move the
gates to the ½ way open position, and unscrew the manual release until the top of the screw is flush with the top of the shaft.
(The gearbox does not have to be engaged with the drive arm, when in the ½ way open position.)
Get into programming mode
11. Remove ALL power from the controller, i.e. charger plug and battery.
12. Fit the SET link to the SET pins as shown in
Fig. 28.
13. Reapply power by reconnecting the charger plug, and then the battery to the controller.
14. Immediately after reconnecting the power, the
STATUS light will flash 5 times. The SET and
L2 lights will now be on. You are now in programming mode.
(See Set-up Troubleshooting Guide step 14).
Setup Tool
Manual Release
Mechanism
Figure 27 Twist Setup Tool Until Marks Align
L1 and L2
Indicator LED's
STATUS
Indicator LED SET
Indicator LED
Fit SET
Link Here
Figure 28 Controller SET Link & Programming LED's
Page 28
Select either Master or
Slave motor setup
TEST
Pushbutton
(The gate limits of the Master and Slave motors are set independently of each other.)
15. Press and hold the TEST button (Fig 29) down for 1 flash of L1, and then release. L2 will go off, and L1 will now be flashing once per second.
16. Again press and hold TEST button, but this time monitor the STATUS light. Release the TEST button after 1 flash for selecting the Master
motor, or 2 flashes for the Slave motor. The
STATUS light will turn on to indicate that gate setup is in progress.
Figure 29 CP75 Controller TEST Pushbutton
(See Set-up Troubleshooting Guide step 16)
Set the gate limits
17. To set the closed limit press and hold the TEST button. The master (or slave) motor will activate, and within ±60sec the release mechanism will engage, and the master (or slave) leaf will begin to slowly CLOSE.
If the gate OPENS, release the TEST button and swop the master or slave motor wires as shown in Fig. 30. To continue the setup, press and hold the test button as in step 17.
Figure 30 CP75 Controller Motor Wire Connections
(See Set-up Troubleshooting Guide step 17)
18. When the connecting and drive arm hinge points are in a straight line (Fig. 22), release the TEST
button. (The gate will now be in the CLOSED position). Light L1 must now be OFF when setting the
Master, or L2 OFF when setting the Slave motor.
For fine adjustment of the gate CLOSED position, lengthen or shorten the connecting arm accordingly.
(See Set-up Troubleshooting Guide step 18)
Has the gate gone too far/short? Simply remove and refit the SET link. The gate will OPEN slightly. Try again by pressing, holding and releasing the test button, as in step 17 and 18.
19. To set the OPEN limit, again press and hold the TEST button. The gate will slowly OPEN.
(See Set-up Troubleshooting Guide step 19)
20. When the gate has reached the OPEN position, release the TEST button. Light L1 must be on when setting the Master, or L2 on when setting the Slave motor.
(See Set-up Troubleshooting Guide step 20)
Has the gate gone too far/short? Simply remove and refit the SET link. The gate will CLOSE slightly. Try again by pressing, holding and releasing the test button, as in step 19 and 20.
Page 29
by pressing, holding and releasing the test button, as in step 19 and 20.
21. Then press and release the TEST button once more to confirm the OPEN limit.
When setting Master motor limits: When setting Slave motor limits:
22. The gate will close completely, pause and then open to the minimum pedestrian position.
If a larger pedestrian opening is required, momentarily short the PED input to COM to jog the master leaf further open.
At the required position, press and
release the TEST button.
The MASTER gate will open fully, then the
SLAVE gate (where fitted) will close slightly. The STATUS light will flash 5 times, and L2 will come on, to indicate that the limits were set.
The gate will close slightly. The STATUS light will flash
5 times, and L2 will come on, to indicate that the limits were set.
The control card has now returned to the initial programming mode.
The control card has now returned to the initial programming mode.
23. If no additional Features are required, then exit programming mode by removing the SET link. Store the link by pushing it over ONE of the two pins.
(See Set-up Troubleshooting Guide step 23)
24. Open and close the gate a few times to check operation.
(See Set-up Troubleshooting Guide step 24)
Setting Additional Features
(Optional)
The default factory settings on the CP75 Controller have been selected to suit most applications. In many cases there would be no need to change the default settings. A list of features can be found on page 47, with a detailed description of each feature on page 32.
Determine What Features are Required
25. Determine from Table 2 on Page 47 what Features are required together with the STATUS or COUNT value.
Example: “To turn the AUTO-CLOSE Feature ON”: According to Table 2 the auto-close feature is
Feature number 2, and to turn it ON is a status of 1.
Get Into Programming Mode
(Exactly the same as for limits setup)
26. Remove ALL power from the controller, i.e. charger plug and battery.
27. Fit the SET link to the SET pins as shown in figure 28.
28. Reapply power by reconnecting the charger plug, and then the battery to the controller.
29. Immediately after reconnecting the power, the STATUS light must flash 5 times, and then SET and L2 will come on. You are now in programming mode.
Page 30
(See Set-up Troubleshooting Guide step 14 or 29)
Selecting the Feature to Change
(This is the first of two steps in setting a Feature. This only SELECTS the feature to change).
30. To select the Feature to change, Press and hold the TEST button while monitoring L1.
31. L1 will flash once then go off, twice in short succession then go off, 3 times then go off, etc.
Release the TEST button when the number of flashes is the same as the Feature number to select.
Example 1:
To set the MODE OF OPERATION to CONDOMINIUM (That is Feature number 4, to a status of 2 according to table 2 on page 47) Press and hold the TEST button while monitoring L1:
The L1 light will flash once and pause, then flash twice and pause…. then flash 3 times and pause…. then flash 4 times and pause….
At this moment release the TEST button to select Feature 4. L2 will turn off, and L1 will keep on flashing 4 times and pausing to indicate that Feature 4 is selected
NOTE: The STATUS of the Feature is not changed yet, the feature has only been selected to be changed!
32. If an incorrect Feature is selected, then remove and re-apply power and re-start from step 30. None of the Feature settings will have been altered at this stage.
Changing the STATUS or COUNT value of a Feature.
33. To set the STATUS value of the Auto Close, Mode of operation, Collision Sensitivity, Positive Close mode, Pre-flashing, or the Leaf delay Features:
Press and hold the TEST button while monitoring the STATUS light. The STATUS light will flash the same as for selecting a Feature. (See Step 31) Release the TEST button when the number of flashes is the same as the STATUS value required.
Example 1 (continued):
To set the MODE OF OPERATION to CONDOMINIUM:
After selecting the Feature, again press and hold the TEST button while monitoring the
STATUS light:
The L1 light will flash once and pause,
then flash twice and pause…..
At this moment release the TEST button to give a STATUS value of 2. The mode of operation has been changed to condominium.
NOTE: Only after setting the STATUS, would the mode of operation be changed to reversing!
Page 31
L2 will come back on, indicating that the STATUS has been updated.
34. To set the COUNT value of the Auto-close timer, Pedestrian Auto-close time, Courtesy light timer,
Auto-close override timer, Pre-flashing time, Collision counter, or the Leaf delay time Features:
Press and hold the TEST button while monitoring the STATUS light. After a slight pause, the
STATUS light will start flashing at an even rate. Count all the flashes, and release the TEST button when the number of flashes is the same as the COUNT value required.
Example 2:
Set the AUTO-CLOSE TIME to 10 seconds (That is Feature number 3, to a COUNT value of
10):
First select the Feature number 3 as in steps 30 to 32. Then press and hold the TEST button while monitoring the STATUS light:
After a slight pause, the STATUS light will start flashing regularly:
Flash (1), Flash (2), Flash (3), Flash (4), Flash (5), Flash (6), ….........Flash (9),
Flash (10).
At this moment release the TEST button to give a COUNT value of 10. This sets the autoclose timer to 10 seconds.
L2 will come back on, indicating that the COUNT has been updated.
Controller Features
The terminology "FEATURE 2-2" refers to Feature number 2 with a status of 2. “FEATURE 3- COUNT” refers to Feature number 3, with a user specified COUNT value.
Auto-close
This can be programmed ON (FEATURE 2-1) or OFF (FEATURE 2-2). The factory default is OFF. Autoclose has the function of automatically closing a gate after a preset auto-close time. Auto-close must not be turned OFF in condominium or PIRAC mode.
A gate that is stopped while opening will always auto-close. A gate that is stopped while closing will remain where it is stopped indefinitely.
This time is set in FEATURE 3-COUNT. It can be set from 1 to 255 seconds. It is possible for the user to temporarily turn off auto-close when the mode of operation is either STANDARD and REVERSING. This is done by applying an impulse to the TRG input at the time of opening the gate, for a period of time longer than the AUTO-CLOSE OVERRIDE TIME as set in FEATURE 8-COUNT. To provide feedback that the override signal has operated, the gate will stop opening after the override time. The instant the impulse is removed the gate will complete its opening cycle. The auto-close is now off and the gate will remain open indefinitely. The next impulse received on TRG will initiate the closing cycle and the auto-close is automatically re-instated.
Mode of Operation
It is possible to select 4 different modes of operation: STANDARD, CONDOMINIUM, PIRAC and
REVERSING (FEATURE 4-1 to 4-4). Only one mode can be activated at any one time. All the modes are triggered by the contact present between the TRG input terminal and the COM terminal.
STANDARD MODE (FEATURE 4-1) (This is the factory default mode) - A trigger impulse will cause the gate to start moving (either open or closed depending on its position). A second
Page 32
impulse while the gate is still moving will stop the gate. A third impulse will cause the gate to reverse its direction of travel, i.e. the action is START - STOP - REVERSE.
CONDIMINIUM MODE (FEATURE 4- 2) - Any trigger will cause a gate, which is closed or closing to open or re-open. If not already active, the auto-close will automatically be turned on when condominium mode is selected. It is only the auto-close signal, which can close a gate in condominium mode. If a trigger impulse is given while the gate is open the auto-close time is reset to its preset value.
PIRAC MODE (FEATURE 4-3) - An acronym for Passive Infra Red Auto Close, this mode operates similarly to condominium mode but instead of waiting for the auto-close timer to close the gate, it will close as soon as an object that has passed through the gate clears the infrared beam. If the beam is not broken the gate will get to its fully open position and close after the preset auto-close time. This feature will only operate if infrared safety beams or if an inductive loop is fitted (IRB terminal).
REVERSING MODE (FEATURE 4-4)- This mode is similar to standard mode but instead of stopping a gate when it is in motion, a trigger will cause the gate to reverse its direction of travel. It is thus impossible to leave a gate stationary in a partly open position. The only two normally stable states are fully open or fully closed. If the auto-close is ON then the gate will always tend towards being closed.
Pedestrian Auto-Close Time
(FEATURE 5 - COUNT)
A separate auto-closer timer exists for the pedestrian opening. The time can be set from 1 to 255 seconds but cannot be turned off completely. The default time is 5 seconds.
Collision Sensitivity
(FEATURE 7-1 to 7-3) (The factory default is 7-1)
If the gate is obstructed the internal collision circuitry will activate. When the gate is opening, and it is obstructed the gate will stop. Master and slave gates operate independently of each other while opening i.e. a collision to the master gate will not stop the slave gate from opening fully. During closing however, an obstruction to either master or slave gate will cause both gates to immediately stop and reverse direction.
There is a counter (FEATURE 12-COUNT) that monitors the number of collisions. If the collision count is reached before both gates reach the fully closed position all trigger signals are inhibited for a 1 minute period. The STATUS LED flashing 4 times indicates this condition. After the 1 minute period. triggers will again become active, (with the exception of auto-close). The fault indication will continue to flash indefinitely after the 1 minute period but will clear after the 1 minute period is a valid trigger is given. The collision counter resets to zero after the 1 minute delay, or the processor is reset. (e.g. By removing all power from the controller.)
Courtesy (Pillar) Light:
The pillar circuit has multiple functions:
• It operates as a courtesy light and switches on for a timed period. (The factory default is 2 minutes) (set by FEATURE 6-COUNT) every time the gate triggers.
• It can be turned on for the preset timed period, by the application of a short impulse between the
SET terminal and COM.
• It can be turned ON permanently by application of an impulse longer than 3 seconds on SET and
COM terminals. A short impulse thereafter will switch the lights off. The gate will not trigger open when using the SET trigger. The fact that the pillar light is ON permanently is indicated by the
STATUS LED flashing once every 2 seconds.
Page 33
• When the PED input is triggered the pillar light flashes for an adjustable (1 to 255 seconds) preflash time (FEATURE 11 - COUNT) before the pedestrian gate opens. (Default pre-f;ash time is 2 seconds).
• The contact can be used to operate a lamp, which will warn that the gate is about to open.
Selection of pre-flashing is done in FEATURE 10. Three modes and OFF are selectable (The factory default is OFF):
Mode 1 - Light comes on only while gates are in motion.
Mode 2 - Light flashes at 1Hz for the pre-flash time and then flashes in synchronism with the
STATUS LED while the gates are in motion.
Mode 3 - Light comes on for the pre-flash time and while the gates are in motion.
Positive Close Mode:
Setting positive close mode to ON (FEATURE 9-1) (default is OFF, FEATURE 9-2) will allow the gate to drive up hard to an end stop without causing the collision circuitry to operate. This Feature operates only during the last 10 degrees of arm travel in the closing moe.
Leaf Delay:
(Feature 13 & 14) It is possible to select 3 different types of leaf delay. Feature 14 selects the delay time.
FEATURE 13-1 Will delay the slave motor during its opening cycle only for the leaf delay time.
FEATURE 13-2
FEATURE 13-3
Will delay the master motor during its closing cycle. This is to ensure that the slave gate will reach the fully closed positions before the master leaf. For example, in situations where the master gate has a flap which must close against the slave gate.
Will cause the slave gate to delay on opening and the master gate to delay on closing.
FEATURE 13-4 Turns all leaf delays OFF (Default setting).
FEATURE 14-COUNT Allows the leaf delay to be set from 1 to 255 seconds. The default delay time is
2 seconds.
NOTE: The solenoid lock strike time is set via the leaf delay timer.
All the known causes of problems are listed, according to the step number in the gate limits setup instructions.
Page 34
SET-UP
STEP
14 or
29
16
17
PROBLEM
SET light is not on:
L2 is not on:
POSSIBLE CAUSES & SOLUTIONS TO PROBLEM
Check that the SET link is correctly fitted. Fit and remove the link a few times to ensure good contact.
All sources of power on the card must be removed. Check by confirming that all the lights turn off, before reconnecting the power with the set link fitted.
The controller did not “boot-up” correctly. Try to fit the charger plug before reconnecting the battery.
STATUS light did not flash 5 times:
L1 is flashing: Check for and remove latching inputs on the TRG terminal then restart from step 11.
STATUS light flashes 5 times and L2 turns on.
This could be due to:
The gate not being correctly positioned. Move the gate to its half way position and restart from step 14.
The origin not being set correctly. Restart the setup from step 14.
A faulty origin PCB or cable. To check, go out of programming mode by removing the SET link. Then insert the origin setup tool, turn the tool a full revolution while monitoring L1 and L2. If either L1 or L2 changed state during the adjustment, then the origin system for the motor tested is
OK. restart the setup from step 4.
If not, check the status of all plugs and wiring. If the problem is not resolved then the sensor, cable or controller might be faulty.
There is a click but the motor does not turn. The
STATUS light flashes rapidly, then flashes 5 times. L2 turns on.
This could be due to:
The motor not being connected to the controller, or
The motor fuse could be blown, or
The motor is faulty. Check motor by connecting motor leads directly to the battery.
Check for loose connections or corrosion on battery terminals.
The motor cables are too thin. They must be 2,5mm 2
Check for low battery condition by following procedure A on page 41.
Correct the problem, remove and refit the SET link and start from step 17.
There is a click, the motor turns but the gate does nor move.
The manual release mechanism is still in manual mode. The manual release must be unscrewed as in step 10.
Not enough time is allowed for the manual release to re-engage.
To continue setup, press the TEST button as in step 17
Page 35
Set-up Troubleshooting Guide Continued...
17
(continued)
Motor briefly starts and
then stops, and STATUS flashes 5 times.
The battery is not connected. Correct the problem, remove and refit the SET link and start from step 17.
Faulty DOSS sensor or cable.
18
Motor starts then stops
after 1 second (STATUS flashes 5 times)
The DOSS sensor system is faulty. Is the DOSS harness plugged in? If so, there could be a fault on the sensor, cable or controller.
Light L1 is on when setting the Master, or L2
is on when setting the
Slave motor:
The leaf has not passed through the origin yet. In which case:
Either keep on pressing and holding the test button until the required gate closed position is reached with L1 off, or
Mechanically reset the gate origin by restarting from step 4.
19
20
23
The gate does not open,
STATUS light flashes 5 times and L2 turns on.
The battery is discharged. Replace or charge the battery.
Light L1 is off when setting the Master, or L2
is off when setting the
Slave motor:
The leaf has not passed through the origin yet. In which case:
Either keep on pressing and holding the test button until the required gate closed position is reached with L1 or L2 on, or
Mechanically reset the gate origin by restarting from step 4.
L2 and SET did not go off Check for, and remove, inputs on the SET terminal.
24 The gate stopped short of either the open or closed position:
The gate limits were not set correctly. Restart from step 4.
The gate dynamics could be detected as a collision by the controller. Set the gate collision sensitivity to be less sensitive (feature 7 to Status 2 or 3)
The open position of the gate was not confirmed by pressing the TEST button as in step 21. Restart from step
11.
The gate does not close when pressing TEST:
Mode of operation could be set to condominium, which only allows the gate to be closed by the auto-close timer.
The safety beams or holiday lockout features could be activated. Check the IRB and LCK lights, both must be ON for normal operation.
The link between COMMON and LCK might not be fitted, when the safety lockout feature id not used.
The link between COMMON and IRB might not be fitted, when safety beams are not used.
The gates do not close simultaneously:
One of the leaf delay modes is selected. The gates can be set to close simultaneously by setting feature 13 to status 4
Page 36
Set-up Troubleshooting Guide Continued...
24
(continued)
The motors keep on driving past the closed position:
Positive close mode has been activated. Deactivate positive close mode by setting feature 9 to 1.
The slave gate runs slower than the master gate:
The slave motor cables are too thin, ensure that the cables are at least 2.5mm²
The gate starts and then stops moving when gate is fully OPEN and triggered to close.
The installation geometry does not give the motor enough mechanical advantage to get the gate started.
• For limited space and wall mounted installations, shorten the drive arm by 25mm and re-adjust the connecting arm as in steps 17 to 213 of the mechanical setup.
• Alternatively, set the collision sensitivity, feature 7, to status 2 (medium) or 3 (low).
PROBLEM
1 Gate does not open at all:
POSSIBLE CAUSES & SOLUTIONS TO PROBLEM
Check that you are out of programming mode, SET light must be OFF.
LCK (lockout) input activated. Green LCK light should be
ON.
IRB (IR beams) input activated (Gates would not move
once open). Green IRB light should be ON. Check cabling, alignment and 12V power (3A auxiliary fuse).
Latching input on TRG or FRX. (Both TRG and FRX lights must be off for gate to operate.)
Check the battery condition with procedure A: Low battery
voltage condition, later in this section.
If STATUS light flashes 4 times then the operator is in
Multiple Collision Mode. Remove & reapply all power, or wait 60 seconds to reset operation. If required, check with procedure B: False collision detection, later in this section.
If the problem persists, the CP75 main controller might be faulty.
Page 37
Fault Finding Guide Continued...
PROBLEM POSSIBLE CAUSES & SOLUTIONS TO PROBLEM
2 Gate does not move, but the relays “click” when the unit is activated:
Check that you are out of programming mode, SET light must be OFF.
Check the battery condition with procedure A: Low
battery voltage condition, later in this section.
Check the motor wires.
If STATUS light flashes 4 times then the operator is in
Multiple Collision Mode. Remove & reapply all power, or wait 60 seconds to reset operation. If required, check with procedure B: False collision detection, later in this section.
If the problem persists, the CP75 main controller might be faulty.
3 Gate moves a short distance and stops:
Check the battery condition with procedure A: Low battery
voltage condition, especially if the STATUS light flashes 3 times.
Motor wires use for the SLAVE operator are too thin.
Check for false collisions with procedure B: False collision
detection, later in this section (STATUS light could also flash 4 times if the number of detected collisions exceeded the COLLISION COUNTER feature value).
Intermittent IRB trigger. Check that the voltage applied to the beams are appropriate.
Spurious trigger. Remote with same coding operated in area, or intermittent short due to possible moisture on the
FRX or TRG inputs.
If the problem is still not solved, the CP75 main controller might be faulty.
4 Gate starts closing then stops & reopens:
Check collision sensitivity and other causes with procedure
B: False collision detection.
Page 38
Fault Finding Guide Continued...
PROBLEM
5
6
7
Gate overruns its limits:
Gate opens on its own
Unreliable auto-close
POSSIBLE CAUSES & SOLUTIONS TO PROBLEM
Check for intermittent IRB (IR Beam) triggers. (Check beam operation, alignment and supply voltage).
Intermittent/spurious signal on FRX or TRG if in CONDO,.
PIRAC or REVERSING modes. (Standard mode would first stop then reverse)
If the problem is still not solved, the CP75 main controller might be faulty.
For both MASTER and SLAVE motors: (only the faulty gate's components need to be inspected)
Check that the ORIGIN sensor wire harness is securely
plugged into the CP75 (master controller) or CP74A (slave board), a nd securely into the ORIGIN sensor.
Check that the respective ORIGIN sensor is securely
clipped into the housing.
Check if the gate origin was accidentally moved, steps 4 to 10 of the electrical setup. If so reset the limits.
For SLAVE motor, check the wiring of S1, S2 and S3 for continuity and short circuits. Look for and correct all loose connections and signs of corrosion, be sure to solder all joints.
Make sure that the ORIGIN dust cover is closed. (Ants could give intermittent false triggers).
If the problem is not solved, the CP75 main controller might be faulty.
Check for latched TRG or FRX input. (Respective lights would be on continuously).
Intermittent fault on TRG or FRX inputs. Look at all joints, switches, etc. (Underground joints with moisture buildup)
Outside transmitter with the same code. (Typically only with DIP switch type remotes)
Faulty receiver
Faulty electric fence
If the problem is still not solved, the CP75 main controller might be faulty.
Latching Receiver on TRG, would activate the auto-close override feature.
Page 39
Fault Finding Guide Continued...
PROBLEM POSSIBLE CAUSES & SOLUTIONS TO PROBLEM
Long pulse on TRG would activate the auto-close override feature.
Faulty IR Beam input.
Intermittent power loss, check for low voltages with procedure A: Low battery voltage condition.
If the problem is still not solved, the CP75 main controller might be faulty.
8 Gate opens to pedestrian and closes
Intermittent fault on PED (pedestrian) input. Check wiring, and key switch operation.
B: False collision detection.
If the problem is still not solved, the CP75 main controller might be faulty.
9 Gate takes a few seconds before it opens to pedestrian
By default the motor would delay opening to pedestrian for
2 seconds. This time can be changed or removed by changing the value of the PREFLASH TIME feature (Feature
11)
10 Gate opens to pedestrian & stays there
There is a continuous PED signal, the PED light will be on continuously. (The PED light & signal must turn on momentarily for the gate to close after a pedestrian signal.)
Check for latching Receiver, or a faulty key switch.
If the problem is still not solved, the CP75 main controller might be faulty.
11 Slave motor moves slower than the master gate
The slave motor wires are too thin.
Either of the Master or Slave motors were not installed on the recommended positions.
12 Gate opens from the intercom but not from the receiver
The fault is with the receiver.
Check the wiring between the receiver and control card.
Check that the receiver has power. If not, check the 3A
Auxiliary fuse on the main controller. (NB. remove fuse before measuring.)
The receiver could be faulty.
Page 40
Fault Finding Guide Continued...
PROBLEM POSSIBLE CAUSES & SOLUTIONS TO PROBLEM
A
Low Battery
Voltage Condition
(STATUS light flashes 3 times)
(If the battery voltage is less than 10.5V, the motor would not operate at all. For any other voltage, the battery could still be the cause of the problem.
Check that the power is turned ON, by first disconnecting the battery and then to check that the green CHARGE light is
ON. If it is OFF, then power is not connected to the charger or the power pack.
Check that the power source link is in the STD position when using the CP84E charger, and in the PSUx (10A power pack) driven installations.
Check the condition of the battery leads, terminals and connectors. Look for and correct all loose connections and signs of corrosion.
The battery might be discharged. Measure the battery voltage with the charger connected, if the voltage is below
12.5V then the battery is discharged. The number of opening cycles per hour may be excessive, thus discharging the battery. Charge the battery, or fit a 10A power pack if required.
Charger might be faulty. Disconnect the battery, and measure the voltage on the battery leads. It must be between
13.6V and 13.8V, if not replace the charger.
Battery might be old, and might have to be replaced. If in doubt test as follows:
Check that the battery is charged, by ensuring that the battery voltage is above 13.5V with the charger connected. (If the battery is in a good condition it would probably pass the test without being fully charged)
Disconnect the charger from the battery
Remove the DC Motor leads from the DC Controller
Apply the DC motor leads directly to the battery, while measuring the battery voltage. WARNING: First make sure that the moving gate will not pose any danger.
If the gate does not move, the battery or motor
could be faulty.
If the battery voltage remains unchanged, then the motor is faulty and must be serviced. If the battery
voltage drops to below 11,5V then the battery must be replaced.
(Before replacing the battery, measure the charging voltage on the battery leads with the battery disconnected. It must be between 13.6V and 13.8V, if not, replace the charger.)
Page 41
Fault Finding Guide Continued...
PROBLEM POSSIBLE CAUSES & SOLUTIONS TO PROBLEM
B
False Collision Detection
(STATUS light could flash
4 times to indicate that number of collisions have exceeded COLLISION
COUNTER feature value. Wait
60 seconds, or remove & reapply all power to reset operation.)
To determine which is the faulty gate in a double swing system, activate the gates. Both gates will stop and reverse on closing, but only the faulty gate will stop when opening.
For both MASTER and SLAVE motors:
(Only the offending gate's components need to be inspected)
Check for tight hinges, unbalanced gate, or something
physically obstructing the gate. Activate the manual override and move the gates to check for ease of operation.
For SLAVE motor, check the wiring of S1, S2, S3 and the 2
motor wires for continuity and short circuits. Look for moisture on any joints and correct all loose connections and signs of corrosion. (Joints should be soldered together to ensure a reliable joint.)
Check for ants and dirt in and around the DOSS sensor.
Check the DC motor wires for loose connections.
Check contact of the fuses with the fuse holder on CP75
(main controller).
Check that the sensor wire harness is securely plugged
into the CP75 (master controller) or CP75A (slave board) and into the DOSS sensor.
Check that the DOSS sensor is securely clipped into the housing.
If the problem is not solved replace the DOSS sensor
(CP75B), then the Slave card (CP75A), and main controller
(CP75).
Note:
Orange Wire = Encoder and Purple Wire = Origin
Page 42
1. Remove all power (Power supply and battery ).
2. Fit the "SET" link.
3. Connect "PED" and "FRX" to "COM".
4. Reconnect all power. (L1 AND L2 will illuminate).
5. Remove all power (Battery and power supply).
6. Remove the "SET" link and disconnect "PED" and "FRX" from "COM".
7. The card is now programmed to default settings as shown in table 2 (see page 47) (Gate end points are not affected).
The manual release mechanism is used to disengage the output shaft from the motor, thus making it possible to open or close the gates manually without turning the motor or any other internal parts.
Normal Operation
1. Flip over the controller enclosure. Open the override dust cover as shown in Fig. 31.
2. Insert the 6mm Allen key supplied into the release mechanism (Fig 25).
3. Turn the Allen key clockwise to release the mechanism as shown in Fig 25.
or
Turn the Allen key counter clockwise to engage the release mechanism.
4. Remove the allen key.
5. Close the override dust cover.
Allen Key
Setup Tool
Figure 31 Manual Release Mechanism Figure 32 Manual Release Operation
Page 43
Use this procedure to accurately determine the gate opening angle:
Step 1
Close the gate and measure a distance of 1m from the gate hinge.
Make a mark on the ground.
1m
Step 2
Open the gate and measure a distance along the gate a distance of 1m from the gate hinge.
Make a mark on the ground.
Measure the distance on the ground between the two marks
(Z). Using this Z value, read off the gate opening angle from the table below.
Step 3 GATE SWING ANGLE
60 Degrees
70 Degrees
80 Degrees
90 Degrees
100 Degrees
110 Degrees
120 Degrees
1m
VALUE Z FROM...
1 000mm
1 075mm
1 218mm
1 351mm
1 474mm
1 587mm
1 687mm
Page 44
Z
...TO
1 075mm
1 218mm
1 351mm
1 475mm
1 587mm
1 687mm
1 732mm
MASTER The master motor is connected to these terminals. If the master motor direction is incorrect swap around the wires connected to these terminals.
SLAVE The slave motor (in dual swing gate applications) is connected to these terminals. As with
MASTER, swap the connected wires around for motor direction reversal.
COM
LIGHT
12V
The battery/power supply negative terminal. All trigger signals etc. have their return path to one of the COM terminals.
These two terminals provide a normally open potential free contact which is generally used to switch on a pillar light (courtesy light). It can also be used for other purposes if required.
Provides a +12V DC supply for auxiliary equipment such as a radio receiver, photo cells etc. It is linked directly to the battery positive via a 3A fast blow fuse (see page 47).
TRG
IRB
FRX
LED
A momentary, normally-open trigger device such as relay, pushbutton etc. connected between
TRG and COM will cause the gate to trigger open/closed. Connect multiple trigger devices in parallel (Refer to the section MODE OF OPERATION on page 32).
The signal from the infra red beam (IRB)(photo cell), safety edge, loop or other safety device.
This prevents the gate from closing when the normally-closed contact between IRB and COM is open. For multiple safety devices wire all contacts in series.
NB: If no safety devices are fitted ensure a wire link is fitted between IRB and COM. If autoclose is selected the time will be reset to the selected value when the device is tripped.
A momentary normally-open contact from a device such as a free exit inductive loop detector (or photo cell or pushbutton) which causes a gate which is closed or closing to open or re-open. If the gate is open or opening the signal has no effect other than to reset the auto-close timer (if selected). Free exit (FRX) will never initiate a closing cycle. If only the FRX input is u sed , the autoclose must be turned on alternatively the TRG input used to close the gate.
An output terminal which provides a low current, (approx. 4,5V DC, 20mA) drive to an LED which can be used to indicate the gate status remotely. If more than 3 LED's are required it is necessary to fit a LED driver card (consult Centurion Systems for details).
PED
LCK
A momentary normally-open contact from a pedestrian key switch, pushbutton, keypad, radio receiver etc which will cause the MASTER gate only, to open to the limited pedestrian open position. The gate opens only after the adjustable pre-flash time (default - 2 seconds). If the contact is held closed the auto-close is suspended until the contact reopens.
If the latched normally-closed contact between LCK and COM is held open, all triggers which would normally cause a closed gate to open (e.g. TRG, PED, FRX) will be inhibited. If the gate is open, opening or closing and the LCK contact is opened the gate will continue to respond until such time as the gate is in the fully closed position.
NB: If the LCK function is not required a link must be fitted between LCK and COM.
SET This terminal has two functions:
1. If SET is linked to COM with no power present to the controller and power is then applied, the controller will be put into PROGRAMME mode.
2. If SET is linked to COM when power is already applied, this action will cause the pillar light relay to energise. A momentary contact causes the relay to energize for a period of time as defined for the courtesy light timer. If the contact is made for a period exceeding 3 seconds the pillar light relay will energize and remain energized indefinitely until a new momentary contact is given.
SOL A solenoid strike lock is connected between SOL and 12V. Each time the gate triggers to open (or close) the SOL terminal switches to COM thus energizing the solenoid. The time that the SOL terminal remains switched to com is set using FEATURE 14. The maximum current draw is 2A.
SS1 to SS3 Limit switch contacts from the slave interface PCB.
Page 45
The controller is fitted with diagnostic lights (LEDs) that assist with the set-up and maintenance of the gate.
Table 1 provides a description and purpose of the indicator lights. Refer to page 46 for location.
During Normal Operation
NAME COLOUR ON OFF REMARKS
STATUS
(During normal operation)
Red Gate fully open Gate fully closed 1 Flash/sec - Pillar light on permanently
2 Flashes/sec - Charging failure
3 Flashes/sec - Battery low detection
4 Flashes/sec - Collision detector operated
5 Flashes/sec - Microprocessor reset
L1 Red
L2 Red
Master origin diagnostic
(Changes state to indicate origin status)
Slave origin diagnostic
(Changes state to indicate origin status)
Green Battery charging CHARGER
ON
TRG
IRB
FRX
PED
LCK
SET
Red
Green
Red
Red
Green
Red
Signal present
Safeties clear
Signal present
Signal present
System ready to operate
Signal present
No charge voltage present.
No signal
Safeties obstructed
No signal
No signal
System locked
No signal
N/A
N/A
N/A
N/A
N/A
N/A
During Programming Mode
STATUS Red
L1
Red If LED2 also on, system reset to factory default.
L2 Red System in programme mode.
If L1 also on, system reset to factory default.
Table 1 LED Indicator Light Description & Purpose
Page 46
The number of flashes correspond to the
STATUS or COUNT value being set.
The number of flashes corresponds with the FEATURE number being selected
FEATURE STATUS or COUNT
DESCRIPTION
FEATURE
NUMBER
STATUS
VALUE
COUNT
VALUE
DESCRIPTION
Gate Limit Settings
Auto-close
1
2
-
1
2
-
-
-
-
Auto-close Time
Mode of Operation
3
4
1
4
-
2
3
1 Flash = 1 second
-
-
-
-
Pedestrian Auto-close
Courtesy Light
Collision Sensitivity
5
6
7
-
1
2
3
-
1 Flash = 1 second
1 Flash = 10 seconds
-
-
-
Auto-close Override
Positive Close Mode
Preflashing
8
9
10
1
2
3
4
-
1
2
1 Flash = 1 second
-
-
-
-
-
-
Preflash Time 11 1 Flash = 1 second
Collision Counter 12
-
1 Flash = 1 count
-
1
2 -
Leaf Delay Select 13
3 -
4 -
Leaf delay time /
Solenoid Strike Time
14
-
1 Flash = 1 second
Table 2 Controller Functions Menus and Submenus
See detailed instructions on page 29
ON
OFF (Default)
15 seconds (Default)
STANDARD (Default)
CONDOMINIUM
PIRAC
REVERSING
5 seconds (Default)
120 seconds (Default)
HIGH (Default)
MEDIUM
LOW
3 second (Default)
ON
OFF (Default)
MODE 1
MODE 2
MODE 3
OFF (Default)
2 seconds (Default)
4 counts (Default)
Delay on slave opening
Delay on master closing
Delay on slave opening & master closing
Delay off (Default)
2 seconds (Default)
Page 47
1 2
M
3 4
TO ORIGIN
SENSOR ON
SLAVE
MOTOR
TO COUNTER
SENSOR ON
SLAVE
MOTOR
ONLY FITTED IN DOUBLE SWING GATE SYSTEMS
FOR DETAILED CONNECTIONS,
REFER TO CP 75 CONTROLLER
TRIGGER WIRING ON PAGE 47
LIVE
NEUTRAL
AUXILIARY
SUPPLY
220V AC
MAINS IN
L
N
E
3-WAY
CONNECTOR
TO ORIGIN
SENSOR ON
MASTER
MOTOR
3-WAY
CONNECTOR
TO COUNTER
SENSOR ON
MASTER
MOTOR
CP84ER5V01
NOTE:
WHEN SETTING THE GATE LIMITS DURING THE
COMMISSIONING PROCEDURE AS DESCRIBED ON
PAGE 29, IT MAY BE NECESSARY TO CHANGE THE
MOTOR DIRECTION.
TO CHANGE THE MASTER MOTOR DIRECTION,
TO CHANGE THE SLAVE MOTOR DIRECTION,
Page 48
SOLENOID
LOCK
RADIO RECEIVER
12V or 24V
IRB Tx IRB RECEIVER
LOOP
LOOP DETECTOR
Page 49
For a detailed description of t e r m i n a l f u n c t i o n s , r e f e r t o
DESCRIPTION OF TERMINAL
FUNCTIONS on page 45.
PUSHBUTTON
FOR SWITCHING
PILLAR LIGHT (N/0)
HOLIDAY
LOCKOUT
SWITCH
(N/C)
PEDESTRIAN
KEYSWITCH (N/O)
(RETURN SPRING)
L
N
E
1 CP84ER5V01 Charger Transformer
2 14.2V DC charger plug to CP75 controller
3 Lightning Earth Point
4 220V AC, 1Ø, Mains Supply for CP84ER5V01 using removable connectors
5 Mains fuse (250mA, size 5 x 20mm)
6 Auxiliary Mains Connecton, 220V AC
CP75
3
6
L
N
E
BATT
-
BATT +
1 PSUx - Power Supply Unit
2 220V AC, 1Ø, Mains Supply for CP84E using removable connectors
3 DC charger plug to CP75 controller
4 12V DC lead acid battery (Amp/hour rating to suit)
5 Mains Fuse - 250mA size - 5x20mm
6 16A Slow-blow fuse
Ensure that the power source link is set to
PSU in Fig. 24 on page 27
Page 50
Once the installation has been successfully completed and tested, it is important for the installer to explain the operation and safety requirements of the system.
NEVER ASSUME THE USER KNOWS HOW TO SAFELY OPERATE AN AUTOMATED GATE. Even if the user has used one before, it does not mean he knows how to SAFELY operate it. Make sure that the user fully understands the following safety requirements before finally handing over the site.
Ensure that the user fully understands:
How to operate the manual release mechanism. (By demonstration)
How the obstruction detection and all other safety features work. (By demonstration)
All the safety considerations associated with operating an automated gate, and that he understands that he is responsible for explaining these safety instructions to all other users of the automated system:
1. Do not activate your gate opener unless you can see it and can determine that its area of travel is clear of people pets, or other obstructions.
2. NO ONE MAY CROSS THE PATH OF A MOVING GATE. Always keep people and objects away from the gate and its area of travel.
3. NEVER LET CHILDREN OPERATE OR PLAY WITH THE GATE CONTROLS, and do not allow children or pets near the gate area.
4. Be careful with moving parts and avoid close proximity to areas where fingers or hands could be pinched.
5. Secure all easily accessed gate opener controls in order to prevent unauthorized use of the gate.
6. Keep the automated gate system properly maintained, and ensure that all working areas are free of debris and other effects that could affect the gate operation and safety.
7. On a monthly basis, check the obstruction detection system and safety devices for correct operation.
8. All repair, and service work to this product must be done by a suitably qualified person.
9. This product was designed and built strictly for the use indicated in this documentation. Any other use, not expressly indicated here, could compromise the good condition/operation of the product an/or be a source of danger.
10. Centurion Systems (Pty) Ltd does not accept any liability caused by improper use of the product, or for use other than that for which the automated system was intended.
11. Ensure that the customer is in possession of the User Guide and also complete the installation details in the back of the User Guide.
Page 51
Installation Details
Installer's Name:
Installer's Address:
Installer's Telephone Number:
Installation Date:
Installation Checked By:
Page 52
Page 53
Page 54
Page 55
Sharecall 0860-CENTURION (0860 236 887)
Head Office: +27 11 699 2400
Sharecall Technical Support 0861 003 123 or
+27 11 699 2481 from 07h00 to 18h00 (GMT+2)
(Sharecall numbers applicable when dialed from within South Africa only)
0.07.A.0058_22072013
www.centsys.com
advertisement
Related manuals
advertisement
Table of contents
- 4 Declaration of Conformity
- 5 Important Safety Instructions
- 6 Fast Track
- 8 General Description
- 8 Specifications
- 10 Product Identification
- 12 Required Tools & Equipment
- 13 Site Considerations
- 14 Cabling Requirements
- 15 Operator Installation
- 15 Pedestal Mount Features
- 15 Wall Mount Features
- 15 Locate the Operator Position
- 16 Where to Position the Operator
- 22 Mount Gate Bracket
- 22 Route Cables & Secure Motor Mounting
- 23 Fasten Gearbox in Position
- 23 Determine Drive Arm Length
- 24 Fit the Drive Arm
- 24 Set the Connecting Arm
- 27 Electrical Set-up
- 27 Connect all Wiring
- 27 Set Up the Gate Origin/s
- 28 Get into Programming Mode
- 29 Select either Master or Slave Motor Setup
- 29 Set the Gate Limits
- 30 Setting Additional Features (Optional)
- 32 Controller Features
- 35 Set-Up Troubleshooting Guide
- 37 Fault Finding Guide
- 43 Procedure to Programme Controller Back to Factory Default Settings
- 43 Manual Release Mechanism
- 43 Normal Operation
- 44 Determine Gate Swing Angle
- 45 Description of Terminal Function
- 46 LED Indicator Lights
- 47 CP75 Controller Functions
- 48 CP75 Controller Connections
- 49 CP75 Trigger Connections
- 50 CP84ER5V01 Charger Connection
- 50 PSUx Power Connection
- 51 Installation Handover