Development of a Directional Definite-Time Overcurrent and Earth Components

Development of a Directional Definite-Time Overcurrent and Earth Components
DEGREE PROJECT, IN ELECTRIC POWER ENGINEERING , SECOND LEVEL
STOCKHOLM, SWEDEN 2015
Development of a Directional
Definite-Time Overcurrent and Earth
Fault Protection based on COTS
Components
FABIAN HOHN
KTH ROYAL INSTITUTE OF TECHNOLOGY
ELECTRICAL ENGINEERING
Abstract
Manufactures of power system products face an increased pressure to reduce the time to
market of their development process without compromising quality. Moreover the operation of power systems needs to be performed in a secure and reliable manner. One of
the key systems to guarantee those stringent requirements is the protection system. The
objective of this Master’s thesis is the development of a protection system, which solidly
relies on Commerciall-o↵-the-Shelf (COTS) components as well as on the developed protection functions. Thereby it is shown that the tight cost requirements can be fulfilled
without jeopardising the reliability and security performance.
This project comprises the development of a definite-time directional overcurrent and
earth fault protection. The applied development process is based on a model-based-design
approach, which comprises the definition of the requirements, the design phase, the implementation on the target system and the test phase. As part of this thesis each stage
is described and executed. Moreover MATLAB/Simulink was used as development environment, since it perfectly supports the model-based-design approach. The considered
functional requirements are mostly based on the standard IEC 60255-151. The developed
protection algorithm runs on a realtime linux system and the interface to the process is
based on the EtherCAT protocol and their corresponding I/O modules. Lastly, the test
phase is based on a functional performance test, a type test according to IEC 60255-151,
a longterm test and an evaluation of the EMC performance of the used I/O modules.
The results of the type tests showed that a IEC 60255-151 compliant solution is yield.
Moreover the functional performance test proofed that the developed protection function
operate as intended for various fault scenarios. Lastly, the realtime performance of protection system has to be further analysed and adapted in order to achieve satisfactory
behaviour.
i
Abstrakt
Tillverkare av elkraftskomponenter står inför ökade utmaningar för att minska tiden för
produktutveckling utan att kompromissa med kvalitén.
Utmaningen blir större när ett säkert och tillförlitligt elkraftsystem måste uppfyllas. Ett
av de viktigaste systemen för att garantera dessa krav är skyddssystemet. Syftet med
detta examensarbete kommer följaktligen bli att utveckla ett skyddssystem som förlitar
sig på Commerciall-o↵-the-Shelf (COTS) komponenter och som dessutom tar hänsyn till
skyddssystems funktioner. Från detta skyddssystem kan det påvisas att det är möjligt att
under ett begränsat tidsspann uppfylla marknadens krav utan att äventyra tillförlitligheten
och säkerheten.
Detta projekt innefattar utvecklingen av ett riktat överströmsskydd och ett jordfelsskydd.
Utvecklingsprocess bygger påen modellbaserad design, som omfattar faserna prestandakrav,
konstruktionsfas, implementering och prestandatest av systemet. Som en del av detta arbete kommer varje steg beskrivas utförligt och genomföras. MATLAB/Simulink användes
som utvecklingsverktyg, eftersom den har stöd för modellbaserad design. De prestandakrav
som anses är för det mesta baserad på IEC 60255-151 standarden. Den utvecklade skyddsalgoritmen implementerat i ett Linux system i realtid, gränssnittet för processen är
baserad på EtherCAT protokollet och deras korresponderade I/O moduler. Testfasen är
indelat i fyra olika tester kallade prestandatest, typtest enligt IEC 60255-151, realtidstest
och utvärdering av EMC prestandan av de använda I/O modulerna.
Resultatet av prestandatest visar att en IEC 60255-151 kompatibel lösningen går att
uppnå. Dessutom visar prestandatestet att de utvecklade skyddsfunktionerna fungerade som planerat för olika fel scenarion. Realtidsprestanda av skyddssystemet behöver
emellertid ytterligare analyseras och anpassas för att uppnåtillfredsställande resultat.
ii
Acknowledgements
There were many people, which have been of great support to me during the planning
and execution of this Master’s thesis project. Therefore I would like to express my sincere
gratitude to them. The thesis has been conducted in collaboration with ABB Substation
Automation Products in Västerås as well as with the Industrial Information and Control
Systems department at KTH in Stockholm.
Johan Salj has been my supervisor at ABB. He has supported me with technical guidance
throughout the project. In addition, I am very thankful to him for sharing his broad expertise. Moreover, I want to thank Henrik Bäckstrand. In his capacity as a line manager
he help me with all administration matters as well as with the arranging of the required
technical equipment.
Furthermore, my supervisor from KTH Nicholas Honeth has been of superb help to me.
Due to his extraordinary commitment to the course ”Advanced Computer Applications in
Power Systems”, I became very well acquainted with the Linux operating system. During
my thesis he has been given me useful guidance for the execution of the project. My
professor Lars Nordström was acting as the responsible examiner of the thesis. I would
like to thank him for given me this great opportunity to conduct the thesis with ABB and
for his valuable advice and support.
Lastly, I would like to thank all my colleagues from ABB and the sta↵ from the ICS
department for supporting and encouraging me.
iii
Contents
Abstract
i
Abstract
ii
Acknowledgements
iii
List of Figures
viii
List of Tables
x
Nomenclature
xi
1 Introduction
1
1.1
Problem Definition . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1
1.2
Objectives . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1
1.3
Outline of the Thesis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2
2 Background
3
2.1
Commercial-o↵-the-shelf . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3
2.2
Power System Protection . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4
2.2.1
General objectives of protection systems . . . . . . . . . . . . . . . .
4
2.2.2
Setups of Protection Systems . . . . . . . . . . . . . . . . . . . . . .
5
2.2.3
Fault current calculation . . . . . . . . . . . . . . . . . . . . . . . . .
6
2.2.4
System Grounding . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
2.3
2.4
2.5
Real-Time Systems . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
2.3.1
Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
2.3.2
Process, Thread & Task . . . . . . . . . . . . . . . . . . . . . . . . . 15
2.3.3
Scheduling policies . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
Communication . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
2.4.1
EtherCAT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
2.4.2
IEC 61850-9-2 & 61850-9-2LE . . . . . . . . . . . . . . . . . . . . . . 20
Related Work . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
iv
3 Methodology
24
3.1
Model-based Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24
3.2
Requirements for protection relays . . . . . . . . . . . . . . . . . . . . . . . 26
3.2.1
Functional requirements . . . . . . . . . . . . . . . . . . . . . . . . . 26
3.2.2
Environmental requirements . . . . . . . . . . . . . . . . . . . . . . . 28
3.3
Selection of communication solution . . . . . . . . . . . . . . . . . . . . . . 32
3.4
Selection of real-time system . . . . . . . . . . . . . . . . . . . . . . . . . . 33
3.5
3.4.1
Hardware . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33
3.4.2
Runtime Environment . . . . . . . . . . . . . . . . . . . . . . . . . . 35
Specified development procedure . . . . . . . . . . . . . . . . . . . . . . . . 37
4 Implementation
39
4.1
Architecture of Protection System . . . . . . . . . . . . . . . . . . . . . . . 39
4.2
Protection Algorithm . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 40
4.3
4.2.1
Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 40
4.2.2
Signal Processing Element . . . . . . . . . . . . . . . . . . . . . . . . 42
4.2.3
Definite-time Directional Overcurrent Protection - PDOC . . . . . . 45
4.2.4
Definite-time Directional Earth Fault Protection - PDEF . . . . . . 50
4.2.5
Phase Selector . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 54
4.2.6
Trip Element - PTRC . . . . . . . . . . . . . . . . . . . . . . . . . . 57
4.2.7
EtherCAT-Communication . . . . . . . . . . . . . . . . . . . . . . . 58
Target System . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 59
4.3.1
Kernel configurations
. . . . . . . . . . . . . . . . . . . . . . . . . . 60
4.3.2
EtherCAT-Master . . . . . . . . . . . . . . . . . . . . . . . . . . . . 60
5 Evaluation
63
5.1
Evaluation Method . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 63
5.2
Functional Performance Tests . . . . . . . . . . . . . . . . . . . . . . . . . . 64
5.3
5.4
5.2.1
Model- & Software-in-the-Loop . . . . . . . . . . . . . . . . . . . . . 64
5.2.2
Hardware-in-the-Loop . . . . . . . . . . . . . . . . . . . . . . . . . . 80
Type Tests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 82
5.3.1
Accuracy of pick-up and drop-o↵ value . . . . . . . . . . . . . . . . . 83
5.3.2
Determination of reset ratio . . . . . . . . . . . . . . . . . . . . . . . 84
5.3.3
Steady state errors of start and operate time . . . . . . . . . . . . . 85
5.3.4
Steady state errors of disengaging and reset time . . . . . . . . . . . 87
5.3.5
Transient overreach
5.3.6
Overshoot time . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 91
5.3.7
Accuracy of directional element . . . . . . . . . . . . . . . . . . . . . 91
. . . . . . . . . . . . . . . . . . . . . . . . . . . 89
Evaluation of realtime performance . . . . . . . . . . . . . . . . . . . . . . . 92
5.4.1
Distribution of start time . . . . . . . . . . . . . . . . . . . . . . . . 93
v
5.4.2
5.5
Distribution of operate time . . . . . . . . . . . . . . . . . . . . . . . 94
Environmental compatibility of I/O modules . . . . . . . . . . . . . . . . . 96
6 Conclusion and Discussion
100
6.1
Conclusion
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 100
6.2
Future Work . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 100
Bibliography
101
Appendix
106
vi
List of Figures
2.1
Three important knowledge domains for this thesis . . . . . . . . . . . . . .
3
2.2
Simplified protection function block diagram
. . . . . . . . . . . . . . . . .
5
2.3
Process interface: hard-wired vs. communication network . . . . . . . . . .
6
2.4
Short-circuit current of a far-from-generator fault . . . . . . . . . . . . . . .
7
2.5
Equivalent circuit digram for a single-phase to earth fault for low-impedance
earthing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
2.6
Equivalent circuit digram for a single-phase to earth fault for resonance
earthing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
2.7
Equivalent circuit digram for a single-phase to earth fault for a isolated
neutral . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
2.8
Parameters of a real-time task . . . . . . . . . . . . . . . . . . . . . . . . . . 15
2.9
Logical versus temporal concurrency . . . . . . . . . . . . . . . . . . . . . . 16
2.10 Feasibility of EDF versus RMS . . . . . . . . . . . . . . . . . . . . . . . . . 18
2.11 Protocol processing within EtherCAT Slaves . . . . . . . . . . . . . . . . . . 19
2.12 EtherCAT Frame . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
2.13 Communication protocols defined in IEC 61850 . . . . . . . . . . . . . . . . 21
2.14 Structure of modelled SV APDU/ASDU & its encapsulation in Ethernet . . 22
3.1
Model-based design is applicable to V-model . . . . . . . . . . . . . . . . . 24
3.2
Number of defects found shifts to earlier stage of development process . . . 26
3.3
Independent time characteristic . . . . . . . . . . . . . . . . . . . . . . . . . 27
3.4
Definite time reset characteristic . . . . . . . . . . . . . . . . . . . . . . . . 28
3.5
Di↵erent EMC requirements for corresponding areas within a substation . . 31
3.6
Quad-core architecture without hyper-threading . . . . . . . . . . . . . . . . 34
3.7
Overview of Linux distribution . . . . . . . . . . . . . . . . . . . . . . . . . 37
3.8
Specified development procedure . . . . . . . . . . . . . . . . . . . . . . . . 38
4.1
Centralised architecture of protection system . . . . . . . . . . . . . . . . . 40
4.2
Overview of protection algorithm . . . . . . . . . . . . . . . . . . . . . . . . 41
4.3
Implemented signal processing algorithm . . . . . . . . . . . . . . . . . . . . 43
4.4
Developed signal processing block and mask . . . . . . . . . . . . . . . . . . 45
4.5
Developed PDOC block and mask . . . . . . . . . . . . . . . . . . . . . . . 46
vii
4.6
Characteristic of directional element . . . . . . . . . . . . . . . . . . . . . . 47
4.7
Definite-time curve of PDOC with 4 stages . . . . . . . . . . . . . . . . . . 49
4.8
Developed PDEF block and mask . . . . . . . . . . . . . . . . . . . . . . . . 50
4.9
Voltage profiles of V2 and 3V0 for ground faults . . . . . . . . . . . . . . . . 52
4.10 Developed phase selector block and mask . . . . . . . . . . . . . . . . . . . 55
4.11 Fault pattern: (a) Positive vs. negative sequence (b) Negative vs. zerosequence . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55
4.12 Scheme of voltage-based phase selector for weak-infeed conditions . . . . . . 56
4.13 Developed PTRC block and corresponding mask . . . . . . . . . . . . . . . 57
4.14 Etherlab library developed by IgH . . . . . . . . . . . . . . . . . . . . . . . 59
4.15 Concurrent access of EtherCAT master
. . . . . . . . . . . . . . . . . . . . 61
4.16 Architecture of IgH EtherCAT master . . . . . . . . . . . . . . . . . . . . . 62
5.1
Functional performance test . . . . . . . . . . . . . . . . . . . . . . . . . . . 64
5.2
Single-line-diagram of first network . . . . . . . . . . . . . . . . . . . . . . . 65
5.3
Single-line-diagram of second network with parallel lines . . . . . . . . . . . 65
5.4
Fault situation of case 1 for MiL . . . . . . . . . . . . . . . . . . . . . . . . 67
5.5
Fault situation of case 1 for SiL . . . . . . . . . . . . . . . . . . . . . . . . . 68
5.6
Fault situation of case 2 for MiL . . . . . . . . . . . . . . . . . . . . . . . . 70
5.7
Fault situation of case 2 for SiL . . . . . . . . . . . . . . . . . . . . . . . . . 71
5.8
Fault situation of case 3 for MiL . . . . . . . . . . . . . . . . . . . . . . . . 73
5.9
Fault situation of case 3 for SiL . . . . . . . . . . . . . . . . . . . . . . . . . 74
5.10 Fault situation of case 4 for MiL . . . . . . . . . . . . . . . . . . . . . . . . 75
5.11 Fault situation of case 4 for SiL . . . . . . . . . . . . . . . . . . . . . . . . . 76
5.12 Fault situation of case 5 for MiL . . . . . . . . . . . . . . . . . . . . . . . . 77
5.13 Fault situation of case 5 for SiL . . . . . . . . . . . . . . . . . . . . . . . . . 78
5.14 Fault situation of case 6 for MiL . . . . . . . . . . . . . . . . . . . . . . . . 79
5.15 Fault situation of case 6 for SiL . . . . . . . . . . . . . . . . . . . . . . . . . 80
5.16 Laboratory setup for the Hardware-in-the-loop test . . . . . . . . . . . . . . 81
5.17 Distribution of start time for di↵erent
If ault
Iset
ratios . . . . . . . . . . . . . . 86
5.18 Measured operate time for a setting of (a) instantaneous & (b) 600 ms . . . 87
5.19 Measured operate time for a setting of 3 s . . . . . . . . . . . . . . . . . . . 87
5.20 Distribution of disengaging time for di↵erent
IpostF ault
Iset
ratios . . . . . . . . . 88
5.21 Measured operate time for a setting of (a) 50 ms & (b) 600 ms . . . . . . . 89
5.22 Measured operate time for a setting of 3 s . . . . . . . . . . . . . . . . . . . 89
5.23 Typical test waveform for transient overreach . . . . . . . . . . . . . . . . . 90
5.24 Ports of equipment under test . . . . . . . . . . . . . . . . . . . . . . . . . . 96
viii
List of Tables
2.1
Used COTS components and their corresponding licenses . . . . . . . . . .
4
2.2
Voltage factor according to IEC 60909-0 . . . . . . . . . . . . . . . . . . . .
9
2.3
Characteristic of di↵erent neutral point treatments . . . . . . . . . . . . . . 13
2.4
Logical nodes and functional numbers for the protection functions . . . . . 21
3.1
Characterisation of the electromagnetic phenomena . . . . . . . . . . . . . . 30
3.2
Normal environmental conditions . . . . . . . . . . . . . . . . . . . . . . . . 32
3.3
Hardware configuration of target system . . . . . . . . . . . . . . . . . . . . 34
4.1
Settings for signal processing element . . . . . . . . . . . . . . . . . . . . . . 45
4.2
Available sequence components during di↵erent fault scenarios . . . . . . . 47
4.3
Settings for directional element of PDOC . . . . . . . . . . . . . . . . . . . 48
4.4
Settings for the definite-time curve of PDOC . . . . . . . . . . . . . . . . . 49
4.5
Available sequence components during ground faults . . . . . . . . . . . . . 51
4.6
Di↵erent cases for virtual polarisation . . . . . . . . . . . . . . . . . . . . . 52
4.7
Settings for directional element of PDEF . . . . . . . . . . . . . . . . . . . . 53
4.8
Settings for the definite-time curve of PDEF . . . . . . . . . . . . . . . . . . 54
4.9
Settings for the phase selector block . . . . . . . . . . . . . . . . . . . . . . 57
4.10 Settings for the PTRC block . . . . . . . . . . . . . . . . . . . . . . . . . . 58
4.11 Configuration of the communication driver blocks and supervision . . . . . 59
5.1
General configuration for the functional performance test . . . . . . . . . . 66
5.2
Configuration of application for case 1 . . . . . . . . . . . . . . . . . . . . . 69
5.3
Configuration of application for case 2 . . . . . . . . . . . . . . . . . . . . . 72
5.4
Configuration of application for case 3 . . . . . . . . . . . . . . . . . . . . . 74
5.5
Configuration of application for case 4 . . . . . . . . . . . . . . . . . . . . . 76
5.6
Configuration of application for case 5 . . . . . . . . . . . . . . . . . . . . . 78
5.7
Configuration of application for case 6 . . . . . . . . . . . . . . . . . . . . . 80
5.8
Comparison between Hil and Sil results (PDOC) . . . . . . . . . . . . . . . 82
5.9
Comparison between Hil and Sil results (PDEF) . . . . . . . . . . . . . . . 82
5.10 Type test results of common relays on the market for PDOC function . . . 83
5.11 Average & maximum error of pick-up/drop-o↵ for 10 di↵erent test points . 84
5.12 Average and minimum value of reset ratio . . . . . . . . . . . . . . . . . . . 85
ix
5.13 Results of the transient overreach test acc. to IEC 60255-151 . . . . . . . . 90
5.14 Results of overshoot time test acc. to IEC 60255-151 . . . . . . . . . . . . . 91
5.15 Ramping test to determine the accuracy of the directional elements . . . . . 92
5.16 Distribution of start time for di↵erent setups of runtime environment . . . . 94
5.17 Worst-case start time for di↵erent setups of runtime environment . . . . . . 94
5.18 Distribution of operate time for di↵erent setups of runtime environment . . 95
5.19 Worst-case operate time for di↵erent setups of runtime environment . . . . 96
5.20 Comparison between IEC 61000-6-5 and IEC 61000-6-2 for enclosure port . 97
5.21 Comparison between IEC 61000-6-5 and IEC 61000-6-2 for d.c. power ports 98
5.22 Comparison between IEC 61000-6-5 and IEC 61000-6-2 for signal ports . . . 99
x
Nomenclature
ANSI American National Standards Institute
APDU Application Protocol Data Unit
ASDU Application Service Data Unit
COMTRADE Common format for Transient Data Exchange for power systems
COTS Commercial O↵-the-Shelf
CPU Central Processing Unit
EDF Earliest Deadline First
EMC Electromagnetic Compatibility
ESC EtherCAT Slave Controller
DC Distributed Clock (EtherCAT domain)
DFT Discret Fourier Transformation
DMS Direct Memory Access
FIFO First-in-First-out
GNU General Public License
GOOSE Generic Object Oriented Substation Event
GSSE Generic Substation Status Event
GUI Graphical User Interface
HiL Hardware-in-the-Loop
HMI Human-Machine-Interface
IEC International Electrotechnical Commission
IED Intelligent Electronic Device
xi
IEEE Institute of Electrical and Electronics Engineers
IRQ Interrupt Request
LVDS Low Voltage Di↵erential Signaling
MiL Model-in-the-Loop
MTA Maximum Torque Angle
NIC Network Interface Card
OEM Original Equipment Manufacturer
PDO Process Data Object
RMS Root Mean Square (Electrical domain)
RMS Rate Monotonic Scheduling (Real-Time domain)
RR Round-Robin
SEI Software Engineering Institute
SiL Software-in-the-Loop
SV Sampled Value
Electrical nomenclature
u: small letters are used for instantaneous values
U : capital letters are used for RMS values
U : underline capital letter is used for complex numbers
U a , U b , U c : phase values are indicted by the subscript a,b,c
U 1 , U 2 , U 0 : symmetrical components are indicted by the subscript 1,2,0
Linux nomenclature
Typewriter font is used for command line output
Bold typewriter font is used for command line inputs
0xFFFF: hexadecimal values are used for data values and addresses
$: the dollar sign is used for shell commands, which require user privileges
#: the mesh sign is used for shell commands, which require superuser privileges
xii
Chapter 1
Introduction
1.1
Problem Definition
Today’s power systems face dramatically changes and challenges. The conventional design
of the power system is based on a controllable and bulk generation of power, which is then
transmitted over the transmission and distribution grid to the consumers. Based on these
characteristics of the grid, various power system stability studies have been performed as
well as the protection systems have been designed. Nevertheless these assumptions have
started to change and for some systems they have already changed. This development
is mainly driven by the replacement of centralised large-scale power generation with distributed medium- to small-scale power generation, based on renewable energy sources like
wind or solar. A high penetration of distributed generation leads to an altered behaviour
of the power system. This change of generation has a major impact on several di↵erent
energy fields, such as energy markets and regulations, power system planning, power system operation or power system stability and protection. The thesis focuses on the latter.
At the same time utilities have to deal with an increased pressure to reduce costs. This
is especially true for operators of distribution grids. Moreover the distribution grid is the
part of network, which is influenced the most by the changes of the power system described
above. Having tight cost restraints on the one side and on the other side an increased
demand for new protection systems in order to handle the high penetration of distributed
generation, the market requires a cost-efficient protection system, which performs in a
reliable and stable manner.
1.2
Objectives
The objective of the Master’s thesis is to develop a protection system, which relies entirely
on Commercially-o↵-the-Shelf (COTS) components. Thereby it is shown that the time to
market of the development process can be reduced without jeopardising the reliability and
security performance. A directional overcurrent function as well as a directional earth fault
1
protection is developed in order to show the performance of the COTS based protection
system. Its performance is compared to proven IEDs on the market. The directional overcurrent and earth fault protection are two types of functions, which are widely employed
in the distribution grids and therefore seen as justifiable choice as the preferred protection
function for this thesis. Moreover the directional element will be of greater importance in
the future due to the bidirectional power flow caused by the distributed generation.
In order to fulfil the demanding environmental constraints in terms of electromagnetic
compatibility (EMC), vibration, shock, moisture and temperature, the I/O modules are
separated from the computing unit. This approach has the advantage that only the measuring units have to be compliant to the harsh environmental constraints, where as the
computing unit is located in a location with less stringent requirements. This setup requires a fast and a deterministic communication solution between the I/O modules and
the computing unit. Moreover, the described design of the protection system leads to a
centralised architecture.
The thesis is seen as a proof of concept and therefore has certain limitations. Firstly,
the current inputs are limited to a maximum current of 1 A (RMS). Normally, secondary
short-circuit currents can rise above 50 A. In addition, the EMC performance of I/O modules is analysed based on data sheets and EMC standards. Thus no actual EMC tests are
performed due to the lack of suitable equipment. Moreover the functional performance
tests of the implemented protection functions are restricted to six di↵erent fault scenarios
due to time constraints. None the less, the fault scenarios have been carefully selected in
order to represent real-case scenarios.
1.3
Outline of the Thesis
The Master’s thesis is mainly divided into five di↵erent parts. First the necessary background knowledge is given in order to better understand the developed protection system.
This part also consists of some references to related work, which has already been performed by other entities. Then the applied methodology of development is explained as
well as the requirements of a directional overcurrent and earth fault protection according
the corresponding IEC standards are described. In the third part of the thesis the actual
implementation of the protection algorithm is explained as well as the overall setup. The
fourth part evaluates the performance of the COTS-based protection system and compares
it with conventional IEDs. In particular a type test is performed in order to check, if the
protection system behaves according to the IEC standard, as well as a functional test is
executed. Moreover a stability test is carried out in order to investigate the long-term
performance. In the last part a discussion on future work is given as well as a conclusion
is stated, which comprised the results of this thesis.
2
Chapter 2
Background
The developed protection system is based on commercial-o↵-the-shelf components. Therefore a definition of these type of components is given. Moreover, for a better understanding
of the later explained protection function, a brief introduction is given to the field of power
system protection. In addition, the protection function eventually requires to run on a
target system and to fetch measurements via a communication network. Therefore these
fields of research are concisely introduced as well. The figure 2.1 depicts those three important domains, which are considered throughout the thesis. Lastly the related work to
those domains is analysed.
Figure 2.1: Three important knowledge domains for this thesis
2.1
Commercial-o↵-the-shelf
Commercial-o↵-the-shelf (COTS) components can be considered as either hardware or software. These components are ready-made and available to the general public. COTS-based
hardware and software can be directly used in large system, without any own development e↵orts. COTS-based systems are seen as a convenient approach for a reduced time
3
to market and a competitive approach compared to developing everything from scratch.
In general COTS components can be bought directly, leased or they are licensed to the
general public. Especially the first and the last case will be of importance in this project
[42].
The table 2.1 below depicts the COTS software components, which are used in this project,
as well as their corresponding licenses.
COTS components
License
Vanilla kernel
GNU General Public License, version 2
Preeempt-rt patch
GNU General Public License, version 2
Ubuntu desktop
GNU General Public License
EtherLAB library
GNU General Public License, version 3
IgH EtherCAT-Master
GNU General Public License, version 2
PdCom library
GNU Lesser General Public License, version 3
PdServ library
GNU Lesser General Public License, version 3
Matlab/Simulink
Di↵erent commercial licenses
Table 2.1: Used COTS components and their corresponding licenses
2.2
Power System Protection
Power system protection is a key issue to ensure a reliable and secure operation. Therefore
the general requirements of a protection system are described below. Since the implemented function is a directional overcurrent as well as an earth fault protection, di↵erent
system grounding designs are explained below. The influence of various grounding techniques on the fault characteristic is essential when developing an earth fault protection.
2.2.1
General objectives of protection systems
Each protection system in the power system has to fulfil certain general objectives. Those
are selectivity, reliability, sensitivity and speed. Selectivity is achieved, if only the faulty
part of the power system is isolated. There are di↵erent techniques in order to obtain
selectivity [41].
• Magnitude of the fault current
• Time grading
• Direction of fault power flow
Reliability refers to the ability of the protective device to operate, when it is supposed
to operate, and otherwise to remain una↵ected. There are two other terms found in the
4
literature, which refer to the same requirement. Dependability describes that the relay
operates in a selective manner in case of a fault. On the other hand security is the requirement, that the protection system does not trip its protected unit for external faults.
External faults are regarded as faults, which lie outside of the corresponding protection
zone [41].
Sensitivity is the ability of the protection device to pick up small deviations of the system
parameters and react to them. Lastly speed refers to the operating speed, which is the
time between the occurrence of the fault and the trip command. Nevertheless the total
clearing time is longer, since it includes operating time of the circuit breaker as well as
the process of arc extinguishing [41].
2.2.2
Setups of Protection Systems
All protection system have the same general procedure of operation. First the input
energising quantities are obtained, which usually consist of currents and voltages. These
quantities are provided either directly by the voltage and current transformers (VT/CT)
or by a data packet via a communication network. According to IEC 60255-1 the preferred
rated RMS secondary voltages are 100 V, 110 V, 115 V, 120 V, 200 V, 230 V and the
preferred rated RMS secondary currents are either 1A or 5A. Lower current values can
also be used according to IEC 60044-8. Secondly the input quantities need to be run
through a measurement element, which extracts the required type of measurement (e.g.
True RMS, RMS of 50Hz component, phasors etc.). Thirdly these measured values are
compared to thresholds or other characteristics. If the logic is fulfilled, the time delays
are added and finally the trip command is issued. The figure 2.2 below is taken from the
overcurrent function standard IEC 60255-151 and illustrates the described procedure [2].
Figure 2.2: Simplified protection function block diagram [2]
In general there are two di↵erent setups to connect the protection system to the process.
5
The conventional approach is to connect the instrument transformers directly to an analog input module of the relay. This has the advantage that the protection application is
located rather close to process and therefore is able to react with only small delays. The
disadvantages of this approach are the increased wiring e↵orts and engineering costs. In
the recent years a new setup has become popular, which involves a process bus between the
protection relay and the instrument transformers and circuit breakers. The current and
voltage transformers are interfaced via a merging unit, which will send the measurements
via a sampled value stream to the protection relay. This approach has the advantage, that
the protection device is able to receive not only measurements from its respective bay,
but also from other bays within the substation. Another advantage is the substantially
decreased wiring e↵orts. Nevertheless replacing wires with a network infrastructure requires stringent latency and synchronisation requirements in order to operate in a correct
manner. The figure 2.3 depicts those two protection system setups.
IED
IED
IED
COPPER
WIRES
COMMUNICATION
NETWORK
IED
Switch'
MU'
MU'
POWER
SYSTEM
Figure 2.3: Process interface: hard-wired vs. communication network
2.2.3
Fault current calculation
The expected short-circuit currents in the power system are one of the most important
design parameters for almost all primary equipments. This is due to the fact that the
current is directly correlated to the magnetic forces exposed on the equipment as well as
the generated thermal energy [43]. Usually the maximum as well as the minimum possible
short-circuit currents are calculated for the corresponding power system. The maximum
short-circuit current is the design parameter for the primary equipment as explained above.
Nevertheless the minimum short-circuit current is of importance for the protection system, since this is the current, which defines the minimum setting of the protection relay.
This minimum short-circuit parameter defines the sensitivity requirement for protection
6
systems, as described in section 2.2.1.
There are two main standards, which describe the short-circuit calculations for three-phase
a.c. systems. The ANSI C37 and the IEC 60909. The following description focuses on
the IEC standard [43]. At this point it is mentioned that transmission lines of 550 kV
and higher need special consideration, which are not defined in IEC 60909. In general a
short-circuit is described by being either close to a generator or far-away. The di↵erence
is that a short-circuit close to a generator consists of a decaying a.c. and d.c component, where as a short-circuit far-away from the generator only consists of a decaying d.c
component and a constant a.c component. In the figure 2.4 a typical characteristic of a
far-from-generator-short-circuit is depicted, which is described by the equation (2.1).
Figure 2.4: Short-circuit current of a far-from-generator fault [1]
In the figure above Ik00 refers to the initial (symmetrical) short-circuit current, ip equals
the peak short-circuit current, A is the initial dc component and Ik is the steady-state
short-circuit current. Moreover it can be seen that the a.c. component is constant, as
characterised for a far-from-generator fault.
i(t) = is (t) + it (t)
p
2U
=
sin(!t +
Zk
✓) +
h p2 U
Zk
Where
7
sin(✓
i
) + i(0)+ e(
t/⌧ )
(2.1)
⇣c U ⌘
n
U : Equivalent voltage source p
3
c : Voltage factor acc. to table 2.2
⇣p
⌘
Zk : Short-circuit impedance
R2 + X 2
: Angle of voltage, when fault occurs
⇣
⇣ ! L ⌘⌘
✓ : Angle of Z k tan 1
R
⇣L
X/R ⌘
⌧ : Time constant
=
R
!
+
i(0) : Initial load current
One can see that the depicted short-circuit consists of a steady-state component is (t) as
well as a transient component it (t). This far-from-generator short-circuit can be described
by a sinusoidal current with a decaying d.c component. The highest instantaneous value
of the short-circuit current depends on the time constant as well as the angle . It can be
shown that the maximum value is reached, when
i(0)+
equals
max ,
if the initial load current
is neglected. From equation (2.2) and assuming a purely inductive short-circuit
impedance Zk , the highest o↵set occurs at the zero-crossing of the voltage [7].
max
=✓
⇡
2
(2.2)
The standard IEC 60909 is based on some assumptions, which are stated below [1].
• Type of fault remains constant during fault duration (e.g. initial single-phase-toearth fault does not evolve to line-line-to-earth fault)
• No change of network topology and parameters occurs during time of short-circuit
• No arc resistance are considered
• Shunt capacitances and shunt admittances (loads) are neglected for the positive- and
negative sequence network.
• Shunt capacitance are only omitted for e↵ectively grounded systems, that means
that the earth fault factor
is smaller than 1.4
The general procedure for the calculation of short-circuit current is given by the following
steps [43].
1. Obtain one-line diagram with the following information of all primary equipment:
base MVA Sbase , base voltage Un , positive-, negative-, zero-sequence-impedance
(Z 1 , Z 2 , Z 0 ) as well as the neutral connection of each transformer and generator
2. Derive the positive, negative and zero-sequence network as seen from the faulty bus
8
3. Connect sequence networks according to type of fault (e.g. for single-phase to ground
fault, all sequence networks are connected in series)
4. Obtain equivalent voltage source at faulty bus according to
cpUn
,
3
where c is a voltage
factor found in table 2.2
5. Calculate initial symmetrical short-circuit current Ik00
From the above steps it can be seen that an equivalent voltage source at the fault location
is used together with a correction factor c. This approach is applied in the IEC 60909 in
order to avoid to run a large number of load flow calculations, which then yield the pre-fault
voltage. The voltage factor c considers various aspects, such as voltage variations due to
time and place of the fault or subtransient behaviour of generators or motors. Calculations
of c are found in IEC 60909-1. The IEC standard 60909-0 considers a symmetrical threephase fault as well as the following unbalance faults [1].
• line-to-line short circuit
• line-to-line short circuit with earth connection
• line-to-earth short circuit
Nominal Voltage
Maximum short-circuit
Minimum short-circuit
currents
currents
cmax
cmin
100 V to 1 kV
1.05
0.95
IEC 60038, table I
1.10
Un
Low Voltage
Medium Voltage
>1 kV to 35 kV
IEC 60038, table III
1.10
1.00
High Voltage
>35 kV
IEC 60038, table IV
Table 2.2: Voltage factor according to IEC 60909-0 [1]
As explained above, the protection systems need to consider the minimum possible shortcircuit current in order to achieve maximum sensitivity. Therefore the following considerations should be applied, when calculating the short-circuit current [1].
• Choose cmin according to table 2.2
9
• Choose network topology with minimum contribution to short-circuit from generators
• Motors are neglected
• Resistance of line is taken with maximum allowable conductor temperature
A single-line-to-earth fault is by far the most frequent type of faults [26]. Considering
a far-from-generator fault Z1 = Z2 and a high zero-sequence impedance
Z0
Z1
> 3, the
single-phase-to-earth fault will yield the smallest short-circuit current in comparison to
the other types of faults (e.g. three-phase, line-line). Considering the short-circuit in
figure 2.1, the following formulas are applied to calculate the initial RMS value of the
00 and the breaking current I
short-circuit Ik1
b1 of a single-phase-earth fault. The subscript
1 refers to ”single-phase-to-earth”.
I 00k1
=
p
3 cUn
Z1 + Z2 + Z0
I b1 = I 00k1
(2.3)
(2.4)
From the equation 2.4 it can be seen, that for a far-from-generator fault the short-circuit
breaking current equals the initial RMS value of the short-circuit current. This is due to
the fact, that the a.c. component of the short-circuit is constant.
Above a brief introduction to the short-circuit calculation of far-away-from-generator faults
is given. An extended short circuit study for near-to-generator short circuits and for different fault types is found in the IEC 60909-0.
2.2.4
System Grounding
In the previous section the general approach of short-circuit calculation is explained. Since
the most frequent faults are earth faults, it is important to understand the influence of
di↵erent grounding techniques on the earth fault current magnitude as well as on the
change in voltage of the healthy lines. In principal there are four di↵erent characteristics of neutral point treatment, which are low-impedance earthing, earthing with current
limitation, resonance earthing and isolated neutral, which are explained below. Power
systems above 132 kV are usually low-impedance earthed. Nevertheless all other types of
system groundings are found in distribution grids. Especially isolated networks are often
found in industrial power systems due to their high availability, as shown below. From the
equations (2.5) and (2.6) it can be seen, that there is a trade-o↵ between low short-circuit
currents and high voltages on the healthy phases [26].
|U b | = |U c | = Un
10
p
k2 + k + 1
2+k
(2.5)
Un
3
00
Ik1
=p
3 Z1 2 + k
(2.6)
Where
k=
Z0
Z1
Un : Nominal system voltage
Ub ; Uc : Voltages of healthy phases
00
Ik1
: Single-line-to-earth fault of phase a
The type of neutral point treatment is directly related to the zero-sequence impedance.
00 decreases and
From the variable k it can be seen, that for higher Z0 the earth fault Ik1
the voltage of the healthy lines increases, and vice versa for lower Z0 .
Low-impedance earthing: Neutral points, which are low-impedance earthed, are solidly
earthed without any intentional resistance or reactance. This is the most common earthing
Short-circuit currents
technique for high voltage systems, since the 100
voltage
on the healthy lines remains below
(a) Z
0; Z1; Z2
1.4 Un at the expense of an increased short-circuit current
during
a fault. 1.4 is the earth
fault factor
and it is defined as the ratio between the maximum RMS value of the over-
voltage during a fault and the rated voltage of the line. The figure 2.5 shows an equivalent
I
B
Y
R
R
circuit digram (a) as well as the series connection of the symmetrical components
network
UY; UB
(b) in case of a single-phase to earth fault.
I1
(b)
Z1
E1 = E 0
U1
01
I2
Z2
U2
02
I0
Z0
U0
00
Figure 5.1
Equivalent circuit diagram of a single-phase short-circuit (system with
Figure 2.5: Equivalent circuit digram for a single-phase
to earth earthing).
fault for
low-impedance
(a)low-impedance
Diagram in RYB-system, (b) equivalent
circuit diagram in the system of symmetrical components
earthing [43]
with voltage factor c according to Table 4.1. If the single-phase short-circuit current
is related to the three-phase short-circuit current
c ∗ Un earthing, a reactance or resisCurrent limiting earthing: In case of currentI ′′limiting
=√
k3
3∗Z
(5.2)
tance is placed between the neutral point and the ground.1 The objective of this type of
it follows that
neutral point treatment is the reduction of the earth
Nevertheless this leads
I ′′ fault
3 ∗current.
Z
k1
′′
=
1
I k3
2 ∗ Z 1 + Z 0 earthing is mainly applied
to an increase earth fault factor . Therefore current
limiting
(5.3)
The relation of single-phase to three-phase short-circuit current depending on the
in networks, which have a nominal voltage Unratio
below
/Z0 kV
with [43].
the difference of phase angles (γ1 − γ0 ) of the impedances
of Z120
as parameter is outlined in Figure 5.2. The phase angles γ1 and γ0 are defined
by the arcustangens-function γ1 = arctan(X1 /R1 ) in the positive-sequence system
11 respectively γ0 = arctan(X0 /R0 ) in the zero-sequence system.
Influence offormers
neutralthrough
earthing
109 (Petersen-coils), normally adjustable, which will be
reactances
resonance to the phase-to-earth capacitances of the system. The principal arrange
80system
per cent
ofresonance earthing is outlined in Figure 5.10.
MV-systems having nominal voltages Un = 10–30 kV and
of nearly
a power
with
110-kV-systems are operated with resonance earthing (Criteria:The
Total
line
lengths).
impedances of transformers and lines of the positive-sequence compone
Some MV-systems are operated with a combined schemebeofneglected
resonance
earthingwith those of the zero-sequence component due to the
compared
under normal operating conditions and low-impedance earthing
in
case
of
earthof magnitude of the
impedances. The admittance of the zero-sequence compon
fault. Resonance earthing, therefore, is the dominating type of system earthing in
Resonance
earthing:
earthing
is achieved
by
Germany for
power systems
with voltageResonance
10 kV up to 110
kV. In other
countries
suchplacing a controllable reac(a)
~
B (L3)
as India, South
Africa
and
China,
power
systems
with
resonance
earthing
have
gained
tance between the neutral point and the earth potential. This controllable reactance is
an increasing importance during the last decades, however are still not so common
Y (L2)
~
a Peterson
coil. The reason of resonance earthing is to limit to capacitive fault
as systemsusually
with low-voltage
earthing.
~
R (L1)
Resonance
earthing
is realiseditbywith
earthing
of one or current
several neutrals
of the
transcurrent
by opposing
a inductive
through
Peterson coil. The figure 2.6
U
formers through reactances (Petersen-coils), normally adjustable, which will be set
E =in n
GE sethe equivalent
circuit (a)
and
its sequence
network
(b). The
positive and negative
3
resonance shows
to the phase-to-earth
capacitances
of the
system.
The principal
arrangement
CE
of a powerquence
system with
resonance
is outlined
5.10.small in comparison to the zero-sequence
impedance
is earthing
neglected,
since itin isFigure
relative
The impedances of transformers and lines of the positive-sequence component canU
0
LD resonance
impedance.
From
figure
(b) it can be
seen that
circuit is created,
be neglected
compared with
those
of the2.6
zero-sequence
component
dueatoparallel
the order
of magnitude
of the
impedances.can
The be
admittance
of the
is
which
admittance
described
byzero-sequence
the equationcomponent
(2.7) [43].
310
(a)
~
~
B (L3)
(b)
Y (L2)
~
R (L1)
E =
LD
~
E1
01/02
Un
GE
3
CE
3RD
U0
3LD
GE
310
CE
U0
00
(b)
System with resonance earthing, earth-fault in phase R. (a) Equiv
Figure 2.6: Equivalent circuit digram Figure
for a 5.10
single-phase
to earth fault for resonance
~
diagram in RYB-system and (b) equivalent diagram in the syst
symmetrical components
E1
earthing [43]
01/02
3RD
GE
⇣
Y 0 = j! CE 1
CE
U0
⌘
1
1
+ GE +
3! 2 LD CE
3 RD
(2.7)
3LD
In order to
yield minimum earth fault currents, maximum impedance need to be obtained.
This is done by minimising 00
the imaginary part of the admittance in equation (2.7) for the
system frequency of 50 Hz in European networks. The tuning of LD is done by changing
Figure 5.10
System with resonance earthing, earth-fault in phase R. (a) Equivalent
the diagram
tap position
of the Peterson
coil. Thediagram
resonance
in RYB-system
and (b) equivalent
in theearthing
system ofis widely applied in Central
symmetrical components
European power systems. In Nordic countries the resonant earth systems become more
popular due to the increase cable networks and their high capacitive fault currents [28].
Isolated neutral: The forth type of neutral point treatment is the isolated neutral.
In this case the neutral point is floating. The main application of isolated neutrals are
industrial power systems. In case of single-phase to earth fault only capacitive fault current flows (neglecting the conductances G). This capacitive fault current ICE is usually
smaller than the nominal load current. In such an event the neutral point rises to the
phase-to-ground voltage of the faulty line and therefore the voltage of the healthy lines
p
increases by 3. Thus the insulation requirements for isolated neutral systems are much
higher than for low-impedance earthed networks. The corresponding circuit diagrams for
this described single-phase to earth fault are depicted in the figure 2.7.
12
0 The
1
k1
analysis of a single-phase earth-fault is based on Figure 5.6.
is required. The earth-fault factor in this case will be δ = 1.44–1.61. By this, the
system is no longer a system with low-impedance earthing.
(a)
5.4
~
B (L3)
~
Y (L2)
~
PowerFor
system
with isolated
neutral
low-voltage
systems,
which require a high availability, isolated neutral systems are
R (L1)
U
E = n
contact
voltage
3in
to
systems
applied.
due to neutrals
the factisthat
if the
case of a single-phase
GE
The operationmostly
of power
systemsThis
withisisolated
applicable
CE
with nominal fault
voltages
up
to
60
kV,
however
the
main
application
is
seen
in
power
is less than 50 V (acc. to IEC 60364), the fault does not have to be cleared right away.
station auxiliary installations and industrial power systems with voltages up to 10 kV.
This
type isolated
of neutral
point
for low-voltage systems is compulsory for hospitals
In public supply
systems,
neutrals
are treatment
not very common.
The analysis
of
a
single-phase
earth-fault
is
based
on
Figure
5.6.
in France [27].
(a)
~
B (L3)
~
Y (L2)
~
R (L1)
U
E = n
3
GE
(b)
~
E1
01/02
CE
CE U0
GE
00
(b)
Figure 5.6
Power system with isolated neutral with single-phase ear
Figure 2.7: Equivalent circuit digram for a single-phase
to earth
fault
for ainisolated
(a) Equivalent
circuit
diagram
RYB-system and (b) equivalen
~
E1
diagram in the system of symmetrical components
neutral [43]
01/02
Contrary to power systems with low-impedance earthing or earthi
The table 2.3 shows a summarised view of the
di↵erent
characteristics
of the
various types
current
limitation
the capacitances
phase-to-earth
capacitances in the zero-s
of system groundings,
as Cshown
above.
GE
E U0
Low-
Earthing
00
impedance
Figure 5.6
component cannot be neglected in power systems with isolated neutral as
seen from Figure 5.6. To determine the respective parameters of the equ
no-load measurements are necessary. The single-phase earth-fault current, in
Resonance earth-
with current
ing
Power system with earthing
isolated neutral with
single-phase earth-fault.
limitation
(a) Equivalent circuit diagrampin RYB-system andp
(b) equivalent circuit
p
c (3)Un components
c (3)Un
diagram
in
the
system
of
symmetrical
00
00
SP current Ik1 = 2Z +Z
Ik1 = 2Z +Z
I R ⇡ j 3Un ! ⇤
1
0
1
0
CE ( with
0 + jv)
Contrary to power systems with low-impedance earthing or earthing
p
p
p
current limitation
the capacitances<phase-to-earth
capacitances
in3 the zero-sequence
Earth-fault
1.38
1.38
⇡ 3 1.1 3
component cannot be neglected in power systems with isolated neutral as can be
fac.5.6. To determine the respective parameters of the equipment,
seen from Figure
no-load measurements
The single-phase2earth-fault
current, in
k = Z0are necessary.
High
4
>general,
4
Z1
Repetition
Double earth-
of faults
fault
None
Isolated neutral
None
I CE ⇡ j
⇡
p
p
(3)!Ce Un
3
Infinite
Double earth-fault
Table 2.3: Characteristic of di↵erent neutral point treatments [43]
2.3
Real-Time Systems
The protection system need to run in a reliable and deterministic way. Therefore it
is deployed on a real-time operating system. The characteristics of such a system are
described below.
2.3.1
Description
In the literature a real-time system is described as followed:
13
”A real-time computer system is a computer system in which the correctness of
the system behaviour depends not only on the logical results of the computation,
but also on the physical instant at which these results are produced” ([44])
From the quote above it can be noticed that the timing aspect of real-time systems is
of major concern. Therefore the term real-time does not refer to a fast execution of a
program, but rather to its deterministic behaviour. Moreover a real-time system is a
computer system with the following requirements [45]:
• Time requirements (hard vs. soft)
• Time-triggered and event-triggered events
• Concurrent activities
• Digital and analogue signals
Hard vs. Soft Real-Time: The time requirements are distinguished between hard and
soft real-time. Computer systems, which are not allowed to miss a single deadline, are
regarded as hard real-time. On the other hand, if the system still operates reliable and
securely in case of occasional missed deadlines, it is described as soft real-time.
Events: Moreover a real-time system need to handle events. Events can be either periodic
or aperiodic and internal or external. An example for an external aperiodic event would
be a received ethernet frame by the network interface card (NIC). The computer system
handles those events by the means of tasks (see 2.3.2).
Concurrent activities: Real-time systems are able to react to co-concurrent events.
The required tasks to handle those events are either multiplexed on a single CPU (singlethreading) or run on several CPU cores at the same time (multi-threading). Therefore
some scheduling policies (see 2.3.3) and interrupts (see below) are needed.
Signals: It is obvious that the real-time system need a interface to the process, which its
controls, in order to receive information in the form of digital or analogue measurements.
Those information can either be obtained by a dedicated I/O module or via a network
interface card.
Moreover it is important to understand the function of the kernel. The kernel is the
main entity of the operating system, which represent the interface between the hardware
and the application. The kernel has mainly four important components [8]:
• Scheduler: The role of the scheduler is to allocate processors time to di↵erent task
according to the scheduler policy (see 2.3.3)
• Interrupt handler: The interrupt handler manages requests from hardware, like
network interface card (NIC) or keyboard, or from software directly
14
• Memory manager: The memory manager is responsible of allocating memory
space to each task
• Other services: During operation of the kernel, there are many services running
in the background. For example synchronisation of shared resources, supervision of
task resource allocation, timing synchronisation
2.3.2
Process, Thread & Task
In order to understand how a real-time system behaves and the corresponding scheduler
works, it is important to understand the di↵erence between a process, a thread and a task.
The description given below is mainly based on the Linux environment.
A process is a program, which is executed and has its own allocated memory. Furthermore, a process can consist of multiple of threads, which implement di↵erent part of the
computations. Lastly, a task is either a single-threaded process or a thread as part of
multi-threaded process. The task is the basic unit, which is handled by the scheduler (see
2.3.3) [31]. A task Ji is characterised by the following attributes, as shown in figure 2.8:
[45]
• Arrival time ai , at which the task Ji becomes ready to execute (sometimes referred
as release time ri )
• Computation time Ci , is the CPU time to execute Ji without interruption
• Deadline: The relative deadline di is time, when Ji has to be completed and is
relative to ai . The absolute deadline Di is a time with respect to the global system
time
• Start time si is the actual time, when Ji starts to execute
• Finishing time fi is the actual time, when Ji finishes to execute
Moreover if the task is scheduled periodically, then the task Ji has also the attribute period
18 the period of time, when the next
HARDWARE-DEPENDENT
Ti . Ti defines
instance of the task isSOFTWARE
released.
FigureParameters
2.1. Parameters
real-time task.
Figure 2.8:
of of
a areal-time
task Ji [45]
As described above, di↵erent task can occur at the same time and therefore need to be
under control of the application task. A task which is not known to the RTOS
multiplexed on the CPU core. The figure 2.9 shows this behaviour. It can be seen that
obviously is also not considered by it.
Another parameter that comes with the application task is its computation
time Ci . This is the WCET which has to be determined previously and has to
15the WCET only under the assumption
be known by the RTOS. Of course it is
that the task is not interfered by any other task. Interference can happen only
when managed by the RTOS. So any influence by interference due to other
tasks is known by the RTOS and has to be considered by the RTOS.
the current runnable task is preempted and a context switch occurs. Context switch
means that the context of the previously task is saved and the context of the new task
is restored. The decision, which task is executed next, is made by the scheduler of the
operating system, as shown in section 2.3.3.
Logical concurrency
Task A
Task B
Task C
time
Temporal concurrency
Context
switch
Task A
Task B
Task C
time
Figure 2.9: Logical versus temporal concurrency
2.3.3
Scheduling policies
The scheduler can be distinguished between clock-driven and priority-driven scheduling. In clock-driven systems the scheduling decision are based on time. Therefore the
scheduler is calculated o↵-line and then used during run-time. This approach is very applicable for hard real-time systems. Nevertheless the drawback is that all tasks and its
resources need to be known before. Moreover only periodic tasks are able to be scheduled
and tasks, which are created during execution, are not considered. On the other hand,
the priority-driven scheduling rests upon the di↵erent priorities of each tasks, which define
the execution order. Thus the scheduling process is performed online during execution.
Therefore periodic as well as aperiodic tasks are able to be scheduled. The drawback of the
online scheduling method is the increased overhead. There are many di↵erent scheduling
strategies based on priorities and this scheduling method is quite popular for commercially available kernels (e.g. WinCE, Free RTOS, VxWorks, Xenomai, RTAI, RT-Preempt
Patch). Therefore priority-driven scheduling is discussed below [8].
The priority-driven scheduling can be further classified between periodic and aperiodic
tasks algorithms. Since the developed protection function is run as multiple periodic
16
tasks, the following description focuses on priority-driven periodic scheduling algorithm.
Within this classification there are two popular algorithms for assigning priorities to tasks,
namely rate monotonic scheduling (RMS) and earliest deadline first (EDF) [45].
• Earliest Deadline First: The EDF algorithm assigns the priorities to the tasks
according to their deadline di . Thus a task with the shortest di obtains the highest
priority and is therefore executed first. Therefore the priority of a task changes
dynamically during its lifetime. This algorithm works also for aperiodic tasks.
• Rate Monotonic Scheduling: The RMS algorithm assigns static priorities to
task according to their period Ti . The task with the smallest Ti yields the highest
priority. This algorithm is only suitable for periodic tasks, since its decision making
is based on Ti .
In order to determine the feasibility of the chosen scheduling algorithm, the utilisation
of the CPU U has to be analysed for a number of tasks n, which is given by equation
(2.8). For the following analysis, it is assumed that the tasks are independent (no data
dependency of other tasks) and periodic. Furthermore preemptive scheduling is applied.
This means that each task is able to be preempted by another task with a higher priority.
All tasks are suppose to run on an uniprocessor [45].
U=
n
X
Ci
k=1
(2.8)
Ti
For both scheduling policies EDF and RMS the equation (2.9) has to be fulfilled. That
means that the utilisation of the CPU must be less than 1.
U 1
(2.9)
Nevertheless this condition is not sufficient for the RMS policy. Therefore equation (2.10)
has to be satisfied for the rate monotonic scheduling.
U  n (21/n
1)
(2.10)
If the number of tasks n approaches infinity, the utilisation of the CPU should be less
then 69%. The figure 5.4 depicts the feasibility of the two schedule policies EDF and RMS
for two periodic and independent tasks. It can be seen that the conditions for a feasible
schedule is tighter for RMS than for EDF.
17
U1
1
U≤1
0.83
U ≤ 2 (21/2 - 1)
EDF
RMS
U2
0.83
1
Figure 2.10: Feasibility of EDF versus RMS
2.4
Communication
Concerning the setup with a process bus, described in section 2.2.2, di↵erent communication protocols are considered. The IEC 61850-9-2 is the ”de-facto” standard for gathering
sampled values in substation. Nevertheless IEC 61850-9-2 is still highly customised. Moreover EtherCAT is an emerging real-time protocol, which is mainly used in the industrial
automation field, and it is considered as a COTS-solution. Therefore both protocols are
described below.
2.4.1
EtherCAT
EtherCAT is a Ethernet fieldbus protocol, which supports real-time performance down to
the I/O level and which is based on the fieldbus standard IEC 61158. This protocol is
based on a master-slave communication. If the EtherCAT protocol is applied, then the
ethernet frame is not longer received, interpreted and resend at every node in the network.
Instead the frame is read and processed by the EtherCAT slaves ”on the fly”. That means
that the data is read and written before the frame has been fully received. This approach
leads to the ability of very short cycle times ( 100 µs). In order to achieve full Ethernet
support down to I/O terminals, the physical layer is changed from 100BASE-TX or -FX
to the E-bus, which signal is based on LVDS [11].
18
Figure 2.11: Protocol processing within EtherCAT Slaves [9]
Furthermore a high synchronisation precision of the EtherCAT slaves ( 1 µs) is achieved
by the usage of the distributed clock (DC) algorithm. Each slave, equipped with the DC
algorithm, has a local clock, which starts from zero once it is powered on. Since the slaves
can be powered at di↵erent time instances and the quarts based clocks have a natural
frequency deviation, these deviations have to be compensated by the distributed clock
mechanism. The propagation delay between two slaves is considered as well [11]. Moreover commercial-o↵-the-shelf components can be used to implement to EtherCAT master
and slaves.
Master: The EtherCAT Master is the head of the communication and consists of a
standard network interface card as well as a dedicated EtherCAT driver. A standard network card is sufficient due to the usage of direct memory access (DMS). Thus the CPU
performance is not needed for the network access. Furthermore the master provides the
bus configuration as well as gathers the process data from the EtherCAT slaves [39].
Slaves: The slaves devices are based on ASIC or FPGA in order to achieve a fast response
time. Those chips implement the EtherCAT Slave Controller (ESC), which is basically
the gateway between the E-bus and the digital I/Os. There are several EtherCAT slaves
for di↵erent applications based on digital inputs/outputs as well as analog inputs/outputs. Those inputs and outputs are represented as Process Data Objects (PDO) on the
application layer [39].
Infrastructure: The EtherCAT infrastructure does not require any hubs or switches.
The lack of switches is seen as a step towards a better deterministic behaviour due to
the absence of bu↵ers. Standard CAT5 cable can be used to connect the Master with the
19
AT is:
onization
ial Ethernet
slaves. Nevertheless in a substation environment CAT5 cables are not recommended due
to their weak EMC performance. Instead, fiber optic cables should be used.
Process Data: The Process Data Objects (PDO), as described above, represent the
inputs and outputs of the EtherCAT slaves. The total sum of all PDOs is described as
the Process Data Image. This Process Data Image can have an addressable size of up to 4
Gigabyte. Nevertheless not all PDOs have to be exchanged/updated each cycle time and
the Ethernet frame has a limited size as shown below. Therefore Process Data Domains
are introduced to manage the datagram structures as well as the concerned PDOs for
corresponding communication cycle.
EtherCAT-Protocol: The EtherCAT protocol uses the standard Ethernet frame according to IEEE 802.3, which indicates the EtherCAT protocol by the EtherType field
(0x88A4) as shown in figure 2.12. Concerning real-time ethernet protocols the Process
EtherCAT
is Industrial
Data Domain is usually
directly inserted inEthernet!
the payload of the Ethernet frame. Nevertheless the option to use IP-packets is still available, but not recommended for time critical
applications. From figure 2.12 it is seen that the maximum payload of the EtherCAT
• datagram
EtherCAT
uses[11].
Standard
Ethernet
IEEE
802.3
is 1498 Bytes
The EtherCAT
protocol Frames:
tries to utilise
the entire
available
within one Ethernet
If the(if
Process
Data Domain
is larger than 1498 Bytes,
• space
Alternatively
via frame.
UDP/IP
IP Routing
is needed)
frame is send. This approach leads to a very high bandwidth usage (80 to
• thennoa second
shortened
frames
97%) in comparison to other ethernet based protocols [3].
e Topology
MTU: max. 1514 Byte
to configure
fective
48 Bit
to implement
Destination
oven
48 Bit
16 Bit
16 Bit
Source
EtherType
Header
48 -1498 Byte
EtherCAT Datagrams
Embedded in Standard Ethernet
Frame, EtherType 0x88A4
mance
160 Bit
dancy
Ethernet H.
IP Header
32 Bit
CRC
1…n EtherCAT
Datagrams
64 Bit
UDP H.
48 -1470 Byte
16 Bit
Header
EtherCAT Datagrams
CRC
le
Or: via UDP/IP
UDP Port 0x88A4
11 Bit
1 Bit
4 Bit
Length
Res.
Type
Figure 2.12: EtherCAT Frame [3]
2.4.2
IEC 61850-9-2 & 61850-9-2LE
© EtherCAT Technology Group, 2012
The IEC standard 61850 covers the communication networks between di↵erent intelligent
electronic devices (IED) in a substations of all di↵erent voltage levels. Di↵erent protocols
are defined as part of IEC 61850 depending on its timing requirements as shown in figure
20
2.13. It can be seen that the time critical protocols (SV, GOOSE, GSSE) are directly
mapped to the data link layer. This standard also introduces the concept of logical nodes
(LN) in IEC 61850-7-4. LNs are subfunctions, which communicate with each other in
order to carry out the main function. Some important logical nodes, which are used in
this thesis, are shown in table 2.4. For clarity reasons the ANSI function numbers are
stated as well.
Function Description
IEC 61850-7-4
IEEE/ANSI C37.2
Logical Nodes
Function Numbers
Time delayed phase overcurrent protection
PTOC
51
Time delayed earth fault protection
PTOC
51N
Directional overcurrent protection
PDOC
67
Directional earth fault protection
PDEF
67N
Protection trip condition
PTRC
-
Current transformer (e.g. Analog Inputs)
TCTR
-
Voltage transformer (e.g. Analog Inputs)
TVTR
-
Circuit breaker (e.g. DI/DO)
XCBR
52
Human machine interface
IHMI
-
Data Logging
GLOG
-
Table 2.4: Logical nodes and functional numbers for the protection functions [20]
One of the main objectives of this IEC standard is the interoperability between IEDs of
di↵erent vendors. For this thesis the part 9.2 is of major importance, since it describes
the implementation of the process bus based on Sampled Values (SV) [20].
Other substation
devices (e.g. HMI)
Time-critical
OSI stack
Sampled
Values
GOOSE
Direct
mapping
GSSE
GSSE
Specific
Time Sync
Client-Server
MMS
Application
UDP
TCP
Transport
IP
Switched
Ethernet
HMI – Human-Machine Interface
P&C – Protection & Control
MU – Merging Unit
CB – Circuit Breaker
Network
Ethernet (ISO/IEC 8802-3)
Data Link
Physical Medium
Physical
P&C
Switched
Ethernet
MU
CB
1. Communication protocols
services defined
in IEC 61850
Figure 2.13: Fig.
Communication
defined
in IEC 61850 [24]
Fig. 2.
Simplified protection & control system
The basic parts of the process bus
the merging
unit, defined in IEC 60044-8, a time
II. Oare
VERVIEW
OF IEC 61850
other
monitoring
synchronisation source
SVthestreams
and standard
a Ethernet
switch.
merging
unitunits of the action by i
Thefor
firstmultiple
edition of
IEC 61850
comprises
12 The
packet. The exchange of time-critica
parts in total. Each part describes different aspects of the
can be seen as the core
of the process bus, since it realises the interface between the process
communications taking place within a substation automation above is based on the publisher/subscr
which
one bus
or more subscribers subs
and the network. The
need
Ethernet
given
by the
that in
the
process
system.
Forfor
example,
partswitches
7 presentsis the
logical
viewfact
of the
stating that they want to be notified of
communicationconnection.
system, i.e., logical
of devices,
abstract
is usually not a point-to-point
The models
principle
of publisher-subscriber
is used.
communication service interface (ACSI), etc., while parts 8 this case, to act as sinks for SV or GO
Time
The 61850-9-2 is also
whichought
usestomulticast
its Sync
dataservice
via which was not men
and a9 Ethernet
specify howbased
these protocol,
logical concepts
be mappedto send
above is substation-wide in scope and
a specific
communications
i.e., indicates
protocol Sampled
Ethernet switches into
to the
respective
IEDs. The infrastructure,
EtherType field
Values
common timing information across sub
stack.
such information.
For instanc
with the value 0x88BA.
Furthermore
priority tagging
according
IEEE 802.1q
in
Throughout
this investigation
part 9-2 is
of used
the standard
was to require
scrutinised in-depth since it describes how Sampled Values
protocol should be designed and
21 mapped to Ethernet (ISO/IEC
8802-3). Part 9-1 was also analysed, however, in less detail
since it is likely to be withdrawn from the future releases of
the standard [5].
IEC 61850 defines 5 types of communication services as
correctly handle processing of current
need to be provided with timing inform
popular methods for time synchronis
include Global Positioning System (GPS
IEEE 1588 Precision Time Protocol (PT
Client-Server MMS, similarly to T
substation-wide in scope and is used to
ator
communiwith DERs
otocol was
LAN tags.
V-specific
Similarly,
V-specific
g various
e OPNET
on implesimulator.
ndard and
TOR
uring this
0 standard
on guidee network
of many
is openmulator if
, i.e., both
gramming
e bindings
ngs).
generator
ator node
protocol
s as their
layers as
cal layer.
mented by
nd by SV
onality of
erface and
e physical
rface and
model the
Q support,
order to separate time critical data for protection purposes from other traffic. The payload
of the Ethernet frame consists of the SV header, the APDU (Application Protocol Data
Unit) and several ASDUs (Application Service Data Unit) as shown in figure 2.14. [20].
Type Length
savPdu
0x60 Length
noASDU
0x80
Sequence of ASDU
0xA2 Length
Sequence ASDU 1
svID
Value
1
10
0x30 Length
ASDU 1
0x80
10-34
Value
smpCnt
0x82
2
Value
confRev
0x83
4
1
smpSynch
0x85
1
Value
Sequence of Samples
0x87
64
Samples
(each
8-bytes
long)
Sequence ASDU 2
Sequence ASDU 10
Fig. 4.
Value
Type Length
0x30 Length
0x30 Length
2
2
APPID
Length=
m+8
2
Resrv1
2
6
6
ASDU 10
MAC
Dst
MAC
Src
Resrv2
m
46-(m+8) bytes
APDU
Padding
Application
layer
2
VLAN
TCI
ASDU 2
2
EtherType=
Payload
0x88BA
2
VLAN TPID=
Payload
0x8100
VLAN Interface
sublayer
4
FCS
FDEthernet
sublayer
Structure of modelled SV APDU/ASDU (ASN.1/BER TLV triplets)Fig. 5. Encapsulation of SV APDU as it goes down the protocol stack
Figure 2.14: Structure of modelled SV APDU/ASDU & its encapsulation in Ethernet[24]
i.e., payload coming from upper layers is encapsulated inside
the units,
length of
the APDU
m IEC
bytes61850-9-2
and since the
In order to be able to build the first merging
a lite
editionis of
waslength of
the Ethernet-II (EtherType) type framing with VLAN tagging.
the SV-specific header is 8 bytes, Length field shall be set to
All parts
of thebytraffic
were fully
designed and
created
UCAgenerator
International
Usersgroup
and
IEC 61850-9-2LE. This lite edition,
m +called
8.
engineered in the simulator in order to gain first-hand experiThe Resrv1
field two
stands
for Reserved
It is 2 bytes long,
which is regarded as an implementation guideline,
specifies
profiles
for the1.exchange
ence in working with the standard. Moreover, since the main
and features a set of blocks of bits each serving different
values [21].
aim wasofto sampled
create a realistic
traffic generator, as packets go
function. The MSB, if set to 1, indicates that this SV packet
up/down the protocol stack appropriate headers and trailers are
has been issued by a test device. The following 3 bits are
appended/removed
on a layer basis
to show
how it 80 samples per nominal system frequency
• Protection:
For similarly
protection
purposes
reserved for future standardised application, and by default,
occurs in a real communication scenario.
are set to 0. The remaining 12 bits are reserved for security
(50Hz - Europe) are gathered. A set of
samples consists of 4 current (phase A,B,C
purposes, and by default, should also be set to 0x000. The
A. SV Publisher/Subscriber Application
& N) and 4 voltage (phase A,B,C &Resrv2
N) samples,
which
are send2. at
in one
field stands
for Reserved
It isonce
2 bytes
long, and is
Every SV packet is created by SV Publisher application, and
used
to
denote
additional
security
parameters
carried
by this
ASDU ofwithin
at aencapsulated
rate of 250 µs.
upon creation consists
a seriesthe
of APDU
SV ASDUs
SV packet. By default, it should be set to 0x0000.
inside the SV APDU. The byte structure of SV APDU and In our model, APPID and Resrv2 fields assume their default
• Metering:
metering
256 samples per nominal system frequency are
SV ASDU implemented
in theFor
model
is based purposes
on the Abstract
values, that is APPID is set to 0x4000 and Resrv2 to 0x0000.
Syntax Notation
One (ASN.1)
Basicconsists
Encoding
Rules
Resrv1
is set to
0x8000
to indicate
were gengathered.
Each and
ASDU
of one
set of field
samples
and
8 ASDUs
are that
sentpackets
within
(BER) Type-Length-Value (TLV) triplets specified in [14].
erated by a test device. Length field is updated automatically
APDU.
Thus
every
625 the
µs amodel
Ethernet
frame is sent.
The structure isone
shown
in Fig.
4. At
present,
of
based on the actual length of SV APDU. If the total length of
SV APDU/ASDU does not include any of the optional TLV
the packet (SV APDU + SV-specific header) is smaller than 46
triplets, i.e., datSet, refrTm, smpRate and smpMod. Moreover,
bytes, SV Publisher application will pad it with zeros in order
the majority
implemented Work
triplets have their Value fields
2.5of theRelated
to ensure that it conforms with the requirements of Ethernet,
set to 0 or an arbitrary value to simply preserve the struci.e., the minimum length of the payload encapsulated inside
ture of SV APDU/ASDU rather than carry any meaningful
the Ethernet
frame must
not beand
smaller
than 46 bytes.
Concerning
the
three
fields
power
system
protection,
real-time
systems
ethernet-based
information. Future work will involve adding optional triplets,
The SV Subscriber application on the other hand acts
and setting
Value fields
to something
moreofmeaningful
as the quite substantial research has been perreal-time
protocols,
in each
those domains
as a simple sink for SV packets. It basically removes SVSV traffic generator will be improved, and models of other
specific
header
(if any)
packet in
which was
formed. Before going into detail of those, the
author
likesand
topadding
point out
thatfrom
theaEPFL
protocols such as GOOSE/GSSE will be added.
forwarded up to the application by VLAN Interface sublayer.
Switzerland
published
a research
proposal,
SV-specific
header ishas
appended
to SV
APDU before
it is which deals with the ”Design of a Reliable
sent down the protocol stack to lower layers. The header
B. VLAN
Interface
Sublayer
Controller for Smart Grids” [36]. This research
proposal
involves
exactly the above menis 8 bytes long and comprises 4 fields: APPID, Length,
A
VLAN
Interface
sublayer
was designed to imitate the
research
fields.
Resrv1, tioned
and Resrv2
(see Fig.
5, topmost packet structure).
behaviour
of
an
IEEE
802.1Q
VLAN-aware
end station/device,
The APPID field stands for Application Identifier [14], and
i.e.,
a
network
node
which
is
capable
of
explicitly VLAN
is used to select those Ethernet frames which contain SV
tagging
the
frame
before
it
is
ever
sent
out
[17]. It is clearly
For to
thedistinguish
sake of between
this thesis
the research,
in the area of directional overcurAPDU, and
GOOSE/GSSE
and performed
SV
stated
in
[14]
that
frames
carrying
SV
APDU
have to be
protocols.rent
APPID
always
2 bytes
long and isinofcase
of SV
and isearth
fault
protection,
importance.
In
[46] explicitly.
challenges
formain
directional
relays
VLAN
tagged
The
task
of
this
sublayer is
protocol has the two most significant bits (MSBs) set to 01,
to
append/remove
VLAN
Tag
Control
Information
(TCI) and
stated,14which
arise
underIDcertain
power
while theare
remaining
bits are
the actual
used within
thesystem conditions, and some improvements
EtherType
field
to/from
the
packet
received
from
upper/lower
substation
the values
arecommunication
proposed. Innetwork.
[14] theTherefore,
working group
D-3of
of the
IEEE
System
Committee
layer
(see
Fig. Power
5, middle
packetRelay
structure).
The VLAN TCI
APPID range from 0x4000 to 0x7FFF. By default, it should
comprises
three
fields
[17]:
Priority,
Canonical
format
is indibe set todescribes
0x4000. an approach based on virtual polarisation for directional relays. This approach
cator
(CFI),
and
VLAN
ID.
The Length field is also 2 bytes long, and indicates the
length of the packet including the SV-specific header, i.e., 22
if The Priority field is 3 bits long, and is used to denote the
priority which the frame should be treated with when travelling
through priority-aware switched Ethernet network. Its value
can range
no strict r
among di
payload, p
The CF
ordering f
ing howev
Token Rin
sent with
The VL
identify fr
VLAN se
[14]. Othe
own band
from the o
The va
determine
SV Publis
sublayer t
of EtherTy
values: Pr
EtherType
carried wi
is 0x88BA
When th
Interface
It then in
it with th
forwarded
Otherwise
nism was
carrying S
applicatio
C. FDEth
The FD
behaviour
Therefore
frames for
destination
Protocol
up/down
structure);
Check Seq
The va
0x8100) i
terface to
is receive
checksum
up the pro
II header
ployed) m
is discard
only VLA
sublayer.
very applicable for high resistance faults, for which the polarising voltage is usually quite
low in magnitude. Therefore it is partially implemented for the directional element of the
earth fault protection (see 4.2.3). Furthermore in [18] a new algorithm for ground fault
phase selection has been introduced, which is applicable in case of a weak-infeed. This
weak-infeed situation is usually given in case of a high penetration of renewable energies
and therefore will have more and more importance in the future. Thus the described
algorithm is also implemented for the phase selector element (see 4.2.5).
Concerning real-time systems [25] analysis the di↵erent scheduling algorithms and their
benefits and drawbacks. In [29] the importance of detailed schedulability analysis is described, in order to achieve a feasible scheduler. Since a power system protection system
has to run stable for long life time (
20 years), the ageing problematic of linux operating
systems is analysed in [13] and their e↵ects are stated.
In case of Ethernet based real-time protocols there are many IEEE papers found, which
analyse the performance of either EtherCAT [37], [40] or IEC61850-9-2 [16], [35], [32].
In [37] and in [40] the performance of EtherCAT and its application in the industry is
analysed. Moreover in [12] the IgH EtherCAT Master (see [39]), which will be used in this
thesis, is evaluated. [12] states that the IgH EtherCAT Master provides a maximum cycle
time of 250 µs with a jitter of 13 µs. In [16] protection schemes based on Sampled Values are tested. Moreover [35] deals with performance of IEC 61850-9-2 and its corrective
measure for digital relaying.
A direct comparison between GOOSE protocol, specified in the IEC 61850 standard, and
the EtherCAT fieldbus protocol is made in a conference [15]. This paper claims, that
the EtherCAT protocol outperforms the GOOSE protocol in terms of transfer-time and
deterministic behaviour. None the less, a direct comparison between the IEC 61850-9-2
SV protocol and EtherCAT has not been found.
23
Chapter 3
Methodology
The applied methodology for the development of the directional overcurrent and earth
fault protection is mainly based on a model-based design approach. The input to this
approach are the requirements of the system to be developed. Therefore the model-based
design as well as the requirements of the corresponding protection functions are explained
below. Moreover the selection of specific target system as well as the selection of a suitable
Ethernet based real-time protocol is described.
3.1
Model-based Design
Model-based design is an efficient and cost-e↵ective development process for embedded
software systems. This process is applicable to the well-known V-model of software development as shown in figure 3.1. Model-based design approach starts from the requirements
specification through the design phase, implementation and lastly the testing [34].
Complete+
Integra)on+&+
Test+
Requirements+
De
fin
e+
Modeling+of+
Power+System+
&+IED++
De
si g
n+
Ph
a
se
+
Hardware@in@
the@Loop+
Model@in@the@
Loop+
SoDware@in@
the@Loop+
s)
Te
+
ng
Code+
Genera)on+
Implementa)on+
Figure 3.1: Model-based design is applicable to V-model
Define Requirements: At the beginning of each development process the requirements
24
for the developed product has to be analysed and specified (see 3.2). Those requirements
are usually provided by international standard organisation like IEC or ANSI [30].
Design: Based on the specified requirements the first model is build. There will be plant
(e.g. power system) and controller (e.g. IED) model in order to test the designed protection function based on model-in-the-loop (MiL) simulation. Testing during the design
phase has the significant advantage that potential defects are found at a very early development stage and therefore can be solved in a cost-e↵ective manner (see figure 3.2). [34]
Implementation: Once the model-in-the-loop simulation has been successful completed,
the code for the protection function is generated. In order to generate efficient and e↵ective code the architecture of the processor as well as the operating system of the target
system have to be specified (see 3.4). Moreover some recommendations for the usage of
Simulink are given in the appendix in order to obtain efficient C-code.
Testing: After the implementation phase the comprehensive testing phase begins. This
phase mainly consists of the software-in-the-loop (SiL) and hardware-in-the-loop (HiL)
simulation. During SiL the generated code of the protection function is embedded in the
simulation environment. Thus the inputs (e.g. sampled values) can be provided to protection function by the simulated power systems. If the SiL simulation is successful, it can
be derived that the code-generation process has been performed correctly as well. This
process is regarded as code verification and validation. The results of the software-in-theloop simulations are shown in section 5.2.1. [34]
In the next step the hardware-in-the-loop phase is executed. HiL means that the generated code has been deployed on the target system and the power system is simulated
on a real-time simulator, which provides its measurements either as analog values or as
Sampled Value stream via the network. Thereby it is important that the simulated environment (e.g. power system) runs at least 10 times faster than the controller (e.g. IED).
Nevertheless as part of this thesis the measurements, which are usually provided by the
real-time simulator, are provided by a signal generator (e.g. Omicron). In order to test the
conformance of the protection function to the requirements a type test for the directional
overcurrent as well as earth fault protection is conducted as part of the HiL. The test
results are shown in section 5.3 and 5.2.2.
Considering the model-based design approach, described above, the Matlab/Simulink environment is chosen to develop the protection function. This decision has been made
based on the fact that Matlab/Simulink can be used to carry out the entire model-based
design process within one application. The design phase is executed by the simulation
environment together with the vast supply of di↵erent libraries. Then the Simulink Coder
takes care of the implementation phase, followed by the testing.
25
Defect Discovery
Requirements+
Design+
Implementa2on+
Model7based+design+
Tes2ng+
SEI+7+industry+average+
Figure 3.2: Number of defects found shifts to earlier stage of development process [30]
3.2
Requirements for protection relays
As shown above the requirements are the input to the model-based design development
process. Therefore the functional requirements as well as the environmental requirements,
in terms of electromagnetic compatibility as well as vibration and shock resistance of a
protection system are explained. Nevertheless this thesis focuses rather on the functional
performance than on the environmental constraints.
3.2.1
Functional requirements
The IEC technical committee 95, which is responsible for the standard IEC 60255, has
planned to publish the functional requirements for a directional overcurrent relay in the
IEC 60255-167. Nevertheless at the point in time of the thesis, this part of the standard has not been released yet. Thus the functional requirements are based on a normal
overcurrent protection stated in the IEC 60255-151, which includes earth fault protection
as well. There is also a standard (IEC 60255-12) from 1980 for directional relays in general.
In section 2.2.2 the general setup of a protection system has been evaluated. Considering the operating characteristic of an overcurrent relay, the standard specifies two types
[2].
• independent time characteristic (i.e. definite time delay)
• dependent time characteristic (i.e. inverse time delay)
The point in time, when the current value crosses the threshold setting value GS until
the trip outputs become true, is regarded as the operate time top and it is given by the
26
time characteristics, which is shown in figure 3.3. The figure shows an independent time
characteristic with a definite time delay, since this is the implemented time characteristic
in this project. In the figure only one stage is shown. In most overcurrent functions two to
four stages are found. The current value is given by the measuring principle (see section
2.2.2). In this thesis it will be the RMS value of the 50 Hz component. Nevertheless the
implementation of the trueRMS value as well as the dependent time characteristic are still
on the author’s to-do-list. Nevertheless the
50–Hz RMS value as well60255-151
as a definite-time
– 10
© IEC:2009
characteristic is a common approach for a directional overcurrent protection.
t(G)
top
Gs
G
IEC
Figure 3.3: Independent time characteristic [2]
1706/09
Figure 2 – Overcurrent independent time characteristic
Next
to the operate
time,t(G)
the =start
another
value to consider.
The start is
whenis G
< G S .important
The independent
time characteristic
For
undercurrent
relays,
t op time
presented
in Figure
3. from the instance the fault occurs the in power system until the start
time is the
duration
signal occurs. This value is mainly influenced by the communication solution between the
I/Os and the relay as well as the applied measuring principle (e.g. DFT).
t(G)
The ”opposite” of the start time is the disengaging time, which is defined as the period
of time between the instance the fault disappears and the operate signal of relay becomes
false. This duration is usually influenced by the same factors as the start time. All those
di↵erent time characteristics are depicted in figure 3.4 for clarity.
top
Moreover the standard IEC 60255-151 requires not only a definite operating time, but
also a corresponding reset characteristic. This is important in order to be able to assess
the behaviour of the protection system for repetitive faults. The reset time is the duGs
G
ration between the instance the fault disappears in the power system and the point in
IEC
1707/09
time the relay resets its internal time delay counter, as shown in figure 3.4. Similar to
Figure 3 – Undercurrent independent time characteristic
the time characteristics the standard provides di↵erent options for implementing the reset
characteristics
[2]. time characteristics
4.4.1.3
Dependent
Dependent time characteristics are only defined for overcurrent relays.
• No intentional delay on reset
For dependent
characteristic curves shall follow a law of the form:
• Definitetime
timerelays
reset the
characteristic
• Dependent time resetting
where
⎡
⎤
⎢
⎥
⎢
⎥
k
t (G ) = TMS ⎢
+ c⎥
α
27⎛
⎢ G ⎞
⎥
⎢ ⎜⎜ G ⎟⎟ − 1
⎥
⎣⎝ S ⎠
⎦
(1)
element continues normal operation starting from the retained value.
Following G > G S for a cumulative period causing relay operation, the relay shall maintain its
operated state for the reset time period after the operating quantity falls below G S as shown in
Figure 5. Alternatively, the relay may return to its reset state with no intentional delay as soon
as The
the operating
quantity
below Gdelay
as be
shown
6.
first option
with nofalls
intentional
reset can
usedinforFigure
the definite-time
as well
S afterontripping
as dependent-time characteristic. Nevertheless the other two reset characteristics must
This reset option can apply to both dependent and independent time elements. A graphical
be used according
their
time delay is
characteristics.
Therefore
timecomplete
reset
representation
of this to
reset
characteristic
shown in Figures
5 and 6the
fordefinite
partial and
operation of the element.
characteristic, shown in figure 3.4, is chosen for this project.
Energising
quantity > Gs
Start time
Start (pick-up)
signal
Disengaging time
Operate
signal
Value of
internal time
delay counter
Time delay setting
Tripping
tr Reset time setting
tr
tr
Reset time
tr
Reset time
IEC
1709/09
Figure
Definite time
time reset
reset characteristic
[2]
Figure3.4:
5 – Definite
characteristic
Furthermore the standard IEC 60255-151 requires a performance specification of the developed overcurrent protection. Those specifications comprise the accuracy of the characteristic quantity G (e.g. current 50 Hz RMS value), operate time, reset time as well as
the transient performance. The procedure, on how these tests are performed, as well as
the results are found in section 5.3.
Since the standard IEC 60255-167 for the directional overcurrent function has not been
For ABB use only . Publication provided under IEC subscription agreement 2013 - 2014. This file is copyright of IEC, Geneva, Switzerland. All rights reserved.
released yet, there are no suitable requirements on the directional element.
3.2.2
Environmental requirements
The environmental requirements comprise di↵erent aspects, such as electromagnetic compatibility, vibration and shock resistance, ambient temperature, solar radiation etc. None
the less this thesis focuses on the EMC performance of the I/O modules. The other aspects
of the environmental requirements are stated, but not evaluated.
The EMC performance can be divided into emission and immunity. The emission aspect deals with the radiation of the electro magnetic waves of the equipment under test
itself. From the point of view of immunity the equipment under test is subject the externally applied electromagnetic force and its performance is evaluated. This thesis focuses
in the latter.
28
The general EMC requirements are tackled by the IEC 61000-6-5 in case of high voltage
substation and power station applications. The more specific EMC requirements for relays and communication equipment in the substation environment are described in the
IEC 60255-26 and IEC 61850-3, respectively. The general EMC requirements, stated in
IEC 61000-6-5, are used in this project due to its better comparability to the IEC 610006-2, which comprises the general electro magnetic compatibility of the used EtherCAT
components.
According to IEC 61000-6-5 there are a couple of important electromagnetic phenomena,
as shown in table 3.1, which are grouped into continuous phenomena, transient phenomena with high occurrence and transient phenomena with low occurrence. Depending on
the implemented function, di↵erent performance levels have to be fulfilled for those three
groups of electromagnetic phenomena [19].
Performance criterion A: The equipment under test (e.g. EtherCAT slaves) must
perform error-free during and after the applied electromagnetic phenomena.
Performance criterion B: The equipment under test must perform error-free after
the applied electromagnetic phenomena.
Performance criterion C: The equipment under test may stop operating as intended
temporarily. None the less the function has to be self-recoverable or restorable by an
operator [19].
In case of protection functions the performance criterion A has to be fulfilled for all
three groups of electromagnetic behaviour. That means that the developed protection
system has to operate during as well as after the test. Only for certain functions, such as
Human-Machine-Interface, lower performance criterion, like B and C, are allowed.
29
Continuous
Transient phenomena
Transient phenomena
phenomena
with high occurrence
with low occurrence
Voltage dips:  0.02s
Voltage dips: > 0.02s
- a.c. power supply
- a.c. power supply
- d.c. power supply
- d.c. power supply
- d.c. power supply
Harmonics, interharmonics
Voltage fluctuations
Voltage interruptions:
Signalling voltages
Fast transient/burst
- a.c. power supply
Ripple on d.c. power
Damped
- d.c. power supply
supply
wave
Power frequency variation
Damped oscillatory mag-
Short duration power fre-
netic field
quency variation
Electrostatic discharge
Surge
Voltage variations:
- a.c. power supply
Conducted disturbances in
oscillatory/ring
the range 2 kHz to 150 kHz
Conducted disturbances in
Short duration power fre-
the range 1,6 MHz to 30
quency voltage
MHz
Power frequency magnetic
Short duration power fre-
field (according to IEC
quency magnetic fields (ac-
61000-4-8)
cording to IEC 61000-4-8)
Radiated, radio frequency
Radiated
electromagnetic field
bances
Conducted
pulsed
distur-
disturbances,
induced by radio-frequency
fields
Mains frequency voltage
(according to IEC 61000-416)
Table 3.1: Characterisation of the electromagnetic phenomena [19]
The exact EMC test, which have to be performed in order to satisfy the immunity requirements, are stated in the evaluation section 5.5. The magnitude of the applied test values
depend on the intended location of the equipment under test. The figure 3.5 shows those
di↵erent locations, which are found in a substation environment.
30
– 16 –
IEC 61000-6-5:2015 © IEC 2015
Control room area
HV area
Protected area
2
1
4
Interface area
3
2
2
2
Outside
area
Process area
3
4
3
4
4
IEC
Figure 3.5: Di↵erent EMC requirements for corresponding areas within a substation [19]
Key
Interface types
1
Locations:
Inside protected area
2
Inside interface and/or control room area
3
Inside or from process area
4
Connections
from outside
(HV and
externalroom
telecommunication)
2. Inside interface
and/or
control
area
1. Inside interface and/or control room area
NOTE
3. Inside or from process area
The control room area contains control systems, computers, fire fighting systems, UPS, etc.
4. Connections
from
outside
(HV (if36available)
kV andwith
external
telecommunication)
The process
area contains
mainly
MV systems
circuit breakers
and MV-bus bars.
The protected area contains for example special sensitive equipment like routers, special computers, etc.
As stated in the introduction of the thesis, only the I/O modules are placed in the high
The interface area contains equipment and systems connected to the outside with measures like surge protection
voltage environment indicated by the number 4. Moreover the control PC is run in a
and bonding of cable shields.
”protected” area with less harsh EMC requirements indicated the capital letter 1. There-
The outside area contains for example control centres.
fore in section 5.5 only the high voltage location is considered, when evaluating the EMC
The HV area contains GIS, earthing bus bars, transformers, etc.
performance of the EtherCAT modules.
Figure 4 – Example of the situation of a gas-insulated substation (GIS)
Moreover the environmental requirements not only cover the electromagnetic compati5 Performance criteria
bility, but also the vibration and shock resistance as well as ambient temperature and
The
performance
criteria
are closely
related
to the nature
of the electromagnetic
phenomena
altitude.
The table
3.2 shows
the normal
environmental
conditions,
which are required
by
(types and occurrence), as given in Table 1 and to the applicable representative functions of
the IEC 61850 standard for communication equipment used in a substation. There are
the equipment concerned.
special environmental conditions stated in the standard for harsher environments. NeverTable
listsnormal
the suggested
performance
criteria
to be
applied
for the corresponding
theless2 the
environmental
conditions
shown
below
are considered
as reference function
for
of equipment. A functional description and a definition of performance criteria, during or as a
this project. of the EMC testing, shall be provided by the manufacturer and noted in the test
consequence
report, based on one of the following criteria, for each test as specified in Table 3 to Table 10.
a) Performance criterion A: The EUT shall continue to operate as intended during and after
the test. No degradation of performance or loss of function is allowed below a
performance level specified by the manufacturer, when the EUT is used as intended. If the
performance level is not specified by the manufacturer, this may be derived from the
31
For ABB use only . Publication provided under IEC subscription agreement 2013 - 2014. This file is copyright of IEC, Geneva, Switzerland. All rights reserved.
Environmental parameters
Ambient temperature
Conditions
 +55 C
Upper limit
Lower limit
10 C
Solar radiation
Negligible
Altitude
 2 000m
Air pollution (dust, smoke, vapours, etc.)
No significant pollution
Relative humidity (24 h average)
From 5 % to 95 %
Vibration, earth tremors
According to IEC 60255-21 (class 0 or 1)
Electromagnetic disturbances
Defined by specified location (see below)
Table 3.2: Normal environmental conditions [20]
Concerning the vibration and shock requirements the IEC 60255-21 has to be satisfied for
equipment used for protection purposes in substation environments.
3.3
Selection of communication solution
In section 2.4 two important real-time ethernet based protocols have been described,
namely EtherCAT and IEC61850-9-2 (Sampled Values). EtherCAT has mainly been designed for industrial process applications and is characterised by its highly deterministic
behaviour as well as its fast cycle times. The disadvantage of EtherCAT is the single head
of communication, since only one EtherCAT master receives the measurements from the
EtherCAT slaves. On the other hand IEC61850-9-2 is the communication standard for
sampled based measurement values in the substation domain as well as has the advantage
that the sampled value packets can be sent to multiple subscribers via multicast. The
disadvantage of IEC61850-9-2 is the less deterministic behaviour, especially during high
traffic rates.
Since one important objective of this thesis is, that the developed protection system is
based on COTS components, the EtherCAT communication solution is chosen as the link
between the power system and the protection logic on the target system (PC). At the
point in time of the thesis EtherCAT components are widely available on the market in
comparison to respected merging units, which are needed for IEC 61850-9-2.
Moreover the protocol stack for the EtherCAT master is freely available under the terms
of the GNU General Public License GPL, version 2. The IgH EtherCAT Master 1.5.2 is
used in this project [11]. The detailed features of the chosen EtherCAT Master are found
in section 4.3.2.
32
3.4
Selection of real-time system
The target system, on which the protection algorithm runs as a kernel module, is a realtime system with the components stated in section 2.3. Therefore the selection of the
corresponding hardware as well as software in terms of kernel, Linux distribution and
EtherCAT Master is discussed.
3.4.1
Hardware
The required hardware for the real-time system can be divided into computer- and communicationrelated hardware, as shown below.
Computer: Considering the hardware selection of the target system there is vast variety of di↵erent components to choose from. In order to have a rough guideline to select
proper hardware, some considerations are made. The developed protection function is run
as multi-threaded process. Therefore a multi-core architecture of the processor is proposed
in order to yield the maximum efficiency due to hardware-based multithreading. Nevertheless the actual benefit of this approach has to be evaluated later, since the increase
in performance is limited by the sequential fraction of the application (Amdahl’s law).
This might be of interest, when it comes to protection of multiple bays. Furthermore
the communication between the di↵erent threads should be performed mainly in the processors’ caches rather than in the memory [33]. The bandwidth of reading and writing
in the level 3 cache (used for inter-core communication in case of INTEL processors) is
faster than in the memory. Thus a large level 3 cache is picked (e.g.
4 MB). Moreover a
bandwidth of 100 Mbit/s (up/down-link) of the NIC for EtherCAT is seen as sufficient [11].
Under consideration of the above circumstances the following hardware for the target
systems has been chosen in table 3.3:
33
Processor Number
i7-2760QM
Instruction Set
64-bit
Level 1 cache
32 kByte
Level 2 cache
256 kByte
Level 3 cache
6144 kByte
Number of cores
4
Processor Base Frequency
2.4 GHz
Memory
4 GB
Network interface card
Intel PRO/1000 Gigabit-Ethernet
NIC-Connector
RJ-45
PCI-BUS
PCI Express chipset
Table 3.3: Hardware configuration of target system
The figure 3.6 shows the used quad-core architecture as schematic overview. It can be
seen that the level 1 and 2 caches are individual for each processor core, whereas the level
3 cache is accessed by all four cores. Furthermore each physical core has only one logical
core due to the fact that hyper-threading is not used. Since hyper-threading introduces
random latency and deterministic behaviour is of major concern, this feature is disabled
in the BIOS. Moreover the NIC is connected via the PCI-bus.
Figure 3.6: Quad-core architecture without hyper-threading
Communication: The communication-related hardware consists of the EtherCAT coupler and slaves as well as the communication medium itself. As described above, a communication medium based on fiber optics (e.g. 100BASE-FX) is recommended for the
34
substation environment. Since this project is regarded as a proof-of-concept, a copper
based communication medium is used, in particular 100BASE-TX with RJ-45 connectors.
Besides the EtherCAT coupler (e.g EK1100), the following EtherCAT slaves are needed
for the application of this project:
• Digital Input: potential-free (e.g EL1034)
• Analog Input: 3xVoltage, 3xCurrent, oversampling (e.g. EL3773)
• Relay Outputs: Circuit breaker contacts (e.g. EL2624)
• Digital Outputs: Tracking di↵erent signals, like Pick-Up (e.g. EL2798)
The EtherCAT components are obtained from Beckho↵ and supplied by a 24 V-DC power
supply. The detailed datasheets are found in the appendix. At this point it is already
mentioned, that the current inputs of the EL3773 are not comparable to the current inputs
of common IEDs. The maximum permitted overcurrent of the EL3773 equals 1.2 A (RMS).
Current inputs of IEDs currently available on the market can handle overcurrent of up to
100 A. This high ratings are needed, since the secondary currents during a short circuit
increase above 50 A and higher. Nevertheless a EtherCAT slaves with those high current
ratings is not found on the market.
3.4.2
Runtime Environment
The most important parts of the runtime system is the kernel as well as the EtherCAT
Master. Also a suitable distribution has to be selected. Moreover there are some libraries,
which have to be available as well. There is guideline in the appendix, which describes
the process of setting up the runtime environment.
Kernel: Linux is chosen as operating system, due to its open-source availability and
its wide support community. In order to achieve the required deterministic behaviour, the
open-source vanilla Linux-Kernel is chosen, which is patched with the preempt-rt patch.
In particular the kernel version 3.4.41 is used due to some constraints imposed by the
chosen EtherCAT master below. The normal mainline kernel has only limited real-time
capabilities. Therefore the rt-patch is used to reduce the non-preemptible sections and
add the following real-time features and to make the standard kernel fully preemptible
[22].
• Usage of mutexes instead of spinlocks
• Implementation of priority inheritance to avoid priority inversion
• Conversion of interrupt handlers into preemptible kernel threads
35
Before the Linux-Kernel is compiled, it has to be configured. The most important configurations are found in the implementation part of the thesis (see section 4.3.1). The
Linux real-time scheduler are First-in-First-Out (FIFO) and Round-Robin (RR). The
FIFO scheduler always schedules the task with the highest priority. This task runs until it completes or until it is preempted by a higher priority task. The RR scheduler is
very similar to the FIFO scheduler. The only di↵erence is that the tasks scheduled by
RR are time-sliced. That means that the running task is preempted after its time-slice
is exhausted and is placed in the expired-queue [22]. For the threads of the developed
protection algorithm the RR scheduler is used. In section 3.4.1 it is stated that a multicore architecture is beneficial for application with a high parallisable fraction. In order to
achieve this increase in performance, the corresponding scheduler policy has to support
this multicore approach. Nevertheless research has shown (see [38]) that the scheduler
classes FIFO and RR execute an active push-pull approach between the cores with a load
over 50%. This leads to unpredictability, which is tried to be avoided. Therefore the developed protection application is run with CPU affinity, despite the multicore architecture.
Linux distribution: The selection of Linux distribution is made based on its main
function. There are many di↵erent linux distribution on the market. The figure 3.7 shows
a rough classification of the di↵erent linux distributions according to their purposes, such
as server applications, desktop or embedded systems. Since the protection system can
be best characterised by a server and the author is more familiar with Debian-based systems, Ubuntu Server would be most suitable. None the less some part of the development
process is also executed on the target system. Thus the Ubuntu desktop distribution is
chosen for this project. The server and desktop version mainly di↵er in terms of desktop
packages, such as X or GNOME and server related packages, like Apache2. Thus choosing
Ubuntu desktop over Ubuntu server should not influence the developed protection system.
In particular the The Ubuntu 12.04 LTS (Long Term Support) is picked as distribution,
since it uses kernel version, which are similar to the chosen 3.4 kernel. Therefore potential
integration issues are limited.
36
Figure 3.7: Overview of Linux distribution
EtherCAT Master: The head of the EtherCAT communication is the EtherCAT Master, as described above. As part of this project, the open-source IgH EtherCAT Master
is used [39], which runs as a kernel module as well. This specific EtherCAT master includes a EtherCAT-capable native drivers. That means that the native driver operates
the hardware without the usage of interrupts, which increases the deterministic behaviour.
Currently the IgH EtherCAT Master together with the native driver approach only supports certain hardware (e.g. Intel PRO/1000 Gigabit-Ethernet chipsets) and linux kernels
(<3.4) [39]. Those constraints are considered during the selection process of the hardware
and the runtime system above.
3.5
Specified development procedure
Under consideration of the model-based design approach as well as the stated requirements, the figure 3.8 depicts the specified development procedure of the protection system
based on COTS components. The design and implementation phase is executed in the
development environment. The setup of the runtime and development environment are
described in the appendix. The SiL testing is also performed in the development environment. Once the target system is set up and communication infrastructure is implemented,
the HiL testing is performed. Moreover a type test is performed, which is required by the
IEC standard. The results of this type test are compared against comparable IEDs from
ABB and Siemens. Lastly, a stability test is performed in order to evaluate the realtime
system in terms of determinism and long-term behaviour.
37
Proposed Approach
Protection
Algorithm
Setup Target System
Desktop Environment / Software-in-the-Loop
Adjust
application for
EtherCAT com.
upload to
- Ubuntu 12.04.5 LTS
- RT-Kernel 3.4.41
- EtherCAT Master (IgH)
Power
System
EtherCAT Infrastructure
- EtherCAT Coupler
- EtherCAT Slaves
- Power Supply 24 DC
- CAT-5 patch cables
Target System
install on
Protection Algorithm with
EtherCAT communication
connect to
Testing
- Functional Performance Test
- Type Test according to IEC 60255-151
OEM IEDs
compare to
- Stability Test (Schedulability analysis, long-term test)
- Compliance to environmental requirements (EMC, …)
© ABB Group
August 12, 2015 | Slide 4
Figure 3.8: Specified development procedure
38
ABB: REL670 2.0
Siemens: 7SJ82
Chapter 4
Implementation
This chapter comprises the design and implementation phase of the model-based design
approach. First the architecture of the protection system is discussed, followed by a detail
description of the implemented protection algorithm itself. Lastly, the configuration of
the target system are evaluated in terms of kernel and EtherCAT master setup.
4.1
Architecture of Protection System
The architecture of the protection system is divided into two levels, namely process and
station level. The approach is that the input/output modules are separated from the
computer executing the protection function. This has the advantage that only the EtherCAT couplers and slaves have to fulfil the harsh environmental requirements, described
in section 3.2.2. On the other hand, the computer unit is located at a station level in a
protected area, with less environmental constraints. Nevertheless whether the chosen I/O
modules are complaint to the required EMC and vibration/shock standards is shown in
the evaluation section 5.5. Moreover this described architecture of the protection system
leads inevitably to a centralised approach.
The figure 4.1 depicts the chosen system design from a hardware, functional and logical
nodes perspective. The latter logical nodes perspective is just seen as functional description of the protection system. This does NOT mean that the actual data objects and
attributes, which are defined in the IEC 61850 standard, are implemented. The developed
definite-time directional overcurrent and earth fault protection are described by the logical
nodes PDOC and PDEF, respectively. The logical node PTRC describes the developed
trip element, which combines the trip outputs of the individual protection functions. The
voltage and current inputs are described by TVTR and TCTR respectively, whereas the
circuit breaker, seen by the relay outputs, is shown by XCBR. The logical nodes IHMI and
GLOG represent the human machine interface (HMI) and data logging service respectively.
Those two functions are not developed as part of this thesis. Instead an open-source Testmanager and Data Logging Service, o↵ered by EtherLab, is used, which interfaces whith
39
the protection application via the protocol-independent PdCom library.
From the functional perspective it can be seen, that the protection function runs in the
kernel space of the RT-Linux system. This is important in order to communicate directly
with the native EtherCAT driver without the usage of system calls. Moreover analog
voltage and current values are provided by the signal generator Omicron in order to test
the system in HiL (see section 5.3 and 5.2.2).
Hardware Perspective
Function Perspective
Logical Nodes Perspective
IHMI
GLOG
C-File
Protection
Function
HMI
Data logging
RT-Linux
Application Layer
TCP/IP
Linux-Kernel
Kernel Modules
Compile...
PDEF
PDOC
Realtime Modules
EtherCAT
Master
Network
Driver
Network
Driver
NIC
NIC
PTRC
Data Link
EtherCAT
Physical
100BASE-TX
EtherCAT Slave
EtherCAT
Coupler
I/O
TCTR
TVTR
XCBR
Omicron
Signal
Generator
Figure 4.1: Centralised architecture of protection system
4.2
4.2.1
Protection Algorithm
Overview
The protection function consists of a definite-time directional overcurrent and earth fault
protection, as described above. In order to build up this functionality, di↵erent elements
are required based on the concept described in section 2.2.2 and depicted in figure 2.2.
Those elements are divided into signal processing elements, directional elements, phase
selector, overcurrent and earth fault protection, trip element and lastly the communication
driver and supervision blocks. Those elements are depicted in figure 4.2.
40
3xI
Preprocess
ing
EL3773
Signal
processing
PDOC
Relay
outputs
PTRC
EL2624
3xV
Preprocess
ing
EL3773
Signal
processing
PDEF
Phase
selector
Communication
supervision
1 ms
Period of task
8 ms
Period of task
1 ms
Figure 4.2: Overview of protection algorithm
The application has a base sample time of 1 ms, which defines the period T of the task
(see section 2.3.2). At this time interval of 1 ms the scheduler has to run the application.
None the less the individual elements of the application (e.g. signal processing, phase selector, etc...) can run at a multiple of this base sample time. The selection of the sample
time of the individual elements should not be performed randomly. For instance it is not
advisable to run the signal processing block at a slower speed than the protection function
itself. Moreover the tripping unit and the communication driver blocks should run at the
base cycle time in order to archive a high accuracy. In the figure 4.2 the signal processing
and the protection functions (PDOC, PDEF) run at sample time of 8ms.
In order to assure data integrity and determinism between to elements running at different sample times, either transition blocks or bu↵ers are implemented between those.
Depending on transition fast to slow or slow to fast the transition block implements a
Zero-Order-Hold or a Unit Delay, respectively.
In the following sections the implementation of each of the above stated elements are
described in detail. Moreover the configurable parameters, which can be set by the user,
are stated and explained at the end of each section. The base sample time timeBASE of
the application is set at a global level.
41
4.2.2
Signal Processing Element
Since the protection function (PDOC & PDEF) are based on phasor measurements, the
core function of the signal processing element is to calculate those phasors based on sampled values. From a mathematical perspective a discrete Fourier-Transformation (DFT) is
implemented in order to convert the time-based signal into the frequency domain. Based
on the Fourier-Series each periodic signal f (t) can be described by a infinite number of
sin and cos waves as described by equation (4.1).
1
a0 X
f (t) =
+
an cos(n!t) + bn sin(n!t)
2
(4.1)
n=1
In the equation above n represents the rank of the harmonics. In this project the signal
f (t) represents the current or voltage signal of the power system. Since the focus lies
on European systems the fundamental component (n = 1) equals 50 Hz. Moreover the
magnitude and the phase of the harmonic n is obtained by the equations (4.2) and (4.3)
respectively.
|Hn | =
p
a2n + b2n
\Hn = arctan
Where
an =
2
T
Z
⇣b ⌘
n
an
(4.3)
t
f (t)cos(n!t)dt
t T
Z t
2
f (t)sin(n!t)dt
T t T
1
1
T =
=
f1
50 Hz
bn =
(4.2)
(4.4)
The implemented Fourier transformation is based on the above equations. Nevertheless
since the computer environment is a discrete and not a continuous one, the equations are
slightly re-written below. The continuous signal f (t) is sampled at a discrete rate of 250 µs
(see section 4.2.7) using a running window. Thus the required 80 samples per fundamental
period is yield for protection purposes. This window F has a window size T of 80. The
implemented protection function only requires the fundamental 50 Hz component of the
signal. Therefore from now on n = 1. Moreover the continuous sin and cos waves are
represented by two row vectors, S and C respectively, comprising 80 discrete values. Now
the equation (4.4) is re-written in a discrete form below.
42
T
⌘
2X
2 ⇣
a1 =
Fi C i =
F · C
T
T
b1 =
2
T
i=1
T
X
Fi S i =
i=1
⌘
2 ⇣
F · S
T
(4.5)
T = 80 window size
i = corresponding element of row vector
The calculation in equation (4.5) is performed at each sample time of the signal processing
element psp . The signal processing element needs to run at least as fast as the fastest
implemented protection function. In addition the window F has to be updated with new
sampled values at each psp . Moreover the row vectors S and C have to be circulated by the
amount of new sampled values added to the window F . The number of newly added SV
is determined by the di↵erence in sample time between the signal processing element and
the fundamental sample time (1 ms). The figure 4.3 clarifies the above described process.
Row vector is circled by 32 samples each 8 ms
discrete sin wave samples
1#
1#
2#
3#
4#
78#
5#
79#
80#
1#
2#
2#
3#
3#
Dot#
Product#
2
80
Real
Part
Dot#
Product#
2
80
Imaginary
Part
8 ms
cycle time
SV#
SV#
SV#
SV#
SV#
SV#
SV#
SV#
SV#
SV#
SV#
SV#
SV#
SV#
SV#
SV#
49#
49#
50#
50#
80#
80#
buffered
1#
2#
3#
4#
5#
78#
79#
80#
discrete cos wave samples
4 times oversampled
at base cycle time of 1
ms
Row vector is circled by 32 samples each 8 ms
Figure 4.3: Implemented signal processing algorithm
The SV, marked in green, indicate the sample values, which are exchanged each 8 ms
(sample time of the signal processing element). Those updated SVs sum up to 32 (psp · 4).
Once the real and imaginary parts are yield, the phasor is constructed. Moreover the
PDOC and PDEF expect RMS values. Therefore the magnitude of the phasor is divided
43
by
p
2. This signal processing implementation is executed on current as well as voltage
measurements for all three phases. Furthermore the symmetrical components of the threephase system are calculated based on the equations (4.6). Those components are essential
in the power system protection field, since many functions rely on those quantities.
1
U0 = (U a + U b + U c )
3
1
U1 = (U a + a U b + a2 U c )
3
1
U2 = (U a + a2 U b + a U c )
3
Where a represents the rotation operator of 120 (ej
2⇡
3
(4.6)
).
Above implemented DFT is performed in the signal processing element itself. Nevertheless the pre-processing part prepares the running window F and provides it to the
signal processing element each 8 ms. Secondly, since the entire protection algorithm is
based on normalised values, the sampled values are also normalised in the pre-processing
element based on the given ratio of the instrument transformers as well as the base values.
Thirdly, an estimation of lost sampled values is implemented based on second order SV
estimation. Therefore three known sampled values SV0 , SV1 and SV2 are used to define
the second order polynomial p2 (tk ) as shown in equation (4.7). tk is the point in time,
when the sampled value is lost.
SVk,est = p2 (tk ) = C0 SV0 + C1 SV1 + C2 SV2
(4.7)
Where
(tk
(t0
(tk
C1 =
(t1
(tk
C2 =
(t2
C0 =
t1 )(tk
t1 )(t0
t0 )(tk
t0 )(t1
t0 )(tk
t0 )(t2
t2 )
=1
t2 )
t2 )
= 3
t2 )
t1 )
=3
t1 )
The above constants are calculated based on three successful received SVs and a lost forth
SV. This SV estimation is used in case of lost and delayed EtherCAT frames. Nevertheless
a higher order polynomial could also been used in order to achieve a better estimation.
But this leads to a higher computational requirements. Thus there is a trade-o↵ between
accuracy of the estimation and computational demand. In the table 4.1 the configurable
parameters are declared and the developed signal processing block is shown in figure 4.4.
44
Figure 4.4: Developed signal processing block and mask
Name
Default
Min
Max
Unit
Description
freq
50
50
60
Hz
Fundamental frequency
ratio
1000
1
5000
-
Ratio of instrument transformers
A or V
Base value of input quantity
base
1000
1
106
initial
0
0
100
p.u.
Initial output until window is filled
nrSV
4
1
10
-
Oversampling factor
timePRE
0.001
0.001
1
s
Sample time of input port
timeSP
0.008
0.001
1
s
Sample time of signal processing element
Table 4.1: Settings for signal processing element
4.2.3
Definite-time Directional Overcurrent Protection - PDOC
Once the corresponding phasor measurements are calculated, the actual protection function can start performing its algorithm based on those data. The PDOC is divided into
directional sensing and threshold sensing based on a definite-time curve. The implementation of both elements is described in the following paragraphs. The developed PDOC
block and mask are shown in figure 4.5.
45
Figure 4.5: Developed PDOC block and mask
Directional element: Both protection function PDOC and PDEF comprise a directional element, which indicates the fault direction seen from the relay. Directional sensing
is important in order to enhance the selectivity performance of the protection system and
thereby increase the security objective (see section 2.2.1). This is especially important for
ring and meshed networks as well as for feeder protection with bi-directional power flow
due to a high infeed of distributed energy sources.
The directional element for the PDOC performs its directional decision on a per-phase
basis. Most directional sensing is based on the comparison of a polarising quantity with
an operating quantity. In case of the overcurrent protection the phase currents IA , IB and
IC are the respective operating quantities for each phase. Nevertheless the selection of
the polarising quantity is made based on its application. For example for the detection of
transient faults the individual phase voltages UA , UB and Uc would be chosen in order to
detect the direction of the fault. None the less low for low resistive faults UA , UB and Uc
tend to be very small and therefore can not provide any reliable information. Therefore
a common approach is to use the 90 connected phase directional element. That means
that the line-to-line voltages UBC , UCA and UAB are used as polarising quantities. This
has the advantage of reliable polarising measurements during single-phase and multi-phase
faults. None the less in this project a third approach has been implemented, which uses
the positive-sequence component U1 as polarising quantity. Considering table 4.2 below
the positive-sequence component is always available for all types of balance and unbalance faults. The only exception is a three-phase fault in close proximity to the voltage
transformers.
46
3-Phase Faults
Ground
Quantity
Close
No-Ground
No-Ground
Ground
Close
Far
Close
Far
Close
Far
X
X
X
X
X
X
X
U2
X
X
X
X
X
X
U0
X
o
X
o
X
Close
Ground
SL-Ground
Far
U1
Far
Phase-Phase Faults
Table 4.2: Available sequence components during di↵erent fault scenarios
In that case also U1 decreases to a very low value (see equation (4.6)) and is therefore not
reliable any more. If this type of fault occurs, then the memory voltage of the pre-fault
state is used to make a directional decision. The memory voltage can be used due to the
fact that the source is best described by a voltage source and therefore the phase of the
voltage changes only slightly during the fault state. The figure 4.6 depicts the operating
area of the directional element for four di↵erent stages.
Figure 4.6: Characteristic of directional element
The coloured areas are the operating areas for the four di↵erent stages, which are normally
+/- 90 from the polarising quantity. If the operating quantity is within this area, the
fault is indicated as forward. Normally this area is shifted by the angle of the positive
impedance of the line, also called maximum torque angle (MTA). The MTA for the above
characteristics is
60 .
The directional algorithm itself does actually not examine the angles directly. Instead
it calculates the active power according to equation (4.8). Therefore it is also regarded
47
as a wattmetric directional element. A forward fault is indicated by a positive sign and
reverse faults, vice versa.
PA = Re(V 1 · I ⇤A,adj )
PB = Re(a2 V 1 · I ⇤B,adj )
(4.8)
PC = Re(a V 1 · I ⇤C,adj )
Where a is the 120 rotational operator, Z 1,line is the positive line impedance and I A,adj ,
I B,adj and I C,adj is described by:
I A,adj = I A · 1\Z 1,line
I B,adj = I B · 1\Z 1,line
I C,adj = I C · 1\Z 1,line
The table 4.3 shows the configurable parameters of the directional element.
Name
Default
Min
Max
Unit
Description
enableDIR
true
true
false
-
Enable directional element
angZ1
80
0
90
degree
Angle of Z 1,line
thresP67
0.5
0
10
p.u.
Threshold of active power (PA ,PB ,PC )
thresV
0.1
0
1
p.u.
Minimum polarising voltage (V1 )
ringBUF
0.1
0.16
1
s
Size of ring bu↵er for pol. quantity
Table 4.3: Settings for directional element of PDOC
Definite-time overcurrent element: Once the directional elements indicates the fault
in forward direction, the operating quantities IA , IB and IC are checked against a threshold
on a per-phase basis. Therefore four di↵erent stages can be set with the according delay
time. For the first stage the directional sensing can also be disabled. Furthermore a reset
time is implemented to reset the delay timer for each stage according to the IEC 60255151, as stated in section 3.2.1. Once the operating quantity exceeds the threshold, the
start signal is set to true and the timer starts. After the set time delay has expired, a
trip signal is issued and send to the trip element PTRC, which collects the trip signals
of all implemented protection function. The PDOC itself runs at a sample time of 8 ms.
Nevertheless the time delay function runs at the base sample time in order to achieve a
highly precise trip time. All implemented timer functions are based on 16bit-counters.
Thus the maximum setable time delay is 65 seconds, if the timer function runs at the
recommended base cycle time. The figure 4.7 depicts the characteristic definite-time curve
for the four stage overcurrent protection.
48
Figure 4.7: Definite-time curve of PDOC with 4 stages
The table 4.4 depicts the configurable parameters of the PDOC.
Name
Default
Min
Max
Unit
Description
enableST1
true
true
false
-
Enable first stage
disableDIRst1
false
true
false
-
Disable dir. sensing (1.Stage)
thresIst1
50
0.5
100
p.u.
Current threshold of first stage
delayST1
0.05
0
3
s
Delay time of first stage
resetST1
0.05
0
3
s
Reset time of first stage
enableST2
true
true
false
-
Enable second stage
thresIst2
50
0.5
100
p.u.
Current threshold of second stage
delayST2
0.05
0
3
s
Delay time of second stage
resetST2
0.05
0
3
s
Reset time of second stage
enableST3
true
true
false
-
Enable third stage
thresIst3
50
0.5
100
p.u.
Current threshold of third stage
delayST3
0.05
0
3
s
Delay time of third stage
resetST3
0.05
0
3
s
Reset time of third stage
enableST4
true
true
false
-
Enable forth stage
thresIst4
50
0.5
100
p.u.
Current threshold of forth stage
delayST4
0.05
0
3
s
Delay time of forth stage
resetST4
0.05
0
3
s
Reset time of forth stage
timePDOC
0.008
0.001
1
s
Sample time of PDOC element
timeTIMER
0.001
0.001
1
s
Sample time of timer element
Table 4.4: Settings for the definite-time curve of PDOC
49
4.2.4
Definite-time Directional Earth Fault Protection - PDEF
The operating principal of the earth fault protection is very alike to the overcurrent protection. The di↵erence is the selection of the operating quantity. Instead of choosing the
phase currents, the PDEF takes the residual earth current into consideration (see section
2.2.4). There are di↵erent approaches for obtaining this residual earth current. If the
neutral point of the transformer grounding is accessible, a current transformer is placed
at this neutral point. Nevertheless this might not always be the case, therefore another
common approach is to use a current transformer for each phase and then use a Holmgreen
connection in order to obtain the residual current. Both approaches require a forth current input for the analog inputs. Since the chosen EL3773 only has three current inputs,
a mathematical approach is used in order to obtain the residual current. Based on the
three-phase measurements the zero-sequence current I0 is calculated (see equation (4.6)).
Thus the residual current equals 3I0 . The figure 4.8 depicts the developed PDEF block as
well as its corresponding mask for configurations.
Figure 4.8: Developed PDEF block and mask
Directional element: The principal of the directional element for the PDEF is similar
to the one of the PDOC. Nevertheless the selection of the polarising quantity is a bit
di↵erent. Table 4.5 shows the available symmetrical components during di↵erent ground
faults. It can be seen that all sequence quantities are involved in ground faults. None
the less the positive-sequence quantities should be avoided, since they are highly a↵ected
by normal load current. Thus it would be difficult to distinguished between a high load
situation and fault situation.
50
Phase-Phase-Ground Faults
Single-Line-Ground Faults
Quantity
......Close......
........Far........
......Close......
........Far........
U1
X
X
X
X
U2
X
X
X
X
U0
X
o
X
o
I1
X
X
X
X
I2
X
X
X
X
I0
X
X
X
X
Table 4.5: Available sequence components during ground faults
Therefore the directional element is based on either the zero-sequence or the negative
sequence quantities (configurable by user). Both directional sensing methods use the
wattmetric approach described by the equations (4.9) and (4.10) respectively to distinguish
the fault direction. In case of an isolated star point, the reactive power is examined instead
the active power. This approach is also called sin( ) method and is justified by the fact,
that mainly capacitive fault current flows in case of single-line-to-ground fault. A positive
sign indicates the forward direction and vice versa.
P0 = Re( 3V 0 · 3I ⇤0,adj )
(4.9)
P2 = Re( V 2 · I ⇤2,adj )
(4.10)
Q0 = Im( 3V 0 · 3I ⇤0,adj )
Q2 = Im( V 2 · I ⇤2,adj )
Where
I 0,adj = I 0 · 1\Z 0,line
I 2,adj = I 2 · 1\Z 2,line
Z 0,line is the zero-sequence line impedance and Z 2,line is the negative sequence line impedance. None the less Z 2,line = Z 1,line due to the fact that the faults are considered far
away from rotating machines (see section 2.2.4). Normally the zero-sequence components
are chosen as operating and polarising quantities for the directional element. None the less
in case of strong zero-sequence mutual coupling between two parallel circuits and isolated
zero-sequence sources at the same time, then the negative sequence components are chosen
in order to avoid miss-operation on the healthy lines.
The table 4.5 shows that the zero-sequence and negative sequence voltage might be very
low for far-away faults as indicated by the ’o’. This phenomenon is clarified in the figure
51
4.9, which shows the voltage profile for the negative-sequence and zero-sequence voltage
during a single-line to ground fault. It can be seen that voltage V2 , measured by the relay
at bus G, is higher than 3V0 , if a solidly grounded transformer is connected to the same
bus.
ZT
G
H
Z0GH
Source
Voltages
at relay
3V0
V2
Z0HF
3V0
G
ZT
F
V2
Z0GH
H
F
Z0HF
FIGURE 12.18 Typical voltage profiles of V2 and 3V0 for ground faults.
Figure 4.9: Voltage profiles of V2 and 3V0 for ground faults[23]
With 3V0 maximum at the fault, the value at a grounding bank may be quite
small.
ZT Vof the
transformer is small because of the large bank, and Z0 of the
In such cases either
2 and I2 are chosen as polarising quantities or virtual polarisation is
lines is large because of distance and the +3Z1 factor. Modern ground relay
used as described
byalthe
working
group
Power
Relay
in
direction
units
are quite
sensitD-3
ive, of
sothe
thisIEEE
may not
pose System
a problem
, unleCommittee
ss
lines or settings
arethat
madethe
well
into the
remotise not
adjacent
lines.
[14]. Virtuallong
polarisation
means
faulty
phase
considered,
when calculating
the zero-sequence voltage. This approach yields a high magnitude of the virtual zero12.22 DUAL POLARIZATION FOR GROUND RELAYING
sequence voltage V0,virt , which comprises reliable angle information. The requirement for
A common practice is to use current and voltage polarization jointly. Many
this approach
is a high
selector,
the faulty
ground
relayssensitive
are ‘‘dual phase
polarized.’’
Some which
use twocan
separdistinct
ate directional
units, phase. The
one voltage
polarizedcases
and thefor
other
currentpolarisation.
polarized. They operate in parallel,
table 4.6 depicts
the di↵erent
virtual
so that either one can release the overcurrent units. Other designs use a hybrid
circuit, with oPhase
ne direction
al unit that Virtual
can be energized
current or voltage, or
Selector
pol., by
3V
0,virt
both. These types offer flexibility of application to various parts of the system.
Phase A fault
VB +VC
Phase BDIRECTIONAL
fault
VA+
VC
12.23 GROUND
SENSING
WITH NEGATIVE
SEQUENCE
Phase C fault
VA+VB
An excellent No
alternat
ive is the useV of +negativ
to operate the
selection
V B +e Vsequence
A
C
directional unit. Zero-sequence 3I0 is still used for the fault-detecting overcurrent elements, with V2 and I2 for the directional unit. It is applicable
Table 4.6: Di↵erent cases for virtual polarisation [14]
generally, but is particularly useful at autotransformer stations, with problems, as discussed earlier, and where mutual induction is involved, as
discussed in Section 12.24.
The table 4.7 shows the configurable parameters for the directional element.
! 2006 by Taylor & Francis Group, LLC.
52
Name
Default
Min
Max
Unit
Description
enablePDEFdir
true
true
false
-
Enable directional element
isolNET
false
true
false
-
Enable sin
angZ0
60
0
90
degree
Angle of Z 0,line
thresP67N
0
0
10
p.u.
Threshold of power (P0 or Q0 )
thresV
0.1
0
1
p.u.
Minimum polarising voltage (3 V0 )
enableV2
false
true
false
-
Enable negative-sequence quant.
angZ2
80
0
90
degree
Angle of Z 2,line
thresP67N
0
0
10
p.u.
Threshold of power (P2 or Q2 )
thresV
0.1
0
1
p.u.
Minimum polarising voltage (3 V2 )
method
Table 4.7: Settings for directional element of PDEF
Definite-time earth fault element: The earth fault protection element is based on
the same definite-time principal as described for the PDOC. The characteristic curve has
implemented a 4 stage definite-time curve, whereas the directional sensing can be disabled
for the first stage. The di↵erence to the PDOC is that the PDEF considers the residual
current 3I0 as operating quantity. Moreover the earth fault protection is more sensitive
than the overcurrent protection. Therefore the corresponding thresholds are chosen below
the base current values. The PDEF usually runs at slower sample time than PDOC. None
the less the time delay function runs at the base sample time in order to archive a high
accuracy.
The table 4.8 depicts the configurable parameters of the PDEF.
53
Name
Default
Min
Max
Unit
Description
enable67NST1
true
true
false
-
Enable first stage
disable67Ndir
false
true
false
-
Disable dir. sensing (1.Stage)
thres67NIst1
50
0.5
100
p.u.
Current threshold of first stage
delay67NST1
0.05
0
3
s
Delay time of first stage
reset67NST1
0.05
0
3
s
Reset time of first stage
enable67NST2
true
true
false
-
Enable second stage
thres67NIst2
50
0.5
100
p.u.
Current threshold of second stage
delay67NST2
0.05
0
3
s
Delay time of second stage
reset67NST2
0.05
0
3
s
Reset time of second stage
enable67NST3
true
true
false
-
Enable third stage
thres67NIst3
50
0.5
100
p.u.
Current threshold of third stage
delay67NST3
0.05
0
3
s
Delay time of third stage
reset67NST3
0.05
0
3
s
Reset time of third stage
enable67NST4
true
true
false
-
Enable forth stage
thres67NIst4
50
0.5
100
p.u.
Current threshold of forth stage
delay67NST4
0.05
0
3
s
Delay time of forth stage
reset67NST4
0.05
0
3
s
Reset time of forth stage
blockPDEF
true
true
false
-
Block PDEF after s.p. tripping
thresSP
0.1
0
0.5
p.u.
Thres. to indicate s.p. operation
timePDEF
0.008
0.001
1
s
Sample time of PDEF element
timeTIMER
0.001
0.001
1
s
Sample time of timer element
Table 4.8: Settings for the definite-time curve of PDEF
4.2.5
Phase Selector
The phase selector is mainly needed for two reasons. The virtual polarisation algorithm of
the PDEF directional element has to have information about the faulty phase on order to
calculate the virtual zero-sequence voltage. The second reason is to provide information
about the faulty phase to the trip element during an earth fault and single-pole tripping
enabled. The phase selector is divided into two di↵erent algorithms, which can be selected
by the user. One is based on the di↵erent sequence currents and the other one uses the
sequence voltages. Both of them are described in the following paragraphs. The figure
4.10 depicts the developed phase selector block and its corresponding mask.
54
Phase Selection for Single-Pole Tripping – Weak Infeed Conditions and Cross-Country Faults
The method described in this paper directly checks the angular relationships between
the sequence quantities according to the principle pictured in Fig.2. By using the phase
angle information alone, the recognition is made more robust and faster. Additionally,
this allows for the application of adaptive techniques.
With reference to Fig.5 six symmetrical “bells” are established to enclose the characteristic positions of the negative-sequence current with the positive-sequence current as
reference (Fig.5a), and three “bells” to enclose the characteristic positions of the negative-sequence current with the zero-sequence current as reference (Fig.5b).
The maximum limit angle for the negative-to-positive-sequence check is 0.5•60 degrees = 30 degrees; for the negative-to-positive-sequence check the maximum limit is
0.5•120 degrees = 60 degrees. Practically, the limit angles should be smaller than 30 and
60 degrees, respectively. Smaller limit angles increase precision of fault type identification, but slow down the algorithm and create the danger of failure to operate as a given
fault may not fall into any of the angle “bells” due to some angle abnormalities (seriescompensation, for example).
The presented algorithm checks consistency between the recognition according to
Fig.5a and Fig.5b. If the solution is consistent, it becomes the final fault type identified. If
not, the algorithm uses the voltages.
Figure 4.10: Developed phase selector block and mask
The voltage part is identical to the current-based algorithm. The same relations (Fig.2)
hold true for voltages. The only difference is the adaptive level check for sequence voltCurrent-based algorithm: The current based-algorithm of the phase selector uses the
ages
and different values of limit angles.
characteristic fault pattern for ground faults, as shown in figure 4.11. It can be seen
If only the line-to-line voltages are available, the check shown in Fig.5b cannot be ap-
frombecause
figure 4.11
(a) that one pattern
based on
correlation
positive
plied
the zero-sequence
voltageis cannot
be the
estimated
and between
the faultthe
signature
sequence
and the
negative
sequence of the fault current. It should be noticed that singleshown
in Fig.5a
is applied
only.
to ground faults
(AG,
and CG) can
be distinguished
precisely
by they
If line
the voltage-based
fault
typeBG
recognition
is consistent,
it becomes
the final
faultangular
type
identified.
If not, None
the VOID
flagthe
is line-line-faults
set and the algorithm
its inability
to provide
relationships.
the less
and thereports
line-line-ground
faults
share a
reliable
fault
type
identification.
common angular pattern and therefore can not be distinguished uniquely.
(a)
BG
(b)
AB, ABG
CG, ABG
I1F
I2F
Θmax
I0F
I2F
Θmax
BC, BCG
AG
AG, BCG
Θmax
Θmax
CG
AC, ACG
BG, CAG
Figure
5. Illustration
of the angle
comparator
negative-sequence
vs.(b)
positive-sequence
Figure
4.11:
Fault pattern:
(a)
Positivelimits:
vs. negative
sequence
Negative vs. fault
zero-
sequence [10]
signature (a) and negative-sequence vs. zero-sequence fault signature (b).
The other fault pattern compares the zero-sequence component with the negative-sequence
Page 8 of 19
component of the fault current. It can be seen from figure 4.11 (b) that this algorithm
distinguishes between line-line faults and ground faults. None the less it is not suitable for
55
selection between single-line-ground and line-line-ground faults. Therefore the currentbased phase selector algorithm is based on the positive and negative component of the
fault current, since the single-line to ground faults are of greater importance to the earth
fault protection. Line-line
and line-line-ground
faults
are picked
up by the
HUANG et al.:faults
NOVEL METHOD
OF GROUND FAULT PHASE
SELECTION
IN WEAK-INFEED
SIDE PDOC
anyway due to their high magnitude of fault current.
Voltage-based algorithm: In case of a weak-infeed condition the magnitude of the
fault currents are quite small and therefore can not provide reliable information. In this
case a phase selector algorithm is chosen, which uses the symmetrical components of the
voltage values. This principal has been described in [18]. This algorithm uses the angular relationship between the negative-sequence U 2 and zero-sequence voltage U 0 as well
as between the superimposed positive-sequence
U 1 and superimposed negative-sequence
7. Fault-type
identification.
U 2 voltage. TheFig.
described
phase
selector scheme is depicted in figure 4.12.
Fig. 9. Simulation model. (a) IEEE 39-bus system
between Buses 16 and 21.
the simulation is carried out in the IEE
(shown in Fig. 9) by using the PSC
The fault types include a single-phas
phase-to-phase-to-ground fault. The re
Fig. 8. Scheme of fault phase selection.
Fourier correlation
analysis to extract
Figure 4.12: Scheme of voltage-based phase selector for weak-infeed conditions
[18]
quency components. It takes a transient
where
is the fault region obtained from the distinctive (0.0167 ms) to extract the 60-Hz fundam
The algorithm shows that
it
is
separated
intoortwo
parts,
phaseThe
region
ponents.
sample rate of the relay is
phase region
(e.g., for A-G
BC-G
faults,namely
is A).distinctive
Define
Compared to the sequence current-based fault phase selector,
and fault-type identification. The distinctive phase region is divided into 3 zones, from
this principle can be used in the weak-infeed side. The se-
-90 to 30 , from quence
-210 to
-90 and from 30 to 150 . This part of the schema uses U 0
current-based fault phase selector utilizes the measured
impedance
to distinguish
single-phase-to-ground
as reference to identify
the most
probablebetween
faulty the
phase.
Then the fault-type identification
fault and phase-to-phase-to-ground fault, which may be affected by overload. The method using the relative phase-angle
where is the fault region number obta
the superimposed relationship
voltages U
U 2superimposed
.
between
positive- and nega1 and the
In the IEEE 39-bus system, when the
tive-sequence voltages can solve this problem.
necting Bus 21 to Bus 22 is out of operat
3) Scheme of the Fault Phase Selection: Finally, combining
is under the weak-infeed condition. The
The table 4.9 shows
the phase
selector
thethe
two configurable
steps above, theparameters
scheme for thefor
ground
fault phase
selec- element.
beginning of the line between Bus 16 a
tion is obtained, as shown in Fig. 8. First, the scheme uses the
middle of the line, and k3 is at the end o
relative phase-angle relationship between negative- and zeroat
0.05 s.
sequence voltages to indicate the probable fault phase. Then,
Under the weak-infeed condition, the
the scheme uses the relative phase-angle relationship between
sequence current magnitudes measured
the superimposed positive- and negative-sequence voltages to
are shown in Fig. 10 when an A-G fault w
identify the fault type.
at k3. The negative- and zero-sequence v
56
in phase. Meanwhile, the phase-angle dif
IV. SIMULATION VERIFICATION
perimposed positive- and negative-sequ
In order to verify and evaluate the proposed method of fault 0 . According to the proposed scheme,
phase selection, a series of faults under different conditions phase selection is phase A. Besides, the s
along the transmission line is simulated in this chapter, and fault phase selector cannot be used in su
part di↵erentiates between a single-line-ground fault and a line-line-ground fault based on
Name
Default
Min
Max
Unit
Description
timePS
0.008
0.001
1
s
Sample time of phase selector block
delayPS
0.016
0
1
s
Delay time for stable operation
enableI120
true
true
false
-
Enable current-based algorithm
thresI2
0.05
0
1
p.u.
Thres. of negative-sequence current I2
angLim
10
0
30
degree
Angle tolerance (±)
ringI1
0.80
0
1
s
Size of ring bu↵er for load current I1
enableV120
false
true
false
-
Enable voltage-based algorithm
thresV0
0.1
0
1
p.u.
Thres. of zero-sequence voltage 3 V0
ringV1
0.80
0
1
s
Size of ring bu↵er for voltage V1
Table 4.9: Settings for the phase selector block
4.2.6
Trip Element - PTRC
The trip element is described by the logical node PTRC, which is supposed to be used to
gather the trip signals of all implemented protection functions (PDOC, PDEF) according
to IEC 61850. Moreover the single pole tripping is implemented in the PTRC based on the
information provided by the phase selector. If a single phase has been tripped, the PDEF
usually has to be block due to the high earth fault current in solidly grounded systems.
Lastly once a trip has been issued, the trip relay contact has to remain active for a given
amount of time (e.g >150 ms). This value is also set by the user. The figure 4.13 shows
the developed PTRC block and its corresponding mask.
Figure 4.13: Developed PTRC block and corresponding mask
The table 4.10 shows the configurable parameters.
57
Name
Default
Min
Max
Unit
Description
outputACTIVE
0.15
0.001
3
s
Duration of time for trip outputs
activeSP
true
true
false
-
Enable single pole tripping
delay3P
0.5
0
3
s
Delay time for 3-Phase Trip
timePS
0.008
0.001
1
s
Sample time of phase selector block
Table 4.10: Settings for the PTRC block
4.2.7
EtherCAT-Communication
Above the implementation of the core functionalities of the protection system has been
explained, starting from the sampled values until the trip signal. None the less the communication interface to the process has not been described yet and is done in the following
paragraphs. The communication part of the application is divided into two parts. The
first part consists of the communication driver blocks, which interface with the EtherCAT
master and the corresponding EtherCAT slaves (see section 3.4.1). The second part comprises the communication supervision functionality.
EtherCAT driver blocks: The EtherCAT driver blocks are developed by IgH [39]
and provided by the EtherLAB library. This library provides Simulink blocks for the
EtherCAT coupler EK1100 and the EtherCAT slaves EL2624 (relay output) and EL2798
(digital output). The communication block EL2624 can be seen as the logical node XCBR,
which controls the circuit breaker. None the less there is a generic driver block, which
is used for the EtherCAT slaves not covered by the EtherLAB library. In this case the
EtherCAT slaves EL3773 for the current and voltage inputs is not directly provided by
EtherLAB and therefore the generic block is used. In order to setup the EL3773, a Matlab
structure has to be created, which defines the configuration of the given slave, and this
then given as a parameter to the generic block. The structure is similar the EtherCAT
slaves information (ESI) XML file, provided by the manufacture. The driver block EL3773
can be seen as the logical node TVTR and TCTR, which interface with the voltage and
current transformer respectively. All driver blocks run at the base cycle time. Thus there
is only one domain (see section 2.4.1). The figure 4.14 depicts the used Etherlab library,
which is developed by IgH [4].
58
Figure 4.14: Etherlab library developed by IgH [4]
Communication supervision: The second part consists of the supervision of the communication. Each communication cycle time the working counter of the EtherCAT frame
is checked for consistency. If the working counter deviates from its expected value, which
is an indication for lost or corrupt values, then the value estimation algorithm is triggered
in the signal processing block (see section 4.2.2). If the working counter keeps deviating
from its expected value for a adjustable number of frames in a row, then the protection
function is blocked, since its reliability and security can not be guaranteed anymore.
The tunable parameters of the implemented EtherCAT communication is found in the
table 4.11.
Name
Default
Min
Max
Unit
Description
masterID
0
0
3
-
ID of EtherCAT master to connect to
domainID
0
0
3
-
ID of domain to supervise
lostSV
3
1
5
-
# of lost frames, function is blocked
SIek1100
0
0
1000
-
Slave index of EtherCAT coupler
timeEL1034
0.001
0.001
3
s
Sample time of digital input
SIel1034
1
0
1000
-
Slave index of digital input
timeEL3773
0.001
0.001
3
s
Sample time of analog input
SIel3773
2
0
1000
-
Slave index of analog input
filter
200
200
15000
Hz
Cuto↵ frequency of low pass filter
timeEL2624
0.001
0.001
3
s
Sample time of relay output
SIel2624
3
0
1000
-
Slave index of relay output
timeEL2798
0.001
0.001
3
s
Sample time of digital output
SIel2798
4
0
1000
-
Slave index of digital output
Table 4.11: Configuration of the communication driver blocks and supervision
4.3
Target System
In section 3.4.2 the selection of the runtime environment has been described in terms of
kernel, distribution and EtherCAT master. The following section deals with the configu59
ration of the target system. A guideline to setup the runtime environment is found in the
appendix as well as a detail list of the kernel configuration.
4.3.1
Kernel configurations
In order to evaluate the performance impact of the realtime linux kernel, two di↵erent
kernels are build and compared in section 5.4. All kernels are based on the kernel version
3.4.41. One kernel remains the standard vanilla kernel and the other one is patched with
the preempt-rt patch 3.4.41-rt55-feat3.
The proper configuration of the realtime linux kernel is of importance in order to guarantee real-time capabilities. There are many di↵erent options to tune, before building the
kernel. Below the most important configurations are explained.
Proc types and features -> Preemption Model -> FULL RT
In order to build a fully preemptible kernel, the above option needs to be enabled.
Proc types and features -> Timer Frequency -> Timer Freq 1000
The timer frequency should be set to 1 kHz in order to assure a high scheduling frequency.
This frequency is also called tick rate, defining the resolution of the timer interrupt.
Power Management and ACPI option -> ACPI enable
Power Management and ACPI option -> ACPI -> enable only Power Management Timer
Support
Power Management and ACPI option -> CPU Freq scaling disable
Power Management and ACPI option -> CPU Idle disable
In general power management (e.g. ACPI) should be disabled, since they can decrease
the deterministic behaviour. None the less ACPI is need for the high resolution timer.
Therefore it is enabled above, whereas frequency scaling as well as CPU idle are disabled.
4.3.2
EtherCAT-Master
The IgH EtherCAT master has been implemented according to the Industrial Ethernet
standard IEC 61158-4-12 (Data-link protocol specification) and the 61158-6-12 (Application Layer protocol specification). This EtherCAT master comprises native EtherCAT
drivers for some common Ethernet chips (e.g. e1000, e1000e). Native approach has the
advantage that the NIC writes incoming data directly in the memory (DMA) and the
processors can then just poll the respective memory address. Thus the NIC does not
have to issue an interrupt. None the less the generic linux driver can still be used for
Ethernet chips, which are not supported by the IgH EtherCAT master. None the less this
approach has the disadvantage that the incoming EtherCAT frame has to go through the
lower network stack and therefore issues a soft-interrupt or a hard-interrupt in case of the
60
RT-kernel or the standard vanilla kernel, respectively [39].
Moreover if the target system provides more than one Ethernet device, then multiple
master modules can run in parallel. In order to ensure a deterministic architecture, a
master module can only be controlled by one application. If multiple applications want
to access the same bus, then the respective application, controlling the EtherCAT master,
needs to implement an according locking mechanism [39]. The figure 4.15 clarifies this
3.5 Distributed Clocks
procedure.
Master Module
Application Module
Application
Interface
Task
Master0
EoE
Figure
3.3: Concurrent
Access
Figure 4.15:
Concurrent
access ofMaster
EtherCAT
master [39]
Furthermore
the IgH EtherCAT
master provides the capability of domains for di↵erent
3.5
Distributed
Clocks
task periods as well as of the distributed clock mechanism (see section 2.4.1). The figure
From
version
the master
supports
EtherCAT’s
Clocks” feature. It
4.16 shows
the1.5,
described
architecture
of the
EtherCAT “Distributed
master.
is possible to synchronize the slave clocks on the bus to the “reference clock” (which
is the local clock of the first slave with DC support) and to synchronize the reference
In consideration of the described hardware in section 3.4.1 and the implemented runtime
clock to the “master clock” (which is the local clock of the master). All other clocks
environment
in section
3.4.2, the clock)
following
configurations
of the (see
EtherCAT
on
the bus (after
the reference
areimportant
considered
as “slave clocks”
Figuremas3.4).
ter has been chosen:
Master
--enable-generic=yes
The generic linux driver is Slave
enabled
later.
0 for testing
Slavepurposes
1
Slave 2
Master Clock
Slave n
(No DC)
--enable-8139too=no
The driver 81379too is not needed dueReference
to the selected
Clock hardware. Slave Clocks
--enable-e1000e=yes
Figure 3.4: Distributed Clocks
Since the target system supports PCI express, the native EtherCAT driver e1000e is selected as well.
Local Clocks Any EtherCAT slave that supports DC has a local clock register with
nanosecond resolution. If the slave is powered, the clock starts from zero, meaning
--enable-cycles=yes
that
when slaves are powered on at different times, their clocks will have different
values.
These
“offsets” have
to architectures
be compensated
by the
distributed
clockscalculations.
mechanism.
This option
is supported
by Intel
in order
to achieve
finer timing
On the other hand, the clocks do not run exactly with the same speed, since the
used quarts units have a natural frequency deviation. This deviation is usually very
--enable-debug-if=yes
small, but over longer periods, the error would accumulate and the difference between
local clocks would grow. This clock “drift” has also to be compensated by the DC
61
mechanism.
Application Time The common time base for the bus has to be provided by the
application. This application time t
is used
If the native EtherCAT driver is chosen, there won’t be any Ethernet interface, since the
EtherCAT frame does not go through the network stack. None the less a debug interface
should be provided to capture some EtherCAT frames with Wireshark for diagnostic purposes.
--enable-debug-ring=yes
The recorded frames at the debug interface are then stored in a ring bu↵er.
RTDM
Device
Master 1
Application
Interface
ecrt_*()
Task
Generic
Ethernet
Driver Module
EtherCAT Master Module
Master 0
Generic
Ethernet
Device
Device
Interface
ecdev_*()
netif_*()
Native EtherCAT-capable Ethernet Driver
net_device
Hardware
Network Stack
Application Module
Character
Device
Packet Socket
Kernelspace
NIC
net_device
NIC
EtherCAT
Standard
Ethernet Driver
net_device
NIC
EtherCAT
Ethernet
2.1: Master
Figure 4.16:Figure
Architecture
of IgHArchitecture
EtherCAT master [39]
6
72b61b089625, 2013/12/10
62
Chapter 5
Evaluation
After the design and implementation phase of the model-based design approach, the test
phase is conducted. The test phase has the objective of code verification and validation
as well as to guarantee the compliance of the solution to the requirements.
5.1
Evaluation Method
The evaluation process of the protection system consists of di↵erent dimensions. Firstly,
a functional performance test is conducted on three di↵erent levels, as shown in figure 5.1.
On the first level the model-in-the-loop test is executed in order to evaluate the functionality of the implemented algorithm. On the second level, the software-in-the-loop test is
performed. The purpose of Sil is the verification and valudation of the the automatic code
generation of the Simulink Coder. This is done by comparing the SiL solution with the
MiL solution (see section 5.2.1). Thirdly, those simulated test results need to be compared
with the hardware-in-the-loop results (see section 5.2.2). The successful deployment of the
protection application on the target system is evaluated by the Hil test.
In addition to the described functional performance test above a type test is conducted as
required in the IEC 60255-151 for overcurrent protection systems (see 5.3). The results of
the type test are compared with comparable IEDs of OEMs like ABB or Siemens. Once
the functionality of the protection system has been proven and its compliance to the IEC
60255-151 has been tested, then the long term stability of the system is evaluated in section
5.4. The stability test is important to evaluate the performance of the realtime operating
system RT-Linux. Lastly, the I/O modules are examined in terms of their environmental
compliances to the requirements for power system environment (see section 5.5 and 3.2.2).
63
simulate
Simulink
Model
check results
Model-in-the-loop
Matlab/Simulink
compare results
COMTRADE
Files
simulate
feed to test harness
S-function
(compiled mex-file)
check results
Software-in-the-loop
Matlab/Simulink
compare results
inject
Omicron
Target System
check results
Hardware-in-the-loop
Figure 5.1: Functional performance test
5.2
5.2.1
Functional Performance Tests
Model- & Software-in-the-Loop
This section has two objects. On the one side the automatic code generation process,
conducted by the Simulink Coder, is verified and validated. This is done by the comparison
between the results of the MiL with the results of SiL. The second object of this part is
to assure the intended functionality of the implemented protection function. Therefore
three di↵erent fault scenarios are tested for the PDOC as well as the PDEF. Those fault
scenarios are provided as COMTRADE files. COMTRADE is the file format for recording
disturbances in power systems. Usually those files a generated by the disturbance recorders
located in the substations. Those files provide the three-phase voltages and currents as
primary values with a sampling frequency of 1 kHz. The time duration lasts from some
multiple 100 ms before the fault until some multiple 100 ms after the fault has been cleared.
Another reason to use COMTRADE files is the possibility to provide those files as input
to the signal generator (Omicron) in the Hardware-in-the-Loop section. Thus it can be
guaranteed to provide the same fault scenario as in MiL and SiL without the usage of a
real-time simulator until the trip signal occurs.
64
Figure 5.2: Single-line-diagram of first network
The figures 5.2.1 and 5.3 depict the two networks, which have been used for generating
the fault scenarios in section 5.2.1 and 5.2.1.
Figure 5.3: Single-line-diagram of second network with parallel lines
Moreover the table 5.1 shows the configuration of the protection system, which is used for
all di↵erent fault scenarios described below. It can bee seen that the communication driver
blocks and trip element run at the base sample time of 1 ms. The other protection elements
like signal processing element, PDOC, PDEF and the phase selector run at a sample time
of 8 ms. Another important setting is the angle of the positive- and zero-sequence line
impedance. Those parameters are set to 80 degrees and 60 degrees, respectively, in order
to assure correct operating directional elements. In addition, only the first stage of the
definite-time curve of the PDOC and of the PDEF are activated for the cases 1-3 and 4-6
respectively. Lastly, the trip contact remains active for 100 ms, as well. The configuration
of the definite-time curve is specified for each case individually.
65
Name
Default
Min
Max
Unit
Description
freq
50
50
60
Hz
Fundamental frequency
nrSV
1
1
10
-
Oversampling factor
timePRE
0.001
0.001
1
s
Sample time of input port
timeSP
0.008
0.001
1
s
Sample time of signal proc. element
angZ1
80
0
90
degree
Angle of Z 1,line
thresP67
0.1
0
10
p.u.
Threshold of active power
thresV
0.1
0
1
p.u.
Minimum polarising voltage (V1 )
angZ0
60
0
90
degree
Angle of Z 0,line
thresP67N
0.1
0
10
p.u.
Threshold of power (P0 or Q0 )
thresV
0.2
0
1
p.u.
Minimum pol. voltage (3 V0 )
timePS
0.008
0.001
1
s
Sample time of phase selector block
delayPS
0.016
0
1
s
Delay time for stable operation
enableI120
true
true
false
-
Enable current-based algorithm
outputACTIVE
0.15
0.001
3
s
Duration of time for trip outputs
activeSP
true
true
false
-
Enable single pole tripping
delay3P
0.5
0
3
s
Delay time for 3-Phase Trip
timePS
0.008
0.001
1
s
Sample time of phase selector block
timeEL3773
0.001
0.001
3
s
Sample time of analog input
filter
200
200
15000
Hz
Cuto↵ frequency of low pass filter
timeEL2624
0.001
0.001
3
s
Sample time of relay output
Table 5.1: General configuration for the functional performance test
Directional Overcurrent Protection - PDOC
By the means of the following three test scenarios the functionality of the PDOC is evaluated as well as the automatic code generation is validated. This is done by comparing
the results from the MiL and SiL tests with each other.
Case 1: forward single-phase-to-earth fault (phase A)
This test scenario represents a single-phase-to-ground fault at the fault location F 5 in
figure 5.2.1. Thus the general functionality of the PDOC is tested. Moreover the correct
directional sensing and phase selection is proven. The voltage measurements are taken
from bus A and the current measurements are yield from line A to B.
The figure 5.4 shows the condition for a single-phase-to-ground fault for the MiL test.
In total there are five di↵erent points in time indicated by fault occurrence tf , appearance
of start signal tstr , appearance of trip signal ttr , disappearance of start signal tdis and
disappearance of trip signal tres . The time durations between tf and tstr and between
66
tstr and ttr are called start time and trip time, respectively. In addition, the disengaging
time and reset time is the time duration between ttr and tdis and between tdis and tres ,
respectively. Those times need to be evaluated as part of the type test in section 5.3.
Fault situation in case 1 for MiL
SV
Magn i t u d e
S t ar t
Tr i p
D i r e c t i on
√
2 x Thre s.
10
Current [p.u.] & Boolean [0,1]
8
6
4
2
0
−2
−4
tf tstr
−6
0
0.05
0.1
0.15
0.2
ttrtdis
0.25
time [s]
0.3
0.35
tres
0.4
0.45
0.5
Figure 5.4: Fault situation of case 1 for MiL
In case 1, the following times have been measured for the MiL test:
start time :
tstr
tf = 17 ms
trip time :
ttr
tstr = 100 ms
disengaging time :
tdis
ttr = 12 ms
reset time :
tres
tdis = 100 ms
Moreover from the figure 5.4 it can be seen that the directional sensing works correctly as
well as the phase selection of phase A has been performed as expected. In addition the
protection system needs a certain amount of time (start time) to detect the fault. This is
mainly caused by the fact that the signal processing element uses a running window, which
has to be filled with sampled values of the fault current (see section 4.2.2). Therefore a
time delay occurs from the injection of the fault until the start signal occurs. The same
phenomena occurs once the trip signal occurs. The time from fault clearance until the
start signal vanishes is regarded as disengaging time.
67
The same fault situation, represented by the COMTRADE file, is tested in the SiL context as depicted in figure 5.5 below. Examining the curves, the SiL test shows the same
behaviour as the MiL test, which is a good indication for a successful code generation
process. None the less a closer look at the exact characteristic times has to be conducted.
Fault situation in case 1 for SiL
SV
Magn i t u d e
S t ar t
Tr i p
D i r e c t i on
√
2 x Thre s.
10
Current [p.u.] & Boolean [0,1]
8
6
4
2
0
−2
−4
t t
−6
0
f
0.05
0.1
0.15
t t
str
0.2
tr dis
0.25
time [s]
0.3
0.35
t
res
0.4
0.45
0.5
Figure 5.5: Fault situation of case 1 for SiL
In case 1, the following times have been measured for the SiL test:
start time :
tstr
tf = 17 ms
trip time :
ttr
tstr = 100 ms
disengaging time :
tdis
ttr = 12 ms
reset time :
tres
tdis = 100 ms
It can be seen that the MiL and the SiL test yield exactly the same results. Therefore the
conclusion is drawn that the automatic code generation process has been successful.
The table 5.2 show the configuration of the protection application for case 1.
68
Name
Default
Min
Max
Unit
Description
enableST1
true
true
false
-
Enable first stage
disableDIRst1
false
true
false
-
Disable dir. sensing (1.Stage)
thresIst1
3.5
0.5
100
p.u.
Current threshold of first stage
delayST1
0.1
0
3
s
Delay time of first stage
resetST1
0.1
0
3
s
Reset time of first stage
timePDOC
0.008
0.001
1
s
Sample time of PDOC element
timeTIMER
0.001
0.001
1
s
Sample time of timer element
Table 5.2: Configuration of application for case 1
Case 2: Forward single-phase-to-earth fault, 44.5 Hz system frequency
For case 2 the same fault scenario is applied as for case 1. None the less the system
frequency has a quite low value of 44.5 Hz instead of 50. A frequency of 44.5 Hz is not
a realistic case for the operation of power systems. None the less it is interesting to see
how the signal processing element, which is designed to extract the 50 Hz component, can
handle such a large deviation from the nominal frequency. Thereby the reliability of the
signal processing element is tested.
The figure 5.6 shows the measurements for the MiL test. First of all the correct operation of the protection system can be noted. None the less there are also di↵erence in
comparison to case 1. The calculated magnitude of the 44.5 Hz varies during the steadystate conditions. In addition the start time is longer, since the calculated magnitude of the
signal processing element rises slower than in case 1. The same phenomena is witnessed
for the disengaging time.
69
Fault situation in case 2 for MiL
SV
Magn i t u d e
S t ar t
Tr i p
D
√ i r e c t i on
2 x Thre s.
10
Current [p.u.] & Boolean [0,1]
8
6
4
2
0
−2
−4
−6
−8
t
−10
0.3
t
f
0.35
0.4
0.45
t t
str
0.5
t
tr dis
0.55
time [s]
0.6
0.65
res
0.7
0.75
0.8
Figure 5.6: Fault situation of case 2 for MiL
In case 2, the following times have been measured for the MiL test:
start time :
tstr
tf = 29 ms
trip time :
ttr
tstr = 100 ms
disengaging time :
tdis
ttr = 12 ms
reset time :
tres
tdis = 100 ms
In case of the Sil test the results are shown in figure 5.7 below. Exact the same behaviour
is noted as for the Mil case. This can be clearly seen when comparing the di↵erent time
durations start-, trip-, disengaging- and reset time of Mil and Sil with each other.
70
Fault situation in case 2 for SiL
SV
Magn i t u d e
S t ar t
Tr i p
D
√ i r e c t i on
2 x Thre s.
10
Current [p.u.] & Boolean [0,1]
8
6
4
2
0
−2
−4
−6
−8
t
−10
0.3
t
f
0.35
0.4
0.45
t t
str
0.5
t
tr dis
0.55
time [s]
0.6
0.65
res
0.7
0.75
0.8
Figure 5.7: Fault situation of case 2 for SiL
In case 2, the following times have been measured for the SiL test:
start time :
tstr
tf = 29 ms
trip time :
ttr
tstr = 100 ms
disengaging time :
tdis
ttr = 12 ms
reset time :
tres
tdis = 100 ms
In conlusion it can be said, that the signal processing element also works reliable for large
frequency deviations from its nominal value. The table 5.3 show the configuration of the
protection application for case 2.
71
Name
Default
Min
Max
Unit
Description
enableST1
true
true
false
-
Enable first stage
disableDIRst1
false
true
false
-
Disable dir. sensing (1.Stage)
thresIst1
3.5
0.5
100
p.u.
Current threshold of first stage
delayST1
0.1
0
3
s
Delay time of first stage
resetST1
0.1
0
3
s
Reset time of first stage
timePDOC
0.008
0.001
1
s
Sample time of PDOC element
timeTIMER
0.001
0.001
1
s
Sample time of timer element
Table 5.3: Configuration of application for case 2
Case 3: Reverse 3-phase fault (close-by)
In the last case for the PDOC element a reversed three-phase fault is applied at position
F 11 in figure 5.2.1, which is in close proximity of the bus A in figure 5.3. This scenario
represents are switch-on fault, meaning that the circuit breakers are closed onto a faulty
line at the time instance of 200 ms. Moreover the magnitudes of the voltages are almost
zero due to the close-by fault. The objective of this case is to test the correct operation
of the directional element based on the memory voltage (see section 4.2.3).
The figure 5.8 shows the measurements for the MiL test. It can be seen that there no
currents flowing up to time instance of 200 ms due to the opened lines. Once the fault
is applied the current magnitude rises quickly over the set threshold. None the less no
start signal occurs, since the directional element senses the fault correctly in the reverse
direction.
72
Fault situation in case 3 for MiL
12
SV
Magn i t u d e
S t ar t
Tr i p
D
√ i r e c t i on
2 x Thre s.
10
Current [p.u.] & Boolean [0,1]
8
6
4
2
0
−2
−4
−6
−8
0
tf
0.05
0.1
0.15
0.2
0.25
time [s]
0.3
0.35
0.4
0.45
0.5
Figure 5.8: Fault situation of case 3 for MiL
The same situation is depicted in figure 5.9 for the Sil test. Exactly the same behaviour
is noticed and therefore the code generation process is seen as verified.
73
Fault situation in case 3 for SiL
12
SV
Magn i t u d e
S t ar t
Tr i p
D
√ i r e c t i on
2 x Thre s.
10
Current [p.u.] & Boolean [0,1]
8
6
4
2
0
−2
−4
−6
−8
0
tf
0.05
0.1
0.15
0.2
0.25
time [s]
0.3
0.35
0.4
0.45
0.5
Figure 5.9: Fault situation of case 3 for SiL
The table 5.4 show the configuration of the protection application for case 3.
Name
Default
Min
Max
Unit
Description
enableST1
true
true
false
-
Enable first stage
disableDIRst1
false
true
false
-
Disable dir. sensing (1.Stage)
thresIst1
3.5
0.5
100
p.u.
Current threshold of first stage
delayST1
0.1
0
3
s
Delay time of first stage
resetST1
0.1
0
3
s
Reset time of first stage
timePDOC
0.008
0.001
1
s
Sample time of PDOC element
timeTIMER
0.001
0.001
1
s
Sample time of timer element
Table 5.4: Configuration of application for case 3
Directional Earth Fault Protection - PDEF
The following test cases 4 to 6 are performed in order to verify the correct operation of
the PDEF function.
Case 4: High resistive forward SGL-fault (phase A)
In case 4 a high resistive single-line-to-ground fault is applied in forward direction on phase
A at the position F 5 in figure 5.2.1. Due to the nature of low residual currents in case of
74
a high resistive fault the zero-sequence voltage, measured at bus A, is below 0.1 p.u. and
therefore the implemented virtual polarisation algorithm is used (see section 4.2.4).
The figure 5.10 shows the described situation for the MiL test. In spite of the very
low zero-sequence voltage (3xV0 ) during the fault, the directional sensing is performed
correctly and the fault is cleared. Furthermore the residual fault current (3xI0 ) has a
RMS value of 0.4 p.u. Thus it would not be possible to detect this fault with the PDOC
function.
Fault situation in case 4 for MiL
2.5
Current [p.u.] & Boolean [0,1]
2
3xV0
3xI0
Start
Trip
Direction
Threshold
1.5
1
0.5
0
−0.5
t
−1
0
t
f
0.05
0.1
0.15
t t
str
0.2
t
tr dis
0.25
time [s]
0.3
0.35
res
0.4
0.45
0.5
Figure 5.10: Fault situation of case 4 for MiL
The following duration of times are yield in case 4 for the Mil test.
start time :
tstr
tf = 25 ms
trip time :
ttr
tstr = 100 ms
disengaging time :
tdis
ttr = 12 ms
reset time :
tres
tdis = 100 ms
The same high-resistive fault situation is tested for the Sil test. The figure 5.11 shows the
result of this corresponing case. Comparing the figures 5.10 and 5.11 shows that they are
identical. This becomes even clearer, when comparing the start- , trip- , disengaging- and
reset time of Mil and Sil with each other.
75
Fault situation in case 4 for SiL
2.5
3xV0
3xI0
Start
Trip
Direction
Threshold
Current [p.u.] & Boolean [0,1]
2
1.5
1
0.5
0
−0.5
t
−1
0
t
f
0.05
0.1
0.15
t t
str
0.2
t
tr dis
0.25
time [s]
0.3
0.35
res
0.4
0.45
0.5
Figure 5.11: Fault situation of case 4 for SiL
In case 4, the following times have been measured for the SiL test:
start time :
tstr
tf = 25 ms
trip time :
ttr
tstr = 100 ms
disengaging time :
tdis
ttr = 12 ms
reset time :
tres
tdis = 100 ms
The table 5.5 show the configuration of the protection application for case 4.
Name
Default
Min
Max
Unit
Description
enable67NST1
true
true
false
-
Enable first stage
disable67Ndir
false
true
false
-
Disable dir. sensing (1.Stage)
thres67NIst1
0.3
0.5
100
p.u.
Current threshold of first stage
delay67NST1
0.1
0
3
s
Delay time of first stage
reset67NST1
0.1
0
3
s
Reset time of first stage
Table 5.5: Configuration of application for case 4
Case 5: Forward SGL-fault (phase A), single pole tripping
In case 5 the successful blocking of the PDEF function after single pole tripping is evaluated. This is important in order to prevent miss-operation during an unbalance operation
76
of the power system with only two phases. The fault is applied at position F 5 in figure .
The figure 5.12 shows the behaviour of the protection system for the MiL test. It can
be seen that the PDEF function operates correctly, in spite of the presents of very low
zero-sequence voltage. Additionally, there is no second trip during the two-pole operation
of the network. The directional elements senses a residual power flow in forward direction.
None the less the start signal is blocked for this situation.
Fault situation in case 5 for MiL
4
Current [p.u.] & Boolean [0,1]
3.5
3
3xV0
3xI0
Start
Trip
Direction
Threshold
2.5
2
1.5
1
0.5
0
−0.5
−1
0
t
t
f
0.05
0.1
0.15
t t
str
0.2
t
tr dis
0.25
time [s]
0.3
0.35
res
0.4
0.45
0.5
Figure 5.12: Fault situation of case 5 for MiL
In case 5, the following times have been measured for the MiL test:
start time :
tstr
tf = 25 ms
trip time :
ttr
tstr = 100 ms
disengaging time :
tdis
ttr = 12 ms
reset time :
tres
tdis = 100 ms
In figure 5.13 the Sil test is depicted for the given fault scenario above. Comparing both
figures it is verified that the compiled function works in the same way as the designed
model.
77
Fault situation in case 5 for SiL
3xV0
3xI0
Start
Trip
Direction
Threshold
4
Current [p.u.] & Boolean [0,1]
3.5
3
2.5
2
1.5
1
0.5
0
−0.5
−1
0
t
t
f
0.05
0.1
0.15
t t
str
0.2
t
tr dis
0.25
time [s]
0.3
0.35
res
0.4
0.45
0.5
Figure 5.13: Fault situation of case 5 for SiL
In case 5, the following times have been measured for the SiL test:
start time :
tstr
tf = 25 ms
trip time :
ttr
tstr = 100 ms
disengaging time :
tdis
ttr = 12 ms
reset time :
tres
tdis = 100 ms
The table 5.6 show the configuration of the protection application for case 5.
Name
Default
Min
Max
Unit
Description
enable67NST1
true
true
false
-
Enable first stage
disable67Ndir
false
true
false
-
Disable dir. sensing (1.Stage)
thres67NIst1
0.3
0.5
100
p.u.
Current threshold of first stage
delay67NST1
0.1
0
3
s
Delay time of first stage
reset67NST1
0.1
0
3
s
Reset time of first stage
Table 5.6: Configuration of application for case 5
Case 6: Changing direction of power flow
The case 6 is simulated with the single-line diagram in figure 5.3. The fault location is at
78
F18 closer to bus B than to A and the voltage measurements are taken from bus A and
the current measurements from line A1 to B1.
Examining figure 5.14, a forward power flow is detected during fault inception. At the
time instance of 0.31 ms circuit breaker B2 opens and the fault current flows in the reverse
direction as seen from circuit breaker A1. Then at the time instance of roughly 0.38 ms the
the circuit breaker A2 opens and the fault is cleared (single pole tripping). Thereby one
of the main objectives of a protection system, namely selectivity, is provided by PDEF, if
the time delay is set accordingly. In this cases the time delay is set to 150 ms. Since the
fault duration in forward direction only occurs for 88 ms, the protection system does not
operate.
Fault situation in case 6 for MiL
7
Current [p.u.] & Boolean [0,1]
6
3xV0
3xI0
Start
Trip
Direction
Threshold
5
4
3
2
1
0
−1
0
0.05
0.1
0.15
tf
tstr
0.2
0.25
time [s]
0.3
tdis
0.35
0.4
0.45
0.5
Figure 5.14: Fault situation of case 6 for MiL
In case 6, the following times have been measured for the MiL test:
start time :
tstr
tf = 25 ms
duration of start :
tdis
tstr = 88 ms
The figure 5.14 and 5.15 depict the same behaviour of the protection system as well as
the start time are exactly the same in both cases.
79
Fault situation in case 6 for SiL
3xV0
3xI0
Start
Trip
Direction
Threshold
7
Current [p.u.] & Boolean [0,1]
6
5
4
3
2
1
0
−1
0
t
0.05
0.1
t
f
0.15
str
0.2
0.25
time [s]
t
0.3
dis
0.35
0.4
0.45
0.5
Figure 5.15: Fault situation of case 6 for SiL
In case 6, the following times have been measured for the SiL test:
start time :
tstr
tf = 25 ms
duration of start :
tdis
tstr = 88 ms
The table 5.7 show the configuration of the protection application for case 6.
Name
Default
Min
Max
Unit
Description
enable67NST1
true
true
false
-
Enable first stage
disable67Ndir
false
true
false
-
Disable dir. sensing (1.Stage)
thres67NIst1
0.3
0.5
100
p.u.
Current threshold of first stage
delay67NST1
0.15
0
3
s
Delay time of first stage
reset67NST1
0.15
0
3
s
Reset time of first stage
Table 5.7: Configuration of application for case 6
5.2.2
Hardware-in-the-Loop
In the previous section it has been shown that the protection application operates as
expected. In the Hil test the same fault scenarios are applied as for the Sil test in order
to evaluate the overall system performance and to prove the successful integration on the
target system. The figure 5.16 shows the setup in the laboratory.
80
Figure 5.16: Laboratory setup for the Hardware-in-the-loop test
The 24 DC power supply supplies the EtherCAT coupler and slaves. The generated analog current and voltage values, corresponding to the fault scenarios in section 5.2.1, are
provided by the signal generator OMICRON to the current and voltage inputs (EL3773),
respectively. In addition, the relay outputs (EL2624) are linked back to the binary inputs
of the OMICRON for time tracking purposes. The EtherCAT coupler is connected via a
CAT-5 patch cable to the computer running the protection function as a kernel module in
RT-Linux.
The tables 5.8 and 5.9 depict the comparison between the Hil results and the Sil results. It can be seen that only the start and trip time is given. The reason for that is that
the software, which runs the OMICRON, can only replay the entire COMTRADE file and
can not change the current and voltage values during the playback time. Therefore the
same situation as in Mil and Sil can only be recreated, until the trip signal occurs.
Directional Overcurrent Protection - PDOC
The table 5.8 shows the case 1 to 3 for the PDOC function. The protection function
behaves in the same manner as for the Mil and Sil scenario. It operates for case 1 and 2
and not for case 3. None the less it can be seen that the start time di↵ers. This is due to the
fact that the signal processing element runs at sample time of 8 ms and the application
is not synchronised to the signal generator OMICRON. Once the fault is applied, it is
unknown when the signal processing element is executed the next time. Thus there is an
algorithmic jitter of 8 ms. None the less the trip time is quite deterministic, since the
timer functions run at a sample time of 1 ms. The maximum time resolution of the used
signal generator in this project is 100 µs.
81
Hil
SiL
start time
23.3 ms
17 ms
trip time
99.8 ms
100 ms
start time
33.6 ms
29 ms
trip time
99.7 ms
100 ms
start time
- ms
- ms
trip time
- ms
- ms
CASE 1
CASE 2
CASE 3
Table 5.8: Comparison between Hil and Sil results (PDOC)
Directional Earth Fault Protection - PDEF
In table 5.9 the results of case 4 to 6 are shown for the PDEF function. The same behaviour
is witnessed for the Hil as well as Sil scenario. The trip times are deterministic, having a
jitter of 200 µs.
Hil
SiL
start time
27.4 ms
25 ms
trip time
99.8 ms
100 ms
start time
28.5 ms
25 ms
trip time
99.8 ms
100 ms
start time
32.8 ms
25 ms
trip time
- ms
- ms
duration of start
86.7
88ms
CASE 4
CASE 5
CASE 6
Table 5.9: Comparison between Hil and Sil results (PDEF)
5.3
Type Tests
In this section the performed type test is evaluated, which is described in the standard IEC
60255-151. The obtained results are compared with an ABB and Siemens relay, described
in table 5.10 below. The values below can not be compared directly, since both OEMs use
di↵erent settings in order to calculate those accuracy levels. The data below is based on
the technical manuals provided by the corresponding manufactures [5] [6].
82
Quantity
Pick-up value
ABB: REL670 2.0
Siemens: 7SJ82
Accuracy
Accuracy
Drop-o↵ value
± 1.0 % of In
Reset ratio
>95 %
start time
operate time
disengaging time
± 1.0 % of Iset
or 5 mA
config. 90 % to 99 %
Min: 15 ms
Max: 30 ms
± 0.2 % or ± 35 ms
Min: 15 ms
Max: 30 ms
Approx. 37 ms + OOT
± 1 % or ± 10 ms
Approx. 20 ms + OOT
1 % or ± 10 ms
reset time
-
Overshoot time
10 ms
Transient overreach
-
<5%
Angle error
± 2 degrees
± 1 degrees
-
Table 5.10: Type test results of common relays on the market for PDOC function
In in the table above is usually 1 A or 5 A. Iset in the table above can be set from 30
mA to 35 A for the Siemens relay. OOT means output operating time and described the
additional time due to the output medium. For fast relays this value is usually 5 ms.
5.3.1
Accuracy of pick-up and drop-o↵ value
The accuracy of the pick-up and drop-o↵ values are tested by the means of ramping test.
The initial value is set to 20 mA below the given threshold in case of the pick-up value
testing and the ramping steps are 10 times smaller than the given accuracy for the element
EL3773, which is given by 7.5 mA. Thus the ramping steps are set to 750 µA. In addition
the step time of the ramping function shall be between 2 and 5 times of the start time,
which is given in section 5.3.3. Thus the step time is set to 50 ms. In case of drop-o↵
value testing, the same ramping function is applied just with a negative slope.
Considering the ramping function described above, ten di↵erent test points have been
selected along the entire available range from 50 mA to 1 A. Each of the test points has
been tested for the individual phases 5 times. The table 5.11 shows the average and
maximum error for each of those test points.
83
Pick-up
Drop-o↵
Threshold
Average
Maximum
Average
Maximum
50 mA
0.25 mA
0.25 mA
0.33 mA
0.5 mA
54.75 mA
0.5 mA
0.5 mA
0.5 mA
0.5 mA
59.5 mA
0.5 mA
0.5 mA
0.5 mA
0.5 mA
69 mA
0.25 mA
0.25 mA
0.25 mA
0.25 mA
78.5 mA
0.5 mA
0.5 mA
0.5 mA
0.5 mA
97.5 mA
0.25 mA
0.25 mA
0.25 mA
0.25 mA
145 mA
0.5 mA
0.5 mA
0.5 mA
0.75 mA
335 mA
0.5 mA
0.5 mA
0.54 mA
0.75 mA
620 mA
0.25 mA
0.25 mA
0.46 mA
1.0 mA
1000 mA
0.25 mA
0.25 mA
0.75 mA
1.0 mA
Average
0.5 mA
0.75 mA
Maximum
0.5 mA
1 mA
Table 5.11: Average & maximum error of pick-up/drop-o↵ for 10 di↵erent test points
The maximum errors are 0.5 mA and 1 mA for the pick-up and drop-o↵ value, respectively.
Those level of accuracy is really good in comparison to other relays. None the less the
operating range of the analog input (EL3773) is not sufficiant (max 1.2 A RMS) to operate
in a power system environment. The ABB relay REL670 2.0 above states an accuracy
of ±1 % of In for the pick-up and drop-o↵ value, where In is usually 1 A or 5 A. The
Siemens relay 7SJ82 of the SIPROTEC 5 series states an accuracy of ±1 % of Iset or 5
mA, depending which is greater, for the pick-up and drop-o↵ value.
5.3.2
Determination of reset ratio
In table 5.12 the reset ratio is depicted. The reset ratio is given by the ratio of the actual
pick-value and the actual drop-o↵ value. For this test the same ten test points are selected
as for the accuracy of the pick-up/drop-o↵ value. The average and minimum values are
shown for each test point, which has been tested five times on a individual phase basis.
84
Reset ratio
Threshold
Average
Minimum
50 mA
99.50 %
99.00 %
54.75 mA
98.19 %
98.19 %
59.5 mA
98.33 %
98.33 %
69 mA
99.28 %
99.28 %
78.5 mA
98.73 %
98.73 %
97.5 mA
99.49 %
99.49 %
145 mA
99.31 %
99.14 %
335 mA
99.69 %
99.63 %
620 mA
99.89 %
99.80 %
1000 mA
99.90 %
99.88 %
Average
99.23 %
Minimum
98.19 %
Table 5.12: Average and minimum value of reset ratio
The average and minimum reset ratio of the implemented protection system is given by
99.23 % and 98.19 %, respectively. The ABB relay shows a reset ratio of greater than
95 % and the Siemens relay has the option to configure the reset ratio from 90 % to 99
%. Comparing those results against reset ratios of common relays on the market, it can
be seen that the obtained results are competitive. None the less the described narrow
operating range of the analog input is a limiting factor.
5.3.3
Steady state errors of start and operate time
In this section the accuracy of the start and operate time is evaluated. This test has been
performed with di↵erent ratios of
If ault
Iset ,
as shown in figure 5.17. It should be kept in mind
that the time resolution of the OMICRON device is 100 µs. The accuracy test below has
been conducted for 360 test points.
Start time:
The figure 5.17 shows the distribution of the start time for di↵erent
If ault
Iset
ratios. The
start time is measured from the point in time of fault occurrence until the pick-up signal
appears. The first thing, that should be noticed, is that the recorded start time is always
a multiple of 8 ms. This is due to the fact that the application has been synchronised to
the OMICRON. That means, when the fault is applied exactly, when the signal processing
element is executed, which runs at a sample time of 8 ms. Moreover the start time tends
to decrease with an increase of the
If ault
Iset
ratio. This phenomenon is caused by the fact,
that only few sampled values of the fault current are needed to calculate a RMS value
above the threshold value.
85
Distribution of start time for different (Ifault/Iset) ratios
1
Ratio 1.2
Ratio 2
Ratio 5
Ratio 10
Ratio 20
0.9
0.8
Probability
0.7
0.6
0.5
0.4
0.3
0.2
0.1
0
0
0.005
0.01
0.015
0.02
Start time in [s]
0.025
Figure 5.17: Distribution of start time for di↵erent
0.03
If ault
Iset
ratios
The worst-case start time, which is measured above, equals 32.4 ms. ABB states for its
relay a minimum start time of 15 ms and a maximum start time of 30 ms. Siemens claims
to achieve a start time of approximately 37 ms plus some additional operating time (approx. 5 ms) for the relay operation. Considering those values, the start times, obtained for
the developed protection function based on COTS components, are considered as sufficient.
Operate time:
The accuracy of the operate time is measured for di↵erent delay times 0 s, 600 ms and 3 s.
The operate time is defined by the duration from the appearance of the pick-up value until
the trip signal occurs. Therefore the operate time should not be dependent on the
If ault
Iset
ratio, but rather on the deterministic behaviour of the operating system. The figures 5.18
(a), (b) and 5.19 show the distribution of the recorded operate time for the delay times 0
s, 600 ms and 3 s, respectively. It can be seen that the deviation from the expected value
is very small.
86
Distribution of accuracy of operate time
Distribution of accuracy of operate time
0.8
0.7
Set time delay: 0s
Set time delay: 0.6s
0.7
0.6
0.6
0.5
Probability
Probability
0.5
0.4
0.4
0.3
0.3
0.2
0.2
0.1
0.1
0
−3
−2.5
−2
Operate Time in [s]
−1.5
0
0.5996
−1
0.5996
−4
x 10
0.5997
0.5997
0.5998
Operate Time in [s]
0.5998
0.5999
Figure 5.18: Measured operate time for a setting of (a) instantaneous & (b) 600 ms
Distribution of accuracy of operate time
0.7
Set time delay: 3s
0.6
Probability
0.5
0.4
0.3
0.2
0.1
0
2.9996
2.9996
2.9997
2.9997 2.9998 2.9998
Operate Time in [s]
2.9999
2.9999
Figure 5.19: Measured operate time for a setting of 3 s
The worst-case deviation shown above is 400 µs. Comparing this result with the selected
ABB and Siemens relay shows that the results are very competitive with OEM solutions.
ABB claims an accuracy of ± 0.2 % of the delay time or ± 35 ms, depending which of them
is greater. The stated accuracy by ABB includes the measurement time and therefore is
not directly comparable to the recorded operate times above. Siemens states ± 1 % of the
delay time or ± 10 ms, depending which of them is greater.
5.3.4
Steady state errors of disengaging and reset time
This section analysis the accuracy of the disengaging and reset time. The disengaging
time is measured from fault clearance until pick-up signal disappears. On the other hand,
the reset time is defined as the duration from the disappearance of the pick-up signal until
the trip output releases (see section 3.2.1).
Disengaging time:
87
The figure 5.20 shows the disengaging time for di↵erent
IpostF ault
Iset
ratios. The disengaging
time decreases with an decrease of the given ratio. This phenomenon is caused by the fact
that only few sampled values of the post fault are need to obtain a RMS value below the
threshold.
Distribution of disengaging time for different (IpostFault/Iset) ratios
Ratio 0.8
Ratio 0.4
Ratio 0.2
Ratio 0.1
Ratio 0
0.5
Probability
0.4
0.3
0.2
0.1
0
0
0.005
0.01
0.015
0.02
Disengaging time in [s]
0.025
Figure 5.20: Distribution of disengaging time for di↵erent
0.03
IpostF ault
Iset
ratios
The worst-case disengaging time above is 30.1 ms. ABB states a disengaging time of
minimum 15 ms and maximum 30 ms. Siemens, on the other hand, claims to yield a
disengaging time of approximately 20 ms plus OOT. Thus the obtained results of the
developed protection function are in the same range as the results of the two big OEMs.
Reset time:
The distribution of the reset time is plotted in the figures 5.21 (a), (b) and 5.22. As
stated above, the reset time is measured from the disappearance of the pick-up signal
until the disappearance of the trip signal. Since this function mainly involves a timer
function, running at 1 ms, the results should be highly deterministic and mostly depending on the operating system behaviour. The figure show the accuracy of reset times for
the configurable values of 50 ms, 600 ms and 3 s.
88
Distribution of accuracy of reset time
Distribution of accuracy of reset time
0.8
0.5
Set time delay: 0.05s
Set time delay: 0.6s
0.45
0.7
0.4
0.6
0.35
Probability
Probability
0.5
0.4
0.3
0.25
0.2
0.3
0.15
0.2
0.1
0.1
0.05
0
0.0498
0.0498
0.0499
0.05
0.05
Rest Time in [s]
0.05
0.0501
0
0.5998
0.0502
0.5999
0.6
0.6001
Rest Time in [s]
Figure 5.21: Measured operate time for a setting of (a) 50 ms & (b) 600 ms
Distribution of accuracy of reset time
0.7
Set time delay: 3s
0.6
Probability
0.5
0.4
0.3
0.2
0.1
0
2.9999
2.9999
3
Reset Time in [s]
3
3.0001
Figure 5.22: Measured operate time for a setting of 3 s
The largest deviation from the expected value is 200 µs. Siemens claims to achieve an
accuracy of ± 1 % or ± 10 ms, similar to the claimed operate time. ABB does not state
the corresponding quantity. None the less, the obtained worst-case deviation of 200 µs is
a sufficient level of accuracy.
5.3.5
Transient overreach
The intention of the transient overreach test is to determine the impact of a dc o↵set on
the protection performance. The set value for the trip command Iset is set to 1 p.u. In
the first step the actual trip threshold is determined for a waveform without any dc o↵set.
This is done by applying a current of 0.9x Iset , which is constantly increased until the trip
occurs. This determined value is then reduced by 2% and is called test current IN Odc .
Then the test is conducted with the maximum d.c o↵set and three di↵erent time constants,
defined by the X/R ratio (10, 40, 120, see section 2.2.3). If the protection system operates,
then Iset is increased until no start signal occurs five times in a row. This set value is then
called IsetDC . The table 5.13 shows the results of the transient overreach test.
89
Iset
1.00
INOdc
0.98
X/R Ratio
10
40
120
IsetDC
1.1
1.03
1.02
Transient Overreach
12.24%
5.10%
4.08%
Table 5.13: Results of the transient overreach test acc. to IEC 60255-151
The worst-case transient overreach of the developed protection system is 12.24 %. Moreover the transient overreach decreases with an increase of the time constant. This due to
the fact that the protection function are based on the 50 Hz component and the signals,
60255-151 © IEC:2009
– 25 –
having a lower X/R ratio, have an higher ratio of the 50 Hz component. The measured
With
theistest
current
established,
tests shall
be performed
with solution
the maximum
value
rather
highmagnitude
in comparison
to the transient
overreach
of Siemens
of < 5d.c.
offset present and with a constant X/R ratio up to 120 (preferred test points are for X/R ratios
the less,
quantity
the Siemens
is measured
100
of %.
10,None
40 and
120).this
Typical
testof waveform
is relay
shown
in Figure at11time
for constant
a 50 Hzof nominal
frequency.
During
the
tests,
current
shall
be
stepped
from
0
A
to
the
test
current
magnitude
ms, which corresponds to a X/R ratio of 31.4 for a 50 Hz system.
with no intentional delay, and relay operation shall be monitored for at least the duration of
the time constant of the current waveform. If the element starts to operate, the test shall be
until application
of to
thethe
offset
waveform
re-performed
with a higher
for G S overreach
The IEC 60255-151
definessetting
the transient
according
equation
below.does
The not
cause relay starting. Five successive non-operations for a given setting value indicate that the
figure 5.23
depictsstability
the typical
transient
overreach
pointtest
haswaveform.
been reached.
The transient overreach at
X/R value is given by:
⇣ each
Setting at which no operation occurs for o↵set waveform
Transient overreach =
1
⎛
⎞
Setting
at which
no no
operation
without o↵set
Setting
at which
operationoccurs
occursfor
for waveform
offset waveform
Transient overreach (in %) = ⎜⎜
− 1⎟⎟ × 100
IsetDC
which no operation occurs for waveform without offset
N Odc
⎝ SettingIat
⎠
=
0
0,05
IsetDC
0,1
0,15
0,2
IEC
1715/09
Figure 5.23: Typical test waveform for transient overreach [2]
Figure 11 – Typical test waveform for transient overreach
6.5.3
Overshoot time
Overshoot time is relevant for overcurrent relay and it is not applicable for undercurrent relay.
90
With the relay setting at reference conditions (setting value of I n), current shall be switched
from an initial value of zero to 5 × G S and the relay operate time shall be measured as a
maximum value out of five attempts. With this known operating time, the same current of
5 × G S shall be applied for a period of time 5 ms less than the maximum operate time and
5.3.6
Overshoot time
The test for overshoot time is performed at a set trip value of 1 p.u. and a time delay
of 200 ms. Then a fault current of 2 p.u. is applied and the time from fault inception
to trip occurrence is measured. This is done five times in a row and the maximum time
measured is denoted as tmax . Then the injection period is decreased by 5 ms (tmax 5 ms).
If the protection system operates, then then the injection period is reduced by another
5 ms, until no trip occurs for five successive tries. This yield injection period, for which
no trip occurs, is denoted as tnoT RIP . The di↵erence in time between tmax and tnoT RIP
is described as the overshoot time. The overshoot time for the implemented protection
system is 6.4 ms, as seen in table 5.14 below.
top1
221 ms
top2
221.1 ms
top3
221.1 ms
top4
221.3 ms
top5
221.4 ms
tmax
221.4 ms
tnoTRIP
215 ms
overshoot time
6.4 ms
Table 5.14: Results of overshoot time test acc. to IEC 60255-151
ABB claims to obtain an overshoot time of 10 ms for the corresponding PDOC function
of the REL670 2.0 relay. Siemens does not state this quantity.
5.3.7
Accuracy of directional element
The accuracy of the directional element is not required in the IEC 60255-151, since this
standard only refers to overcurrent protection without directional sensing. The IEC 60255167 actually covers the directional current protection, but it has not been released yet.
Therefore the accuracy of the directional element has been tested according to in a similar
approach as the accuracy of the start value.
91
PDOC
PDEF
MTA
60
50
Upper limit
30
40
Lower limit
-150
-140
Initial value
-151
31
-141
41
Ramping steps
0.01
0.01
0.01
0.01
Step time
500 ms
500 ms
500 ms
500 ms
Measured angle 1
-150.46
30.05
-140.95
40.05
Measured angle 2
-149.99
30.05
-140.04
40.05
Measured angle 3
-150.00
30.05
-140.08
40.05
Measured angle 4
-150.16
30.13
-140.47
40.53
Measured angle 5
-150.47
30.29
-140.41
40.88
Absolute error 1
0.46
0.05
0.95
0.05
Absolute error 2
0.01
0.05
0.04
0.05
Absolute error 3
0.00
0.05
0.08
0.05
Absolute error 4
0.16
0.13
0.47
0.53
Absolute error 5
0.47
0.29
0.41
0.88
Average error
0.22
0.11
0.39
0.31
Maximum error
0.47
0.29
0.95
0.88
Table 5.15: Ramping test to determine the accuracy of the directional elements
From the table above shows that the maximum error of the angle measurement is roughly
±1 . Since the tested protection system does not involve any instrument transformers, this
value is likely to increases for the overall implementation. Therefore blinders should be
implemented for the upper and lower angle limit for future approaches. The ABB solution
states an accuracy of the angle of ± 2 and the Siemens solution claims an accuracy of ±
1 .
5.4
Evaluation of realtime performance
Above the functional performance test as well as the required type test has been performed.
This section comprises the evaluation of the realtime performance of the used operating
system. Due to practical reasons for longterm testing and the requirement to rebuild the
protection system at the facilities of the university, the test setup above has been changed.
Instead of using the OMICRON as signal generator to the EtherCAT slaves, a realtime
simulator (OPAL-RT OP5600) has been connected to the corresponding analog inputs and
digital outputs. Since the analog outputs of the OP5600 provide voltage measurements
in the range of ± 10 V and amplifiers has not been available during the project execution, the EtherCAT module EL3773 (current/voltage input) has been replaced with the
92
module EL3104 (voltage input ± 10 V). In addition the runtime environment has been
implemented on a di↵erent hardware (dual-core 2.4 GHz, 2048 MB memory). This change
of setup is seen as justifiable, since the evaluation of the realtime performance focuses on
the behaviour of the operating system.
Di↵erent setups of the runtime environment are analysed. Thus the influence of the
preempt-rt patch on the worst-case trip time is determined. The reduction of the worstcase trip time is the overall objective of the usage of a realtime system. There are four
di↵erent setups in total, which di↵er in terms of the used kernel (mainline vs. rt-kernel)
as well as in terms of the driver usage (native vs. generic). The following configuration is
applied for all four setups of the runtime environment.
• CPU affinity of threads are set to single core (taskset)
• Generic driver: NIC interrupts with same CPU affinity as threads
• All threads run with realtime priority 99 (chrt)
• All threads are scheduled with First-in-First-out scheduler policy (chrt)
• irqbalance is disabled
• Load on CPU is generated by the Linux program stress
The fault scenario runs 24 hours for each setup of the runtime environment. The fault
scenario itself consists of a single-phase forward fault and is applied every second, which
yields roughly 86400 (60x60x24) test points. The PDOC function is used as protection
function with a configured time delay of 100 ms. In order to evaluate the realtime performance of the protection system, the start time as well as the operate time (from start to
trip) are recorded for each test point.
5.4.1
Distribution of start time
The worst-case start time should not exceed 24 ms for a short-circuit fault. The thread,
comprising the signal processing element and protection function (PDOC), has task period
of 8 ms. Thus 24 ms is the smallest multiple of 8 ms, which is higher than the fundamental
period of the signal (20 ms - 50 Hz system). At this point in time the entire moving window of the signal processing element consists of samples of the fault current (see section
4.2.2).
The figures in table 5.16 show the distribution of the start time for each setup of the
runtime environment. The second table 5.17 shows the exact worst-case start time of the
roughly 86400 test points.
93
RT-kernel
Mainline
Mainline and Native driver
1
1
0.9
0.9
0.8
0.8
0.7
0.7
0.6
0.6
Probability
Probability
RT−preempt and Native driver
0.5
0.4
0.4
0.3
0.3
0.2
0.2
0.1
0
0
Native
0.5
0.1
0.005
0.01
0.015
Start time [s]
0.02
0
0
0.025
0.005
0.01
0.015
Start time [s]
0.02
0.025
driver
Mainline and Generic driver
1
0.9
0.9
0.8
0.8
0.7
0.7
0.6
0.6
Probability
Probability
RT−preempt and Generic driver
1
0.5
0.4
0.4
0.3
0.3
0.2
0.2
0.1
Generic
0.5
0
0
0.1
0.1
0.2
0.3
Start time [s]
0.4
0.5
0
0
0.02
0.04
0.06
0.08
Start time [s]
0.1
0.12
0.14
driver
Table 5.16: Distribution of start time for di↵erent setups of runtime environment
The dashed line in the above figures indicates the worst-case start time. It can be seen
that the native driver approach yields satisfactory results for the rt-kernel as well as for
the mainline kernel, since the start time is below 24 ms for all test points. None the less,
the worst-case start times are quite long in case of the generic driver. Those performance
di↵erences between the two drivers could be explained by the usage of direct memory
access in case of the native driver approach.
Native
driver
Generic
driver
RT-kernel
Mainline
tstr = 18.2 ms
tstr = 18.4 ms
tstr = 426.1 ms
tstr = 134.1 ms
Table 5.17: Worst-case start time for di↵erent setups of runtime environment
5.4.2
Distribution of operate time
In order to evaluate the realtime performance of the protection system, the worst-case
operate time is more applicable than the start time, since the counter functions run at
task period of 1 ms instead of 8 ms. Thus the resolution is higher. The figures in table
5.18 show the distribution of the operate time for the four di↵erent setups of the runtime environment. The second table 5.19 shows the exact worst-case operate time of the
94
roughly 86400 test points. It should be mentioned that the operate time is measured from
occurrence of start signal until the trip signal appears.
RT-kernel
Mainline
RT−preempt and Native driver
Mainline and Native driver
1
0.9
0.9
0.8
0.8
0.7
0.6
0.6
Probability
Probability
0.7
0.5
0.4
0.2
0.2
0.1
0.1
Native
0.4
0.3
0.3
0
0.0996
0.5
0.0998
0.1
0.1002
0.1004
Start time [s]
0.1006
0
0.095
0.1008
0.1
0.105
0.11
Start time [s]
0.115
0.12
0.125
0.1006
0.1008
driver
RT−preempt and Generic driver
Mainline and Generic driver
1
0.9
0.9
0.8
0.8
0.7
0.6
0.6
Probability
Probability
0.7
0.5
0.4
0.2
0.2
0.1
0.1
Generic
0.4
0.3
0.3
0
0.098
0.5
0.1
0.102
0.104
Start time [s]
0.106
0.108
0
0.0996
0.0998
0.1
0.1002
0.1004
Start time [s]
driver
Table 5.18: Distribution of operate time for di↵erent setups of runtime environment
The dashed line in the above figures indicates the worst-case operate time. The setup
of the runtime environment, based on the native driver and rt-kernel, yields satisfactory
results. The deviation from the expected value of 100 ms (configured time delay) is 100
µs, which is considered as appropriate for AC protection applications. This phenomena
is as expected, since the preempt-rt patch converts the standard kernel into a fully preemmptible kernel. Thus the threads, which are created by the program stress and are
not running with realtime priorities, are preempted by the RT-kernel and the protection
application is able to be executed.
The larger deviations from the expected value were expected in case of the mainline kernel. Nevertheless a deviation of 200 µs has been measured for the setup with the mainline
kernel and the generic driver. Combining the results from the subsections 5.4.1 and 5.4.2,
only the setup with the rt-kernel and the native driver yields stable results. The large
deviations for all other setups are very rare events (1 to 6 out of 86400). Therefore, an
in-depth study on the realtime operating system has to be performed in future in order to
find the root-cause for this odd behaviour above.
95
Note 1 to entry:
In the context of this standard the following terms for system voltage are used (see also 3.1.9):
–
low voltage (LV) refers to U n ≤ 1 kV;
–
medium voltage (MV) refers to 1 kV < U n ≤ 36 kV;
–
high voltage (HV) refers to voltage above 36 kV and includes EHV and UHV.
3.1.7
RT-kernel
Mainline
installation
several combined items ofNative
equipment (including cables) put together at a given place to fulfil a
ttr = 100.1 ms ttr = 124 ms
specific task
driver
Generic
3.1.8
ttr = 106.1 ms ttr = 100.2 ms
low voltage
driver
set of voltage levels used for the distribution of electricity and whose upper limit is generally
accepted to be 1 000 V a.c.
Table 5.19: Worst-case operate time for di↵erent setups of runtime environment
[SOURCE: IEC 60050-601:1985, 601-01-26]
5.5 Environmental compatibility of I/O modules
3.1.9
medium voltage
MVThis section compares the required electromagnetic compatibility in terms in immunity,
any set of voltage levels lying between low and high voltage
which is defined in section 3.2.2, with the given electromagnetic compatibility of the used
NoteEtherCAT
1 to entry:modules
The boundaries
between In
medium
and the
highIEC
voltage
levels overlap
and depend
on local
in this project.
addition
standards
for vibration
and shock
circumstances and history or common usage. Nevertheless the band 30 kV to 100 kV frequently contains the
accepted
boundary.
resistance,
which the I/O modules are compliant to, are stated. None the less this evalu-
is left In
for the
future
investigations.
Noteation
2 to entry:
context
of this standard, medium voltage is defined as the voltage range of
1 Kv < U n ≤ 36 kV.
[SOURCE:
EMC IEC 60050-601:1985, 601-01-28, modified – a note to entry 2 has been added.]
The required electromagnetic immunity for substation applications is given by IEC 61000-
3.1.10
port
6-5. Nevertheless the used EtherCAT modules in this project are only compliant to the
particular interface of the equipment which couples this equipment with, or is influenced by,
industrial standard 61000-6-2. Therefore this EMC evaluation is based on a comparison
the external electromagnetic environment
of those two standards. Both standards define test procedures in order to test the perNote 1 to entry: Examples of ports of interest are shown in Figure 1. The enclosure port is the physical boundary
formance
during
and after the
phenomena
stated
table 3.1.discharge
The tests
of the
equipment
(e.g. enclosure).
The electromagnetic
enclosure port provides
for radiated
and in
electrostatic
(ESD)
energy transfer, whereas the other ports provide for conducted energy transfer.
are carried out on a port-by-port basis. Therefore the corresponding standards define four
di↵erent ports for the equipment under test, as shown in figure 5.24.
AC power port
Enclosure port
Signal/control port
EQUIPMENT
DC power port
IEC
Figure 5.24: Ports of equipment under test [19]
Figure 1 – Equipment ports
The enclosure port, signal/control port and the AC and DC power ports are defined above.
The following three tables (5.20, 5.21, 5.22) compare the standard 61000-6-5 with 610006-2. The AC power port is not evaluated, since the EtherCAT modules are supplied by
direct current. In the first column of the tables the electromagnetic phenomena is stated.
The second and third column specifies the standard, which describes the performed test
For ABB use only . Publication provided under IEC subscription agreement 2013 - 2014. This file is copyright of IEC, Geneva, Switzerland. All rights reserved.
procedure, and states the magnitude of the test values, respectively. The fourth and
fifth column shows the performance criteria, which have to be fulfilled according to the
two respective standards. As stated in section 3.2.2, the performance criteria A has to
be satisfied for protection applications. The last column shows the compliancy of the
EtherCAT modules to the required substation environment.
96
Performance criteria
Environmental
Basic
Test
phenomena
standard
specifications
Power frequency
61000-4-8
100 A/m (cont.)
magnetic field
Radiated,
radio
61000-4-3
80 MHz to 1 GHz
10 V/m (rms)
electromag. field
80 % AM (1 kHz)
radio
61000-4-3
1 GHz to 2.7 GHz
frequency
3 V/m (rms)
electromag. field
80 % AM (1 kHz)
Radiated,
radio
61000-4-3
2.7 GHz - 6 GHz
frequency
1 V/m (rms)
electromag. field
80 % AM (1 kHz)
Electrostatic
61000-6-2
Comp.
A
-
-
A
A
yes
A
-
-
A
-
-
A
B
no
1 kA/m for 1 s
frequency
Radiated,
61000-6-5
61000-4-2
discharge
6 kV (contact)
8 kV (air)
Table 5.20: Comparison between IEC 61000-6-5 and IEC 61000-6-2 for enclosure port
At a first glance it can be seen that a lot of compliance statements are not made. This
is due to the reason that the industrial standard IEC 61000-6-2 requires that most of
the stated tests are performed with lower magnitudes of test values in comparison to the
substation standard IEC 61000-6-5. Therefore the author didn’t give any indication of
compliance.
In case that both standards require the performance criteria A for the same test with
the same test specifications, then the compliance is said to be true. None the less it can
be seen that this is only true for some radio frequency tests. The electrostatic discharge
test for the enclosure port shows that the same test specifications are applied in both
standards. Nevertheless the performance criteria, required by the industrial standard, is
B. That means that the equipment under test is allowed to maloperate during the test.
This is not compliant to the required performance criteria A for protection applications
in high-voltage substation environments.
In the end it is concluded that the used EtherCAT couplers and slaves are not compliant for the substation environment. None the less this project has only evaluated one
particular EtherCAT module of one vendor. Therefore the author suggest to perform an
extended market research for commercial-o↵-the-shelf and suitable EtherCAT modules as
part of future investigations.
97
Performance criteria
Environmental
Basic
Test
phenomena
standard
specifications
Fast transient
61000-4-4
4 kV
61000-6-5
61000-6-2
Comp.
A
-
-
A
-
-
A
-
-
A
A
yes
A
-
-
A
-
-
A
-
-
A
-
-
A
-
-
5 kHz or 100 kHz
Surge
61000-4-5
2 kV
1.2/50 µs
line to ground
1 kV
1.2/50 µs
line to line
Conducted
61000-4-6
150kHz to 80MHz
disturbances,
10 V (rms)
induced by radio-
80 %
frequency fields
AM (1 kHz)
Mains frequency
61000-4-16
voltage
Damped
30 V (cont.)
300 V for 1 s
61000-4-18
oscillatory wave
2.5 kV
common mode
1 MHz
1 kV
di↵erential mode
1 MHz
1 kV
di↵erential mode
10 MHz
Voltage dips &
61000-4-29
70 % UT , 0.1 s
voltage interrup-
40 % UT , 0.1 s
tions
0 % UT , 0.05 s
Table 5.21: Comparison between IEC 61000-6-5 and IEC 61000-6-2 for d.c. power ports
98
Performance criteria
Environmental
Basic
Test
phenomena
standard
specifications
Fast transient
61000-4-4
4 kV
61000-6-5
61000-6-2
Comp.
A
-
-
A
-
-
A
A
yes
A
-
-
A
-
-
A
-
-
5 kHz or 100 kHz
Surge
61000-4-5
2 kV
1.2/50 µs
line to ground
Conducted
61000-4-6
150kHz to 80MHz
disturbances,
10 V (rms)
induced by radio-
80 %
frequency fields
AM (1 kHz)
Mains frequency
61000-4-16
voltage
Damped
30 V (cont.)
300 V for 1 s
61000-4-18
oscillatory wave
2.5 kV
common mode
1 MHz
1 kV
di↵erential mode
1 MHz
Table 5.22: Comparison between IEC 61000-6-5 and IEC 61000-6-2 for signal ports
Vibration and shock resistance
The required vibration and shock resistance for protection systems are defined in IEC
60255-21. The used EtherCAT modules are compliant to 60068-2-6 (vibration) and 600682-27 (shock). Thus those standards have to be compare in future work, in order to give a
statement on those environmental requirements.
99
Chapter 6
Conclusion and Discussion
6.1
Conclusion
The project has shown the development of a directional definite-time overcurrent and
earth fault protection based on COTS components. The development process has been
conducted based on a model-based design approach. As part of the evaluation phase the
implemented functionality of the protection system has been attested and code generation
has been verified. Moreover the performed type test showed the compliance to the IEC
60255-151 standard. In addition the obtained type test results are compatible with the
standard IEDs of di↵erent OEMs. As part of a stability analysis, the realtime operating
system has been tested. Lastly, the environmental compatibility of the I/O modules has
been evaluated in terms of electromagnetic compatibility.
The developed protection system, based on COTS components, has been shown to be
compliant to the functional protection standard IEC 60255-151. None the less the environmental requirements in terms of EMC immunity could not be fulfilled. In addition the
stability of the realtime performance has not been satisfied. Therefore several suggestions
are made for prospective studies and implementations in the section below.
6.2
Future Work
At the beginning of the thesis a design choice has been made to locate only the I/O modules close to the process and to keep the standalone-PC, running the protection function,
in surroundings with less stringent environmental requirements. None the less, the environmental evaluation of the I/O modules has shown, that the chosen EtherCAT coupler
and slaves only fulfil the industrial standard, but not the power system standard in terms
of EMC immunity. In future either EtherCAT slaves with better EMC performance has
to be used or proper shielding has to be provided by other means. In addition, an analog
input with higher current capabilities (100 A RMS) has to be selected in order to resist
the high secondary short-circuit currents.
100
Lastly, the evaluation of the realtime performance has not been satisfied, as shown during
the longterm test in section 5.4. Thus the author suggests an in-depth analysis of the
realtime behaviour of the operating system.
101
Bibliography
[1] IEC-60909-0 Short-circuit currents in three-phase a.c. systems - Calculation of currents. IEC, 2001.
[2] IEC 60255-151 Measuring relays and protection equipment - Functional requirements
for over/under current protection. IEC, 2009.
[3] EtherCAT Technology Introduction Presentation. EtherCAT - Technology Group,
2012.
[4] Etherlab. Technical report, Ingenieurgemeinschaft IgH, 2013.
[5] Line distance protection rel670 2.0 iec - technical manual. Technical report, ABB,
2014.
[6] Siprotec 5 overcurrent protection 7sj82/7sj85. Technical report, Siemens AG, 2014.
[7] P.M. Anderson. Power System Protection. IEEE Press, Wiley-Interscience, 1999.
[8] Nima Asadi. Enhancing the monitoring of real-time performance in linux. Master’s
thesis, Mälardalen University Sweden, 2013.
[9] Beckho↵, June 2015.
[10] Je↵ Mazereeuw Bogdan Kasztenny, Bruce Campbell. Phase selection for single-pole
tripping: Weak infeed conditions and cross-country faults. Technical report, General
Electric, 2000.
[11] J David Irwin Bogdan M., Vilamowski. Industrial Communication Systems. CRC
Press, 2011.
[12] M. Cereia, I.C. Bertolotti, and S. Scanzio. Performance of a real-time ethercat master
under linux. Industrial Informatics, IEEE Transactions on, 7(4):679–687, Nov 2011.
[13] D. Cotroneo, R. Natella, R. Pietrantuono, and S. Russo. Software aging analysis of
the linux operating system. In Software Reliability Engineering (ISSRE), 2010 IEEE
21st International Symposium on, pages 71–80, Nov 2010.
102
[14] Working Group D-3. Considerations in choosing directional polarizing methods for
ground overcurrent elements in line protection applications. Technical report, IEEE,
2014.
[15] Normann Fischer David Dolezilek and Robert Schloss. Improvements in synchronous
wide-area data acquisition design and deployment for telecontrol and teleprotection.
Technical report, Schweitzer Engineering Laboratories, Inc., 2012.
[16] Pascal Schaub Gerard Ledwich David M. E. Ingram, Duncan A. Campbell. Test and
evaluation system for multi-protocol sampled value protection schemes. Technical
report, IEEE, 2011.
[17] José Carlos Molina Fraticelli. Simulink code generation - tutorial for generating c code
from simulink models using simulink coder. Technical report, NASA MARSHALL
SPACE FLIGHT CENTER, 2012.
[18] Shaofeng Huang, Lan Luo, and Kai Cao. A novel method of ground fault phase
selection in weak-infeed side. Power Delivery, IEEE Transactions on, 29(5):2215–
2222, Oct 2014.
[19] IEC. Iec-61000-6-5. Technical report, IEC, 2000.
[20] IEC61850. Communication networks and systems for power utility automation. Technical report, IEC, 2013.
[21] IEC61850-9-2LE. Implementationguidelinefordigital interface to instrument transformers using iec 61850- 9-2. Technical report, UCA International Users Group.
[22] Gabriele Manduchi Ivan Cibrario Bertolotti. Real-Time Embedded Systems: OpenSource Operating Systems Perspective. CRC Press, 2012.
[23] Thomas J. Domin J. Lewis Blackburn. Protective Relaying - Principles and Applications. CRC Press, third edition edition, 2006.
[24] Francisco J. Garcia Robert C. Atkinson Jakub W. Konka, Colin M. Arthur. Traffic
generation of iec 61850 sampled values. IEEE.
[25] Li Jie, Guo Ruifeng, and Shao Zhixiang. The research of scheduling algorithms
in real-time system. In Computer and Communication Technologies in Agriculture
Engineering (CCTAE), 2010 International Conference On, volume 1, pages 333–336,
June 2010.
[26] Edward J. Holmes Juan M. Gers. Protection of Electricity Distribution Networks.
The Institution of Engineering and Technology, 3rd edition, 2011.
[27] F. Jullien. Cahier technique - The IT earthing system in (unearthed neutral) LV.
Schenider Electric, 1999.
103
[28] Hakola T Lehtonen, M. Neutral earthing and power system protection. ABB Transmit
Oy, 1996.
[29] M. Lewandowski, M.J. Stanovich, T.P. Baker, K. Gopalan, and A.-I.A. Wang. Modeling device driver e↵ects in real-time schedulability analysis: Study of a network
driver. In Real Time and Embedded Technology and Applications Symposium, 2007.
RTAS ’07. 13th IEEE, pages 57–68, April 2007.
[30] Joy Lin. Measuring return on investment of model-based design. Technical report,
Mathworks.
[31] Robert Love. Linux Kernel Development. Developer’s Library, 3rd edition, 2010.
[32] Muhammad Shoaib Almas Luigi Vanfretti. Performance evaluation of protection
functions for iec 61850-9-2 process bus using real-time hardware-in-the-loop simulation approach. Technical report, CIRED, 2013.
[33] Franke Petrini Xenidis Meneghin, Pasetto. Performance evaluation of inter-thread
communication mechanisms on multicore/multithreaded architectures. Technical report, IBM Research Lab.
[34] Christian Guß Michael Hopfenzitz. Improve complexity management with modelbased design in v-modell. In Polarion User-Conference, 2013.
[35] Tarlochan S. Sidhu Mitalkumar G. Kanabar. Performance of iec 61850-9-2 process
bus and corrective measure for digital relaying. Technical report, IEEE, 2011.
[36] Maaz Mashood Mohiuddin. Design of a reliable controller for smart grids, 2015.
[37] D. Orfanus, R. Indergaard, G. Prytz, and T. Wien. Ethercat-based platform for
distributed control in high-performance industrial applications. In Emerging Technologies Factory Automation (ETFA), 2013 IEEE 18th Conference on, pages 1–8,
Sept 2013.
[38] Eduardo Tovar Paulo Baltarejo Sousa, Nuno Pereira. Enhancing the real-time capabilities of the linux kernel. Technical report, ISEP, 2012.
[39] Florian Pose. IgH - Master 1.5.2 Documentation. Ingenieurgemeinschaft IgH, 2013.
[40] G. Prytz. A performance analysis of ethercat and profinet irt. In Emerging Technologies and Factory Automation, 2008. ETFA 2008. IEEE International Conference on,
pages 408–415, Sept 2008.
[41] Szafran Janusz Wiszniewski Andrze Rebizant, Waldemar. Digital Signal Processing
in Power System Protection and Control. Spronger-Verlag London, 1 edition, 2011.
104
[42] Volker Gruhn Sami Beydeda. Testing Commercial-o↵-the-Shelf Components and Systems. Springer, 2005.
[43] Jürgen Schlabbach. Short-Circuit Currents. The Institute of Engineering and Technology, London, 2005.
[44] John Stankovic. Misconceptions about real-time computing: A serious problem for
next generation systems. IEEE Computer, 1988.
[45] R. Dömer W. Ecker, W. Müller. Hardware-dependent Software: Principles and Practice. Springer, 2009.
[46] K. Zimmerman and D. Costello. Fundamentals and improvements for directional
relays. In Protective Relay Engineers, 2010 63rd Annual Conference for, pages 1–12,
March 2010.
105
Appendix
Setting up the runtime environment
This section gives a guideline on how to setup the runtime environment for the protection
system. The Ubuntu 12.04.5 LTS (Long Term Support) is picked as distribution, which
comes with the kernel version 3.13. Therefore the following steps are undertaken to setup
the kernel versions 3.4.41-generic and 3.4.41-rt55-feat3. Furthermore the required steps
to install the EtherCAT master and the required libraries are mentioned. The guideline
is mainly based on the IgH EtherCAT documentation([39]) and the ”LinuxTricksNTips”
website of Autonomous System Lab of the Technical University of Darmstadt.
# apt-get upgrade
# apt-get update
# apt-get install kernel-package fakeroot build-essential libncurses5-dev
Get the kernel source from http://kernel.org/. The main vanilla kernel 3.4.41 is needed as
well as the rt-patch patch-3.4.41-rt55 and patch-3.4.41-rt55-feat3. The patches are found
under http://www.kernel.org/pub/linux/kernel/projects/rt/. Once downloaded, unzip all
packages.
$ cd linux-3.4.41 // Ignore next two commands, if rt-preempt not needed
$ patch -p1 < ../patch-3.4.41-rt55.patch
$ patch -p1 < ../patch-3.4.41-rt55-feat3.patch
$ cp /boot/config-$(uname -r) .config // Copy current config file
$ make oldconfig // Optional
$ make menuconfig // Note section 4.3.1
$ make-kpkg clean
$ CONCURRENCY LEVEL=$(getconf NPROCESSORS ONLN) fakeroot make-kpkg --initrd
--revision=0 kernel image kernel headers // Creates kernel binaries and headers
# cd ..
&& sudo dpkg -install linux-image* linux-headers*
# reboot // Choose the RT-kernel in the bootloader (e.g GRUB)
# rm /lib/modules/8 uname -r8 /build //Symbolic link points still to old headers/source
106
# ln -s /usr/src/linux-headers-8 uname -r8 /lib/modules/8 uname -r8 /build
Now the real-time kernel is up and running. Since the realtime application is linked against
the EtherCAT master library and the PdServ library, those libraries have to be installed.
The PdServ library has the following dependencies: Log4plus Library, CommonCpp2 Library, YAML library.
# apt-get upgrade
# apt-get update
# apt-get install build-essential kernel-package libncurses5-dev bzip2 hfsprogs
fakeroot ia32-libs cmake dh-autoreconf vim udev mercurial git python htop hwloc
sysstat ethtool
# apt-repository ppa:ubuntu-toolchain-r/test
# apt-get update
# apt-get install gcc-4.7 g++-4.7
# rm /usr/bin/gcc && rm /usr/bin/g++ // Current link refers to version 4.6
# ln -s /usr/bin/gcc-4.7 /usr/bin/gcc
# ln -s /usr/bin/g++-4.7 /usr/bin/g++
# apt-get install liblog4cplus-dev libccgnu2-1.7-0 libcommoncpp2-dev libyaml-dev
Download the EtherCAT master and the PdServ library from etherlab.org and unpack
them. There should be folder called ”pdserv-1.1.0” and ”ethercat-1.5.2”. The following
commands are executed starting from the same level as the named folders.
$ mkdir pdserv-1.1.0-build
$ cd pdserv-1.1.0-build
$ cmake -DCMAKE INSTALL PREFIX=/vol/opt/etherlab ../pdserv-1.1.0
$ make
$ make install // Make sure the folder etherlab has user rights
$ cd ..
&& cd ethercat-1.5.2
$ ./configure --enable-generic=yes --enable-8139too=no --enable-e1000e=yes
--prefix=/vol/opt/etherlab --with-linux-dir=/usr/src/linux-headers-$(uname -r)
--enable-cycles=yes --enable-debug-if=yes --enable-debug-ring=yes
// See section 4.3.2
$ make
$ make modules
# make install
# make modules install
# depmod
# ln -s /vol/opt/etherlab/etc/init.d/ethercat /etc/init.d/ethercat
107
# cp /vol/opt/etherlab/etc/sysconfig/ethercat /etc/sysconfig/ethercat
# nano /etc/sysconfig/ethercat
Minimal configuration (see section 4.3.2 for more details):
MASTER DEVICE=<MAC-ADDRESS of used ethernet device>
DEVICE MODULES="generic", or native driver (e.g. e1000e)
# touch /etc/udev/rules.d/99-EtherCAT.rules
# nano /etc/udev/rules.d/99-EtherCAT.rules
Paste in the following lines for automatic device node generation with user read-access
KERNEL=="EtherCAT[0-9]*", MODE="0664"
Setting up the development environment
The development environment can be either setup on the target system as well or on a
separated platform. This environment consists mainly of the EtherLAB library as well as
the Matlab/Simulink software. At this point Matlab and Simulink Coder is assumed to
be already installed. Moreover a linux operating system used for the development environment. This guideline describes the installation process of the EtherLAB library, which
is developed by [4].
All EtherLAB components are installed under /vol/opt/etherlab. Therefore the corresponding directory is created and user rights are assigned to.
# mkdir -p /vol/opt/etherlab
# chown :username /vol/opt/etherlab
# chmod 775 /vol/opt/etherlab
$ mkdir /vol/opt/etherlab/src
The C compile GCC and the builsystem cmake has to be installed on the development
system. Matlab 2014b is used for this project, which uses the gcc version 4.7. In addition the source for the EtherLAB library is obtained from etherlab.org and extracted to
/vol/opt/etherlab/src. The name of the folder is etherlab-2.1.0.
# apt-get install gcc-4.7 cmake
Check, if gcc version 4.7 is linked correctly
$ gcc -version
If another gcc version is shown, create new symbolic link
# rm /usr/bin/gcc
108
# ln -s /usr/bin/gcc-4.7 /usr/bin/gcc
Now, EtherLAB library is installed
$ cd /vol/opt/etherlab/src
$ mkdir etherlab-2.1.0-build
$ cd etherlab-2.1.0-build
$ cmake -DPREFIX=/vol/opt/etherlab ../etherlab-2.1.0
$ make
$ make install
If a Matlab version later than 2012b is used, then the c-file ec slave3.c under
/vol/opt/etherlab/rtw/blocks/EtherCAT has to be updated. The updated c-file is obtained from www.symbitron.eu
$ cd /vol/opt/etherlab/rtw/blocks/EtherCAT
$ wget http://symbitron.eu/wiki/images/b/b6/Ecslave.c
$ mv ec slave3.c ec slave3.c.bak
$ mv Ecslave.c ec slave3.c
The EtherLAB library is installed under /vol/opt/etherlab/rtw. In order to setup
EtherLAB within Matlab, the pathdef.m file has to be writable for users.
# chown :username $MATLABDIR/toolbox/local/pathdef.m
# chmod 775 $MATLABDIR/toolbox/local/pathdef.m
Open Matlab and execute the following commands in the command window in order to
setup EtherLAB
# cd /vol/opt/etherlab/rtw
# setup etherlab
Simulink Code Generation - Recommendations
As part of this thesis the automatic code generation of Simulink has been used. In order
to obtain efficient and optimised C code, there are certain steps and rules, which should
be applied, while designing the protection algorithm. The recommendations are mainly
based on [17].
Design stage:
• Use bus creator instead of mux. Bus creator are coded as c structures and therefore
makes the debugging process much easier
• Use unique names for busses
109
• Define the variables types. Simulink uses 64-bit double as the default data type,
which may be a bit oversized for some variables
• In case of implemented MATLAB functions, add %#codegen at the beginning of the
function in order indicate the code generation purpose to Simulink
Code generation:
• Use discrete step solver
• Code interface: Use classic call interface
• Each time step in Simulink is represented by di↵erent period of task
Description of developed Graphical User Interface
As seen from above, there are many di↵erent parameters, which have to be tune accordingly, in order to guarantee a reliable and secure operation of the protection system.
Therefore a graphical user interface (GUI) has been developed in order to provide a convenient approach of setting up the protection system.
Main window
110
Window for System configurations
Window for PDOC configurations
111
Window for phase selector configurations
Window for EtherCAT configurations
112
Datasheets of EtherCAT coupler - EK1100
EtherCAT
EK1100
Power LEDs
Link/Act In
E-bus
Signal input EtherCAT
Coupler
supply
Link/Act Out
Signal output EtherCAT
Input for
power contacts
Power contacts
EK1100 | EtherCAT Coupler
The EK1100 coupler connects EtherCAT with the EtherCAT Terminals (ELxxxx). One station consists of an EK1100 coupler, any number of EtherCAT
Terminals and a bus end terminal. The coupler converts the passing telegrams from Ethernet 100BASE-TX to E-bus signal representation.
The coupler is connected to the network via the upper Ethernet interface. The lower RJ45 socket may be used to connect further EtherCAT devices in the
same strand. In the EtherCAT network, the EK1100 coupler can be installed anywhere in the Ethernet signal transfer section (100BASE-TX) – except
directly at the switch. The coupler BK9000 (for K-bus components) is suitable for installation at the switch.
Technical data
EK1100
Task within EtherCAT system
coupling of EtherCAT Terminals (ELxxxx) to 100BASE-TX EtherCAT networks
Data transfer medium
Ethernet/EtherCAT cable (min. CAT 5), shielded
Distance between stations
max. 100 m (100BASE-TX)
Number of EtherCAT Terminals
up to 65,534
Protocol
EtherCAT
Delay
approx. 1 µs
Data transfer rates
100 Mbaud
Configuration
not required
Bus interface
2 x RJ45
Power supply
24 V DC (-15 %/+20 %)
Current consumption from US
70 mA + (Â E-bus current/4)
Current consumption from UP
load
Current supply E-bus
2000 mA
Power contacts
24 V DC max./10 A max.
Electrical isolation
500 V (power contact/supply voltage/Ethernet)
Operating/storage temperature
-25…+60 °C/-40…+85 °C
Relative humidity
95 %, no condensation
Vibration/shock resistance
conforms to EN 60068-2-6/EN 60068-2-27
EMC immunity/emission
conforms to EN 61000-6-2/EN 61000-6-4
Protect. class/installation pos.
IP 20/variable
Approvals
CE, UL, Ex
Accessories
Cordsets
cordsets and connectors
System
EtherCAT
For further EtherCAT products please see the system overview
BECKHOFF New Automation Technology
We reserve the right to make technical changes.
113
Datasheets of EtherCAT slave - EL1034
Digital Input
EL1034
Signal LED1
Signal LED2
Signal LED3
Signal LED4
Input 1
Input 2
GND1
Power contact
+24 V
GND2
GND3
Power contact 0 V
GND4
Input 3
Input 4
Top view
Contact assembly
EL1034 | 4-channel digital input terminal 24 V DC,
potential-free inputs
The EL1034 digital input terminal acquires the binary 24 V control signals and transmits them, in an electrically isolated form, to the higher-level
automation system. The EtherCAT Terminal contains four channels that indicate their signal state by means of light emitting diodes. The EL1034 features
electrical isolation of individual channels. The input signal meets the requirements of EN 61131-2, type 1.
Technical data
EL1034 | ES1034
Connection technology
2-wire
Specification
EN 61131-2, type 1
Number of inputs
4
Nominal voltage
24 V DC (-15 %/+20 %)
“0“ signal voltage
-3…+5 V (EN 61131-2, type 1)
“1“ signal voltage
15…30 V (EN 61131-2, type 1)
Input current
typ. 3 mA (EN 61131-2, type 1)
Input filter
typ. 10 µs
Distributed clocks
–
Current consumption power
contacts
–
Current consumption E-bus
typ. 90 mA
Electrical isolation
500 V (E-bus/field potential)
Bit width in the process image
4 inputs
Configuration
no address or configuration setting
Special features
4 electrically isolated fast inputs, potential-free
Weight
approx. 50 g
Operating/storage temperature
0…+55 °C/-25…+85 °C
Relative humidity
95 %, no condensation
Vibration/shock resistance
conforms to EN 60068-2-6/EN 60068-2-27
EMC immunity/emission
conforms to EN 61000-6-2/EN 61000-6-4
Protect. class/installation pos.
IP 20/variable
Pluggable wiring
for all ESxxxx terminals
Approvals
CE, UL, Ex
BECKHOFF New Automation Technology
We reserve the right to make technical changes.
114
Datasheets of EtherCAT slave - EL3773
Analog input
EL3773
Run LED
L1 error
L2 error
L3 error
Meas. error
IL1 error
IL2 error
IL3 error
L1
IL1
L2
IL2
L3
IL3
N
IN
Top view
Contact assembly
EL3773 | Power monitoring oversampling terminal
The EtherCAT Terminal EL3773 is a power monitoring terminal for state monitoring of a 3-phase AC voltage system. For each phase
voltages up to 288 Veff/410 V DC and currents up to 1 Aeff/1.5 A DC are sampled as instantaneous values with a resolution of
16 bits. The six channels are measured simultaneously based on the EtherCAT oversampling principle with a temporal resolution of
up to 100 µs and passed on to the control system. The control system has sufficient computing power for true RMS or performance
calculation and complex custom algorithms based on the measured voltages and currents. Through the oversampling principle the
terminal is able to measure at significantly shorter intervals than the cycle time of the control system. AC and DC parameters must
be connected and measured with a common reference potential. The EL3773 supports distributed clocks and can therefore measure
synchronous with other EtherCAT devices.
Technical data
EL3773
Number of inputs
3 x current, 3 x voltage
Technology
3-phase power monitoring for alternating/direct voltages
Oversampling factor
n = 1…100 selectable
Distributed clocks
yes
Conversion time
min. 100 µs, all channels simultaneously
Measured values
current, voltage as instantaneous values (oversampling)
Measuring voltage
max. 500 V AC 3~ (ULX-N: max. 288 V AC), max. 410 V DC
Measuring current
max. 1 A (AC)/1.5 A (DC), via measuring transformers x A AC/1 A AC
Resolution
16 bit (incl. sign)
Measuring error
0.5 % relative to full scale value
Electrical isolation
2,500 V
Current consumption power
contacts
–
Current consumption E-bus
typ. 215 mA
Special features
oversampling, AC/DC measurement, single-phase operation also possible, adjustable hardware filters
Weight
approx. 75 g
Operating/storage temperature
0…+55 °C/-25…+85 °C
Relative humidity
95 %, no condensation
Vibration/shock resistance
conforms to EN 60068-2-6/EN 60068-2-27
EMC immunity/emission
conforms to EN 61000-6-2/EN 61000-6-4
Protect. class/installation pos.
IP 20/variable
BECKHOFF New Automation Technology
We reserve the right to make technical changes.
115
Datasheets of EtherCAT slave - EL2624
Digital Output
EL2624
Signal LED1
Signal LED2
Signal LED3
Signal LED4
13
23
14
Power contact
24
33
Power contact
43
34
44
Top view
Contact assembly
EL2624 | 4-channel relay output terminal 125 V AC/30 V
DC
The EL2624 output terminal has four relays each of which has a single contact. The relay contact is suitable for use at up to 125 V AC or 30 V DC. The
EtherCAT Terminal indicates its signal state by means of light emitting diodes. The EL2624 has potential-free contacts. The power contacts are looped
through.
Technical data
EL2624 | ES2624
Connection technology
relay output
Number of outputs
4 x make contacts
Rated load voltage
125 V AC/30 V DC
Load type
ohmic
Distributed clocks
–
Ohmic switching current
0.5 A AC/2 A DC
Inductive switching current
no data
Minimum permitted load
10 µA at 10 mV DC with intact contact coating
Current consumption E-bus
typ. 200 mA
Electrical isolation
500 V (E-bus/field potential)
Current consumption power
contacts
–
Bit width in the process image
4 outputs
Operating cycles mech. (min.)
1 x 108
Operating cycles electr. (min.)
2 x 105 (1 A/30 V DC)
Configuration
no address or configuration setting
Weight
approx. 50 g
Operating/storage temperature
0…+55 °C/-25…+85 °C
Relative humidity
95 %, no condensation
Vibration/shock resistance
conforms to EN 60068-2-6/EN 60068-2-27
EMC immunity/emission
conforms to EN 61000-6-2/EN 61000-6-4
Protect. class/installation pos.
IP 20/variable
Pluggable wiring
for all ESxxxx terminals
Approvals
CE
BECKHOFF New Automation Technology
We reserve the right to make technical changes.
116
Datasheets of EtherCAT slave - EL2798
Digital output
EL2798
Signal LEDs
1…8
Output 1
Output 1&apos;
Output 2
Output 2&apos;
Output 3
Output 3&apos;
Power contact
+24 V
Output 4
Output 4'
Output 5
Output 5'
Power contact 0 V
Output 6
Output 6'
Output 7
Output 7'
Output 8
Output 8'
Top view
Contact assembly
EL2798 | 8-channel digital output terminal 30 V AC/DC,
2 A, solid state
The digital EL2798 EtherCAT Terminal provides eight switches that can be used like a relay contact for AC/DC voltages. The electronic switch is realised
through high-performance MOSFET transistors with low switch-on resistance. The switch itself is not short-circuit-proof, but due to its high pulse current
capability it can cope with current until an external fuse triggers a switch-off. Wear resistance increases the availability of the application. Resistive and
light inductive loads can be switched up to a rated voltage of 30 V AC/DC, completely resistive loads also up to a rated voltage of 48 V DC. High peak
voltages and electromagnetic interference pulses are prevented.
Technical data
EL2798
Connection technology
2-wire
Number of outputs
8 x make contacts
Rated load voltage
0…30 V AC/DC (only ohmic load: 0…48 V DC)
Distributed clocks
–
Short circuit current
not short-circuit-proof, see peak current
Reverse voltage protection
–
Switching times
TON: typ. 1.8 ms, TOFF: typ. 30 ms
Output current
2 A (Â 10 A @ 55° C, see documentation)
Breakdown voltage
80 V
Peak current
5 A (100 ms), < 50 A (10 ms)
Isolation voltage
(channel/channel)
< 200 V
Current consumption E-bus
typ. 140 mA
Electrical isolation
500 V (E-bus/field potential)
Switching on speed
typ. 1.8 ms, max. 5 ms
Switching off speed
typ. 30 ms, max. 50 ms
On-resistance
typ. 0.03 Ω
Conductor types
solid wire, stranded wire and ferrule
Conductor connection
solid wire conductors: direct plug-in technique; stranded wire conductors and ferrules: spring actuation by screwdriver
Rated cross-section
solid wire: 0.08…1.5 mm²; stranded wire: 0.25…1.5 mm²; ferrule: 0.14…0.75 mm²
Special features
substitute for relay contacts; potential-free
Operating/storage temperature
0…+55 °C/-25…+85 °C
Relative humidity
95 %, no condensation
Vibration/shock resistance
conforms to EN 60068-2-6/EN 60068-2-27
EMC immunity/emission
conforms to EN 61000-6-2/EN 61000-6-4
Protect. class/installation pos.
IP 20/variable
Related products
KL2798
8-channel digital output terminal, 30 V AC/DC, solid-state relay
BECKHOFF New Automation Technology
We reserve the right to make technical changes.
117
TRITA TRITA-EE 2015:101
ISSN 1653-5146
www.kth.se