Verifying RMS Deployment

Verifying RMS Deployment
Verifying RMS Deployment
Verify if all the RMS Virtual hosts have the required network connectivity.
• Verifying Network Connectivity, page 1
• Verifying Network Listeners, page 2
• Log Verification, page 3
• End-to-End Testing, page 4
Verifying Network Connectivity
Procedure
Step 1
Verify if the RMS Virtual host has network connectivity from the Central Node, using the following steps:
a) Ping the gateway. (prop:vami.gateway.Central-Node or prop:Central_Node_Gateway).
b) Ping the DNS servers. (prop:vami.DNS.Central-Node or prop:Central_Node_Dns1_Address &
prop:Central_Node_Dns2_Address).
c) Ping the NTP servers. (prop:Ntp1_Address, prop:Ntp2_Address, prop:Ntp3_Address & prop:Ntp4_Address).
Step 2
Verify if the RMS Virtual host has network connectivity from the Serving Node, using the following steps:
a) Ping the gateway. (prop:vami.gateway.Serving-Node or prop:Serving_Node_Gateway).
b) Ping the DNS servers. (prop:vami.DNS.Serving-Node or prop:Serving_Node_Dns1_Address &
prop:Serving_Node_Dns2_Address).
c) Ping the NTP servers. (prop:Ntp1_Address, prop:Ntp2_Address, prop:Ntp3_Address & prop:Ntp4_Address).
Step 3
Verify if the RMS Virtual host has network connectivity from the Upload Node, using the following steps:
a) Ping the gateway. (prop:vami.gateway.Upload-Node or prop:Upload_Node_Gateway).
b) Ping the DNS servers. (prop:vami.DNS.Upload-Node or prop:Upload_Node_Dns1_Address &
prop:Upload_Node_Dns2_Address).
c) Ping the NTP servers. (prop:Ntp1_Address, prop:Ntp2_Address, prop:Ntp3_Address & prop:Ntp4_Address).
Step 4
Perform the additional network connectivity testing on each of the nodes, for the following optional services:
a) Ping the Syslog servers (Optional).
b) Ping the SNMP servers (Optional).
RAN Management System Installation Guide, Release 4.0
February 9, 2015
1
Verifying RMS Deployment
Verifying Network Listeners
c) Ping the SNMP trap servers (Optional).
d) Ping the LDAP servers (Optional).
e) Ping the TACACS servers (Optional).
Verifying Network Listeners
Verify that the RMS virtual hosts have opened the required network listeners. If the Upload Server process
is not up, for more details seeUpload Server is Not Up.
RMS Node
Component
Central Node
BAC RDU
Network Listener
• netstat -an | grep 443
• netstat -an | grep 8005
• netstat -an | grep 8083
• netstat -an | grep 49187
• netstat -an | grep 8090
Serving Node
Cisco Prime Access Registrar
(PAR)
• netstat -an | grep 1812
• netstat -an | grep 8443
• netstat -an | grep 8005
Cisco Prime Network Registrar
(PNR)
• netstat -an | grep 61610
• netstat -an | grep 9005
BAC DPE
• netstat -an | grep 2323
• netstat -an | grep 49186
Upload Node
Upload Server
• netstat -an |grep 8080
• netstat -an |grep 8082
• netstat -an |grep 443
RAN Management System Installation Guide, Release 4.0
2
February 9, 2015
Verifying RMS Deployment
Log Verification
Log Verification
Server Log Verification
Post installation, the following server logs should be checked for verification of clean server start-up.
• Central Virtual Machine (VM):
◦/rms/data/CSCObac/agent/logs/snmpAgent_console.log
◦/rms/data/CSCObac/agent/logs/tomcat_console.log
◦/rms/data/dcc_ui/postgres/dbbase/pgstartup.log
◦/rms/log/pmg/PMGServer.console.log
◦/rms/data/nwreg2/regional/logs/install_cnr_log
◦/rms/log/dcc_ui/ui-debug.lo
• Serving VM: /rms/data/nwreg2/local/logs/install_cnr_log
Note
Any errors in the above log files at the time of application deployment need to be notified to the operation
support team.
Application Log Verification
Application level logs can be referred to in case of facing application-level usage issues:
RMS Node
Component
Log Name
Central VM
DCC_UI
/rms/log/dcc_ui/ui-audit.log
/rms/log/dcc_ui/ui-debug.log
PMG
/rms/log/pmg/pmg-debug.log
/rms/log/pmg/pmg-audit.log
BAC/RDU
/rms/data/CSCObac/rdu/logs/audit.log
/rms/data/CSCObac/rdu/logs/rdu.log
Serving VM
PNR
/rms/data/nwreg2/local/logs/
name_dhcp_1_log
RAN Management System Installation Guide, Release 4.0
February 9, 2015
3
Verifying RMS Deployment
End-to-End Testing
PAR
/rms/app/CSCOar/logs/
name_radius_1_log
Or
/rms/app/CSCOar/logs/name_radius_1_trace
DPE
Upload Server VM
/rms/data/CSCObac/dpe/logs/dpe.log
/opt/CSCOuls/logs/*.log (uls.log,
sb-events.log, nb-events.log)
End-to-End Testing
Perform the following processes for end-to-end testing of the Small Cell device:
Procedure
Step 1
Step 2
Step 3
Step 4
Step 5
Step 6
Step 7
Step 8
Step 9
Step 10
Step 11
Step 12
Step 13
Step 14
Step 15
Step 16
Step 17
Step 18
Step 19
Register a Small Cell Device.
Power on the Small Cell Device.
Verify NTP Signal.
Verify TR-069 Inform.
Verify Discovered Parameters.
Verify Class of Service selection.
Perform Firmware Upgrade.
Verify Updated Discovered Parameters.
Verify Configuration Synchronization.
Activate the Small Cell Device.
Verify IPSec Connection.
Verify Connection Request.
Verify Live Data Retrieval.
Verify HNB-GW Connection.
Verify Radio is Activated.
Verify User Equipment can Camp.
Place First Call.
Verify Remote Reboot.
Verify On-Demand Log Upload.
RAN Management System Installation Guide, Release 4.0
4
February 9, 2015
Verifying RMS Deployment
Updating VMware Repository
Updating VMware Repository
All the system updates for the VMware Studio and the VMware vCenter are stored on the Update Repository,
and can be accessed either online through Cisco DMZ or Offline (delivered to the Customer through Services
team or DVD).
Perform the following procedures to apply updates on the RMS nodes:
Procedure
Step 1
Step 2
Step 3
Step 4
Disable the network interfaces for each virtual machine.
Create a snapshot of each virtual machine.
Mount the Update ISO on the vCenter server.
Perform a check for new software availability.
Step 5
Step 6
Step 7
Step 8
Install updates using the vSphere Console.
Perform system tests to verify that the updated software features are operating properly.
Enable network interfaces for each virtual machine in the appliance.
Perform end-to-end testing.
RAN Management System Installation Guide, Release 4.0
February 9, 2015
5
Verifying RMS Deployment
Updating VMware Repository
RAN Management System Installation Guide, Release 4.0
6
February 9, 2015
Was this manual useful for you? yes no
Thank you for your participation!

* Your assessment is very important for improving the work of artificial intelligence, which forms the content of this project

Download PDF

advertising