Closed Circuit Television System Commissioning Standard CCTV

Closed Circuit Television System Commissioning Standard CCTV
Closed Circuit Television System Commissioning
Standard
CCTV and Lighting Upgrade
University of Wollongong
5 March 2012
V2
FMD-MAI-STA-003
Commissioning Standard Cctv V2
Document Control
Rev No
Date
01
09/02/07
02
Typist
Author
First Issue
DJAR
JGC
07/03/07
Final Issue
DJAR
03
12/05/09
Updated 3. Commissioning Process with “to meet Practical
Completion” in Commissioning Planning box
04
16/9/11
2
5/3/2012
FMD-MAI-STA-003
Revision Details
Verifier
Approver
DJAR
SJN
PGT
YB
DA
DA
DA
Reviewed throughout
YB
TJ
TJ
TJ
Document updated to reflect name change from Buildings &
Grounds (B&G) to Facilities Management Division (FMD) and
rebranding logo
YB
YB
YB
YB
Commissioning Standard Cctv V2
Contents
Section
Page
1.
Closed circuit television
4
2.
Overview
4
3.
Commissioning Process
5
4.
Pre-Commissioning Hardware Inspection
6
5.
Pre-Commissioning Software Inspection
7
6.
Documentation
7
7.
Commissioning Time and Date
7
Commissioning Tests
8
8.
9.
8.1
8.2
8.3
8.3.1
Cameras
Operator Workstation
Control Unit
Digital Recording and Playback Functions
Minor Defects
10
10. Commissioning Schedules
FMD-MAI-STA-003
8
9
9
9
Commissioning Standard Cctv V2
10
1. Closed circuit television
(CCTV) systems form part of the overall security strategy at the University of Wollongong (UOW).
CCTV systems are used in conjunction with physical and operational security measures to protect
people, property and processes.
The CCTV systems provide the following key functions:
a.
Real time surveillance;
b.
Recording of events and historical video data for video evidence of a security incident;
c.
Deterrent to criminal and unruly behaviour.
To obtain optimum performance the CCTV systems may be interfaced with other building services, in
particular intruder alarm monitoring and access control.
The CCTV system installed at the UOW is an Internet Protocol (IP) CCTV system. The system utilises
digital technology for recording and for transmitting video images via the University’s Local Area
Network (LAN). The IP CCTV system allows the flexibility for additional cameras to be added to the
system at anytime and be viewed on any workstation on the campus with a network connection and
software licence.
All future CCTV installations at UOW shall conform with the prescribed CCTV design standards.
System monitoring and programming is performed from the operator workstation. As a minimum, three
access levels are provided. These being operator, system administrator and technician.
2. Overview
The quality control process for IP CCTV equipment involves the following stages:
Stage 1: Unit Testing - Performed by the manufacturer at a component level;
Stage 2: Installation Inspections - Performed by the project manager during the installation process.
The objective is to identify poorly installed equipment or areas of the installation that do not comply
with the provisions of the design specifications. Provided the defect is identified at an early stage, the
cost of remedial work and delays to the project program can be minimised;
Stage 3: Final Commissioning - Performed by the installation contractor and witnessed by the project
manager.
Final commissioning is the most important part of the quality control process. It is at this stage of the
project that the project manager will determine whether the system is ready to be approved for
Practical Completion.
All commissioning tests are critical and shall be performed to ensure that all CCTV equipment will
operate correctly. It is UOW's objective to complete the commissioning tests with zero defects
remaining in the system.
Note: The contractor shall ensure that all works have been completed prior to performing
commissioning tests or state what is not complete to the project manager.
FMD-MAI-STA-003
Commissioning Standard Cctv V2
3. Commissioning Process
The following flow diagram depicts the commissioning process:
Commissioning Planning
Review scope of works.
Identify tasks to be performed.
Organise access.
Prepare commissioning program to meet Practical Completion.
Identify responsibilities.
Test sheets to be prepared and submitted for approval as per operational design requirements.
Comply with AS4806 CCTV Standards.
















Pre-Commissioning Inspection
Visually inspect cameras, cabling and equipment.
Determine whether installation is complete.
Determine whether cabling and equipment is
mechanically secure.
Perform all hardware and software pre-commissioning
tasks.
Determine whether the as-installed documentation is
complete.
The contractor shall liaise with ITS during the
commissioning process.
Commissioning Schedule
Complete commissioning test schedules.
Complete commissioning schedule.
Submit commissioning schedule to project manager.
FMD-MAI-STA-003
Commissioning Standard Cctv V2
4. Pre-Commissioning Hardware Inspection
At the completion of the installation and prior to the commencement of the commissioning tests, the
contractor shall inspect all hardware and verify that the following tasks have been completed in
accordance with the design specifications:
a.
All IP CCTV cameras have been installed at the locations specified in the design
documentation;
b.
Cameras of the specified type (e.g. colour, black and white, fixed, pan tilt zoom)
have been installed;
c.
Electrical and communications cables have been appropriately sized and selected to
ensure that they will support currently installed and future equipment;
d.
Cabling has been concealed where possible in ceiling spaces, wall cavities or risers;
e.
Mechanical protection has been provided to minimise the likelihood of physical
damage to cabling;
f.
Ducting, conduit and cable trays have been effectively secured to ensure that they
can support currently installed and future cabling;
g.
Cameras have been correctly secured to protect against operational damage and
ensure stability for continuous use;
h.
Connections have been correctly terminated and insulated to ensure satisfactory
connectivity and protection against faults and interference;
i.
External cameras have been provided with adequate protection against moisture
and other environmental conditions;
j.
Operator workstation CPU, LCD screen and peripheral devices have been installed
at the specified location. Interconnecting cables have been protected from
mechanical damage and have been permanently connected;
k.
Cameras and operator workstation have been identified with equipment labels that
are in accordance with UOW's asset register convention;
l.
Associated equipment such as power supplies and switches have been connected
correctly and secured appropriately.
All equipment must be installed and must pass the pre-commissioning inspection before commencing
the commissioning tests.
FMD-MAI-STA-003
Commissioning Standard Cctv V2
5. Pre-Commissioning Software Inspection
Prior to the commencement of the commissioning tests, the contractor shall verify that the correct
application software has been installed and configured on the IP CCTV control equipment.
As a minimum the contractor shall confirm the following:
a.
All software modules specified in the design documentation or the modules required
to perform all specified operation functions have been installed and configured to
meet UOW’s system requirements;
b.
The latest release version of all software modules including patches and upgrades
have been provided;
c.
The control equipment hardware has sufficient capacity to support the software
routines and functions under worst case demand conditions;
d.
All cameras, system reports, screens and menus have been correctly configured;
e.
Software has been registered to UOW.
If any of the above has not been completed, the commissioning tests shall be abandoned and rescheduled.
6. Documentation
The contractor shall submit a complete set of documentation to the client and project manager for
approval no later than one (1) week prior to the planned commissioning date. As a minimum the
documentation shall comprise:
•
•
•
•
•
As-installed drawings;
Test plan and test report sheets
Hardware and software technical manuals;
Operator and maintenance manuals
Programming schedules;
The contractor shall obtain written approval of the documentation from UOW before commencing the
commissioning tests.
7. Commissioning Time and Date
The contractor shall submit a program to the project manager containing the proposed time and date
for each commissioning test at least two (2) weeks prior to the planned commissioning date. The
program must contain allowances for defect rectification and remedial works.
The contractor shall obtain written approval of the program from the project manager and UOW before
commencing the commissioning tests.
FMD-MAI-STA-003
Commissioning Standard Cctv V2
8. Commissioning Tests
Commissioning tests shall be performed to assess the overall functionality of the IP CCTV system as
per the standards and design specifications. Each camera must be individually tested to ensure that it
transmits the correct signal or data to the operator workstation.
The commissioning tests require at least two qualified and approved testers. One tester shall be
located at the operator workstation and the other at the camera location. Portable communication
devices, such as handheld radios, shall be used for communication between the two testers.
As each commissioning test is performed, the results shall be recorded on the appropriate
commissioning test schedule. Each test performed shall be marked as a pass or fail. Any comments
regarding abnormal operation in particular to failed tests shall be recorded in the comments section of
the commissioning schedule.
8.1 Cameras
The following tests shall be performed for each CCTV camera:
•
Verify that the camera produces a clear picture with a resolution no less than that specified;
•
Verify that the camera maintains a clear picture and automatically compensates for changing
light conditions including day/night change;
•
Verify that cameras have wide dynamic range installed where specified and operate to prevent
camera blinding;
•
Verify that cameras provide complete and correct coverage of the area specified;
•
Verify that pan, tilt and zoom (PTZ) cameras are fully controllable and function correctly
including camera presets;
•
Verify that pan, tilt and zoom (PTZ) cameras are able to perform camera call preset positions by
simulating an event alarm;
•
Verify that areas of the camera view may be masked to prevent unwanted alarm activation;
•
Verify that cameras have been fitted with anti-tamper devices;
•
Simulate a tamper alarm and verify that the correct signal is transmitted to the operator
workstation;
•
Simulate a video feed fault and verify that the correct signal is transmitted to the operator
workstation;
FMD-MAI-STA-003
Commissioning Standard Cctv V2
8.2 Operator Workstation
Where cameras are alarm activated and have been interfaced with a security operator workstation,
verify the following functions:
•
•
•
•
•
•
Alarm activation;
Manual control of cameras;
Automatic sequencing and control of cameras;
Reporting;
Verify that historical data reports may be generated in less than five (5) seconds;
Site plans showing all relevant features.
8.3 Control Unit
The following tests shall be performed for the control unit:
•
Verify that control strategies have been correctly configured;
•
Verify that data is correctly transmitted to all equipment;
•
Verify the control unit activates an alarm when abnormal environmental conditions occur (where
programmed);
•
Verify that real time video data analysis functions (such as movement detection) are performed
in real time and the corresponding view displayed on the monitor;
•
Verify the IP CCTV system interfaces with the electronic monitoring and access control system
and/or the intercom system to display the correct camera view on the monitor when the
corresponding signal is received.
8.3.1
Digital Recording and Playback Functions
The following tests shall be performed for the digital IP CCTV system software:
•
•
•
Verify that adequate data storage capacity has been installed on the workstation as specified;
Verify the system hardware supplied meets the minimum specifications;
Verify the following functions for the digital IP CCTV system software:
•
•
•
•
•
•
•
•
Record;
Stop;
Play;
Pause;
Rewind;
Fast forward;
Frame by frame.
Activate an alarm area then verify that the correct video data is recorded by the system.
FMD-MAI-STA-003
Commissioning Standard Cctv V2
9. Minor Defects
As minor defects are identified during the commissioning tests, each defect shall be rectified before
proceeding to the next test. The camera, associated cabling, control equipment or software that was
found to be defective will be recorded in the commissioning report and rectified.
Once rectification is complete, the equipment shall be retested and the results recorded in the
commissioning schedules.
10. Commissioning Schedules
The commissioning schedules shall be completed in accordance with this standard. Where equipment
needs to be retested, the retest results shall be recorded. At the completion of the commissioning
tests, UOW shall have one complete set of commissioning schedules containing all field devices that
are free of defects.
FMD-MAI-STA-003
Commissioning Standard Cctv V2
Commissioning Schedule – IP CCTV Cameras
Building Number: _______________
Test
Building Name: _______________________
Commissioning
Results
Pass
Fail
Installation
⃞
⃞
Coverage
⃞
⃞
Cables & Connections
⃞
⃞
Mechanical Protection
⃞
⃞
Environmental Protection
⃞
⃞
Labelling
⃞
⃞
Picture Reproduction
⃞
⃞
Highlight Suppression
⃞
⃞
Controllable (PTZ)
⃞
⃞
Masking
⃞
⃞
Anti-Tamper Devices
⃞
⃞
Tamper Alarm
⃞
⃞
Fault Alarm
⃞
⃞
Camera Number: _____________
Commissioning Date: ___/___/___
Test Reference Notes
Camera Location: ___________________
Defect Details
Camera Type: _____________
Commissioning Contractor Name: ___________________________
FMD-MAI-STA-003
Camera Rating: __________
Project Manager Name:
Commissioning Standard Cctv V2
_______________________
Commissioning Contractor Representative: ____________________
FMD-MAI-STA-003
Project Manager Reference:
Commissioning Standard Cctv V2
____________________
5.9.2
Commissioning Schedule - Operator Workstation
Building Number: _______________
Test
Building Name: _______________________
Commissioning
Results
Pass
Fail
Hardware Installation
⃞
⃞
Software Installation
⃞
⃞
Cables & Connections
⃞
⃞
Labelling
⃞
⃞
Operator Profiles
⃞
⃞
Reporting
⃞
⃞
Alarm Activation
⃞
⃞
Manual Camera Control
⃞
⃞
Automatic Sequencing/Control
⃞
⃞
Test Reference Notes
Defect Details
Site Plans
Equipment Number: _____________
Commissioning Date: ___/___/___
Equipment Location: ___________________
Equipment Type: _____________
Commissioning Contractor Name: ___________________________
FMD-MAI-STA-003
Equipment Rating: __________
Project Manager Name:
Commissioning Standard Cctv V2
_______________________
Commissioning Contractor Representative: ____________________
FMD-MAI-STA-003
Project Manager Reference:
Commissioning Standard Cctv V2
____________________
5.9.3
Commissioning Schedule - Matrix Switcher
Building Number: _______________
Test
Building Name: _______________________
Commissioning
Results
Pass
Fail
Hardware Installation
⃞
⃞
Software Installation
⃞
⃞
Cables & Connections
⃞
⃞
Labelling
⃞
⃞
Configuration
⃞
⃞
Switching Strategies
⃞
⃞
Switch Between Views
⃞
⃞
Equipment Number: _____________
Commissioning Date: ___/___/___
Test Reference Notes
Equipment Location: ___________________
Defect Details
Equipment Type: _____________
Commissioning Contractor Name: ___________________________
FMD-MAI-STA-003
Equipment Rating: __________
Project Manager Name:
Commissioning Standard Cctv V2
_______________________
Commissioning Contractor Representative: ____________________
5.9.2
Project Manager Reference:
____________________
Commissioning Schedule - Control Unit
Test
Commissioning
Results
Pass
Fail
Hardware Installation
⃞
⃞
Software Installation
⃞
⃞
Cables & Connections
⃞
⃞
Labelling
⃞
⃞
Control Strategies
⃞
⃞
Data Transmission
⃞
⃞
Alarm Activation
⃞
⃞
Video Data Analysis
⃞
⃞
Interface with EMAC/Intercom
⃞
⃞
Building Number: _______________
Equipment Number: _____________
Commissioning Date: ___/___/___
FMD-MAI-STA-003
Test Reference Notes
Building Name: _______________________
Equipment Location: ___________________
Defect Details
Equipment Type: _____________
Commissioning Standard Cctv V2
Equipment Rating: __________
Commissioning Contractor Name: ___________________________
Commissioning Contractor Representative: ____________________
FMD-MAI-STA-003
Project Manager Name:
Project Manager Reference:
Commissioning Standard Cctv V2
_______________________
____________________
5.9.2
Commissioning Schedule - Digital Recording and Playback Functions
Building Number: _______________
Test
Building Name: _______________________
Commissioning
Results
Pass
Fail
Hardware Installation
⃞
⃞
Software Installation
⃞
⃞
Cables & Connections
⃞
⃞
Labelling
⃞
⃞
Data Storage Capacity
⃞
⃞
Memory
⃞
⃞
Record
⃞
⃞
Stop
⃞
⃞
Play
⃞
⃞
Pause
⃞
⃞
Rewind
⃞
⃞
Fast Forward
⃞
⃞
Frame by Frame
⃞
⃞
Alarm Recording
⃞
⃞
Equipment Number: _____________
Commissioning Date: ___/___/___
Test Reference Notes
Equipment Location: ___________________
Defect Details
Equipment Type: _____________
Commissioning Contractor Name: ___________________________
FMD-MAI-STA-003
Equipment Rating: __________
Project Manager Name:
Commissioning Standard Cctv V2
_______________________
Commissioning Contractor Representative: ____________________
FMD-MAI-STA-003
Project Manager Reference:
Commissioning Standard Cctv V2
____________________