ASBESTOS MANAGEMENT
Table of Contents
1. Background
2. Policy
3. Scope
4. Definitions
5. Roles and Responsibilities
6. Guidelines
1. Implementation
2. Monitoring
7. Procedures
8. Compliance
9. References
10. Inquiries
Annex A - Definitions
Annex B - Roles and Responsibilities
Annex C - Code of Practice
Appendix 1 - Evaluation of Asbestos Containing Materials (ACM) and Recommendations for
Control
Appendix 2 - Contractor Notification and Acknowledgement
Appendix 3 - Certificate of Training for Asbestos-Related Work
Appendix 4 - Asbestos-Related Work Record
Appendix 5 - Classification of Asbestos-Related Work
Appendix 6 - Work Procedures
1.
BACKGROUND
1. Public Works and Government Services Canada shall comply with all federal,
provincial, territorial and municipal regulations, statutes and requirements with regard
to asbestos containing materials (ACM) in government owned or leased buildings
and facilities.
2. This departmental policy and code of practice are established in response to the
requirement for a comprehensive approach to departmental asbestos management.
This will ensure that the responsibilities of the department, as building owner, tenant,
landlord and employer, with respect to safety and health issues and environmental
control issues, are fully addressed.
3. This departmental policy and code of practice specify the role and responsibilities of
the Regional Asbestos Coordinator and provide standard methods and procedures to
address the following:
1. identification, assessment and inventory of ACM in buildings and facilities;
2. notification to employees, client departments and contractors regarding the
presence of friable asbestos;
3. reassessment of friable ACM on an annual basis;
4. maintenance of departmental information regarding ACM;
5. training modules for PWGSC personnel, based on the responsibilities and
duties to be undertaken in relation to asbestos management;
6. identification, classification, monitoring, inspection and control of asbestos-
related work undertaken by departmental personnel or contractors.
2.
POLICY
Public Works and Government Services Canada shall ensure the control of asbestos
containing materials (ACM). The responsibilities of the department, as building owner, tenant,
landlord and employer, with respect to safety and health issues and environmental control
issues, shall be fully addressed and in accordance with the Canada Labour Code, Part II, the
Canada Occupational Safety and Health Regulations, Part X - Hazardous Substances, and
applicable provincial and territorial occupational health and safety and environmental
protection legislation.
3.
SCOPE
This departmental policy and code of practice apply to all managers, supervisors and
employees where the duties required to be undertaken involve the removal, repair or
maintenance of ACM. This departmental policy and code of practice apply to any building or
facility in which friable material, that may contain asbestos, has been used, and all repairs,
alterations or maintenance of any building or facility where ACM may exist.
4.
DEFINITIONS
See Annex A.
5.
ROLES AND RESPONSIBILITIES
See Annex B.
6.
GUIDELINES
1. Implementation
The Director, Corporate Environment, Safety and Health shall provide the framework
for departmental asbestos management through the provision of approved
departmental training modules to meet requirements, and the issue of standard
methods and procedures. Training requirements shall be reviewed on an annual
basis.
The Regional Asbestos Coordinator shall implement the departmental methods and
standards within the region and shall ensure that initial surveys for asbestos are
conducted, inventories are developed and properly maintained, and that training
requirements for departmental employees are identified and that the training is
provided.
2. Monitoring
The Director, Corporate Environment, Safety and Health shall monitor asbestos
management to ensure that requirements are met, and that procedures are
established and implemented as required throughout the department.
The Regional Asbestos Coordinator and the Regional Manager responsible for
Safety and Health shall review the progress of asbestos surveys and training, and
the overall implementation of asbestos management and subsequent safety and
health issues, on a quarterly basis.
Training requirements, notifications, records, procedures and other safety and health
issues related to asbestos management shall be reviewed on a quarterly basis by the
network of Workplace Safety and Health Committees and Representatives.
Issues related to asbestos management that cannot be resolved at the workplace
level shall be reported to the Regional Safety and Health Committee. Issues that
cannot be resolved at the regional level shall be reported to the National Safety and
Health Committee.
7.
PROCEDURES
Annex C - Code of Practice
8.
COMPLIANCE
Compliance with this departmental policy is mandatory and in accordance with all existing
safety and health legislation. The refusal of an employee at any level to comply with this
departmental policy or with the provisions of the prescribed codes, standards, regulations,
and/or departmental policies will be considered as misconduct.
9.
REFERENCES
Acts and Regulations:

Canada Labour Code, Part II:
 Part II of the Canada Occupational Safety and Health Regulations, (COSH),
Building Safety,
 Part X of the Canada Occupational Safety and Health Regulations, (COSH),
Hazardous Substances,
 Part XIV of the Canada Occupational Safety and Health Regulations,
(COSH), Materials Handling.
Treasury Board Publications:



Occupational Health Evaluation Standard;
Procedures for occupational exposure to asbestos;
Canadian National Master Specifications, Sections 13280, 13281 and 13282.
PWGSC Publications:



DP 007 - Health and Safety Policy
DP 017 - Personal Protective Equipment for Employees
DP 018 - Hazardous Occurrence Investigating, Reporting and Recording
Other Publications:


Provincial and Territorial Occupational Health and Safety Legislation;
Provincial and Territorial Environmental Protection Legislation.
10. INQUIRIES
Departmental:
Director
Corporate Environment, Safety and Health
Regional:
Regional Managers responsible for Safety and Health
R. A. Quail
Deputy Minister and
Deputy Receiver General for Canada
Annex A - Definitions
Asbestos Containing Material (ACM) (Matériau contenant de l'amiante (MCA)) means
any material found to contain asbestos that is at or above the limit defined by provincial
standards, as determined by the standard Polarized Light Microscopy (PLM) method for
the analysis of bulk samples.
Department (ministère) means Public Works and Government Services Canada
(PWGSC).
Employee (employé) means a person employed by the department.
Employer (employeur) means a supervisor who is responsible for the work of one or
more employees at the workplace.
Friable asbestos product (produit friable à base d'amiante) means ACM, that when dry,
can be crumbled, pulverized or powdered by hand pressure. This definition also includes
dust or debris arising from non-friable materials that are, or will become, crumbled,
pulverized or powdered, i.e., asbestos containing plaster disturbed by demolition. Friable
asbestos-suspect products include: Sprayed asbestos products, (fireproofing, thermal
insulation, acoustic insulation or decorative products), applied in 1974 or earlier; Acoustic
or texture plaster applied in 1983 or earlier; Mechanical insulation installed in 1983 or
earlier, (jacketed or not); Compressed mineral fibre ceiling tiles installed in 1983 or
earlier.
Hazardous occurrence (situation dangereuse) means an event occurring at a PWGSC
managed building or worksite, or through the course of an employee's work that results
in, or has the potential to result in, a fatality, injury, property damage or an escapement of
a hazardous material. For the purpose of investigating, recording and reporting of
hazardous occurrences, the following are included under this term: Critical Incidents;
Disabling Injuries; Non-Disabling Injuries; Minor Injuries; Minor Occurrences and NearMisses.
Manager in charge of worksite (gestionnaire responsable du lieu de travail) means the
person to whom the supervisor reports directly.
Person in charge (personne responsable) means a qualified person, appointed by
management, to ensure the safe and proper conduct of an operation, or the work of
employees.
Personal protective equipment (équipement de protection individuelle) means any
clothing, equipment or device worn or used by a person to protect that person from injury
or illness.
Qualified person (personne qualifiée) means, with respect to a specified duty, an
individual who, because of knowledge, training and experience, is qualified to safely and
properly perform the duty.
Region or Regional, (région ou régional) when utilized in Safety and Health
Departmental Policies and Codes of Practice, refers to all Regions and includes the
National Capital Area.
Senior employer representative (représentant supérieur de l'employeur) means the
individual with the delegated authority to make and carry out decisions of an operational
nature, on behalf of the department, for the workplace.
Supervisor (superviseur) means the person at the workplace to whom the employee(s)
report(s) directly.
Workplace (lieu de travail) means any place where an employee is engaged in work for
the department.
Annex B - Roles and Responsibilities
1. Branch/Agency Heads are accountable for the implementation of this
departmental policy within their areas of responsibility. This accountability is
further referenced in DP 007, Annex A - Accountability Framework for the Health
and Safety Function.
In addition, Regional Directors General are responsible for appointing a qualified
person as the Regional Asbestos Coordinator.
2. Senior Employer Representatives are responsible for ensuring that all
workplaces within their area of responsibility implement the requirements of this
departmental policy and code of practice.
3. The Director, Corporate Environment, Safety and Health is responsible for:
1. monitoring the departmental program to ensure that requirements for
asbestos management are met, and that procedures are established and
implemented as required throughout the department;
2. approving training modules prior to implementation, and ensuring that an
annual review of training requirements is undertaken;
3. liaising, on behalf of the department, with regulatory bodies, central
agencies, and provincial bodies on matters related to asbestos
management.
4. The ADM, Human Resources Branch, is responsible for ensuring that the
appropriate procedures are implemented so that Asbestos-Related Work
Records are maintained on employee files for a period of thirty (30) years.
5. The Regional Asbestos Coordinator is responsible for:
1. implementing the requirements for departmental asbestos management
within the region;
2. arranging for initial asbestos surveys and the reassessments of buildings
and facilities;
3. preparing standard notification letters regarding the existence of friable
asbestos, for issue by Property, Facility or Project Managers;
4. maintaining a data base of survey and reassessment information relating
to the existence of ACM;
5. issuing copies of asbestos inventory and assessment reports and
updates to Property and Facility Managers;
6. classifying asbestos-related project work on behalf of Project Managers,
and arranging for the preparation of specifications when required;
7. ensuring that Property and Facility Managers are aware of the
requirements of asbestos management, and ensuring that standard
procedures are implemented for asbestos work, required training is
provided, current information relating to ACM is available and records are
properly maintained;
8. coordinating training requirements for departmental employees and
maintaining records of training;
9. maintaining all records relating to asbestos management within the
region and asbestos work undertaken in the region, i.e., asbestos
inventory and assessment reports, training records, notification letters
and work records;
10. reviewing all work requirements that have been classified as Type 3, and
undertaking the direction of the work when required;
11. assisting in the identification of circumstances where an employee is, or
may be, exposed to airborne asbestos during work not subject to the
precautions required by the Asbestos Management Code of Practice and
ensuring that any required hazard assessments are undertaken;
12. ensuring that the Regional Manager responsible for Safety and Health
has been notified in situations where an employee has been exposed to
a hazardous occurrence where an investigation may be required;
13. reviewing asbestos-related work requirements, at random, to ensure that
work has been properly classified, and that all required specifications
have been addressed;
14. reviewing, on a quarterly basis, the progress of asbestos surveys and
training, and implementation of asbestos management, and safety and
health issues with the Regional Manager responsible for Safety and
Health.
6. Property Managers, Facility Managers and Project Managers shall implement
this departmental policy and code of practice as required, based on the nature of
their function and the duties for which they are responsible, by:
1. ensuring that the requirements for departmental asbestos management
are fully implemented within their area of responsibility;
2. reviewing all maintenance work requirements against survey information
to determine the possibility of friable asbestos being disturbed, and
classifying the work based on the approved criteria;
3. notifying, in writing, Workplace Safety and Health Committees and
Representatives, (tenant departments and PWGSC), and employees and
contractors of the existence of friable ACM, and providing updates on
conditions as modifications or changes are made;
4. maintaining asbestos inventory, assessment and reassessment reports
and ensuring that a copy of this information is maintained in a location
that is accessible to maintenance staff and contractors;
5. obtaining the approval of the Regional Asbestos Coordinator prior to
arranging for the removal or repair of damaged or deteriorated friable
ACM;
6. submitting all Type 3 work requirements to the Regional Asbestos
Coordinator for review prior to arranging for the work to be undertaken;
7. consulting the Regional Asbestos Coordinator, when necessary, to
determine the impact of a specific project with regards to ACM;
8. maintaining a stock of required equipment for work classified as Type 1
and Type 2;
9. identifying and providing a suitable storage area for waste resulting from
asbestos work, and arranging for periodic waste removal.
7. Managers in Charge of Worksites and Supervisors shall implement this
departmental policy and code of practice as required by the nature of the tasks
for which they are responsible, by:
1. ensuring that employees have been provided with the required training to
undertake the work;
2. ensuring that the appropriate personal protective equipment, tools and
clothing required for the work are provided;
3. ensuring that testing, maintenance and storage routines are established
and implemented for all personal protective equipment and tools;
4. identifying a qualified person to undertake the duties of the "Person in
Charge";
5. ensuring that an Asbestos-Related Work Record Form (PWGSC-TPSGC
55) is completed for each period of work, and that a copy of this record is
submitted to Human Resources Branch to be placed on employee files,
and a copy is submitted to the Regional Asbestos Coordinator;
6. ensuring that all employees required to perform work classified as Type 2
or Type 3 undertake health evaluations as per the requirements of DP
059 - Health Evaluations - Safety and Health, PWGSC;
7. notifying the Asbestos Coordinator of any hazardous occurrence that has
taken place or when their has been a requirement to undertake
emergency asbestos-related work for a particular situation.
8. The Person in Charge is responsible for:
1. ensuring that workers on site have been provided with the required
training for the work to be undertaken;
2. ensuring that all required equipment is on site before commencement of
the work;
3. ensuring that the appropriate personal protective equipment, tools and
clothing required for the work are worn and/or utilized;
4. ensuring that the appropriate procedures for the work are implemented
and that all workers are aware of, and comply with, established
procedures;
5. ensuring that all procedures for inspection and air monitoring are
implemented based on the classification of the work and the specified
requirements;
6. immediately informing the Manager in Charge of the Worksite or the
Supervisor of a hazardous occurrence involving asbestos-related work.
9. Regional Managers responsible for Safety and Health are responsible for:
1. monitoring worksites periodically to ensure that standard procedures are
implemented for asbestos work, required training is provided, current
information relating to ACM is available and records are properly
maintained;
2. investigating specific workplace complaints concerning asbestos and
asbestos-related work and taking appropriate action;
3. providing assistance and advising the Asbestos Coordinator of specific
safety and health issues and requirements related to asbestos
management;
4. reviewing, on a quarterly basis, with the Regional Asbestos Coordinator
the implementation of asbestos management and safety and health
issues.
10. Workplace Safety and Health Committees and Representatives are
responsible for:
1. participating in hazard investigations to determine the risks and hazards
associated with asbestos-related work requirements;
2. monitoring workplaces to ensure that the requirements for asbestosrelated work have been addressed, i.e., training has been provided;
personal protective equipment is provided and properly utilized; records
are maintained and procedures are implemented;
3. reporting immediately, specific workplace complaints related to asbestos
management, to the Regional Manager responsible for Safety and
Health;
4. undertaking a review of training requirements for asbestos-related work
on an annual basis.
11. Employees are responsible for:
1. applying the appropriate practices, procedures and equipment for the
type of asbestos-related work;
2. wearing and/or utilizing and maintaining the required personal protective
equipment, clothing and tools;
3. reporting immediately, to the Person in Charge, the Manager in Charge
of the Worksite, or the Supervisor, all known or suspected conditions or
activities that are in violation of approved practices and procedures and
that may cause a hazardous occurrence.
Annex C - Code of Practice
1. Asbestos Surveys, Assessments and Inventories
To ensure that a complete inventory of ACM that includes friable ACM and the
principal types of non-friable ACM is developed, it is necessary to undertake a
thorough survey of all government-owned or leased facilities. Once ACMs are
identified through surveys and assessments of the materials are made,
inventories shall then be established and maintained.
Leasing Space and Friable Asbestos
When space is considered for lease in a building that was constructed before
1983, PWGSC shall request and obtain from the lessor, an asbestos survey that
identifies all friable asbestos materials located within the structure.
This survey shall be signed by and conducted under the direction of a qualified
person, competent in asbestos control, i.e., a Professional Engineer, a Certified
Industrial Hygienist, or a Registered Occupational Hygienist.
If friable asbestos is present the following rules shall be applied in considering the
space:
1. the department shall not lease space when there is friable asbestos
material located directly within the space to be occupied;
2. the department may lease space when friable asbestos is present
elsewhere in the building, provided that there is an asbestos
management program in place that meets the basic requirements of the
department, as described herein by the departmental policy and code of
practice for asbestos management.
Asbestos Surveys
The Regional Asbestos Coordinator shall undertake the planning and
coordination of all asbestos surveys. A detailed survey of each location within the
region shall be undertaken initially, in order to determine the presence of ACM,
including all friable asbestos materials, applications of floor finishes and asbestos
reinforced cement products, i.e., asbestos cement sheeting and piping. This
survey shall be conducted on a floor-by-floor and room-by-room basis.
The Regional Asbestos Coordinator shall ensure that all surveys are conducted
under the direction of a qualified person competent in asbestos control, i.e.,
Professional Engineer, Certified Industrial Hygienist, or Registered Occupational
Hygienist.
The Regional Asbestos Coordinator shall ensure that each survey is signed off by
the qualified person who directed the survey.
Assessment of Asbestos Materials
ACM that is identified during the survey shall be assessed, and recommendations
regarding the action to be taken shall be determined as per the specifications
provided in Appendix 1 - Evaluation of Asbestos Containing Materials (ACM) and
Recommendations for Control.
Appendix 1 provides specific criteria for the assessment of materials based on
condition and accessibility, and provides an Action Matrix, which is utilized in
determining the recommended action to control ACM based on the particular
circumstances. Detailed information regarding the requirements to properly
undertake each action are also provided.
NOTE: Analysis of materials to determine asbestos content shall be performed by
Health Canada, or by private laboratories accredited by the National Voluntary
Laboratory Accreditation Program (NVLAP) of the U.S. National Institute of
Science and Technology (NIST), in the use of the Polarized Light Microscopy
method. The analysis of bulk samples shall be performed to the detection limits
as indicated in Appendix 1 - Detection Limit of Bulk Analysis.
Asbestos Inventories
Once surveys have been completed and assessment of materials has been
made, the Asbestos Coordinator shall ensure that this inventory information is
entered into the PWGSC Asbestos Management Database. The Asbestos
Coordinator shall update this information as changes are made at the various
locations, or where new information identifies the existence of ACM not
previously identified.
The Asbestos Coordinator shall ensure that Completed Asbestos Inventory,
Assessment Reports and Reassessment Reports are forwarded to the respective
Property or Facility Manager, and that current copies of these documents are
made available at a location in each building or facility that is accessible to
maintenance staff, contractors and workplace safety and health committee
members and representatives.
NOTE: Property and Facility Managers shall notify the Regional Asbestos
Coordinator prior to arranging for, or undertaking, removal or repair of damaged
or deteriorated friable asbestos materials identified by the Asbestos Inventory
and Assessment.
2. Notification of Friable Asbestos
The Regional Asbestos Coordinator shall provide written notice to Property and
Facility Managers concerning the presence of friable ACM, as per the findings of
surveys and assessments.
For those locations where a survey and assessment are pending, and the
presence of friable ACM is known, the Regional Asbestos Coordinator shall
provide interim written notice to the Property or Facility Manager.
Upon receipt of Asbestos Inventory and Assessment reports, the Regional
Asbestos Coordinator shall provide updated written notification to Property and
Facility Managers.
Property and Facility Managers shall ensure that written notice is provided to the
following groups:



Workplace Safety and Health Committees and Representatives;
Maintenance Employees;
Contractors, Inspectors. (Those who may enter parts of the building or
facility where friable ACM may be present, i.e., telecommunications firms,
boiler maintenance contractors, inspectors, etc.) See Appendix 2 -
Contractor Notification and Acknowledgement.
Copies of all notices issued to Property and Facility Managers shall be
maintained by the Regional Asbestos Coordinator.
3. Reassessment of Friable Asbestos
The Regional Asbestos Coordinator shall arrange for an annual reassessment of
all friable ACM present in exposed locations.
Copies of reassessment reports shall be distributed to Property and Facility
Managers. Property and Facility Managers shall provide updated information to
the following groups:



Workplace Safety and Health Committees and Representatives;
Maintenance Employees;
Contractors, Inspectors. (Those who may enter parts of the building or
facility where friable ACM may be present, i.e., telecommunications firms,
boiler maintenance contractors, etc.) See Appendix 2 - Contractor
Notification and Acknowledgement.
Property and Facility Managers shall notify the Regional Asbestos Coordinator
prior to arranging for, or undertaking, removal or repair of damaged or
deteriorated friable ACM.
4. Training
Training shall be provided to PWGSC personnel, as required, based on their
roles and responsibilities related to asbestos management. Training shall be
delivered in modules in order to target specific requirements and related duties,
and to avoid duplication.
The duration of training and mode of delivery shall be determined by the Director,
Corporate Environment, Safety and Health, in consultation with the National
Safety and Health Committee.
The Regional Asbestos Coordinator and the Human Resources Branch, shall
maintain records of training.
Training requirements shall be reviewed annually by the network of Workplace
Safety and Health Committees and Representatives.
Asbestos Management Training
Asbestos management training shall be provided to the Regional Asbestos
Coordinators, Property and Facility Managers, and Project Managers. This
training will include an introduction to the asbestos inventory and assessment
reports, health hazards of asbestos exposure, regulations, the Asbestos
Management Code of Practice, classification of asbestos work, asbestos project
control, and emergency procedures.
Asbestos Procedures Training
Training shall be provided to maintenance workers who will perform Type 1 or
Type 2 work. The training will include an introduction to the asbestos inventory
and assessment reports, health hazards of asbestos exposure, regulations, the
Asbestos Management Code of Practice, Type 1 and Type 2 work practices, and
disposal procedures. Upon completion of the training, workers shall sign a form
acknowledging the training received. See Appendix 3 - Certificate of Training for
Asbestos-Related Work.
Respirator Training
Respirator training shall be provided to all those who will perform Type 2 work,
and to employees who will perform Type 1 work and request a respirator. The
training will cover limitations of use, fitting, and maintenance of respirators.
Persons provided with a respirator will be fit-tested with the assigned respirator,
using the CSA irritant smoke method. See Appendix 6 - Respirator Fitting,
Inspection, Cleaning and Disinfecting for procedures and related information
regarding respirators.
NOTE: Employees who will utilize a respirator shall be required to undertake a
medical evaluation as per the requirements of DP 059 - Health Evaluations Safety and Health, PWGSC
Asbestos Awareness Training
Training shall be provided to all maintenance and operations personnel who may
work near asbestos materials.
This training shall also be required for those who supervise workers or
contractors who may work near asbestos materials.
The module will introduce the asbestos inventory and assessment reports, health
hazards of asbestos exposure, the Asbestos Management Code of Practice, and
emergency procedures.
This training shall also be made available to Workplace Safety and Health
Committee Members and Representatives.
5. Identification, Classification and Control of Asbestos-Related Work
Maintenance Work
Property and Facility Managers, or their designates, are responsible to review all
maintenance work for the possibility of the disturbance of ACM when required
work is undertaken.
When there are friable or non-friable ACMs in the area, and this material will be
disturbed by the work, then the work shall be determined as asbestos-related
work and classified as Type 1, Type 2, or Type 3. Appropriate procedures shall
be implemented based on the classification of the work. See Appendix 5 Classification of Asbestos-Related Work, and Appendix 6 - Work Procedures.
If there are friable or non-friable ACMs in the area of maintenance, that will be
disturbed by the intended work, the Property or Facility Manager or designate
shall classify the work as Type 1, Type 2, or Type 3. Work determined to be a
Type 3 classification shall be forwarded to the Asbestos Coordinator for review.
The Regional Asbestos Coordinator shall review all work that is classified as
Type 3 asbestos work. The Regional Asbestos Coordinator shall determine,
based on the requirements and specific circumstances of the work, the degree of
his/her personal involvement in the direction of the work.
NOTE: If there are friable ACMs in the area of maintenance, and it has been
determined that these materials will not likely be disturbed by the maintenance
work, the Property or Facility Manager shall inform maintenance staff and/or the
contractor of the presence of friable ACMs prior to the commencement of work.
On completion of any maintenance work which involves asbestos removal or
repair, a report will be provided to the Regional Asbestos Coordinator which
indicates the asbestos-related work that has been completed. See Appendix 4 Asbestos-Related Work Record. The Regional Asbestos Coordinator will then
update the information in the inventory as required, and ensure that this
information is distributed as required.
NOTE:



Property and Facility Managers shall maintain a stock of the approved
equipment required for Type 1 and Type 2 asbestos work, where
PWGSC staff perform asbestos work.
When asbestos work is performed by PWGSC staff, asbestos debris
shall be packaged in double-bagged containers or other suitable
containers, by those completing the project. These containers shall be
held at a pre-determined, secure location in the building.
The Property or Facility Manager shall arrange for periodic collection of
asbestos waste containers from this location.
Renovation and Construction Work
Project Managers shall consult the Regional Asbestos Coordinator prior to
undertaking renovation or construction work. The Regional Asbestos Coordinator
shall review the asbestos survey reports for the possible impact on asbestos
materials, prior to all renovation and construction work.
Prior to commencement of projects that include the demolition of plaster installed
prior to December 1983, testing of the plaster for asbestos shall be undertaken,
unless previous comprehensive testing in the building has shown this plaster to
be free of asbestos. Records of plaster test results shall be maintained by the
Asbestos Coordinator and the Property or Facility Manager along with the
asbestos surveys of the building.
The Regional Asbestos Coordinator, on behalf of the Project Manager, shall
classify the work as Type 1, Type 2, or Type 3.
In Ontario, the Project Manager, through the Regional Asbestos Coordinator,
shall obtain a Designated Substance Report (a prescribed listing of asbestos,
lead, silica, and other hazardous materials) prior to tendering the work.
The Regional Asbestos Coordinator, on behalf of the Project Manager, shall
arrange for specifications to be prepared for asbestos work, following the
National Master Specification. Alterations to specifications, in order to
accommodate specific provincial requirements, shall be determined when
required.
Services related to the design and preparation of specifications shall be
performed by Consultants or Engineers with the appropriate training, experience
and insurance for asbestos-related work. Insurance shall specifically include
professional liability with pollution coverage.
When there are friable asbestos materials in the renovation area, and the
Regional Asbestos Coordinator has determined that these materials are not likely
to be disturbed by the work, the maintenance staff or the contractor must be
notified of the presence of friable asbestos materials. The contractor shall be
required to sign the Contractor Notification and Acknowledgement Form prior to
commencement of the work. See Appendix 2 - Contractor Notification and
Acknowledgement.
At the completion of any project work which alters the amount or condition of
friable ACM, a report will be provided to the Regional Asbestos Coordinator
which indicates the work that has been completed. See Appendix 4 - AsbestosRelated Work Record. The Regional Asbestos Coordinator will then update
information in the inventory, and ensure that this information is distributed as
required.
6. Asbestos Work Records and Medical Surveillance
Managers in Charge of Worksites and Supervisors shall ensure that an AsbestosRelated Work Record is completed for employees performing Type 2 or Type 3
work, or entering a Type 2 or Type 3 work area. A work record shall be
completed for each period of work.
Managers in Charge of Worksites and Supervisors shall ensure that a copy of
each work record is forwarded to Human Resources Branch and to the Regional
Asbestos Coordinator. See Appendix 4, for a sample of the Asbestos-Related
Work Record.
Human Resources Branch shall maintain Asbestos-Related Work Reports on
employee files for a period of thirty (30) years. Asbestos-Related Work Reports
shall be maintained by the Office of the Regional Asbestos Coordinator for a
period of thirty (30) years.
All PWGSC employees who will perform Type 2 or Type 3 work shall undertake a
medical evaluation as per the requirements of DP 059 - Health Evaluations -
Safety and Health, PWGSC.
7. Asbestos Work Procedures
Type 1, Type 2, and Glove Bag Procedures
Standard procedures for performing Type 1, Type 2, and Glove Bag asbestos
work are provided in Appendix 6 - Work Procedures.
Type 3 Procedures
Type 3 procedures are not included in the standard procedures provided in
Appendix 6 - Work Procedures.
Procedures for Type 3 work are developed for the particular work to be
undertaken, and the specific circumstances and worksite. These procedures shall
be developed in compliance with the National Master Specification, Section
13282, Asbestos Abatement (maximum precautions).
Emergency Procedures
Procedures for asbestos work, required on an emergency basis, as an immediate
response to floods, pipe breaks, ceiling collapses, or other emergencies that
affect asbestos materials, are provided in Appendix 6 - Work Procedures. These
procedures shall be implemented to protect those undertaking the work, and to
protect all others from, or limit exposure to, airborne asbestos.
Emergency procedures, indicated in Appendix 6 - Work Procedures, shall be
followed as closely as possible, in the event of an emergency situation.
Emergency Plans
An Emergency Plan that corresponds with the emergency procedures for the
specific site shall be developed and implemented, to ensure that safety and
health requirements are addressed in the event of emergency situations that
require work shut-down and evacuation.
8. Asbestos Work Inspection and Air Monitoring
Type 1 and Type 2 Work
Type 1 and Type 2 work shall be subject to the standard maintenance or project
inspection requirements for non-asbestos work. Asbestos-specific air monitoring
or inspection is not mandatory.
Type 3 Work
The Regional Asbestos Coordinator, on behalf of the Project Manager, may
arrange for the inspection and air monitoring during Type 3 asbestos projects.
These services shall be provided by consultants or engineers with the
appropriate training, experience and insurance for asbestos-related work.
When Type 3 work is to be undertaken in an occupied building, or in a building in
use, daily inspection and air monitoring shall be required. If the building is not
occupied, inspection shall be at critical stages of the work, unless provincial
standards require daily inspection, as necessary in Quebec and British Columbia.
All Type 3 removal projects shall be subject to final clearance air testing. The
clearance criteria shall be a maximum fibre concentration of 0.01 fibre/ml of air,
as determined by the standard Phase Contrast Microscope (PCM) method.
9. Air Monitoring and Bulk Analysis
Air Monitoring for Hazard Assessment
When the Regional Asbestos Coordinator is requested to, and has determined
the requirement for, air monitoring under normal conditions of building use (i.e.,
away from asbestos work), the measurements shall be made by the
Transmission Electron Microscopy (TEM) analytical method.
NOTE: Air monitoring shall not be used as the primary method for the
assessment of hazard from asbestos materials.
Air Monitoring During Asbestos Work
The Regional Asbestos Coordinator shall arrange for air monitoring during Type 3
work, as required, to confirm the safety of work practices and the effectiveness of
work area isolation. These measurements shall be made by the Phase Contrast
Microscope (PCM) method recognized by Human Resources Development
Canada (HRDC) - Labour Programs and provincial occupational health and
safety authorities.
PCM measurements shall be made by National Institute of Occupational Safety
and Health (NIOSH) method 7400, except work in British Columbia and Quebec,
where provincial analytical methods are in place.
Analysis of PCM samples shall be performed by Health Canada or individuals or
organizations successfully participating in a recognized external quality control
program.
Bulk Sample Collection and Analysis
Procedures for collection and labeling of bulk samples for asbestos analysis are
detailed in Appendix 6 - Work Procedures.
Analysis of materials to determine asbestos content shall be performed by Health
Canada or by private laboratories accredited by the National Voluntary
Laboratory Accreditation Program (NVLAP) of the U.S. National Institute of
Science and Technology (NIST). The laboratories shall report to the limits of
detection as indicated in Appendix 1 - Detection Limit of Bulk Analysis.
Maintenance of Records
The Regional Asbestos Coordinator shall maintain copies of all reports and
records relating to testing, sampling and analysis undertaken for buildings and
facilities within the region.
10. Hazard Investigation
When an employee is or may be exposed to airborne asbestos as a result of
direct disturbance of asbestos materials during maintenance, renovation or
construction work not subject to the appropriate precautions required by the
Asbestos Code of Practice, or by similar inadvertent direct contact not subject to
the appropriate precautions, the Regional Asbestos Coordinator shall appoint a
qualified person to conduct a hazard assessment. This assessment must
consider the potential hazard, and must conclude as to whether the hazardous
material could be present.
The Regional Asbestos Coordinator shall notify, in writing, the Workplace Safety
and Health Committee or Representatives of this assessment.
The assessment shall determine the potential hazard, and must conclude as to
whether the hazardous material could be present as an airborne hazard, at a
level of at least 50% of the exposure limit. When it has been determined that the
hazardous material could be present at a level of at least 50% of the exposure
limit, a control plan must be instituted.
Control Plans for Asbestos
When an assessment has determined that asbestos could be present as an
airborne hazard, at a level of at least 50% of the exposure limit, a control plan
must be established and implemented to address the following requirements:




a record of where asbestos materials are located;
written procedures for control;
medical surveillance, when applicable;
training of employees.
The control plan must be reviewed at least once per year, or as new information
is received that changes the requirements of the plan.
Annex C - Appendix 1 - Evaluation of Asbestos Containing Materials (ACM) and
Recommendations for Control
1. Assessment of Condition
Spray Applied Fireproofing, Insulation and Texture Finishes
In evaluating the condition of ACM spray applied as fireproofing, thermal
insulation or texture, decorative or acoustic finishes, the following criteria apply:
GOOD Surface of material shows no significant signs of damage,
deterioration or delamination. Up to one percent visible damage to
surface is allowed within range of GOOD. Evaluation of sprayed
fireproofing requires the surveyor to be familiar with the irregular
surface texture typical of sprayed asbestos products. GOOD
condition includes unencapsulated or unpainted fireproofing or
texture finishes, where no delamination or damage is observed, and
encapsulated fireproofing or texture finishes where the encapsulation
has been applied after the damage or fallout occurred.
POOR Sprayed materials show signs of damage, delamination or
deterioration. More than one percent damage to surface of ACM
spray.
In observation areas, where damage exists in isolated locations, both GOOD and
POOR condition may be reported. The extent or percentage of each condition will
be recorded on the survey or reassessment form.
NOTE: FAIR condition is not utilized or considered as a valid criterion in the
evaluation of sprayed fireproofing, sprayed insulation, or texture coat finishes.
The evaluation of ACM spray applied as fireproofing, non-mechanical thermal
insulation, or texture, decorative or acoustic finishes which are present above
ceilings, may be limited by the number of observations made, and by building
components such as ducts or full height walls that obstruct the above ceiling
observations. Persons entering the ceiling area are advised to be watchful for
ACM DEBRIS prior to accessing or working above ceilings in areas of buildings
with ACM, regardless of the reported condition.
Mechanical Insulation
In evaluating the condition of mechanical insulation (on boilers, breeching,
ductwork, piping, tanks, equipment etc.) the following criteria are used:
GOOD Insulation is completely covered in jacketing and exhibits no evidence
of damage or deterioration. No insulation is exposed. Includes
conditions where the jacketing has minor surface damage (i.e., scuffs
or stains), but the jacketing is not penetrated.
FAIR
Minor penetration damage to jacketed insulation (cuts, tears, nicks,
deterioration or delamination) or undamaged insulation that has
never been jacketed. Insulation is exposed but not showing surface
disintegration. The extent of missing insulation ranges should be
minor to none.
POOR Original insulation jacket is missing, damaged, deteriorated or
delaminated. Insulation is exposed and significant areas have been
dislodged. Damage cannot be readily repaired.
The evaluation of mechanical insulation may be limited by the number of
observations made and building components such as ducts or full height walls
that obstruct observations. In these circumstances, it is not possible to observe
each foot of mechanical insulation from all angles.
Non-Friable and Potentially Friable Materials
Non-friable materials generally have little potential to release airborne fibres,
even when damaged by mechanical breakage. However, some non-friable
materials, i.e., exterior asbestos cement products, may have deteriorated so that
the binder no longer effectively contains the asbestos fibres. In such cases of
significantly deteriorated non-friable material, the material will be treated as a
friable product.
2. Evaluation of Accessibility
The accessibility of building materials known or suspected of being ACM is rated
according to the following criteria:
ACCESS (A)
Areas of the building within reach (from floor level) of all building
users. Includes areas such as gymnasiums, workshops, and
storage areas where activities of the building users may result in
disturbance of ACM not normally within reach from floor level.
ACCESS (B)
Frequently entered maintenance areas within reach of
maintenance staff, without the need for a ladder. Includes:
frequently entered pipe chases, tunnels and service areas or
areas within reach from a fixed ladder or catwalk, i.e., tops of
equipment, mezzanines.
ACCESS (C)
EXPOSED
Areas of the building above 8'0" where use of a ladder is required
to reach the ACM. Only refers to ACM materials that are exposed
to view, from the floor or ladder, without removing or opening
other building components such as ceiling tiles, or service access
doors or hatches. Does not include infrequently accessed service
areas of the building.
ACCESS (C) Areas of the building which require the removal of a building
CONCEALED component, including lay-in ceilings and access panels into solid
ceiling systems. Includes rarely entered crawl spaces, attic
spaces, etc. Observations are limited to the extent visible from
the access points.
ACCESS (D)
Areas of the building behind inaccessible solid ceiling systems,
walls, or mechanical equipment, etc., where demolition of the
ceiling, wall or equipment, etc., is required to reach the ACM.
Evaluation of condition and extent of ACM is limited or
impossible, depending on the surveyor's ability to visually
examine the materials in Access D.
3. ACM Debris
Debris from Friable ACM
The presence of fallen ACM is noted separately from the presumed friable ACM
source (sprayed fireproofing, thermal insulation, texture, decorative or acoustic
finishes or mechanical insulation) and is referred to as DEBRIS.
Debris from Damaged Non-Friable ACM
The presence of fallen ACM, from damaged non-friable ACM, is reported
separately from the non-friable ACM source. Only fallen non-friable ACM, that
has become friable, is reported as DEBRIS.
The identification of the exact location or presence of DEBRIS on the top of
ceiling tiles is limited by the number of observations made and the presence of
building components such as ducts or full height walls that obstruct observations.
Workers are advised to be watchful for the presence of DEBRIS prior to
accessing, or working in proximity to, mechanical insulation or above ceiling
areas of buildings with ACM, regardless of the reported presence or absence of
DEBRIS.
4. Action Matrix and Action Descriptions
The Asbestos Management Program requires the following responses:


Immediate clean-up of DEBRIS that is likely to be disturbed;
The removal, repair or enclosure of friable ACM in POOR or FAIR
condition where continued deterioration will result in DEBRIS that is likely
to be disturbed.
The following factors shall be considered in making site-specific
recommendations for compliance with the regulation, and for the practical
implementation of asbestos management:
3. ACM in POOR condition is not routinely repairable.
If an abatement action is necessary, removal is the recommended action
(enclosure is a viable option in unusual circumstances).
4. Mechanical insulation in FAIR condition will be repaired or removed
based on the following general recommendations, applied on a case by
case basis.
Repair ACM mechanical insulation found in FAIR condition in ACCESS
(B) or ACCESS (C) EXPOSED areas.
Remove ACM mechanical insulation found in FAIR condition in ACCESS
(B) and ACCESS (C) EXPOSED areas, where future damage to the
ACM is likely to occur.
5. ACM in GOOD condition present in ACCESS (A) can be managed by
surveillance, as long as it is not disturbed by future renovation,
maintenance or demolition. Proactive removal of the ACM in ACCESS
(A) will be considered where damage is possible by ongoing occupant
activity (accidental or intentional).
6. Non-friable or manufactured products are considered in the action matrix
as follows:
 Non-friable and manufactured products reported in POOR
condition, or friable DEBRIS resulting from the deterioration of
non-friable ACM, are treated as friable materials and the
appropriate Action, depending on accessibility, is determined
from the Action Matrix for friable ACM.
 For non-friable or manufactured products reported in GOOD
condition, Action 7 (surveillance) is recommended regardless of
Accessibility.
7. Remove all ACM from a particular area where small quantities of
asbestos are present and removal will negate the need for the use of the
Asbestos Management Program in that area.
The Action Matrix provided below establishes the recommended
asbestos control action. The ACTIONS are described in full following the
matrix.
ACTION MATRIX TABLE
FRIABLE ACM
CONDITION
ACCESS
GOOD
(A)
FAIR
DEBRIS
POOR
ACTION 5/71 ACTION 5/62 ACTION 3 ACTION 1
(B)
ACTION 7
(C)
exposed
ACTION 7
ACTION 6/53 ACTION 3 ACTION 1
ACTION 6
ACTION 4 ACTION 2
(C)
concealed
ACTION 7
ACTION 7
ACTION 4 ACTION 2
(D)
ACTION 7
ACTION 7
ACTION 7 ACTION 7
1
If material in ACCESS (A)/GOOD condition is not removed ACTION 7 is
required.
2
If material in ACCESS (A)/FAIR condition is not removed ACTION 6 is required.
3
Remove ACM in ACCESS (B)/FAIR condition if ACM is likely to be disturbed.
ACTION 1 Immediate Clean-up of Debris That is Likely to be Disturbed
Restrict access that is likely to cause a disturbance of the ACM
DEBRIS and clean up ACM DEBRIS immediately. Utilize correct
asbestos procedures. This action is required for compliance with
regulatory requirements. The surveyor should immediately notify
the Regional Asbestos Coordinator of this condition.
ACTION 2 Entry Into Areas With ACM Debris - Type 2 Precautions
At locations where ACM DEBRIS can be isolated in lieu of
removal or cleaned up, use appropriate means to limit entry to the
area. Restrict access to the area to persons utilizing Type 2
asbestos-work precautions. The precautions will be required until
the ACM DEBRIS has been cleaned up, and the source of the
DEBRIS has been stabilized or removed.
ACTION 3 ACM Removal Required for Compliance
Remove ACM for compliance with regulatory requirements. Utilize
asbestos procedures appropriate to the scope of the removal
work.
ACTION 4 Access into Areas Where ACM is Present and Likely to be
Disturbed by Access - Type 2 Precautions
Use Type 2 asbestos precautions when entry or access into an
area is likely to disturb the ACM. ACTION 4 must be used until
the ACM is removed (Use ACTION 1 or 2 if DEBRIS is present).
ACTION 5 Proactive ACM Removal
Remove ACM in lieu of repair, or at locations where the presence
of asbestos in GOOD condition is not desirable.
ACTION 6 ACM Repair
Repair ACM found in FAIR condition, and not likely to be
damaged again or disturbed by normal use of the area or room.
Upon completion of the repair work, treat ACM as material in
GOOD condition and implement ACTION 7. If ACM is likely to be
damaged or disturbed, during normal use of the area or room,
implement ACTION 5.
ACTION 7 Routine Surveillance
Institute routine surveillance of the ACM. Trained workers or
contractors must use appropriate asbestos precautions (Type 1,
Type 2 or Type 3) during disturbance of the remaining ACM.
5. Detection Limit of Bulk Analysis
Asbestos containing material, (ACM), is defined as any material found to contain
asbestos at or above the limit for an asbestos containing material, (ACM), set
provincially, as determined by the standard Polarized Light Microscopy method
for the analysis of bulk samples. The provincially regulated limits, or generally
accepted guidelines, to consider a material as an asbestos containing material,
(ACM), subject to asbestos in buildings regulation, is provided as follows:
MINIMUM CONCENTRATION TO CONSIDER
AS AN ASBESTOS CONTAINING MATERIAL
(BY PROVINCE)
PROVINCE/REGION
NEWFOUNDLAND
NOVA SCOTIA
PRINCE EDWARD ISLAND
NEW BRUNSWICK
ALBERTA
BRITISH COLUMBIA
1.0%
ONTARIO (includes part of National Capital Region) 0.5%
SASKATCHEWAN (no published concentration)
QUEBEC (includes part of National Capital Region) 0.1%
MANITOBA
Annex C - Appendix 2 - Contractor Notification and Acknowledgement
Form PWGSC-TPSGC 16
Annex C - Appendix 3 - Certificate of Training for Asbestos-Related Work
Form PWGSC-TPSGC 15
Annex C - Appendix 4 - Asbestos-Related Work Record
Form PWGSC-TPSGC 55
Annex C - Appendix 5 - Classification of Asbestos-Related Work
The following criteria shall be utilized in determining the classification of asbestos work.
TYPE 1 WORK






Installation or removal of a non-friable ACM with a hand tool.
Disturbance of a non-friable ACM with a powered tool equipped with a HEPA
dust collection device.
Removal of drywall materials where joint filling materials contain asbestos.
Removal or replacement of ten or less asbestos-containing compressed mineral
fibre type ceiling tiles.
Collecting samples of asbestos-suspect friable materials.
Working close to friable sprayed asbestos, where the material may be affected by
the work activities.
TYPE 2 WORK





Removal or replacement of more than ten asbestos-containing compressed
mineral fibre type ceiling tiles.
Entry into ceiling spaces, crawlspaces, pipe tunnels, etc., where friable asbestos
debris is present.
In British Columbia, removal of drywall installed before 1980.
Minor removal of friable ACM. Type 2 removal is limited to a maximum per work
period of:
 In British Columbia - 0.1 m2 surface area, or 3 lineal metres of pipe
insulation;
 In Quebec - 0.03 m2 of Debris;
 All Others - 1 m2 of surface area.
Repair of asbestos mechanical insulation. (No limit is imposed as to the amount
of repair permitted under Type 2 conditions.)
TYPE 3 WORK


More than minor removal or disturbance of friable ACM.
Use of a power tool on non-friable ACM without HEPA exhausted dust collection.



The spray application of an encapsulant or sealer to friable asbestos surfacing
materials.
Disturbance of the ductwork and air handling equipment serving or passing
through areas of buildings with sprayed asbestos fireproofing or insulation.
Repair, alteration or demolition of a boiler, furnace, kiln, or similar equipment with
asbestos-containing refractory.
Annex C - Appendix 6 - Work Procedures
TYPE 1 - Work Procedures
For locations of non-friable ACM, refer to the current version of the Asbestos Inventory and
Assessment Report.
NOTE: These Type 1 procedures assume the non-friable material can be removed with relatively
little loose dry dust released. Generation of debris is permissible as long as the debris can be well
wetted before being removed. If the work will release more than a trivial amount of dry loose dust,
do not proceed. The Regional Asbestos Coordinator will determine which of Type 1, 2 or 3
procedures are appropriate.
1.
Equipment
All equipment must be on site before proceeding.
1. Vacuum
Use of a vacuum is optional. Wet cleaning methods may be used in place of a
vacuum. If a vacuum is used it must be equipped with a high efficiency particulate
(HEPA) filter and all brushes, fittings, etc. The vacuum must only be opened in an
enclosure, following Type 2 procedures, or in a laboratory exhaust hood. The
vacuum exterior should be carefully wet cleaned after emptying. A HEPA filter is at
least 99.97% efficient in collecting a 0.3 micrometre particle.
2. Respirators
Use of a respirator is optional for Type 1 work. However, a respirator is strongly
advised for work on sheet flooring, any type of ceiling tile, any other work performed
overhead. Respirators shall be supplied by the employer upon request. The type of
respirator supplied shall be a half-face respirator with HEPA filter. Training in the
proper use of the respirator and qualitative fit testing shall also be provided.
Respirators must be NIOSH approved and acceptable to the Provincial Authorities
having jurisdiction. Respirators shall be used according to the written procedures
for use, provided to the worker during training sessions. Filters must be changed
after 24 hours of wear, or sooner if breathing resistance increases.
NOTE: Employees are required to undertake a medical evaluation as specified by
DP 059 - Health Evaluations - Safety and Health, PWGSC prior to being trained in
the proper use of respirators.
3. Protective Clothing
Reusable or disposable clothing may be used. Non-disposable clothing with visible
asbestos contamination shall be cleaned with a HEPA vacuum and laundered as
asbestos contaminated. Disposable clothing and respirator filters will be disposed of
as asbestos waste.
4. Other Equipment
 plastic sheet (0.15 mm (6 mil) polyethylene) - to serve as a drop sheet;
 pump sprayer with mister nozzle, or alternate method to wet material;
 labelled, yellow asbestos waste bags, 0.15 mm (6 mil) - for all asbestos
waste, disposable equipment, plastic, etc.;
 small tools and cleaning supplies - e.g., scouring pads, sponges, brushes,
buckets, etc.
2.
Other Protective Measures
1. Do not eat, drink or smoke in the work area.
2. On leaving work area, proceed to washroom and wash all exposed skin on hands
and face.
3.
Preparation
1. Before disturbing non-friable asbestos materials, (wherever practical) cover floor
and surfaces below work with polyethylene sheeting to catch debris.
2. Wherever dust on a surface is likely to be disturbed, remove with HEPA vacuum or
damp cloth.
4.
Execution
1. Removal of Vinyl Asbestos Floor Tile
1. Do not use electric powered scrapers.
2. Start removal by wedging a heavy duty scraper in seam of two adjoining
tiles and gradually force edge of one tile up and away from floor. Do not
break off pieces of tile, but continue to force balance of tile up.
3. Continue removal of tiles using hand tools, removing tiles intact wherever
possible. When adhesive is spread heavily or is quite hard, it may prove
easier to force scraper through tightly adhered areas by striking scraper
handle with a hammer using blows of moderate force while maintaining
scraper at 25° to 30° angle to floor. When this technique does not loosen
tile, removal can be simplified by heating tile thoroughly with a hot air gun
until heat penetrates through tile and softens the adhesive.
4. As each tile is removed, place into asbestos waste receptor. Do not break
into smaller pieces.
5. After removal of a small area, scrape up adhesive remaining on floor with a
hand scraper until only a thin smooth film remains. Where deposits are
heavy or difficult to scrape, a hot air gun may be used. Deposit scrapings in
the asbestos waste disposal bag. Do not dry scrape surface pieces of tile
that remain adhered. Do not use powered electric scrapers.
6. On completion of the area, vacuum clean floor with HEPA vacuum or wet
mop. Dispose of the mop head as contaminated waste.
2. Removal of Asbestos-Containing Sheet Flooring
1. Remove binding strips or other restrictive mouldings. Workers shall wear air
purifying respirator fitted with high efficiency filter, and coveralls, at all
times.
2. Make series of cuts 100 mm to 200 mm (4" to 8") apart through top layers
and about halfway through felt backing, parallel to wall.
3. Start at end of room furthest from door and pry up corner of strip,
separating top sheet from backing layer. Pull top layer back upon itself
slowly and evenly, and half backing and top layers should pull free. After it
is removed, roll up strip face out into tight roll, tape or tie securely, and
place into asbestos waste receptor. Wet the asbestos felt underlay
remaining on floor as soon as exposed.
4. Continue with successive strips. Avoid walking on exposed asbestos felt.
Seal asbestos waste receptors when filled. Remove maximum of three
strips before wet scraping exposed felt underlay.
5. Remove remaining adhered underlay by wet scraping. Soak area with
water applied by sprayer. Allow water to penetrate felt. Scrape off
remaining material. Maintain material wet by applying more water. Place
scrapings in asbestos waste receptor.
6. Continue this procedure alternately removing top sheets and then wet
scraping felt, three strips at a time. Be careful not to walk on stripped floor.
7. When whole floor has been cleaned of asbestos felt, allow it to dry and
vacuum up any dirt with a HEPA vacuum or wet mop. Do not dry sweep.
Dispose of the mop head as contaminated waste.
8. Thoroughly clean tools and equipment with a damp cloth before returning to
regular service. Dispose of cloth as contaminated waste.
3. Installing, Cutting or Drilling Non-Friable Asbestos Materials
1. Work using power tools not fitted with HEPA filter dust collectors, must not
be performed as Type 1 work.
2. Where possible wet all materials to be disturbed.
3. Immediately place waste in asbestos waste receptor. Clean area frequently
during work with HEPA vacuum or by wet methods.
4. At completion of work, drop sheets that will be reused must be cleaned with
HEPA vacuum or by wet methods.
5. Drop sheets that will not be reused must be disposed of as asbestos waste.
4. Removal of Other Non-Friable Asbestos Materials
1. Type 1 procedures apply only to materials which can be removed intact, or
in sections, without producing a pulverized or powdered waste. This
method is most applicable to asbestos-cement board products, acoustic
ceiling tiles, gaskets, etc.
2. Where possible wet all material to be disturbed.
3. Undo fasteners necessary to remove material. Whenever possible remove
asbestos cement panels intact. Break only if unavoidable. If broken, wet
freshly exposed edges.
4. Where sections are adhered to the substrate, wet material and use hand
scraping to remove adhering material.
5. Place removed material into asbestos waste receptor. Clean surrounding
surfaces and asbestos work area frequently with HEPA vacuum or with wet
methods (i.e., damp cloth that is disposed of as asbestos waste after
cleaning).
6. Drop sheets shall be disposed of as asbestos waste.
5.
Waste Transport and Disposal
1. Place waste into asbestos labelled disposal bag, seal with tape, clean the exterior
of the bag with a clean cloth, and place into a second clean bag, also to be sealed
with tape. Use a barrel, fibre drum, or cardboard or wooden box in place of the
second bag when the asbestos waste material is likely to tear the inner bag. Seal
the outer container.
2. Place waste containers in storage area for holding asbestos waste. Containers shall
be labelled and assigned exclusively for asbestos waste.
3. Prepare waste for disposal in compliance with provincial regulations. The Property
Manager will arrange for disposal.
TYPE 2 - Work Procedures
For locations of asbestos materials, refer to the current version of the Asbestos Inventory and
Assessment Report.
1.
Equipment
Equipment required for the work must be on-site before proceeding.
1. Vacuum
An asbestos-approved vacuum (HEPA filtered), equipped with brushes, fittings, etc.
Vacuum must not be opened except by a fully protected worker within a Type 2
enclosure. The vacuum exterior shall be carefully wet cleaned after emptying. A
HEPA filter is at least 99.97% efficient in collecting a 0.3 micrometre particle.
2. Respirators
Workers within the work area shall wear approved respirator. Respirators and filters
will be provided by the employer, and individually assigned to workers. Respirator
shall be a half-facepiece respirator with high efficiency filters. Respirators must be
NIOSH approved and acceptable to the Provincial Authorities having jurisdiction.
Respirators shall be kept in position throughout the entire time the worker is in the
area of the work, from first disturbance of a ceiling tile or asbestos material, until the
final cleaning of the area and bagging of waste is complete. Change filters after 24
hours of wear or sooner if breathing resistance increases.
3. Protective Clothing
All workers shall wear disposable coveralls with attached elasticized hood.
Coveralls should be worn with the hood in place at all times. Coveralls may be
vacuumed or wet wiped clean for reuse, for a maximum of 8 hours cumulative wear.
Suit and head cover shall remain in place until worker leaves work area or the
enclosure is dismantled. Boot covers or dedicated boots are recommended.
4. Other Equipment
 plastic sheet (0.15 mm (6 mil) polyethylene) - to erect a total enclosure or to
serve as drop sheet;
 wood framing or clips to support polyethylene sheeting, as appropriate to
work area;
 tape - to fasten plastic enclosure to ceiling or to tape drop sheet to floor; ¾"
double-sided tape recommended for attaching polyethylene to T-bar ceiling;
 labelled asbestos waste bag 0.15 mm (6 mil) - for all asbestos waste,
disposable suit, plastic for disposal, etc.;
 pump sprayer containing water with wetting agent to wet asbestos as
necessary (dilute wetting agent as per manufacturer's recommendations);
 asbestos warning signs;
 cleaning supplies - e.g., scouring pads, sponges, brushes, buckets, etc.;
 insulation repair supplies (lagging compound, cloth, PVC covers);
 encapsulating sealer, for brush or airless spray application.
2.
Other Protective Measures
1. Do not eat, drink or smoke in the work area.
2. On leaving work area, proceed to washroom and wash all exposed skin on hands
and face.
3.
Scheduling of Work
1. Schedule work when occupants are absent. If persons are present, do not start
work.
2. If work above ceiling is required on an emergency basis, and the area is occupied,
ensure that client department(s) advise occupants to vacate area until work is
complete and clearance is given to return.
4.
Preparation
1. Shut down ventilation systems to and from the work area. Seal over all ventilation
openings, diffusers, grilles, etc., with plastic and tape.
2. Where practical, clear areas of movable furnishings or equipment. This should
include anything that occupants may wish to use during work period. Any
furnishings or equipment not removed shall be adequately covered and sealed
using 0.15 mm (6 mil) polyethylene and tape. The intent of the protection is to
provide an airtight envelope to protect the articles from airborne dust or splashed
debris.
3. Post signs or barrier tape, appropriate to the work area, to indicate asbestos hazard
and requirement for protective clothing for anyone entering the space.
4. For small rooms, cover walls with plastic such that the complete room becomes the
work area. For larger rooms, erect enclosure of 0.15 mm (6 mil) polyethylene, of
suitable dimensions to enclose the work area, and scaffolds and ladders required to
gain access. If a suspended ceiling is present, the enclosure shall extend to the
ceiling line. The enclosure shall be as airtight as conditions permit, and will include
the provision of a double overlapping flap at the entrance. The floor of the work
area shall be a layer of 0.15 mm (6 mil) polyethylene sealed to the plastic walls of
the enclosure.
5. Don protective clothing and respirator prior to removing ceiling tile or disturbing pipe
jacketing or sprayed fireproofing.
5.
Execution
1. To remove fireproofing or texture plaster, saturate with amended water solution,
using a pump sprayer. Do not remove the asbestos material until the material is
thoroughly wetted to the substrate. Do not use water where electrical hazard exists.
2. To remove pipe insulation, first wet any area of damage, then carefully cut jacket.
Keep insulation surface wetted by mist of water with wetting agent. Remove
insulation in large sections and place immediately in disposal bag. After large
pieces have been removed, saturate debris on mechanical equipment and clean all
exposed surfaces with abrasive pads, sponges, cloths, etc.
3. To repair pipe insulation, use drop sheet under area of work to aid clean-up of any
dislodged material. Plastic enclosure is not required. Mist any exposed insulation to
wet surface and apply lagging paint and canvas or PVC jacketing as required.
4. For removal of suspended ceiling tiles (where asbestos debris is present on top of
tiles or equipment to be accessed), remove the first tile carefully and vacuum all
surfaces. Vacuum the upper surface of each subsequent tile prior to removal. Store
tiles in the work area.
5. Remove dust and loose friable material likely to be disturbed in the process of doing
the work, with a HEPA vacuum or by damp wiping.
6. When asbestos material is removed, all pieces should be placed directly into 0.15
mm (6 mil) polyethylene bags as they are removed. Avoid dropping material to floor
wherever possible. After bulk removal is complete, wet wash the exposed surface.
7. Frequently, and at regular intervals during the work, clean up dust and waste in the
work area by wet mopping, placing in disposal bags, or by HEPA vacuuming.
8. After completion of removal, seal exposed ends of fireproofing, texture plaster, or
mechanical insulation with heavy layer of encapsulating sealer. Apply sealer coat to
surfaces from which asbestos material was removed.
9. At completion of work, decontaminate equipment, tools and materials used in the
work area by wet cleaning or HEPA vacuum.
10. Dispose of drop sheets and enclosures by wetting the polyethylene, then folding
into disposal bags. Do not reuse drop sheets or enclosures.
11. Before leaving work area, decontaminate shoes and protective clothing by using
HEPA vacuum or damp wiping. When protective clothing is to be disposed of, it
shall be decontaminated as above and placed in labelled disposal bags. Workers
shall vacuum all exposed skin, suit and respirator, and proceed to nearest
washroom to wash hands and face.
6.
Waste Transport and Disposal
1. Place waste into asbestos labelled disposal bag, seal with tape, clean the bag, and
place into a second clean bag, also to be sealed with tape. Use a barrel, fibre drum,
or cardboard or wooden box in place of the second bag when the asbestos waste
material is likely to tear the inner bag. Seal the rigid outer container.
2. Place waste containers in storage area for holding asbestos waste. Containers shall
be labelled and assigned exclusively for asbestos waste.
3. Prepare for waste disposal in compliance with provincial regulations. The Property
Manager will arrange for disposal.
TYPE 3 - Work Procedures
Type 3 procedures are not included in the standard work procedures due to the requirement for
the development of specific procedures for the site and for the particular circumstances.
Glove Bag Work Procedures
1.
Equipment
All equipment must be on site before proceeding with the work. Note that these procedures
are primarily based on the use of Safe-T-Strip polyvinyl chloride movable glove bags. (Only
the Safe-T-Strip glove bag is permitted for use in Ontario.) If the single use polyethylene
glove bags permitted in some other jurisdictions are used, it should be understood that they
are for use at one location only, and cannot be moved or used elsewhere.
NOTE: If single use polyethelene glove bag is used Section 5 - Execution, shall be replaced
by manufacturer's recommended procedures.
1. Glove Bag
Prefabricated, 0.25 mm (10 mil) minimum thickness polyvinyl-chloride bag with
integral 0.25 mm (10 mil) thick polyvinyl-chloride gloves and elasticized port. Bag
shall be equipped with reversible double-pull double throw zipper on top. Bag must
incorporate internal closure strip if it is to be removed from pipe for reuse
elsewhere. Provide size and configuration appropriate for insulation to be removed.
The bag must be disposed of once filled. Bag shall not be emptied and reused.
2. Securing Straps
Reusable nylon straps at least 25 mm (1") wide with metal buckle for sealing ends
of bags around pipe and/or insulation.
3. Water Sprayer
Garden reservoir type, low velocity, capable of producing mist or fine spray with
water-containing wetting agent. Wetting agent shall be diluted as per
manufacturer's recommendations.
4. Respirators
Workers using glove bag must wear approved respiratory protection. Respirators
and filters must be provided by the employer, and individually assigned to workers.
Respiratory protection must be equal to, or exceed, protection of half-face respirator
with high efficiency filters. Respirators must be NIOSH approved and acceptable to
the Provincial Authorities having jurisdiction. Respirators shall be kept in position
from the time the worker is attaching bag to pipe until final cleaning of the pipe and
bagging of waste is completed. Filters shall be changed after 24 hours of wear or
sooner if breathing resistance increases.
5. Protective Clothing
Workers shall wear disposable coveralls with attached elasticized hood. Coveralls
and hood shall remain in place until worker completes cleaning of pipe. Suit may be
cleaned for reuse or disposed of as asbestos waste.
6. Other Equipment
 labelled asbestos waste bags 0.15 mm (6 mil) - for all asbestos waste in
glove bag, disposable suit, cleaning materials, etc.;
 asbestos warning signs;
 wire saw - saw with flexible serrated wire blade and handles to allow use
inside glove bag;
 knife with fully retractable blade for use inside glove bag;
 plastic sheet (4 mil polyethylene) to cover exposed or damaged section of
pipe prior to attaching glove bag;
 tape-to fasten plastic to pipe if required;
 cleaning supplies e.g., scouring pads, sponges, brushes, buckets, etc.;
 HEPA vacuum, for evacuating air from bag prior to removing bag from pipe.
A HEPA filter is at least 99.97% efficient in collecting a 0.3 micrometre
particle.
2.
Other Protective Measures
1. Do not eat, drink or smoke in the work area.
2. On completing clean-up of work area, use HEPA vacuum or wet cloth to clean
hands, face, respirator and boots. Remove protective equipment and proceed to
nearest washroom to wash all exposed skin on hands and face.
3.
Scheduling of Work
1. Schedule work when occupants are absent. If persons are present, do not start
work.
4.
Preparation
1. Where practical, clear area below pipe of moveable furnishings or equipment.
Provide scaffold as required to reach pipe.
2. Post an asbestos warning sign at all entrances to room in which the procedure is
being used. If necessary use rope or tape barriers to separate work area.
3. Segregate the area of asbestos work, from other parts of the building required to
remain in use by using polyethylene walls or barrier tape.
4. Shut off and seal all diffusers, vents and other openings to ventilation and exhaust
systems in the room with polyethylene secured with tape.
5. Cover all items or equipment located in the designated work area with polyethylene
when items or equipment cannot be cleaned in the case of a spill. Tape the
polyethylene in place. The polyethylene should cover a width equal to the height of
the pipe from the floor, with a minimum width of 3.6 m (12 feet), where required.
6. Seal all openings and voids in the vicinity of the glove bag operation with one layer
of polyethylene secured with tape.
7. Check condition of pipe insulation where work will be performed. If the pipe
insulation has minor isolated damage, mist surface and patch with tape. If damage
is more extensive, wrap pipe with plastic and "candy stripe" it with duct tape first. If
pipe insulation is severely damaged and cannot be simply repaired, glove bag is not
appropriate. (Use Type 2 Procedures.)
8. Pre-clean with HEPA vacuum or wet methods any loose material on surface of pipe
or any material on the floor. If significant amount of material is on floor, Type 2
procedures may be required for clean-up. (See Type 2 Procedures.)
9. Place necessary tools in bottom of glove bag.
5.
Execution
1. Zip the bag onto the pipe and seal each end to the pipe with the securing straps. Do
not pull the bag tightly to the ends - a small amount of slack allows better room to
work within the bag. If a vertical bag is in use, ensure lower strap passes through
plastic grommet and cloth tab on zipper.
2. Place hands into gloves and use necessary tools (wire saw, utility knife, wire
cutters) to remove insulation from pipe. Arrange insulation in bottom of bag to
obtain full capacity of bag. Roll metal jacketing carefully to minimize ripping or
puncturing of the bag.
3. Insert nozzle of spray pump into bag through valve and wash pipe and interior of
upper section of bag thoroughly. Use one hand to aid washing process. Wet
surface of insulation in lower section of bag and any exposed ends of asbestos
insulation remaining on pipe.
4. Prior to removing bag from the pipe, wash the top section of the bag and tools
thoroughly. Insert nozzle of HEPA filtered vacuum into bag through the elasticized
valve and evacuate air from bag. Seal the closure strip, remove the vacuum nozzle
and straps, and remove the bag. Re-install and seal in new location before
reopening closure.
5. If bag is to be moved along the same pipe, loosen securing straps, move bag, reseal to pipe using double-pull zipper to pass hangers. Repeat insulation removal
operation.
6. If during use the glove bag is ripped, cut or opened in any way, cease work and
repair opening before continuing work. All spilled material must be cleaned up and
removed with a HEPA vacuum or wet cleaning.
7. To remove bag after completion of insulation removal, thoroughly wash top section
8.
9.
10.
11.
12.
6.
of bag and tools and seal internal zip-lock closure. Place tools in one glove, pull
hand out inverted, twist to create a separate pouch, tape inside-out glove at two
separate locations 1" apart to seal pouch. Remove inside-out glove and tools by
cutting between the tape seals.
Place glove pouch and tools into the next clean glove bag to be used. Alternately,
place the tool pouch into water bucket, open pouch underwater and clean tools,
then allow to dry.
Prior to disposal of bag, evacuate the bag with a HEPA vacuum. Pull a 0.15 mm (6
mil) polyethylene bag over glove bag before removing from pipe. Remove securing
straps. Unfasten zipper. Seal glove bag and seal 0.15 mm (6 mil) polyethylene bag.
After removal of bag ensure pipe is clean of all residue. If necessary, after removal
of each section of asbestos, vacuum all surfaces of pipe, using HEPA filtered
vacuum equipment, or wipe with wet cloth.
Seal all surfaces of freshly-exposed pipe with encapsulating sealer to tack-down
any residual dust. Cover exposed ends of any remaining asbestos insulation with
lagging cloth or tape.
Before leaving work area, a worker shall decontaminate shoes and protective
clothing by using HEPA vacuum or damp wiping. When protective clothing is to be
disposed of, it shall be decontaminated as above and placed in labelled disposal
bags. Workers shall vacuum all exposed skin, suit, respirator and hair (after
removing hood) and proceed to nearest washroom to wash hands and face.
Waste Transport and Disposal
1. Place waste containers in storage area for holding asbestos waste. Containers shall
be labelled and assigned exclusively for asbestos waste.
2. Prepare waste for disposal in compliance with provincial regulations. The Property
Manager will arrange for disposal.
Asbestos Work Procedures
Emergency Asbestos Work Procedures
Emergency asbestos procedures shall be implemented when required in order to protect those
undertaking the work, as well as to protect all others from, or limit exposure to, airborne asbestos.
Procedures indicated shall be followed as closely as possible, in the event of an emergency
situation.
Procedures for asbestos work, required as an immediate response to floods, pipe breaks, ceiling
collapses, or other emergencies that affect asbestos materials, are as follows:
1.
2.
3.
4.
Clear area of all occupants.
Construct enclosure around area if time permits.
Shut down ventilation system serving area.
Worker performing repair shall wear protective respirator and disposable suit. If normal
work clothes are worn they must be disposed of if visibly contaminated.
5. Use drop sheet under work, if possible, to minimize clean-up.
6. Perform emergency repair with minimum disturbance of asbestos.
7. Obtain asbestos equipment and perform clean-up of visible material. Use HEPA filtered
vacuum or wet cleaning. Dispose of all cleaning supplies as contaminated waste.
8. The worker should wipe off or vacuum disposable clothing and footwear. Proceed to
washroom to wash face and hands.
9. Notify the Property Manager regarding the asbestos disturbance, before allowing
unprotected persons to enter the area. The Property Manager will contact the Regional
Asbestos Coordinator to determine if additional precautionary measures are to be
implemented. The Regional Asbestos Coordinator will arrange for removal, clean-up or
repair of the asbestos material.
10. The Regional Asbestos Coordinator shall investigate the extent of asbestos disturbance,
will determine additional actions to be undertaken and will determine if a hazard
investigation under the Canada Occupational Safety and Health Regulation is
appropriate.
Bulk Sample Collection Procedures
1. Sample the material when the area is not in use. Only those persons needed for
sampling should be present in the immediate area.
2. Spray the material with a light mist of water to prevent fibre release during sampling. Do
not disturb the material any more than necessary.
3. Materials of different appearance should be sampled separately. Mechanical insulation
must be sampled separately on all systems, tanks, vessels, etc. Sample both the straight
sections of pre-formed insulation and the insulating cement typically present at elbows,
fittings, etc. (unless visually identified as fibreglass).
4. Collect the sample by penetrating the entire depth of the material, as the insulation may
have been applied in more than one layer or covered with paint or other protective
coating.
5. The use of a respirator is recommended for all sampling. Depending on the condition of
the material, significant amounts of airborne fibres can be generated during sampling.
6. If pieces of material break off during sampling, the contaminated area must be cleaned
up with a HEPA vacuum cleaner or by wet cleaning. Any debris generated must be
placed in plastic bags, labelled, sealed and disposed of as asbestos waste.
7. Place samples in labelled plastic bags with a zip-lock closure or in sealed plastic vials.
Samples shall be identified with the following information:
 Sample Number;
 Building;
 Room Number;
 Date of Sampling;
 Name of Sampler;
 Source of sample, e.g., Cold Water Pipe, Cold Water Fitting, etc.
8. Temporarily seal any openings created to collect the sample, (for example, with tape,
paint or metal foil tape wrapped completely around the pipe). Advise the Property
Manager or Regional Asbestos Coordinator.
9. Analysis must be performed by the Health Canada Laboratory or by a laboratory
accredited by the National Voluntary Laboratory Accreditation Program (NVLAP). Contact
the Regional Asbestos Coordinator for a list of acceptable laboratories.
Respirator Fitting, Inspection, Cleaning and Disinfecting
Notes for Air Purifying Half-Facepiece Respirators
WARNING: This respirator does not supply oxygen. It must not be used in or for: oxygen deficient
atmospheres (less than 19.5%); poorly ventilated areas or enclosed spaces such as tanks or
small rooms; abrasive blasting or firefighting; or for protection against contaminants excluded or
not covered by the applicable Approval Label.
Respirators must be approved for protection against asbestos. Check for NIOSH certification.
1.
Respirator Fitting
Persons required to wear respirators must first pass a qualitative fit-test administered
according to the current version of CSA standard Z-94.4. The fit-test should be repeated
yearly.
2.
Inspection Items Prior to Each Use
1. Examine facepiece for:
 dirt;
 cracks, tears or holes;
 distortion and inflexibility;
 cracks or breaks in filter holders, worn threads and missing gaskets.
2. Examine head straps for:
 breaks or tears;
 loss of elasticity;
 broken or malfunctioning buckles and attachments.
3. Examine valves for:
 detergent residue, dust or other material on valves or valve seats;
 cracks, tears or distortion in the valve material;
 missing or defective valves or valve covers.
4. Examine filter for:
 proper filter for protection against asbestos (High Efficiency Particulate);
 incorrect installation, loose connections, missing or worn gaskets or cross
threading;
 cracks or dents in filter housing.
5. Leak-checks:
Perform the following tests on each donning:


3.
negative pressure test: cover inlets to filters, breathe in and hold breath;
respirator should be drawn to face for minimum of ten seconds (if not,
check exhalation valve and fit);
positive pressure test: cover exhalation valve cover and puff out slightly and
hold breath; respirator should slightly pressurize and still hold seal (if not,
check inhalation valves and fit).
Respirator Cleaning and Disinfecting
1. Remove filters and disassemble facepiece. Discard or repair defective parts.
2. Wash components in warm water (50°C - 60°C) with mild detergent, using a brush.
Cleaning and disinfectant solutions are available from respirator manufacturers.
3. Thoroughly rinse components in clean, warm water.
4. Air dry or hand dry components with a clean, lint-free cloth.
5. Reassemble respirator and test to ensure that all components are working properly
(see above). Be careful to check that valves are not lost in the cleaning.
4.
Filter Cartridge Handling and Replacement
1. Filters can be reused until an increase in breathing resistance is noted. Under
typical Type 2 conditions, filter cartridges should last a minimum of 24 hours. Inlet
side of filter cartridge to be reused shall be sealed on the inlet side with tape for
storage.
2. When no longer usable, filter cartridges will be sealed on the inlet side with tape,
and disposed of as contaminated waste.