JetSpray Six-Step Installation Process
™
This simple step-by-step
guide will help you install
JetSpray Thermal Insulation.
Recommended Materials
and Equipment
It’s easy to install JetSpray Thermal Blow-in
Core Items:
Insulation. This guide will provide you with
• JetSpray Thermal Insulation
• Portable generator
• Blowing wool machine with
required hoses and vacuum
collector box
• Scrubber
a list of necessary materials and equipment,
and six steps to successfully install JetSpray
Thermal Insulation. Please review this guide in
full before starting installation. If you have any
questions, please call Knauf Service at
1-800-825-4434. ext. 8727.
• Water pump, tank and
supply line
• Vacuum with required hoses
• JetSpray nozzle
• Personal Protective Equipment
(PPE)
Additional Items:
• Extra spray tips
• Extension cords
• Water bucket
• Ladder/Scaffold
• Densi-Checker™
• Hose reducers and
couplers
• Portable digital scale
(Fish Scale) 10 lb. min.
• Batt insulation
• Portable moisture meter
• Portable lighting, as needed
• Netting
• Vented vacuum bag/vented
bag for measurement
• Staples and stapler
• Poly film
• Duct tape
• Brooms
• EcoSeal™ Plus or other
air sealant
• Knauf mobile app
1
JOBSITE
PREPARATION
• Sweep and remove construction debris, dust, dirt
and other trash from the work area.
• Net any unbacked walls.
• Mask and cover electrical boxes, HVAC duct/
return openings and windows.
• Remove or properly secure any nails or staples
that will impede or damage the scrubber.
• Air seal any gaps, joints and or penetrations in
the wall cavities; chink or backfill any large gaps
or cracks prior to air sealing. Knauf recommends
using EcoSeal Plus™ as a high-performance air
sealing system.
The JetSpray™ System from
Knauf Insulation.
Designed for quick and easy installations that save you time and
money, JetSpray allows you to easily insulate difficult-to-reach
areas, and provides a wide range of benefits:
• Cost-efficient thermal protection
• Bright, clean-looking finish
• Grade I installations
• Formaldehyde-free
• Drywall can typically be installed within 24 hours
• Less product waste
• Efficient way to meet or exceed minimum code requirements
2
EQUIPMENT
CHECK AND
SETUP
• Set up blowing wool machine (see equipment settings).
• Set up water pump (see equipment settings).
• Attach hoses and supply lines to appropriate equipment.
• Attach spray nozzle to fiber feed line and water supply line.
In cold weather, protect liquid supply lines from freezing.
• Plug scrubber into power source.
• Attach vacuum suction attachment (VSA) to vacuum line.
• Conduct Flow and Feed Rate checks.
3
SPRAYING
• Stand 36"– 40" from wall holding nozzle at a 10° downward angle toward bottom of cavity.
• Engage fiber flow and then start the water supply once fiber is flowing.
• From bottom of cavity, move side-to-side in an upward direction.
• Within 10" from the top of cavity, step closer, 18"–24," and fill top of cavity.
• In a downward motion, fill in any voids or gaps in the cavity just filled and move to next
cavity and repeat.
4
SCRUBBING
AND VACUUMING
• Scrub the face of stud cavities, removing excess material.
Make sure to repair any voids or gaps created during
scrubbing.
• Vacuum excess material regularly into the collector box at the
blowing machine.
• Introduce re-feed into the hopper while maintaining an adequate
supply of virgin material in the hopper.
5
FIELD TESTING–
DENSITY AND
MOISTURE
• Randomly conduct density checks to ensure proper
coverage and density.
First check should occur after filling four to five
cavities, and then random afterwards.
Follow instructions that came with the
Densi-Checker.™
Make adjustments accordingly.
• Conduct three to four moisture checks (beginning,
middle and end) with the moisture meter to ensure you
are installing between 18–22%.
• It is recommended that a moisture check be made
prior to drywall or vapor retarder installation, ensuring
a moisture reading <15%.
6
SITE AND
EQUIPMENT
CLEANUP
• Sweep and remove any excess material from site.
• Remove window, HVAC duct/return and electrical
box coverings.
Installation Machine Settings:
Adapt based on initial equipment settings.
Air Pressure:___________________________________________________
_____________________________________________________________
Water Pressure: ________________________________________________
Notes: _______________________________________________________
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
THE ULTIMATE
WALL SYSTEM
To build the ultimate wall, combine
JetSpray with ECOSEAL Plus™ Air
Sealant to form a total air barrier
within the building envelope.
The ultimate wall
provides better
comfort, energy
efficiency and
sustainability.
Become an authorized
installer for both by visiting
ecosealplus.knaufinsulation.us
Knauf Insulation, Inc.
One Knauf Drive
Shelbyville, IN 46176
Sales and Marketing...... (800) 825-4434, ext. 8485
Technical Support........... (800) 825-4434, ext. 8727
Fax.............................. (317) 398-3675
Information.................... [email protected]
www.knaufinsulation.us