ETS INSTALLATION (TYPICAL)
-An inspection by a Municipality approved inspector is required (per UCC code).
-ALL EQUIPMENT SHOWN WILL BE PROVIDED AND INSTALLED BY MEMBER EXCEPT WHERE NOTED.
B
A
C
D
E
K
Finished Grade
F
G
H
J
A
Non-controlled (load) meter position.
B
Service entrance cable (where
Cooperative service drop is overhead).
I
C
2 position meter base (provided by
the Cooperative and installed by the member). May be used for overhead or
underground service drops.
D
Controlled (heating load) meter position.
E
Service entrance cable to controlled (heating) panel. 200 amp maximum capacity.
F
Service entrance cable to non-controlled panel. Sized to load.
G
Grounding conductor. #6 copper to approved ground. (This wire will ground both
panels, bonding will be between the panels; external of either panel).
(Do not connect to meter base).
H
Ground rods (2 required) (5/8" galvanized steel or 1/2" copper - 8' long) and ground
clamps for #6 copper (see H).
I
Ground rod separation - 6' minimum.
J
Service cable riser conduit (where Cooperative service drop is underground). (Provided
and installed by the member).
K
Meter base height - 5' to 5'6".
Revised 1/11/16 by BF