Instructions to Install Retrofit Kit
6/7000 Machine
**TURN POWER OFF OF MACHINE BEFORE INSTALLATION**
READ ALL INSTRUCTIONS BEFORE STARTING INSTALLATION
Retrofit kit contents:
PART NAME
PCBA, GG Retro VMC2
QUANTITY
1
PART NUMBER
10-0253-00
Cable, Retrofit Display
Cable, Retrofit Keypad 1
(Pin2 = Key)
Cable, Retrofit Keypad 2
(Pin12 = Key)
Cable, MDB Extension
1
1
11-1700-01
11-1700-02
1
11-1700-03
1
11-1700-06
Cable, 6/7000 Micromech
1
11-0187-21
Cable, 6/7000 Power Ext
1
11-0188-21
Front Cover, Retrofit
1
05-0150-02
Hardware Kit
1
05-0169-01
Panel, Retrofit Display
Assembly
Lens, Display Retrofit
6/7000 VMC
Retrofit Sensor Assembly
1
05-0091-00
1
05-0153-00
1
10-0073-67
Clamp Kit Assembly
1
05-0157-00
CheckMate Label
1
15-0082-04
Tools Needed:
Additional Accessories Needed:
Screwdriver, Philips
Pliers, needle nose
MDB Coin Changer
MDB Bill Validator
1. Fully open the vending machine door and set door stop to hold door open. Then
slide the peripheral panel out to gain access to electronics and connections.
Figure 1.
2. Remove cover, pictured in Figure 2, encasing the Vending Machine control board
(VMC) by removing the four retaining screws. You will no longer need this
cover.
Figure 2
2
3. Remove display board by removing the three retaining screws. Refer to Figure 3.
Save Screws.
Figure 3
4. Remove the coin return mechanism assembly as follows referring to figure 4:
Remove the E Snap Clip with needle nose pliers and lift pusher bar off axel and
slip from push button shaft. Save E snap clip.
Remove four screws retaining the coin-return push button bracket and remove
bracket. Save screws.
Remove the base sheet metal box/bell crank assembly by removing the three
mounting screws. Save screws. Save all brackets and Return Push Button.
Figure 4
5. Remove Coin Changer by disconnecting the coin changer and then lifting it
vertically and with horizontal motion towards technician, away from keyhole
mounting studs. Set Coin Changer aside.
3
6. Remove the Bill Acceptor. Remove the cassette and set aside. Remove four
screws, holding the bezel to the VM mounting bosses, two on the right and two on
the left side of the validator respectively. Set bill acceptor and screws aside.
Note: the screws for the bill validator are specific for this purpose.
7. Referring to figure 5, locate the two flat-ribbon flex cables exiting the rear of the
selection keypad. Remove the extension cables that are connected to them.
Figure 5
8. Referring to figure 6, remove the 10 capped screws on the rear side of the
selection panel.
Figure 6
4
9. Slide the selection keypad bezel apart from the front of the drawer and carefully
remove the Red/Silver plastic display cover. Replace this with the Retrofit
display cover, 05-0090-01 after its protective plastic cover is removed from both
sides. Make sure the cover is oriented like the below figure 7 when looking at
front of machine with the door shut.
Figure 7
Slide the selection keypad bezel flush to drawer front and re-fasten at the rear
with the screws 3-10. When replacing screws 1 and 2, remove the ferrules (caps)
and save them.
10. Referring to figure 8, remove the cover of the High Voltage PCB. Next, locate
cable originally connected to P1 (extending from the Jones plug). This is a 3 pin
connector with pin 2 keyed. Connect 11-0188-21 to this cable with the male pins
and the other end into P1 of the small PCB. You can now replace the cover to
this PCB.
MM Power
Cable
Figure 8
10. Reposition the Green-Yellow
ground wire as shown. This new hole
is to the right and above the current
one. Assure it is fastened securely.
5
Figure 9
11. If using MDB: Install the MDB Bill Acceptor. Attach using the 4 screws saved
from step 6 above. Install the MDB Coin Changer. Re-install the coin return button,
brackets and bell crank assembly removed in step 4.
12. There are two flat ribbon cable male connectors coming directly from the
selection keypad. These connectors are attached to the new control board using two
extension cable assemblies, 11-1700-02 and 11-1700-03. Connect these cables as
follows:
13. Mount the retrofit display assembly. Remove the protective cover on the display
before installing. Locate the top two studs used to mount the previous display board,
attach the display assembly at its two upper holes using the ferrules that were saved
from Step 8. Place the ferrules over the two studs and screw the assembly in. The
display should match up with the window from the display cover already installed
from Step 8.
Figure 10.
6
14. The new control board can now be installed. Remove existing control board.
Slide the new control board on to the four right pegs and secure.
Figure 11.
15. Connections:
Connect the display to J2 of the retrofit control board using the Retrofit Display
cable assembly.
The power will be connected using the original connector. In order for this cable
and the motor cable to reach and plug into the new control board, you will have to
undo the cable harness that guides these cables. This harness is located near the
back of the pull out door. It is a small white “hook”. Simply, lift the end facing the
front of the machine and slide the cable sleeve out.
Figure 12.
7
This will allow the power and motor connectors to plug into the board. The power
connector will be a five (5) pin connector with pin 4 keyed. This will plug into J19
of the new control board.
The motor connector will be the 18 pin connector with pin 11 keyed. This will plug
directly in J17 of the new control board.
The MDB coin mech and bill validator will be connected to each other. There will
be a 2 x 3 connector coming off of their connecting cable. This will plug directly
into the cable assembly included in the kit, 11-1700-06. The other end of this
extension cable will plug directly into J4 of the new control board. Make sure that
the coin mech and validator are connected to each other.
There is a switch located on the front of the pull out door. Its connector is a two pin
0.156” spacing connector. This will plug into the new control board at location J8.
Connect the keypad extension cables to the control board. Connect 11-1700-02 to
Control board connector J13. Connect 11-1700-03 to Control board connector J10.
The DEX header, J5, will be connected to the panel mounted connector on the front
cover. Be careful when plugging this in. This should be the last connection you
make on the board.
After all these connections are made, you may carefully line up the front cover with the
standoffs that are on the control board. Once this is done, you may screw the front
cover on with the screws included in the kit, 08-0632-00.
8