Remaining Works - incomplete list schedule -

GERDA Topical Session
Remaining Works
- incomplete list schedule -
K.T.Knöpfle
MPI Kernphysik, Heidelberg
ktkno@mpi-hd.mpg.de
GERDA Collaboration Meeting at LNGS
10 - 12 November 2008
sites
cryostat & cryogenic infrastructure
water tank*
GERDA building & platform
clean room* & commissioning lock
slow control & DAQ
FE & test of full readout chain
general infrastructure
* with muon veto
11 Nov 08 @ LNGS
Remaining Works
K.T.Knöpfle
2
general infrastructure
nov dec
removal ex-proof doors
fast water drainage pit
ventilation system
tender
installed
LN2 & LAr storage tanks
authorization for
water drainage
11 Nov 08 @ LNGS
jan
feb mar apr may
!
!
!
!
!
!
Remaining Works
K.T.Knöpfle
3
GERDA building
nov dec
jan
feb mar apr may
electrical plant
safety plant
water plant
Rn monitor
electronics cabinet
install racks, etc
gates to access galleries
access to manifold
access to filter unit @ 6m
asap
asap
asap
floor cover
desks, chairs
asap
asap
11 Nov 08 @ LNGS
Remaining Works
K.T.Knöpfle
4
water tank – tests & works inside
nov dec
jan
feb mar apr may
close gap cryostat-WT
hydrostatic test
WT cleaning
cryostat insulation *
muon veto installation **
water distribution line ***
water plant commissioning
fill water tank
* check for potential problems with XPS
** detailed procedure and schedule available
*** design such that it can be installed by GERDA – cleanliness!
11 Nov 08 @ LNGS
Remaining Works
K.T.Knöpfle
5
water tank – tests & works inside
nov dec
jan
feb mar apr may
close gap cryostat-WT
hydrostatic test
WT cleaning
cryostat insulation
muon veto installation
water distribution line
water plant commissioning
fill water tank
11 Nov 08 @ LNGS
Remaining Works
K.T.Knöpfle
6
cryostat & cryogenic infrastructure
nov dec
jan
feb mar apr may
cryostat cleaning
cut hole in HEB700 beam
manifold & active cooling
insulation vacuum system
cryogenic infrastructure
exhaust gas heater
support for heater
relevant milestones:
cleanroom commissioned
dto. ventilation system
(dto. fast water drainage)
DN600 shutter installed
!!!
LAr filling
water tank filling
11 Nov 08 @ LNGS
Remaining Works
K.T.Knöpfle
7
clean room & commissioning lock
nov dec
jan
feb mar apr may
clean room construction
commissioning lock
d&b ad hoc support
d&b glove box
d&b dewar, cryogenics
assemble lock
string test at Munich
transport to LNGS
installation in cleanroom
cabling
……………
plastic muon veto install.
earliest
or later – after main lock installation
11 Nov 08 @ LNGS
Remaining Works
K.T.Knöpfle
8
FE & full readout chain test
nov dec
jan
feb mar apr may
3-channel pcb v1
fabrication
bench test milano
test with SUB milano
test at LNGS ?
test w string at Munich
3-channel pcb v2
design
fabrication
test …….
11 Nov 08 @ LNGS
?
Remaining Works
K.T.Knöpfle
9
last NOT least
►►►
nov dec
jan
slow control & DAQ
feb mar apr may
to be ready
slow control
network, firewall, etc
FE control
DAQ phase I
link to slow control/db
available
asap
test system for string tests
11 Nov 08 @ LNGS
Remaining Works
K.T.Knöpfle
10
The END
11 Nov 08 @ LNGS
Remaining Works
K.T.Knöpfle
11