Application Report
SLUA917 – August 2018
Start Guide for the BQ27546-G1
Onyx Ahiakwo, David Dolt
ABSTRACT
The bq27546 is a flash based battery gauge that uses TI’s patented impedance track technology for
predicting the remaining capacity of battery amongst other functionalities. This documents helps users
walk through the process of setting up the gauge, identifying a chemical id, performing a learning cycle
and creating a golden file ready for production.
1
2
3
4
Contents
Introduction ................................................................................................................... 1
Gauge set up and Golden file generation ................................................................................ 1
Summary .................................................................................................................... 10
References .................................................................................................................. 10
List of Figures
1
EVM set-up ................................................................................................................... 2
2
Non-auto detection of device firmware by bqstudio ..................................................................... 3
3
Auto Detected Device ....................................................................................................... 4
4
Programming the firmware on the gauge using bqstudio .............................................................. 4
5
Exporting a gg file. ........................................................................................................... 5
6
Chem id programming
7
Searching for a parameter in data memory .............................................................................. 7
8
Logging the registers ........................................................................................................ 8
9
Learning cycle. ............................................................................................................... 9
10
Extracting the golden image .............................................................................................. 10
......................................................................................................
6
Trademarks
All trademarks are the property of their respective owners.
1
Introduction
For first time users, the complexity of the impedance track algorithm might seem overwhelming, but in
actuality, setting up the gauge and getting it fully functional is a straight forward and simple process. This
start guide is geared towards the first time user to facilitate coming up to speed and getting the gauge fully
functional.
2
Gauge set up and Golden file generation
The processes of getting the gauge fully functional are summarized below with elaborate details following
thereafter:
1. Set up the EVM following the instructions listed in the EVM User Guide.
2. Make sure the gauge has the most up-to-date G1 firmware on the chip which is 0546_2_01(your board
will come with this firmware already loaded).
3. Perform voltage, current and temperature calibration as described in the evm user guide if using your
board. If using the EVM, there will be no need for calibration as the EVM already comes factorycalibrated.
SLUA917 – August 2018
Submit Documentation Feedback
Start Guide for the BQ27546-G1
Copyright © 2018, Texas Instruments Incorporated
1
Gauge set up and Golden file generation
4.
5.
6.
7.
8.
2.1
www.ti.com
Identify your chem id and program the identified chem id on the gauge
Configure the data flash for your specific application.
Perform a learning cycle.
Extract the golden file
Evaluate the accuracy of the gauge.
EVM set up
For EVM setup, you need a power supply or charger, a second power supply or battery, an electronic
load, an EV2300 or EV2400, bqstudio software and the necessary connecting cables. Please see the
EVM user guide here for step by step details on getting the board set up as shown in Figure 1. Connect
jumpers to J3 and J4 for 10k pull ups on the I2C SDA and SCL lines, place a jumper on pin 1 and 2 of J6
(ON) to ensure the chip is powered on .
Figure 1. EVM set-up
2.2
Verify the firmware is most recent
Upon startup of bqstudio, the device should be automatically detected. If that isn’t the case, and a screen
as seen in Figure 2 appears, then you need to check to make sure your device is properly powered on
and that your gauge IC isn't damaged. Also, check to make sure you are connected to the I2C port on the
EV2300 and on the EVM.
2
Start Guide for the BQ27546-G1
SLUA917 – August 2018
Submit Documentation Feedback
Copyright © 2018, Texas Instruments Incorporated
Gauge set up and Golden file generation
www.ti.com
Figure 2. Non-auto detection of device firmware by bqstudio
If the device is auto detected upon booting your screen will look like Figure 3.
SLUA917 – August 2018
Submit Documentation Feedback
Start Guide for the BQ27546-G1
Copyright © 2018, Texas Instruments Incorporated
3
Gauge set up and Golden file generation
www.ti.com
Figure 3. Auto Detected Device
If you need to update the firmware on the device, the process of updating the firmware is as follows:
• - Select gauge from the device type as shown in Figure 2 . Then select the 0546_2_01bq27546G1.bqz from the next window that pops up.
• - Then go to the programming window as shown in Figure 4 and browse to where the srec is stored on
your computer. Select it, and then hit the program button. This process will update the firmware on the
chip.
Figure 4. Programming the firmware on the gauge using bqstudio
2.3
Calibrate Voltage, Current, Temperature, CC and Board Offset.
The EVM user guide (section 9) contains the description of how to calibrate the voltage, current and
temperature measurements as well as the offsets. If you are using your own boards, then calibration is
required. If there is a need to avoid calibrating each board, 20 boards should be calibrated and the
average of each of the calibration parameters obtained should be programmed in the corresponding
section of the gauge data flash. It is easier to make edits to the gauge parameters using the gg file rather
than making edits via bqstudio. You can extract a gg file by clicking the data memory section of bqstudio
and then click export button and then save the file to a desired location. See Figure 5. A gg file can also
be programmed on the device by clicking the import button. . The evm board already comes pre-calibrated
so if running tests on an EVM, there is no need to perform calibration.
4
Start Guide for the BQ27546-G1
SLUA917 – August 2018
Submit Documentation Feedback
Copyright © 2018, Texas Instruments Incorporated
Gauge set up and Golden file generation
www.ti.com
Figure 5. Exporting a gg file.
2.4
Chem id Identification and programming
The chem id is a look up table which the gauge uses for determination of state of charge during
initialization. The gauge also uses this table as part of the IT algorithm to predict remaining capacity. This
table consists of the open circuit voltage profile of the battery as well as the resistance profile of the
battery which is split up into grid points that corresponds to different state of charges. Both the OCV and
resistance tables have the temperature dependent components which aids gauge performance at different
temperatures. It is important that the chem id programmed on the gauge was either generated by TI for
that battery or a close match to an existing chem id in TI data base for batteries has been identified using
our online chem id identification tool- gpcchem. The chem id identification requires running a relaxdischarge-relax (rel-dis-rel) test while logging data using the gauge’s GUI (bqstudio) and then using gpc
chem tool with the logged data to identify a close match. If there is no match, then the cells have to be
sent to TI for characterization and chem id generation. Contact a local field applications engineer if cells
have to be sent to TI. Once a chem id has been identified or created, it has to be programmed on the fuel
gauge. You can select the new found chem id and program it using the chemistry plug-in of bqstudio as
shown in Figure 6 below. Note that if an incorrect chem id is used, learning cycle may never successfully
complete and state of charge prediction will never be accurate.
SLUA917 – August 2018
Submit Documentation Feedback
Start Guide for the BQ27546-G1
Copyright © 2018, Texas Instruments Incorporated
5
Gauge set up and Golden file generation
www.ti.com
Figure 6. Chem id programming
2.5
Configuration of the data flash for your specific application
In order to have learning cycle successfully complete, certain parameters in the data memory of the gauge
need to be configured specific to the application and the battery typ. At a minimum, these parameters are
design capacity, taper current, discharge (dsg) current threshold, charge (chg) current threshold, quit
current, and terminate voltage. You can search for these parameters in data memory by typing in the
filter/search box as seen in Figure 7:
6
Start Guide for the BQ27546-G1
SLUA917 – August 2018
Submit Documentation Feedback
Copyright © 2018, Texas Instruments Incorporated
Gauge set up and Golden file generation
www.ti.com
Figure 7. Searching for a parameter in data memory
Design Capacity
The design capacity should be set to the value specified in the cell manufacturer’s data sheet as the
nominal capacity. If there are n cells in parallel, the design capacity will be n x nominal capacity of 1cell
Taper Current
Most battery chargers have a +/-10% error in taper current threshold at which point the charger cuts off
charging. It is very important to set the taper current programmed in the data flash of the gauge slightly
higher than the taper current threshold of the charger. This will ensure that the gauge detects the battery
is fully charged before the charger cuts off charge. For example, if your charger taper current is 50mA, it is
recommended to set the taper current in data flash greater than 50mA. A good value to use will be 70mA.
Also, it is recommended that the taper current should be less than C/10 to ensure that the battery gets
properly fully charged.
Discharge (Dsg) Current Threshold
This is the current threshold above which the gauge detects that it is in discharge mode. It is an unsigned
integer as the gauge has the ability to detect the direction of current flow. This value should be set lower
than the charge termination taper current. In the previous example, if charge termination taper current is
set to 70mA, a good value for discharge current threshold is 45mA
Charge Current Threshold
This is the current above which the gauge detects that it is in charge mode. This value should be set lower
than the charge termination taper current as well. As with the previous example, a good value for charge
current threshold would be 40mA.
Quit Current Threshold
This is the threshold that determines that the gauge is in relax mode. This mode is very important because
this is where the gauge takes OCV readings which are used for Qmax calculations. It is recommended
that the quit current be less than C/20 and must be less than the discharge and charge current threshold.
In the previous example mentioned, a good value to use will be 10mA.
Terminate Voltage
This is the voltage where the gauge should detect that the battery is at 0% SOC. For learning cycle
purposes, this should be set to the minimum voltage of the battery as specified in the manufacturer’s data
sheet. After learning cycle is completed, this value can be adjusted upwards if there is a need for the
gauge to report 0% at a higher voltage.
SLUA917 – August 2018
Submit Documentation Feedback
Start Guide for the BQ27546-G1
Copyright © 2018, Texas Instruments Incorporated
7
Gauge set up and Golden file generation
2.6
www.ti.com
Learning Cycle
The learning cycle is needed for the gauge to update the total chemical capacity (Qmax) and the
resistance (Ra) tables of the cell in data flash. It is also needed for the update status which the gauge
controls to indicate that the learning cycle has been completed. Before the learning cycle is started,
extract a gg file and start logging the registers by clicking the start log button in the register window as
shown in Figure 8and save the file at a desired location. The purpose of the log file is for debug purposes
in case learning isn’t successful. It will enable the understanding of the failure.
Figure 8. Logging the registers
The learning cycle as seen in Figure 9 is as follows:
1. Enable impedance track (0x21), issue a reset command (0x41). Update status will go from 00 to 04.
2. Discharge the cell to empty and let it relax for 5 hours.
3. Charge the cells to full ensuring that the current goes below taper current and fc bit gets set, then let it
relax for two hours. Qmax updates at this point and update status goes to 05. At least 90% of the cells
design capacity has to go into the battery for qmax to learn. The learning cycle must be done at room
temperature.
4. Discharge the cells to empty using the typical discharge rate of your application. It must be between
c/5 to c/10 rate otherwise learning will fail. Resistance tables will get updated during this discharge
cycle.
5. Let the cells relax for 5 hours. Update status would have changed to 06 before the end of relaxation
indicating learning cycle was successful. If Update status is not 06 at the end of learning, go back to
step 3 and repeat the process one more time.
8
Start Guide for the BQ27546-G1
SLUA917 – August 2018
Submit Documentation Feedback
Copyright © 2018, Texas Instruments Incorporated
Gauge set up and Golden file generation
www.ti.com
Figure 9. Learning cycle.
2.7
Extract the golden file
The golden file can be extracted by clicking the golden image tab and then clicking the create image files
button if one of the srec , bqfs or dffs field box is checked. see Figure 10The srec and bqfs both contain
the instruction flash (IF) and dataflash (DF) while the DFFS contains just the data flash content which is
why it is a smaller in size than either of the aforementioned files and is the preferred file format for insystem gauge programming.
SLUA917 – August 2018
Submit Documentation Feedback
Start Guide for the BQ27546-G1
Copyright © 2018, Texas Instruments Incorporated
9
Gauge set up and Golden file generation
www.ti.com
Figure 10. Extracting the golden image
2.8
Evaluate for accuracy.
Cycle the gauge one more time to evaluate for accuracy. Follow the blog here to perform gauging
accuracy calculations
3
Summary
In summary, the process of setting up the gauge, while may be lengthy, is a very straight forward and
simple process. If this guide is followed step by step, the gauge will be fully functional and configured in
less than a week.
4
References
•
•
•
10
bq27546 EVM With Pack Side, Single-Cell Impedance Track™ Technology Evaluation Module User
Guide
Technical Reference Manual SLUUB74
How accurate is your battery fuel gauge part 2/2
Start Guide for the BQ27546-G1
SLUA917 – August 2018
Submit Documentation Feedback
Copyright © 2018, Texas Instruments Incorporated
IMPORTANT NOTICE FOR TI DESIGN INFORMATION AND RESOURCES
Texas Instruments Incorporated (‘TI”) technical, application or other design advice, services or information, including, but not limited to,
reference designs and materials relating to evaluation modules, (collectively, “TI Resources”) are intended to assist designers who are
developing applications that incorporate TI products; by downloading, accessing or using any particular TI Resource in any way, you
(individually or, if you are acting on behalf of a company, your company) agree to use it solely for this purpose and subject to the terms of
this Notice.
TI’s provision of TI Resources does not expand or otherwise alter TI’s applicable published warranties or warranty disclaimers for TI
products, and no additional obligations or liabilities arise from TI providing such TI Resources. TI reserves the right to make corrections,
enhancements, improvements and other changes to its TI Resources.
You understand and agree that you remain responsible for using your independent analysis, evaluation and judgment in designing your
applications and that you have full and exclusive responsibility to assure the safety of your applications and compliance of your applications
(and of all TI products used in or for your applications) with all applicable regulations, laws and other applicable requirements. You
represent that, with respect to your applications, you have all the necessary expertise to create and implement safeguards that (1)
anticipate dangerous consequences of failures, (2) monitor failures and their consequences, and (3) lessen the likelihood of failures that
might cause harm and take appropriate actions. You agree that prior to using or distributing any applications that include TI products, you
will thoroughly test such applications and the functionality of such TI products as used in such applications. TI has not conducted any
testing other than that specifically described in the published documentation for a particular TI Resource.
You are authorized to use, copy and modify any individual TI Resource only in connection with the development of applications that include
the TI product(s) identified in such TI Resource. NO OTHER LICENSE, EXPRESS OR IMPLIED, BY ESTOPPEL OR OTHERWISE TO
ANY OTHER TI INTELLECTUAL PROPERTY RIGHT, AND NO LICENSE TO ANY TECHNOLOGY OR INTELLECTUAL PROPERTY
RIGHT OF TI OR ANY THIRD PARTY IS GRANTED HEREIN, including but not limited to any patent right, copyright, mask work right, or
other intellectual property right relating to any combination, machine, or process in which TI products or services are used. Information
regarding or referencing third-party products or services does not constitute a license to use such products or services, or a warranty or
endorsement thereof. Use of TI Resources may require a license from a third party under the patents or other intellectual property of the
third party, or a license from TI under the patents or other intellectual property of TI.
TI RESOURCES ARE PROVIDED “AS IS” AND WITH ALL FAULTS. TI DISCLAIMS ALL OTHER WARRANTIES OR
REPRESENTATIONS, EXPRESS OR IMPLIED, REGARDING TI RESOURCES OR USE THEREOF, INCLUDING BUT NOT LIMITED TO
ACCURACY OR COMPLETENESS, TITLE, ANY EPIDEMIC FAILURE WARRANTY AND ANY IMPLIED WARRANTIES OF
MERCHANTABILITY, FITNESS FOR A PARTICULAR PURPOSE, AND NON-INFRINGEMENT OF ANY THIRD PARTY INTELLECTUAL
PROPERTY RIGHTS.
TI SHALL NOT BE LIABLE FOR AND SHALL NOT DEFEND OR INDEMNIFY YOU AGAINST ANY CLAIM, INCLUDING BUT NOT
LIMITED TO ANY INFRINGEMENT CLAIM THAT RELATES TO OR IS BASED ON ANY COMBINATION OF PRODUCTS EVEN IF
DESCRIBED IN TI RESOURCES OR OTHERWISE. IN NO EVENT SHALL TI BE LIABLE FOR ANY ACTUAL, DIRECT, SPECIAL,
COLLATERAL, INDIRECT, PUNITIVE, INCIDENTAL, CONSEQUENTIAL OR EXEMPLARY DAMAGES IN CONNECTION WITH OR
ARISING OUT OF TI RESOURCES OR USE THEREOF, AND REGARDLESS OF WHETHER TI HAS BEEN ADVISED OF THE
POSSIBILITY OF SUCH DAMAGES.
You agree to fully indemnify TI and its representatives against any damages, costs, losses, and/or liabilities arising out of your noncompliance with the terms and provisions of this Notice.
This Notice applies to TI Resources. Additional terms apply to the use and purchase of certain types of materials, TI products and services.
These include; without limitation, TI’s standard terms for semiconductor products http://www.ti.com/sc/docs/stdterms.htm), evaluation
modules, and samples (http://www.ti.com/sc/docs/sampterms.htm).
Mailing Address: Texas Instruments, Post Office Box 655303, Dallas, Texas 75265
Copyright © 2018, Texas Instruments Incorporated
Was this manual useful for you? yes no
Thank you for your participation!

* Your assessment is very important for improving the work of artificial intelligence, which forms the content of this project

Related manuals

Download PDF

advertising