INSTALLATION GUIDELINES

GALVANIZED ROOF EDGE

PRE-DRILL HOLES

RAKE

EAVE

ROOF EDGE ROOF EDGE

Begin installation along the eaves, starting at a corner and working your way around, overlapping each succeeding piece of drip edge by 2-3 inches.

After the eave drip edge has been installed, apply the underlayment and/or ice-water barrier.

Once the underlayment has been installed, apply the drip edge to the rakes.

Make box corners by wrapping the rake edge around the eave metal.

Depending on local conditions, roof edge should be nailed every 16" - 24".

Over Driven 1/32"

CAUTION!

Working above grade is inherently dangerous, be sure that proper fall protection measures are in place.

When working with power tools and sheet metal, gloves and eye protection are absolutely required.

These installation guidelines are for use with typical or standard applications. Refer to SM-Rib installation guide for panel and flashing install details. It is always recommended to seek advice from a licensed professional, and to check with your local building inspector or building permit office for approvals and possible variations that may apply.

advertisement

Was this manual useful for you? Yes No
Thank you for your participation!

* Your assessment is very important for improving the workof artificial intelligence, which forms the content of this project

Related manuals

advertisement