M-system Mini-M M2ADS Instruction Manual
M-system Mini-M M2ADS is suitable for use in Class I, Div. 2, Groups A, B, C, and D or Non-Hazardous Locations only. It is suitable for Pollution Degree 2, Measurement Category II, and Installation Category II. It features reinforced insulation (input 1 or input 2 or output to power input: 300V) and basic insulation (input 1 or input 2 to output: 300V). It has a power input rating of 100 – 240V AC, 24V DC, 11 – 27V DC, or 110V DC and an operational range of 85 – 264V (90 – 264V for UL), 47 – 66 Hz, approx. 3 – 5VA for 100 – 240V AC, approx.
Advertisement
Advertisement
Mini-M
™
INSTRUCTION MANUAL
ADDER
BEFORE USE ....
Thank you for choosing M-System. Before use, please check contents of the package you received as outlined below.
If you have any problems or questions with the product, please contact M-System’s Sales Office or representatives.
■ PACKAGE INCLUDES:
Signal conditioner (body + base socket) .............................(1)
■ MODEL NO.
Confirm Model No. marking on the product to be exactly what you ordered.
■ INSTRUCTION MANUAL
This manual describes necessary points of caution when you use this product, including installation, connection and basic maintenance procedures.
POINTS OF CAUTION
■ NONINCENDIVE APPROVAL OPTION
• This equipment is suitable for use in Class I, Div. 2,
Groups A, B, C and D or Non-Hazardous Locations only.
• WARNING!
Before You Remove the Unit from Its Base
Socket or Mount It, Turn Off the Power Supply and Input
Signal for Safety.
• WARNING! – Explosion Hazard –
Substitution of Components May Impair Suitability for
Class I, Div. 2.
• WARNING! – Explosion Hazard –
Do Not Disconnect Equipment Unless Power Has Been
Switched Off or The Area is Known To Be Non-Hazardous.
• The equipment was evaluated for use in the ambient temperature and relative humidity as mentioned in ‘ENVI-
RONMENT’ section.
• The input and output wiring must be in accordance with
Class I, Div. 2 wiring methods and in accordance with the authority having jurisdiction for use in these hazardous locations.
■ CONFORMITY WITH EU DIRECTIVES OR UL
• This equipment is suitable for Pollution Degree 2, Measurement Category II (input, transient voltage 2500V) and
Installation Category II (transient voltage 2500V). Reinforced insulation (input 1 or input 2 or output to power input: 300V) and basic insulation (input 1 or input 2 to output: 300V) are maintained. Prior to installation, check that the insulation class of this unit satisfies the system requirements.
• Altitude up to 2000 meters.
• The equipment must be mounted inside a panel.
• The equipment must be installed such that appropriate clearance and creepage distances are maintained to conform to CE/UL requirements. Failure to observe these requirements may invalidate the CE/UL conformance.
MODEL
M2ADS
• The actual installation environments such as panel configurations, connected devices, connected wires, may affect the protection level of this unit when it is integrated in a panel system. The user may have to review the CE requirements in regard to the whole system and employ additional protective measures to ensure the CE conformity.
• Install lightning surge protectors for those wires connected to remote locations.
■ POWER INPUT RATING & OPERATIONAL RANGE
• Locate the power input rating marked on the product and confirm its operational range as indicated below:
100 – 240V AC rating: 85 – 264V (90 – 264V for UL),
47 – 66 Hz, approx. 3 – 5VA
24V DC rating: 24V ±10%, approx. 3W
11 – 27V DC rating: 11 – 27V, approx. 3W
110V DC rating: 85 – 150V (110V ±10% for UL), approx. 3W
■ GENERAL PRECAUTIONS
• Before you remove the unit from its base socket or mount it, turn off the power supply and input signal for safety.
■ ENVIRONMENT
• Indoor use.
• When heavy dust or metal particles are present in the air, install the unit inside proper housing with sufficient ventilation.
• Do not install the unit where it is subjected to continuous vibration. Do not subject the unit to physical impact.
• Environmental temperature must be within -5 to +55°C
(23 to 131°F) with relative humidity within 30 to 90% RH in order to ensure adequate life span and operation.
• Be sure that the ventilation slits are not covered with cables, etc.
■ WIRING
• Do not install cables close to noise sources (relay drive cable, high frequency line, etc.).
• Do not bind these cables together with those in which noises are present. Do not install them in the same duct.
■ AND ....
• The unit is designed to function as soon as power is supplied, however, a warm up for 10 minutes is required for satisfying complete performance described in the data sheet.
• With voltage output, do not leave the output terminals shortcircuited for a long time. The unit is designed to endure it without breakdown, however, it may shorten appropriate life duration.
5-2-55, Minamitsumori, Nishinari-ku, Osaka 557-0063 JAPAN
Phone: +81(6)6659-8201 Fax: +81(6)6659-8510 E-mail: [email protected]
EM-5088 Rev.7 P. 1 / 3
COMPONENT IDENTIFICATION
Fixing Screw
Model
Zero Adj.
Span Adj.
Body
ZERO
SPAN
Base Socket
Connection
Diagram
Specifications
M2ADS
INSTALLATION
Loosen the fixing screw at the front of the unit in order to separate the body from the base socket.
■ DIN RAIL MOUNTING
Set the base socket so that its DIN rail adaptor is at the bottom. Position the upper hook at the rear side of base socket on the DIN rail and push in the lower.
When removing the socket, push down the DIN rail adaptor utilizing a minus screwdriver and pull.
DIN Rail
35mm wide
Spring Loaded
DIN Rail Adaptor
■ WALL MOUNTING
Refer to “EXTERNAL DIMENSIONS.”
TERMINAL CONNECTIONS
Connect the unit as in the diagram below or refer to the connection diagram on the side of the unit.
■ EXTERNAL DIMENSIONS unit: mm (inch)
6 (.23)
DIN RAIL
35mm wide
2–4.2x5
(.17x.20)
MTG HOLE
6 (.24) deep
8
4 1
5
21.5 (.85) 10 (.39)
8–M3
SCREW
12
14 13
9
84 (3.31)
114 (4.49) [4 (.16)]
15 (.59)
23 (.91)
• When mounting, no extra space is needed between units.
■ CONNECTION DIAGRAM
INPUT 1
INPUT 2
+ 1
– 4
+ 5
– 8
9 +
12 –
13 U(+)
14 V(–)
OUTPUT
POWER
WIRING INSTRUCTIONS
■ SCREW TERMINAL
Torque: 0.8 N·m
■ SOLDERLESS TERMINAL
Refer to the drawing below for recommended ring tongue terminal size. Spade tongue type is also applicable.
Applicable wire size: 0.25 to 1.65 mm 2 (AWG 22 to 16)
Recommended manufacturer: Japan Solderless Terminal
MFG.Co.Ltd, Nichifu Co.,ltd
3.3 (.13) max mm (inch)
5-2-55, Minamitsumori, Nishinari-ku, Osaka 557-0063 JAPAN
Phone: +81(6)6659-8201 Fax: +81(6)6659-8510 E-mail: [email protected]
EM-5088 Rev.7 P. 2 / 3
CHECKING
1) Terminal wiring: Check that all cables are correctly connected according to the connection diagram.
2) Power input voltage: Check voltage across the terminal
13 – 14 with a multimeter.
3) Input: Check that the input signal is within 0 – 100% of the full-scale.
4) Output: Check that the load resistance meets the described specifications.
EQUATION
M2ADS
Output = K
1
× Input 1 + K
2
× Input 2
K
1
, K
2
: 0.10 to 2.00 specified when ordering
(0.40 ≤ K
1
+ K
2
)
Input 1, Input 2: 0 to 120%
Forcibly limited to 0% and 120% respectively when the signal is out of range.
ADJUSTMENT PROCEDURE
This unit is calibrated at the factory to meet the ordered specifications, therefore you usually do not need any calibration.
For matching the signal to a receiving instrument or in case of regular calibration, adjust the output as explained in the following.
■ HOW TO CALIBRATE THE OUTPUT SIGNAL
Use a signal source and measuring instruments of sufficient accuracy level. Turn the power supply on and warm up for more than 10 minutes.
1) ZERO: Apply the input signals which should lead the calculated result as 0%, and adjust output to 0%.
2) SPAN: [ K lead the calculated result as 100%, and adjust output to
100%.
1
+ K
2
≥ 1] Apply the input signals which should
[ K
1
+ K
2
< 1] Apply the input signals which should lead the calculated result as [100 × ( K
1
+ K
2
)]%, and adjust output to [100 × ( K
1
+ K
2
)]%.
3) Check ZERO adjustment again.
4) When ZERO value is changed, repeat the above procedure 1) – 3).
MAINTENANCE
Regular calibration procedure is explained below:
■ CALIBRATION
Warm up the unit for at least 10 minutes.
[ K
1
+ K
2
≥ 1] Apply the input signals which should lead the calculated result as 0%, 25%, 50%, 75% and 100%. Check that the output signal for the respective input signal remains within accuracy described in the data sheet.
[ K
1
+ K
2
< 1] Apply the input signals which should lead the calculated result as 0%, [25 × ( K
1
+ K
2
)]%, [50 × ( K
1
+ K
2
)]%,
[75 × ( K
1
+ K
2
)]% and [100 × ( K
1
+ K
2
)]%. Check that the output signal for the respective input signal remains within accuracy described in the data sheet. When the output is out of tolerance, recalibrate the unit according to the “AD-
JUSTMENT PROCEDURE” explained earlier.
LIGHTNING SURGE PROTECTION
M-System offers a series of lightning surge protector for protection against induced lightning surges. Please contact
M-System to choose appropriate models.
5-2-55, Minamitsumori, Nishinari-ku, Osaka 557-0063 JAPAN
Phone: +81(6)6659-8201 Fax: +81(6)6659-8510 E-mail: [email protected]
EM-5088 Rev.7 P. 3 / 3

Public link updated
The public link to your chat has been updated.
Advertisement