Von Duprin 9954 Installation instructions
Advertisement
Advertisement
*941365-00*
941365-00
Removable Hurricane Mullion
HH9954
1.
Adjust ball plunger for top and bottom fitting.
Adjust ball plunger out until ball is compressed when fitting is engaged with mullion. Once adjusted properly, lock-tite in place. See Figure 1.
Lock-tite when adjusted
Ball plunger 2.
Line up and install bottom mullion fitting with center of door opening and flush with closed doors. If threshold is used, it must be cut to fit around the bottom fitting. See Figures 2 and 3.
Expansion Anchor
(4 places)
Door
Door
Threshold
HILTI KB3
Supplied Nut
Adapter
Washer
HILTI KB3
Supplied Washer
(Not Required)
HILTI KB3
Stud
Door 3-1/2”
Figure 2
Drill Bit: 1/4” Dia
Min Hole Depth: 2”
(See Expansion
Anchor HILTI KB3
Instructions)
1-3/8”
Installation Instructions
Figure 1
1-3/8”
2”
3”
Figure 3
1/2”
Customer Service
1-877-671-7011 www.allegion.com/us
© Allegion 2018
Printed in U.S.A.
941365-00 Rev. 07/18-a
3. Line up and install top mullion fitting with center of door opening and flush with closed doors. If stop is less than 3-1/2” wide, a filler block must be provided by others. See Figure 4.
!
NOTE
Reinforcement for all sheet metal frames is to be supplied by frame manufacturer.
4. If required, cut mullion body from the top to provide clearance as shown in Figure 4. Be sure mullion is seated on bottom fitting.
5. Remove top mullion fitting and insert in top of mullion body. Slide mullion into place and replace mounting screws. Install top mullion clamp. See Figure 5.
1/4-20 x 3/8”
PPHMS
(2 places)
5/16-18 x 1-1/4”
FPHMS (4 places)
Reinforcement
1-1/4” clearance ref.
2-7/16”
(If required)
Cut mullion
1-1/4” less than this dimension
Figure 4
*Mullion sized to install with max engagement in 8’ opening.
Top clamp
6. Install strikes per exit device instructions.
Figure 5
Drop bottom end into place