Savant PKG-ESS200AEVAULTSE2-00 INCHARGE ESS SCHNEIDER - FREESTANDING DOUBLE Deployment Guide
Add to My manuals51 Pages
advertisement
Savant Power System Deployment Guide
Savant Power & Light™ app
Document Number:
Document Date:
Document Supports:
009-2140-00
April 2022 da Vinci 10.1 or higher
This document guides the installer through the complete process of configuring and deploying a Savant Power System, including:
– Wiring Savant Power Modules and breakers
– Creating a Savant Power & Light app Account and Home
– Scanning for Savant Power Modules and pairing them
– Adding and editing breaker panels and modules within the Savant Power & Light app.
– Adding a battery power source to automatically switch to during a power outage
– Creating Energy Scenes to control power usage off the grid
– Upload configuration to a Savant Power Director
Copyright © 2022 Savant Systems Inc.
45 Perseverance Way, Hyannis, MA 02601
Savantpower.com
| 508.683.2500
Savant Power® Panel Deployment Guide
Table of Contents
To access links to the topics within this document, click the corresponding entry in the table below.
11.5. Pair Added Savant Power Modules (Optional) ........................................27
5.1. Dual 20 Amp Relay Savant Power Module ..................................................6
5.2. 240V AC 2-Pole Savant Power Relay Module ............................................8
5.3 240V 60A Savant Power Relay Module ........................................................9
5.6. MicroGrid Three-Line Wiring Diagram ........................................................ 12
6.1. Configure Savant Power Module Channels ................................................ 14
Appendix B: Schneider ESS and Conext MiniPDP ......................................... 48
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 2 -
Appendix C: System Information Checklist .......................................................50
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
Important Safety Information - Read First
Before installing, configuring, or operating any equipment, Savant recommends that each dealer, integrator, installer, etc. access and read all relevant technical documentation. Savant Power technical documentation can be located by visiting Savantpower.com
. Vendor documentation is supplied with the equipment.
Read and understand all safety instructions, cautions, and warnings in this document and the labels on the equipment.
Safety Classifications In this Document
NOTE :
Provides special information for installing, configuring, and operating the equipment.
IMPORTANT!
CAUTION!
WARNING!
Provides special information that is critical to installing, configuring, and operating the equipment.
Provides special information for avoiding situations that may cause damage to equipment.
Provides special information for avoiding situations that may cause physical danger to the installer, end user, etc.
Electric Shock Prevention
ELECTRIC
SHOCK!
The source power poses an electric shock hazard that has the potential to cause serious injury to installers and end users.
ELECTRICAL
DISCONNECT :
The source power outlet and power supply input power sockets should be easily accessible to disconnect power in the event of an electrical hazard or malfunction.
Weight Injury Prevention
WEIGHT INJURY!
Installing some of the Savant equipment requires two installers to ensure safe handling during installation.
Failure to use two installers may result in injury.
Safety Statements
All safety instructions below must be read, understood, and carefully followed under all applicable circumstances when working with any Savant equipment.
1. Follow all input power ratings marked on product near power input!
2. If fuse replacement is required, replacement fuse should match fuse rating marked on the product.
3. Do not use equipment near water.
4. Clean only with dry cloth.
5. Do not block any ventilation openings or install near any heat sources such as heat registers, stoves, radiators, amplifiers, etc.
6. Refer all servicing to qualified service personnel. Servicing is required when any part of the apparatus has been damaged in any way, or fails to operate normally for any reason.
7. Use only attachments/accessories specified by the manufacturer, following all relevant safety precautions for any such attachments/accessories.
8. For applicable equipment, use the included power cord with the grounding prong intact to insure proper grounding of the device.
9. If the provided plug does not fit the desired outlet, contact a licensed electrician to replace the obsolete outlet.
10. Protect any power cord from being walked on, pinched, strained, or otherwise potentially damaged, especially at the outlet or device connections.
11. Disconnect any outlet powered apparatus from its power source during lightning storms or when unused for long periods of time.
12. To completely disconnect equipment from AC mains power, disconnect the power supply cord plug from the AC receptacle on the device.
13. For any hardwired or fixed in-wall apparatus, carefully follow all wiring diagrams and instructions. All electrical wiring and servicing should be performed by a properly licensed electrician.
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 3 -
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
1. Before You Begin
Read this document in its entirety before starting deployment of the product, and ensure that the following required items are available: iOS Device Running iOS 14.0 or Higher ......................................................................................................................................................................................
2. Deployment Steps
To successfully deploy a Savant Power Panel (Savant Power Modules and Director) using the Savant Power and Light app, follow the steps listed below.
This page can be used as a checklist to track progress as items are completed.
1. Install Director, Savant Power Modules, and Breakers..................................................................................................................................................................................
See
2. Complete On-Device Setup ....................................................................................................................................................................................................................................
See
3. Connect to Director V1 Hotspot ............................................................................................................................................................................................................................
See
4. Create Savant Power & Light Account and Home .........................................................................................................................................................................................
See
5. Discover devices .........................................................................................................................................................................................................................................................
See
6. Get Configuration from Director ...........................................................................................................................................................................................................................
See
7. Test Circuits ...................................................................................................................................................................................................................................................................
See Test Circuits
8. Configure Breaker Panels, Add and Pair Modules ..........................................................................................................................................................................................
See
9. Configure Current Monitors and Contactors ....................................................................................................................................................................................................
See
Energy Monitoring and Contactor Linking
10. Configure Dedicated Loads and Backed Up Loads ......................................................................................................................................................................................
See
11. Configure Energy Scenes ........................................................................................................................................................................................................................................
See
12. Upload Configuration to Director .........................................................................................................................................................................................................................
See
13. Confirm System Functionality ...............................................................................................................................................................................................................................
See
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 4 -
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
3. Gestures
The deployment of a Savant Power & Light app requires an iOS device. The following icons represent their respective gestures.
Tap Press and release (tap) a button or icon.
Press and
Hold
Swipe Left or
Right
Swipe Up or
Down
Press and hold a button or icon on the screen until a pop-up menu or other feature appears.
Press and swipe finger to the left or right.
Press and swipe finger up or down.
4. Third Party Documentation
This document assumes the installer has read all relevant 3rd party documentation. Read all manufacturer documentation for all 3rd party products in use; which may include, but is not limited to:
IMPORTANT!: For further information on 3rd party components, review the following documentation:
Schneider Fortress ESS
– eFlex Installation Manual
– Schneider Electric XW Pro inverter
– Generac Automatic Transfer Switch Manual
NOTES: For Savant Power Systems with Generator integration, locate the specific Installation & Operations manual for your generator and complete the generator installation process.
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 5 -
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
5. Wiring Diagrams
It is important to ensure the Savant Power Module™ and Director are installed and wired correctly. Review the wiring diagrams below and confirm that all proper physical installation has been completed before proceeding.
IMPORTANT NOTE: Any Savant Host used with a Schneider Energy Storage System or a generator must be backed up by a Universal Power Supply
(UPS).
5.1. 120V 20A Savant Power Dual Relay Modules (GPM-QP2R20120-21)
ARC Fault Breakers
Bluetooth To
Companion Modules
Savant Director+
IMPORTANT NOTES!
– The 120V 20A Dual Relay Modules switches on and off loads A and B.
– The main electrical panel contains ARC fault breakers. See
ARC fault breaker diagram.
– The diagram shows connections for both a plug-on neutral and pigtail neutral wire modules. Make connections according to the type of breaker being installed.
– Neutral and ground wires on both load centers must be common.
Load A Load B
The neutral on an ARC fault breaker can be either a pigtail wire, or plug-on neutral bus bar clip.
BREAKER
BREAKER
Connect a Gnd wire to each load
Savant Power® Panel Deployment Guide
009-2140-00 | 042522
Ground Bar
BREAKER
- 6 -
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
Standard non-ARC Fault Breakers
Bluetooth to
Companion Modules
Load A
Load B
Main Electrical Panel
Savant Director+
IMPORTANT NOTES!
– The 120V 20A Dual Relay Modules switches on and off
Loads A and B.
– The main electrical panel contains standard non-ARC fault
breakers.
– Neutral and ground wires on both load centers must be common.
BREAKER
BREAKER
BREAKER
Neutral
Bar
Ground Bar
Connect a Gnd wire to each load
Neutral
Bar
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 7 -
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
5.2. 240V 30A Savant Power Relay Modules (GPM-QP1R30240-21)
Savant Director+
Bluetooth to
Companion Modules
IMPORTANT NOTES!
– The 240V 30A Relay Module is used to switch loads that require 240V AC.
– A 2-pole 30 amp breaker supplies the 240V AC to the 240V
30A Relay Modules.
– Neutral and ground wires on both load centers must be common respectively.
240V AC Load
Main Electrical Panel Power Module Panel
2-POLE BREAKER
BREAKER
Neutral
Bar
L1
Ground Bar
L2
Neutral
Bar
Savant Power® Panel Deployment Guide
009-2140-00 | 042522
Neutral
Bar
Connect a Gnd wire to load
Ground Bar
Neutral
Bar
- 8 -
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
5.3. 240V 60A Relay Module (GPM-CP1R60240-21)
Load
240V AC
Neutral Bar
Main Distribution Panel
IMPORTANT NOTE!
– The 240V 60A Relay Module can accept up to a #4 AWG wire.
2-POLE BREAKER
STANDARD
BREAKER
STANDARD
BREAKER
Savant Power® Panel Deployment Guide
009-2140-00 | 042522
120V AC
Plug-on neutral bar
Phase A
Phase B
- 9 -
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
5.4. Powerlink Wiring Diagram
Main Electrical Panel
240V
Load
Bluetooth to
Companion Modules
Savant Power Director
IMPORTANT NOTES:
– The neutral wire, from the load wired through an arc fault circuit interrupter breaker, is connected to the neutral screw on the breaker.
– The neutral wire on the breaker will either be a pigtail wire, or a plug on neutral breaker connection.
– The neutral wire, from the load wired through a non-arc fault circuit interrupter breaker, is connected to the neutral bar in the panel.
– The Powerlink power supply can provide power for three Powerlink breakers.
– Two Powerlink breakers can be controlled by one
Savant Power Module:
Companion Module Panel
– Output A is wired to white low voltage wire on Powerlink breaker 1.
– Output B goes to white low voltage wire on Powerlink breaker 2.
Wire Nut Connections
POWERLINK
BREAKER
240V
LOADS
QO PL Power Supply
1 per 3, 40-60A
2-POLE BREAKERS
Neutral
Bar
To Gnd on loads
Ground Bar
To Gnd on loads
Neutral
Bar
Neutral
Bar
Ground Bar
Neutral
Bar
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 10 -
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
5.5. MicroGrid Communication Wiring Diagram
MICROGRID ATS
EFLEX BATTERY MODULES
LEGEND
WIRE DETAILS:
CAT5
MODBUS TCP/IP CAT5
IP CAT 5
STATIC SIGNAL TWISTED PAIR
STATIC SIGNAL TWISTED PAIR (RETURN)
AC4: (1) #14 AWG 90C MIN
RJ45 Pinout Converter
CAN Bus Terminator + Cap
Network Switch
2 x CAN/RS485
PORTS PER
MODULE
(RJ45 jack)
5 VDC
1 2 3 4 5 6 7 8
Power
From UPS
Xanbus 1
Power
9-24VDC
TERMINATOR
From component
AC/DC power supply plugged into local receptacle
To
Home Network
Director V1
Ethernet RS232
5 VDC
Savant Power Director
CT CONNECTIONS
11+ 22+ 3- 3+ 4- 4+
CT 1 CT 2 CT 3 CT 4
TO N1 + N2 INPUT
MICROGRID ATS
Reference High-Voltage
Three-Line for CT and VT locations
TO T1 + T2
MICROGRID ATS OUT
VT CONNECTIONS
+A- +B- +C-
CT CONNECTIONS
+1- +2- +3- +4- +5- +6- +7- +8-
Wifi
+
BLE
Adapter
GPIO
Pair Test Reset
From UPS
Bottom Enclosure within Director V1
From L1 AC CB 2
IN MDP
AC 4
VT1
N G
Wire Nut
To GND +
NTRL Bar in MDP
+9- +10- +11- +12- +13- +14- +15- N/A
From L2 AC CB 2
IN MDP
PS
G
L
12VDC
+
-
UPS
Output
5V 2A
12V 2A
Director
E-Net Switch
VT2
N G
AC 4
VT Black wire is for
NEUTRAL feed
To GND +
NTRL Bar in MDP
From L2 AC CB 2
IN MDP MDP = Main Distribution Panel
Xanbus 2
10/100
Ethernet
CONEXT GATEWAY
1 3 5 7 9 11 13 15 17 19 21 23 25
2 4 6 8 10 12 14 16 18 20 22 24 26
Wires stripped from
CAT 5 cable
INVERTER
AC SYNC XANBUS
BTS JU-1
+12V
JU-2
RPO
AUX
JU-3
COM
JU-4
TS OUT
JU-5
TS IN
TERMINATOR
250mA
#18 twisted pair
Bottom Right Corner of XW Pro Inverter
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 11 -
UTILITY
SOURCE
CONNECTIONS
N1 N2
LOAD
(UPPER)
CUSTOMER LOAD
T1
(LOWER)
T2
CONNECTIONS
MICROGRID ATS
Power and Control Tray
Auxiliary Contact
(on right side of ATS)
0 DC GROUND
194 +12VDC
23 TRANSFER
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
5.6. MicroGrid Three-Line Diagram
UT
N
L1
L2
MTR
N
L1
L2
M
L1
L2
L1
L2
MS
G
N
L1
L2
EXISTING UTILITY
TRANSFORMER
TO REMAIN
120/240V,
1P, 3W SECONDARY
EXISTING 200A,
120/240V UTILITY
METER TO REMAIN
EXISTING 200A,
120/240V,
2-POLE, 1Ø, 3W
SERVICE FUSED
DISCONNECT SWITCH
TO REMAIN
AC1
TAP
CT 1/2
Microgrid ATS
RXSW200A3
N1 N2
L1 L2
To MDP
To Mini PDP
G N
To MDP
To Mini PDP
L1 L2
E1 E2
CONDUCTOR SCHEDULE:
AC1: (2) #3/0 AWG 90C MIN (L1 / L2)
AC2: (2) #1 AWG 90C MIN (L1 / L2)
AC3: (2) #6 AWG 90C MIN (L1 / L2)
AC4: (1) #14 AWG 90C MIN
DC1: (2) #4/0 AWG 90C MIN (+ / -)
N1: (1) #3/0 AWG 90C MIN
N2: (1) #1 AWG 90C MIN
N3: (1) #6 AWG 90C MIN
G1: (1) #4 AWG 90C MIN
G2: (1) #6 AWG 90C MIN
G3: (1) #8 AWG 90C MIN
G4: (1) #12 AWG 90C MIN
MAX 200A MDP
120/240V, 1Ø, 3W
AC2
Inverter
XW Pro 6848
AC DC
To Director V1 and Loads G1
G
CT 3/4
T1 T2
AC1
CUSTOMER MAIN
DISTRIBUTION PANEL
(MDP)
N1
N
L1 L2
200A
AC CB 2
L1 1 L1
L2 2 L2
AC 4
120V to VT1
120V to AC/DC PS
120V to VT2
In
Director V1
To mPDP
Neut. Bar
AC OUT
INV
OUT
N3
L1 N L2
GRID
AC
CBs
1
L1 L2
L1 L2
AC 3
L1 L2
LOAD
2
L1 L2
AC IN
GRID
(AC1)
L1 N L2
G
G3
AC IN
GEN
(AC2)
L1 N L2
To mPDP
Gnd. Bar
AC 3
DC DC
DC CB
+
+
+ DC Bus
DC 1
- DC Bus
G2 N2
FROM GND+N
BARS IN ATS
N
G
To Inverter
To Director mPDP Neut. Bar mPDP Gnd. Bar
To Battery
To Inverter
Mini Power Distribution Panel (mPDP)
XW MINI PDP 865-1013-01
DC 1
-
To mPDP
Gnd. Bar G2
-
DC 1
-
To mPDP
Gnd. Bar
G2
-
Battery Module eFlex 5.4
Battery Module eFlex 5.4
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 12 -
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
6. Power Source Requirements
The Savant Power System can be integrated with an automatic generator or battery storage system for a complete energy management experience. This
Deployment Guide includes instructions on how to set up your energy solution for integration either power source, but not both. Review the following notes on specifications.
Generator Physical Requirements
– IMPORTANT!: All Automatic Transfer Switches (ATS) must have Auxiliary Position-Indicating Contacts to connect to the Savant Power
Hosts GPIO terminals.
– Auxiliary Position-Indicating Contacts come standard on all commonly sold Generac Model residential ATS.
– Kohler residential ATS models RXT and RDT (600A and 400A) can be purchased as an accessory for Kohler model ATS under 600A. They can also be purchased as an accessory for ASCO ATS, and most other brands.
– When configuring an Savant Power System to work with a generator, the system needs to map the GPIO input to the ATS position. The ATS position can either be set to the Utility Grid or the Emergency Backup source. Please review the generator-specific ATS Operation & Installation manual for information on the auxiliary contact position.
Generator ATS Mapping
– The ATS position mapping is inputted using the Grid Available when ATS GPIO is Low checkbox within Tools > Energy Manager . For more information, see Section 15.3 ATS Position Mapping .
– When the auxiliary contact is closed , the ATS GPIO is Low .
– When the auxiliary contact is open , the ATS GPIO is High .
Schneider Energy Storage System
IMPORTANT!: For Schneider Energy Storage System (ESS) deployments, follow the steps listed in Appendix B: Schneider ESS and Conext MiniPDP before continuing deployment.
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 13 -
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
7. On-Device Setup
7.1. Configure Savant Power Module Channels
Savant Power Module room, name, and slot number can be set by configuring the Savant Power Module using the PAIR button. See
PAIR Button Functions for more information.
NOTE: New Savant Power Modules will have no names and begin at step 2.
1
TAP AND HOLD
PAIR BUTTON FOR
5 SECONDS TO
CLEAR SETTINGS
2
TAP PAIR TO
BEGIN PRE-APP
SETUP. SELECT
THE ROOM FOR
CHANNEL A
3
SELECT CIRCUIT
NAME FOR
CHANNEL A
4
CHANNEL A IS
CONFIGURED
5
SELECT ROOM
FOR CHANNEL B
6
SELECT CIRCUIT
NAME FOR
CHANNEL B
7
CHANNEL B IS
CONFIGURED
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 14 -
8
SELECT SLOT
GROUP
9
SELECT SLOT
NUMBER
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
7.2. Pair Savant Power Modules
Savant Power Modules must be paired with the Director to establish Bluetooth communication.
1. For each Savant Power Module, press and hold the PAIR button for 3 seconds until the gear icon appears on the LCD screen.
1
1
CIRCUIT PO
WER
A
B
PAIR
Y
Y
120V 20A DU
AL RELA
MODULE INPUT
LOAD OUTPUT
UTOMA
HOME A
1HP MA
INPUT
B
X\CHAN
120-21
120V
AC 60Hz
120V
AC 60Hz
120V Y
TION EQUIP
-QP2R20
798A
120
120
INPUT A
YYW
W
OUTPUT
B
2
2. On the front of the Director, firmly press the PAIR button.
3. Confirm the Director is in Association Mode by the Status LED alternating between red and green continuously.
4. Pairing is complete when all Savant Power Modules have the gear icon replaced with a Bluetooth icon and the status LED of the Director is solid green. A default configuration is uploaded to the Director containing all Savant Power Modules and their location within the breaker panel.
NOTE: This process takes between 2-5 minutes.
4
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 15 -
3
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
7.3. Director Hotspot (Optional)
For sites without an Ethernet connection, the Director can be used as a hotspot for the Savant Power & Light app to configure the Director:
1
1. Press and hold the Test button on the Director.
2. Once the Status LED blinks green and amber, on the iOS device navigate to Wireless Networks .
3. Connect to the wireless network titled SavantAP <DirectorUID>
Example: SavantAP 001aae469f9e0000
4. Enter the wireless network password.
NOTES:
– The default password is 12345678
– The Director UID is located on the front of the device.
2
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 16 -
3
ESS-BLDDIRV12VT-00
ESS-BLDDIRV12VT-00
UID: 001AAF023E7E0000
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
8. App Setup
The Savant Power & Light app must be installed on an iOS device on the same network as the Savant Power Director. Using the app Store, search for
Savant Power & Light and tap install. When the app is downloaded, launch the app and complete the steps below:
8.1. Create a Home
1
TAP CREATE AN
ACCOUNT OR LOG IN
WITH AN EXISTING
ACCOUNT
2
FILL IN ACCOUNT DETAILS
AND AGREE TO THE USER
AGREEMENT BEFORE
TAPPING CREATE ACCOUNT
3
TAP CREATE HOME
4
NAME THE HOME AND
TAP NEXT.
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 17 -
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
8.2. Add Photo
The Savant Home is represented within the Savant Power & Light app with a name and image.
1
TAP NEXT
2
SELECT AN IMAGE
FROM THE ARRANGED
PHOTOS
OR
TAP THE PLUS SIGN TO
TAKE A PHOTO OR USE AN
EXISTING PHOTO
3
TAP USE PHOTO
OR CHOOSE
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 18 -
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
8.3. Discover Devices
1
TAP ON THE HOME
2
SELECT THE TYPE OF
DEVICES TO BE
CONFIGURED AND
TAP NEXT.
3
THE POWER & LIGHT
APP AUTOMATICALLY
SCANS FOR ALL
DEVICES ON THE
NETWORK.
4
IF THE DIRECTOR
HAS ALREADY BEEN
DEPLOYED
BEFOREHAND,
CHOOSE EITHER TO
GET THE CONFIG OR
CONFIGURE FROM
SCRATCH
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 19 -
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
8.4. Energy Dashboard
The Dashboard appears after all devices have been discovered, or when the Savant Home is selected after initial deployment. is an overview of all configured power sources, loads, Energy Scenes and breaker panels.
A
B
C
D
A
B
C
D
E
F
Menu
Breaker Panels
Test Circuits
Power Sources
Energy
Monitoring
Energy
Management
Tap to open the Menu screen.
Quantity of breaker panels configured. Tap to
view the Breaker Panels screen.
Tap to view the Test Circuits screen.
Tap to view and configure a Power Source .
Tap to view and configure
and
Quantity of Energy Scenes created. Tap to view
.
E
F
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 20 -
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
9. Get Config
A Config is a file that contains all Savant Power Modules, breakers, their slots, power sources, and associated settings.
IMPORTANT!: The initial config must be downloaded from the Director to the Savant Power & Light app before making any changes or continuing deployment.
1
TAP THE SYNC ICON
2
TAP GET CONFIG
FROM THE HOST
3
TAP SYNC CONFIG
4
TAP OK WHEN
DOWNLOAD IS
COMPLETE
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 21 -
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
10. Test Circuits
With the Config uploaded to the Power & Light app, test the functionality of the Savant Power Modules and their associated circuits before continuing deployment.
1 ON THE HOME SCREEN,
TAP TEST CIRCUITS
2 TAP THE TOGGLE
SWITCH TO TURN
INDIVIDUAL LOADS ON
OR OFF
3 TAP THE ... ICON TO
SORT CIRCUITS
ALPHABETICALLY OR BY
ROOM
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 22 -
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
11. Breaker Panels
For proper functionality, ensure that the breaker panel settings match the physical specifications. The steps are identical for any type of breaker panel, save for data entered into the fields. Follow the steps below:
11.1. Add Breaker Panel
Alexis Home
1 TAP BREAKER
PANELS
2 TAP ADD PANEL 3 SELECT EITHER BLANK
PANEL, OR TEMPLATES
4 CHOOSE WHICH
POWER SOURCE WILL
PROVIDE BACKUP
POWER WHEN THE
GRID IS UNAVAILABLE
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 23 -
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
11.2. Breaker Panel Settings
Refer to the manufacturers documentation to confirm the following settings are correct before uploading the configuration to the Director.
C
D
E
F
G
H
I
A
B
A
B
C
D
E
F
G
H
I
Panel Name
Panel Hierarchy
Main Breaker (Feed)
Phase Type
Name of the breaker panel as it will appear in the Power & Lighting app.
Main Distribution Panel: Panel will control distribution of power throughout the Savant Home.
Sub Panel: Panel is subordinate to a
Main Distribution Panel.
Current output from the main feed into this panel.
Quantity of phases in this panel.
Panel Size
Panel Breaker
Columns
Location
Backup Power Source
Panel Type
Quantity of slots in the breaker panel.
Quantity of columns in the breaker panel.
Room within the Savant Pro App the breaker panel is located.
Which Power Source is backing up the panel.
Make and Model of the breaker panel.
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 24 -
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
11.3. Slots
A
B
E
H
I
F
G
J
K
C
D
G
H
I
Panel
A Panel Side
B Slot Number
C Empty Slot
D
Module
Model
E Menu
F Load Type Indicator
J
K
Status Indicator
Power Meter
Switch Status
Circuit Name
Display Name
Which side of the panel is being displayed.
Individual slot in the panel. Tap to test the associated load.
Tap to add a module to the slot.
User-entered breaker panel model.
Tap to change zoom level or save panel template.
Indicates whether the Savant Power Module controls a Lighting or Energy type load.
: Unpaired.
: Paired to the Director.
Real-time power consumption.
Indicates whether or not the circuit is enabled.
Name of associated circuit as it will appear in the Savant Pro app. Tap to assign or re-assign
Circuit Name.
Shorthand name for the circuit.
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 25 -
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
11.4. Add Module (Optional)
The Slots screen is a list of all slots ordered by physical location on the breaker panel. Skip this section if
On-Device Setup has been completed. In
this example, a Savant Power Module will be added.
1 TAP BREAKER
PANELS
2 TAP THE CONFIGURED
PANEL
3 TAP AN EMPTY SLOT 4 SELECT THE MODULE
TYPE
NOTE: To remove an existing module, tap the device icon and then tap Delete Device .
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 26 -
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
Pair Added Savant Power Module (Optional)
Once a Savant Power Module has been added, it must be paired to the Director to establish communication.
1
TAP PAIR
Savant Power® Panel Deployment Guide
009-2140-00 | 042522
2 TAP THE PAIR BUTTON ON
AN INCHARGE MODULE TO
CAUSE IT TO FLASH IN THE
POWER & LIGHT 2.0 APP
OR
TAP IDENTIFY IN THE APP
TO TURN THE INCHARGE
MODULE AND ASSOCIATED
LOAD ON AND OFF
3
SELECT THE MODULE
AND TAP PAIR
4 THE INCHARGE MODULE
WILL DISPLAY A
BLUETOOTH ICON WHEN
PAIRED
Copyright 2022 Savant Systems, Inc
- 27 -
Savant Power® Panel Deployment Guide
11.5. Assign Circuit Name (Optional)
Names configured during On-Device Setup
are displayed. To change the circuit name, follow the steps below..
1 TAP ASSIGN CIRCUIT NAME 2
SELECT THE ROOM THE
CIRCUIT PROVIDES ENERGY
TO AND TAP SAVE ROOM
3
SELECT THE SPECIFIC
CIRCUIT THE CHANNEL
POWERS AND TAP ASSIGN
CIRCUIT
4
THE CHANNEL WILL
APPEAR NAMED WHEN
COMPLETE
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 28 -
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
12. Energy Monitoring
The Savant Energy Monitor (SEM) and Current Transformers (CTs) are used to monitor power of the main feed, grid power, and loads in the home that are greater than 60A.
12.1. VT and CT Placement
Voltage Transformers (VT) and Current Transformers (CT) are used to monitor Voltage and Current respectively. Review the following tables for correct placement.
Savant Power System with Generator
SEM CT
1 / 2
3 / 4
Physical Connection
ATS Normal Input
ATS Emergency Input
Circuit Name
Grid Feed
Generator Power
CT Size
250A
150A
Classification
Feed
Production
Savant Power System with Schenider ESS
SEM CT
1 / 2
3 / 4
Physical Connection
ATS Input
ATS Output
Circuit Name
Grid Feed
Total Consumption
CT Size
250A
150A
Classification
Feed
Total Consumption
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 29 -
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
12.2. Configure Current Monitors
To for live data for loads greater than 60A to display correctly, Current monitors must be assigned to the correct panel, size and channel.
Circuit Panel and Slots
In this configuration, a car charger will be configured to be monitored by a 50A Savant Energy Monitor.
1
TAP ENERGY
MONITORING
2
TAP SETUP CURRENT
MONITORS. THEN
SELECT A CIRCUIT
CLASSIFICATION AND
TAP NEXT.
3
TAP THE PANEL TO
BE MONITORED AND
TAP NEXT.
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 30 -
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
Circuit Name and Group
Circuit names and groups are the visual representation of the circuit within the Savant Pro App.
5
ENTER THE CIRCUIT
NAME AND TAP NEXT.
6 TAP IMAGE 7 SELECT AN IMAGE
THAT WILL REPRESENT
THE CIRCUIT
8
TAP ROOM AND CHOOSE
A ROOM WITHIN THE
CONFIGURATION OR
CREATE A NEW ONE.
REPEAT STEPS 5
THROUGH 8 FOR CIRCUIT
GROUPS
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 31 -
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
Current Sensor Size and Channel
Current sensor size and channel must match the specifications of the installed current sensor.
5 SELECT THE CURRENT
SENSOR SIZE. TAP NEXT.
TAP SHOW MORE SENSORS
FOR ALL SUPPORTED
SENSOR SIZES
6 TAP SELECT CHANNEL
NEXT TO L1, SENSOR A
7 SELECT THE CHANNEL
WIRED TO L1, SENSOR A.
8 REPEAT THIS PROCESS FOR
CHANNEL 2 AND TAP NEXT.
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 32 -
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
12.3. Channel Settings
B
A
C
D
E
F
G
H
I
J
K
L
M
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 33 -
Current Channel
A Channels
B Live Data
C Invert
Required Settings
D Classification
E Circuit
F Current Monitors
G
H
VT Connections
Room
I Image
N
O
P
J Current Size
K Image
L
Current Transformer
Size
Optional Settings
M Group
Group Image
Parent Circuit
Contactor
All associated channels.
– Selected channel is outlined.
– Blue channels are configured.
– Grey channels are unconfigured.
Live data sorted by individual channel.
Tap to invert live data values.
Whether the CT channel is Consumption,
Feed, or Main.
The selected circuit used to monitor energy consumption.
Quantity of Current Monitors and which channel is monitoring which slots.
Quantity of voltage sensors and which slots they are linked to.
Room within the config
Image representing the Savant Power
Module and Channels within the Savant
Pro App
Total amps the
The icon that the channel will be represented as in the Pro app.
Tap to assign transformer size (in Amps).
Which group these channels will be associated with.
Image associated with the group.
Tap to assign a Parent Circuit.
Tap to link selected channels to a Savant
Power Module.
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
12.4. Contactor Linking
Loads greater than 60A are controlled using a Savant Power Module Control Relay + Contactor, and monitored by the Savant Energy Monitor
(SEM). Contactor Linking is required within the Savant Power & Light app to link the Current Transformer (CT) to the Savant Power Module channel communication, it is important to configure the gateway to have a reserved IP address.
4
TAP SETUP CONTACTOR
AND TAP NEXT.
5
TAP THE COMPANION
MODULE CONTROLLING
THE CONTACTOR THEN
TAP NEXT.
6
THE APP WILL LINK
THE CONTACTOR TO
THE CIRCUIT. TAP GOT
IT WHEN DONE.
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 34 -
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
12.5. Add Power Source
Power sources are devices wired to provide auxilliary power to the Savant Home. Add power source within the Power & Light app by following the steps below. In this example, a Battery is chosen.
I MPORTANT NOTES!:
– The Director must be connected to the main network for all further steps.
–
before completing this section.
– For a battery power source, both the Director and battery gateway must both be on the same subnet.
1 TAP POWER SOURCES 2
TAP THE PLUS SIGN TO
CREATE A NEW POWER
SOURCE
3
SELECT THE POWER
SOURCE AND TAP NEXT
4
ENTER GENERAL
SETTINGS AND TAP
NEXT
5
CHOOSE WHICH
BREAKER PANEL TO
BACK UP AND TAP NEXT
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 35 -
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
12.6. Configure Power Source (Optional)
Once the power source has been added, its settings can be configured. The process to configure settings is the same regardless of type, however the settings are different.
5
WITHIN THE POWER
SOURCES SCREEN, SWIPE
LEFT OR TAP ON THE
EDIT ARROW
Savant Power® Panel Deployment Guide
009-2140-00 | 042522
6
TAP THE PENCIL ICON
NOTE: TAP THE TRASHCAN
ICON TO REMOVE POWER
SOURCE
7
CONFIGURE ALL
BATTERY SETTINGS AS
LISTED ON NEXT PAGE
AND TAP NEXT
Copyright 2022 Savant Systems, Inc
- 36 -
Savant Power® Panel Deployment Guide
12.7. Power Source Settings
Generator Settings
IMPORTANT!: Before completing all fields in power source settings, see Generator Considerations and Whole Home Backup for term clarification.
D
E
F
G
A
B
C
General Settings
A Start Timeout
B
C
Host on UPS
Backup
Whole Home
Backup
ATS Controller Settings
D ATS Controller
E
F
G
Length of time before the generator is consider to have failed starting up.
Total capacity of the battery in kilowatt per hour.
Inverter capacity in kilowatts per hour.
ATS Controller
Port
ATS on Grid
Position
ATS on Backup
Position
IP address and port of the Conext gateway as reserved in Appendix
B: Schneider ESS and Conext
MiniPDP.
Port of the Conext gateway as reserved in Appendix B:
Schneider ESS and Conext
MiniPDP .
Which position dictates the
Savant Power System has access to the grid.
Which position dictates the
Savant Power System does not have access to the grid.
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 37 -
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
Battery Settings
A
D
E
F
B
C
G
H
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 38 -
General Settings
A Name
B
C
D
E
Battery Inverter
Type
Battery Capacity
(kWh)
Battery Inverter
(kW)
Host on UPS
Backup
F
Whole Home
Backup
Controller Settings
G IP Address
H Port
Name as it will appear in the
Savant Power & Light app and
Savant Pro app.
Total capacity of the battery in kilowatt per hour.
Inverter capacity in kilowatts per hour.
Whether the Host is backed up by UPS or not.
Whether the entire hme is backed up by the power source or not.
IP address and port of the Conext
.
Port of the Conext gateway as reserved in Conext Gateway
Setup .
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
Microgrid Settings
J
K
G
H
I
A
B
C
D
E
F
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 39 -
General Settings
A
B
C
Name
Controller Type
IP Address
D Port
E
F
Host on UPS
Backup
Whole Home
Backup
Battery Settings
G
Battery Inverter
Type
H Battery Capacity
I
Battery Inverter
(kW/h)
Generator Settings
J
Output Power
(kW)
Solar Settings
K
Name as it will appear in the
Savant Power & Light app and
Savant Pro app.
Which type of controller will control the Microgrid.
IP address and port of the Conext
.
Port of the Conext gateway as reserved in Conext Gateway
Setup .
Whether the Host is backed up by UPS or not.
Whether the entire home is backed up by the power source or not.
Type of battery inverter
Total capacity of the battery in kW.
Maximum kW/h the battery inverter can supply.
Maximum kW the generator can produce.
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
13. Circuits
13.1. Dedicated Circuit
For proper Energy Scene functionality, dedicated loads and their max wattage must be defined. A dedicated circuit is a circuit that serves a single appliance or electrical fixture. No other loads are allowed to draw energy from a dedicated circuit. See the following table for examples of circuit classification for a 200 Amp service size home as a guide.
Examples of Circuit Classification for a 200A Service Size Home
Dedicated Circuits
– Kitchen Small appliance Circuit
– Sewer Ejection Pump Outlet
– Microwave
– Electric Cooktop
– Electric Range
– Fridge
– Electric Dryer
– Dining Room Outlets
– Garage Door Opener(s)
– Bathroom GFCI Outlet(s)
– Smoke Detectors (Bedroom)
– Basement Freezer
– Garage Outlet(s)
– Car Charger
– Basement Sump Pump
– Well Pump
– Furnace Air Handler
– AC Condenser
– Washing Machine Outlet
– Electric Water Heater
– Dishwasher
Non-Dedicated Circuits
– Living Room Lights
– Living Room and Hall Outlet(s)
– 2nd Floor East Bedroom Lights and Outlets
– Bathroom and Hall Lighting
– Kitchen Lighting
– Basement Light(s)
– 2nd Floor West Bedroom Lights and Outlets
– Garage and Mudroom Lights
– Master Bedroom Lights and Outlets
– Master Bath Lighting
– Foyer and Outdoor Lighting
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 40 -
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
13.2. Configure Circuits
To configure dedicated loads and loads backed up by the the power source configured in section 11.5
Alexis Home
1 TAP TEST CIRCUITS 2
TAP DEDICATED
AND SELECT ALL
DEDICATED LOADS
3
TAP MAX WATTAGE
AND ENTER
MAXIMUM WATTAGE
FOR DEDICATED
LOADS
4
TAP BACKUP
TO VIEW AND EDIT
WHICH LOADS ARE
BACKED UP BY A
CONFIGURED POWER
SOURCE
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 41 -
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
14. Energy Scenes
Energy Scenes are commands configured within the Savant Power & Light app. Energy Scenes determine which loads will be enabled if a power outage occurs.
14.1. Create Energy Scene
In this example, an Off Grid Energy Scene is created. An Off Grid Scene will automatically activate in the event of a power outage. Off Grid Scenes set which loads will remain powered (critical) when the system switches to backup power. Additional scenes can be created and configured to trigger based on battery state of w or on a schedule. The default Essentials Off Grid Scene will automatically activate in the event of a power outage.
1 TAP ENERGY
MANAGEMENT
2
TAP THE PLUS SIGN
TO CREATE A NEW
SCENE
3 SELECT AN
OFF GRID SCENE
4
CONFIGURE SCENE
SCHEDULE AND TURN
CONDITIONS AND TAP
NEXT
IMPORTANT!:
– If two scenes have the same battery and grid conditions are scheduled to occur at the same time, the scene that satisfies more specific conditions is run.
– If the battery state of charge reaches a level that exists in an Off Grid Scene condition while the grid is down, that particular Off Grid Scene will activate.
– If the battery state of charge has reached a level that exists in an Off Grid Scene condition when the grid goes down, that particular Off Grid will activate.
– On The Grid scenes can be used at any time and will be implemented in a future release.
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 42 -
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
14.2. Energy Budget
The energy budget is a percentage of the maximum kW the power source can provide. This is handled automatically by the Power & Light app when the energy budget is given for an off grid scene. This section is informational.
– If the battery inverter or generator size is less than or equal to 10kW , the energy budget for off grid scenes is equal to the size of the inverter or generator.
– If the battery inverter or generator size is greater than 10kW , calculate the energy budget using the following equation:
Budget = Power Source Size + ( Power Source Size - 10kW / 0.4).
Example: A battery inverter has a size of 13.6 kW . The following equations represent calculating its energy budget.
Energy Budget = 10kW + (13.6 kW - 10kW)/0.4
Energy Budget = 10kW + 3.6kW/0.4
Energy Budget = 10kW + 9kW
Energy Budget = 19kW .
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 43 -
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
14.3. Edit Scene Loads
This window is a visual representation of all of the loads that will be available while the scene is enabled. When a load is unchecked, the load will be unavailable while the Scene is active. Tap Done to finish Energy Scene creation.
NOTES:
– Only configured and detected loads will be visible on this screen.
– Only dedicated loads need to be selected on this screen. Non-dedicated loads will remain available for any off grid scene.
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 44 -
Copyright 2022 Savant Systems, Inc
15. Upload Configuration
Once all changes have been made to the configuration, it must be uploaded to the Director.
1 TAP SYNC CONFIG 2 TAP SAVE THE CONFIG TO
THE HOST
3
TAP SYNC CONFIG. THE
GREEN CIRCLES INDICATE
THE CONFIGURATION IS
BEING UPLOADED
4 TAP OK WHEN THE UPLOAD
IS COMPLETE
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 45 -
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
16. Confirm System Functionality
Once the configuration is synced to the Director, the configuration is complete. However, it is important to test the system to ensure correct functionality.
1. Check that All Circuits are Named Correctly on Savant Power Module Display ................................................................................................
2. Confirm that Circuit Power Readings appear Correctly on Savant Power Module Display ...........................................................................
3. Ensure that All Circuits can be Powered On and Off from the Savant Pro app .................................................................................................
4. Check that All Loads Report Energy Readings Properly in the Savant Pro app ................................................................................................
5. Check that Total Consumption, Battery, and Grid Power are Reported Properly in the Savant Pro app .................................................
6. Take the System Off the Grid and Check that the appropriate Off Grid Scene Triggers ................................................................................
7. Test all Configured Off-Grid Scenes — Check that the Load States are Set Accordingly ..............................................................................
8. Bring the System Back onto the Grid and Check that All Loads are Restored ...................................................................................................
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 46 -
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
Appendix A: Savant Power Module PAIR Button Functions
The PAIR button on Savant Power Modules has multiple functions depending on the length of time pressed.
– To cycle through options, tap the PAIR button.
– To select an option, hold the PAIR button for 1 second.
– To clear pairing, hold the PAIR button for 3 seconds until the Gear icon appears.
– To reset the Savant Power Module, hold the PAIR button for 5 seconds.
1
CIRCUIT PO
WER
A
B
PAIR
Y
Y
X\CHAN
120-21
:
120V 20A DU
GPM-QP2R20
MODULE INPUT
:
120V
120V
:
AC 60Hz
AC 60Hz
120V
AC 20A/
Y
1HP MA
120
120
#12-8 A
HOME A
UTOMA
798A
-QP2R20
INPUT B
INPUT A
YYW
W
OUTPUT
B
OUTPUT
A
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 47 -
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
Appendix B: Schneider ESS and Conext MiniPDP
Schneider Energy Storage Systems (ESS) require communication to be established between Director and Conext Gateway. To facilitate this communication, it is important to configure the gateway to have a reserved IP address.
Schneider Conext MiniPDP Labeling
The Schneider Conext MiniPDP ships with incorrect labeling. Review the image to the right for correct labeling.Schneider Conext Gateway Setup
AC IN AC OUT INVERTER IN
(GRID)
INVERTER
DISCONNECT
1
00:77:FF:84:D1:50
Software Version
V1.08BBN415
Wifi Password
3a0a7fb335c8c
BC21135002412
MANUFACTURED
07/Dec/21
Reserve Schneider Conext Gateway IP Address
1. Locate the MAC address of the Schneider Conext Gateway and note it down.
NOTE: The MAC address is located on the rear of the unit.
2. Find the make of the router installed and download the respective app. In this example, an eero router is used.
3. Create an account and log into the eero application.
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 48 -
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
4 SELECT SETTINGS TAB 5 TAP NETWORK
SETTINGS
8. Tap the Unnamed Device and enter the desired IP address.
9. Tap and reboot the Conext gateway.
6 TAP RESERVATIONS
& PORT
FORWARDING
7 SEARCH FOR
“SCHNEIDER CONEXT
GW” MAC ADDRESS
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 49 -
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
Appendix C: System Information Checklist
This page is used to record all important information for the installation.
Site Information
Date of Deployment:
Site WiFi SSID:
Site WiFi Password:
Schneider Information
WiFi Password:
MAC Address:
Serial Number:
Software Version:
MFG:
Fortress Information
Battery Install Date:
Savant Information
Bootloader:
Firmware Version:
Savant Power & Light Build:
Savant Pro app Version:
NOTES:
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 50 -
Copyright 2022 Savant Systems, Inc
Savant Power® Panel Deployment Guide
Important Notice
Disclaimer
Savant Systems, Inc. reserves the right to change product specifications without notice, therefore, the information presented herein shall not be construed as a commitment or warranty.
Savant Systems, Inc. shall not be liable for any technical or editorial errors or omissions contained herein or for incidental or consequential damages resulting from the performance, furnishing, reliance on, or use of this material.
Patents
Certain equipment and software described in this document is protected by issued and pending U.S. and foreign patents.
All products and services are trademarks or registered trademarks of their respective manufacturer.
Coypright
This document contains confidential and proprietary information protected by copyright. All rights reserved. Copying or other reproduction of all or parts of this document is prohibited without the permission of Savant Systems.
Trademarks
© 2022 Savant Systems, Inc. All rights reserved. Savant, Savant app, TrueImage, Savant Host, Now You Can, RacePoint Blueprint, Single app Home,
TrueCommand, TrueControl, and the Savant logo are trademarks of Savant Systems, Inc.
AirPlay, apple, AirPort Express, AirPort Extreme, apple TV, apple Remote Desktop, FireWire, iMac, iTunes, iPad, iPad mini, iPad Air, iPhone, MacBook, Mac and OS X are trademarks or trade names of apple Inc. iOS is a trademark of Cisco®. Android, Google, Google Play, and other Google marks are trademarks of Google, Inc. Wi-Fi is a registered trademark of the Wi-Fi Alliance®. HDMI® is a trademark of HDMI Licensing, Inc. MOTU® is a registered trademark of
Mark of the Unicorn, Inc. Luxul is a registered trademark of Luxul Wireless. NETGEAR®, the NETGEAR Logo and ProSAFE are trademarks of NETGEAR, Inc.
Extreme™ is a trademark of Extreme Networks, Inc.
All other brand names, product names, and trademarks are the property of their respective owners.
Technical and Sales Support
Savant Power, Inc. is dedicated to providing prompt and effective support in a timely and efficient manner.
– To contact Savant Power Support, access the Savant Customer Community and enter a support Case ticket.
– To contact Savant Sales, visit Savant.com and select Contact Us to locate a local sales representative in your area.
Savant Power® Panel Deployment Guide
009-2140-00 | 042522 - 51 -
Copyright 2022 Savant Systems, Inc