EC-Vent Installation instructions_CE_GB (A003)

EC-Vent Installation instructions_CE_GB (A003)
EC Vent
Installation instructions
-EN_GB
2012-11-20 A003
Contents
1 Declaration of Conformity ........................................................................................................... 1
2 Warnings................................................................................................................................... 2
3 Product Introduction ................................................................................................................... 3
3.1 General ........................................................................................................................... 3
3.1.1 Description of the room unit ..................................................................................... 3
3.1.2 Description of the control board................................................................................ 3
3.2 Technical Data ................................................................................................................. 4
3.2.1 Rated voltage and current ....................................................................................... 4
3.3 Transport and Storage ...................................................................................................... 4
4 Installation................................................................................................................................. 4
4.1 Unpacking........................................................................................................................ 4
4.2 Where to Install ................................................................................................................ 5
4.3 Installing the room unit and control board ........................................................................... 6
4.3.1 Installation of the room unit...................................................................................... 6
4.3.2 Installation of the control board ................................................................................ 6
4.4 Description of internal parts .............................................................................................. 8
4.4.1 Control board.......................................................................................................... 8
4.4.2 Room unit............................................................................................................... 9
5 Electric Connections ..................................................................................................................10
5.1 Connectors ......................................................................................................................10
5.2 Signal ..............................................................................................................................10
5.2.1 Control board..........................................................................................................10
5.2.2 Room unit...............................................................................................................10
5.2.3 General ..................................................................................................................11
5.3 External connections wiring...............................................................................................12
5.3.1 Control board..........................................................................................................12
5.3.2 Room unit...............................................................................................................12
6 System layout............................................................................................................................14
1 Declaration of Conformity
Manufacturer
Systemair AB
Industrivägen 3
SE-739 30 Skinnskatteberg SWEDEN
Office: +46 222 440 00 Fax: +46 222 440 99
www.systemair.com
hereby confirms that the following products:
EC Vent
(The declaration applies only to product in the condition it was delivered in and installed in the facility in
accordance with the included installation instructions. The insurance does not cover components that are
added or actions carried out subsequently on the product)
Comply with all applicable requirements in the following directives
• Low Voltage Directive 2006/95/EC
• EMC Directive 2004/108/EC
• RoHS2 Directive 2011/65/EC
The following harmonized standards are applied in applicable parts:
EN 60 730-1
Automatic electrical controls for household and similar use – part 1: General
requirements.
EN 60 730-2-9
Automatic electrical controls for household and similar use – part 2: Particular
requirements for temperature sensing controls.
EN 60 730-2-13
Automatic electrical controls for household and similar use – part 2-13:
Particular requirements for humidity sensing controls.
EN 60 730-1 A 16
Automatic electrical controls for household and similar use – part 1: General
requirements.
The complete technical documentation is available.
Skinnskatteberg, 11–03–2011
Mats Sándor
Technical Director
EC Vent
Installation instructions
1
Systemair AB
2 Warnings
The following admonitions will be presented in the different sections of the document.
Danger
• Make sure that the Mains supply to the unit is disconnected before performing any maintenance or
electrical work!
• All electrical connections must be carried out by an authorized installer and in accordance with
local rules and regulations.
Warning
Protective earth (PE) and signal ground reference (GND) must not be connected to each other
Modbus should be connected with an unshielded cable connector of type RJ45.
EC Vent
Installation instructions
2
Systemair AB
3 Product Introduction
3.1 General
The controller will control an EC fan (0-10 V) depending on an internal time schedule or according to
internal/external sensors (Temp, CO2 etc.) or Building Management System. It consists of 2 parts, a
control board (CB) and a room unit (RU). The control board will ideally be situated close to the fan while
the room unit will be situated close to the user or the designated ventilation area.
This installation manual concerns the room unit and control board manufactured by Systemair AB. It
consists of basic information and recommendations concerning the design, installation, start-up and
operation, to ensure a proper fail-free operation of the unit.
The key to proper and safe operating of the unit is to read this manual thoroughly, use the unit according to
given guidelines and follow all safety requirements.
3.1.1 Description of the room unit
The objective of the room unit is to display the
information provided by the installed sensors and
make it possible for the user to enter desired
settings. The room unit is equipped with 2 internal
sensors; Temperature and humidity sensor, which
register the temperature and humidity in the
location of the installed room unit. It is possible to
connect 2 extra sensors to the internal connection
block.
Up to 10 room units can be active simultaneously.
Note:
The installed room units can only be regulated one
by one. It is not possible to perform settings on two
or more room units simultaneously!
Fig. 1 room unit
3.1.2 Description of the control board
The purpose of the control board is to provide
the room unit with 24 V DC mains supply, to
communicate information to and from the room
unit given by the sensors connected to it, and to
provide the correct output control voltage to the fan
or separate heater/cooler based on the settings in
the room unit.
Fig. 2 control board
EC Vent
Installation instructions
3
Systemair AB
3.2 Technical Data
Fig. 3 Dimensions room unit
Fig. 4 Dimensions control board
Model
A
B
C
D
c/cH
Room unit
80,0
89,0
20,0
2,4
60,0
Control board
180,0
60,0
-
-
164,0
3.2.1 Rated voltage and current
• 230V 50/60 Hz
• Max 6 A supply to fan via terminals in the control board
• Max 10 A mains supply fuse
3.3 Transport and Storage
The room unit and control board should be stored and transported in such a way that it is protected against
physical damage that can harm the product. The appliance is delivered complete in a cardboard box.
The room unit and control board can be stored i temperatures ranging between –20°C and +70°C
4 Installation
4.1 Unpacking
Verify that all ordered equipment are delivered before starting the installation. Any discrepancies from the
ordered equipment must be reported to the supplier of Systemair products.
EC Vent
Installation instructions
4
Systemair AB
4.2 Where to Install
The room unit is meant for indoor wall mounting preferably in an area of the building which is representative
for control of temperature or humidity, since these two functions are enclosed inside the casing of the
control. If the enclosed functions are not used and the fan or heater is controlled by sensors connected to
the central board, the physical location of the room unit inside the building is of less importance. Allowed
maximum and minimum operating temperatures are from 0°C to +50°C.
The control board is normally mounted somewhere close to the location of the fan or heater it is supposed
to control and can also be installed outdoors if necessary. Allowed maximum and minimum operating
temperatures are from –20°C to +50°C.
EC Vent
Installation instructions
5
Systemair AB
4.3 Installing the room unit and control board
4.3.1 Installation of the room unit
1
Find an appropriate place to install the room unit. Maximum length between room unit and control board
is 30 m. The enclosed 4 pole signal cable has a length of 10 m.
2
If needed, drill two holes in the wall (centre to
centre: 60 mm). Fasten the room unit to the wall
with 2 screws.
4.3.2 Installation of the control board
1
Find an appropriate place on the wall to install the control board, preferably close to the location of
the fan unit.
2
If needed, drill 4 holes to fasten the control board
(centre to centre: 164 mm) to the wall.
Note:
It’s recommended to mount the control board with
the enclosed transformer (pos.1) down side.
3
Connect sensors and the fan control (0–10 V DC) signal cables (figure 7).
EC Vent
Installation instructions
6
Systemair AB
4
Connect the enclosed 4 pole signal/power cable to
the modular jack on the print card.
The maximum length of the cable is 30 m.
Enclosed cable has a length of 10 m .
The cable is connected to the external plug on the
room unit.
If the connection plug on the room unit is not used
it is possible to connect the 4 pole signal/power
cable directly to a terminal in the room unit (pos.
4–7, figure 6). More information concerning the
wiring (figure 8 , table 2).
EC Vent
Installation instructions
7
Systemair AB
4.4 Description of internal parts
4.4.1 Control board
Fig. 5 Internal connections Control board
Position
Description
1
Earth connection terminal
2
Mains power supply terminal (230 V 1~)
3
Analog/Digital input 1 terminal
4
Analog/Digital input 2 terminal
5
Analog/Digital input 3 terminal
6
Alarm output terminal
7
Connection to fan terminal
8
Analog/Digital output 3 terminal
9
Analog/Digital output 2 terminal
10
Analog/Digital output 1 terminal
11
Modbus modular jack
12
Room unit modular jack
Backup battery1
13
14
Transformer 230V/24 V DC
1. To be installed first when the system is started. Intended for clock backup during
power failure. Dimensioned for 12 hours operation.
EC Vent
Installation instructions
8
Systemair AB
4.4.2 Room unit
Fig. 6 Internal connections Room unit
Position
Description
1
GND reference
2
Analogue input 1 & 2 and connection to PT1000
sensor (T1)
3
24 V DC (mains supply to external PT1000 sensor)
4
Communication signal from CB (wired from factory)
5
Communication signal from CB (wired from factory)
6
GND reference from CB (wired from factory)
7
24 V DC from CB (wired from factory)
EC Vent
Installation instructions
9
Systemair AB
5 Electric Connections
Danger
• Make sure that the Mains supply to the unit is disconnected before performing any maintenance or
electrical work!
• All electrical connections must be carried out by an authorized installer and in accordance with
local rules and regulations.
Warning
Protective earth (PE) and signal ground reference (GND) must not be connected to each other
Modbus should be connected with an unshielded cable connector of type RJ45.
The unit must not be put into operation before all the electrical safety precautions have been read and
understood. See wiring diagram (figure 7 ) how to connect external equipment and mains supply to
the control board.
5.1 Connectors
The following connectors are available in the control board and the room unit:
• Connector for communication between RU and CB: 4-Pole Modular Jacks
• Connector for Modbus communication 8-Pole Modular Jacks
• Connector for sensor in RU for cable with an area of 0,05-0,5 mm2
• Other connectors: Screw terminal block for cable with an area of 0,326-2 mm2.
5.2 Signal
The control board and room unit are prepared with the following connection possibilities:
5.2.1 Control board
• 3 Input, terminals selectable to Digital /0-10 V or PT1000
• 1 Counter input for tacho signal from motor
• 1 +10V input from motor. Max load 1,1 mA
• 3 Output, terminals selectable to Digital or 0-10 V
• 1 Output signal to motor. PWM.
5.2.2 Room unit
• 1 Input, terminals selectable to Digital /0-10 V or PT1000
• 1 Input, Digital or 0-10 V
• 1 Internal temperature sensor
• 1 Internal humidity sensor
EC Vent
Installation instructions
10
Systemair AB
5.2.3 General
5.2.3.1 Outputs
0...10 V
DC, 1 mA, short-circuit protected tolerance ±5%.
Digital
24 V DC, Isink 50 mA.
Alarm
Relay 1-pol no/nc <30 V AC/DC 500 mA cosφ >0,95.
5.2.3.2 Inputs
0...10 V DC
>100KΩ Polarity and over voltage protected <30 V, tolerance +-5%.
PT-1000
Temperature range - 30.. +70. Accuracy ±1°C (excluding sensor
tolerances).
Digital
For potential free contacts. U <24 V DC I <10 mA.
Internal Temperature
±1°C.
Internal humidity
±5% unit. From 30-70% Rh.
EC Vent
Installation instructions
11
Systemair AB
5.3 External connections wiring
5.3.1 Control board
Fig. 7 Example of connection to external components on the control board
5.3.2 Room unit
Fig. 8 Example of connection to external components on the room unit
EC Vent
Installation instructions
12
Systemair AB
Table 1: Description of connections
Position
Description
A
Mains supply 230 V 1~ AC (10A)
B
Analogue sensor (e.g. pressure sensor)
C
Analogue sensor (e.g. temperature sensor type PT1000)
D
Digital sensor (e.g. IR presence detector)
E
Alarm output (Max 24V AC/DC, Max 500 mA Cosφ >0,95)
F
Output to EC Fan
G
Output to analogue actuator with 24V DC supply
H
Output to digital signal (DC Max 24V, I Max 50mA)
I
Output to analogue actuator (e.g. heat regulator)
J
Connection to Modbus
K
Connection to room unit
Table 2: Description of wire colours
W
White
Y
Yellow
Br
Brown
Gr
Green
Bl
Black
R
Red
EC Vent
Installation instructions
13
Systemair AB
6 System layout
The EC Vent control system can have up to 5 active sensors (analogue), i.e. temperature, humidity, CO2,
pressure and airflow and up to 10 room units connected simultaneously. If a fan is regulated by e.g. 2
temp. sensors at the same time the highest signal controls the fan speed. Temperature sensors need to
be of the type PT1000.
Separate regulation of heating and cooling with possibility for maximum and minimum temperature
limitation in when using room sensor.
3 Digital inputs for e.g. forcing fan speed, changing set point, stop, extended running etc.
For more information about the possible operation options see “User Manual”
Fig. 9 Possible layout of the EC Vent system
Position
Description
A
Sensors ≤2pcs (room unit)
B
Sensors ≤3pcs (control board)
C
Alarm
D
Modbus
E
EC fan
F
Internal bus
RU
Room unit
CB
Control board
AI AO
Analogue in and outputs, alternatively Digital in- and outputs
DI DO
BMS
Building management system
EC Vent
Installation instructions
14
Systemair AB
EC Vent
Installation instructions
15
Systemair AB
lastpage
Systemair AB reserves the right to make changes and improvements to the contents
of this manual without prior notice.
Systemair AB
Industrivägen 3
SE-739 30 Skinnskatteberg, Sweden
Phone +46 222 440 00
Fax +46 222 440 99
www.systemair.com