LPI Stormaster ESE 15, 30, 50, 60 Lightning Protection System Installation Manual

LPI Stormaster ESE 15, 30, 50, 60 Lightning Protection System Installation Manual

Stormaster ESE 15, Stormaster ESE 30, Stormaster ESE 50, Stormaster ESE 60 are lightning protection systems designed to provide protection for structures from direct lightning strikes. The Stormaster ESE terminals are designed to attract lightning strikes and direct them to the earth through a downconductor and earthing system.

advertisement

Assistant Bot

Need help? Our chatbot has already read the manual and is ready to assist you. Feel free to ask any questions about the device, but providing details will make the conversation more productive.

Stormaster ESE 15, ESE 30, ESE 50, ESE 60 Installation Manual | Manualzz

Stormaster ESE

Hướng dẫn lắp đặt kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30, ESE 50, ESE 60

Installation Manual

LIGHTNING PROTECTION INTERNATIONAL PTY LTD

ABN 11 099 190 897

Web: www.lpi.com.au

Email: [email protected]

http://www.chongset.com

. Tel: 08 3968 2884 : Phân phối kim thu sét Stormaster ESE 15 , ESE 30 , ESE 50 , ESE 60

Hướng dẫn lắp đặt kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30, ESE 50, ESE 60

STORMASTER ESE INSTALLATION MANUAL

As a result of continuing research and product development in the area of lightning and lightning protection, LPI reserves the right to alter any detail contained within at any time without notice.

Prior to installation of the Stormaster ESE system, installers should check with

LPI or an authorised distributor to confirm they have the most recent version of the Stormaster ESE Installation manual.

It should be noted that 100% (100 percent) protection level for direct lightning strikes is not possible and cannot be provided due to the lightning discharge process being a natural atmospheric event.

Stormaster ESE Lightning Protection System

System Owner:___________________________________________

Date Installed:___________________________________________

Installation Contractor:____________________________________

Supplied by:_____________________________________________

Location of Installation:____________________________________

Lightning Protection International Pty Ltd

ABN 11 099 190 897

Complex #1, 16 Mertonvale Circuit, Kingston,

Tasmania, Australia, 7050

Phone: +61 3 62271955

Fax: +61 3 62291900

Email: [email protected]

Web: www.lpi.com.au

http://www.chongset.com

. Tel: 08 3968 2884 : Phân phối kim thu sét Stormaster ESE 15 , ESE 30 , ESE 50 , ESE 60

Hng dn lp t kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30,

ESE 50, ESE 60

Stormaster ESE

Installation Manual

LIGHTNING PROTECTION INTERNATIONAL PTY LTD

ABN 11 099 190 897

Web: www.lpi.com.au

Email: [email protected]

http://www.chongset.com

. Tel: 08 3968 2884 : Phân phối kim thu sét Stormaster ESE 15 , ESE 30 , ESE 50 , ESE 60

1

Hướng dẫn lắp đặt kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30, ESE 50, ESE 60

Contents

Protection Performance

Warranty

3

4

Lightning Protection

Recommended Order of Installation

4

5

Quick Installation Guide 5

Step 1.

Installation of the Lightning Earth 5

Step 2.

Installation of the HVSC Downconductor 5

Step 3.

Lower Termination of the HVSC

Downconductor and connection to the

Lightning Earth

Step 4.

Upper Termination of the HVSC

Downconductor and connection to the

Stormaster ESE terminal

6

6

Step 5.

Preparation and Raising of the Mast into position 7

Checking Lightning Protection

Components Supplied

LPI Stormaster ESE Installation

14

14

15 Installation of the Lightning Earth

Ground Resistance Lowering Compounds 16

Bonding the Lightning Earth 16

Labelling 17

Installation of the HVSC Downconductor 17

Hauling the HVSC Downconductor 17

HVSC Downconductor Clearance Holes 19

Routing

Fixing the HVSC Downconductor

19

21

Installation of Conventional

Downconductors

Installation of Stormaster GI Terminal to threaded pipe

Termination of the HVSC Lower End

21

22

24

Lower Termination of Conventional

Downconductor to the Lightning Earth 27

Termination of the HVSC Upper End 27

Connection of Factory Pre-Terminated

HVSC (Upper End) to Stormaster

Terminal

Labelling

Masts

Types of Mast Configurations

Mast Bases

Mast Couplings and Guying Points

Guying

Preparation and Raising of the Mast into position

Raising of Mast

Lightning Strike Recorder (LSR1)

Certification

Operation and Maintenance

Testing the Stormaster Terminal

Testing the Lightning Earth and the

HVSC Downconductor 40

31

31

32

32

33

34

34

35

36

38

39

39

40 http://www.chongset.com. Tel: 08 3968 2884: Phân phi kim thu sét

Stormaster ESE 15, ESE 30, ESE 50, ESE 60

Hướng dẫn lắp đặt kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30, ESE 50, ESE 60

PROTECTION RADIUS (M) - (Rp)

h = height of Stormaster terminal 2 4 5 6 10 15 20 45 60 above area to be protected (m)

Protection Level 1 (High Protection)

Stormaster 15

Stormaster 30

Stormaster 50

Stormaster 60

Protection Level 2 (Medium Protection)

Stormaster 15

Stormaster 30

Stormaster 50

Stormaster 60

Protection Level 3 (Standard Protection)

Stormaster 15

Stormaster 30

Stormaster 50

Stormaster 60

13 25 32 32 33 34 35 35 35

19 28 48 48 49 50 50 50 50

28 55 68 69 69 70 70 70 70

32

18

25

35

40

20

28

38

44

64 79

36 45

50 63

69 86

78 97

41 51

57 71

76 95

79

46

64

87

97

52

72

96

79

49

66

88

99

56

75

98

80

52

68

90

101 102 105 105

60

77

80

55

71

92

63

81

80

60

75

95

73

89

80

60

75

95

75

90

100 102 110 110

87 107 107 109 111 113 120 120

Protection

Performance

The protection radius (Rp) of a Stormaster ESE terminal is calculated using the following formula as defined by the French National

Standard NF C 17-102 (July 1995).

Rp =

√h(2D-h) + ∆T(2D + ∆T) for ≥5m where:

The following key parameters determine the calculation of RP.

∆T as established during the test.

Stormaster-ESE-15 = �

Stormaster-ESE-30 = �

∆T (µs) 30

Stormaster-ESE-50 = �

∆T (µs) 50

Stormaster-ESE-60 = �

∆T (µs) 60

• h = actual height of Stormaster terminal above the

area to be protected (m).

• D (in m) depends on the selected level of protection,

protection levels are specified in annex B of the

standard NF C 17-102.

D = 20m for protection level 1 (High Protection)

D = 45m for protection level 2 (Medium protection)

D = 60m for protection level 3 (Standard protection) http://www.chongset.com. Tel: 08 3968 2884: Phân phi kim thu sét

Stormaster ESE 15, ESE 30, ESE 50, ESE 60

Hướng dẫn lắp đặt kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30, ESE 50, ESE 60

Warranty

LPI’s Stormaster ESE terminals are guaranteed against defects in materials and workmanship for a period of 5 years from the original sales date when it was purchased from LPI or one of its authorised distributors.

The warranty is limited to the ex factory cost of replacement of equipment providing it has been installed and or certified by LPI or its distributor. All other costs such as freight, re-installation, loss of profit, insurance premiums are not included.

Responsibility for other direct or indirect damages or death is also specifically excluded from the warranty.

The range of Stormaster ESE terminals (or to our knowledge any other lightning protection system) cannot provide 100% protection and therefore it is not inferred.

As confirmation of the above paragraph we refer to French Standard NF

C 17-102.

Lightning

Protection

Figure 1.

Comments on the French Standard NF C 17-102.

We refer to the section in the standard titled “foreward” where it states the following:

“As in the case with anything related to the natural elements, a lightning protection system designed and installed in accordance with the standard, cannot guarantee absolute protection to structures, persons or objects: however , applying this standard will significantly reduce the risk of protected structures being damaged by lightning.”

The LPI Stormaster ESE Terminal should only be installed during storm free periods.

http://www.chongset.com. Tel: 08 3968 2884: Phân phi kim thu sét

Stormaster ESE 15, ESE 30, ESE 50, ESE 60

Hướng dẫn lắp đặt kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30, ESE 50, ESE 60

Quick Installation Guide

Recommended

Order of

Installation

To assist in the installation of the Stormaster ESE terminal and accessories refer to drawings GA-1, SM-1, ST-1, SW-1, ST-2 & HVS-1 as illustrated on pages 8-13.

1. Installation of the lightning earth.

2. Installation of the HVSC Downconductor.

3. Lower termination of the HVSC Downconductor and connection to

the lightning earth.

4. Upper termination of the HVSC Downconductor and connection to

the Stormaster ESE terminal.

5. Preparation and raising of the mast into position.

Step 1.

Installation of the Lightning

Earth

LPI recommends the installation of a radial lightning earth as illustrated in figure 8 on page 15.

• Each radial will consist of a trench (Approx: 500mm Deep x 200mm

Wide x 10m Length).

• An earth rod should be driven at the end of each trench.

• All rods should be interconnected through the use of 25mm x 3mm

copper tape and earth rod clamps.

• The application of earth enhancing compounds such as LPI RESLO

and GRIP assists to reduce soil resistivity to the recommended level

of less than 10 ohms.

Refer to page 15 for more detailed information on installation of the lightning earth.

Step 2.

Installation of the HVSC

Downconductor

• It is very important to check that the correct length of HVSC has

been supplied.

• The HVSC may be installed internally or externally on the structure.

• The HVSC should be installed as close (flush) as possible to the

structure.

http://www.chongset.com. Tel: 08 3968 2884: Phân phi kim thu sét

Stormaster ESE 15, ESE 30, ESE 50, ESE 60

Hướng dẫn lắp đặt kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30, ESE 50, ESE 60

• The HVSC should be fixed to the structure every 2m for the entire

length of the run. (Use LPI supplied or recommended saddles,

fixings and cable ties).

• Most direct route to ground is recommended, avoid sharp bends.

• Be sure to allow for enough HVSC at the top end for connection to

the Stormaster ESE terminal and the raising of the mast. Refer to

drawing HVS-1 on page 13 when installing HVSC over the edge of a

structure.

·

Refer to page 17 for more detailed information on the installation of

the HVSC.

·

If installing conventional downconductor such as copper tape or

stranded copper cable refer to page 21 for further instructions.

·

If installing Stormaster-GI model for connection to 2 inch male

threaded pipe refer to drawing ST-2 on page 12. Further instructions

are also given on page 22.

Step 3. Lower

Termination of the HVSC

Downconductor and connection to the Lightning

Earth

• When installing the HVSC downconductor a lower termination kit

(Model Number: LTERMKIT) should have been supplied as part of

the system.

• Refer to page 24 for detailed instructions on completion of the HVSC

lower termination and connection to the lightning earth.

·

If installing a conventional downconductor such as copper tape

or stranded copper cable refer to page 27 for instructions on

connection to the lightning earth.

Step 4.

Upper Termination of the

HVSC Downconductor and connection to the Stormaster

ESE terminal

• When installing the HVSC downconductor the upper termination

may have already been completed at the LPI factory prior to

shipment. If so refer to page 31 for further instructions.

• If the HVSC is supplied without the upper termination completed,

an upper termination kit (Model Number: UTERMKIT) should have

been supplied as part of the system. Refer to page 27 for detailed

instructions on completion of the HVSC upper termination and

connection to the Stormaster ESE terminal.

·

If installing a conventional downconductor such as copper tape or

cable refer to page 21 for detailed instructions on connection to the

Stormaster ESE terminal.

http://www.chongset.com. Tel: 08 3968 2884: Phân phi kim thu sét

Stormaster ESE 15, ESE 30, ESE 50, ESE 60

Hướng dẫn lắp đặt kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30, ESE 50, ESE 60

Step 5.

Preparation and Raising of the Mast into position

• With the upper termination of the HVSC completed and the FRP mast

in position it is now time to finalise the mounting arrangement so

that the mast can be raised and secured into position.

• If using the recommended installation methods as per drawings

GA-1, SM-1, SW – 1 & ST-1 fit the inline coupling to the lower mast

material.

• Fit the HVSC downconductor in and out of the slot in the coupling.

Refer to figure 34 on page 37.

• Carefully fit the mast butt adaptor of the Stormaster terminal into

the top of the FRP.

• It may be necessary to pull back any slack of HVSC down-

conductor through the FRP support mast to achieve a tight fit for

the mast butt adaptor. This should be completed carefully so as to

not damage the upper termination.

• Now fix the FRP support mast firmly into the inline coupling and

tighten the coupling so that the FRP mast and lower mast material

are secured tightly into position.

• If a guy kit is to be installed the guys should be securely fixed to the

eyelets as provided on the inline coupling. See figure 34 page 37.

• Refer to page 35 for instructions on how to safely raise the mast.

·

Refer to page 32 onwards for more detailed information on

preparation and raising of the mast.

http://www.chongset.com. Tel: 08 3968 2884: Phân phi kim thu sét

Stormaster ESE 15, ESE 30, ESE 50, ESE 60

Hướng dẫn lắp đặt kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30, ESE 50, ESE 60

Figure 2.

http://www.chongset.com. Tel: 08 3968 2884: Phân phi kim thu sét

Stormaster ESE 15, ESE 30, ESE 50, ESE 60

Hướng dẫn lắp đặt kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30, ESE 50, ESE 60

Figure 3.

http://www.chongset.com. Tel: 08 3968 2884: Phân phi kim thu sét

Stormaster ESE 15, ESE 30, ESE 50, ESE 60

Hướng dẫn lắp đặt kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30, ESE 50, ESE 60

Figure 4.

http://www.chongset.com. Tel: 08 3968 2884: Phân phi kim thu sét

Stormaster ESE 15, ESE 30, ESE 50, ESE 60

Hướng dẫn lắp đặt kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30, ESE 50, ESE 60

Figure 5.

http://www.chongset.com. Tel: 08 3968 2884: Phân phi kim thu sét

Stormaster ESE 15, ESE 30, ESE 50, ESE 60

Hướng dẫn lắp đặt kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30, ESE 50, ESE 60

Figure 6.

http://www.chongset.com

. Tel: 08 3968 2884 : Phân phối kim thu sét Stormaster ESE 15 , ESE 30 , ESE 50 , ESE 60

12

Hướng dẫn lắp đặt kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30, ESE 50, ESE 60

Figure 7.

http://www.chongset.com

. Tel: 08 3968 2884 : Phân phối kim thu sét Stormaster ESE 15 , ESE 30 , ESE 50 , ESE 60

13

Hướng dẫn lắp đặt kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30, ESE 50, ESE 60

Checking

Lightning

Protection

Components

Supplied

The LPI Stormaster ESE components received should be checked against the “Bill of materials” for loss during shipping and for damage.

Check the following:

Terminal (s)

• Terminals have not been dented or damaged in any way during transit.

Downconductor(s)

• The HVSC cable drum (if supplied) is not damaged.

• The correct HVSC length(s) have been supplied.

• No obvious damage to the HVSC cable.

• If a factory completed upper termination is supplied check to see

that the termination is not damaged.

Lengths and quantities of HVSC (if multiple lengths on one drum), will be shown on the side of the Cable Drum(s).

LPI STORMASTER ESE Installation

All site and safety requirements must be followed during the installation of the LPI Stormaster ESE.

The correct order of installation is as follows:

1. Installation of the lightning earth.

2. Installation of the HVSC downconductor.

3. Lower termination of the HVSC downconductor and connection to

the lightning earth.

4. Upper termination the HVSC downconductor and connection to the

Stormaster ESE terminal.

5. Preparation and raising of the mast into position.

LPI Stormaster ESE should only be installed during storm-free

periods.

If the Stormaster ESE terminal needs to be raised prior to connection to the lightning earth or immediate connection is not possible then connect the lower end of the downconductor to structural steel reinforcing or other suitable earth point.

http://www.chongset.com

. Tel: 08 3968 2884 : Phân phối kim thu sét Stormaster ESE 15 , ESE 30 , ESE 50 , ESE 60

14

Hướng dẫn lắp đặt kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30, ESE 50, ESE 60

Installation of the Lightning

Earth

Before installation of the lightning protection earth consult site drawings of underground services so that these are not damaged during installation of the earthing system.

Earth DC resistance (typically ‹10 ohms) and impendence (typically ‹30 ohms) is required for successful operation of LPI Stormaster ESE.

Figure 8.

LPI recommends the installation of a radial lightning earth as shown in figure 8.

• Recommended to install a 3 length radial trench.

• Each radial will consist of a trench (Approx: 500mm Deep x 200mm

wide x 10m length).

• An earth rod should be driven at the end of each trench.

• All rods should be interconnected through the use of 25mm x 3mm

copper tape. The use of earth rod clamps to fix the tape to rods is

recommended.

http://www.chongset.com

. Tel: 08 3968 2884 : Phân phối kim thu sét Stormaster ESE 15 , ESE 30 , ESE 50 , ESE 60

15

Hướng dẫn lắp đặt kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30, ESE 50, ESE 60

• The application of earth enhancing compounds such as LPI RESLO

and GRIP assists to reduce soil resistivity to the recommended level

of less than 10 ohms.

• A ground pit should be installed where the end of the down-

conductor terminates to the lightning earth as shown in figure 8.

This gives an access point for disconnection and future testing.

• Do not lower terminate (connect) the downconductor to the earthing

system at this point in time.

Note: If due to space constraints it is not possible to install a radial earth as recommended consult with LPI or an authorised distributor for further advice.

When using earth rods:

• Use driving heads to prevent mushrooming on top of rod.

• Use driving heads when using coupled rods.

• Use a post or picket driver.

Methods for bonding the earthing system components are listed below:

• The use of the EXOWELD exothermic welding process is a safe

and efficient way of providing a permanent connection between

conductors. EXOWELD connections will not corrode or rust with age.

• DO NOT use aluminium lugs or couplings

Ground

Resistance

Lowering

Compounds

• Ground resistance lowering compounds (such as LPI RESLO and

GRIP) are supplied when the existing soil mass has a high

resistivity.

• Using the compounds can lower earth resistance/impedance.

• Compounds will require water and a mixing container.

• Follow all installation and safety instructions as supplied with

products when applying the compounds.

Bonding the

Lightning

Earth

Where separate earths exist eg: Structure, Power, Communications and

Lightning Protection, they need to be bonded to form an equipotential ground plane. This will stop ground loops and potential differences arising under transient conditions.

http://www.chongset.com

. Tel: 08 3968 2884 : Phân phối kim thu sét Stormaster ESE 15 , ESE 30 , ESE 50 , ESE 60

16

Hng dn lp t kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30,

ESE 50, ESE 60

Before bonding of these earths takes place make sure proper authorisation is gained.

Bonding cable must be 70mm (2/0AWG) minimum depending on local standards. It may be necessary to use a Transient Earth Clamp (LPI

TEC) which bonds all earths to the same potential under transient conditions.

For further information, it is advisable that local applicable standards are used, ie IEC 61024-1, BS 6551, AS1768-2003, NFPA 780. C22.1

-98 and NEC.

Labelling

Installation of the HVSC

Downconductor

Hauling the

HVSC Downconductor

It is the responsibility of the customer/installer to label earth pits or earthing systems to local requirements.

If installing LPI HVSC, the HVSC downconductors(s) may have had the upper terminations completed at a pre-specified end of the cable by the

LPI factory before being shipped.

When removing HVSC downconductor packaging, do not use a knife or cut in any way as this can damage the outer layer of termination.

LPI’s HVSC has an outer layer which is approximately 2mm (1/16in.) thick. Be careful not to damage this layer.

Place the HVSC downconductor cable drum close to where it is to be installed.

Figure 9.

http://www.chongset.com

. Tel: 08 3968 2884 : Phân phối kim thu sét Stormaster ESE 15 , ESE 30 , ESE 50 , ESE 60

17

Hướng dẫn lắp đặt kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30, ESE 50, ESE 60

• Make sure that the cable drum is in a good condition.

• Check that the correct length of HVSC downconductor has been

supplied. The length of HVSC will be marked on the drum.

• If the HVSC downconductor has been upper terminated on the

outside of the drum, then the HVSC downconductor will need to be

hauled up the structure with the drum staying on the ground.

• If the HVSC downconductor has been upper terminated on the

inside of the drum, then the drum has to be taken to the top or near

the top of the structure, then the HVSC downconductor can be

hauled downwards from the drum to the ground.

• Any lifting slings or ropes must be securely attached.

• DO NOT haul the HVSC downconductor from the termination lug, see

Figure 10.

• Protect the HVSC downconductor at all times when it is being

moved.

Figure 10.

http://www.chongset.com

. Tel: 08 3968 2884 : Phân phối kim thu sét Stormaster ESE 15 , ESE 30 , ESE 50 , ESE 60

18

Hướng dẫn lắp đặt kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30, ESE 50, ESE 60

HVSC Downconductor

Clearance

Holes

Before running the HVSC downconductor through any clearance holes, ensure that:

• A minimum hole diameter of 60mm (23/8in.) is used.

• Enough protection is provided so that the HVSC downconductor is

not damaged.

A waterproofing sealant or sealing gland should be used if the hole needs to be weatherproof.

Routing

The routing of the HVSC downconductor needs to follow these guidelines:

The route of the HVSC downconductor should be as set out in the original design. Ensure no structural changes such as new antenna or mast installations, air conditioning towers or ducting has been installed.

• DO NOT double the HVSC downconductor back against itself after

changes of direction, ie: 180°.

• The HVSC downconductor may be installed internally or externally

on the structure.

• The HVSC downconductor should be installed as close (flush) as

possible to the structure.

• Minimise the number of bends and use the most direct route to

ground.

• Minimise strain on the HVSC downconductor.

• Ensure bend radius maintained ›500mm (20in.).

• Parallel routing with other services – Minimum separation = 20cm.

See Figure 11 on page 20.

• If the HVSC downconductor has to cross other services make sure it

crosses at right angles using a conduit that extends at least 1m past

either side of the existing service.

• The lower end of the HVSC downconductor must terminate close to

the initial injection point of the lightning earth.

• Be sure to allow for enough slack in the HVSC at the top end for

connection to the Stormaster ESE Terminal and the raising of the

mast.

• If it is necessary to isolate the HVSC downconductor from the

structure put the cable in an insulating conduit with a minimum wall

thickness of 3mm (1/8in.). The maximum length isolated from the http://www.chongset.com

. Tel: 08 3968 2884 : Phân phối kim thu sét Stormaster ESE 15 , ESE 30 , ESE 50 , ESE 60

19

Hướng dẫn lắp đặt kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30, ESE 50, ESE 60

structure should be 2.5m (9ft). The entire length of the HVSC down-

conductor cannot be run in insulated conduit.

• HVSC Downconductor should be protected from damage at the

lower end by installing a sleave of no more than 2m from ground

level.

The HVSC downconductor must be checked by an LPI representative if it is damaged during installation to see if the damage will affect performance.

Radius <500mm

INCORRECT

Radius >500mm

2m Max.

20cm

20cm

CORRECT

Figure 11.

http://www.chongset.com

. Tel: 08 3968 2884 : Phân phối kim thu sét Stormaster ESE 15 , ESE 30 , ESE 50 , ESE 60

20

Hướng dẫn lắp đặt kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30, ESE 50, ESE 60

Using non LPI saddles can damage the downconductor outer sheath.

Fixing the

HVSC Downconductor

• The HVSC downconductor should be fixed to the structure every 2m

for the entire length of the run.

• For masonry walls or roofs, use the LPI saddles provided. These

can be used with masonry anchors, suitable fastenings for wood,

fibreglass and metallic surfaces or self tapper screws.

• Use cable ties when fixing to pipes, tower legs, masts, etc.

• If the HVSC downconductor is to be routed above a false ceiling,

ensure that it is fixed to the underside of the concrete floor slab.

• Do not use explosive fastening methods on LPI saddles or

HVSC downconductors.

Installation of

Conventional

Downconductors

In some installations the use of copper tape or insulated stranded copper cable may be installed as the downconductor. In such cases it may be necessary to install multiple downconductors in compliance with local standards. (NFC 17-102, AS1768-2003, BS6651). See the following dot points for further information.

The Stormaster ESE Terminal provides a bolt for the lug connection to the lower finial connector of the mast butt adaptor. All conventional downconductors should be lugged and fixed to the terminal as per figure 12 below.

Figure 12.

http://www.chongset.com

. Tel: 08 3968 2884 : Phân phối kim thu sét Stormaster ESE 15 , ESE 30 , ESE 50 , ESE 60

21

Hướng dẫn lắp đặt kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30, ESE 50, ESE 60

The following are recommendations and points that should be considered when installing conventional downconductors.

• Downconductors should be installed at each external corner of

the building and additional downconductors installed at spacing not

exceeding 20m.

• The most direct path to ground is recommended avoiding sharp

bends.

• Downconductors should be installed around the outside walls of the

structure. It is not recommended to install downconductors

internally to the structure.

• It is not recommended to locate downconductors in areas where

personnel are liable to congregate.

• Any extended metal running vertically through the structure should

be bonded to the lightning downconductor at the top and bottom of

the structure.

• Each downconductor should be connected to the earthing system.

• Where practical all structural steel and metallic reinforcement in the

structure should be bonded to the downconductor system.

• The use of copper conductors are recommended and should have a

cross sectional area of not less than 35mm

2

.

• Recommended copper conductor size is 25mm x 3mm.

• The copper should be of a grade normally used for commercial

electrical work.

• The use of PVC insulated copper, bare aluminium and stainless steel

can be used as downconductors.

• Suitable fasteners should be installed to adequately secure all

downconductors.

• Downconductors should be fastened at spacings not exceeding 1.0m

on horizontal runs and not exceeding 1.5m on vertical runs.

Installation of Stormaster

GI Terminal to threaded pipe

LPI offers within it’s range of Stormaster terminals a GI version which is designed for a threaded connection to a 2 inch GI pipe. Please refer to drawing ST-2 on page 12 and figure 13 for further details.

The Stormaster GI terminal is supplied with a threaded coupler (female thread) fixed to the terminal and designed for connection to a 2 inch pipe (Male thread). http://www.chongset.com

. Tel: 08 3968 2884 : Phân phối kim thu sét Stormaster ESE 15 , ESE 30 , ESE 50 , ESE 60

22

Hướng dẫn lắp đặt kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30, ESE 50, ESE 60

Figure 13.

Figure 14.

http://www.chongset.com

. Tel: 08 3968 2884 : Phân phối kim thu sét Stormaster ESE 15 , ESE 30 , ESE 50 , ESE 60

23

Hướng dẫn lắp đặt kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30, ESE 50, ESE 60

• Following installation of the Stormaster GI terminal to the threaded

pipe as per drawing ST-2 and figure 13 it will be necessary to

connect the metallic pipe to a conventional downconductor in order

to convey the lightning energy to the earthing system.

• Ideally the connection between the metallic pipe and the

conventional downconductor should be completed by lugging

or exothermically welding (LPI EXOWELD) the downconductor at a

practical point somewhere along the length of the pipe.

• Particular care should be taken to ensure that compatible metals are

used when connecting the downconductor to the metallic pipe.

• For installation details of the conventional downconductor please

review instructions and comments as detailed under the heading

Installation of Conventional Downconductors on page 21.

Termination of the HVSC Lower End

Tools required for the completion of the HVSC Lower Termination include:

• Compression or Mechanical Crimping Tool

• Sharp Knife

• Insulation Friction Cutting Tool

• Shifting Spanner

• Rubber Gloves

Lower Termination Kit Consists of

1 x Roll Denso Tape

1 x 95mm Crimp Lug

2 x Warning Stickers

1 x Earth Clamp

1 x Insulation Friction Cutting Tool

The following steps outline the termination of the lower end of the High

Voltage Shielded Cable to the lightning earth.

The inner screen copper conductors and the outer screen copper conductors should be connected to the earthing system.

http://www.chongset.com

. Tel: 08 3968 2884 : Phân phối kim thu sét Stormaster ESE 15 , ESE 30 , ESE 50 , ESE 60

24

Hướng dẫn lắp đặt kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30, ESE 50, ESE 60

Figure 15.

1. Remove the outer sheath for a length of 15cm from the lower end of the HVSC by cutting radially around HVSC cable with the supplied insulation friction cutting tool. (This is less likely to damage individual copper conductors than by cutting radially with a knife).

The lengthwise cut can be completed with a knife.

2. Remove the binder tape (2 nd

layer) for a length of 15cm from the end of the HVSC, this will expose the outer screen copper conductors as shown in Figure 16.

Figure 16.

3. Fold outer screen conductors back without damaging them. For a length of 5cm from the end of the HVSC remove XLPE insulation (4 th layer) and inner binding tape (5 th layer) to expose inner screen copper conductors. Be sure not to remove outer screen conductors in this step. It is recommended to use the insulation friction cutting tool in this step.

4. Fold inner screen conductors back without damaging them. For a length of 5cm from the end of the HVSC remove the inner PVC spacer under the inner screen copper conductor leaving the inner screen copper conductor in place.

Figure 17.

http://www.chongset.com

. Tel: 08 3968 2884 : Phân phối kim thu sét Stormaster ESE 15 , ESE 30 , ESE 50 , ESE 60

25

Hướng dẫn lắp đặt kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30, ESE 50, ESE 60

5. Bunch together both inner and outer screen conductors. If con- necting directly to the earth system as per figure 20 then the bunched conductors should be connected to the earth rod clamp and the clamp tightened holding the conductors firmly in place. To avoid oxidisation of this connection seal it using the water resistant

(Denso Tape) as provided in the kit.

Figure 18.

6. If terminating the lower end of the HVSC to a bus bar then bunch together both inner and outer screen conductors, crimp them together in the crimp lug provided using a compression or mechanical crimping tool and connect the bus bar as per Figure 19.

HVSC

LSR1

Compression

Lug

Copper

Bus Bar

Figure 19.

To Earthing System

http://www.chongset.com

. Tel: 08 3968 2884 : Phân phối kim thu sét Stormaster ESE 15 , ESE 30 , ESE 50 , ESE 60

26

Hướng dẫn lắp đặt kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30, ESE 50, ESE 60

STEP 1.

STEP 2.

Ground Level

HVSC

Downconductor

HVSC

Downconductor

Denso Tape

Earth Rod Clamp

Earth Rod Earth Rod

Figure 20

Lower

Termination of

Conventional

Downconductor to the Lightning

Earth

If a conventional downconductor such as copper tape or stranded copper cable has been installed as the downconductor then the lower end of the conductor should be directly connected to the lightning earth and sealed with a water resistant Denso tape so as to avoid oxidisation.

• If installing stranded copper cable as a downconductor then the

lower end should be connected to the lightning earth through the

use of a earth rod clamp and then wrapped with water resistant

Denso tape to avoid oxidisation.

• If installing a copper tape (25mm x 3mm) as a downconductor then

the lower end should be directly connected to the lightning earth

through the use of a suitable earth rod clamp and then wrapped

with water resistant Denso tape to avoid oxidisation.

Termination of the HVSC Upper End

Tools Required for the completion of the HVSC Upper Termination

Include:

• Compression or Mechanical Crimping Tool

• Sharp Knife

• Insulation Friction Cutting Tool

• Shifting Spanner

• Rubber Gloves http://www.chongset.com

. Tel: 08 3968 2884 : Phân phối kim thu sét Stormaster ESE 15 , ESE 30 , ESE 50 , ESE 60

27

Hướng dẫn lắp đặt kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30, ESE 50, ESE 60

Upper Termination Kit Consists of:

1 x 2.25m/19mm Semi Conductive Tape

1 x 50mm Crimp Lug

1 x 0.5m /38mm Mastic Tape

1 x 15cm Cold Shrink

The following steps outline the terminating of the upper end of the High

Voltage Shielded Cable.

1. In preparation for the upper termination of the HVSC it is important

to feed the HVSC cable through the FRP Support mast prior to

starting the upper termination. Refer to figure 21.

Draw HVSC Downconductor through

FRP Mast before terminating upper end

Figure 21

Downconductor FRP Mast

(2 or 3 metre)

2. Firstly remove the outer sheath material for a length of 1.2 metres

by cutting radially around HVSC cable with the supplied insulation

friction cutting tool. (This is less likely to damage individual copper

conductors than by cutting radially with a knife). The lengthwise cut

can be completed with a knife.

3. Cut and remove the outer screen copper conductors 3 cm above the

end of the outer sheath.

Figure 22.

http://www.chongset.com

. Tel: 08 3968 2884 : Phân phối kim thu sét Stormaster ESE 15 , ESE 30 , ESE 50 , ESE 60

28

Hướng dẫn lắp đặt kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30, ESE 50, ESE 60

4. Fold the outer screen copper conductors back over the outer sheath,

secure the outer screen conductors in place by wrapping 50cm of

the HV insulation tape provided (5cm covering XLPE insulation, 5cm

covering folded screen over the outer sheath).

Figure 23.

5. Remove XLPE insulation (4th layer) and inner binding tape (5th

layer) to expose inner screen copper conductors for a length of

5cm from the top end of the HVSC. It is recommended to use the

insulation friction cutting tool in this step.

6. Fold back inner screen copper conductors and for a length of 5cm

from the end of the HVSC, remove the inner PVC spacer under the

inner screen copper conductors and return these conductors to their

original position.

7. Crimp the inner screen copper conductors in the crimp lug provided

using a compression or mechanical crimping tool.

Figure 24.

8. Slide cold shrink onto the cable in preparation for later step (ensure

release strap is coming out from inside white tube at the lower end

i.e. The other end from the crimp lug so the cold shrink contracts

from top to bottom but with the strap being pulled out from the

inside of the bottom of the cold shrink).

http://www.chongset.com

. Tel: 08 3968 2884 : Phân phối kim thu sét Stormaster ESE 15 , ESE 30 , ESE 50 , ESE 60

29

Hướng dẫn lắp đặt kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30, ESE 50, ESE 60

Note: The cold shrink should be placed into position in this step,

however it should not be applied until step 11.

9. The lugged HVSC is now ready to be connected to the base of

the Stormaster ESE terminal. Take the mast butt adaptor as

supplied in the Stormaster box and screw the mast butt adaptor

firmly into the base of the Stormaster terminal. Connect the crimp

lug to the Stormaster terminal mast butt adaptor using the nut and

bolt as supplied with the mast butt adaptor. Ensure the connection

is tightly secured.

Figure 25.

10. Using the 19mm semi conductive tape (2.25m) apply the tape

starting at the white XLPE material and continue to the mast butt

adaptor. Build up as smooth a finish as possible from the insulation

to the bottom of the mast butt adaptor.

Figure 26.

11. Place the cold shrink up against the bottom of the mast butt

adaptor, pull the release strap away from the mast butt adaptor

(rotate around the cable as the release strap is pulled to ensure http://www.chongset.com

. Tel: 08 3968 2884 : Phân phối kim thu sét Stormaster ESE 15 , ESE 30 , ESE 50 , ESE 60

30

Hướng dẫn lắp đặt kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30, ESE 50, ESE 60

semi conductive tape is not effected by cold shrink application

process). When the cold shrink is applied it should be situated hard

up against the mast butt adaptor and continue 15cm down the cable

covering the entire semi conductive taped connection.

Connection of

Factory Pre-

Terminated

HVSC (Upper

End) to

Stormaster

Terminal

Tools required for the installation of the factory completed upper termination include:

• Sharp Knife

• Medium size Phillips head screw driver

1. Firstly remove the protective packaging from the cable and upper

terminated end section taking care not to cut cable or associated

upper termination parts in the process.

2. Using Phillips head screwdriver remove screw holding mast butt

adaptor to lower connector and retain both screw and mast butt

adaptor.

3. In preparation for completion of the installation of the factory

completed upper termination it is important to feed the HVSC cable

through the FRP support mast.

4. Once the terminated HVSC has been carefully fed through the top

end of the FRP mast, slide the black plastic mast butt adaptor back

onto brass lower connector, line up holes and insert phillips head

screw into position tightly. Now screw the mast butt adaptor into the

Stormaster terminal.

Figure 27.

Labelling

Warning Labels are supplied with all Stormaster ESE terminals and should be installed as per the following.

• In locations where personnel may be in close contact to the HVSC

Downconductor.

http://www.chongset.com

. Tel: 08 3968 2884 : Phân phối kim thu sét Stormaster ESE 15 , ESE 30 , ESE 50 , ESE 60

31

Hướng dẫn lắp đặt kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30, ESE 50, ESE 60

• Where the HVSC downconductor connects to the earthing system.

• At the base of the support mast.

There are 2 Warning Label’s supplied in the front cover of this manual and also 2 supplied in the lower termination kit. If more labels are required, contact your nearest LPI supplier or Distributor.

Masts

The mast chosen for the application must:

• Raise the terminal to a height of at least 2 metres (6.5ft.) higher

than the structure. (Minimum accepted).

• An (FRP) mast section of at least 2 metres (81 in.) must be used

below the air terminal, if using LPI HVSC.

• Be suitable for local weather conditions. Seek guidance from a local

civil engineer.

• Be guyed and securely attached to the dedicated mounting points if

required.

Types of Mast

Configurations

When mounting a Stormaster ESE terminal there are generally three types of mast configurations that can be used.

Cantilevered

Typically used for mounting to a tower or the side wall of a plant room when a mast and base are not suitable. See drawings ST-1, SW-1 and Figure 28 .

• 1/3 of the overall mast height must be

fixed to the structure for adequate mechanical

strength.

• Cantilevered masts can be guyed for

additional strength. If guying the use of a guy

ring and or the eyelets provided on the inline

coupling can be utilized.

Figure 28.

Cantilevered Mast

http://www.chongset.com

. Tel: 08 3968 2884 : Phân phối kim thu sét Stormaster ESE 15 , ESE 30 , ESE 50 , ESE 60

32

Hướng dẫn lắp đặt kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30, ESE 50, ESE 60

Guyed

When mounting a Stormaster ESE terminal a typical guyed configuration would involve the following. See drawing SM-1 and Figure 29.

• Two sections of mast (Aluminium mast

& FRP mast) coupled together with a inline coupling. Securing of guy wires is completed at the eyelets as provided on the inline coupling.

• Alternatively a guy ring can be supplied which is installed at the neck of the mast in between the Stormaster terminal and the top section of the FRP. The guy ring provides eyelets for connection of the guy wires.

Figure 29. Guyed Mast

Freestanding

A freestanding mast configuration is typically used in situations where protection by isolation is required. For example a

Stormaster ESE terminal is installed 5 metres or more away from a fuel storage tank.

Prior to installing the freestanding mast ensure that:

• A spigot has been supplied with the freestanding mast which allows for external or internal mounting of the FRP mast.

• The downconductor can exit through the base of the freestanding mast if run internally.

• Adequate information is provided for mast foundation requirements.

Figure 30.

Freestanding Mast

Mast Bases

LPI supplies a mast base welded directly onto the required length of aluminium mast. The base has a hole in the bottom for the downconductor to run if being routed inside the mast. Ordering Code:

ALUMB-3M.

http://www.chongset.com

. Tel: 08 3968 2884 : Phân phối kim thu sét Stormaster ESE 15 , ESE 30 , ESE 50 , ESE 60

33

Hướng dẫn lắp đặt kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30, ESE 50, ESE 60

Mast

Couplings and

Guying Points

There are two methods of coupling two sections of mast:

1. The U-Bolt set uses two stainless steel U-Bolts to clamp the two

masts together.

2. The inline coupling fixes the upper and lower mast sections

together and provides guying points and an exit point for the HVSC

downconductor.

Figure 31.

U-Bolts and Inline Couplings nuts must be tightened to no more than

55kg/cm (45in.lb).

A Guying Ring is supplied for guy points for any two piece masts that require double guying. This fits on the terminals mast butt adaptor between the Stormaster ESE terminal and the top of the mast. See Figure

32 under the heading titled Guying.

Guying

LPI offers a standard 4m (13 ft) guy kit made up of light weight plastic coated fibreglass non-conductive cable. If using conductive guy lines they must be connected at the lower anchor points to the downconductor by a conductor, or alternatively use appropriate guying insulators.

http://www.chongset.com

. Tel: 08 3968 2884 : Phân phối kim thu sét Stormaster ESE 15 , ESE 30 , ESE 50 , ESE 60

34

Hướng dẫn lắp đặt kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30, ESE 50, ESE 60

Figure 32.

Important Recommendations:

• The guying angle must be no greater than 60° from horizontal.

• The inline coupling couples the upper and lower mast sections

and provides guying points and an exit point for the HVSC

downconductor.

• Minimum of 3 guying grips per guy end.

• Guying grips spaced at a minimum of 30mm (1 in.).

• Grips are correctly orientated –saddle on the longer length side of

the guy and U-bolt over the tail side of the guy.

• Tighten grips to no more than 60cN.m (5Ibf.in) of torque.

• Customised guy kits can be supplied upon request.

Preparation and Raising of the Mast into

Position

• With the upper termination of the HVSC completed and the FRP mast

in position it is now time to finalise the mounting arrangement so

that the mast can be raised and secured into position.

• If using the recommended installation methods as per drawings

GA-1, SM-1, SW – 1 & ST-1 fit the inline coupling to the lower mast

material.

http://www.chongset.com

. Tel: 08 3968 2884 : Phân phối kim thu sét Stormaster ESE 15 , ESE 30 , ESE 50 , ESE 60

35

Hướng dẫn lắp đặt kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30, ESE 50, ESE 60

• Fit the HVSC downconductor in and out of the slot in the coupling.

Refer to Figure 34 on page 37.

• Carefully fit the mast adaptor of the Stormaster terminal into the top

of the FRP.

• It may be necessary to pull back any slack of HVSC downconductor

through the FRP support mast to achieve a tight fit for the

Stormaster terminal. This should be completed carefully so as to not

damage the upper termination.

• Now fix the FRP support mast firmly into the inline coupling and

tighten the coupling so that the FRP mast and lower mast material

are secured tightly into position.

• If a guy kit is to be installed the guys should be securely fixed to

the eyelets as provided on the inline coupling and or the guy ring.

See text and graphics as detailed under the heading Guying for

more information.

When raising the mast.

Raising of

Mast

• Guys to inline coupling and or guy ring must be properly secured.

• Guys must not be twisted, kinked or damaged.

• Guys must be able to be easily secured at the base when the mast

has been raised.

Turnbuckles or Rigging Screws are recommended at the base anchor points of the guys.

Other guying methods such as conductive stainless steel can be used only on aluminium masts or inline couplings below an FRP section.

Using a crane is recommended or other suitable equipment for anything over 6 metres (20ft.) in height, or for hazardous areas such as heights.

• It is very important to keep the mast straight during the lift to avoid

damaging the mast.

• The Stormaster ESE terminal must NOT be used as a slinging point.

• When lifting the mast, ensure that the slings or ropes cannot

damage the Stormaster ESE terminal, see Figure 33.

• When lifting the mast the HVSC downconductor must be tied off

to the mast to remove any strain on the HVSC downconductors

termination to the Stormaster ESE terminal.

http://www.chongset.com

. Tel: 08 3968 2884 : Phân phối kim thu sét Stormaster ESE 15 , ESE 30 , ESE 50 , ESE 60

36

Hướng dẫn lắp đặt kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30, ESE 50, ESE 60

Figure 33.

• Protect the HVSC downconductor at the base of the mast when

lifting, maintain a minimum bending radius of 500mm (20 in.) and

ensure it does not drag over rough or sharp surfaces.

Figure 34.

http://www.chongset.com

. Tel: 08 3968 2884 : Phân phối kim thu sét Stormaster ESE 15 , ESE 30 , ESE 50 , ESE 60

37

Hướng dẫn lắp đặt kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30, ESE 50, ESE 60

Lightning

Strike

Recorder

(LSR1)

The Lightning Strike Recorder (LSR1) should be installed at a position along the downconductor length where it can be accessed easily for inspection. Typically the LSR1 should be installed approximately 1.5m from ground level or alternatively within the ground pit at the lower termination point of the HVSC.

When installing the LSR1 the following should be considered.

• The LSR1 should be mounted away from areas where damage may

occur due to theft, vandalism or damage from nearby operations.

• The LSR1 can be enclosed in a security enclosure but the display

should be kept visible to allow for the checking of recorded strikes.

Figure 35.

Lightning

Strike Recorder installed on HVSC

Downconductor

Figure 36.

Lightning Strike

Recorder installed on Rod.

http://www.chongset.com

. Tel: 08 3968 2884 : Phân phối kim thu sét Stormaster ESE 15 , ESE 30 , ESE 50 , ESE 60

38

Hướng dẫn lắp đặt kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30, ESE 50, ESE 60

Certification

The certification of the LPI Stormaster ESE installation should be performed by an authorised LPI representative.

A certificate of compliance and warranty registration is provided with the installation manual. This certificate should be completed in full following the successful inspection and certification of the installation.

The following should be checked for quality of workmanship and compliance to recommended installation instructions.

Certification checklist

• Correct mast and any associated brackets and fastenings have been

used for installation.

• Guying, anchor points and fastenings.

• HVSC Downconductor routing, fixing and weatherproofing.

• Lower termination of HVSC Downconductor.

• Earthing System.

• Labelling.

Operation and

Maintenance

The LPI Stormaster ESE Lightning Protection System is designed to react to the rise in electric field which is present in approaching thunder storms. The Stormaster ESE Terminal becomes active only during storm activity.

• The system operates without the need for external power supply or

spare parts for standard operation.

• To keep the LPI Stormaster ESE Lightning Protection System

operating at optimum levels it needs to be regularly checked.

Maintenance checks must be done:

• After each known lightning strike to the terminal.

• Once every twelve months.

• If changes have been made to the structure.

Checks to be conducted in standard maintenance inspection:

• Is there any damage to Stormaster ESE system?

• Has the structure to be protected been modified since the last

maintenance check?

• Check finial tip for excessive pitting.

http://www.chongset.com

. Tel: 08 3968 2884 : Phân phối kim thu sét Stormaster ESE 15 , ESE 30 , ESE 50 , ESE 60

39

Hướng dẫn lắp đặt kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30, ESE 50, ESE 60

• Check all rigging, mast mounts, saddles and conductor fixings are

secure and tight.

• Ensure that no dirt or other matter is sitting in the air gap between

the finial tip and the surrounding panel edges.

• If conventional downconductors are used, check that all conductors

are securely fixed and not damaged.

• Check for damage to the LPI HVSC, the installed position of the

downconductor should not be able to be accessed by non

authorised people or machinery.

• All warning labels must still be in place.

• Check LSR1 for secure installation and record number of strikes.

Testing the

Stormaster

Terminal

LPI manufactures and supplies a terminal spark-over tester suitable for testing the Stormaster ESE range of terminals. Contact your local distributor for further details.

Testing the

Lightning

Earth and the

HVSC Downconductor

Use the table on page 41 to record the results following completion of the following steps.

1. Remove the waterproofing denso tape from the lower termination.

2. Disconnect the HVSC downconductor from the lightning earth.

3. Disconnect the structure earth bonding cable from the earth system.

4. Measure the earth resistance of the lightning earth system and

record in column 1 under the heading Earth Resistance Readings in

the table provided on page 41.

5. Measure the earth resistance of the structure and record in column 2.

6. Reconnect the structure earth bonding cable to the lightning earth

and measure and record in column 3 the earth resistance reading.

7. Use a multimeter to measure the continuity between the inner and

outer conductors of the HVSC downconductor. The measurement

should exceed 10,000 ohms.

8. Reconnect the HVSC lower termination to the lightning earth and

re-seal the termination using denso tape to ensure that it is

waterproof.

9. Reconnect the structure earth bonding cable to the lightning earth.

10. Report any problems arising from the above tests to your local LPI

distributor for further advice.

http://www.chongset.com

. Tel: 08 3968 2884 : Phân phối kim thu sét Stormaster ESE 15 , ESE 30 , ESE 50 , ESE 60

40

Hướng dẫn lắp đặt kim thu sét Kim thu sét LPI Stormaster ESE 15, ESE 30, ESE 50, ESE 60

Ground Resistance�

Meter

HVSC Downconductor�

(Disconnected from�

LP Earth)

LP Earthing System

Structure Earth Cable�

(Disconnected from�

LP Earth)

Figure 37.

Date of Inspected

Inspection by:

Earth Earth Earth LSR

Resistance Resistance Resistance Reading

Reading #1 Reading #2 Reading #3

Comments

IMSTORM-V4 http://www.chongset.com

. Tel: 08 3968 2884 : Nhập khẩu và phân phối kim thu sét Stormaster ESE 15 , ESE 30 , ESE 50 , ESE 60

41

advertisement

Key Features

  • ESE Technology
  • Protection Radius
  • High Voltage Shielded Cable
  • Modular Mast System
  • Easy Installation
  • Comprehensive Warranty

Frequently Answers and Questions

What is the protection radius of a Stormaster ESE terminal?
The protection radius of a Stormaster ESE terminal is calculated using the formula defined by the French National Standard NF C 17-102.
How do I install the Stormaster ESE system?
The Stormaster ESE system should be installed in accordance with the recommended order of installation outlined in this manual.
What is the warranty on the Stormaster ESE terminals?
LPI's Stormaster ESE terminals are guaranteed against defects in materials and workmanship for a period of 5 years from the original sales date.
What types of masts can be used with the Stormaster ESE terminals?
The mast chosen for the application must raise the terminal to a height of at least 2 metres higher than the structure, be suitable for local weather conditions and be securely attached to the dedicated mounting points if required.