Septech 2000 is a Domestic Waste Water Treatment system. It provides a safe and environmentally friendly way to treat wastewater. The Septech 2000 system is designed to be easy to install and maintain. It is also highly efficient, reducing the amount of water and energy that is used. In order to install the system, you will need to have an excavator on site for the day of delivery.

advertisement

Assistant Bot

Need help? Our chatbot has already read the manual and is ready to assist you. Feel free to ask any questions about the device, but providing details will make the conversation more productive.

Septech 2000 Installation Instructions | Manualzz

Raharney, Mullingar, Co. Westmeath

TEL: (044) 74108 FAX: (044) 74552 email: [email protected]

www.shaymurtagh.ie

ELECTRICAL WIRING DETAILS

Fig 4

Client's Fuse Board

M

C

B

Septech 2000

Control Panel

Power Supply

7 Core Cable to Treatment Plant

An MCB from the client’s fuse board will supply the power to the Septech 2000 Control

Panel. If an RCBO is installed in the fuse board the MCB should receive the power from the Primary side of the RCBO, not power from the secondary side of the RCBO.

ELECTRICAL WIRING DIAGRAM FOR

SEPTECH 2000 CONTROL PANEL

Mains Switch

MCB 1

MCB 2

Aeration Hour Counter

24hr Timer

Fig 5

Transformer

Buzzer

Alarm Mute

Switch

Neutral

Bar (2,4)

Earth

Bar (7)

Mains Supply

Mains (L)

Aeration Pump (L) (3)

Percolation Pump (L) (1)

Design & Print by Mind’s I • 044 32926 • www.mindsi.ie

Float Switch 2 (6)

Float Switch 1 (5)

no.

no.

slope

Fig 2

EXCAVATION DETAIL

Fig 3

PERCOLATION DETAIL

Section through

Percolation Trench

Plan View of Trench

Septech 2000

– Domestic Waste Water Treatment system

Minimum Separation Distances in Metres

Watercours e Stream

Wells

Springs

Lake

Any

Dwelling

Site

Boundary

Road

Treatment

Plant

Percolation

Area

10m

10m

10m

30m

50m

50m

Installation:

1. The excavator must be on site on morning of delivery. The client must indicate the level of the inlet pipe at the hole. If ground conditions are dry, the hole can be dug before our installation personnel arrive.

Where the conditions are wet, the hole should only be excavated through the dry material and not below until the installer arrives. The level of rock on the site (if any) should be noted during the percolation test trial hole excavation. The client must have adequately sized rock breaking equipment where required. All excavation is the responsibility of the client.

7m

10m

3m

3m

4m

4m

Percolation Area:

1. For the percolation the following items are required.

Approx. 50m of normal gauge hydradare pipe

Minimum 1 no. 1_” Philmac Tee.

Minimum 20 tonnes 20-30mm clean round stone.

2. Check the planning guidelines for the required length of percolation pipe and whether the percolation is sub-surface or a raised bed.

2. The installer will explain the levels for the bottom of the hole as per Fig. 2

3. The outlet pipe of the Septech ends in a connector for the 1_” pipe. The percolation installer joins onto this pipe but only starts the stone when the percolation area is reached. Do not start the stone at the outlet from the Septech.

3. The truck arrives and the installer places the tanks in the hole with the truck mounted crane. The installer will assemble the interconnecting pipework and carry out the wiring of the tanks. The excavator may be required for backfilling at this stage. The excavation must be backfilled on the day of installation.

4. The percolation trenches should be constructed similar to Fig. 1 & Figure 3. The two inspection pots at the end of the pipe will arrive with the Septech.

Notes:

The inlet pipe into the Septech must be connected by the builder/owner.

4. The installer will leave the required amount of cable to run back into the house/garage.

The control panel will be left with the most senior person on site and this should be kept for the electrician for fixing and wiring.

When the lids are on the tanks and the backfilling is complete, the installer is finished.

Note :

Please have a mobile number for the excavator driver the evening before the installation.

Please indicate before the day of installation the level from the top of the finished ground to the invert of the inlet pipe. This is important to allow enough risers to be placed on the tanks.

Commissioning:

Normal use in a house will take 1-2 weeks for the tanks to fill up. When the tanks are nearly full the system is ready to be commissioned.

This involves the Service Engineer checking the installation and turning on the power. The

Septech warranty commences at the time of commissioning.

If you have any queries about Septech

Treatment Plants please contact us at the address on back page.

advertisement

Key Features

  • Domestic Waste Water Treatment system
  • Easy to install and maintain
  • Highly efficient
  • Environmentally friendly

Frequently Answers and Questions

What are the minimum separation distances for the Septech 2000 treatment plant?
The manual lists minimum separation distances in meters for various locations, including watercourses, streams, wells, springs, lakes, dwellings, site boundaries, and roads. Check the manual for specific distances.
What is the role of the excavator during the installation process?
The excavator is used for digging the hole for the tanks, backfilling after the tanks are installed, and possibly breaking any rocks on the site. The client is responsible for the excavation and providing necessary rock breaking equipment.
How long will it take for the tanks to fill up and the system to be ready for commissioning?
It will take approximately 1-2 weeks of normal household use for the tanks to fill up and the system to be ready for commissioning.