Installation Guide
The panels, flashings and trim shown in this guide, illustrated
over solid and plumb substrate, assume that the structure has
been designed and prepared in accordance with local building
codes.
Review and understand complete guide
before beginning installation. This guide
has been prepared as suggested details to
particular design conditions. Each condition
has certain limitations to performance, aethetics or economics.
Professionals qualified to assess the information regarding suitability for a specific project, should determine that the selection
and installation are made to their requirements. ATAS cannot
assume any responsibility for the actual selection and/or installation of materials.
For panel lengths over 15’ consult factory for proper
panel installation procedures.
“J” Channel
3 Panels @ 40” coverage nominal.
No attachment at this row to prevent distortion of panel
X - Stitch Screw
SWR8XX
Approximately 15/sq.
X - Anchor Screw
SWR9XX
Approximately 1 for every
8” of eave.
O - Screws
SWR6?? (for metal)
SWR7?? (for wood)
Approximately 38/sq.
O- RSS211 (for wood)
RSS210 (for metal)
Approximately 8/sq.
High points of
tile pattern (typ.)
Side Lap
(Joints)
PANEL LAYOUT FROM RIGHT TO LEFT
1. Start by stitching panels together from right to left, using fastener (x). Locate fasteners just below step, at high point of profile. Do not
fasten to substrate until 3 panels are stiched together.
2. Align 3 panel assembly along eave, allowing for 1/4” to 1/2” space within “J” receiver. Locate fasteners (X) in low point of panel.
3. Fasten panel at ridge line with fastener ( O ).
4. Fasten panels to substrate with fastener (O) at location shown.
5. Stitch subsequent panels to previous panel using fastener (X). Install panel at eave and ridge with fasteners (X). Fasten panel to substrate
using (O).
**During installation DO NOT stand on or over fastening point.
Note: For ease of installation, pre-drill the panels at ground level.
NOTE: Use extreme care not to overdrive the fasteners in the main field of the panel.
In high wind zones, additional fastening may be required. Consult governing codes.
Eave Detail
1. In re-roofing applications: cut back and remove
existing shingles and drip edge to be flush with the
eave and gable lines. Apply new eave and gable
trim as detailed.
Techo Tile Panel
Neoprene
Closure
2. Install ATA-Shield underalyment. Install drip edge.
Install ATA-Guard over drip edge.
Bottom
Closure
Angle
3. Install bottom closure angle beyond step,
approximately 4” from edge.
4. Install neoprene strip (optional) behind bottom
angle closure.
Eave
Trim
ATA-Guard
5. Fasten panel at low point making sure fasteners
penetrate solid substrate.
ATA-Shield
Gable Detail
1. Install channel flush with gable edge, fasteners 2’
min. o.c. Seal at fastener penetrations.
2.Install first panel or cut last panel to fit and install.
Leave 1/4 - 1/2” space in channel.
Techo Tile Panel
Gable Trim
ATA-Guard
J-Channel
3. Place gable trim cap over edge; fasten with
appropriate fasteners.
Valley Detail
1. Install ATA-Shield** 19” up both side of the valley
line.
Valley Cover
Techo Tile
Panel
Valley Clip
2. Install valley sheet, fasten with valley clips and
appropriate fasteners.
Valley Pan
3. Cut panel to angle, allow 2” to 3” from center of
valley, depending on length of panel.
4. Install panels on both sides of valley. Locate panel
fastener above valley pan.
5. Install cover (optional) with stitch screws.
Underlayments: ATA-Guard* is a polyolefin based, 100% asphalt
free, high strength reinforced roofing underlayment for use on
steep slopes beneath metal roofing. 1000 sq. ft. per roll at 48”
wide.
ATA-Guard
Underlayments: ATA-Shield** is the recommended self adhesive
underlayment for eaves, sidewall and any critical areas exposed
to ice damming and extensive water run off.
Available in 65’-8” x 3’ 3-3/8” rolls. (2000 sq. ft. per roll).
Hip & Ridge Detail
Hip Cap
Hip Closure
Hip and ridge applications are handled in the same
manner.
1. Install panels to meet the Hip/Ridge.
Techo Tile
2. Fasten top closure angle and neoprene closure
Panel
(optional) to panel using #12 x 1” pancake screw.
3. Apply butyl tape to top of closure angle, set
ridge/hip cap in place, fasten with stitch screw.
4. Prior to installing the last ridge cap, cut it to size and
fasten the end plug to the ridge cap before installing.
At the Hip:place a hip base over the hip, fasten with
clip (HPC903). Install the panel to the center of the hip
base. Install closure angle, put sealant at the edge of
the panel. Install hip cap.
Hip Base
ATA-Guard
Ridge Cap
Top
Neoprene
Closure
Techo Tile
Panel
Note: Do not cut any metal over an installed metal
roof. Do not use an abrasive saw for cutting metal.
When cutting the panels on the hips use a nibbler or a
Tenryu steel - pro blade for ferrous metals or equal. To
prevent metal particles from falling on the panel, turn it
upside down when cutting. Remove all chips and dust
immediately from roof panels.
Top Angle
Closure
ATA-Guard
Headwall Detail
Install appropriate underlayment to the edge.
1. Depending on the wall treatment, cut a reglet in the
wall.
2. Install panel to headwall.
3. Fasten top closure angle and neoprene closure
(optional) on the panel.
4. Install headwall trim over the panel while insuring that
the perpendicular section is flush to the wall.
Counterflashing
Headwall Trim
Techo
Tile
Panel
Top Angle Closure
Appropriate
Anchor
Screw
ATA-Guard
Shed Ridge Detail
1. Install panel to edge of roof.
Shed
Ridge
Cap
2. Fasten top closure angle and Neoprene Closure
(optional) to the panel, max. 5” from roof edge.
3. Put high quality sealant along curve of panel and on
top of closure angle.
Appropriate
Fasteners
Top Angle Closure
4. Fasten with appropriate fasteners.
Techo Tile
Panel
ATA-Guard
Sidewall Detail
1. Install ATA-Shield** below sidewall flashing and up
sidewall if possible.
2. Fasten channel with SWR8XX screws.
Sidewall Trim
3. Fit and install panel into channel.
Techo Tile
Panel
ATA-Guard
J-Channel
4. Install sidewall flashing prior to wall treatment or
cut a reglet and install counter flashing (not shown).
ATA-Shield
Note Regarding Trim Details
The applicaiton of flashing and trim requires a detailed approach. Consideration should be given to the roof’s geometry and course
it creates for water run-off. Location of gutters and the use of snow retention systems should also be considered. Proper planning
regarding the sequence of material overlap is critical. Sealants, such as butyl tapes and tripolymers, should be used at overlapping
trim edges, in conjunction with exposed fasteners, and to seal flashings and other ancillaries. All fasteners should be properly tightened and not overdriven at an angle. Fasteners that are too loose can “back out” over time. An overdriven fastener may cause a
depression in the material, which becomes a collection point for standing water.
Pipe Detail
Step 1
Cut on the proper pipe
diameter marked on the
flashing.
Step 2
Position over pipe and
slide down the pipe.
Step 3
Apply polyurethane
sealant to the bottom of
the base.
Pipe drawings provided by Triangle Fasteners
Tools and Rules:
Basic Equipment Required:
Tie-off ropes, safety harness, long level, ladders, scaffolding with
approved planking, extension cords with approved ground plugs and
services.
Additional Tools:
Metal folding tool, hammer, chalk line, measuring tape, metal cutting
tools - nibblers, drills, hacksaw, utility knife, pop-rivet gun, caulking
guns, layout and combination square, C clamps, sheet metal shears
(including RH, LH, straight and overhand). Power driven screw gun
with proper bits, depth setting nosepiece, variable speed.
Choose the correct equipment and tools to do the job in a safe
manner. Wear safety gear and follow OHSA requirements.
Step 4
Mold the flexible base
to the panel contours.
Step 5
Fasten with 1/4” x
1-1/8” drilling
fastener every 1-1/2”
around the base.
Follow of few simple rules:
1. Never cut the panels with an abrasive cut-off wheel or torch, as
this will damage the finish.
2. Do not weld the trim or panels.
3. Remove any small burrs left by cutting, screwing or drilling.
4. Remove protective masking immediately after trim is installed.
5. Caution should be taken when unloading the panels to prevent
damage.
6. Use appropriate screws for the type of underlayment and long
enough to fully penetrate and secure the panel.
7. The stored materials should be kept dry.
8. Do not cut on finished roof. Remove all drill spirals, chips and
dust immediately.
9. Seal neoprene closures and soft cell foam by applying appropriate sealant to both surfaces.
10. Put appropriate sealant/butyle tape between overlapping trims.
11. Overlap trims in a manner not to impede the flow of water.
For further information or assistance, contact our Residential Product Support at 877-286-3320
©2004 Accel Roofing Products. All
Corporate Office
rights reserved. Techo Tile Shingle
6612 Snowdrift Road
is a tradename owned by ATAS
International, Inc.
Allentown, PA 18106
ATAS International, Inc.
Was this manual useful for you? yes no
Thank you for your participation!

* Your assessment is very important for improving the work of artificial intelligence, which forms the content of this project

Download PDF

advertisement