Below you will find brief information for Pressure Vacuum Breaker 720A. The WILKINS Model 720A Pressure Vacuum Breaker is used on irrigation, industrial, and other non-potable services where a health hazard could exist if a backsiphonage situation were to occur. The device is designed to prevent backflow and ensure that water from the system does not contaminate the potable water supply. The instruction manual explains the installation, testing, and maintenance of the device. It includes testing procedures to verify proper operation. Additionally, it provides instructions for freeze protection to preserve the device during winter.
advertisement
Assistant Bot
Need help? Our chatbot has already read the manual and is ready to assist you. Feel free to ask any questions about the device, but providing details will make the conversation more productive.
Model 720A
Pressure Vacuum Breaker
(1/2", 3/4", 1", 1 1/4", 1 1/2" & 2")
Installation Testing Maintenance Instructions
INSTALLATION INSTRUCTIONS
CAUTION: Installation of Pressure Vacuum breakers must be performed by qualified, licensed personnel. Faulty installation could result in an improperly functioning device.
The installer should be sure the proper device has been selected for the particular installation.
WILKINS Model 720A Pressure Vacuum Breakers are for use on irrigation, industrial, and other non-potable services where a health hazard could exist if a backsiphonage situation were to occur. They must not be installed where backpressure may occur.
Proper performance depends upon following these installation instructions and prevailing governmental and industry standards and codes. Failure to do so releases WILKINS of any liability that it might otherwise have with respect to that device. Such failure could also result in an improperly functioning device.
1. Before installing the WILKINS Model 720A Pressure Vacuum Breaker, flush the
lines thoroughly to remove all debris, chips and other foreign matter.
2. The Model 720A must be installed in a vertical position (see Fig. 1) to provide
proper operation of the air inlet valve.
3. Provide adequate space around the installed unit so that the test cocks will be
accessible for testing and servicing.
4.
PLACING THE DEVICE IN SERVICE
After the installation of a Model 720A Pressure Vacuum Breaker has been completed, place the unit in service as follows:
1. Start with both shut-off valves and test cocks closed. Open the inlet shut-off valve until the Pressure Vacuum Breaker is completely pressurized.
2. A brief discharge from the air vent may occur while the device is pressurizing.
CAUTION: If installation of a Model 720A unit is in a building, provide a suit-
able drain arrangement to drain off spillage from the air vent.
5. Install valve at least 12 inches above the highest piping or water outlet down
stream of the Model 720A Pressure Vacuum Breaker.
6. Always consult local codes for installation methods, approvals and guidance.
7. The Model 720A Pressure Vacuum Breaker may be installed outdoors only if the
device is protected against any freezing conditions. Warning: do not block air vent
opening with insulation. Exposure to freezing conditions will result in improper
function or damage to the device. The installation location must be kept above 32°F.
Fig 1
MAIN SHUT-OFF
VALVE (1)
INLET DRAIN
VALVE (2)
TESTCOCKS (4)
DRAIN
WILKINS
ZW3
1” 720A PVB
(25MM)
OUTLET SHUT OFF
VALVE (5)
INLET SHUT OFF
VALVE (3)
ZW-3 WINTERIZER
1/2” NPT DRAIN PLUG
OR BLOW DOWN
12” MIN.
DIRECTION OF FLOW
OUTLET DRAIN
VALVE (6)
TO IRRIGATION
SYSTEM
The discharge should cease by the time the shut-off valve is in the full open position.
3. If the discharge does not stop, refer to "MAINTENANCE INSTRUCTIONS".
Repressurize device as in Step 1. Device should function properly.
4. Slowly open the No. 2 shut-off valve.
The Model 720A is now in service.
5. After the Model 720A has been properly installed, test the device. If the device fails the test, refer to "MAINTENANCE
INSTRUCTIONS"
Drain Procedure for Freeze Protection
1. Turn off main shut-off (1) that supplies water to the system.
2. Open both inlet and outlet drain valves in the system (2 & 6). Open inlet and outlet shut-off valves on the pressure vacuum breaker (3 & 5) and all of the test cocks.
Leave all valves and test cocks in the half open/half closed (45°) position to allow full drainage of the ball valves and test cocks.
3. If you "blow out" the system downstream of the pressure vacuum breaker, make sure the outlet drain valve (6) is open and the pressure vacuum breaker shut-off valve (5) is closed.
4. Connect an air hose to the outlet drain valve (6) and inject an adequate volume of air to remove all water from the downstream portion of the system.
5. CAUTION: Open outlet shut-off valve to the pressure vacuum breaker (5) and outlet drain valve (6) to the half open/half closed
(45°) position after "blow out" process is completed.
6. If drain valves (2 & 6) are not part of the system, and if air pressure is not used to "blow out" the system, the internal components of the pressure vacuum breaker should be removed for the duration of the winter.
7. Leave all drain valves (2 & 6), shut-off valves (3 & 5) and test cocks in the half open/half closed position (45°) for the duration of the winter to prevent freezing.
Caution: Be certain that main shut-off (1) remains tightly closed to prevent refilling of the system. Also, the main shut-off valve must be resilient seated to insure no leakage of water into the system.
WARRANTY: WILKINS Valves are guaranteed against defects of material or workmanship when used for the services recommended.
If in any recommended service, a defect develops due to material or workmanship, and the device is returned, freight prepaid, to
WILKINS within 12 months from date of purchase, it will be repaired or replaced free of charge. WILKINS' liability shall be limited to our agreement to repair or replace the valve only.
Proposition 65 Warning This product contains chemicals known to the State of California to cause cancer or birth defects or other reproductive harm.
Maintenance
1. Close inlet and outlet shut-off valves before disassembling device.
2. Remove canopy screws counterclockwise and remove canopy.
3. Bleed off pressure by opening the No. 2 test cock.
4. Unscrew the bonnet from the body by turning counterclockwise.
5. Remove the disc & poppet assembly, check spring and spider assembly from body.
6. Clean all parts with clean water only.
7. After completing inspection, replace necessary parts and reassemble. Repair kits are available from your supplier.
8. Retest according to "TEST PROCEDURES".
Testing Procedures
TEST NO. 1 TEST NO. 2
CANOPY
SCREW
Purpose: To test the opening pressure differential of the air inlet valve.
Requirement: The air inlet valve shall open when the pressure in the body is no less than 1.0 psi above atmospheric pressure.
The air inlet valve shall be fully open when the water drains from the body.
Purpose: To test the check valve for tightness in the direction of flow.
Requirement: The check valve shall be driptight in the normal direction of flow when the inlet pressure is 1.0 psi and the outlet pressure is atmospheric.
STEPS:
BONNET
O-RING
STEPS:
1. Bleed water through both test cocks
to eliminate foreign material.
2. Install appropriate fittings for test kit
hoses.
3. Remove air inlet valve canopy.
4. Install the high side hose of the differ-
ential pressure gauge to test cock #2.
Open test cock #2 and bleed air from
hose and gauge.
5. Close #2 shut-off valve then close #1
shut-off valve.
6. Slowly open the high side bleed
needle valve being especially careful
not to drop the pressure differential
too fast. Record the pressure differ-
ential at which the air inlet valve
opens.
7. Close test cock #2 and remove equip-
ment.
8. Open #1 shut-off valve.
1. Attach high side hose of differential
gauge to test cock #1. Open test cock
#1 and bleed all air from the hose and
the gauge by opening high side bleed
needle valve. Close high side bleed
needle valve.
2. Close #1 shut-off valve.
3. Open test cock #2. The air inlet valve
will open and the water in the body
will drain out through test cock #2.
When this flow of water stops, the dif-
ferential pressure indicated by the
gauge after it has settled will be the
pressure drop across the check valve.
This value must be 1.0 psi or greater.
Record this value. If water continues
to flow out of test cock #2, then the #1
shut-off valve is leaking.
4. Close test cocks #1 and #2 and re-
move equipment.
5. Replace air inlet valve canopy.
6. Open #1 shut-off valve, then #2 shut-
off valve.
SPRING
BODY
Troubleshooting
PROBLEM POSSIBLE CAUSES
CANOPY
PLASTIC
WASHER
DISC &
POPPET ASSY
SPIDER
ASSY
TEST COCK#2
TEST COCK#1
BALL VALVE
Air inlet valve does not open as gauge drops to 0.0 psid.
Air inlet valve does not open and differential on gauge will not drop.
Air inlet opens below 1.0 psid.
1. Air inlet disc stuck to seat.
2. “Old Style” pressure vacuum breaker (non-loaded air
inlet valve).
1. Leaking No. 1 shut-off valve.
2. Parallel installation with leaky No. 2 shut-off valve.
Check valve opens below 1.0 psid.
1. Dirty or damaged air inlet disc.
2. Scale buildup on seat.
1. Dirty or damaged air inlet disc.
2. Damaged seat.
IS720A (REV. 6/09)
WILKINS, a ZURN Company
1747 Commerce Way, Paso Robles, CA 93446 Phone:805/238-7100 Fax:805/238-5766
advertisement
Key Features
- Backflow Prevention
- Potable Water Protection
- Installation Instructions
- Testing Procedures
- Maintenance Instructions
- Freeze Protection