Waterbox Removal and Installation
the installation and servicing of this equipment.
waterboxes.
1. Determine the type and size of chiller being serviced. Refer to Trane® nameplate located on chiller control panel.
Discussion
This section will discuss recommended hoist ring/ clevises and lifting. Proper lifting technique will vary based on mechanical room layout.
• It is the responsibility of the person(s) performing the work to be properly trained in the safe practice of rigging, lifting, securing, and fastening of the waterbox.
• It is the responsibility of the person(s) providing and using the rigging and lifting devices to inspect these devices to ensure they are free from defect and are rated to meet or exceed the published weight of the waterbox.
• Always use rigging and lifting devices in accordance with the applicable instructions for such device.
Procedure
de atth ov errh ess ((cch aiin x m usstt b e cca pa orr sslliin gss)) m ptta e orr w atte
information only for Trane CenTraVac
™ chillers built in La Crosse. For Trane
CenTraVac ™ chillers built outside the
United States, refer to literature provided by the applicable manufacturing location.
2. Select the proper lift connection device from
26, p. 91 . The rated lifting capacity of the selected
lift connection device must meet or exceed the published weight of the waterbox. Verify the waterbox weight from the latest published literature.
3. Ensure that the lift connection device has the correct connection for the waterbox (e.g., thread type [course/fine, English/metric] and bolt diameter
[English/metric]).
4. Properly connect the lift connection device to the waterbox. Refer to the following figure and ensure that the lift connection device is securely fastened.
Install hoist ring on to the lifting connection on the waterbox. Torque to 100 ft·lb (135.6 N·m) for 3/4-in.
(19.05-mm) threaded connections and 28 ft·lb
(38.0 N·m) for 1/2-in. (12.7-mm) threaded connections.
5. Disconnect water pipes, if connected.
6. Remove waterbox bolts.
7. Lift the waterbox away from the shell.
otte
for waterbox weights.
an d b en de n d ea
8. Store waterbox in a safe and secure location and position.
lifting device.
grra du niiffiicca nttlly oiid ed he
Lo ad an e o
Review mechanical room limitations and determine the safest method or methods of rigging and lifting the
CVHE-SVX02M-EN 89
Figure 60.
Waterbox rigging and lifting—condenser and evaporator connections
Reassembly
Once service is complete, the waterbox should be reinstalled on the shell following all previous procedures in reverse. Use new O-rings or gaskets on all joints after thoroughly cleaning each joint.
an
Torque Requirements and Waterbox Weights
Table 24.
CenTraVac™
Bolt Size in.
mm
3/8
9.525
Gasket type O-ring ft·lb
25
N·m
33.9
1/2
12.7
5/8
15.875
70
150
94.9
203.4
3/4
19.05
250 339.0
ft·lb
12–18
Flat
N·m
16.3–24.4
33–50
70–90
105–155
44.7–67.8
94.9–122.0
142.4–
210.2
Table 25.
Waterbox weights
Shell
Size
Description
Fabricated Non-Marine
Waterbox, Welded Flat
Plate
Weight lb kg
Lifting
Connection
032
050
Evaporator, 150 psig
(1034.2 kPaG)
Evaporator, 300 psig
(2068.4 kPaG)
Condenser, 150 psig
(1034.2 kPaG)
Condenser, 300 psig
(2068.4 kPaG)
Evaporator, 150 psig
(1034.2 kPaG)
265
265
397
—
120
120
180
3/4 - 10
—
3/4 - 10
3/4 - 10
Non-Marine Cast
Waterbox
Weight lb kg
Lifting
Connection
—
176 80
—
—
1/2 - 13
—
397 180
Lifting Fixture
Fabricated Non-
Marine Waterbox
Welded Dome
Weight lb kg
Lifting
Connection
Marine Style Waterbox
Cover
Weight lb kg
Lifting
Connection
—
—
—
—
—
—
—
—
176
176
80
80
221 100
265 120
1/2 - 13
1/2 - 13
1/2 - 13
1/2 - 13
90 CVHE-SVX02M-EN
Table 25.
Waterbox weights (continued)
Shell
Size
Description
Fabricated Non-Marine
Waterbox, Welded Flat
Plate
Weight lb kg
Lifting
Connection
Non-Marine Cast
Waterbox
Weight lb kg
Lifting
Connection lb
Fabricated Non-
Marine Waterbox
Welded Dome
Weight kg
Lifting
Connection
Marine Style Waterbox
Cover
Weight lb kg
Lifting
Connection
080
142
Evaporator, 300 psig
(2068.4 kPaG)
Condenser, 150 psig
(1034.2 kPaG)
Condenser, 300 psig
(2068.4 kPaG)
Evaporator, 150 psig
(1034.2 kPaG)
Evaporator, 300 psig
(2068.4 kPaG)
Condenser, 150 psig
(1034.2 kPaG)
Condenser, 300 psig
(2068.4 kPaG)
Evaporator, 150 psig
(1034.2 kPaG)
Evaporator, 300 psig
(2068.4 kPaG)
Condenser, 150 psig
(1034.2 kPaG)
Condenser, 300 psig
(2068.4 kPaG)
353
265
551
662
882
551
882
882
1323
1543
1985
160
120
250
300
400
250
400
400
600
700
900
3/4 - 10
1/2 - 13
3/4 - 10
3/4 - 10
3/4 - 10
3/4 - 10
3/4 - 10
3/4 - 10
3/4 - 10
3/4 - 10
3/4 - 10
265
662
551
—
—
—
—
—
—
—
—
120
300
250
—
1/2 - 13
—
Lifting Fixture
—
3/4 - 10
—
—
—
—
—
441
—
—
—
—
—
—
—
—
—
—
200
—
—
—
—
—
—
—
—
—
3/4 - 10
—
265
265
441
441
551
441
882
662
882
1323
1764
120
120
200
200
250
200
400
300
400
600
800
1/2 - 13
1/2 - 13
1/2 - 13
3/4 - 10
3/4 - 10
1/2 - 13
3/4 - 10
3/4 - 10
3/4 - 10
3/4 - 10
3/4 - 10
210
Evaporator, 150 psig
(1034.2 kPaG)
Evaporator, 300 psig
(2068.4 kPaG)
Condenser, 150 psig
(1034.2 kPaG)
1544
2205
2205
700
1000
1000
3/4 - 10
3/4 - 10
3/4 - 10
—
—
—
—
—
— 662
—
—
300
—
—
3/4 - 10
1323
1764
1764
600
800
800
3/4 - 10
3/4 - 10
3/4 - 10
Condenser, 300 psig
(2068.4 kPaG)
2867 1300
3/4 - 10
— — — — 2426 1100
3/4 - 10
Evaporator, 150 psig
(1034.2 kPaG)
Evaporator, 300 psig
1985 900 3/4 - 10 — — — — 1544 700 3/4 - 10
250
(2068.4 kPaG)
Condenser, 150 psig
3087 1400
3/4 - 10
— — — — 2205 1000
3/4 - 10
(1034.2 kPaG)
Condenser, 300 psig
2867 1300 3/4 - 10 — — 662 300 3/4 - 10 2205 1000 3/4 - 10
(2068.4 kPaG)
3528 1600 3/4 - 10 — — — — 3087 1400 3/4 - 10
otte
Refer to product block identifier on the model number plate which identifies the evaporator and condenser shell sizes and the rated pressure. The designators are as follows:
Weights shown are maximum for waterbox size. Verify the waterbox from the latest published literature.
Connection Devices Information
Table 26.
Connection devices
Unit Product
Part
Number
CTV
CTV
CTV
Safety Hoist
Ring 3/4-10
Safety Hoist
Ring 1/2-13
Evap Lifting
Fixture
RNG01884
RNG01885
BAR00400
Order Information
Contact Trane Parts
Department
Contact Trane Parts
Department
Contact Trane Parts
Department
CVHE-SVX02M-EN 91
advertisement
Related manuals
advertisement
Table of contents
- 8 Unit Nameplate
- 9 Model Number Descriptions
- 10 Pre-Installation
- 10 ASHRAE Standard 15 Compliance
- 10 Unit Shipment
- 10 Installation Requirements and Contractor Responsibilities
- 12 Storage Requirements
- 14 Unit Components
- 15 Unit Clearances and Weights
- 15 Recommended Unit Clearances
- 16 General Weights
- 16 Weights (lb)
- 19 Weights (kg)
- 22 Installation: Mechanical
- 22 Operating Environment
- 22 Foundation Requirements
- 22 Rigging
- 22 Standard Chiller Lift
- 24 Special Lift Requirements
- 24 Unit Isolation
- 24 Isolation Pads
- 24 Spring Isolators
- 26 Leveling the Unit
- 27 Installation: Water Piping
- 27 Overview
- 27 Water Treatment
- 27 Pressure Gauges
- 27 Valves—Drains and Vents
- 27 Strainers
- 28 Required Flow-Sensing Devices
- 28 Paddle Switches
- 28 Water Flow Detection Controller and Sensor
- 30 Evaporator and Condenser Water Piping
- 31 Water Piping Connections
- 32 Waterbox Locations
- 32 Grooved Pipe Coupling
- 32 Flange-connection Adapters
- 33 Victaulic Gasket Installation
- 34 Bolt-Tightening Sequence for Water Piping Connections
- 35 Flanges with 4, 8, or 12 Bolts
- 35 Flanges with 16, 20, or 24 Bolts
- 35 Flanges with More than 24 Bolts
- 36 Evaporator Waterbox Covers
- 36 Pressure Testing Waterside Piping
- 37 Vent Piping
- 37 Refrigerant Vent Line
- 37 General Requirements
- 37 Purge Discharge
- 37 Vent Line Materials
- 37 Vent Line Sizing
- 38 Vent Line Installation
- 41 Vent Line Sizing Reference
- 44 Insulation
- 44 Unit Insulation Requirements
- 44 Insulation Thickness Requirements
- 44 Factory Applied Insulation
- 46 Installation: Controls
- 46 UC800 Specifications
- 46 Power Supply
- 46 Wiring and Port Descriptions
- 47 Communication Interfaces
- 47 Rotary Switches
- 47 LED Description and Operation
- 51 Installing the Tracer AdaptiView Display
- 52 Adjusting the Tracer AdaptiView Display Arm
- 53 Electrical Requirements
- 53 Installation Requirements
- 53 Electrical Requirements
- 54 Trane-supplied Starter Wiring
- 55 Customer-supplied Remote Starter Wiring
- 55 Current Transformer and Potential Transformer Wire Sizing
- 57 Power Supply Wiring
- 57 Three-Phase Power
- 57 Circuit Breakers and Fused Disconnects
- 57 Power Factor Correction Capacitors (Optional)
- 58 Interconnecting Wiring
- 59 Starter to Motor Wiring (Remote-Mounted Starters Only)
- 59 Ground Wire Terminal Lugs
- 60 Terminal Clamps
- 60 Wire Terminal Lugs
- 60 Bus Bars
- 61 Starter to Control Panel Wiring
- 62 10 to 13.8kV Medium Voltage Motor
- 62 Motor Terminal Box
- 63 Motor Supply Wiring
- 63 Motor Terminals
- 63 Ground Wire Terminal Lug
- 64 System Control Circuit Wiring (Field Wiring)
- 65 Water Pump Interlock Circuits and Flow Switch Input
- 65 Chilled Water Pump
- 65 Chilled Water Proof of Flow
- 65 Condenser Water Pump
- 65 Condenser Water Proof of Flow
- 65 Temperature Sensor Circuits
- 66 CWR—Outdoor Option
- 66 Optional Control and Output Circuits
- 66 Optional Tracer Communication Interface
- 66 Starter Module Configuration
- 66 Schematic Wiring Drawings
- 67 Operating Principles
- 67 General Requirements
- 67 Cooling Cycle
- 67 CVHE and CVHG 3-Stage Compressor
- 67 CVHF 2-Stage Compressor
- 68 Oil and Refrigerant Pump
- 68 Compressor Lubrication System
- 70 Motor Cooling System
- 70 Tracer AdaptiView Display
- 71 Start-up and Shut-down
- 71 Sequence of Operation
- 71 Software Operation Overview Diagram
- 72 Start-up Sequence of Operation—Wye-delta
- 76 Power Up Diagram
- 76 Ice Machine Control
- 78 Free Cooling Cycle
- 79 Free Cooling (FRCL)
- 79 Hot Gas Bypass (HGBP)
- 79 Hot Water Control
- 80 Heat Recovery Cycle
- 80 Auxiliary Condensers
- 80 Control Panel Devices and Unit-Mounted Devices
- 80 Unit Control Panel
- 80 User-Defined Language Support
- 81 Unit Start-up and Shut-down Procedures
- 81 Daily Unit Start-up
- 82 Seasonal Unit Start-up
- 82 Daily Unit Shut-down
- 82 Seasonal Unit Shut-down
- 83 Recommended Maintenance
- 83 Record Keeping Forms
- 83 Normal Operation
- 85 Recommended Compressor Oil Change
- 86 Purge System
- 86 Leak Checking Based on Purge Pump Out Time
- 86 Long Term Unit Storage
- 87 Refrigerant Charge
- 87 Leak Testing
- 87 Recommended System Maintenance
- 87 Condenser
- 88 Evaporator
- 88 Waterbox and Tubesheet Protective Coatings
- 88 Sacrificial Anodes
- 89 Waterbox Removal and Installation
- 89 Discussion
- 89 Procedure
- 90 Reassembly
- 90 Torque Requirements and Waterbox Weights
- 91 Connection Devices Information
- 92 Forms and Check Sheets
- 92 Unit Start-up/Commissioning
- 93 CenTraVac™ Chiller Installation Completion and Request for Trane Service
- 95 CVHE, CVHF, and CVHG CenTraVac™ Chiller Start-up Tasks to be Performed by Trane
- 97 CVHE, CVHF, and CVHG CenTraVac™ Chiller Annual Inspection List
- 98 CVHE, CVHF, and CVHG CenTraVac™ Chiller Operator Log