Reinstalling the Operating System on the Dell™

PowerVault™ 745N

This document details the following steps to reinstall the operating system on a

PowerVault 745N system:

1.

Install the Reinstallation Console

on a system running Microsoft

Windows® 2000, Microsoft Windows Server® 2003, or Microsoft Windows

XP Professional.

2.

Prepare the USB Key

provided with your NAS system for the reinstallation. If you do not have the USB Key that came with your system, any should work as long as it is 64MB in size or larger.

3.

Reinstall the operating system

on your NAS system.

NOTICE:

This procedure resets your Network Attached Storage (NAS) system to the default settings. It also deletes all data on the software-RAID

NAS system. Hardware-RAID NAS system data volumes and external storage data volumes are not affected.

Requirements

Client system with a CD drive running Windows 2000 (Professional or

Server), Windows Server 2003, or Windows XP Professional

64MB USB Key included with your NAS system

Resource

CD included with your NAS system

Reinstallation

CDs included with your NAS system

Keyboard, mouse, and monitor attached to your NAS system

Network Interface Cable

You must disable any firewall that might be running on the client system

Your client system must NOT be part of a domain or set up to be part of a domain, even if the system is not actually connected to a network

Installing the Reinstallation Console

You must set up a client system running one of the supported operating systems

(Windows 2000 Professional or Server, Windows Server 2003, or Windows XP

Professional) to reinstall the operating system image on your NAS system. Part

Initial Release: 2 January 2007 1

of this setup includes installing a set of NAS utilities used for the reinstallation process.

NOTE:

You must have administrator privileges on the client system to install the Reinstallation Console.

NOTE:

On systems running Windows XP Professional, network sharing is disabled by default. You must enable network sharing before installing the

Reinstallation Console.

NOTE:

You must disable any firewall running on the client system.

NOTE:

Your client system must NOT be part of a domain or set up to be part of a domain, even if the system is not actually connected to a network.

Perform the following steps to set up your client system:

1. Insert the that came with your NAS system into your client system's CD drive.

The

Resource CD

automatically starts and shows the following:

2. From the menu, click

Reinstallation Utilities.

The following screen appears:

Initial Release: 2 January 2007 2

3. Click on .

4. When prompted to open the file or save it to your computer, click

Open

.

5. Follow the prompts and accept the defaults to complete the installation.

When complete, an icon appears on your client system desktop labeled “

Dell

PowerVault NAS Reinstallation Console

.”

Preparing the USB Key

Because the USB key is used to boot the NAS system to start the reinstallation process and to provide configuration information, the USB Key must be configured with the necessary information.

NOTICE:

This procedure deletes all existing data on the USB Key.

NOTICE:

The following procedures can be performed on a USB Key larger than 64MB in size, but the size of the USB Key capacity will change to 64MB in size. This is NOT a permanent change.

NOTE:

You must have administrator privileges on the client system to install the Dell PowerVault USB Key Preparation Tool.

To configure the USB Key, perform the following steps:

1. Insert the USB Key into a USB port on the client system.

2. Insert the that came with your NAS system into your client system CD drive.

Initial Release: 2 January 2007 3

The

Resource CD

automatically starts and the following screen appears:

3. From the menu, click

Reinstallation Utilities

to display the reinstallation utilities.

The following screen appears:

5. Click .

6. When prompted to open the file or save it to your computer, click

Open

.

7. Follow the prompts and accept the defaults to complete the installation.

An icon appears on the client system’s desktop labeled “

Dell PowerVault

USB Key Preparation Utility

.”

8. Click

Dell NAS Reinstallation Tools > Dell

PowerVault USB Key Preparation Utility

.

Initial Release: 2 January 2007 4

When you open the

Dell PowerVault USB Key Preparation Utility

, it should look like this:

9. Make sure that the proper drive letter for the inserted USB key is listed on the client system under

Detected USB Keys

.

10. In the

Client Network Name

text box, type the name of the client system you are using for the reinstallation process.

NOTE:

You can get the client system’s name by right clicking on

My

Computer

and selecting

Properties.

Click the tab labeled

Computer

Name

. The name of the client system is listed on this tab in the

Full computer name

field.

11. If your system is in a DHCP environment, click

Prepare USB Key

.

If your system is in a non-DHCP environment: select the

No-DHCP

radio button; enter an IP address, subnet mask, and default gateway; and click

Prepare USB Key

.

NOTE:

The IP address is NOT that of the client system, but the Subnet

Mask and Default Gateway ARE of the client system.

Initial Release: 2 January 2007 5

NOTE:

If you do not enter the client name, you will be prompted for the client system name and network configuration each time you attempt to reinstall.

The USB Key configuration is complete, and the USB Key is ready for use.

1. Click the icon on the Windows toolbar and then click

Safely Remove Mass Storage Device

.

2. Remove the USB key from the client system.

Using the PowerVault NAS Reinstallation Console

1. Click the icon to open the

Dell PowerVault Reinstallation Console

.

2. From the dropdown menu, select the drive letter where you want to copy the NAS operating system reinstallation image to the client system. This location requires 3GB of available space.

Initial Release: 2 January 2007 6

Reinstallation Console

3. Click .

NOTE:

Some PowerVault 745N systems ship with three Reinstallation CDs, while others include four Reinstallation CDs. The following information depicts a system that requires three Reinstallation CDs, however the procedure also applies to systems requiring four CDs. If your system requires four CDs, you will be automatically prompted to insert the fourth CD during reinstallation.

4. Insert the into the CD-ROM drive and click

OK

.

The image of the operating system is copied to the client system’s hard drive. The Reinstallation Console shows the status of the copy process.

Insert PV 745 Reinstallation CD 1

Initial Release: 2 January 2007 7

Reinstallation Console Copy Status

5. When prompted for the second CD, remove reinstallation CD 1, insert reinstallation CD 2, and click

OK

.

The image of the operating system continues to copy to the client system’s hard drive. The Reinstallation Console shows the status of the copy process.

Insert PV 745 Reinstallation CD 2

6. When prompted for the third CD, remove reinstallation CD 2, insert reinstallation CD 3, and click

OK

.

The image of the operating system continues to copy to the client system’s hard drive. The Reinstallation Console shows the status of the copy process.

Insert PV 745 Reinstallation CD 3

Initial Release: 2 January 2007 8

7. When the image transfer is complete, the Reinstallation Console prompts to

Insert USB Key in PV 745N to continue

.

NOTE:

Do not close the

Dell PowerVault NAS Reinstallation Console

application until after you have finished reinstalling the operating system on your NAS system.

Insert USB Key in PV 745N

Reinstalling the Operating System on Your NAS System

NOTICE:

This procedure resets your NAS system to the default settings. Any data on the internal operating system drives will be deleted. Data on external

SCSI enclosures will not be affected.

Before performing this procedure on an External Storage NAS system, attempt to recover your system by following the procedures in

" Troubleshooting External Storage Configuration NAS Systems ." For instructions on how to determine the configuration of your NAS system, see

" Determining a NAS System's Configuration " in "NAS Manager."

NOTE:

Dell recommends that you back up your system, if possible, before attempting a system reinstallation. See " Backing Up the System ."

1. Shut down the NAS system. See " Shutting Down the NAS System " in

"NAS Manager."

2. Ensure that the NAS system is using NIC 1 to connect to the same network as the client system or directly to the client system.

Initial Release: 2 January 2007 9

NOTICE:

Failure to disconnect all external storage enclosures from your NAS system before performing a system reinstallation may lead to data loss.

Disconnect all external storage enclosures from your NAS system prior to continuing with this procedure.

NOTE:

During reinstallation, you must use NIC 1 to connect the NAS system to a network that includes your client system or directly to the client system.

NOTE:

Turn off any external storage enclosures attached to your system.

3. Disconnect all external storage enclosures from your NAS system.

4. Insert the prepared USB Key into one of the USB connectors on the

PowerVault 745N.

5. Turn on the NAS system.

NOTE:

There are three (3) USB connectors on the PV745. One (1) connector is located under the front panel bezel and two (2) are located on the back panel.

Initial Release: 2 January 2007 10

6. During the boot process, press <F2> when “

F2=Setup

” displays on the screen (at the “Dell” splash screen just before POST starts).

7. In the BIOS setup screen, select

Boot Sequence

and press <Enter>.

8. Ensure that

Hard drive C

is first in the list and press <Esc> to exit the

Boot Sequence

menu.

9. Select

Hard-Disk Drive Sequence

and press <Enter>.

10. Ensure that

Hard-disk-emulated USB flash drive

is first in the list by using the <+>\<-> keys and press <Esc>.

The system screen should look similar to this:

11. Press <Esc> again, select

Save Changes and Exit

, and press <Enter>.

The system automatically shuts down and reboots from the USB Key.

12. When the Dell PowerVault NAS 745N menu displays, press <1> to select

Reinstall NAS system

, and press <Enter>.

The system screen should look similar to this:

Initial Release: 2 January 2007 11

13. Follow the on screen instructions to reimage the operating system.

14. Read the warning message.

15. Type

Y

and press <Enter> to continue with the installation.

A message appears asking you to confirm your selection.

Warning Message

16. Type

Y

and press <Enter> to confirm your selection.

The system begins reimaging the boot partition. Once the imaging process is complete, the appliance instructs you to remove the USB key and reboot the system.

Initial Release: 2 January 2007 12

Confirm selection

Remove the USB key and reboot

Initial Release: 2 January 2007 13

17. Shut down the PowerVault 745N and remove the USB key.

18. Reconnect all external storage that you disconnected in Step 3, then turn on the PowerVault 745N.

The PowerVault 745N boots into Windows Storage Server 2003.

It may take up to a couple of hours for this process to complete.

Automated Sequence of the PowerVault 745N Reinstall Process

NOTICE:

During the install, you will be prompted to restart the server.

Ignore this message

and the system will continue reinstalling. When a reboot is necessary, the system will reboot on its own with out user intervention.

1. The PowerVault 745N will automatically log on and begin processing the installation scripts. A dialog box appears with the message “

Reinstalling your PowerVault NAS system. Do not restart your system during this process. When the reinstallation is complete, the system will reboot automatically

.”

Do not reboot the system

Initial Release: 2 January 2007 14

2. During the install, you will be prompted to restart the server.

Ignore this message

. The system will continue reinstalling. When a reboot is necessary, the system will reboot on its own, without user intervention, and the reinstallation process will continue. The reinstallation process can take several hours.

Ignore restart messages

NOTE

: After the operating system has finished reinstalling, it may take up to

5 hours for the disks to complete synchronizing the RAID 5.

3. When the procedure completes, log in to the PowerVault 745N.

4. On the client system, close the Reinstallation Console.

NOTE:

During the reinstallation process, do not attempt to connect to your

NAS system. Depending on your configuration, this part of the reinstallation process may take several hours. During this process, the system may reboot several times while completing the reinstallation process. The reinstallation process is complete when the logon screen is displayed.

NOTE:

The default administrator user name is

administrator

and the default password is

powervault

.

See " Configuring Your NAS System for the First Time " in " Initial Configuration ."

Initial Release: 2 January 2007 15

NOTE:

Check the Dell Support website at

support.dell.com

for the latest driver and software updates. You may need to install updates after completing the operating system reinstallation.

Information in this document is subject to change without notice.

©

2007 Dell Inc. All rights reserved.

Reproduction in any manner whatsoever without the written permission of Dell Inc. is strictly forbidden.

Trademarks used in this text:

Dell

, the

DELL

logo, and

PowerVault

are trademarks of Dell Inc.;

Microsoft

,

Windows

, and

Windows Server

are registered trademarks of Microsoft Corporation.

Other trademarks and trade names may be used in this document to refer to either the entities claiming the marks and names or their products. Dell Inc. disclaims any proprietary interest in trademarks and trade names other than its own.

Initial Release: 2 January 2007 16

advertisement

Was this manual useful for you? Yes No
Thank you for your participation!

* Your assessment is very important for improving the workof artificial intelligence, which forms the content of this project

Related manuals

advertisement