BEFORE YOU BEGIN

Read these instructions completely and carefully.

WARNING/ADVERTISSEMENT

RISK OF ELECTRIC SHOCK

• Turn power off before inspection, installation or removal.

• Properly ground electrical enclosure.

RISQUES DE DECHARGES ELECTRIQUES

• Coupez l’alimentation avant d’inspecter, installer ou déplacer le luminaire.

• Assurez-vous de correctement mettre à la terre le boîtier d’alimentation électrique.

RISK OF FIRE

• Follow all NEC and local codes.

• Use only UL or IEC approved wire for input/output connections.

Minimum size 18 AWG.

RISQUES D’INCENDIE

• Respectez tous les codes NEC et codes locaux.

• N’utilisez que des fils approuvés par UL ou IEC pour les entrées/sorties de connexion. Taille minimum 18 AWG.

Save These Instructions

Use only in the manner intended by the manufacturer. If you have any questions, contact the manufacturer.

Prepare Electrical Wiring

Electrical Requirements

The LED driver must be supplied with 120-277

VAC, 50/60 Hz and connected to an individual properly grounded branch circuit, protected by a circuit breaker. Use min. 75 C supply conductor.

Electrical Requirements

The grounding and bonding of the overall system shall be done in accordance with the National

Electric Code (NEC) Article 600 and local codes

This device complies with Part 15 of the FCC Rules. Operation is subject to the following two conditions: (1) This device may not cause harmful interference, and (2) this device must accept any interference received, including interference that may cause undesired operation. CAN ICES-005 (A) / NMB-005 (A)

Note: This equipment has been tested and found to comply with the limits for a Class A digital device, pursuant to part 15 of the FCC Rules. These limits are designed to provide reasonable protection against harmful interference when the equipment is operated in a commercial environment. This equipment generates, uses, and can radiate radio frequency energy and, if not installed and used in accordance with the instruction manual, may cause harmful interference to radio communications. Operation of this

1

Properly inspect for defects to the luminaire and acrylic light guide before installing. Do not remove the green protective film until fixture installation is complete.

Albeo ® ALC Series

Unit Installation

1

2

Carefully unpack unit and properly inspect for defects before installing. Wear work gloves to prevent dirt and oil from being transferred to the luminaire.

Choose a mounting method: chain, cable, rod, or surface mount.

NOTE: Please follow all UL, NEC and minimum load rating guidelines when selecting and installing a cable, chain, or rod.

3 The mounting brackets come pre-installed. Loosen the screws to move the brackets to a desired location, then re-tighten. Each mounting bracket can connect to a chain, cable, rod, or be surface mounted.

1 Chain or Cable Mounting

Installation Guide

Size

4ft Fixture

8ft Fixture

ALC6

120-277V

7.5 lbs

15.4 lbs

347-480V

10.5 lbs

17.5 lbs

Hang two chains/cables from a structural member of the ceiling. Fixture must be supported independently of an outlet box. Loop chain/cable through the two mounting brackets.

2 Rod Mounting

Secure two 1/2” threaded rods into structural members in ceiling. Place a nut on each threaded rod where the fixture should hang. Slide mounting brackets onto threaded rods and tighten second nut onto rods to secure the fixture.

2

Albeo ® ALC Series

3 Surface Mounting

Installation Guide

A Position the two mounting brackets at the ends of the fixture and tighten. Attach the fixture to ceiling using appropriate hardware (not supplied).

B Loosen end cap screw and swing open end cap to remove.

Repeat for both end caps.

C Loosen screws on side of fixture and unhinge LED lightbar.

D Remove LED lightbar by disconnecting the provided quick-connectors.

E Run power through one of the 0.875” holes in top of fixture and into a junction box. Connect AC wires from junction box to fixture wires

(see Step 4 under Electrical

Connections for details).

F Reattach lightbar to fixture and tighten screws. Reattach both end caps and tighten screws.

4 Electrical Connections

Note: Please see additional wiring instructions if installing multiple fixtures in a Continuous Run.

A Loosen end cap screw and swing open end cap to remove.

B Option: power input from top - A) Install 1/2” conduit or B) install AC power cord with strain relief through .875” hole on top of fixture

3

Albeo ® ALC Series Installation Guide

C Option: power input from side

- Remove knockout in endcap and A) install 1/2” conduit, or

B) install AC power cord with strain relief. Plug unused hole on top with appropriate fitting.

D 120-277V: Connect the green (ground), black (line) and white

(neutral) wires of the AC line to the similarly colored wires of the fixture’s power supply using UL listed wire connectors. Reattach endcap.

347-480V: Connect the green (ground), red (line) and black

(neutral) wires of the AC line to the similarly colored wires of

5 Continuous Run Installation

A Choose the first fixture for the run and connect the starter wire harness (provided in Continuous Run Kit) to the fixture wire harness. If connectors don’t mate, use small adapter harness (also found in kit).

B Option: Sensor – Insert sensor

(ordered separately) into endcap knockout (provided in

Continuous Run Kit) and wire to starter wire harness per sensor wiring instructions.

C Using two people, hang the first fixture. The side opposite the starter harness will connect with next fixture on the run.

Connect the starter harness with building power as shown in Electrical Connections section of this guide.

D Align and mount the second fixture on run such that the wire harness quick-connectors will mate correctly.

E Make wiring connections between the fixtures with the wire harness quick-connectors.

F Align the metal “joiningbracket” on the first fixture with the corresponding opening on the second fixture and push fixtures together

4

Albeo ® ALC Series

G Secure the “joining-bracket” by tightening the four #6-32 screws provided.

H Snap on decorative lens cover

(provided in Continuous Run

Kit) over the seam between the fixtures.

I Repeating Steps 3-7, add fixtures as needed to complete the continuous run. Do not exceed the maximum number of fixtures per run listed in the table above (maximum current through wire harness must not exceed 15A).

NOTE: If there are unused quickconnectors at the end of a run, cut off the connectors and cap the ends with wire connectors to terminate the wires.

J

Attach end caps (provided in Continuous Run Kit) and tighten screws on each end of the run.

Sympton

Luminaire will not turn on

Mounting bracket slides from side to side

Solution

• Check that the color of the supply side wires match the color of the wires they are connected to.

• Check that all wire connectors are properly connected.

• Verify that your input voltage is within specs.

• If using any additional controls (i.e. wireless controls or motion sensors), please also verify

• that those are working properly and that the unit is setup to interface with the controllers.

Check that the mounting bracket is properly tightened using the adjustment screws provided.

Questions Web: products.gecurrent.com Phone: 1-866-855-8629

All product and company names are trademarks or registered trademarks of their respective holders. Use of them does not imply any affiliation with or endorsement by them.

2021 Current Lighting Solutions, LLC. All rights reserved. GE and the GE monogram are trademarks of the General

Electric Company and are used under license. Information provided is subject to change without notice. All values are design or typical values when measured under laborator conditions.

ALB066 | REV 05/06/21

5

advertisement

Was this manual useful for you? Yes No
Thank you for your participation!

* Your assessment is very important for improving the workof artificial intelligence, which forms the content of this project

Key Features

  • High efficiency and long life
  • Available in 4ft and 8ft lengths
  • Can be mounted using chain, cable, rod, or surface mount
  • Ideal for use in warehouses, factories, retail stores, and other large spaces

Related manuals

Frequently Answers and Questions

What is the power requirement of the ALC6?
The ALC6 requires 120-277 VAC, 50/60 Hz.
How do I wire the ALC6?
Refer to the Electrical Connections section of the installation guide.
Can I use the ALC6 in a continuous run?
Yes, the ALC6 can be used in a continuous run using the Continuous Run Kit.