Swegon CDKa: High-performance diffuser for precise airflow control and efficient ventilation. Designed for supply and exhaust air applications, the CDKa features adjustable blades for customized airflow patterns and a wide range of accessories for flexible installation options. With its robust construction and easy maintenance, the CDKa is ideal for commercial, industrial, and public buildings.
Anuncio
Anuncio
CDKa/CKPa
Installation – Commissioning – Maintenance
20150101
Accessories
Commissioning box:
ALS. Made of galvanised sheet steel. Contains removable commissioning damper, fixed measurement tapping and sound absorbing insulation with reinforced surface layer. Fire resistance rated to
B-s1,d0 in accordance with EN ISO 11925-2.
Frame:
SAR C. For aesthetic installation of a lowered diffuser.
Blanking-off a sector of the diffuser face:
SAV. For blanking off a sector of the air distribution pattern.
Installation
The diffuser inlet sleeve should be secured to the connecting duct with blind rivets. The diffuser face can be removed by turning the springs that hold the diffuser face’s "pins" one quarter of a turn
(see Figure 2). If an ALS commissioning box is used, the sleeve coupling between the ALS and the air diffuser can be lengthened using an ordinary circular duct of up to 500 mm without having to lengthen the measuring tubes and damper adjustment cords. See
Figure 2.
Commissioning
Commissioning must be carried out with the diffuser face mounted. Pull the measuring tubes and damper adjustment cords out through the air diffuser slot. Then connect the manometer to the correct measuring tube. The red tube in the ALS commissioning box is used for supply air. The rated coefficient of performance of the air register can be used in a calculation to determine the required commissioning pressure. Conclude commissioning by adjusting the damper to the correct blade position, tie a commissioning knot in the damper cords to indicate the damper position.
See Figure 1.
Measurement accuracy and requirement on straight duct before the commisioning box, see Figure 2. The requirements of straigh duct depends on the type of disturbance before the commissioning box. Figure 2 shows a bend, a dimensional change and a
T-piece. Other types of disturbances requires at least 2xD straight
(D = connection dimension) for measurement accuracy of ± 10% of the flow.
The rated coefficient of performance (K-factor) is specified on the identification label of the product and in the relevant commissioning instructions at www.swegon.com.
Maintenance
The air diffuser can be cleaned, if necessary, using lukewarm water with dishwashing detergent added or by vacuum cleaning using a brush nozzle.
The duct system can be accessed for cleaning by removing the diffuser face. Do so by turning the springs that hold the diffuser face’s "pins" one quarter of a turn. If a type ALS commissioning box is used, swing the distribution plate to the side on so that you then can grip the handle of the tubular damper casing and rotate it out of its holder. See Figure 2.
q = flow reading l/s p = current pressure reading (Pa) k = commissioning factor k-factor
Tomelilla
Sweden
CDK 200
+ ALS 160-200
K = 26,9/27,6 q
=
k
⋅
p p
=
q
Figure 1. Commissioning.
0xD / ±5%
Figure 2. Installation k q
0xD / ±5%
TILLUFT / SUPPLY
AIR p
2xD / ±10%
CDK/CKP
Dimensions and weights
CDK/CKP
Size
100
125
160
200
ØA
192
228
304
380
Ød
99
E
36/46
ØJ
125
124 36/46 160
159 46/56 215
199 46/56 280
250
315
456
568
249 50/60 350 95
314 50/60 450 114
ØJ = Size of the opening
L
51
56
73
87
Weight, kg
0.6
0.8
1.3
1.8
2.5
3.7
CDK/CKP + ALS
Size ØA
100
125
160
200
250
315
192
228
304
380
456
568
B
227
282
342
404
504
622
C
192
217
252
288
332
388
ØD
79
99
124
159
199
249
E
36/46
36/46
46/56
46/56
50/60
50/60
Figure 3. CDK/CKP.
Size
100
125
160
200
250
315
340
420
CL = Center line
F
177
202
243
292
G
107
122
151
183
211
255
H
200
270
315
375
465
575
K
50
80
80
100
115
140
Weight, kg
1.8
2.7
3.5
4.5
6.3
9.3
Figure 4. CDK/CKP + ALS. CL = Centerline.
SAR C frame
Size
100
125
160
200
250
315
M
40
40
65
65
100
100
Ø L
187
223
299
375
451
563
Figure 5. SAR C.
K-factor (Rated COP)
CDK
ALSd
Size
80-100
100-125
Size
100
125
CDKa, supply air, 360°
Slot
20 mm
Slot
30 mm
Slot
40 mm
6.8
9.8
6.9
10.1
125-160
160-200
200-250
250-315
160
200
250
315
–
–
–
Number of measuring tubes: 1
16.3
26.9
38.5
57.6
–
–
27.6
42.1
69.9
Colour of the tube
Red
Red
Red
Red
Red
Red
CKP
ALSd
Size
80-100
100-125
125-160
160-200
Size
100
125
160
200
CKPa, supply air, 360°
20 mm slot
30 mm slot
40 mm slot
3.8
9.9
–
–
6.8
10.1
16.2
27.3
200-250
250-315
250
315
–
–
Number of measuring tubes: 1
39.8
60.6
–
–
16.5
27.9
42.2
68.7
Colour of the tube
Red
Red
Red
Red
Red
Red
2
Swegon reserves the right to alter specifications. 20150101