Sun Microsystems VTL Value Hardware Virtual Tape Library Installation Guide
Below you will find brief information for Virtual Tape Library VTL Value Hardware. The VTL Value Hardware Installation Guide details the steps for physically installing the VTL Value appliance and applying power. It walks you through the process of setting up the VTL Value equipment from beginning to end, with all the needed information immediately to hand and the alternatives clearly indicated. The first chapter details the physical installation of the appliance hardware, including rack mounting, cabling, and power up procedures. The second chapter explains the initial configuration of the operating system software and network and some basic checks that should be run on a newly installed system.
Advertisement
Advertisement
Sun Microsystems, Inc.
www.sun.com
Part No. 316196101
Aug 2007, Revision A
EC000066
Submit comments about this document at: [email protected]
Virtual Tape Library
VTL Value Hardware Installation Guide
Copyright 2007 Sun Microsystems, Inc., 4150 Network Circle, Santa Clara, California 95054, U.S.A. All rights reserved.
Sun Microsystems, Inc. has intellectual property rights relating to technology that is described in this document. In particular, and without limitation, these intellectual property rights may include one or more of the U.S. patents listed at http://www.sun.com/patents and one or more additional patents or pending patent applications in the U.S. and in other countries.
This document and the product to which it pertains are distributed under licenses restricting their use, copying, distribution, and decompilation. No part of the product or of this document may be reproduced in any form by any means without prior written authorization of
Sun and its licensors, if any.
Third‐party software, including font technology, is copyrighted and licensed from Sun suppliers.
Parts of the product may be derived from Berkeley BSD systems, licensed from the University of California. UNIX is a registered trademark in the U.S. and in other countries, exclusively licensed through X/Open Company, Ltd.
Sun, Sun Microsystems, the Sun logo, Java, AnswerBook2, docs.sun.com, and Solaris are trademarks or registered trademarks of Sun
Microsystems, Inc. in the U.S. and in other countries.
AMD Opteron is a trademark or registered trademark of Advanced Microdevices, Inc.
All SPARC trademarks are used under license and are trademarks or registered trademarks of SPARC International, Inc. in the U.S. and in other countries. Products bearing SPARC trademarks are based upon an architecture developed by Sun Microsystems, Inc.
The OPEN LOOK and Sun™ Graphical User Interface was developed by Sun Microsystems, Inc. for its users and licensees. Sun acknowledges the pioneering efforts of Xerox in researching and developing the concept of visual or graphical user interfaces for the computer industry. Sun holds a non‐exclusive license from Xerox to the Xerox Graphical User Interface, which license also covers Sun’s licensees who implement OPEN
LOOK GUIs and otherwise comply with Sun’s written license agreements.
U.S. Government Rights—Commercial use. Government users are subject to the Sun Microsystems, Inc. standard license agreement and applicable provisions of the FAR and its supplements.
DOCUMENTATION IS PROVIDED ʺAS ISʺ AND ALL EXPRESS OR IMPLIED CONDITIONS, REPRESENTATIONS AND WARRANTIES,
INCLUDING ANY IMPLIED WARRANTY OF MERCHANTABILITY, FITNESS FOR A PARTICULAR PURPOSE OR NON‐INFRINGEMENT,
ARE DISCLAIMED, EXCEPT TO THE EXTENT THAT SUCH DISCLAIMERS ARE HELD TO BE LEGALLY INVALID.
Copyright 2007 Sun Microsystems, Inc., 4150 Network Circle, Santa Clara, Californie 95054, Etats‐Unis. Tous droits réservés.
Sun Microsystems, Inc. a les droits de propriété intellectuels relatants à la technologie qui est décrit dans ce document. En particulier, et sans la limitation, ces droits de propriété intellectuels peuvent inclure un ou plus des brevets américains énumérés à http://www.sun.com/patents et un ou les brevets plus supplémentaires ou les applications de brevet en attente dans les Etats‐Unis et dans les autres pays.
Ce produit ou document est protégé par un copyright et distribué avec des licences qui en restreignent l’utilisation, la copie, la distribution, et la décompilation. Aucune partie de ce produit ou document ne peut être reproduite sous aucune forme, par quelque moyen que ce soit, sans l’autorisation préalable et écrite de Sun et de ses bailleurs de licence, s’il y en a.
Le logiciel détenu par des tiers, et qui comprend la technologie relative aux polices de caractères, est protégé par un copyright et licencié par des fournisseurs de Sun.
Des parties de ce produit pourront être dérivées des systèmes Berkeley BSD licenciés par l’Université de Californie. UNIX est une marque déposée aux Etats‐Unis et dans d’autres pays et licenciée exclusivement par X/Open Company, Ltd.
Sun, Sun Microsystems, le logo Sun, Java, AnswerBook2, docs.sun.com, et Solaris sont des marques de fabrique ou des marques déposées de
Sun Microsystems, Inc. aux Etats‐Unis et dans d’autres pays.
AMD Opteron est une marque de fabrique ou une marque deposee de Advanced Microdevices, Inc.
Toutes les marques SPARC sont utilisées sous licence et sont des marques de fabrique ou des marques déposées de SPARC International, Inc. aux Etats‐Unis et dans d’autres pays. Les produits portant les marques SPARC sont basés sur une architecture développée par Sun
Microsystems, Inc.
L’interface d’utilisation graphique OPEN LOOK et Sun™ a été développée par Sun Microsystems, Inc. pour ses utilisateurs et licenciés. Sun reconnaît les efforts de pionniers de Xerox pour la recherche et le développement du concept des interfaces d’utilisation visuelle ou graphique pour l’industrie de l’informatique. Sun détient une license non exclusive de Xerox sur l’interface d’utilisation graphique Xerox, cette licence couvrant également les licenciées de Sun qui mettent en place l’interface d ’utilisation graphique OPEN LOOK et qui en outre se conforment aux licences écrites de Sun.
LA DOCUMENTATION EST FOURNIE ʺEN L’ÉTATʺ ET TOUTES AUTRES CONDITIONS, DECLARATIONS ET GARANTIES EXPRESSES
OU TACITES SONT FORMELLEMENT EXCLUES, DANS LA MESURE AUTORISEE PAR LA LOI APPLICABLE, Y COMPRIS NOTAMMENT
TOUTE GARANTIE IMPLICITE RELATIVE A LA QUALITE MARCHANDE, A L’APTITUDE A UNE UTILISATION PARTICULIERE OU A
L’ABSENCE DE CONTREFAÇON.
Revision History
Short Name
VTL Value Hardware Installation Guide
Part Number
316196101
Dash
A
Date
August 2007
Comments
Revision History
iii
iv
VTL Value Hardware Installation Guide • Aug 2007
Contents
ix
Taking advantage of this book’s hypertext features
Understanding the conventions used in this book
x
1.
Installing the VTL Value appliance in an equipment rack
▼
Obtaining required tools, personnel, and materials
Installing slide‐rail assemblies
▼
▼
▼
▼
▼
Preparing the slide-rail assemblies for installation
Attaching the inner rails to the server chassis
Positioning the outer/middle rail assembly in the rack
Attaching the outer/middle rail assembly to the rack
Adjusting and securing middle/outer slide rails
Mounting the appliance in the rack
4
5
8
11
1
2
1
1
3
3
v
Installing the cable management arm
▼
Attaching the Outer Rail Extension
▼
Installing data and power cables
▼
▼
2.
Setting up the VTL Value ILOM service processor
Changing the IP address of the ILOM SP
▼
▼
Attaching a laptop to the ILOM via the VTL private network
Changing the IP address of the ILOM
▼
Resetting the default ILOM password
Checking the health of the internal storage systems
▼
▼
Accessing the Solaris desk top via the ILOM
Running basic storage diagnostics
Changing the Solaris root password
▼
Changing the default Solaris root password
▼
Logging out of the operating system and ILOM
A.
The back and front panels of the VTL Value server
B.
C.
Connecting to ILOM via a serial port
D.
vi
VTL Value Hardware Installation Guide • Aug 2007
E.
▼
Removing the cable management arm
Removing the VTL appliance from a rack
▼
▼
Preparing to remove the appliance
Removing the appliance from the rack
Contents
vii
viii
VTL Value Hardware Installation Guide • Aug 2007
About this book
This book describes the installation and initial configuration processes specific to the Sun
StorageTek VTL Value appliance. In VTL Value deployments, it supersedes the Sun Fire™
X4500 Server Installation Guide (819-4358-11) that ships with the X4500 platform. While the VTL Value appliance hardware is almost identical to the X4500, it has been specially preconfigured to host Virtual Tape Library software on the Solaris operating system.
Using this book
This book leads you through the process of setting up the VTL Value equipment from beginning to end, with all the needed information immediately to hand and the alternatives clearly indicated. Each chapter and section begins with a list of the tasks it contains. Tasks are presented in order, and the steps in each process are numbered, in the sequence in which they are to be performed. Conditional steps (steps that you perform only in specified circumstances) begin with the condition (“If A ...”) and end with the corresponding action
(“... do B”); if the condition does not apply, you simply skip the step. Each task ends with a reference to the next task in the sequence:
Next task: “Installing slide-rail assemblies” on page 3.
When the setup process branches, the tasks ends with conditional alternatives:
Next task:
• If the customer does not plan to run the management console from a host on the local area network (LAN), press Skip, and go to the next task.
• Otherwise, carry out the procedure “Configuring the Ethernet management interface” on page 57.
To minimize the time you spend switching between publications or major sections of the document, we have made an effort to avoid cross references to external information wherever possible. If you need to have a figure, a table, or a procedure, it should always be, at worst, on a neighboring page.
ix
The chapters are organized to reflect top-level tasks. The first chapter details the physical installation of the appliance hardware, including rack mounting, cabling, and power up procedures. The second chapter explains the initial configuration of the operating system software and network and some basic checks that should be run on a newly installed system.
Appendices provide additional information that, while not essential to a normal installation, may prove useful in special circumstances. These list the private network addresses used when installing the VTL Value appliance, provide instructions for serially connecting to the
VTL Value Integrated Lights Out Manager (ILOM) service processor, and summarize commands that can be entered at the ILOM commandline interface (CLI).
Taking advantage of this book’s hypertext features
If you choose to view this book online, rather than in printed form, you can jump quickly to any part of the book by clicking on the corresponding entry under the Bookmarks tab on the left side of the Adobe Acrobat interface. In addition, clicking on entries in the table of contents, cross references, or references to subsequent tasks will take you directly to the indicated part of the document. You can then use the back arrow on the Adobe Acrobat
Reader to return, if desired, to the point you left. In addition, clicking on most Uniform
Resource Locators (URLs) and on most references to online resources will open your default web browser to the corresponding web page, so that you can, if necessary, obtain a required download immediately (be aware, however, the URL to specific pages change frequently and may not always be accurate).
Understanding the conventions used in this book
The table below illustrates the conventions that represent literal and variable values, commands, and property names in this book.
Convention Meaning
AaBbCc123
Fixed-width text is used for literal values, including names of commands, files, directories, literal computer inputs/outputs, and Uniform Resource Locators (URLs)
AaBbCc123
ABCD
Oblique text is used for variables that stand for real names or values and for book titles.
Bold, san-serif text indicates callouts in illustrations.
Examples
Edit your.login file.
Use ls -a to list files.
% You have mail .
To delete a file, type: rm
filename.
Click Submit
(
A
below).
1.
■
Numbered paragraphs indicate steps in a process that should be executed in sequential order.
Bulleted paragraphs indicate lists of alternatives or components.
x
VTL Value Hardware Installation Guide • Aug 2007
About this book
Using the Sun StorageTek Customer Resource Center (CRC) to obtain the latest information and supporting resources
The Sun StorageTek Customer Resource Center <www.support.storagetek.com> stores the latest documentation, software updates, and licensing resources for VTL Value solutions. Always check the CRC for updates to this document before proceeding.
Documents distributed on CDROM may not reflect the latest changes to VTL hardware, software, and services.
You must have an account to use the CRC. If you do not currently have access, click the
Request a CRC Password
link at the URL shown above.
Commenting on this book
Sun welcomes your comments and suggestions for improving this book. Contact us at [email protected].
Please include the title, part number, issue date, and revision: VTL
Value Hardware Installation Guide , part number 316196101 (Aug 2007 revision A).
xi
xii
VTL Value Hardware Installation Guide • Aug 2007
C H A PT E R
1
316196101 • A
Installing VTL Value hardware
This chapter describes the process of physically installing the VTL Value appliance and applying power. The tasks break down as follows:
■
■
■
This chapter contains procedures for:
“Installing the VTL Value appliance in an equipment rack” on page 1 (if a rack is used)
“Starting the VTL appliance” on page 22.
Installing the VTL Value appliance in an equipment rack
To safely install the VTL Value appliance in an equipment rack, you need to carry out the following tasks:
■
■
■
“Preparing for the job” on page 1
“Installing slide-rail assemblies” on page 3
“Mounting the appliance in the rack” on page 13
Preparing for the job
Before you start the assembly and installation process, you must assess the compatibility of the selected rack and gather the necessary personnel, tools, and materials. Proceed as follows.
1
INSTALLING THE VTL VALUE APPLIANCE IN AN EQUIPMENT RACK
▼
Obtaining required tools, personnel, and materials
1. Make sure that the selected rack meets the following specifications:
■
■
The rack has four posts, with a mounting at both front and rear (two-post racks are not compatible with the VTL Value slide-rails).
The horizontal opening and unit vertical pitch of the rack conform to ANSI/EIA
310-D-1992 or IEC 60927 standards.
■
■
■
■
The rack’s front and rear rack-mounting planes are 23-34 inches (58-87 cm) apart.
The minimum depth from the rack’s front cabinet door to the front rack-mounting plane is
1.85 inches (4.7 cm).
The minimum depth from the rear cabinet door to the front rack-mounting plane is
38 inches (96.5 cm) with the cable-management arm installed (recommended) or
31.5 inches (80.0 cm) without the cable management arm.
The minimum width between obstructions (such as structural supports and cable troughs) is 18 inches (45.6 mm) at all points between the front and rear mounting planes.
2. Make sure that the available power meets the requirements listed in the table below:
Location
US/North America:
EMEA:
Voltage Amperage
250 VAC 30 A
230 VAC 32 A
Plug type Receptacle type
NEMA L6 30P NEMA L6-30R
IEC-309P IEC-309R
3. Have the orderable slide-rail assemblies at hand.
4. Have the following tools at hand:
■ one 10-inch #2 Phillips screwdriver, preferably with a magnetic tip
■
■ a carpenter’s spirit level a mechanical lift (highly recommended).
Caution – The VTL Value appliance weighs 160 pounds (72.7 kg) when fully loaded with components. To prevent injury to personnel or damage to the equipment, Sun strongly recommends using a mechanical lift when installing the server in a rack.
5. If a mechanical lift is not available, make sure that at least four trained people are available to remove the server or reduce the weight of the server by removing components:
■
■
Remove both power supplies.
Remove the system controller.
2
VTL Value Hardware Installation Guide • Aug 2007 A • 316196101
316196101 • A
INSTALLING THE VTL VALUE APPLIANCE IN AN EQUIPMENT RACK
■
Label the hard disk drives in slots 2 to 46 and then remove them (you will reinstall the drives in their original slots using the labels as a guide).
Do not uninstall the fan trays or the bootable drives in slots 0 and 1.
6. If a mechanical lift is available, make sure that at least three people are on hand to install the server in the rack.
It takes two people to operate the lift and install the server and one additional person to insure that the rails are engaged correctly.
Next task:
“Installing slide‐rail assemblies” on page 3.
Installing slide-rail assemblies
■
■
The VTL Value slide-rail system use three-part rails. Each rail assembly consists of an outer rail that is fixed to the equipment rack, an inner rail that is fixed to the chassis of the VTL
Value appliance, and a middle rail that slides on the inner and outer rails. To install the rail assemblies, carry out the following tasks:
■
■
■
“Preparing the slide-rail assemblies for installation” on page 3
“Attaching the inner rails to the server chassis” on page 4
“Positioning the outer/middle rail assembly in the rack” on page 5.
“Attaching the outer/middle rail assembly to the rack” on page 8.
“Adjusting and securing middle/outer slide rails” on page 11.
▼
Preparing the slide-rail assemblies for installation
The slide-rail assemblies are shipped assembled, so you have to take them apart before you proceed further. Prepare each rail assembly as described below.
1. Unpack the slide-rail assembly.
2. Place the assembly on a flat surface.
Chapter 1 Installing VTL Value hardware
3
INSTALLING THE VTL VALUE APPLIANCE IN AN EQUIPMENT RACK
3. Push the slide-rail lock ( A below) to release the inner rail, and start to pull the inner rail out of the middle rail ( B ).
A
B
D
E
C
4. Continue to pull the inner rail out of the middle rail ( C above) until it contacts the internal stop ( D ).
5. Press the Push Here button on the green mounting-bracket release (
E above), and pull the mounting bracket free of the middle/outer rail assembly.
6. Repeat for the remaining slide-rail assembly.
Next task:
“Attaching the inner rails to the server chassis” on page 4.
▼
Attaching the inner rails to the server chassis
This procedure explains how to attach the inner rails to the server chassis. For each rail, proceed as described below.
4
VTL Value Hardware Installation Guide • Aug 2007 A • 316196101
316196101 • A
INSTALLING THE VTL VALUE APPLIANCE IN AN EQUIPMENT RACK
1. Position the inner rail ( A below) against the chassis with the slide-rail lock ( B ) at the front.
E
D
C
C
C
A
B
2. Align the three pairs of keyed openings on the inner rail with the three pairs of locating pins on the side of the chassis ( C above).
3. While pressing the rear of the rail against the side of the chassis, push the rail toward the rear of the chassis ( D above) until the rail clip ( E ) locks into place with an audible click.
4. Make sure that all six locating pins are locked into the keyed openings.
Next task:
▼
Positioning the outer/middle rail assembly in the rack
The VTL Value appliance is four rack-units (4U) high and quite heavy, due to the number of internal storage disks installed. You must therefore position the appliance in the rack carefully. The chosen location must allow enough space for a 4U appliance while presenting the smallest possible tipping hazard. Proceed as follows.
Chapter 1 Installing VTL Value hardware
5
INSTALLING THE VTL VALUE APPLIANCE IN AN EQUIPMENT RACK
1. Before you start, select the lowest possible position in the rack, and deploy the rack’s anti-tilt bar.
A top-heavy system tips over easily. So always load equipment into a rack from the bottom up and always place the heaviest equipment as low as possible. Always use the anti-tilt bar to keep the rack from tipping during installation. See the service label on the VTL Value appliance cover and/or the label on the rack.
2. Place the paper, rack-mount template ( E below) in the selected position.
The rack-mount template ships with the slide-rail assemblies. It is the same height as the appliance (four rack-units—4U) and is marked with four arrows that show the location of the rail mounting screws. In a rack with 3 mounting holes per rack unit (as in the illustration), the template covers 12 holes.
4 U
E
F
4 U
3. Use the arrows on the template to select the rack mounting hole that will take the top slide-rail mounting screw ( F above).
In the illustration above, the installed position of the slide rail is shown in pale gray.
6
VTL Value Hardware Installation Guide • Aug 2007 A • 316196101
INSTALLING THE VTL VALUE APPLIANCE IN AN EQUIPMENT RACK
4. At the rear of the rack, use tape ( G below) or a pin to temporarily mark the mounting hole ( H ) that corresponds to the mounting hole that you selected on the front.
4 U
G
H
5. Repeat steps 2-4 for the remaining middle/outer rail.
Next task:
“Attaching the outer/middle rail assembly to the rack” on page 8.
316196101 • A Chapter 1 Installing VTL Value hardware
7
INSTALLING THE VTL VALUE APPLIANCE IN AN EQUIPMENT RACK
▼
Attaching the outer/middle rail assembly to the rack
1. Before you begin, push the middle rail into the corresponding outer rail so that the ends are more or less flush. To do this, release the spring-activated slide-rail lock (
A
below) by pushing twice in the direction shown ( B ), then telescope the middle rail into the outer rail ( C ):
B
A
C
D
2. Adjust the length of the middle/outer slide-rail assemblies to the distance between the front and rear posts of the rack ( D above).
8
VTL Value Hardware Installation Guide • Aug 2007 A • 316196101
316196101 • A
INSTALLING THE VTL VALUE APPLIANCE IN AN EQUIPMENT RACK
3. Insert the oval-shaped neck of a temporary installation pin ( E below) into the ovalshaped hole in rear mounting bracket of the outer slide-rail ( F ), and turn the pin clockwise 90 degrees, so that the pin locks into place in the 3 o’clock position.
F
E
Temporary installation pins are packed in a plastic bag, with the slide-rail hardware.
4. Standing at the front of the rack, position the rail and bracket ( G below) so that you can draw the temporary installation pin ( H ) into the mounting hole in the rear rack post ( J ).
J
G
H
Chapter 1 Installing VTL Value hardware
9
INSTALLING THE VTL VALUE APPLIANCE IN AN EQUIPMENT RACK
5. If the rack has threaded mounting holes in the rack posts, insert the correct, metric or standard mounting screws through the slide-rail brackets and into the threaded holes.
The Sun™ Rack 1000 hardware uses metric screws.
6. If your rack does not have threaded mounting holes, insert the mounting screws through both the slide-rail brackets and rack posts, and then secure them with caged nuts.
7. Hand-tighten the screws in the front bracket holes ( K below).
You will use a slide-rail spacing tool later to make final adjustments.
K
8. Repeat this procedure with the remaining, unsecured middle/outer rail.
Next task:
“Adjusting and securing middle/outer slide rails” on page 11.
10
VTL Value Hardware Installation Guide • Aug 2007 A • 316196101
316196101 • A
INSTALLING THE VTL VALUE APPLIANCE IN AN EQUIPMENT RACK
▼
Adjusting and securing middle/outer slide rails
1. Once both slide rails are loosely fastened at the front, insert the slide-rail spacing tool/rack installation aid (
A below) into the outer rail brackets at the front of the rack
( B ).
A
B
C
2. Hold the slide-rail spacing tool in place as you tighten all four front screws with a #2
Phillips screwdriver ( C above).
The spacing tool should be a snug fit and might require pressure to ensure that it is fully engaged with the left and right slide rails.
3. Pull the slide-rail spacing tool straight out from the slide rails, taking care not to deform its alignment tabs.
Chapter 1 Installing VTL Value hardware
11
INSTALLING THE VTL VALUE APPLIANCE IN AN EQUIPMENT RACK
4. At the rear of the rack, hand-tighten a screw in each of the bottom holes on the outer rail brackets ( D below).
F
E
D
5. Once the bottom screw is started, replace the installation pins at the top ( E above) with hand-tightened screws ( F ).
12
VTL Value Hardware Installation Guide • Aug 2007 A • 316196101
INSTALLING THE VTL VALUE APPLIANCE IN AN EQUIPMENT RACK
6. Once both slide rails are loosely fastened at the rear, insert the slide-rail spacing tool into the outer rail brackets ( D below).
D
316196101 • A
E
F
7. Hold the spacing tool in place ( E above) as you tighten all four rear screws with a #2
Phillips screwdriver ( F ).
The spacing tool should be a snug fit and might require pressure to ensure that it is fully engaged with the left and right slide rails.
8. Pull the slide-rail spacing tool straight out from the slide rails, taking care not to deform its alignment tabs.
Next task:
“Mounting the appliance in the rack” on page 13.
Mounting the appliance in the rack
Once the inner rails are attached to the appliance chassis and the outer/middle rail assemblies are attached to the rack, you are ready to install the appliance in the rack. Proceed as follows.
Chapter 1 Installing VTL Value hardware
13
INSTALLING THE VTL VALUE APPLIANCE IN AN EQUIPMENT RACK
Caution – To reduce the risk of serious personal injury or equipment damage, use a mechanical lift when mounting the server in the rack. If a lift is not available, remove
1. Pull the middle rails out from the outer rails, past the internal stop, so that the middle rails are about 1.5 inches from the front face of the rail mounting bracket ( A below).
B
C
D
A
2. Make sure that the outer-rail ball-bearing retainer ( B above) is pulled to front of rail.
3. Make sure that the spring tab on the outer rail ball-bearing retainer is securely latched over the dimple on the middle slide rail ( C above).
14
VTL Value Hardware Installation Guide • Aug 2007 A • 316196101
INSTALLING THE VTL VALUE APPLIANCE IN AN EQUIPMENT RACK
4. Using a level ( D above), align the server with the rails, and insert the inner rails into the middle rails at the correct angle ( E below).
E
5. Have an assistant stand at the rear of the rack.
6. As you push the server into the rack, the assistant makes sure that the inner rails are engaged with the ball-bearing retainers ( F below) and sliding on the bearings on both slide rails.
The assistant makes sure that the rails are NOT merely pushing the ball-bearing retainers back into the rail assembly (
G
).
F G
316196101 • A
7. If there are problems, support the server with the mechanical lift, and realign the chassis-mounted inner rails with the rack-mounted middle rails.
8. Once the inner rails are correctly engaged and riding on the bearings, slide the server all the way into the rack to set the rail locks.
Chapter 1 Installing VTL Value hardware
15
CABLING
Caution – To prevent damage to the server or physical injury, if you are using a lift, keep the lift under the server. If you are manually installing the server, hold handles on each side of the server.
9. Test the operation of the slide-rails by slowly pulling the server out of the rack until the slide-rails reach their stops.
10. Test the operation of the slide-rails by pushing the server back into the rack until it reaches the internal stops.
11. Push the middle rail release button on each slide-rail while you simultaneously push the server past the stops.
12. Continue pushing the server fully into the rack until the slide-rail locks engage.
13. If you depopulated the server of components, reinstall the components that were removed. Make sure to replace hard disk drives in the same locations from which they were removed.
Next task:
“Installing the cable management arm” on page 16.
Cabling
To provide power and network connectivity to the VTL appliance, carry out the following tasks:
■
“Installing the cable management arm” on page 16
■
“Routing and connecting cables” on page 20.
Installing the cable management arm
■
■
The cable management arm (CMA) is optional, but highly recommended. The CMA protects
I/O and power cables from damage that might otherwise occur when you slide the server in and out of the rack. The CMA kit includes the following components:
■ an outer rail extension that, when viewed from the rear of the server, mounts the cable management arm on the right outer rail a bracket that connects the cable management arm to the chassis the cable management arm itself.
Use one CMA for each appliance. Never run cables from one appliance through a CMA attached to another server.
16
VTL Value Hardware Installation Guide • Aug 2007 A • 316196101
316196101 • A
CABLING
Note – References to “left” or “right” in the following procedures assume that you are facing the rear of the equipment rack.
▼
Attaching the Outer Rail Extension
1. Unpack the cable management arm (CMA) parts, and take them to the rear of the equipment rack.
A
B
C
2. Pull out the captive thumbscrew ( A above) and insert the outer rail extension to the right outer rail.
3. Insert the extension as far as it will go while aligning the captive thumbscrew with the hole in the outer rail ( B above).
4. Tighten the captive thumb screw to secure the rail extension ( C above).
5. Make sure that the server is all the way back in the rack, against the internal stops.
Chapter 1 Installing VTL Value hardware
17
CABLING
6. Align the CMA-to-chassis bracket with the mounting holes in the right side of the server, and hand tighten the upper and lower screws ( D and E below).
D
E
F
7. Using a #2 Phillips screwdriver, tighten all three screws. Access the lower screw using the hole provided ( F above).
8. Fold the cable management arm (CMA) back on itself ( G below).
H
G
18
VTL Value Hardware Installation Guide • Aug 2007 A • 316196101
CABLING
9. Push the CMA hinge plate ( H above and below) into the outer rail extension ( J below) until the captive thumbscrew on the hinge plate ( K ) aligns with the hole in the outer rail extension ( L ).
L
J
K
H
10. Tighten the captive thumbscrew (K above) to secure the cable management arm (CMA) to the rail extension.
316196101 • A Chapter 1 Installing VTL Value hardware
19
CABLING
11. Placing your hand under the CMA for support, fit the two pins ( M , N below) into the keyholes in the CMA-to-chassis bracket ( P , Q ) and rotate CMA towards you until it seats with an audible snap ( R ).
Q
P
M
N
R
Next task:
“Routing and connecting cables” on page 20.
Routing and connecting cables
■
■
Once you have racked the server and installed the cable management arm (CMA), you are ready to install cables, including:
■ power cords
Ethernet local area network (LAN) cables
Fibre Channel storage area network (SAN) cables
Proceed as follows.
▼
Installing data and power cables
1. On the cable management arm (CMA), pop the green tabs to open the cable hangers
( A
below).
20
VTL Value Hardware Installation Guide • Aug 2007 A • 316196101
CABLING
2. Route power, SAN, and LAN cables to the server through the CMA cable hangers
( B below).
You need to route the following cables:
■
■
■ one Ethernet LAN cable for the NETMGT port up to four Ethernet LAN cables for the LAN ports (NET0, NET1, NET2, and NET3).
optical Fibre Channel cables for each SAN client (backup server).
A
B
3. Connect the power cords to the connectors on the power supplies, and secure them to the chassis using the clips provided ( C below).
C
C
PORT 1 PORT 1
F
PORT 2 PORT 2
D
E
4. Route Ethernet LAN cables to the NETMGT port (
D
above) and the LAN ports, NET0,
NET1
, NET2, and NET3 (
E ), but do not connect them yet.
Wait to connect Ethernet cables until after LAN connectivity has been configured.
316196101 • A Chapter 1 Installing VTL Value hardware
21
STARTING THE VTL APPLIANCE
5. Route Fibre Channel Storage Area Network (SAN) cables to the host bus adapters
( W above), but do not connect them at this time.
Wait to connect Fibre Channel cables until after the Fibre Channel interfaces have been zoned to hosts.
6. Inspect the attached cables for binding or kinks, and make sure that the CMA extends easily and does not bind in the slide-rails. Adjust the cable hangers and CMA as required.
7. To maximize airflow, tie-wrap power cords at the bottom of the CMA troughs and LAN and SAN cables at the top.
Next task:
“Starting the VTL appliance” on page 22.
Starting the VTL appliance
Powering up a VTL appliance is a two-step process. First, you apply standby power to bring up the Integrated Lights Out Manger (ILOM) service processor. Then you apply main power to start the VTL server and boot the Solaris operating system.
Caution – The VTL Value appliance requires 200 to 240 VAC.
▼
Powering up
Caution – Do not operate the server for longer than 60m seconds unless all fans, component heat sinks, air baffles, and covers are installed. Severe damage to server components can occur if the server is operated without adequate cooling mechanisms.
22
VTL Value Hardware Installation Guide • Aug 2007 A • 316196101
STARTING THE VTL APPLIANCE
1. To apply standby power and start the service processor, plug the two VTL appliance power cords in to grounded, 200-240 VAC power outlets.
The startup process begins. It may take up to 58 seconds. When the service processor is up and the system is standing by, the OK LED on the front panel (
A
below) blinks, as does the
Enclosure Status OK
LED on the system controller (
B
).
A
B
316196101 • A Chapter 1 Installing VTL Value hardware
23
STARTING THE VTL APPLIANCE
2. Once standby power is on, start the VTL server. Use a stylus to press and release the recessed main power button on the server front panel ( C below).
The VTL appliance ships with a pre-configured Solaris operating system, so you do not have to do any additional configuration before applying main power.
When the server is up and running on main power, the OK LED (
D
) stops blinking and stays lit.
C
D
Next task:
“Setting up the VTL Value ILOM service processor” on page 25.
▼
Powering down
If you need to power off the appliance, you can proceed in any of three ways, depending on the circumstances.
1. Under normal circumstances, power off the server gracefully by using a stylus to press and release the power button on the front panel.
This is the normal way you shut down the VTL server. Pressing and releasing the power button causes the Advanced Configuration and Power Interface (ACPI) to stop the operating system in an orderly fashion before shutting main power off. It places the system in standby power mode. The OK LED on the front panel starts blinking.
2. In an emergency, power off the server immediately by using a stylus to press and hold the power button for four seconds.
This shuts the main power off and places the system in standby power mode. The OK LED on the front panel starts blinking.
3. Then, if you need to power off the appliance completely, so that neither the server nor the service processor draws power, unplug the AC power cords from the power supplies at the rear of the server.
The OK LED on the front panel is not lighted.
24
VTL Value Hardware Installation Guide • Aug 2007 A • 316196101
C H A PT E R
2
Setting up the VTL Value ILOM service processor
■
■
■
The Sun StorageTek VTL Value appliance is implemented on a Sun Fire X4500 server platform that has been specially configured for tape virtualization. Much of the configuration of the base X4500 server has already been done at the factory. You merely need to set the IP address of the VTL Value Integrated Lights Out Manager (ILOM) service processor. This chapter covers the following tasks:
“Understanding the ILOM” on page 25
“Changing the IP address of the ILOM SP” on page 26
“Changing the ILOM password” on page 29
■
“Checking the health of the internal storage systems” on page 30.
316196101 • A
Understanding the ILOM
The Sun Integrated Lights Out Manager (ILOM) is a service processor that supports operating-system independent management interfaces and applications for the Sun
StorageTek VTL Value appliance.
The core of the system is the Graphics Redirect and Service Processor (GRASP) hardware.
The GRASP monitors the status and configuration of field-replaceable VTL Value components, including fans, disk drives, and power supplies. It also provides the physical, serial and Ethernet management interfaces to the VTL Value system.
GRASP firmware provides a suite of management applications that run independent of the operating system and CPU:
■
A server-side Secure Shell (ssh) implementation supports encrypted remote login.
■
A commandline interface (CLI) supports serial access to the system.
25
CHANGING THE IP ADDRESS OF THE ILOM SP
■
■
A Simple Network Management Protocol (SNMP) interface supports network management using SNMP versions 1, 2c, or 3.
A web server supports Remote Console operations. The server provides a browseraccessible ILOM graphical user interface (GUI) and supports VTL Value console redirection. By downloading a Java application from the ILOM web interface, users can access the Solaris desktop on a remote VTL Value appliance using a local keyboard, monitor, and mouse.
Changing the IP address of the ILOM SP
The ILOM Ethernet management interface of the VTL appliance ships preconfigured with a private IP address. To complete the VTL hardware-installation process, you must change this private IP address to a customer specified address on the customer’s local area network
(LAN). This section explains:
■
■
Attaching a laptop to the ILOM via the VTL private network
Changing the IP address of the ILOM
▼
Attaching a laptop to the ILOM via the VTL private network
The VTL Value server incorporates a service processor running the Sun Integrated Lights
Out Management (ILOM) interface. ILOM is a Java-based remote management tool that can export the Solaris desktop from a VTL Value server to a browser running on another computer. VTL Value servers come preconfigured with a temporary IP address that is located on a private subnet. To connect a laptop to the server, you simply join the private subnet by setting your laptop’s IP address, attach a network cable, and open a web browser to the VTL
Value server’s ILOM address. This section describes the procedure in detail.
1. On your laptop, configure your local area network (LAN) connection using the IP
address 10.0.0.77.
The recommended address is on the private, 10.0.0.0 subnet used internally by the VTL
2. Connect the LAN port of the laptop to the Ethernet management (NETMGT) port on the
VTL server (
A below) using either of the following:
■
an Ethernet crossover cable
26
VTL Value Hardware Installation Guide • Aug 2007 A • 316196101
■
two standard Ethernet cables and a hub
CHANGING THE IP ADDRESS OF THE ILOM SP
A
3. Obtain passwords for the VTL Value ILOM and for Solaris.
Default passwords are posted on the Sun StorageTek Customer Resource Center at Current
Products > Appliance > Virtual Tape Library (VTL)
. If the defaults have already been changed, obtain the replacement passwords from the Sun engagement team or from a customer system administrator.
4. Open a web browser to the IP address of the VTL appliance ( B below). When the login
page appears, log in as root, and enter the server password (
C
). Press Log In (
D ).
B
https://10.0.0.100
316196101 • A root
********
C
Next task:
“Changing the IP address of the ILOM” on page 28.
D
Chapter 2 Setting up the VTL Value ILOM service processor
27
CHANGING THE IP ADDRESS OF THE ILOM SP
▼
Changing the IP address of the ILOM
1. When the Integrated Lights Out Manager page appears, press the
Configuration
button (
A below).
A
B
10.0.0.100
C
255.255.255.0
D
2. On the Network Settings panel, click the Use the Following IP Address
radio button ( B above).
3. Change the default IP Address and Subnet Mask shown to the IP address and
subnet mask specified by the customer ( C above).
4. Press Save (
D above).
5. Pass the ILOM IP address and subnet mask on to the rest of the engagement team.
The storage systems engineer will need this information when configuring the VTL software.
Next task:
“Changing the ILOM password” on page 29.
28
VTL Value Hardware Installation Guide • Aug 2007 A • 316196101
CHANGING THE ILOM PASSWORD
Changing the ILOM password
The Integrated Lights Out Manager (ILOM) service processor on the VTL Value appliance ships with a well-known default password that facilitates deployment and initial configuration. Once the initial configuration is complete, you must change this password to something that is more secure. Use the procedure below.
▼
Resetting the default ILOM password
1. On the Integrated Lights Out Manager web GUI page, press the User
Management
button ( A below).
A
C
B
2. Click the radio button for the root user account (
B above).
3. Press the Edit button (
C above).
316196101 • A Chapter 2 Setting up the VTL Value ILOM service processor
29
CHECKING THE HEALTH OF THE INTERNAL STORAGE SYSTEMS
4. When the edit dialog appears, enter the new password in the New Password and
Confirm New Password
fields ( D below).
D
E
F
5. Press Save (
E
above) and then Close (
F ).
Next task:
“Checking the health of the internal storage systems” on page 30.
Checking the health of the internal storage systems
Finally, check the health of the VTL Value appliance’s internal boot and storage volumes as follows:
■
■
“Accessing the Solaris desk top via the ILOM” on page 31.
“Running basic storage diagnostics” on page 33.
■
30
VTL Value Hardware Installation Guide • Aug 2007 A • 316196101
CHECKING THE HEALTH OF THE INTERNAL STORAGE SYSTEMS
▼
Accessing the Solaris desk top via the ILOM
1. On the Integrated Lights Out Manager (ILOM) page, press the Remote Control
button (
A below).
A
2. On the Launch Redirection panel, click the radio button for 8‐ or 16‐bit
resolution (
B
below), and press Launch Redirection (
C
).
B
C
Java starts, downloads files, and launches the Java console.
316196101 • A Chapter 2 Setting up the VTL Value ILOM service processor
31
CHECKING THE HEALTH OF THE INTERNAL STORAGE SYSTEMS
3. When the download dialog appears, click the Open with radio button, and select
Java(TM)
Web Start Launcher from the list (
D
below). Then press OK (
E
).
D
E
The jnlp file launches the Sun ILOM Remote Console application and displays the Solaris login screen for the VTL Value server.
4. When the Sun ILOM Remote Console application interface appears, select
Devices
from the main menu (
F
below), and check the Mouse check box in the
submenu (
G
).
You check the Mouse check box to enable mouse support inside the Remote Console environment.
F
G
H root
5. In the Please enter your user name field (
H above) of the Solaris login page,
enter root.
32
VTL Value Hardware Installation Guide • Aug 2007 A • 316196101
CHECKING THE HEALTH OF THE INTERNAL STORAGE SYSTEMS
6. When the Welcome root appears, enter the password for the Solaris root
account in the Please enter your password field (
J below).
J
When you enter your password, the Solaris desktop appears within the Sun ILOM
Remote
Console application.
Next task:
“Running basic storage diagnostics” on page 33.
▼
Running basic storage diagnostics
Before going further, make sure that the appliance’s storage subsystem is healthy.
316196101 • A Chapter 2 Setting up the VTL Value ILOM service processor
33
CHECKING THE HEALTH OF THE INTERNAL STORAGE SYSTEMS
1. On the VTL Value Solaris desktop, open a terminal window, and enter the metastat
command. Make sure that all metadevices return Okay:
# metastat d30: Mirror
Submirror 0: d31
Submirror 1: d32
Pass: 1
Read option: roundrobin (default)
Write option: parallel (default)
Size: 512007615 blocks (244 GB) d31: Submirror of d30
Size: 512007615 blocks (244 GB)
Stripe 0:
Device Start Block Dbase State Reloc Hot Spare c5t0d0s4 0 No
Okay
Yes d32: Submirror of d30
Size: 512007615 blocks (244 GB)
Stripe 0:
Device Start Block Dbase State Reloc Hot Spare
Okay Yes c5t4d0s4 0 No d40: Mirror
Submirror 0: d41
Submirror 1: d42
State: Okay ...
2. In the Solaris terminal window, enter the zpool status command. Make sure that:
■ there are six pools listed (vtlpool0-5)
■
■ every element—vtlpooln, raidz1, and disk (cxtydz)—is online four spares are listed and available (AVAIL) for each pool
34
VTL Value Hardware Installation Guide • Aug 2007 A • 316196101
316196101 • A
CHANGING THE SOLARIS ROOT PASSWORD
■ no data errors are reported
See the example below:
# zpool status
pool: vtlpool0
state: ONLINE
scrub: none requested config:
NAME
vtlpool0
raidz1
c0t0d0
c0t1d0
c0t2d0
c0t3d0
c0t4d0
c0t5d0
c0t6d0
spares
c0t7d0
c1t7d0
c7t7d0
c4t7d0 errors: No known data errors
AVAIL
AVAIL
AVAIL
AVAIL
STATE
ONLINE
ONLINE
ONLINE
ONLINE
ONLINE
ONLINE
ONLINE
ONLINE
ONLINE
READ WRITE CKSUM
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
Alternatively, to limit the output to problem pools only, use the following form of the command:
# zpool status -xv
3. Once you have finished your checks, close the terminal window.
Next task:
“Changing the Solaris root password” on page 35.
Changing the Solaris root password
You should not leave the system system configured with the default Solaris root password or share the default with the customer. Instead, change the default password to something the customer prefers. Proceed as follows.
Chapter 2 Setting up the VTL Value ILOM service processor
35
LOGGING OUT
▼
Changing the default Solaris root password
1. Enter the passwd command:
# passwd root passwd: Changing password for root
2. When prompted, enter the default root password
# passwd root passwd: Changing password for root
Enter login password:
3. When prompted, enter and re-enter the new root password:
# passwd root passwd: Changing password for root
Enter login password:
New password:
Re-enter new password: passwd (SYSTEM): passwd successfully changed for root
Next task:
Logging out
▼
Logging out of the operating system and ILOM
When you are finished changing the system root password and ILOM IP address and running diagnostics, log out, as described below.
1. Log out of the Solaris session on the appliance, and close the Sun ILOM Remote
Console
application.
36
VTL Value Hardware Installation Guide • Aug 2007 A • 316196101
LOGGING OUT
2. When the Integrated Lights Out Manager page reappears, go to the top of the
page and press LOG OUT (
A below).
A
This concludes the installation and initial configuration of the VTL Value appliance.
For VTL software configuration instructions, consult the VTL Software Configuration Guide, available from the Sun StorageTek Customer Resource Center under Current
Products > Appliance > Virtual Tape Library (VTL) > Manuals and
Guides
.
316196101 • A Chapter 2 Setting up the VTL Value ILOM service processor
37
LOGGING OUT
38
VTL Value Hardware Installation Guide • Aug 2007 A • 316196101
A P P E N D I X
A
The back and front panels of the
VTL Value server
1. AC power connectors with clips to secure power cables
2. Chassis ground 3. Mounting plate for CMA bracket
PORT 1 PORT 1
PORT 2 PORT 2
FIBRE
CHANNEL
FIBRE
CHANNEL
4 5 6 7 8 9 10 11 12 13
14
4. PCIX-0 and PCIX-1
7. SER MGT (serial connection to SP)
10. System OK/On Standby
5. NET MGT (SP)
8. Locate button/LED
11. USB connectors (2)
6. Video connector
9. Chassis fault LED
12. 10/100/1000 Gigabit Ethernet ports
13. System Controller status lights: Blue = Ready to remove; Amber = Fault; Green = OK
14. Service only: NMI and Reset
316196101 • A
39
USB connectors (2) Serial number labels on ledge (2)
1. Locate button/LED 2. System Fault LED
4. Power button 5. Top (hard disk drive or fan fault)
6. Rear (power supply or system controller fault)
1 2 3 4 5 6 7
3. Power/OK LED (system power)
7. System over temperature warning
40
VTL Value Hardware Installation Guide • Aug 2007 A • 316196101
A P P E N D I X
B
VTL private network addresses
Offering
Service
Device
laptop
Port name Port label IP address
10.0.0.77
Subnet mask
255.255.255.0
VTL Value system
ILOM e1000g0
VTL Plus Node1
Node1
Node1
Node2
Node2
Node2
Controller 1A
Controller 1B
Controller 2A
Controller 2B
BG0
BG1 mgmt
BG0
BG1 mgmt
Net 0
NETMGT
10.0.0.10
10.0.0.100
255.255.255.0
255.255.255.0
eth0 10.0.0.10
eth1 10.0.0.11
mgmt 10.0.0.100
eth0 10.0.0.20
eth1 10.0.0.21
mgmt 10.0.0.200
10.0.0.1
10.0.0.2
10.0.0.3
10.0.0.4
255.255.255.0
255.255.255.0
255.255.255.0
255.255.255.0
255.255.255.0
255.255.255.0
255.255.255.0
255.255.255.0
255.255.255.0
255.255.255.0
316196101 • A
41
42
VTL Value Hardware Installation Guide • Aug 2007 A • 316196101
A P P E N D I X
C
Connecting to ILOM via a serial port
Normally, you access the Integrated Lights Out Manager (ILOM) service processor of a VTL
Value appliance via the preconfigured Ethernet management port (NETMGT) and the ILOM graphical user interface (GUI). However, if network services are not available, you can still access the ILOM commandline interface (CLI) by connecting a terminal or a computer running terminal emulation software to the RJ-45 serial port on the back panel of the VTL
Value appliance.
1. Configure the terminal device or the terminal emulation software for
■
■
■
■ eight data bits, no parity, one stop bit
9600 baud no hardware flow control (CTS/RTS) no software flow control (XON/XOFF)
2. Connect an RJ-45 serial cable from the terminal device to the SER MGT port on the
back panel of the VTL appliance ( A below).
316196101 • A
A
3. Press Enter on the terminal device.
This establishes the connection between the terminal device and the ILOM.
43
Note – If you connect a terminal or emulator to the serial port before it has been powered up or during its power-up sequence, you will see bootup messages.
When the system has booted, the ILOM displays its login prompt:
SUNSP nnnnnnnnnn login:
The first string in the prompt is the default host name. It consists of the prefix SUNSP and the ILOM’s MAC address.
4. Log in to the CLI as root and enter the root password.
When you have successfully logged in, the SP displays the ILOM default command prompt:
->
The ILOM is now accessing the CLI. You can now run CLI commands.
For example, to display status information about the motherboard in your server, type the following command:
-> show /SYS/MB
Use the ILOM commands to configure the server’s user accounts, network settings, access lists, alerts, and so on. For detailed instructions on CLI commands, see the Integrated Lights
Out Manager (ILOM) Administration Guide, 819-1160.
5. To go to the host serial console (host COM0), type the following commands:
cd /SP/console
-> start
Note – After you have returned to the serial console, to switch back to the CLI, enter the
Escape
and left parenthesis [ ( ] key in rapid succession.
44
VTL Value Hardware Installation Guide • Aug 2007 A • 316196101
A P P E N D I X
D
ILOM command reference
The following table summarizes Integrated Lights Out Manager (ILOM) commands you can use to manage the service processor. For more information on ILOM commands, see the ILOM Administration Guide.
Description
User Commands
Add a local user.
Command
Delete a local user.
Change a local user’s properties.
Display information about all local users.
Display information about LDAP settings.
Change LDAP settings.
create /SP/users/
user1 password=password
role=administrator|operator delete /SP/users/
user1
set /SP/users/
user1 role=operator
show -display [
targets|properties|all]
-level [
value|all] /SP/users
show /SP/clients/ldap set /SP/clients/ldap binddn=
proxyuser
bindpw=
proxyuserpassword
defaultrole=administrator|operator ipaddress=
ipaddress
Network and Serial Port Setting Commands
Display network configuration information.
Change network properties for the ILOM.
Changing certain network properties, like the
IP address, disconnects your active session.
Display information about the external serial port.
show /SP/network set /SP/network pendingipaddress=
ipaddress
pendingipdiscovery=dchp|static pendingipgateway=
ipgateway
pendingipnetmask=
ipnetmask commitpending=true
show /SP/serial/external
316196101 • A
45
Description
Change the external serial port configuration.
Command set /SP/serial/external pendingspeed=
integer
commitpending=true show /SP/serial/host
Display information about the serial connection to the host.
Change the host serial port configuration.
Note: This speed setting must match the speed setting for serial port 0, COM1 or /dev/ttyS0 on the host operating system.
Alert Commands
Display information about PET alerts. You can configure up to 15 alerts.
Change alert configuration.
set /SP/serial/host pendingspeed=
integer
commitpending=true show /SP/alert/rules/1...15
set /SP/alert/rules/1...15 destination=
ipaddress
level=
down|critical|major|minor
System Management Access Commands
Display information about HTTP settings.
Change HTTP settings, such as enabling automatic redirection to HTTPS.
Display information about HTTPS access.
Change HTTPS settings.
show /SP/services/http set /SP/services/http port=
portnumber
secureredirect enabled|disabled servicestate=
enabled|disabled
show /SP/services/https set /SP/services/https port=
portnumber
servicestate=
enabled|disabled
Display SSH DSA key settings.
Display SSH RSA key settings.
SNMP Commands
Display information about SNMP settings. By default, the SNMP port is 161 and v3 is enabled.
show /SP/services/ssh/keys/dsa show /SP/services/ssh/keys/rsa
show /SP/services/snmp engineid=snmpengineid
port= v1
snmpportnumber sets=enabled|disabled
=enabled|disabled v2c=enabled|disabled
v3
=enabled|disabled
Display SNMP users.
Add an SNMP user.
Delete an SNMP user.
Display information about SNMP public
(read‐only) communities.
show /SP/services/snmp/users create /SP/services/snmp/users/
snmpusername
authenticationpassword=
password
authenticationprotocol=
MD5|SHA
permissions=
rw|ro privacypassword=
password
privacyprotocol=
none|DES
delete /SP/services/snmp/users/
snmpusername
show /SP/services/snmp/communities/public
46
VTL Value Hardware Installation Guide • Aug 2007 A • 316196101
Description Command
Add this device to an SNMP public community.
create /SP/services/snmp/communities/ public/
comm1
Delete this device from an SNMP public community.
Display information about SNMP private
(read‐write) communities.
Add this device to an SNMP private community.
delete /SP/services/snmp/communities/ public/
comm1
show /SP/services/snmp/communities/private create /SP/services/snmp/communities/ private/
comm2
Host System Commands
Delete this device from an SNMP private community.
Start the host system.
Stop the host system.
Reset the host system.
delete /SP/services/snmp/communities/ private/
comm2
start /SYS stop /SYS reset /SYS
Start a session to connect to the host console.
start /SP/console
Stop the session connected to the host console.
stop /SP/console
Clock Settings
Set the ILOM clock to synchronize with a primary NTP server.
Set the ILOM clock to synchronize with a secondary NTP server.
set /SP/clients/ntp/server/1 address=
ntpIPaddress
set /SP/clients/ntp/server/2 address=
ntpIPaddress2
316196101 • A Chapter D ILOM command reference
47
48
VTL Value Hardware Installation Guide • Aug 2007 A • 316196101
A P P E N D I X
E
Removing VTL Value hardware
When preparing to remove a VTL Value system from an equipment rack, see the following:
■
“Shutting off system power” on page 49
■
“Removing the cable management arm” on page 50
■
“Removing the VTL appliance from a rack” on page 51.
316196101 • A
Shutting off system power
▼
Powering down
If you need to power off the appliance, you can proceed in any of three ways, depending on the circumstances.
1. Under normal circumstances, power off the server gracefully by using a stylus to press and release the power button on the front panel.
This is the normal way you shut down the VTL server. Pressing and releasing the power button causes the Advanced Configuration and Power Interface (ACPI) to stop the operating system in an orderly fashion before shutting main power off. It places the system in standby power mode. The OK LED on the front panel starts blinking.
2. In an emergency, power off the server immediately by using a stylus to press and hold the power button for four seconds.
This shuts the main power off and places the system in standby power mode. The OK LED on the front panel starts blinking.
3. Then, if you need to power off the appliance completely, so that neither the server nor the service processor draws power, unplug the AC power cords from the power supplies at the rear of the server.
The OK LED on the front panel is not lighted.
49
REMOVING THE CABLE MANAGEMENT ARM
Removing the cable management arm
If you need to access the system controller (SC), remove the cable management arm (CMA) using the following procedure.
1. If you have not already done so, shutdown main (server) and standby (service
processor) power, as described in “Shutting off system power” on page 49.
2. Unplug the power and data cables from the server.
3. Lift the small tab (
A
below) on the CMA-to-chassis bracket to release the right pinhead
( B ).
A
E
D
B
C
4. Push the CMA toward the chassis ( C above), so that the second pinhead ( D ) aligns with the keyhole ( E ), freeing the CMA to drop away from the bracket.
5. Pull the CMA away from the rear of the chassis, and remove the CMA from the slide-rail extension.
50
VTL Value Hardware Installation Guide • Aug 2007 A • 316196101
316196101 • A
REMOVING THE VTL APPLIANCE FROM A RACK
Removing the VTL appliance from a rack
This procedure assumes you have turned off the server, removed the cable management arm, and removed any cables or cords that would restrict the movement of the server.
▼
Preparing to remove the appliance
1. If you have not already done so, shutdown main (server) and standby (service
processor) power, as described in “Shutting off system power” on page 49.
2. If you have not already done so, remove the cable management arm (CMA), as
described in “Removing the cable management arm” on page 50.
3. Have a mechanical lift on hand, if at all possible.
Caution – The VTL Value appliance weighs 160 pounds (72.7 kg) when fully loaded with components. To prevent injury to personnel or damage to the equipment, Sun strongly recommends using a mechanical lift when installing the server in a rack.
4. If a mechanical lift is not available, make sure that at least four trained people are available to remove the server and/or reduce the weight of the server by removing components:
■
■
■
Remove both power supplies.
Remove the system controller.
Label the hard disk drives in slots 2 to 46 and then remove them (you will reinstall the drives in their original slots using the labels as a guide).
Do not uninstall the fan trays or the bootable drives in slots 0 and 1.
5. If a mechanical lift is available, make sure that at least three trained people are available to install the server in the rack.
It takes two people to operate the lift and install the server and one additional person to insure that the rails are engaged correctly.
Next task:
“Removing the appliance from the rack” on page 51.
▼
Removing the appliance from the rack
1. From the front of the rack, squeeze the slide-rail locks (with green plastic handles) to release the lock and pull the server about 1.5 inches from the rack.
2. Push the green plastic tabs on the middle slide rails to release the first stop.
Chapter E Removing VTL Value hardware
51
REMOVING THE VTL APPLIANCE FROM A RACK
3. Push the green plastic tabs on the middle slide rails to release the second stop and pull the server out about 36 inches from the rack.
4. If you do not have a mechanical lift, open the hard disk drive access cover and remove
5. Slide the server completely out of the slide rails and place on a clean, stable surface.
Note – If you are removing the server in a data center with narrow aisles (under
44 inches or approximately 1.12 meters wide), you can order a narrow aisle removal kit from
Sun Service.
52
VTL Value Hardware Installation Guide • Aug 2007 A • 316196101
Download
Advertisement
Key features
Rack mounting
Cabling
Power up procedures
Initial configuration
Network configuration
Basic checks
Installation guide
VTL appliance setup
Frequently asked questions
The installation guide provides detailed steps for installing the appliance in a rack, including preparing the slide-rail assemblies, attaching the inner rails to the server chassis, positioning the outer/middle rail assembly in the rack, attaching the outer/middle rail assembly to the rack, and adjusting and securing middle/outer slide rails.
You need to connect power cords, Ethernet LAN cables, and Fibre Channel SAN cables. The guide provides instructions for routing and connecting these cables.
To power up the appliance, you need to apply standby power to bring up the Integrated Lights Out Manager (ILOM) service processor and then apply main power to start the VTL server and boot the Solaris operating system. The guide provides step-by-step instructions for powering up and down the appliance.
The guide explains how to change the IP address of the ILOM SP, change the ILOM password, and check the health of the internal storage systems.