Teradata 1700 Platform Integrated Big Data Platform Product and Site Preparation Guide
Below you will find brief information for Integrated Big Data Platform 1700 Platform. The 1700 Platform is a high-performance data warehouse and analytics platform that can handle large volumes of data. It is designed for organizations that need to make quick and informed decisions based on their data. The platform includes a variety of features that make it easy to manage and use, including a user-friendly interface and a powerful query engine. The 1700 Platform is a versatile solution that can be used for a variety of applications, including data warehousing, business intelligence, and analytics.
Advertisement
Advertisement
What would you do if you knew?™
Teradata Integrated Big Data Platform
1700 Platform
Product and Site Preparation Guide
B035-5473-063K
December 2016
The product or products described in this book are licensed products of Teradata Corporation or its affiliates.
Teradata, Applications-Within, Aster, BYNET, Claraview, DecisionCast, Gridscale, MyCommerce, QueryGrid, SQL-MapReduce, Teradata
Decision Experts, "Teradata Labs" logo, Teradata ServiceConnect, Teradata Source Experts, WebAnalyst, and Xkoto are trademarks or registered trademarks of Teradata Corporation or its affiliates in the United States and other countries.
Adaptec and SCSISelect are trademarks or registered trademarks of Adaptec, Inc.
Amazon Web Services, AWS, [any other AWS Marks used in such materials] are trademarks of Amazon.com, Inc. or its affiliates in the United
States and/or other countries.
AMD Opteron and Opteron are trademarks of Advanced Micro Devices, Inc.
Apache, Apache Avro, Apache Hadoop, Apache Hive, Hadoop, and the yellow elephant logo are either registered trademarks or trademarks of the
Apache Software Foundation in the United States and/or other countries.
Apple, Mac, and OS X all are registered trademarks of Apple Inc.
Axeda is a registered trademark of Axeda Corporation. Axeda Agents, Axeda Applications, Axeda Policy Manager, Axeda Enterprise, Axeda Access,
Axeda Software Management, Axeda Service, Axeda ServiceLink, and Firewall-Friendly are trademarks and Maximum Results and Maximum
Support are servicemarks of Axeda Corporation.
CENTOS is a trademark of Red Hat, Inc., registered in the U.S. and other countries.
Cloudera, CDH, [any other Cloudera Marks used in such materials] are trademarks or registered trademarks of Cloudera Inc. in the United States, and in jurisdictions throughout the world.
Data Domain, EMC, PowerPath, SRDF, and Symmetrix are registered trademarks of EMC Corporation.
GoldenGate is a trademark of Oracle.
Hewlett-Packard and HP are registered trademarks of Hewlett-Packard Company.
Hortonworks, the Hortonworks logo and other Hortonworks trademarks are trademarks of Hortonworks Inc. in the United States and other countries.
Intel, Pentium, and XEON are registered trademarks of Intel Corporation.
IBM, CICS, RACF, Tivoli, and z/OS are registered trademarks of International Business Machines Corporation.
Linux is a registered trademark of Linus Torvalds.
LSI is a registered trademark of LSI Corporation.
Microsoft, Active Directory, Windows, Windows NT, and Windows Server are registered trademarks of Microsoft Corporation in the United States and other countries.
NetVault is a trademark or registered trademark of Dell Inc. in the United States and/or other countries.
Novell and SUSE are registered trademarks of Novell, Inc., in the United States and other countries.
Oracle, Java, and Solaris are registered trademarks of Oracle and/or its affiliates.
QLogic and SANbox are trademarks or registered trademarks of QLogic Corporation.
Quantum and the Quantum logo are trademarks of Quantum Corporation, registered in the U.S.A. and other countries.
Red Hat is a trademark of Red Hat, Inc., registered in the U.S. and other countries. Used under license.
SAP is the trademark or registered trademark of SAP AG in Germany and in several other countries.
SAS and SAS/C are trademarks or registered trademarks of SAS Institute Inc.
Simba, the Simba logo, SimbaEngine, SimbaEngine C/S, SimbaExpress and SimbaLib are registered trademarks of Simba Technologies Inc.
SPARC is a registered trademark of SPARC International, Inc.
Symantec, NetBackup, and VERITAS are trademarks or registered trademarks of Symantec Corporation or its affiliates in the United States and other countries.
Unicode is a registered trademark of Unicode, Inc. in the United States and other countries.
UNIX is a registered trademark of The Open Group in the United States and other countries.
Other product and company names mentioned herein may be the trademarks of their respective owners.
The information contained in this document is provided on an "as-is" basis, without warranty of any kind, either express or implied, including the implied warranties of merchantability, fitness for a particular purpose, or non-infringement.
Some jurisdictions do not allow the exclusion of implied warranties, so the above exclusion may not apply to you. In no event will Teradata Corporation be liable for any indirect, direct, special, incidental, or consequential damages, including lost profits or lost savings, even if expressly advised of the possibility of such damages.
The information contained in this document may contain references or cross-references to features, functions, products, or services that are not announced or available in your country. Such references do not imply that Teradata Corporation intends to announce such features, functions, products, or services in your country. Please consult your local Teradata Corporation representative for those features, functions, products, or services available in your country.
Information contained in this document may contain technical inaccuracies or typographical errors. Information may be changed or updated without notice. Teradata Corporation may also make improvements or changes in the products or services described in this information at any time without notice.
To maintain the quality of our products and services, we would like your comments on the accuracy, clarity, organization, and value of this document. Please e-mail: [email protected]
Any comments or materials (collectively referred to as "Feedback") sent to Teradata Corporation will be deemed non-confidential. Teradata
Corporation will have no obligation of any kind with respect to Feedback and will be free to use, reproduce, disclose, exhibit, display, transform, create derivative works of, and distribute the Feedback and derivative works thereof without limitation on a royalty-free basis. Further, Teradata
Corporation will be free to use any ideas, concepts, know-how, or techniques contained in such Feedback for any purpose whatsoever, including developing, manufacturing, or marketing products or services incorporating Feedback.
Copyright © 2013 - 2016 by Teradata. All Rights Reserved.
NOTICE
This is a contractual document. It contains important warnings and confers important legal rights and obligations. You are advised to read it carefully.
It is the responsibility of the customer to assure that all installation preparations are complete and in compliance with Teradata Corporation specifications and requirements and all applicable national, state, or local codes, regulations, and laws.
SITE PREPARATION
This document contains the information necessary for the preparation of a site conforming to Teradata Corporation specifications.
• It is very important that the site complies with the requirements specified in this document because, once the equipment has been installed, deficiencies in site preparation or the problems caused by these deficiencies are much more difficult to detect and correct.
• Failure to comply with these requirements or take proper steps to protect equipment against risks identified in this document may cause serious damage to the equipment and to the customer's business.
• In addition to the need to comply with the requirements specified, electrical wiring and mechanical systems must also comply with all relevant codes, laws, and regulations.
• It is important that the site be prepared by a customer or his agent who is fully conversant with the special requirements of electronic equipment.
• The responsibility for ensuring that the site is prepared in compliance with this document remains with the customer.
For information and guidance purposes only, a list is provided, in general terms, of these matters for which the customer is responsible. This list is not intended to be comprehensive, and in no way modifies, alters, or limits the responsibility of the customer for all aspects of adequate site preparation.
Teradata staff will be available to answer questions relating to the contents of this document, except where:
• The customer has been notified that a full or partial consultant service is available and/or that Teradata will be willing to undertake a preliminary or final site survey, and
• The customer shall have entered into a formal contract with Teradata for provision of the same.
No comment, suggestion, or advice offered or not offered about preparation of the site, nor any inspection of the site whether before or after preparation, is to be taken as approval of the location of the site and equipment, or of its preparation, and Teradata will not be liable in respect of any comment, suggestion, or advice given by its staff, or in respect of any failure to give advice. Problems caused by a customer’s failure to meet any of the site prep requirements may result in Teradata doing any, or all, of the following:
• Charging the customer for additional services
• Reclassifying a reported problem priority
• Being relieved of the obligation to perform services
Finally, only the customer can know the full extent of damage which may be caused to his business by reason of failure of equipment which is to be installed. For this reason it is the customer's responsibility to ascertain the extent of any such possible damage to his existing or planned business, and to effect full insurance in respect of it.
CUSTOMER RESPONSIBILITIES
The customer must do or provide the following:
• When required by Teradata, provide the Teradata customer service representative with appropriate drawings that indicate:
• Location of the equipment
• Site wiring (power and signal, paths and lengths)
• Location of other equipment capable of generating electrical noise, electromagnetic interference, heat, etc.
• Make building alterations necessary to meet wiring and other site requirements.
• Provide and install all communications cables, wall jacks, special connectors, and associated hardware.
• Make sure all applicable codes, regulations, and laws (including, but not limited to, electrical, building, safety, and health) are met.
• Provide and install auxiliary power or other equipment as required.
• Make sure the environmental requirements of the system/unit are met.
• Provide floor coverings and environmental systems that limit or control static electricity build-up and discharge.
• Allow Teradata ServiceConnect remote connectivity.
AC POWER LINE TRANSIENT PROTECTION
In the process of power distribution, transient electrical energy (including, but not limited to, lightning strikes, intermittent short circuits, and switching transients) can be introduced on to power lines. Such transient energy can be very damaging to electronic hardware and can also cause data corruption.
Under these circumstances, Teradata Corporation recommends the use of AC power transient suppressors and data (communication) line transient suppressors. Such protective devices are intended to guard against power and data line transients that can result in hardware damage and various system or program errors.
Improvement of any deficiencies in power quality is a customer responsibility. Malfunction and/or component failure as a result of power quality problems are/is not covered by Teradata Maintenance Agreement. Teradata Corporation accepts no liability for any such occurrence nor for its consequences.
DATA LINE TRANSIENT PROTECTION
The nature of the transient phenomenon may extend to the data communication lines connected to this equipment. It is the responsibility of the customer to install and connect a data line transient suppression system to correct or prevent any deficiencies. Malfunction and/or component failure as a result of data quality problems are/is not covered by the Teradata Maintenance Agreement. Teradata Corporation accepts no liability for any such occurrence or for its consequences.
Table of Contents
Preface
.................................................................................................................................................................13
Chapter 1:
Product Information
........................................................................................................................ 17
1700 Platform Product and Site Preparation Guide 5
6
Table of Contents
Chapter 2:
Site Preparation Summary
......................................................................................................67
Chapter 3:
Hardware Installation Planning
......................................................................................73
Chapter 4:
Uncrating and Installation
......................................................................................................75
1700 Platform Product and Site Preparation Guide
Table of Contents
Appendix A:
Physical Specifications for Site Planning
...........................................................91
Appendix B:
Site Power Distribution Planning
................................................................................103
Appendix C:
Site Environmental Planning
............................................................................................. 117
1700 Platform Product and Site Preparation Guide 7
Table of Contents
Hardware Placement Guidelines for Non-Raised Floor and Containment Environment ..................126
Measuring Air Flow Rate Using an Air Flow Meter and Handmade Air Capture Hood
8 1700 Platform Product and Site Preparation Guide
List of Figures
Figure 8: 108-Port BYNET Switch Cabinet: Primary and Secondary Server Management Networks in
Figure 9: 162-Port BYNET V5 Cabinet: Primary and Secondary Server Management Networks in Cabinets
Figure 10: 324-Port BYNET V5 Cabinet: Primary and Secondary Server Management Networks in
Figure 13: Server Management Network for System with Maximum 162 Nodes, 2 BYNET V5 Cabinets ....51
Figure 35: Recommended Front-to-Front Hardware Placement on Raised Floor and Open Return
1700 Platform Product and Site Preparation Guide 9
List of Figures
Figure 36: Recommended Raised Floor Layout for Optimum Cooling and Airflow with Open Return
Figure 41: Cold Air Delivery through Cabinet Front by In-Row Cooling Units in Hot Aisle Containment
10 1700 Platform Product and Site Preparation Guide
List of Tables
Table 8: Processing/Storage Cabinet Two-Cord 60A Three-Phase Delta Watertight Power Plugs and
Table 9: Processing/Storage Cabinet Two-Cord 30/32A Three-Phase Wye Splash-Proof Power Plugs and
1700 Platform Product and Site Preparation Guide 11
List of Tables
12 1700 Platform Product and Site Preparation Guide
Preface
Purpose
The purpose of this guide is to introduce and define the system architecture and components, and to describe the requirements for preparing a site to receive and install the system.
Audience
The audience includes, but is not limited to:
• Customer system administrators and facilities personnel
• Teradata installation, service, and support personnel
Prerequisites
You should have access to, or be familiar with, the following:
• Standard industry terminology
• System networking protocol
• Local installation practices for large computer systems
• Heating, ventilating, and air-conditioning (HVAC) terminology and practices
Revision History
Date
December 2016
April 2016
Description
Added new signed and dated Declaration of Conformity certificates
Added 4TB disk drives
Updated the following notices:
• Regulatory Compliance and Electromagnetic Compatibility Notices
February 2016
• Added information on new Dell R730 and R730xd chassis that can be used as a
TMS or SAS HPA worker node
1700 Platform Product and Site Preparation Guide 13
Preface
Additional Information
Date
March 2015
April 2014
August 2013
Description
Note:
For information on the Dell Server configured for SAS High-Performance
Analytics in-memory software, see the Teradata Appliance for SAS High-
Performance Analytics Model 720 Platform Product and Site Preparation Guide,
B035-5410, or the Teradata Appliance for SAS High-Performance Analytics
Model 750 Platform Product and Site Preparation Guide, B035-6042.
• Added new signed and dated RCM Supplier's Declaration of Conformity
• Clarified the estimated power statement
• Added information for the Dell X1026 24-Port Ethernet switch
• Updated drive capacities for HDDs used in nodes to reflect currently available offerings
• Updated the China declaration statement for RoHS compliance
• Added information about the option to use a BYNET V5 InfiniBand adapter in
TMSs
• Added instructions for uncrating and moving cabinets, as customers are responsible for moving or hiring a service to move Teradata cabinets
• Reorganized the Site Environmental Planning appendix
• Updated the Input Power Plugs and Receptacles sections
• Deleted Suggested Floor Layout topics from the Hardware Placement Guidelines
for Raised Floor and Open Return Environment section; see About Equipment
Floor Layouts
• Added 512 GB memory using 32 GB DIMMs in Platform Features Summary,
Chapter 1
• Added Dell R720 SAS HPA worker nodes
• Added 108-port BYNET V5 switches
• Added non-raised floor information to Floor Layouts, Appendix A
• Added 3+0 clique configuration
• Removed Luminex ESCON
• Added host channel adapters to Platform Features Summary, Chapter 1
• Enhanced Input Power Plugs and Receptacles in Appendix B (added more examples of receptacles and connectors; added sample illustrations of power plugs, connectors, and receptacles for each power option)
• Revised illustrations in About Equipment Floor Layout, Appendix C
Initial release June 2013
Additional Information
Updates and supplementary information are available online.
http://www.teradata.com
Internet site for product, service, resource, support, and other customer information
14 1700 Platform Product and Site Preparation Guide
http://www.info.teradata.com
http://infocentral.daytonoh.teradata.com/tsd-library/ index.cfm
http://infocentral.daytonoh.teradata.com/tsd-library/ isupr.cfm
http://tssprod.teradata.com:8080/TSFS/
Preface
Product Safety Information
Internet site for published Teradata customer documentation
Intranet site for published Teradata service documentation
Section of the intranet site for Teradata service documentation specific to software installation and upgrade information
Intranet site linking to Teradata software server
Product Safety Information
This document contains several types of product safety practices information.
Safety Information Type Description
Notice Indicates a situation which, if not avoided, could result in damage to property, such as to equipment or data, but not related to personal injury.
Caution
WARNING
Indicates a hazardous situation which, if not avoided, could result in minor or moderate personal injury.
Indicates a hazardous situation which, if not avoided, could result in death or serious personal injury.
Examples
Notice:
Wear an anti-static wrist strap attached to an unpainted metal surface on the rack or chassis when handling parts.
Caution:
A drive enclosure weighs approximately 28.6 kg (63 lb). Do not attempt to remove or install the chassis until all the drives and modules have been removed.
WARNING:
Risk of electrical shock! Always remove power to the power supply/fan module before servicing it.
1700 Platform Product and Site Preparation Guide 15
Preface
Product Safety Information
16 1700 Platform Product and Site Preparation Guide
CHAPTER 1
Product Information
Product Description
The Teradata Integrated Big Data Platform 1700 is an optimized, fully-integrated data warehouse solution designed for decision-support workloads that typically require fast data scans and heavy analytics.
The 1700 platform can scale to:
• 22 nodes using in-cabinet BYNET-over-Ethernet switches
• 36 nodes using in-cabinet BYNET V5 switches
• 108 nodes using external BYNET V5 cabinets
• 162 nodes using external BYNET V5 cabinets
• 324 nodes using external BYNET V5 cabinets
The platform is offered with the following software:
• Teradata Database 14.00.03 or later
• Teradata Tools and Utilities 14.0
• SUSE Linux Enterprise Server 11 (SLES 11)
Platform Features Summary
The following table outlines the features and components of the 1700 platform.
Note:
We reserve the right to replace any of the listed drives with an equivalent or better drive.
Feature
Processing Node
Feature Description
Processing and hot standby nodes consist of an Intel R2208 chassis with:
• Two 2.6 GHz eight-core E5-2670 processors (20MB L3 cache)
• 128 GB or 256 GB memory using 16 GB DIMMs, or 512 GB memory using 32
GB DIMMs, all at 1333 MHz DDR3
• Disk drives:
∘ Two 600 GB SAS (serial-attached SCSI) drives for OS
∘ One 600 GB SAS drive for dump processing to improve restart performance
∘ Five additional drive bays available for customer use; 600 GB drives supported
• DVD drive
• Onboard connectivity to the server management network
• Onboard connectivity to the BYNET-over-Ethernet network or adapter connectivity to the BYNET V5 InfiniBand network
1700 Platform Product and Site Preparation Guide 17
Chapter 1: Product Information
Platform Features Summary
Feature
Disk Storage
Channel Server
Extended Channel
Solution (ECS)
Feature Description
• Disk storage adapters
• Optional network communication adapter
• Optional network connection to managed BAR servers
Disk arrays:
Each disk array in a 1700 cabinet contains five Gelding (2Ux12) drive enclosures:
• Each drive enclosure contains two power supply modules.
• The lowest drive enclosure in each array contains two array controller modules
(RIOMs).
• Each of the remaining four drive enclosures contains two expansion modules
(JIOMs).
• Each drive enclosure contains SAS storage drives.
Storage drives:
• 2 TB and 4 TB storage drives (3.5", 7.2K rpm) with one or two global hot spares
(GHSs) per array
Intel R2208 server, configured as dedicated server for interface between Teradata
Database and IBM (or compatible) mainframe:
• Disk drives:
∘ Two 600 GB SAS drives for OS
∘ One 600 GB SAS drive for dump processing to improve restart performance
• Dual 2.0GHz six-core 15MB L3 cache E5-2620 processors
• 128 GB memory using 16 GB DIMMs
• Host channel adapters -- maximum three FICON adapters
• No disk array support
• No amps assigned
• Onboard connectivity to the server management network
• Onboard connectivity to the BYNET-over-Ethernet network or adapter connectivity to the BYNET V5 InfiniBand network, no AMPs assigned
• Optional network communication adapter
For information about HCA configuration, see the Host Channel Adapter
Installation and Service Guide, B035-5044.
Dell R720 server, configured as dedicated server for interface between Teradata
Database and IBM (or compatible) mainframe.
Dell R720 server drive, processor, and memory configuration:
• Two 900 GB or 1.2 TB SAS drives for OS
• Dual 2.0 GHz six-core 15MB L3 cache E5-2620 processors
• 128 GB memory using 16 GB DIMMs
General ECS configuration:
• Host channel adapters -- maximum three FICON adapters
• No disk array support
• Onboard connectivity to the server management network
18 1700 Platform Product and Site Preparation Guide
Chapter 1: Product Information
Platform Features Summary
Feature Feature Description
• Ethernet adapter connection to the processing nodes
• Optional network communication adapter
Network Connectivity
Server (NCS)
Intel R1208 server, configured as dedicated server for providing additional customer network connectivity options:
• Disk drives:
∘ Two 600 GB SAS drives for OS
∘ One 600 GB SAS drive for dump processing to improve restart performance
• Dual 2.0GHz six-core 15MB L3 cache E5-2620 processors
• 128 GB memory using 8 GB DIMMs
• Onboard connectivity to the server management network
• Onboard connectivity to the BYNET-over-Ethernet network or adapter connectivity to the BYNET V5 InfiniBand network
• Optional network communication adapter
• Optional quad-port 1 GbE or dual-port 10 GbE modules for additional network communication
Teradata Managed Server
(TMS)
Teradata Multipurpose
Server (TMS)
TMSs consist of Dell R720, Dell R720xd, Dell R730, or Dell R730xd servers used for solution offerings that are peripheral to Teradata processing.
All TMSs have onboard connectivity to the server management network.
If sufficient BYNET V5 switch ports are available, the server can also be connected to the BYNET V5 switches.
For information about TMS configurations, see the Teradata Platform Framework
Cabinet Model 12 Product and Site Preparation Guide, B035-5388.
SAS HPA Worker Node Dell Server configured for SAS High-Performance Analytics in-memory software.
For more information, see the Teradata Appliance for SAS High-Performance
Analytics Model 720 Platform Product and Site Preparation Guide, B035-5410, or the
Teradata Appliance for SAS High-Performance Analytics Model 750 Platform
Product and Site Preparation Guide, B035-6042.
Dump Server Dell R720xd server, configured as dedicated hardware to be used for crash dump data analysis.
Data can be offloaded from the production data warehouse environment to a dump server, allowing for analysis without disruption to the production system. The dump server must run the same version of Teradata Database as the production system from which the dump data was offloaded.
Each dump server consists of:
• Two 2.6 GHz eight-core 20MB L3 cache E5-2670 processors
• 256 GB memory in 16 GB DIMMs (1333 MHz DDR3)
• Two 2.5" 10K rpm 900 GB or 1.2 TB SAS drives for OS
• Twenty-four 2.5" 10K rpm 900 GB or 1.2 TB SAS drives for storage
• Onboard connectivity to the server management network
1700 Platform Product and Site Preparation Guide 19
Chapter 1: Product Information
Platform Features Summary
Feature Feature Description
Note:
One portable USB DVD ROM drive is included per system to be used by a Dell
R720xd dump server. The product ID number for the USB DVD ROM drive kit is 2021-K944-V001. The kit includes instructions for using the drive.
BYNET-over-Ethernet
Interconnect
Redundant 24-port BYNET-over-Ethernet switches in processing/storage cabinets used for processing node (TPA), channel server, and network connectivity server
(NCS) communication. Switches support a maximum of 22 TPA nodes, hot standby nodes, channel servers, and NCSs in any combination.
BYNET V5 Interconnect Redundant BYNET V5 switches using BYNET V5 InfiniBand for processing node
(TPA), channel server, and NCS communication in processing/storage cabinets or
BYNET V5 cabinets.
• In processing/storage cabinets:
∘ 36-port InfiniBand switch chassis for systems with a maximum 36 TPA nodes, hot standby nodes, channel servers, NCSs, and TMSs in any combination
• In BYNET V5 cabinets:
∘ 108-port InfiniBand switch chassis for systems with a maximum 108 TPA nodes, hot standby nodes, channel servers, NCSs, and TMSs in any combination
Adapters
Note:
CMIC 11.01 or later is required for the 108-port switch.
Note:
The 108-port switch cabinet can have up to two optional Dell R720 or Dell
R720xd TMSs in any combination. Some configurations may also have an
Intel R1208 System VMS. If a System VMS is included, a KVM is also included.
∘ 162-port InfiniBand switch chassis for systems with a maximum 162 TPA nodes, hot standby nodes, channel servers, NCSs, and TMSs in any combination
Note:
The 162-port BYNET V5 cabinets may also have TMSs, Cabinet VMSs, or
System VMSs. If a System VMS is included, a KVM is also included.
∘ 324-port InfiniBand switch chassis for systems with a maximum 324 TPA nodes, hot standby nodes, channel servers, NCSs, and TMSs in any combination
Note:
System configurations larger than 324 nodes (to a maximum of 1,024 nodes) are accommodated by special order.
SAS disk storage adapter:
20 1700 Platform Product and Site Preparation Guide
Feature
Virtualized Management
Server (VMS)
Chapter 1: Product Information
Platform Features Summary
Feature Description
• LSI 9200-16E quad 6 Gbx4 SAS PCIe adapter in processing nodes and some
TMSs
InfiniBand adapter (for connection to the BYNET V5 network or the BYNET V5 switch):
• Mellanox MCX354A-FCBT (ConnectX-3) InfiniBand PCIe3 adapter in PE nodes, channel servers, and as an option in TMSs
Communications adapters:
• Intel I350-T4 quad 1 Gb PCIe2 copper adapter in processing nodes or TMSs
• Intel PRO/1000 PF dual PCIe adapter in processing nodes, TMSs, or NCSs
• Intel PRO/1000 PT quad PCIe adapter in processing nodes, TMSs, or NCSs
• Intel X520-DA2 dual-port 10 Gb copper adapter in processing nodes, TMSs, or
NCSs
• Intel X520-SR2 dual-port 10 Gb optical adapter in processing nodes, TMSs, or
NCSs
Host channel adapter:
• BTI FICON PEFA PCIe adapter
• Luminex FICON SP LR PCIe adapter
TMS BAR adapter:
• QLogic QLE2564 quad port 8 Gb fibre channel to PCI adapter
A virtualized management server (VMS) can reside in a 1700 processing/storage cabinet, a 108-port BYNET V5 cabinet, a 162-port BYNET V5 cabinet, or a Platform
Framework Cabinet.
A VMS is an Intel R1208 chassis and can host the following virtual machines (VMs):
• CMIC -- The CMIC provides server management services for the system cabinets.
• SWS -- The SWS is the service entry for the system.
• Viewpoint -- The Viewpoint VM manages only a single Teradata system.
An Intel R1208 VMS is available in System VMS and Cabinet VMS configurations.
Each System VMS consists of:
• CMIC, SWS, and Viewpoint VMs. A Viewpoint VM supports up to a maximum of 128 nodes and servers.
• Two 2.0 GHz six-core 15MB L3 cache E5-2620 processors
• 64 GB memory using 8 GB DIMMs
• Two 600 GB RAID 1 drives for boot/system operations
• Two 600 GB RAID 1 drives for Viewpoint data storage
• Onboard connectivity to server management network
• Onboard or adapter connectivity to customer network
• OS:
∘ Linux SLES 10 SP3 OS on SWS and Viewpoint VMs
∘ Linux SLES 11 OS on SWS VM (required for CMIC 11.01 and later)
1700 Platform Product and Site Preparation Guide 21
Chapter 1: Product Information
Platform Features Summary
Feature
Server Management Web
(SMWeb) Services
Feature Description
∘ Linux SLES 11 OS on VMS and CMIC VM
Each Small System VMS consists of:
• CMIC, SWS, and Viewpoint VMs. A Viewpoint VM supports up to a maximum of 128 nodes and servers.
• One 2.0 GHz six-core 15MB L3 cache E5-2620 processors
• 32 GB memory using 8 GB DIMMs
• Two 600 GB RAID 1 drives for boot/system operations
• Two 600 GB RAID 1 drives for Viewpoint data storage
• Onboard connectivity to server management network
• Onboard or adapter connectivity to customer network
• OS:
∘ Linux SLES 10 SP3 OS on SWS and Viewpoint VMs
∘ Linux SLES 11 OS on SWS VM (required for CMIC 11.01 and later)
∘ Linux SLES 11 OS on VMS and CMIC VM
Each Cabinet VMS consists of:
• CMIC VM
• One 2.0 GHz six-core 15MB L3 cache E5-2620 processor
• 32 GB memory using 8 GB DIMMs
• Two 600 GB RAID 1 drives for boot/system operations
• Onboard connectivity to server management network
• Onboard or adapter connectivity to customer network
• Linux SLES 11 OS on VMS and CMIC VM
Server management functions run on the CMIC VM (on a VMS). One CMIC VM is designated as the single operational view (SOV) CMIC. The SOV CMIC hosts the
SMWeb Services Home page and provides applications and services for server management on an MPP system:
• Server Management Client: Monitor status, display events, and perform commands from a single operational view of the system.
• Command Line Interface: Download remote command line interface utilities
• Save and Restore: Download, upload, and view configuration files
• Users and Groups: Manage user and group security levels
• Network, Devices, and CMICs: Configure the server management network and device management
• TVI Connection: Configure settings for TVI data communications to Teradata via the Service Workstation
For use by customer on-site staff members, Teradata Services Analysts in the Global
Support Center (GSC), and Teradata Customer Service Representatives.
Notice:
SMWeb 10.04 and Teradata ServiceConnect are required for 1700 systems.
For information about using SMWeb Services, see the Teradata Server Management
Web Services User Guide, B035-5350, or the online help on the SMWeb Services home page.
22 1700 Platform Product and Site Preparation Guide
Feature
Enterprise Service
Workstation (SWS)
Enterprise Viewpoint
Server
Keyboard, Video, Mouse
(KVM) Console
Cable Management
AC Power Subsystem
Chapter 1: Product Information
Platform Features Summary
Feature Description
Rack-mounted Dell R720 workstation dedicated to system servicing and maintenance. The SWS hardware can reside in a 1700 cabinet or a Platform
Framework Cabinet.
• Adapter connection to server management network
• SLES10 SP3 operating system
• SLES 11 operating system (required for CMIC 11.01 and later)
Note:
The level of service depends on the service agreement between Teradata and the customer.
Dell R720 server that hosts the Viewpoint portal that contains portlets for customer management of the Teradata Database. Systems that have more than 128 nodes require dedicated Enterprise Viewpoint hardware (rather than a VMS with a
Viewpoint virtual machine). The Enterprise Viewpoint hardware can reside in a
1700 cabinet or a Platform Framework Cabinet.
• Adapter connection to server management network
• SLES10 SP3 operating system
The KVM can reside in a 1700 base processing/storage cabinet, a 162-port BYNET
V5 cabinet, or a Platform Framework Cabinet. The KVM must be located in the same cabinet as and be connected to the System VMS or rack-mounted SWS workstation.
Processing/storage cabinets have cable harnesses for server management.
BYNET V5 cabinets do not have cable harnesses.
Platform Framework Cabinets have cable harnesses for power and server management.
Openings in cabinet sides near the rear of the rack accommodate inter-rack cabling.
1700 processing/storage cabinets:
• Four PDUs, two on each inside rear panel of the cabinet.
• Two or four AC feeder boxes inside the cabinet. Available AC feeder box types:
∘ AC feeder box with a plug rated at 30A for North America and 32A for
Europe and most other regions. The plug is used for both single-phase
(220V-240V line to neutral) or phase to phase (208V) connections. Each cabinet has four AC feeder boxes; each AC feeder box has one power cord for a total of four power cords per cabinet.
∘ Three-phase Delta AC feeder box with a plug rated at 60A. Each cabinet has two AC feeder boxes; each AC feeder box has one power cord for a total of two power cords per cabinet.
∘ Three-phase Wye 230V L-N AC feeder box with a plug rated at 30A for North
America or 32A for Europe. Each cabinet has two AC feeder boxes; each AC feeder box has one power cord for a total of two power cords per cabinet. For use in North America, this AC feeder box requires a specialized data center with power wired like a data center in Europe.
BYNET V5 cabinet:
1700 Platform Product and Site Preparation Guide 23
Chapter 1: Product Information
Platform Features Summary
Feature
Operating System
Teradata Database
Full Disk Encryption
Feature Description
• Two AC boxes of the same type per cabinet.
• For cabinets with the 108-port, 162-port, or 324-port switch, the AC box type is a single-cord AC box with a plug rated at 30A for North America and rated at 32A for Europe. The plug is used for both single-phase (220-240V line-to-neutral) or phase-to-phase (208V) connections. Each cabinet has two AC boxes; each AC box has one power cord for a total of two power cords per cabinet.
The PFC cabinet has two AC boxes of the same type per cabinet. For information about the PFC cabinet power subsystem, see the Teradata Platform Framework
Cabinet Model 12 Product and Site Preparation Guide, B035-5388.
• SUSE Linux Enterprise Server 11 (SLES11)
• Teradata Database Release 14.00.03 or later
Notice:
Contact your Teradata representative to confirm the exact version of the
Teradata Database and PDE packages required for this platform.
The 1700 platform supports full disk encryption for processing node disks in all system cabinets. Full disk encryption is also supported for Dell R720 servers.
24 1700 Platform Product and Site Preparation Guide
Cabinet Descriptions
Chapter 1: Product Information
Cabinet Descriptions
The Teradata Integrated Big Data Platform 1700 is made up of a combination of cabinet types, depending on the system configuration:
• Processing/storage cabinet
A 1700 processing/storage cabinet contains one clique.
∘ A cabinet with a 1+0 clique contains one database processing node and two disk arrays. The second disk array is half populated.
∘ A cabinet with a 1+1 clique contains one database processing node, one hot standby node, and two disk arrays. The second disk array is half populated.
∘ A cabinet with a 2+0 clique contains two database processing nodes and three disk arrays.
∘ A cabinet with a 2+1 clique contains two database processing nodes, one hot standby node, and three disk arrays.
∘ A cabinet with a 3+0 clique contains three database processing nodes and three disk arrays.
Other chassis in the processing/storage cabinet provide power and server management functionality. For systems scalable to 22 nodes with BYNET-over-Ethernet or to 36 nodes with BYNET V5 InfiniBand, the processing/storage cabinet contains two 24-port BYNET-over-Ethernet switches or two 36-port BYNET
V5 InfiniBand switches. Cabinets may also contain Teradata managed servers (TMSs), channel servers, extended channel solution (ECS) servers, network connectivity servers (NCSs), or SAS HPA worker nodes.
• BYNET V5 cabinet
Each BYNET V5 cabinet contains one or two InfiniBand switches, depending on the configuration. AC boxes in the cabinet provide power. Ethernet switches provide server management functionality.
1700 Platform Product and Site Preparation Guide 25
Chapter 1: Product Information
Cabinet Descriptions
∘ A 108-port switch cabinet supports scalability from one to a maximum of 108 nodes. The cabinet contains two 108-port switches for redundancy. The cabinet can also contain an optional System VMS and KVM and up to two TMS servers.
∘ A 162-port switch cabinet supports scalability from one to a maximum of 162 nodes. 162-port switch cabinets are paired for redundancy. Each cabinet can also contain an optional System VMS and KVM and up to three TMS servers.
∘ A 324-port switch cabinet supports scalability from one to a maximum of 324 nodes. 324-port switch cabinets are paired for redundancy.
Note:
System configurations larger than 324 nodes (to a maximum of 1,024 nodes) are accommodated by special order.
• Platform Framework Cabinet (PFC)
The PFC can contain any combination of channel servers, ECS servers, TMS servers, NCS servers, SAS
HPA worker nodes, and other switches. The PFC can also be used to support system configurations that require a dedicated Service Workstation server. Other chassis in the cabinet provide power and server management functionality.
This guide refers generally to the Platform Framework Cabinets that may be part of your system. For more information, see the Teradata Platform Framework Cabinet Model 12 Product and Site Preparation
Guide for the PFC cabinet delivered with your system. Teradata product and site preparation documentation can be accessed at: http://www.info.teradata.com
.
Cabinet Builds for 1700
Cabinet Build Conventions
The placement of the hardware components in a cabinet follows these general cabinet build conventions:
• Each chassis has a standard position in the cabinet, and is numbered from the bottom up.
∘ Chassis that are managed over the server management network have assigned chassis ID numbers.
The chassis ID number identifies the chassis by position/type in the management interface.
∘ Unmanaged chassis are numbered by position for cabling purposes only. The numbers do not appear in the management interface as identification of the chassis.
• All chassis except the top Ethernet switches are loaded from the front of the cabinet, and accessible from both front and rear of the cabinet. The top Ethernet switches are loaded and accessible only from the rear of the cabinet.
26 1700 Platform Product and Site Preparation Guide
1+0 Configuration Cabinet Builds
Chapter 1: Product Information
Cabinet Descriptions
1700 Platform Product and Site Preparation Guide 27
Chapter 1: Product Information
Cabinet Descriptions
1+1 Configuration Cabinet Builds
28 1700 Platform Product and Site Preparation Guide
2+0 Configuration Cabinet Builds
Chapter 1: Product Information
Cabinet Descriptions
1700 Platform Product and Site Preparation Guide 29
Chapter 1: Product Information
Cabinet Descriptions
2+1 or 3+0 Configuration Cabinet Builds
Cabinet Builds for BYNET
30
Cabinet Build Conventions
The placement of the hardware components in a cabinet follows these general cabinet build conventions:
• All chassis are loaded, in sequence, from the bottom up.
• All chassis are loaded from the front of the cabinet, and accessible from both front and rear of the cabinet.
1700 Platform Product and Site Preparation Guide
Chapter 1: Product Information
Cabinet Descriptions
• AC boxes are mounted at the bottom of the cabinet.
• Each chassis has a standard position in the cabinet, and is numbered from the bottom up.
• Chassis can be managed or unmanaged.
∘ Managed chassis are connected to the primary server management network by an Ethernet port on the chassis. Chassis with a second Ethernet port are connected to the secondary server management network. Managed chassis are actively monitored by server management and allow service personnel to manage various chassis functions through SMWeb Services.
∘ Unmanaged chassis are not connected to the primary or secondary server management networks. The chassis are not monitored by server management and service personnel cannot manage chassis functions through SMWeb Services.
• Chassis that are managed or monitored over the server management network have assigned chassis ID numbers. The chassis ID number identifies the chassis by position/type in the server management interface.
• Unmanaged chassis can be numbered by position for cabling purposes only. If numbered, the numbers do not appear in the server management interface as identification of the chassis.
1700 Platform Product and Site Preparation Guide 31
Chapter 1: Product Information
Cabinet Descriptions
BYNET 108-Port Switch Cabinet Build
32 1700 Platform Product and Site Preparation Guide
BYNET 162-Port Switch Cabinet Build
Chapter 1: Product Information
Cabinet Descriptions
1700 Platform Product and Site Preparation Guide 33
Chapter 1: Product Information
Cabinet Descriptions
BYNET 324-Port Switch Cabinet Build
324-Port BYNET Switch Cabinet
Redundant 324-port BYNET switch cabinets are used per system. One cabinet contains the network-0 switch, the other cabinet contains the network-1 switch.
The network-0 cabinet hosts one or two primary server management switches.
The network-1 cabinet hosts one or two secondary server management switches.
7 Prime/Second SM Enet Switch
6 Prime/Second SM Enet Switch opt.*
*
The second primary and secondary server management switches (chassis #6) are used with systems that require more than 47 ports for server management connections.
1
324-Port
BYNET Switch
34
#
# managed chassis unmanaged chassis no chassis installed in this space
AC Box AC Box
Cabinet_0592
Cabinet Builds for Platform Framework Cabinets
This guide refers generally to the Platform Framework Cabinets (PFCs) that may be part of your system. For more information, see the Teradata Platform Framework Cabinet Model 12 Product and Site Preparation
Guide, B035-5388 for the PFC delivered with your system. Teradata product and site preparation documentation can be accessed at: http://www.info.teradata.com
.
1700 Platform Product and Site Preparation Guide
Chapter 1: Product Information
BYNET-Over-Ethernet Network Topology
BYNET-Over-Ethernet Network Topology
Maximum 22-Node System Configuration
Figure 1: BYNET-over-Ethernet Network Topology for a Maximum 22-Node System
• Consists of one or more processing/storage cabinets, a Service Workstation (SWS) or VMS with SWS
VM, plus additional (optional) PFC cabinets.
• Scalable from one to 22 database processing nodes.
• Two BYNET switch chassis in processing/storage cabinet 1 provide redundant BYNET networks (0 and
1).
• Each processing node provides onboard Ethernet ports for connecting to the BYNET-over-Ethernet switches.
• For port-to-port cabling, see the Cabling and Chassis Ports appendix in the appropriate Hardware
Installation Guide.
BYNET V5 Network Topology
Maximum 36-Node System Configuration
Figure 2: BYNET V5 Network Topology for a Maximum 36-Node System
• Consists of one or more 1700 processing/storage cabinets, a VMS with SWS VM or a Service
Workstation (SWS), plus additional Platform Framework Cabinets.
• Scalable from 1 to 36 processing nodes (TPA nodes and hot standby nodes), channel servers, NCSs, and
TMSs in any combination.
• Two 36-port BYNET V5 InfiniBand switches provide redundant BYNET networks (Network-0 and
Network-1). Both switches reside in the base cabinet.
1700 Platform Product and Site Preparation Guide 35
Chapter 1: Product Information
BYNET V5 Network Topology
• Each processing node, channel server, or NCS contains a dual port BYNET V5 InfiniBand adapter that connects to both BYNET V5 InfiniBand switches. A TMS may contain a dual port BYNET V5 InfiniBand adapter that connects to the switches.
• Individual optical InfiniBand cables are used to connect nodes and servers in expansion cabinets to the
BYNET V5 InfiniBand switches in the base cabinet.
• For port-to-port cabling, see the appropriate Hardware Installation Guide.
Maximum 108-Node System Configuration
Figure 3: BYNET V5Network Topology for a Maximum 108-Node System
36 1700 Platform Product and Site Preparation Guide
Chapter 1: Product Information
BYNET V5 Network Topology
• Consists of one or more 1700 processing/storage cabinets, a VMS with SWS VM or a Service
Workstation (SWS), plus additional (optional ) Platform Framework Cabinets.
• Scalable from 1 to 108 total processing nodes (TPA nodes and hot standby nodes), channel servers, NCSs, and TMSs in any combination.
• One BYNET V5 cabinet provides redundant networks (Network-0 and Network-1). The cabinet contains two 108-port switches.
• Each 108-port BYNET V5 switch contains from 1 to 6 leaf boards. Each leaf board supports up to 18 processing nodes , channel servers, or NCSs. Each switch has 3 spine boards that allow the leaf boards to communicate with each other, and one chassis management board for managing the network.
• Each processing node , channel server, or NCS contains a dual port InfiniBand adapter that connects to the BYNET V5 switch in the BYNET V5 cabinet. A TMS may contain a dual port InfiniBand adapter that connects to the switches.
• Individual optical InfiniBand cables are used to connect processing nodes , channel servers, NCSs, and
TMSs in expansion cabinets, or channel servers, NCSs, and TMSs in (optional) Platform Framework
Cabinets, to the BYNET V5 switches in each BYNET V5 cabinet.
• For port-to-port cabling, see the appropriate Hardware Installation Guide.
Maximum 162-Node System Configuration
Figure 4: BYNET V5 Network Topology for a Maximum 162-Node System
• Consists of one or more 1700 processing/storage cabinets, a VMS with SWS VM or a Service
Workstation (SWS), plus additional (optional ) Platform Framework Cabinets.
1700 Platform Product and Site Preparation Guide 37
Chapter 1: Product Information
BYNET V5 Network Topology
• Scalable from 1 to 162 total processing nodes (TPA nodes and hot standby nodes), channel servers, NCSs, and TMSs in any combination.
• Two BYNET V5 cabinets provide redundant networks (Network-0 and Network-1). Each cabinet contains one 162-port switch.
• Each 162-port BYNET V5 switch contains from 2 to 9 line boards. Each line board supports up to 18 processing nodes, channel servers, NCSs, and TMSs.
• Each processing node, channel server, or NCS contains a dual port InfiniBand adapter that connects to the BYNET V5 switch in each BYNET V5 cabinet. A TMS may contain a dual port InfiniBand adapter that connects to the switches.
• Individual optical InfiniBand cables are used to connect processing nodes, channel servers, NCSs, and
TMSs in expansion cabinets, or channel servers, NCSs, and TMSs in (optional) Platform Framework
Cabinets, to the BYNET V5 switches in each BYNET V5 cabinet.
• For port-to-port cabling, see the appropriate Hardware Installation Guide.
38 1700 Platform Product and Site Preparation Guide
Maximum 324-Node System Configuration
Figure 5: BYNET V5 Network Topology for a Maximum 324-Node System
Chapter 1: Product Information
BYNET V5 Network Topology
• Consists of one or more 1700 processing/storage cabinets, a VMS with SWS VM or a Service
Workstation (SWS), plus additional (optional ) Platform Framework Cabinets.
• Scalable from 1 to 324 total processing nodes (TPA nodes and hot standby nodes), channel servers, NCSs, and TMSs in any combination.
• Two BYNET V5 cabinets provide redundant BYNET V5 networks (Network-0 and Network-1). Each cabinet contains one 324-port BYNET V5 switch.
1700 Platform Product and Site Preparation Guide 39
Chapter 1: Product Information
Server Management Network Topology
• Each 324-port BYNET V5 switch contains 1 to 18 leaf boards. Each leaf board supports up to 18 nodes , channel servers, NCSs, and TMSs. Each switch has 9 spine boards that allow the leaf boards to communicate with each other, and one chassis management board for managing the network.
• Each processing node , channel server, or NCS contains a dual port InfiniBand adapter that connects to the BYNET V5 switch in each BYNET V5 cabinet. A TMS may contain a dual port InfiniBand adapter that connects to the switches.
• Individual optical InfiniBand cables are used to connect processing nodes , channel servers, NCSs, and
TMSs in expansion cabinets, or channel servers and NCSs in (optional) Platform Framework Cabinets, to the BYNET V5 switches in each BYNET V5 cabinet.
• For port-to-port cabling, see the appropriate Hardware Installation Guide.
Server Management Network Topology
Server management subsystems enable overall system monitoring and control. The subsystems include dedicated and redundant Ethernet-based networks that interconnect all managed chassis and VMSs.
The server management network consists of two physical networks on separate paths:
• Primary network — for direct management communications of all managed chassis in all cabinets, through Server Management Web (SMWeb) Services.
• Secondary network — for backup communications of all chassis that support a second Ethernet connection, through SMWeb Services.
Server Management Network Interface
Server management software runs on each CMIC in the system. One CMIC is designated as the single operational view (SOV) CMIC. The SOV CMIC hosts the SMWeb Services home page and provides applications and services for server management in a single server management domain.
Server management can be configured for a single system or multiple systems (multi-system configuration).
Access to the SMWeb Services home page is through the customer LAN or the server management LAN.
The server management LAN is a connection between the CMICs and the chassis they monitor.
Note:
The Service Workstation (SWS) or Service Workstation VM (SWS VM) is one of the chassis a CMIC monitors. Teradata Customer Support uses the SWS for service operations.
Note:
The level of service depends on the service agreements between Teradata and the customer.
40 1700 Platform Product and Site Preparation Guide
Chapter 1: Product Information
Server Management Network Topology
Server Management Network Terminology and Topology
Collectives
Figure 6: Examples of CMIC Collectives in a System with Multiple Cabinets
• In a system, cabinets in the server management network are organized into collectives.
Note:
The system number, collective numbers, and cabinet numbers are viewable in SMWeb Services web applications.
• Depending on your system configuration, a system has one or more collectives.
• A CMIC VM provides server management services for a collective, with one or more cabinets per collective. One cabinet in a collective must contain a CMIC VM hosted by a VMS.
Note:
In single-system and multi-systemconfigurations running CMIC 11.01 or 11.02, a single CMIC VM managing multiple cabinets without CMIC VMs can manage up to 32 nodes and servers.
• The following cabinets can be configured with or without a CMIC VM hosted by a VMS: processing/ storage cabinet, BYNET V5 InfiniBand switch cabinet, or Platform Framework Cabinet (PFC).
• A collective can contain one or more of the following cabinets. At least one of the cabinets must contain a
CMIC VM hosted by a VMS.
∘ Processing/storage cabinet
∘ BYNET V5 cabinet (if used)
∘ PFC (if used)
• Each collective in the system has a unique collective ID (collective number).
• Each cabinet in the system has a unique cabinet ID (cabinet number).
• Collectives and cabinets are numbered as follows:
∘ Collectives are numbered consecutively, beginning with Collective 1.
∘ Cabinets are numbered consecutively, beginning with Cabinet 1.
• In the collectives shown:
∘ Collective 1 contains one cabinet (Cabinet 1) managed by one CMIC VM hosted by a VMS in the cabinet.
∘ Collective 2 contains two cabinets (Cabinet 2 and Cabinet 3). Both cabinets are managed by one
CMIC VM hosted by a VMS in Cabinet 2.
1700 Platform Product and Site Preparation Guide 41
Chapter 1: Product Information
Server Management Network Topology
• For port-to-port cabling, see the appropriate Hardware Installation Guide.
Single-System Configurations
In a single-system configuration, server management monitors and manages a single instance of Teradata.
The system has a unique system name. All the nodes and disk arrays in the system must share a common
Server Management Domain and a common Site ID configured in server management.
Multi-System Configurations
In a multi-system configuration:
• All systems must be running the same version of SMWeb Services (11.01 or later).
• All server management switches in individual systems are joined together in a single server management domain.
• The multi-system configuration has a single server management Site ID.
Nodes in all multi-system configurations share the BYNET V5 InfiniBand switches.
Each system in a multi-system configuration is assigned a unique system name. For example:
• One system name is assigned to each Teradata Database node and disk array in a Teradata system.
• Another system name is assigned to the nodes in an Aster cluster.
• Another system name is assigned to the nodes in a Hadoop cluster.
Shared system components (collectives and cabinets, VMSs, BYNET V5 InfiniBand switches, server management switches, and TMSs) are not assigned system names.
Note:
Contact Teradata Customer Support to verify which Teradata, Aster, and Hadoop systems are valid in multi-system configurations, such as a Unified Data Architecture (UDA) environment.
42 1700 Platform Product and Site Preparation Guide
Chapter 1: Product Information
Server Management Network Topology
In-Cabinet Server Management Network Topology
Figure 7: Primary and Secondary Server Management Networks in 1700 Processing/Storage Cabinets
• Each VMS hosts a CMIC VM. The CMIC VM runs the server management software.
• Every cabinet contains a primary and a secondary server management Ethernet switch.
• The CMIC VM hosted by the VMS interfaces with the chassis in its cabinet through the Ethernet switches.
• Each managed chassis connects to the primary Ethernet switch in its cabinet. Each chassis having a second available Ethernet port connects to the secondary Ethernet switch in its cabinet.
• For port-to-port cabling, see the appropriate Hardware Installation Guide.
1700 Platform Product and Site Preparation Guide 43
Chapter 1: Product Information
Server Management Network Topology
In-Cabinet Server Management Network Topology for 108-
Port BYNET V5 Cabinets
Figure 8: 108-Port BYNET Switch Cabinet: Primary and Secondary Server Management Networks in Cabinets
44
• Each VMS hosts a CMIC VM. The CMIC VM runs the server management software.
• Each cabinet contains a primary and a secondary server management Ethernet switch.
• The CMIC VM hosted by the VMS interfaces with the chassis in the cabinet through the Ethernet switches.
• Each managed TMS and VMS chassis connects to the primary and secondary Ethernet switches in the cabinet.
1700 Platform Product and Site Preparation Guide
Chapter 1: Product Information
Server Management Network Topology
• The network-0 InfiniBand switch connects to the primary Ethernet switch in the cabinet. The network-1
InfiniBand switch connects to the secondary Ethernet switch in the cabinet.
• For port-to-port cabling, see the appropriate Hardware Installation Guide.
In-Cabinet Server Management Network Topology for 162-
Port BYNET V5 Cabinets
Figure 9: 162-Port BYNET V5 Cabinet: Primary and Secondary Server Management Networks in Cabinets
• Each VMS hosts a CMIC VM. The CMIC VM runs the server management software.
• Every cabinet contains a primary and a secondary server management Ethernet switch.
1700 Platform Product and Site Preparation Guide 45
Chapter 1: Product Information
Server Management Network Topology
• The CMIC VM hosted by the VMS interfaces with the chassis in its cabinet through the Ethernet switches.
• Each managed TMS and VMS chassis connects to the primary and secondary Ethernet switches in its cabinet.
• The InfiniBand switch in the network-0 cabinet connects to the primary Ethernet switch in its cabinet.
The InfiniBand switch in the network-1 cabinet connects to the secondary Ethernet switch in its cabinet.
• For port-to-port cabling, see the appropriate Hardware Installation Guide.
46 1700 Platform Product and Site Preparation Guide
Chapter 1: Product Information
Server Management Network Topology
In-Cabinet Server Management Network Topology for 324-
Port BYNET V5 Cabinets
Figure 10: 324-Port BYNET V5 Cabinet: Primary and Secondary Server Management Networks in Cabinets
Primary SM Enet Switch
Primary SM Enet Switch (opt)
Secondary SM Enet Switch
Secondary SM Enet Switch (opt)
324-Port
BYNET V5 Switch
324-Port
BYNET V5 Switch
AC Box AC Box AC Box AC Box
Cabinet_0595
• Each network-0 cabinet contains one or two primary server management Ethernet switches. Each network-1 cabinet contains one or two secondary server management Ethernet switches.
• Each 324-port InfiniBand chassis connects to the primary or secondary Ethernet switch in its cabinet.
• In cabinets with two primary or secondary server management switches:
∘ The in-cabinet server management switches are connected to each other.
1700 Platform Product and Site Preparation Guide 47
Chapter 1: Product Information
Server Management Network Topology
∘ The 324-port InfiniBand chassis connects to the upper primary or upper secondary Ethernet switch in its cabinet.
• For port-to-port cabling, see the appropriate Hardware Installation Guide.
Inter-Cabinet Server Management Network Topology to 36
Nodes
Figure 11: Server Management Network for System with Maximum 36 Nodes, No BYNET Cabinets
48
• This configuration is built on the cabinet and collective topology defined in Collectives .
• This configuration illustrates topology for one to eighteen processing/storage cabinets.
• One or more of the processing/storage cabinets shown above may be in single collective, depending on system configuration. The collective may include Platform Framework Cabinets (not shown).
• The path for the primary network runs:
From the following:
The SWS or VMS
To the following primary Ethernet switches:
Cabinet 1
1700 Platform Product and Site Preparation Guide
To the following primary Ethernet switches:
Cabinets 2, 3, and 4
Cabinets 5 and 6
Cabinets 7 and 8
Cabinets 9 and 10
Cabinets 11 and 12
Cabinets 13 and 14
Cabinets 15 and 16
Cabinets 17 and 18
Chapter 1: Product Information
Server Management Network Topology
From the following:
The primary Ethernet switch in Cabinet 1
The primary Ethernet switch in Cabinet 3
The primary Ethernet switch in Cabinet 5
The primary Ethernet switch in Cabinet 6
The primary Ethernet switch in Cabinet 7
The primary Ethernet switch in Cabinet 8
The primary Ethernet switch in Cabinet 9
The primary Ethernet switch in Cabinet 10
• The path for the secondary network runs:
From the following:
The SWS or VMS
The primary Ethernet switch in Cabinet 2
The primary Ethernet switch in Cabinet 4
The primary Ethernet switch in Cabinet 5
To the following secondary Ethernet switches:
Cabinet 1
Cabinets 1, 3, and 4
Cabinets 5 and 6
Cabinets 9 and 10
The primary Ethernet switch in Cabinet 6
The primary Ethernet switch in Cabinet 7
The primary Ethernet switch in Cabinet 8
Cabinets 7 and 8
Cabinets 13 and 14
Cabinets 11 and 12
The primary Ethernet switch in Cabinet 9 Cabinets 17 and 18
The primary Ethernet switch in Cabinet 10 Cabinets 15 and 16
• Separate primary and secondary paths ensure network backup.
Note:
The SWS can be a VM on the VMS in the first processing/storage cabinet or a rackmounted SWS in a
Platform Framework Cabinet.
• For port-to-port cabling, see the appropriate Hardware Installation Guide.
1700 Platform Product and Site Preparation Guide 49
Chapter 1: Product Information
Server Management Network Topology
Inter-Cabinet Server Management Network Topology to 108
Nodes
Figure 12: Server Management Network for System with Maximum 108 Nodes, 2 BYNET Cabinets
50
• This configuration is built on the cabinet and collective topology defined in Collectives .
• The topology shown in the illustration above is based on a 1700 system with 36 cabinets in a 2+1 node configuration with one clique per cabinet. The topology may differ depending on the number of cabinets in the system. The number of cabinets is based on one 2+1 or 3+0 clique per cabinet for a total of three nodes per cabinet in 36 cabinets.
• One or more of the processing/storage cabinets shown above may be in a single collective, depending on system configuration. The collective may include Platform Framework Cabinets (not shown).
• The BYNET V5 cabinet contains one primary server management Ethernet switch and one secondary server management Ethernet switch.
Note:
Although a cabinet number is not shown for the BYNET V5 cabinet, the cabinet number must be unique in the system.
• Separate primary and secondary paths ensure network redundancy.
• The primary and secondary networks are configured as follows:
∘ The primary Ethernet switch in the BYNET V5 cabinet acts as the gathering switch for the primary switches in cabinets 1-36.
∘ The secondary Ethernet switch in the BYNET V5 cabinet acts as the gathering switch for the secondary switches in cabinets 1-36.
• For port-to-port cabling, see the appropriate Hardware Installation Guide.
1700 Platform Product and Site Preparation Guide
Chapter 1: Product Information
Server Management Network Topology
Inter-Cabinet Server Management Network Topology to 162
Nodes
Figure 13: Server Management Network for System with Maximum 162 Nodes, 2 BYNET V5 Cabinets
• This configuration is built on the cabinet and collective topology defined in Collectives .
• The topology shown in the illustration above is based on a 1700 system with 54 cabinets in a 2+1 or 3+0 configuration with one clique per cabinet. The topology may differ depending on the number of cabinets in the system. The number of cabinets is based on one 2+1 or 3+0 clique per cabinet for a total of three nodes per cabinet in 54 cabinets.
• Each cabinet shown above represents a collective. The collective may include Platform Framework
Cabinets (not shown).
• This configuration has a pair of BYNET V5 cabinets for redundancy (Network-0 Cabinet and Network-1
Cabinet). Each BYNET V5 cabinet contains one primary server management Ethernet switch and one secondary server management Ethernet switch.
• Separate paths for the primary and secondary server management networks ensure network backup. The primary and secondary networks are configured as follows:
∘ The primary Ethernet switch in the BYNET V5 Network-0 Cabinet acts as the gathering switch for the primary switches in all odd-numbered cabinets in the system. The primary switches in those oddnumbered cabinets act as gathering switches for the primary switches in the even-numbered cabinets.
∘ The secondary Ethernet switch in BYNET V5 Network-1 Cabinet acts as the gathering switch for the secondary switches in all even-numbered cabinets in the system. The secondary switches in those even-numbered cabinets act as gathering switches for the secondary switches in the odd-numbered cabinets.
∘ Each BYNET V5 cabinet connects to the gathering switch in the other BYNET V5 cabinet (Network-0
Cabinet primary to Network-1 Cabinet primary, Network-1 Cabinet secondary to Network-0 Cabinet secondary).
1700 Platform Product and Site Preparation Guide 51
Chapter 1: Product Information
Server Management Network Topology
• For port-to-port cabling, see the appropriate Hardware Installation Guide.
Inter-Cabinet Server Management Network Topology to 324
Nodes
Figure 14: Server Management Network for System with Maximum 324 Nodes, 2 BYNET Cabinets
52
• This configuration is built on the cabinet and collective topology defined in Collectives .
• The topology shown in the illustration above is based on a 1700 system with 108 cabinets in a 2+1 or 3+0 configuration with one clique per cabinet. The topology may differ depending on the number of cabinets in the system. The number of cabinets is determined by the clique configuration (1+0, 1+1, 2+0, 2+1, or
3+0) of the cabinets in the system.
• Each cabinet shown above represents a collective. The collective may include Platform Framework
Cabinets (not shown).
• Separate paths for the primary and secondary server management networks ensure network redundancy.
• The primary network is configured as follows:
∘ The upper primary Ethernet switch in the BYNET V5 Network-0 cabinet acts as the gathering switch for the primary switches in odd-numbered cabinets 1-89. The primary switches in those oddnumbered cabinets act as gathering switches for the primary switches in even-numbered cabinets
2-90.
∘ The lower primary Ethernet switch in the PFC acts as the gathering switch for the primary switches in odd-numbered cabinets 91-107. The primary switches in those odd-numbered cabinets act as gathering switches for the primary switches in even-numbered cabinets 92-108.
• The secondary network is configured as follows:
∘ The upper secondary Ethernet switch in the BYNET V5 Network-0 cabinet acts as the gathering switch for the secondary switches in even-numbered cabinets 2-90. The secondary switches in those
1700 Platform Product and Site Preparation Guide
Chapter 1: Product Information
Disk Storage Interconnect even-numbered cabinets act as gathering switches for the secondary switches in odd-numbered cabinets 1-89.
∘ The lower secondary Ethernet switch in the BYNET V5 Network-0 cabinet acts as the gathering switch for the secondary switches in even-numbered cabinets 92-108. The secondary switches in those even-numbered cabinets act as gathering switches for the secondary switches in odd-numbered cabinets 91-107.
• For port-to-port cabling, see the appropriate Hardware Installation Guide.
Disk Storage Interconnect
Nodes and disk arrays are interconnected into a clique configuration for fault tolerance. If a node in a clique fails, its tasks are automatically moved over to the other nodes in the clique. The other nodes in the clique have direct access to all disk arrays in the clique. The system continues running minus the failed node.
Each Teradata database processing (TPA) node has redundant connections to the disk array in its clique. All links are point to point.
1700 Platform Product and Site Preparation Guide 53
Chapter 1: Product Information
Disk Storage Interconnect
Figure 15: Node to Disk Array Interconnect: 1+0 and 1+1 Clique Configurations
54 1700 Platform Product and Site Preparation Guide
Figure 16: Node to Disk Array Interconnect: 2+0 and 2+1 or 3+0 Clique Configurations
Chapter 1: Product Information
Disk Storage Interconnect
1700 Platform Product and Site Preparation Guide 55
Chapter 1: Product Information
Product Statements
Product Statements
Regulatory Compliance
The Teradata cabinets comply with the following regulatory standards:
Country/Region
USA
European Union
Japan
Australia/New Zealand
Emissions/Immunity Certification
FCC CFR 47 - Part 15 - (CISPR 22)
EN 55022
EN 55024
EN 61000-3-2
EN 61000-3-3
EN 61000-3-11
EN 61000-3-12
EMC Directive 2014/30/EU
VCCI V-3
AS/NZS CISPR 22
Product Safety
cTUVus approval to UL 60950-1/CAN/CSA No. 60950-1-07
CB Report to IEC 60950-1 with all national deviations
European Union Low Voltage Directive LVD 2014/35/EU
RoHS
The system complies with Directive 2011/65/EU.
India RoHS
Teradata Operations, Inc., declares that this product has been designed and manufactured in compliance with E-Waste (Management and Handling) Rules, 2011.
56 1700 Platform Product and Site Preparation Guide
Chapter 1: Product Information
Product Statements
Declaration of Conformity 9177
The Teradata platform system complies with the following standards for Electromagnetic Interference (EMI) and Susceptibility:
Declaration of Conformity 9107
The Teradata platform system complies with the following standards for Electromagnetic Interference (EMI) and Susceptibility:
1700 Platform Product and Site Preparation Guide 57
Chapter 1: Product Information
Product Statements
58 1700 Platform Product and Site Preparation Guide
RCM Supplier's Declaration of Conformity 9177
Chapter 1: Product Information
Product Statements
1700 Platform Product and Site Preparation Guide 59
Chapter 1: Product Information
Product Statements
RCM Supplier's Declaration of Conformity 9107
60 1700 Platform Product and Site Preparation Guide
Chapter 1: Product Information
Product Statements
China Declaration Certificate
The following product documentation is required by the People’s Republic of China, in accordance with that country’s Reduction of Hazardous Waste (RoHS) regulations:
1700 Platform Product and Site Preparation Guide 61
Chapter 1: Product Information
Product Statements
China Declaration Certificate (continued)
62
Electromagnetic Compatibility Notices
The following table lists electromagnetic compatibility notices for this product:
USA This equipment has been tested and found to comply with the limits for a Class A digital device, pursuant to Part 15 of the FCC rules. These limits are designed to provide reasonable protection against harmful interference when the equipment is operated in a commercial environment. This equipment generates, uses, and can radiate radio frequency energy, and, if not installed and used in accordance with the instruction manual, may cause harmful interference to radio communications. Operation of this equipment in a residential area is likely to cause harmful interference in which case the user will be required to correct the interference at his own expense.
Notice:
Changes or modifications not expressly approved by Teradata Corporation could void the user’s authority to operate this equipment.
1700 Platform Product and Site Preparation Guide
Chapter 1: Product Information
Product Statements
Japan
Canada
European Union
Translation:This is a Class A product. If this equipment is used in a domestic environment, radio interference may occur, in which case, the user may be required to take corrective actions.
Cet appareil numérique de la classe A est conforme à la norme NMB-003 du
Canada.
Translation:This Class A digital apparatus complies with Canadian ICES-003.
In accordance with meeting the requirements of EMC 2014/30/EU, the rack mount system meets the EMC emissions and immunity standards of CENELEC
(Committee for European Electrotechnical Standardization, or Comité Européen de Normalisation Electrotechnique) EN55022, EN55024, EN61000-6-2,
EN61000-6-3, and IEC (International Electrotechnical Committee) 61000-4-2, 3,
4, 5, 6, 8, 11 and IEC 61000-3-11, -12.
Notice:
This is a Class A product. In a domestic environment this product may cause radio interference in which case the user may be required to take adequate measures.
This equipment complies with IEC 61000-3-12 provided the short-circuit power
S
SC
is greater than or equal to 2650 KVA at the interface point between the user’s supply and the public system. It is the responsibility of the installer or user of the equipment to ensure, by consultation with the distribution network operator if necessary, that the equipment is connected only to a supply with a short circuit power S
SC
greater or equal to 2650 KVA.
Taiwan
Notice:
This is a Class A product. In a domestic environment this product may cause radio interference in which case the user may be required to take adequate measures.
1700 Platform Product and Site Preparation Guide 63
Chapter 1: Product Information
Product Statements
Regulatory Compliance Disclaimer
The statements of regulatory compliance contained in this document do not apply after the addition or substitution of other equipment or connecting cables by or for the user, or to other modifications to the equipment by or for the user, other than as specified by Teradata. The user is solely responsible for, and assumes all risk and liability related to, such additions, substitutions or other modifications. Without limiting the foregoing, the user is responsible for regulatory compliance and correction of interference related to such additions, substitutions or other modifications.
Notice:
Connection from the product to an outside network (customer LAN, public LAN, etc.) must be done with a shielded cable (unless optical Ethernet is used). Failure to use a shielded cable may invalidate the regulatory compliance of the product.
Product Safety Disclaimer
The safety approvals obtained by or for Teradata with respect to the equipment do not apply after the addition or substitution of other equipment or connecting cables by or for the user, or to other modifications to the equipment by or for the user, other than as specified by Teradata. The user is solely responsible for, and assumes all risk and liability related to, such additions, substitutions or other modifications. Without limiting the foregoing, the user is responsible for compliance with any applicable legal and standards requirements (for example safety standards and electric code) related to such additions, substitutions or other modifications. Without limiting the foregoing, the user is responsible for personal injury, including death, and property damage related to such additions, substitutions or other modifications.
Cautions and Warnings
The chassis in the Teradata platform system contain no user-serviceable components. Only a technically qualified customer service representative should service the system. The following cautions and warnings apply:
Proper Cooling and Airflow
Grounding
This equipment has high leakage current. Reliable earth grounding of this equipment must be maintained.
Grounding is provided by the power plug. The ground wire in each power cord is connected to a ground terminal in the power plug. The customer must ensure that the receptacle is properly grounded.
Rack Stabilization
Side stabilizers on the bottom of a stand-alone cabinet must remain in place as installed.
Two or more cabinets must be bolted together to prevent tipping when a chassis is extended.
No more than one chassis should be extended at one time. Extension of more than one loaded module could cause the rack to tip or fall.
A top-heavy rack could tip or fall. Proper weight distribution must be maintained.
64 1700 Platform Product and Site Preparation Guide
Chapter 1: Product Information
Product Statements
Power On/Off
The power on/off switches on rack chassis do not completely remove AC power. After shutting down and turning off a subsystem, the AC power cords must be unplugged from the chassis.
Hazardous Electrical Conditions
Hazardous electrical conditions may be present on power, telephone, and communication cables. Power must be properly removed to access equipment. Contact Teradata Customer Support for assistance.
Electromagnetic Fields and Electrical Noise
Isolate the server from strong electromagnetic fields and electrical noise produced by electrical devices (such as elevators, copy machines, air conditioners, large fans, large electric motors, radio and TV transmitters, and high frequency security devices).
Input Supply
Check nameplate ratings to assure there is no overloading of supply circuits that could have an effect on overcurrent protection and supply wiring.
Cabinet Power
The PDUs, AC feeder boxes, or AC boxes in a cabinet are not intended to provide power to equipment that is not mounted in the cabinet. Plugging equipment not authorized for the cabinet into the PDU, AC feeder box, or AC box may result in an overvoltage condition or damage the external equipment.
The cabinet contains more than one AC power cord. To remove all power from the cabinet, all AC power cords must be disconnected from the site power source. Install the power outlets so they are near the equipment and easily accessible.
AC Input Rating Labels
AC input rating labels indicate the supply voltage and maximum number of Amps for the following cabinet components.
• Cabinets with AC feeder boxes. There are two or four AC feeder boxes per cabinet. AC feeder boxes are mounted inside the rack on the right and left sidewalls. Each AC feeder box has one label.
• Cabinets with AC boxes (blue and orange). There are two AC boxes mounted in U spaces at the bottom of the cabinet. Each AC box has one label.
The AC input rating label is located next to the AC power cord that connects to site power. (The site power cord is the power cord that leaves the cabinet through the top or bottom openings in the cabinet.)
Product Labels
Caution:
Do not use equipment mounted on slides or rails as a shelf or work space.
1700 Platform Product and Site Preparation Guide 65
Chapter 1: Product Information
Product Statements
Caution:
Only push cabinet from front. Only roll over solid floor tiles.
66 1700 Platform Product and Site Preparation Guide
CHAPTER 2
Site Preparation Summary
Site Preparation Task List
The Teradata representative uses the following checklist as a guideline to discuss and complete the required tasks for site preparation.
Table 1: Site Preparation Task List
Done Task
Initiate customer site prep discussion/meeting
Remote connectivity discussion
Comments and Reference
At a minimum, Teradata ServiceConnect is required for remote support and maintenance. For customers with additional security and/or privacy requirements, Teradata ServiceConnect Enhanced is available.
Notice:
Customers without Teradata ServiceConnect or Teradata
ServiceConnect Enhanced will not have access to Critical System
Management and Business Critical services and will receive limited reactive maintenance and support service.
Engage the customer on issues of remote connectivity, including:
• Confirmation of Teradata ServiceConnect or Teradata
ServiceConnect Enhanced remote connectivity acceptance.
Notice:
Server Management Web Services (SMWeb) requires Teradata
ServiceConnect or Teradata ServiceConnect Enhanced.
• If Teradata ServiceConnect or Teradata ServiceConnect Enhanced is not being implemented:
1. Confirm that the customer has signed the ServiceConnect
Decline letter and Maintenance & Support Contract Non-
Compliance Acknowledgement documents.
2. Confirm that no remote connectivity, or that non-standard remote connectivity has been approved by:
∘ CS Region Vice President
∘ Region Operations Director or Area Director
∘ GSO Vice President
∘ GTS Director
1700 Platform Product and Site Preparation Guide 67
Chapter 2: Site Preparation Summary
Site Preparation Task List
Done Task
68
Power capacity
Power receptacles
Site ID created or verified
Final system configuration
Plan for expansion
Servicing clearances
Floor loading
Comments and Reference
Important:
All four levels of approval are required.
For more information about non-standard support policies, see:
Non Standard support process and policy .
• Confirmation that there is outbound network access for FTP
• Verification of security settings
For information on remote connectivity requirements, go to: Remote
Connectivity Guidelines .
Notice:
Connection from the product to an outside network (customer LAN, public LAN, etc.) must be done with a shielded cable (unless optical
Ethernet is used). Failure to use a shielded cable may invalidate the regulatory compliance of the product.
What is the total calculated power in watts or kilowatts for the whole system?
What is the total power capacity at the site?
Is there a power plan with regard to adequate power capacity and power redundancy?
Has the power capacity issue been discussed with the customer?
For power requirement calculation, refer to Power Consumption .
Does the customer have the appropriate type and number of receptacles for all of the system cabinets?
Refer to Input Power Plugs and Receptacles .
For information on Site IDs, go to: Site ID Creation Guidelines .
For new or expansion systems, need to provide for adequate space, power, AC, and security.
For a replacement system, determine if new system can swap in to the existing system's place. If not, is an upgrade required, or is there a need to provide additional space, power, AC, and security.
Is expansion anticipated in the near future? If yes, refer to Physical
Specifications for Site Planning
for the anticipated system size.
Notice:
Future systems generally require more space (ft
2 current one.
/cabinet) than the
What are the front and rear clearances?
Refer to Cabinet Footprint and Clearances: 42-U Cabinet
.
What is the floor tile capacity?
What is the weight limit?
Is the floor loading adequate for the system?
1700 Platform Product and Site Preparation Guide
Done Task
Unloading, uncrating, and entry route considerations
Tile cutouts for cables
Chapter 2: Site Preparation Summary
Site Preparation Task List
Comments and Reference
Refer to Weight and Floor Loading .
Is dock/delivery access adequate?
Is a liftgate truck or raised dock required to unload the system?
Is there an area large enough to uncrate the systems near the delivery dock?
Is there open access to the system floor (doors/ramps/elevators/ appropriate floor covering)?
Is the access path to the system floor unobstructed, large enough, and strong enough (floor loading) to accommodate system cabinets?
Notice:
No ramp steeper than 10°.
Will a pallet jack be available to move the crates?
Are there arrangements for crate disposal or return?
Notice:
Usually, the carrier will take the crates and packing.
Refer to Delivery and Installation
.
Does the customer have adequate tiles with appropriate cutouts?
Are tile cutouts large enough to accommodate cables?
Are cutout edges protected to prevent cable damage?
Notice:
Cutout size must be minimal, and brush sealed tile cutouts are strongly recommended to prevent cold air from coming through.
Refer to Site Environmental Planning for measurements.
Cooling requirements in
BTU/hr
Floor plan: Environmental
Floor plan: Power
Floor plan: PFC cabinet
1700 Platform Product and Site Preparation Guide
Refer to Site Environmental Planning .
Does the customer have multiple power feeds? The system requires multiple power feeds for redundancy.
Does the customer have site UPS units or street power?
Does the floor plan show electrical outlets?
Processing/storage cabinet: Will AC feeder boxes be connected to different power sources?
BYNET cabinet: Will the orange and blue AC boxes be connected to different power sources?
PFC cabinet: Will the orange and blue AC boxes be connected to different power sources?
Will the power sources be connected to different PDU panels?
Does the floor plan show how dual power is connected to each cabinet?
Refer to Site Wiring Options for Dual AC .
Does the floor plan allocate space for the Platform Framework Cabinet ?
69
Chapter 2: Site Preparation Summary
Site Preparation Task List
Done Task
Floor plan: Cabling
Comments and Reference
Does the floor plan show cabling scheme and cable routing?
Refer to Cables and the Cabling appendix in the Hardware Installation
Guide for your system.
Notice:
Cable lengths need to be calculated before actual cabling.
Cabling considerations
Host Channel Adapter (HCA) connectivity
LAN connectivity
BAR (backup and restore)
What is the customer’s cabling scheme?
Does the customer use cable trays? If yes, can we use the same trays?
Teradata does not provide cable trays.
Do we know where we are laying cables?
Do we need to avoid certain areas or other cables?
Is the sub-floor area clean and free from obstructions? Inspect under raised floor; if necessary, have customer clean before installation.
Are we providing adequate cable lengths?
Refer to Cables and the Cabling appendix in the Hardware Installation
Guide for your system.
Does the customer require a mainframe connection?
If so, are the nodes and/or cabinets that are designated for FICON connections identified in the floor planning?
The customer must be told where to connect to the Teradata system, cable lengths, and how many connections. The customer is required to purchase cables. Refer to
Determine/provide host channel connection information (CUAs), if applicable. The customer will need to make sure they plan to define the
IOGEN and MVS devices.
• For new systems, unique IP ranges must be allocated for server management and BYNET IP address ranges:
∘ Use the IP Address Configuration tool in Server Management
11.01 and later to verify that the addresses assigned within the allocated ranges in the system are unique.
∘ Also verify that the addresses assigned within the allocated ranges in the system are not allocated elsewhere on the customer network.
• Is a broadband connection in and out of the building available for
Teradata’s use? Determine/provide customer LAN IP addresses, subnet mask, and aliases to be used at installation. Include router information. This information is also needed for the private LAN for the BAR solution, if applicable.
Does this installation include a new Teradata BAR solution? If so,
• Will this system be connected to an existing Teradata BAR solution?
• Will an existing Teradata BAR solution be upgraded?
• What is the connection type: Fibre Channel or parallel SCSI?
• How many connections are needed?
70 1700 Platform Product and Site Preparation Guide
Done Task
Spare parts location/space
Customer replacement of disk array storage drives, disk array power supplies, and node power supplies
Chapter 2: Site Preparation Summary
Site Preparation Task List
Comments and Reference
On-site spare parts are optional. Consult with the TSC (Teradata Sales
Consultant).
Are additional site spares ordered?
Teradata provides the spare parts storage cabinet. Does the customer have any issue with Teradata providing this cabinet?
Will the customer replace failed storage drives, disk array power supplies, or node power supplies? If yes, the CS installation team must train the customer on how to replace the failed components. Use the appropriate Customer Guide for Hardware Replacement as a reference.
Items that must be covered:
• Identification of system components (for example, cabinets, chassis, drive trays, disk drives, LEDs)
• Overview of SMWeb, up to the component replacement procedure starting point
• Practice run of the end-to-end replacement procedure
• Reinforcement of the cautions and warnings for replacing failed components (detailed in the Customer Guide for Hardware
Replacement document.
1700 Platform Product and Site Preparation Guide 71
Chapter 2: Site Preparation Summary
Site Preparation Task List
72 1700 Platform Product and Site Preparation Guide
CHAPTER 3
Hardware Installation Planning
Policy on Moving and Relocating Cabinets
In order to protect Teradata personnel from injury and to prevent damage to customer equipment, Teradata service representatives are NOT authorized to move or relocate any cabinets.
If required, cabinets must be moved by professional movers with appropriate handling and safety equipment only.
It is the responsibility of the customer to arrange and contract with the moving company.
Per this policy, "Move or Relocate" shall include, but not be exclusive, activities such as:
• Loading or unloading cabinets from delivery trucks.
• Crating or uncrating cabinets.
• Moving cabinets to or from datacenters and loading docks.
• Moving cabinets to or from staging areas.
• Moving cabinets via hallways, ramps, lifts, tunnels, stairs or elevators.
• Moving cabinets between datacenter floors.
• Repositioning cabinets on the datacenter floor.
Nothing in this policy shall absolve a Teradata CSR from any other installation or de-installation activity including appropriate direction and guidance to moving personnel.
It shall be permissible for a Teradata CSR to make slight movements to a cabinet as required for leveling, alignment and bolting purposes, provided such work can be carried out in a safe manner. It will be at the sole discretion of the CSR to request any necessary assistance from the customer if deemed required.
This CS policy is valid globally.
Preinstallation Checklist
Table 2: Preinstallation Checklist
Step
1
2
Instruction
Site preparation task list completed
Site ID created
References
Review the Site Preparation Task List in the appropriate
Product and Site Preparation Guide. Be sure all items in that checklist have been completed and the site is ready for installation.
For information on site ID creation, go to: Site ID
Creation Guidelines
1700 Platform Product and Site Preparation Guide 73
Chapter 3: Hardware Installation Planning
Preinstallation Checklist
Step
3
4
5
6
7
8
9
10
Instruction
Staging checklist completed and returned to Flextronics
References
Make sure that the customer, Customer Services, and the sales team all understand and are in agreement with the system configuration.
Teradata configuration confirmed Make sure that the customer, Customer Services, and the sales team all understand and are in agreement with the system configuration.
Change Control plan confirmed Make sure that a Teradata Change Control has been opened and that it has all necessary approvals. Also verify with the customer if they require an internal Change
Control prior to installation.
Customer power and CRAC adequate
Make sure that the system power and CRAC requirements are met and ready for installation at the customer site.
Refer to the appendixes in this guide.
Customer floor plan validated
Environmental requirements met Make sure that the customer site meets all environmental requirements.
Refer to the appendixes in this guide.
Spare parts ordered
Make sure that the customer's floor plan for the system is still valid and ready for installation at the customer site.
Refer to the appendixes in this guide.
Remote connectivity availability verified
When applicable, make sure appropriate spare parts are ordered and stored properly.
Make sure ServiceConnect (SMWeb 10 or later) access is established.
74 1700 Platform Product and Site Preparation Guide
CHAPTER 4
Uncrating and Installation
Uncrating the Equipment
Important Information
Read the Open Me First document.
Customers, together with their designated movers, are responsible for physically uncrating and moving the cabinets. The Teradata representatives and the customer must be aware of the following information, and the information must be provided to the movers.
Note:
Cabinets are very tall and do not fit into an elevator on a shipping pallet.
WARNING:
The size and weight of the cabinet require that professional movers and riggers deliver the crated units.
To prepare to transport, move, and install a cabinet that is not fully loaded, the account team can estimate the weight using the tools provided in Service Bulletin 502 (SB502).
WARNING:
The cabinet is shipped in a crate with a built-in skid under it. This skid has a clearance of 9.5 cm (3.75 in.) for a forklift or pallet jack to move the unit. The increased height of the shipping container may preclude moving the unit without uncrating it.
WARNING:
The cabinet is top heavy. Do not push it from the side. Push it from front to back. Never move the cabinet with only one person.
Notice:
To prevent or minimize condensation on the system's internal and external surfaces, avoid exposure to extreme temperature or humidity changes when moving it from the uncrating area to its destination.
Tools Needed
• Pallet jack (to move crated units)
• Adjustable wrench
• Knife or scissors
• Large pliers or tongue and groove pliers
• Metal shears (to cut banding)
• 9/16-inch (14 mm*) wrench
• Hammer or large flat-blade screwdriver (to pry off clips)
1700 Platform Product and Site Preparation Guide 75
Chapter 4: Uncrating and Installation
Uncrating the Equipment
• Lift gate or raised dock (to move crated units from truck)
• Socket wrench with 1/2-inch (13 mm*) and 7/16-inch (11 mm*) sockets
• #3 Phillips screwdriver (to attach hex spacers)
• 1/2-inch (13 mm*) wrench (to remove shipping brackets)
• Hook-and-loop strips or cable ties of appropriate length
* Use of SAE tools is recommended. Metric tool equivalent is only approximation.
Uncrating a Cabinet
The following instructions are intended for the customer or designated parties (such as professional movers).
1. Review the Open Me First document.
2. Before you begin unpacking the cabinet:
• Make sure adequate help is available to unpack the crated cabinets.
• Verify that the floor loading at the installation destination is within specifications for the total
number of cabinet systems and other cabinets to be installed. See Data Center Considerations
for additional information.
• Check that the floor can support the concentrated floor loading. Be especially careful with vented floor tiles in sites with raised floors.
WARNING:
Vented floor tiles cannot support as much weight as solid tiles. When moving cabinets, replace vented floor tiles with solid floor tiles along the path where cabinets will be rolled. Failure to do so may cause damage or collapse of vented floor tiles, resulting in physical damage and/or bodily injury.
Caution:
Make sure the equipment is in position before allowing the forklift or pallet jack to leave. A fully
configured cabinet is very heavy. See Weight and Floor Loading for cabinet weights.
3. Locate the panel labeled RAMP.
This is the front of the container.
4. Orient the container so the panel labeled RAMP has at least 3.7 m (12 ft) of clearance area.
The width required in front of the container is 1.8 m (6 ft).
76 1700 Platform Product and Site Preparation Guide
Figure 17: Uncrating the Cabinet and Installing the Ramp
Chapter 4: Uncrating and Installation
Uncrating the Equipment
5. Cut the banding on the outside of the container.
6. Push up and remove the top of the container at the RAMP end.
This allows clearance for the ramp to be lowered.
Caution:
The ramp panel is heavy.
7. Remove the four metal clamps holding the front panel (RAMP) and carefully lower the ramp panel to the floor.
8. Remove the three clips holding the side panel to the rear panel and remove the side panel.
9. Remove the final three clips and remove the other side panel and the rear panel.
10. Locate and remove any boxes attached to the pallet or unit.
11. Remove the protective foam collars from the top and middle.
12. Remove the plastic bag and locate the door key.
13. Gain access to the shipping brackets.
14. Locate the shipping brackets at the front and rear of the cabinet and unbolt them from the pallet and cabinet.
Note:
If the customer intends to use seismic bracing, save the shipping brackets, bolts, and washers for later use.
15. Attach the ramp to the front of the pallet using the rectangular metal brackets.
Secure the ramp using four of the 3/8-inch x 1 1/4-inch long bolts, and four 1-inch flat washers (that held the shipping bracket to the pallet). There are 3/8-inch Tee nuts in both the pallet and the ramp.
Make sure the ramp is securely fastened to the pallet.
Caution:
A fully configured cabinet is very heavy. See
for weight information.
1700 Platform Product and Site Preparation Guide 77
Chapter 4: Uncrating and Installation
Uncrating the Equipment
WARNING:
Be sure the plastic bag is removed before rolling the cabinet down the ramp. The plastic bag presents a slippery hand hold and may prevent you from holding the cabinet securely.
Figure 18: Unpacking Diagram
78
16. The cabinet is now free to be rolled off the pallet; do so now.
WARNING:
The cabinet is top heavy. Do not push it from the side. Push it from front to rear. Never move the cabinet with only one person.
Figure 19: Unpacking Diagram
1700 Platform Product and Site Preparation Guide
Chapter 4: Uncrating and Installation
Uncrating the Equipment
17. With one person at the front and one at the rear of the unit, slowly roll it down the ramp and on to the floor.
WARNING:
Vented floor tiles cannot support as much weight as solid tiles. When moving cabinets, replace vented floor tiles with solid floor tiles along the path where cabinets will be rolled. Failure to do so may cause damage or collapse of vented floor tiles, resulting in physical damage and/or bodily injury.
Figure 20: Moving the Cabinet to the On-Site Destination
18. Move the cabinet to the installation location and let it acclimate to the new environment.
See Performing Environmental Stabilization for more information.
19. Repeat the unpacking procedure for any remaining crated cabinets that make up the system.
Performing Environmental Stabilization
The customer, with the advice of the Teradata representative, is responsible for performing the environmental stabilization.
If temperature and humidity changes have been extreme during transit, cabinets and components may develop condensation. Before installing or powering on the system:
• Cabinets and components must be free of condensation.
1. After moving the cabinets to the installation location, use the guidelines in the following table to determine the appropriate stabilization time.
1700 Platform Product and Site Preparation Guide 79
Chapter 4: Uncrating and Installation
Uncrating the Equipment
Condition
• No extreme temperature and humidity changes during transit and between the customer’s receiving area and on-site destination
• Desiccant is present
• No condensation is present on the cabinets or components
Stabilization Period
None
• Extreme temperature and humidity changes during transit and between the customer’s receiving area and on-site destination
• Desiccant is present
• Condensation is present on the cabinets or components
4 hours
• Extreme temperature and humidity changes during transit and between the customer’s receiving area and on-site destination
• Plastic bag is missing
• Desiccant is missing
• Condensation is present on the cabinets or components
8 hours
2. After the stabilization period, remove and discard the plastic bags and desiccant.
Note:
Check the inside and top of each cabinet for desiccant.
3. Before installation, inspect the surfaces of the cabinets and components for condensation: a) If signs of condensation remain, allow an additional stabilization period of two hours.
b) Repeat the two-hour period until there are no signs of condensation.
4. During installation: a) Continue to inspect the cabinets and components for signs of condensation.
b) If condensation is present, allow additional stabilization periods of two hours until there are no signs of condensation.
Inspecting the Cabinet for Damage
Both the Teradata representative and the customer should inspect the cabinet for damage.
1. Remove any coverings and plastic bags to check the cabinet for damage.
2. Check the cabinets and panels to ensure there are no scrapes, dents, or scratches.
3. Check the switches and indicators to ensure the plastic covers and markings are clear and switch movements are operating properly.
Disposing of the Shipping Materials
1. The customer must dispose of the shipping materials in accordance with applicable procedures or local regulations.
No hazardous materials are used in the shipping materials.
2. [Optional] The customer should save one or two undamaged containers and the shipping materials for possible future use.
80 1700 Platform Product and Site Preparation Guide
Chapter 4: Uncrating and Installation
Positioning and Assembling Staged Cabinets
Repacking for Shipment
The customer is responsible for repacking the equipment when repacking is necessary.
1. Refer to the figures in Uncrating a Cabinet , if needed, during this procedure.
2. Orient the container so the front side (the side where the panel labeled RAMP will be attached) is facing the cabinet.
This requires at least 3.7 m (12 ft) of clearance area in front of the container. The width required in front is 1.8 m (6 ft).
3. Attach the ramp to the front of the pallet using the rectangular metal brackets.
Secure the ramp using four of the 3/8-inch x 1 1/4-inch long bolts, and four 1-inch flat washers (that held the shipping bracket to the pallet). There are 3/8-inch Tee nuts in both the pallet and the ramp.
Make sure the ramp is securely fastened to the pallet.
4. Make sure adequate help is available to support the unit at the front and the rear.
Caution:
A fully configured cabinet is very heavy.
5. Position the cabinet so that its front goes up the ramp first.
6. Position one person at the front of the cabinet to help guide the unit while two other people at the rear slowly roll it up the ramp and onto the container.
7. Bolt the shipping brackets on the front and rear of the cabinet and pallet.
8. Replace the plastic bag, and protective foam collars from top and middle.
9. Attach the side and rear panels of the shipping container with spring clips.
10. Attach the other side panel with spring clips.
11. Unbolt the ramp and carefully raise it to vertical and secure with spring clips.
12. Install the top of the container, to secure the ramp in the vertical position.
13. Install new banding on the outside of the container.
Positioning and Assembling Staged Cabinets
Removing Shipping Screws from the 162-Port InfiniBand
Switch in a BYNET V5 Cabinet
An InfiniBand switch is shipped with three shipping screws on each side securing it to the switch rails to prevent slideout during transport. The shipping screws must be removed before the cabinet can be positioned and ganged.
1700 Platform Product and Site Preparation Guide 81
Chapter 4: Uncrating and Installation
Positioning and Assembling Staged Cabinets
Figure 21: Removing the InfiniBand Switch Shipping Screws
82
1. At the side of the cabinet, remove the three shipping screws securing the switch to the switch rail.
2. Repeat the removal of the shipping screws on the other side of the cabinet.
Positioning a Cabinet
The Teradata representative is responsible for advising the movers on the final location for each cabinet. The
Teradata representative may assist in making minor adjustments to the cabinet placement if he or she determines it is safe to do so.
1. Advise the movers to place the cabinet in position using the worksheets prepared during the site survey and staging.
Refer to the Open Me First document.
2. Adjust the leveling feet to remove the weight from the casters.
3. Level and align the cabinets.
WARNING:
Multiple cabinets must be ganged together for stability. The cabinet may tip when a heavy module is extended.
Ganging Cabinets
Multiple cabinet configurations require the cabinets to be connected to each other side by side (ganged). Hex spacers, located between the cabinets, front and rear, are used to gang the cabinets.
Note:
Ganging to legacy cabinets is not supported. It is recommended that ganged legacy cabinets be spaced one floor tile (24 in.) from current system.
Caution:
We recommend that a minimum of all four corners of ganged cabinets be secured with hex spacers. The cabinets need to be secure at the top and bottom of both the front and rear.
1700 Platform Product and Site Preparation Guide
Chapter 4: Uncrating and Installation
Positioning and Assembling Staged Cabinets
Notice:
Actual cabinet width is 61 cm (24 in.) without side panels. To ensure exact alignment for ganged cabinets, use the exact width when drawing up floor plans and cutting floor tiles.
Notice:
Cabinets must be ganged together before the customer installs seismic bracing.
1. If a cabinet has side panels attached, remove one or both, depending on which side or sides will mate.
Set aside the panels for reattaching at the ends of the row.
2. Remove the doors.
See Installing Cabinet Side Panels and Doors
.
3. Locate the cutouts in the outer edge of the rack frame.
4. Align the cutouts of one cabinet with the cutouts on the adjacent cabinet.
You will be installing a minimum of four hex spacers, one at each corner of the rack.
5. Remove the six hex spacers, twelve screws, and twelve flat washers from their bag.
6. Insert the hex spacer between the cabinets in the cutout provided in one of the corners of the rack.
You may need a pair of small pliers or a wrench to hold the spacer in place.
7. Using your hand, or a Phillips screwdriver, insert one screw and washer through the rack and into the open end of the hex spacer.
Figure 22: Inserting the Hex Spacers
8. On the opposite side, insert the second screw and washer through the rack and into the hex spacer.
9. Hold the hex spacer with a wrench or pliers, and tighten the screws until the cabinet frames come together.
1700 Platform Product and Site Preparation Guide 83
Chapter 4: Uncrating and Installation
Positioning and Assembling Staged Cabinets
Figure 23: Tightening the Hex Spacers
84
10. Repeat steps 6 through 9 for the remaining frame corners (three).
11. Replace the doors.
See Installing Cabinet Side Panels and Doors
.
Installing Stand-Alone Cabinet Stabilizers
Use cabinet stabilizers for stand-alone cabinet configurations only. The side stabilizer kit, 2021-K221, comes with a left and a right stabilizer and four bolts. The bracket for the stabilizers is incorporated in the front bottom rail of the cabinet.
WARNING:
You must install side stabilizers for stand-alone cabinet configurations. Stabilization is required to prevent tipping of the cabinet when a heavy module is extended.
Notice:
Do not block vented tiles with the stabilizers.
1. Align the cabinet so that the stabilizers will not block vented tiles once they are installed.
2. Place the left stabilizer on the floor in front of the left front of the cabinet.
3. Slip the left stabilizer under the front lip of the cabinet cross member and adjust the leveling feet to align the bolt holes.
4. Attach the left front stabilizer to the cabinet cross member, using two of the screws supplied in the kit.
5. Place the right stabilizer on the floor in front of the right front of the cabinet.
6. Slip the right stabilizer under the front lip of the cabinet cross member.
7. Attach the right front stabilizer to the cabinet cross member, using two of the screws supplied in the kit.
1700 Platform Product and Site Preparation Guide
Figure 24: Installing the Side Stabilizers
Chapter 4: Uncrating and Installation
Positioning and Assembling Staged Cabinets
Installing the Bottom Front Cabinet Air Baffle
1. If an air baffle kit (2021-K223) was ordered, at the front of the cabinet, slide the metal part of the baffle under the front lip of the cabinet cross member.
2. Align the swage nuts in the baffle to the oval holes in the front lip of the cabinet cross member.
3. Thread the two screws into the pem nuts and tighten.
1700 Platform Product and Site Preparation Guide 85
Chapter 4: Uncrating and Installation
Positioning and Assembling Staged Cabinets
86
Removing the Shipping Clips for an 18.5-Inch KVM Console
Some models of the KVM console are held in place during shipping with a set of orange clips. Other models are secured with a hook-and-loop strap. If the KVM console uses the shipping clips, the clips must be removed during cabinet installation.
1. At the front of the cabinet, press the orange shipping clips toward the center of the cabinet and remove.
Discard the shipping clips.
1700 Platform Product and Site Preparation Guide
Chapter 4: Uncrating and Installation
Positioning and Assembling Staged Cabinets
Installing Cabinet Side Panels and Doors
A cabinet may be shipped without the side panels and doors attached. Side panels for a ganged row configuration may be shipped on one of the cabinets, and must be removed then replaced after ganging.
Installing Side Panels
The side panels hang on the side of the cabinet using two brackets, top and bottom, and three alignment pins at the top. The brackets have a tight slip fit to keep them in place. One metal clip at the bottom rear of the panel secures the rear of the panel to the cabinet. A handle in the center of the panel for lifting and carrying the panel.
Note:
There is a left side panel and a right side panel.
Caution:
The side panel is large and bulky and may require two people for installation.
1. Using the handle in the center of the panel, take either side panel and hold it against the side of the cabinet.
2. Lift the side panel and hold it against the cabinet so the brackets will slip over the two cross members of the cabinet.
3. Align the three pins at the top of the panel with the holes in the top of the cabinet.
4. Ensure you push the rear of the panel in as you lower the panel into place to engage the clip at the bottom rear of the panel.
5. Repeat all steps for the other panels.
1700 Platform Product and Site Preparation Guide 87
Chapter 4: Uncrating and Installation
Positioning and Assembling Staged Cabinets
88
Installing and Aligning Front and Rear Doors
The cabinet may come with the front door removed. The front door of the cabinet can be adjusted slightly so that all the corners line up when cabinets are ganged together.
1. Mount the door to the cabinet using the three drop on hinges.
a) Lift the door up and align the hinge receptacles with the hinge pins on the cabinet.
b) Drop the door into place.
If the door hinges do not align correctly, you might need to loosen the hinges to adjust them.
Note:
The door is heavy and may require two people for installation.
2. Adjust the door by slightly loosening the nuts that hold the hinge plate to the door.
The hinge plate should only be able to move when pulled. There should be enough pressure from the nuts to create friction between hinge plate and door.
1700 Platform Product and Site Preparation Guide
Chapter 4: Uncrating and Installation
Positioning and Assembling Staged Cabinets
3. Close the door and align the upper corners with either the cabinet side panels or the door corners of the cabinet ganged next to it.
The door can be raised or lowered and canted at a slight angle.
4. While holding the door in the desired position, open the door and tighten the nuts (one at the top and one at the bottom) on the top hinge plate.
5. Close the door to check alignment.
If necessary, loosen the nuts slightly and adjust the door, then re-tighten the nuts.
6. When the door is properly aligned, tighten all the nuts holding the hinge plates to the door.
1700 Platform Product and Site Preparation Guide 89
Chapter 4: Uncrating and Installation
Positioning and Assembling Staged Cabinets
90 1700 Platform Product and Site Preparation Guide
APPENDIX A
Physical Specifications for Site Planning
Cabinet Descriptions
Dimensions: 42-U Cabinet
Figure 25: Cabinet HWD Dimensions: 42-U Cabinet
Notice:
Actual cabinet width is 60.96 cm (24 in.) without side panels. To ensure exact alignment for ganged cabinets, use the exact width when drawing up floor plans and cutting floor tiles.
Cabinets can be stand-alone, or bolted together in rows. Stabilizer feet are required on standalone cabinets.
The stabilizers add width and depth to a stand-alone cabinet.
• Side stabilizer feet are required on the front corners of a stand-alone cabinet.
1700 Platform Product and Site Preparation Guide 91
Appendix A: Physical Specifications for Site Planning
Cabinet Descriptions
• Do not use side stabilizer feet for cabinets bolted together (ganged).
Table 3: 42-U Rack Cabinet HWD Dimensions
Feature
Cabinet frame
+ side stabilizers
+ front door
+ side panels
Height
204.5 cm (80.5 in.)
+ 0
+ 0
+ 0
Width
61 cm (24 in.)
+ 35.5 cm (14 in.) each side
+ 0
+ .4 cm (.15 in.)
Depth
119.4 cm (47 in.)
+ 22.9 cm (9 in.)
+ 5 cm (2 in.)
+ 0
Cabinet Footprint and Clearances: 42-U Cabinet
The required installation and servicing clearances are based on the following:
• Space needed in front of the cabinet to service an extended chassis
• Space needed to open and close cabinet doors
• Space needed between, in front of, and on the sides of the cabinets to install stabilizer feet
Notice:
If two stand-alone cabinets are placed side-by-side, allow 36 cm (14.5 in.) between cabinets to install the side stabilizer feet. There should be at least 1.3 cm (0.5 in.) between the installed side stabilizer feet.
The minimum aisle width requirements from a technical perspective only are:
• 101.6 cm (40 in.) front service clearance
• 81.3 cm (32 in.) rear service clearance
At all levels of government (such as city, state and federal), there are laws that govern minimum aisle width
(such as building safety codes, occupational safety regulations, and disability access laws). It is the customer’s responsibility to determine and comply with all applicable laws.
The footprints are shown on data center tiles. Each square represents one tile with a dimension of 61 cm x 61 cm (24 in. x 24 in.).
92 1700 Platform Product and Site Preparation Guide
Figure 26: Footprint and Minimum Clearances for One Cabinet
Appendix A: Physical Specifications for Site Planning
Cabinet Descriptions
1700 Platform Product and Site Preparation Guide 93
Appendix A: Physical Specifications for Site Planning
Cabinet Descriptions
Figure 27: Footprint and Minimum Clearances for Four Ganged Cabinets
94
Notice:
Actual cabinet width is 60.96 cm (24 in.) without side panels. To ensure exact alignment for ganged cabinets, use the exact width when drawing up floor plans and cutting floor tiles.
1700 Platform Product and Site Preparation Guide
Appendix A: Physical Specifications for Site Planning
Data Center Considerations
Data Center Considerations
Weight and Floor Loading
WARNING:
Vented floor tiles cannot support as much weight as solid tiles. When moving cabinets in a computer room, replace vented floor tiles with solid floor tiles along the path where cabinets will be rolled. Failure to do so may cause damage or collapse of vented floor tiles, resulting in physical damage and/or bodily injury.
Table 4: Weight and Floor Loading for Equipment in System
Unit
1700 cabinet with: one VMS up to five nodes (processing, channel server, or TMS nodes) fifteen drive enclosures, three with controllers two 24-port server management Ethernet switches
Actual
Footprint
Area (No
Stabilizers)
0.726 sq m
(7.8 sq ft)
BYNET cabinet 108-port maximum configuration: two 108-Port InfiniBand switches two TMSs one VMS one KVM two 48-port server management Ethernet switches cabinet doors
0.73 sq m
(7.8 sq ft)
BYNET cabinet 162-port maximum configuration: one 162-Port InfiniBand switch three TMSs one VMS one KVM two 48-port server management Ethernet switches cabinet doors
0.73 sq m
(7.8 sq ft)
Approx.
Installed
Weight
725 kg
(1600 lb)
500 kg (1100 lb)
396 kg
(872 lb)
Distributed Floor Loading
based on cabinet footprint:
998 kg/sq m (205 lb/sq ft) based on footprint plus servicing clearance required to open doors:
493 kg/sq m (101 lb/sq ft) based on cabinet footprint:
688 kg/sq m (141 lb/sq ft) based on footprint plus servicing clearance required to open doors:
340 kg/sq m (69 lb/sq ft) based on cabinet footprint:
545 kg/sq m (112 lb/sq ft) based on footprint plus servicing clearance required to open doors:
269 kg/sq m (55 lb/sq ft)
Concentrated
Floor Loading
13.8 kg/sq cm
(195 lb/sq in.)
9.5 kg/sq cm
(134 lb/sq in.)
7.75 kg/sq cm
(109 lb/sq in.)
1700 Platform Product and Site Preparation Guide 95
Appendix A: Physical Specifications for Site Planning
Data Center Considerations
Unit
BYNET cabinet 324-port maximum configuration: one 324-Port InfiniBand switch two 48-port server management Ethernet switches cabinet doors
Cables
Actual
Footprint
Area (No
Stabilizers)
0.73 sq m
(7.8 sq ft)
Approx.
Installed
Weight
420 kg
(926 lb)
Distributed Floor Loading
based on cabinet footprint:
578 kg/sq m (119 lb/sq ft) based on footprint plus servicing clearance required to open doors:
285 kg/sq m (58 lb/sq ft)
Concentrated
Floor Loading
8.2 kg/sq cm
(116 lb/sq in.)
Allow an additional 22.68 kg (50 lb) per system for the installed weight of the cables. Actual weight will vary depending on the number of cables routed through the cable management system.
Notice:
Weight and floor loading for Platform Framework Cabinets must be based on the maximum configurations supported by the platform. See the Teradata Platform Framework Cabinet Model 12
Hardware Service Guide, B035-5389.
Site Floor and Ceiling Height Specifications
Site Feature
Raised floor
Recommended
Minimum Height
61.0 cm (24 in.)
Explanation
Ceiling 3 m (10 ft)
If a raised floor is used as a cold air delivery plenum, Teradata recommends that the raised floor height be greater than 61 cm (24 in.).
Recommended height prevents warm air that is exhausted at the rear of the cabinets from being trapped in the area above the cabinets, and from being recirculated back into the inlets of the hardware equipment.
Floor Layouts
Floor layouts are part of physical site planning, but based on environmental requirements of the system. For additional floor layout information, refer to
Best Practices for Floor Layout .
96 1700 Platform Product and Site Preparation Guide
Appendix A: Physical Specifications for Site Planning
Cables
Cables
Cable Management
In-cabinet cable harnesses are used for server management in processing/storage cabinets. BYNET cabinets do not use cable harnesses.
Harness cables are cut to specific lengths and assembled to accommodate specific breakouts to each of the chassis in the cabinet. This minimizes the potential for incorrect cabling and the need for cable dressing.
Each cable in the harness assembly is labeled at both ends.
Components that do not have a cable harness have point-to-point cabling. Each cable in point-to-point cabling is labeled at both ends.
See Cable Management Protocol in the platform Hardware Installation Guide for more information about cable management.
Network Cables and Hardware
Note the type of network connections to be used, and make sure that the correct cabling and hardware will be on site during installation. Although network adapters are ordered and provided with systems, the customer is expected to supply the cabling and external hardware for the following:
• Ethernet adapters (see the cable lengths section in this guide)
• HCA adapters (see the HCA cables section in this guide)
Note:
All other cables and hardware are supplied during staging. Cabling kits are also available.
HCA FICON Cables and Connectors
Note:
Teradata does not provide FICON cables for HCAs. You must obtain FICON cables from third-party vendors.
The following adapters require a cable with LC male connectors:
• FICON LP12000
• PEFA
Figure 28: FICON Cable
1700 Platform Product and Site Preparation Guide 97
Appendix A: Physical Specifications for Site Planning
Delivery and Installation
Available Cable Lengths
When developing floor layouts, be sure to refer to and take into account available lengths for the discrete cables that run between cabinets.
Table 5: Available Cable Lengths for Discrete Cables
Cable Type
Ethernet Copper
Ethernet Fiber (1 Gb)
Ethernet Fiber (10 Gb)
Node to BYNET
Storage SAS
Host Channel Adapter
(FICON)
Available Lengths
• Cable, Ethernet, CAT5E, 5 meters (16 feet)
• Cable, Ethernet, CAT5E, 10 meters (32 feet)
• Cable, Ethernet, CAT5E, 20 meters (65 feet)
• Cable, Fiber LC/LC, 15 meters (49 feet)
• Cable, Fiber LC/LC, 100 meters (328 feet)
• Cable, Fiber 8/10Gb OM2 50/125, 10 meters (32 feet)
• Cable, Fiber 8/10Gb OM2 50/125, 30 meters (98 feet)
Intra-cabinet:
• Cable, BYNET Copper QSFP+ Cable, 2.0 meters (6.5 feet)
Inter-cabinet:
• Cable, BYNET QSFP+ Active Optical Cable, 5 meters (16 feet)
• Cable, BYNET QSFP+ Active Optical Cable, 15 meters (49 feet)
• Cable, BYNET QSFP+ Active Optical Cable, 30 meters (98 feet)
• Cable, BYNET QSFP+ Active Optical Cable, 50 meters (164 feet); special order
• Cable, BYNET QSFP+ Active Optical Cable, 100 meters (328 feet); special order
Node to disk array controllers:
• Cable Assembly – SAS, 2.0 meters (6.5 feet)
Disk array controllers to ESMs:
• Cable Assembly – SAS, 1 meters (3 feet)
Teradata does not provide host channel adapter cables. The customer may obtain cables of various lengths through their cable vendor.
Delivery and Installation
Shipping Dimensions and Weights
Caution:
The size and weight of a system requires that professional movers and riggers deliver the crated units.
98 1700 Platform Product and Site Preparation Guide
Appendix A: Physical Specifications for Site Planning
Delivery and Installation
Table 6: Crated Cabinet Dimensions and Weights
Unit
1700 Cabinet
BYNET Cabinet with
108-Port InfiniBand
Switches
Shipping Weight *
948 kg (2089 lb)
680 kg (1500 lb)
Crate Height
2.2 m (86 in.)
2.2 m (86 in.)
Crate Depth
1.5 m (60 in.)
1.5 m (60 in.)
Crate Width
1 m (40 in.)
1 m (40 in.)
BYNET Cabinet with
162-Port InfiniBand
Switch and TMSs
BYNET Cabinet with
324-Port InfiniBand
Switch
577 kg (1272 lb)
601 kg (1326 lb)
2.2 m (86 in.)
2.2 m (86 in.)
1.5 m (60 in.)
1.5 m (60 in.)
1 m (40 in.)
1 m (40 in.)
* Based on maximum cabinet configuration for each cabinet as defined in Weight and Floor Loading
, plus shipping crate. The shipping crate is approximately 181 kg (400 lb).
Notice:
Weight and floor loading for Platform Framework Cabinets must be based on the maximum configurations supported by the platform. See the Teradata Platform Framework Cabinet Model 12
Hardware Service Guide, B035-5389.
Moving and Handling Guidelines
Following are guidelines to help the customer prepare for system delivery.
• The size and weight of a system requires that professional movers and riggers deliver the crated units.
• Make sure that the correct equipment and adequate help is available to move the system to its on-site destination.
• Avoid exposing the cabinet to extreme temperature and/or humidity changes when moving it from the uncrating area to its on-site destination.
• Systems are mounted on casters to facilitate moving. They have adjustable glides to facilitate leveling in their final installed positions.
• The cabinet is weighted toward the front by the equipment. Roll it backwards, pushing from the front of the cabinet, to avoid tipping.
• Maximum degree of tip allowed on the side of a single rack: 10° off of vertical.
• If the site requires use of an elevator to move the system into place, verify the load capacity of the elevator.
• Ensure that the floors along the route to the final installation location can support the weight of the cabinets and do not impede their movement. If necessary, have the customer replace vented tiles with solid tiles.
• If there are any steeply-angled ramps along the installation route, advise the movers. They may need pulleys.
• Floor vents are not designed to handle the weight of a cabinet. Make sure that the cabinet can be negotiated around them.
• Verify that the floor at the site can support the weight of the cabinet. Be especially careful with perforated floor tiles in sites with raised floors.
1700 Platform Product and Site Preparation Guide 99
Appendix A: Physical Specifications for Site Planning
Delivery and Installation
Installation Overview
Figure 29: Installation Overview
100
About Environmental Stabilization
If temperature and humidity changes have been extreme during transit, condensation may develop in the cabinet. An environmental stabilization procedure must be completed for all cabinets in the system once the cabinets are moved to their on-site destination. The stabilization period may vary from 0 to 8 hours. See
Performing Environmental Stabilization
.
1700 Platform Product and Site Preparation Guide
Appendix A: Physical Specifications for Site Planning
Delivery and Installation
Seismic Bracing for a Teradata Cabinet
Teradata recommends using a qualified seismic bracing installation company to secure the Teradata cabinets to the floor.
The shipping brackets that held the cabinet to the shipping pallet may be used to attach the cabinet to the floor. Use the following figure as a guide in locating tie-down points for attaching the shipping brackets.
Figure 30: Seismic Bracing Tie-Down Points
Before attaching multiple cabinets to the floor, join the cabinets together using the cabinet docking hardware. See the Hardware Installation Guide.
1700 Platform Product and Site Preparation Guide 101
Appendix A: Physical Specifications for Site Planning
Delivery and Installation
102 1700 Platform Product and Site Preparation Guide
APPENDIX B
Site Power Distribution Planning
AC Input Power Distribution
Dual AC Concept
The system is referred to as a dual AC system because the power subsystem in each cabinet can accommodate power from two separate power sources.
Each processing/storage cabinet has either two AC feeder boxes (one on each side of the cabinet), or four AC feeder boxes (two on each side of the cabinet).
• The AC feeder box(es) on one side of the cabinet must be connected to one power source, and the AC feeder box(es) on the other side of the cabinet must be connected to a separate power source.
• By default:
∘ If a cabinet has two AC feeder boxes, both share current.
∘ If a cabinet has four AC feeder boxes, the top two AC feeder boxes share current, and the bottom two
AC feeder boxes share current.
• If the power source connected to the AC feeder box(es) on one side of the cabinet is lost, the current on the AC feeder box(es) connected to the remaining power source will increase to take over power for the lost source; however, the system will experience some operational degradation.
Each BYNET and PFC cabinet has two AC boxes (one blue AC box and one orange AC box), providing dedicated inlets for the two power sources.
• Power cords from blue AC boxes must be connected to one power source, and power cords from orange
AC boxes must be connected to a separate power source.
• By default, current is shared between the two AC boxes.
• If one power source is lost, the current on the AC box connected to the remaining power source will increase to take over power for the lost source; however, the system will experience some operational degradation.
Note that power connections to some Ethernet switches are not redundant. A system that loses operation on some of its power cords will lose operation on Ethernet switches that are connected to a single power supply.
For information about which AC boxes provide power to which Ethernet switches, see the Cabling appendix and the Chassis Port Reference appendix in the Hardware Installation Guide for your system.
Site Wiring Options for Dual AC
Dual AC can be implemented at a customer site in one of the following ways:
• Two separate utility power sources
• Two separate circuit breaker panels
• Two site UPSs
1700 Platform Product and Site Preparation Guide 103
Appendix B: Site Power Distribution Planning
AC Input Power Distribution
Site wiring decisions should be made with an understanding of how the customer will benefit from the dual
AC feature.
Note:
A site UPS is not required.
Separate Power Sources
Some customers have two separate sources of AC power. For example, a customer’s site may receive power from two different power substations. In this case, left side AC feeder box(es) and blue AC box(es) can be connected to one source, and right side AC feeder box(es) and orange AC box(es) can be connected to the other source. If the source supplying the AC feeder box(es) or AC box on one side of the cabinet fails, the current on the AC feeder box(es) or AC box on the other side of the cabinet will increase, allowing the system to continue operating.
Separate Circuit Breaker Panels
Some customers are concerned about the loss of power to the system during electrical maintenance work on the site. In this case, the system can be wired so left side AC feeder box(es) and blue AC box(es) can be connected to one circuit breaker panel, and right side AC feeder box(es) and orange AC box(es) can be connected to another circuit breaker panel. If the circuit breaker panel supplying the AC feeder box(es) or
AC box on one side of the cabinet is accidentally shut off, the current on the AC feeder box(es) or AC box on the other side of the cabinet will increase, allowing the system to continue operating.
Two Site UPSs
Some customers may have two site UPSs. If so, the site can be considered as having two separate power sources.
System Load Configurations
Notice:
All power receptacles at the site must be wired to support the rated load specified in
Input Power Plugs and Receptacles
.
Teradata power subsystems use load sharing by default. Sites can expect an approximate increase of 100% in load on the active line when the other source of power fails. That is, a source has 50% of the load to start with, and when AC is lost from the other source, the remaining 50% of the load transfers to the active source.
Notice:
Products with four cords need special attention when plugging in at sites with redundant power to ensure proper operation if one power source fails.
• If the cabinet uses four cords and has four AC feeder boxes, the cords from the two left-hand side AC feeder boxes go to one site source, and the cords from the two right-hand side AC feeder boxes go to the second site source.
Site Wiring for System Integrity
For maximum system integrity, observe the following:
104 1700 Platform Product and Site Preparation Guide
Appendix B: Site Power Distribution Planning
AC Power Cord Egress from Top or Bottom of Cabinet
• All power receptacles at the site must be wired to support the rated load specified in
Input Power Plugs and Receptacles
.
• All system components should be on dedicated branch circuits from a distribution panel that does not supply any switched inductive loads (motors, air conditioners, etc.).
• Nothing else should be connected to the branch circuits except other computer equipment.
• The socket-outlet shall be installed near the equipment and shall be accessible.
AC Power Cord Egress from Top or Bottom of
Cabinet
The cabinet uses AC feeder boxes mounted to the sidewalls on the inside of the cabinet. The AC feeder boxes allow approximately 2.74 m (9 ft) of cable egress out of the top or bottom of the cabinet.
To ensure that the cabinet is configured according to the customer's power cord egress preference (top or bottom egress), the cabinet must be ordered with the power feature for top power cord egress or bottom power cord egress.
The BYNET switch cabinet uses AC boxes mounted in U spaces at the bottom of the cabinet. The AC boxes allow the power cord to egress approximately 4.27 m (14 ft) out of the bottom of the rack or approximately
2.44 (8 ft) out the top of the rack. The BYNET switch cabinet does not have a power feature that specifies top power cord egress or bottom power cord egress.
Input Power Plugs and Receptacles
Platform or Appliance Cabinet Input Power Plugs and
Receptacles
Multiple power options are available for the 1700 cabinet.
Notice:
For site preparation, use the section that corresponds to the power option ordered for the site.
• Four-cord 30A/32A phase-phase or single-phase with splash-proof power plugs and receptacles or connectors. Note that with this power configuration, the full cabinet configuration cannot be achieved.
Refer to the Cabinet Builds section in the Product Information chapter of this guide for limitations.
• Two-cord 60A three-phase Delta with watertight power plugs and receptacles or connectors.
• Two-cord 30/32A three-phase Wye with splash-proof power plugs and receptacles or connectors.
Note:
For input power plugs and receptacles for BYNET cabinets, see this guide.
Note:
For input power plugs and receptacles for Platform Framework Cabinets, see the Teradata Platform
Framework Cabinet Model 12 Hardware Service Guide, B035-5389.
1700 Platform Product and Site Preparation Guide 105
Appendix B: Site Power Distribution Planning
Input Power Plugs and Receptacles
Processing/Storage Cabinet Four-Cord 30A/32A Phase-Phase or Single
Phase with Splash-Proof Power Plugs and Receptacles
The following plug type is for worldwide use. It is used phase-to-phase in locations with traditional North
American power and single phase (line-to-neutral) in locations with traditional European power.
Table 7: Processing/Storage Cabinet Four-Cord 30A/32A Splash-Proof Power Plugs and Receptacles
Unit
Power Type
Nameplate Rating
Expected Utility Power
Sources
(Provided by Site)
a b
1700 Cabinet
30A/32A phase-phase or single phase power:
• Plug is rated at 30A for North America
• Plug is rated at 32A for Europe
24A per cord
200-240V~
• 230 V wired line-to-neutral (single phase). With this line-to-neutral source, the power plug connects to line, neutral, and safety ground.
Note:
This utility source is typical in Europe, but is now sometimes found in
North America in new, specialized data centers.
Or
• Wired line-to-line (phase-phase)
Note:
This utility source is typical in North America and Japan.
∘ Three-phase Wye with a line-to-neutral voltage typically 120V or 127V and a line-to-line voltage of 200V to 240V.
∘ Alternate expected power source (Japan): Delta power source 200V to
240V on each side.
Power Plug and Number of
Cords
(Supplied with Product)
Notice:
With either of the last two utility power sources, each of the 3-pin power plugs connect to two of the three lines and also to safety ground. With these sources the power plug does not connect to neutral.
IEC 60309 CEE17, pin and sleeve, 30/32A, Blue (250V), 2P3W, with 6-hour keying, IP44 splash-proof plug
(Walther Electric brand is shown below. Actual brand supplied with cabinet may vary.)
106 1700 Platform Product and Site Preparation Guide
Appendix B: Site Power Distribution Planning
Input Power Plugs and Receptacles
Four AC feeder box cords per cabinet, top or bottom egress.
Note:
The minimum bend radius limit for the power cord is 12.8 cm (5.0 in.). Do not bend the power cord tighter than this limit.
AC Feeder Box Power Cord
Connections to Site Power
(For Redundancy)
Power Receptacle or
Connector
and
Circuit Breakers
(Provided by Site)
The cabinet contains two AC feeder boxes on the left side of the cabinet and two
AC feeder boxes on the right side of the cabinet. Each AC feeder box has one power cord (four total). The two power cords on the left side of the cabinet connect to one site power source. The two power cords on the right side of the cabinet connect to the second site power source.
IEC 60309 CEE17, pin and sleeve, 30/32A, Blue (250V), 2P3W with 6-hour keying, IP44 splash-proof connector or receptacle
Example receptacles (similar products are available from other companies):
Scame Electrical Solutions SCM330R6S (shown above)
Walther Electric 430306
Example connectors for use with cordage (similar products are available from other companies):
ABL Sursum K32S20A
Scame Electrical Solutions SCM330C6S
Walther Electric 330306 (shown above)
Walther Electric 331306
Example connector for use with ¾-inch NPT fitting for connection to conduit: c
Walther Electric PG21-75 combined with Walther Electric 331306
Customer to supply four receptacles or connectors per cabinet. d
1700 Platform Product and Site Preparation Guide 107
Appendix B: Site Power Distribution Planning
Input Power Plugs and Receptacles
One circuit breaker required for each power cord; use a double-pole breaker for phase to phase implementations and a single-pole breaker for phase to neutral installations. Customer must provide required site circuit breakers.
a
Do not use this table to determine power consumption, to estimate current draw, or to estimate heat
generation. For these parameters, see Site Environmental Planning
. Nameplate ratings are a statement of product certification.
b
Frequency rating is 50 or 60 Hz for all products.
c
Conduit Adapters do not connect to the ground terminal of the connector. Consult your local code grounding requirements before using adapters.
d
Customer can obtain connectors from any source. Connectors are available from Teradata by ordering kit
2021-K900. Two kits are required per processing/storage cabinet.
Note:
For input power plugs and receptacles for Platform Framework Cabinets, see the Teradata Platform
Framework Cabinet Model 12 Hardware Service Guide, B035-5389.
Processing/Storage Cabinet Two-Cord 60A Three-Phase Delta with
Watertight Power Plugs and Receptacles
This plug type is for Canada, Columbia, El Salvador, Japan, Mexico, Nicaragua, Panama, South Korea,
Taiwan, United States, and Venezuela. a
Table 8: Processing/Storage Cabinet Two-Cord 60A Three-Phase Delta Watertight Power Plugs and Receptacles
Unit
Power Type
Nameplate Rating b c
Expected Utility Power
Sources
(Provided by Site)
1700
60A three-phase Delta power
48A per cord
200-240 V~, 3+PE
• Three-phase Wye with a line-to-neutral voltage typically 120V or 127V and a line-to-line voltage of 200V to 240V.
• Alternate expected power source (Japan): Delta power source 200V to 240V on each side.
Notice:
With either of these two utility power sources, each of the 4-pin power plugs will connect to all three lines and also to safety ground. With this power solution the power plug will not have a neutral connection.
Power Plug and Number of
Cords
(Supplied with Product)
IEC 60309 CEE17, pin and sleeve, 60A, Blue (3Ø250V), 3P4W, with 9-hour keying, IP67 watertight plug
(Walther Electric brand is shown below. Actual brand supplied with cabinet may vary.)
108 1700 Platform Product and Site Preparation Guide
Appendix B: Site Power Distribution Planning
Input Power Plugs and Receptacles
Two AC feeder box cords per cabinet, top or bottom egress.
Note:
The minimum bend radius limit for the power cord is 16.5 cm (6.5in.). Do not bend the power cord tighter than this limit.
AC Feeder Box Power Cord
Connections to Site Power
(For Redundancy)
Power Receptacle or
Connector
and
Circuit Breakers
(Provided by Site)
The power cord on the left AC feeder box in the cabinet connects to one site power source. The power cord on the right AC feeder box in the cabinet connects to the second site power source.
IEC 60309 CEE17, pin and sleeve, 60A, Blue (3Ø250V), 3P4W, with 9-hour keying, IP67 watertight receptacle or connector
Example receptacles (similar products are available from other companies):
Hubbell HBL460R9W
Leviton 460R9W
Scame Electrical Solutions SCM460R9W (shown above)
Walther Electric 469409
1700 Platform Product and Site Preparation Guide 109
Appendix B: Site Power Distribution Planning
Input Power Plugs and Receptacles
Example connectors for use with cordage (similar products are available from other companies):
Hubbell HBL460C9W
Leviton 460C9W
Russellstoll ABB460C9W
Scame Electrical Solutions SCM460C9W
Walther Electric 369409 (shown above)
Example connector for use with 1-inch NPT fitting for connection to conduit: d
Hubbell HBL460C9W combined with Hubbell SAC100
Example connector for use with 1 ¼-inch NPT fitting for connection to conduit: d
Walther Electric PG36-125 combined with Walther Electric 369409
Customer to supply two receptacles or connectors per cabinet. e
One three-pole site circuit breaker required for each power cord; customer must provide required site circuit breakers.
Each AC feeder box on separate power source connection.
a
Bahrain, Brazil, Lebanon, Philippines, and Saudi Arabia require discussions with the site team to determine the appropriate power feature for the specific site.
b
Do not use this table to determine power consumption, to estimate current draw, or to estimate heat
generation. For these parameters, see Site Environmental Planning
. Nameplate ratings are a statement of product certification.
c
Frequency rating is 50 or 60 Hz for all products.
d
Conduit Adapters do not connect to the ground terminal of the connector. Consult your local code grounding requirements before using adapters.
e
Customer can obtain connectors from any source. Connectors are available from Teradata by ordering kit
2021-K902. One kit is required per processing/storage cabinet.
Note:
For input power plugs and receptacles for Platform Framework Cabinets, see the Teradata Platform
Framework Cabinet Model 12 Hardware Service Guide, B035-5389.
110 1700 Platform Product and Site Preparation Guide
Appendix B: Site Power Distribution Planning
Input Power Plugs and Receptacles
Processing/Storage Cabinet Two-Cord 30/32A Three-Phase Wye with
Splash-Proof Power Plugs and Receptacles
This plug type is for Europe, Australia, Africa, Asia, Middle East, Territories of the United Kingdom, Russia,
Belarus, Territories of France, Territories of Denmark, Territories of the Netherlands, and the Pacific
(excluding Taiwan, Japan, South Korea) that use IEC 30A/32A three-phase Wye, 220V to 240V line-toneutral. Also used for specialized, energy-saving data center sites in North America that use 220V to 240V line-to-neutral. Not suitable for a 120V Wye power source that is traditional in North America.
Table 9: Processing/Storage Cabinet Two-Cord 30/32A Three-Phase Wye Splash-Proof Power Plugs and Receptacles
Unit
Power Type
Nameplate Rating
Expected Utility Power
Source
(Provided by Site)
a b
Power Plug and Number of
Cords
(Supplied with Product)
1700 Cabinet
30A/32A three-phase Wye, 230V L-N power:
• Plug is rated at 30A for North America
• Plug is rated at 32A for Europe
24A per cord
220-240/381-415V~, 3+N+PE
• Three-phase Wye with a line-to-neutral voltage of 200V to 240V
(Not suitable for a Wye source with a line-to-neutral voltage of 120V that is traditional in North America.)
IEC 60309 CEE17, pin and sleeve, 30/32A, Red (400V), 4P5W, with 6-hour keying, IP44 splash-proof plug
(Walther Electric brand is shown below. Actual brand supplied with cabinet may vary.)
Two AC feeder box cords per cabinet, top or bottom egress.
Note:
The minimum bend radius limit for the power cord is 15.1 cm (5.9 in.). Do not bend the power cord tighter than this limit.
AC Feeder Box Power Cord
Connections to Site Power
(For Redundancy)
Power Receptacle or
Connector
and
Circuit Breakers
The power cord on the left AC feeder box in the cabinet connects to one site power source. The power cord on the right AC feeder box in the cabinet connects to the second site power source.
IEC 60309 CEE17, pin and sleeve, 30/32A, Red (400V), 4P5W, with 6-hour keying, IP44 splash-proof receptacle or connector
1700 Platform Product and Site Preparation Guide 111
Appendix B: Site Power Distribution Planning
Input Power Plugs and Receptacles
(Provided by Site)
Example receptacle (similar products are available from other companies):
Walther Electric 430
Example connectors for use with cordage (similar products are available from other companies):
ABL Sursum K52S30A
Hubbell C530C6S
Walther Electric 330 (shown above)
Walther Electric 331
Example connector for use with ¾-inch NPT fitting for connection to conduit: c
Walther Electric PG21-75 combined with Walther Electric 331
Customer to supply two receptacles or connectors per cabinet. d
One three-pole site circuit breaker required for each power cord; customer must provide required site circuit breakers.
Each AC feeder box on separate power source connection.
a
Do not use this table to determine power consumption, to estimate current draw, or to estimate heat
generation. For these parameters, see Site Environmental Planning
. Nameplate ratings are a statement of product certification.
b
Frequency rating is 50 or 60 Hz for all products.
c
Conduit Adapters do not connect to the ground terminal of the connector. Consult your local code grounding requirements before using adapters.
d
Customer can obtain connectors from any source. Connectors are available from Teradata by ordering kit
2021-K903. One kit is required per processing/storage cabinet.
112 1700 Platform Product and Site Preparation Guide
Appendix B: Site Power Distribution Planning
Input Power Plugs and Receptacles
Note:
For input power plugs and receptacles for the Platform Framework Cabinet, see the Teradata Platform
Framework Cabinet Model 12 Hardware Service Guide, B035-5389.
Switch Cabinet Input Power Plugs and Receptacles
BYNET 108-Port, 162-Port, and 324-Port Cabinet Two-Cord 30A/32A Splash-
Proof Power Plugs and Receptacles
The following plug type is for worldwide use. It is used phase-to-phase in locations with traditional North
American power and single phase (line-to-neutral) in locations with traditional European power.
Table 10: BYNET 108-Port, 162-Port, and 324-Port Cabinet Two-Cord 30A/32A Splash-Proof Power Plugs and Receptacles
Unit
Power Type
Nameplate Rating
Expected Utility Power
Sources
(Provided by Site)
a b
BYNET cabinet with 108-Port, 162-Port, and 324-Port switches
30A/32A phase-phase or single phase power
• Plug is rated at 30A for North America
• Plug is rated at 32A for Europe
24A per cord
200-240V~
• 230 V wired line-to-neutral (single-phase). With this line-to-neutral source, the power plug connects to line, neutral, and safety ground.
Note:
This utility source is typical in Europe, but is now sometimes found in
North America in new, specialized data centers.
Or
• Wired line-to-line (phase-phase)
Power Plug and Number of
Cords
(Supplied with Product)
Note:
This utility source is typically used in North America and Japan.
∘ Three-phase Wye with a line-to-neutral voltage typically 120V or 127V and a line to line voltage of 200V to 240V.
∘ Alternate expected power source (Japan): Delta power source 200V to
240V on each side.
Notice:
With either of the last two utility power sources, each of the 3-pin power plugs connect to two of the three lines and also to safety ground. With these sources the power plug does not connect to neutral.
IEC 60309 CEE17, pin and sleeve, 30/32A, Blue (250V), 2P3W, with 6-hour keying, IP44 splash-proof plug
(Walther Electric brand is shown below. Actual brand supplied with cabinet may vary.)
1700 Platform Product and Site Preparation Guide 113
Appendix B: Site Power Distribution Planning
Input Power Plugs and Receptacles
AC Box Power Cord
Connections to Site Power
(For Redundancy)
Power Receptacle or
Connector
and
Circuit Breakers
(Provided by Site)
Two AC box cords per cabinet, top or bottom egress.
Note:
The minimum bend radius limit for the power cord is 12.8 cm (5.0 in.). Do not bend the power cord tighter than this limit.
The power cord on the orange AC box in the cabinet connects to one site power source. The power cord on the blue AC box in the cabinet connects to the second site power source.
IEC 60309 CEE17, pin and sleeve, 30/32A, Blue (250V), 2P3W, with 6-hour keying, IP44 splash-proof receptacle or connector
Example receptacles (similar products are available from other companies):
Scame Electrical Solutions SCM330R6S (shown above)
Walther Electric 430306
114
Example connectors for use with cordage (similar products are available from other companies):
ABL Sursum K32S20A
Scame Electrical Solutions SCM330C6S
1700 Platform Product and Site Preparation Guide
Appendix B: Site Power Distribution Planning
Three-Phase AC Box - Phase Current Balancing
Walther Electric 330306 (shown above)
Walther Electric 331306
Example connector for use with ¾-inch NPT fitting for connection to conduit:
Walther Electric PG21-75 combined with Walther Electric 331306
Customer to supply two receptacles or connectors per cabinet. c
One site circuit breaker required for each power cord; customer must provide required site circuit breakers.
Each AC box on separate power source connection.
a
Do not use this table to determine power consumption, to estimate current draw, or to estimate heat
generation. For these parameters, see Site Environmental Planning
. Nameplate ratings are a statement of product certification.
b
Frequency rating is 50 or 60 Hz for all products.
c
For 108-Port, 162-Port, and 324-Port cabinets: Customer can obtain connectors from any source. Connectors are available from Teradata by ordering kit 2021-K900. One kit is required per BYNET cabinet.
Note:
For input power plugs and receptacles for Platform Framework Cabinets, see the Teradata Platform
Framework Cabinet Model 12 Hardware Service Guide, B035-5389.
Three-Phase AC Box - Phase Current Balancing
Phase currents are not balanced on three-phase AC feeder boxes. If you have more than one cabinet with the three-phase AC feeder box, you will need to rotate the phase connections on each outlet to minimize the aggregate site imbalance. Consult this table for how to connect the phases to the receptacle in order to rotate the phase connections.
Notice:
With a three-phase Wye AC feeder box, the phase imbalance results in a current on the neutral wire.
Table 11: Three-Phase AC Box Current Balancing
Cabinet #
Cabinet #1
Cabinet #2
Cabinet #3
Cabinet #4
Cabinet #5
Cabinet #6
Cabinet #7
Phase #1
L1
L3
L2
L1
L3
L2 and so on
Phase #2
L2
L1
L3
L2
L1
L3 and so on
Phase #3
L3
L2
L1
L3
L2
L1 and so on
1700 Platform Product and Site Preparation Guide 115
Appendix B: Site Power Distribution Planning
About Grounding
About Grounding
This equipment has high leakage current. Reliable earth grounding of this equipment must be maintained.
Grounding is provided by the power plug. The ground wire in each power cord is connected to a ground terminal in the power plug. The customer must ensure that the receptacle is properly grounded.
Emergency Power Off (EPO)
Teradata cabinets do not have UPSs in their cabinets (no internal battery backup) and, therefore, do not have Emergency Power Off connections.
116 1700 Platform Product and Site Preparation Guide
APPENDIX C
Site Environmental Planning
Objectives of Site Environmental Control and
Preparation
The purpose of site environmental control and preparation (that is, for equipment placement, floor layout,
airflow delivery requirement, and so on) is to meet the specifications as described in Environmental
.
Notice:
Ensure that the cooling air at the inlets of individual chassis enclosures within each hardware cabinet
meets the environmental requirements outlined in Environmental Requirements
.
Environmental Requirements
Table 12: Environmental Specifications
Environmental Requirement Operational
Temperature (dry bulb) a
Moisture
Maximum dew point
Maximum altitude a
Vibration limit
Allowable b
: 15° to 32°C (59° to 90°F)
Recommended c
: 18° to 27°C (64.8° to 80.6°F)
Allowable:
20% to 80% (Relative humidity non-condensing)
Recommended c
:
Low end moisture: 5.5°C DP (41.9°F DP)
High end moisture: 60% RH and 15°C DP (59°F
DP)
17°C (62°F)
3050 m (10,000 ft)
0.01 G/Hz over frequency range of 7-500 Hz system will continue to operate without hard errors during and after a half sine wave show of 2
G/Hz or 11 millisecond duration
27°C
(80°F)
N/A
N/A
Storage
5° to 45°C
(41° to
113°F)
8% to 80% noncondensing
Transit
(Up to 1
Week)
-40° to
60°C
(-40° to
140°F)
5% to 95%
N/A
N/A
N/A
1700 Platform Product and Site Preparation Guide 117
Appendix C: Site Environmental Planning
Power Consumption
Environmental Requirement Operational Storage Transit
(Up to 1
Week) maximum double amplitude displacement is limited to 1.27 mm (0.05 in.) in a range from 0 to
10 Hz
4000 V direct discharge, 8000 V air discharge Static discharge limit N/A N/A a
Operating temperature and moisture level is measured at individual chassis inlet.
b
Due to lower air density at higher altitudes, the maximum dry bulb operating temperature is derated linearly by a value of 3.3° C per 1000 m (1.8° F per 1000 ft) between the altitude of 900 m (2952 ft) and 3050 m (10,000 ft).
c
The allowable environmental envelope is a statement of functionality of the equipment. The recommended environmental envelope is a statement of reliability—operating equipment near the allowable limits for long periods of time could result in increased reliability issues.
Power Consumption
Estimated Power for 1700 Cabinets
The estimated typical power for a 1700 maximum configuration (2+1 clique with two TPA nodes, one hot standby node, three disk arrays, and switches) is approximately 5.5 kW in normal operation.
The actual power consumption levels for a particular configuration may be different depending on many factors such as the hardware configuration of each chassis, the applications running at the time of measurement, and the operating temperature. For power level estimates specific to a particular configuration, contact Teradata Customer Support.
Estimated Power for BYNET Cabinets
The estimated power for BYNET cabinets with a 108-port InfiniBand switch and the maximum configuration (two TMSs, one VMS, one KVM, and two Ethernet switches) is 4,500 watts.
The estimated power for BYNET cabinets with a 162-port InfiniBand switch and the maximum configuration (three TMSs, one VMS, one KVM, and two Ethernet switches) is 4,000 watts.
The estimated power for BYNET cabinets with a 324-port InfiniBand switch and two Ethernet switches is
3300 watts typical, 4,400 watts maximum.
The actual power consumption levels for a particular configuration may be different depending on many factors such as the hardware configuration of each chassis, the applications running at the time of measurement, and the operating temperature. For power level estimates specific to a particular configuration, contact Teradata Customer Support.
118 1700 Platform Product and Site Preparation Guide
Appendix C: Site Environmental Planning
System Thermal Report
System Thermal Report
Cabinet
1700 2 + 1
Config b
BYNET cabinet with
108-Port
InfiniBand
Switch and
TMSs
BYNET cabinet with
162-Port
InfiniBand
Switch and
TMSs
BYNET
Cabinet with
324-Port
InfiniBand
Switch
ASHRAE
Class 1
Typical Heat
Dissipation
BTU/Hr a
18,800
15,400
13,700
11,300
15,100 Max
Air Flow Nominal
CFM
720
590
520
430
580 Max
m
3
/sec
0.340
0.278
0.245
0.203
0.274 Max
lb
1600
1100
Weight kg
725
500
Overall Cabinet
Dimensions
See
See
872
926
396 See
420 See
a
1 watt = 3.412 BTU/Hr.
b
1700 max configuration = Two TPA nodes, one hot standby node, 15 drive enclosures with 12 drives each, one
KVM, one VMS, two BYNET switches, two server management switches, and power hardware.
1700 Platform Product and Site Preparation Guide 119
Appendix C: Site Environmental Planning
Cooling Considerations for Installation Site
Cooling Considerations for Installation Site
About Cooling Capacity Planning
Cooling capacity planning is imperative to ensure Teradata systems perform at the expected reliability and availability levels.
Cooling capacity planning starts with Teradata providing cabinet and system power consumption or heat load estimates of hardware equipment and ends with the customer supplying sufficient cooling capacity to
Teradata equipment. The customer is responsible for providing sufficient cooling to Teradata systems to ensure Teradata equipment operates within recommended environmental specifications at all times. See
The Account Team should use the Estimator tools in Service Bulletin 502 (SB 502) to estimate the heat load of a particular Teradata system. Always use the latest version, as the tool is constantly evolving.
Disclaimer
The calculated power consumption levels are estimates only. They typically represent the worst sustained power consumption levels. The unsustained power consumption levels can be higher during system power up. The actual power consumption will differ depending on operating temperatures, applications, etc.
The calculated floor space is also an estimate only. Aisle widths may differ from one data center to another.
About Cold and Hot Aisles in Floor Layout
The system hardware employs front-to-rear air cooling technology. Cooling air enters the front of each cabinet through the openings in the doors, and heated air is exhausted from the rear of each cabinet.
Cold aisles are the aisle spaces between two rows of cabinets that face each other, front to front. A cabinet row with the front facing open space is also called a cold aisle.
Hot aisles are the aisle spaces between two rows of cabinets that are aligned rear to rear. A cabinet row with the rear facing open space is also considered a hot aisle.
The cold aisle must remain cold. Do not attempt to cool down hot aisles. They are intended to be hot, and are not an indication of environment problems. Cold aisles must remain cold, and hot aisles are supposed to remain hot.
120 1700 Platform Product and Site Preparation Guide
Appendix C: Site Environmental Planning
Floor Layouts
Floor Layouts
About Equipment Floor Layout
When designing floor layouts, it is important to consider future growth.
Equipment floor layout is determined by:
• Number of cabinets
• Power consumption levels of all cabinets
• Available floor space
• Available cold air delivery capacity, including:
∘ Cold air volume
∘ Temperature of conditioned air
∘ Cooling environment (such as open air, containment, liquid cooling, and so forth)
Use cabinet power, cooling air information, and the following charts to determine how many tiles per cabinet are required in the floor layout.
Note:
The account team should use the Supply_Air_Power_Tool in Service Bulletin 502 (SB502) to determine specific supply air requirements in relation to different floor layouts.
Figure 31: Cabinet Power and Cooling Requiring 3 Tiles Per Cabinet
1700 Platform Product and Site Preparation Guide 121
Appendix C: Site Environmental Planning
Floor Layouts
Figure 32: Cabinet Power and Cooling Requiring 4 Tiles Per Cabinet
122 1700 Platform Product and Site Preparation Guide
Figure 33: Cabinet Power and Cooling Requiring 5 Tiles Per Cabinet
Appendix C: Site Environmental Planning
Floor Layouts
1700 Platform Product and Site Preparation Guide 123
Appendix C: Site Environmental Planning
Floor Layouts
Figure 34: Cabinet Power and Cooling Requiring 7 Tiles Per Cabinet
124 1700 Platform Product and Site Preparation Guide
Appendix C: Site Environmental Planning
Floor Layouts
Hardware Placement Guidelines for Raised Floor and Open
Return Environment
Figure 35: Recommended Front-to-Front Hardware Placement on Raised Floor and Open Return Environment
Figure 36: Recommended Raised Floor Layout for Optimum Cooling and Airflow with Open Return Environment
1700 Platform Product and Site Preparation Guide 125
Appendix C: Site Environmental Planning
Floor Layouts
Cabinet alignment
Cold aisle width
Teradata hardware cabinets are designed to take in conditioned supply air or chilled air in the front, pass it over the internal heat dissipating components, and exhaust it from the rear. All hardware cabinets must be installed front-to-front (rear-to-rear).
For a single cabinet row, two vented tiles per Teradata hardware cabinet are typically required. A minimum distance of 2.4 m (8 ft)—or four floor tiles—is recommended in the cold aisles, where the fronts of two rows of cabinets face each other. Perforated floor panels or floor grills must fill the cold aisles. To meet the cold air delivery requirements for a Teradata system, wider aisle width in cold aisles may be necessary to accommodate more perforated floor panels or floor grills. All of the following must be considered in determining how to meet the environmental specifications, specifically the recommended temperature and relative humidity ranges:
• number of perforated tiles in cold aisle
• type of perforated floor panels (opening percentage)
• temperature of conditioned air
BYNET cabinet placement BYNET cabinets should be placed in the center to minimize cable lengths from node cabinets to BYNET cabinets. Leave space for additional BYNET cabinets to allow room for future growth.
To minimize cable lengths from nodes in processing/storage cabinets to InfiniBand switches in BYNET cabinets, BYNET cabinets should be placed in the center of cabinet rows or at the end of cabinet rows. The location depends on cable layout.
Hardware Placement Guidelines for Non-Raised Floor and
Containment Environment
If a Teradata system is to be installed in a containment environment or a non-raised floor environment, the site team must consult with Teradata regional installation personnel, Teradata Customer Support and
Engineering. The site team will need to prepare a detailed site survey and analysis to help the installation personnel determine the proper equipment layouts that meet the stated environmental requirements for the system.
Consider and ensure the following when designing the floor layout:
• Servicing clearances are sufficient
• Cold air requirements meet the standards established in Environmental Requirements
Include the following personnel when discussing the layout:
• Facility personnel at customer site, to discuss cold air delivery systems and other data center-related issues
• Teradata regional installation personnel, which should include assistance from Teradata Engineering
126 1700 Platform Product and Site Preparation Guide
Figure 37: Cold Air Delivery through Overhead Diffusers in an Open Environment
Appendix C: Site Environmental Planning
Floor Layouts
Figure 38: Cold Air Delivery through Overhead Diffusers in Cold Aisle Containment Environment
1700 Platform Product and Site Preparation Guide 127
Appendix C: Site Environmental Planning
Floor Layouts
Figure 39: Cold Air Delivery through Vented Tiles in Cold Aisle Containment Environment
128 1700 Platform Product and Site Preparation Guide
Figure 40: Cold Air Delivery through Vented Tiles in Hot Aisle Containment Environment
Appendix C: Site Environmental Planning
Floor Layouts
1700 Platform Product and Site Preparation Guide 129
Appendix C: Site Environmental Planning
Floor Layouts
Figure 41: Cold Air Delivery through Cabinet Front by In-Row Cooling Units in Hot Aisle Containment Environment
Best Practices for Floor Layout
Consult these illustrations to make optimum decisions for the floor plan.
Figure 42: Vented Tile Proximity to CRAC (Computer Room Air Conditioning)
130 1700 Platform Product and Site Preparation Guide
Figure 43: Cabinet Proximity to CRAC
Figure 44: Vented Tile Placement in Aisles
Figure 45: Cabinet Orientation and Cold Aisle Width
Appendix C: Site Environmental Planning
Floor Layouts
1700 Platform Product and Site Preparation Guide 131
Appendix C: Site Environmental Planning
Floor Layouts
Figure 46: Length of Cabinet Rows
Figure 47: Dropped Ceiling Return Vent Placement
132 1700 Platform Product and Site Preparation Guide
Figure 48: CRAC Placement in Relation to Cabinet Rows
Appendix C: Site Environmental Planning
Environmental Elements
Figure 49: Cabinet Placement Adjacent to Walls
Environmental Elements
How to Measure Environmental Elements
Environmental Measurement Instruments
Following are recommendations for handheld digital meters that can measure temperature, relative humidity, dew point, altitude, and airflow velocity:
1700 Platform Product and Site Preparation Guide 133
Appendix C: Site Environmental Planning
Environmental Elements
Note:
Other calibrated instruments that can measure these parameters can also be used.
• A Kestrel 4000 or similar flow meter (with memory function to log data points for predetermined time intervals)
• An Omega HHF81 or similar thermometer
About Measuring Temperature and Humidity
Temperature and humidity levels for Teradata equipment are specified in Environmental Requirements
.
These environmental specifications are identical to ASHRAE specifications and refer to air conditions at the equipment inlet. The equipment inlet for Teradata equipment is the front of the cabinet. Measurements of air temperature and humidity must be taken at the front of the cabinet.
If using one of the instrument readers recommended under
Environmental Measurement Instruments ,
orient the air flow impellers parallel to the door inlet vents, so that air going into the door opening will pass through the impellers and sensors.
The following drawing shows the positions (bottom, middle, and top) from which temperature and humidity measurements should be taken. To achieve measurement accuracy, place temperature, humidity sensors, and probes close to the vents on the front door of the cabinet, but do not allow the temperature, humidity sensors, or probes to touch any part of the door.
134 1700 Platform Product and Site Preparation Guide
Figure 50: Temperature and Humidity Measurement Locations Outside Cabinet
Appendix C: Site Environmental Planning
Environmental Elements
About Measuring Air Flow
For environmental evaluation, you may need to measure air flow rates of conditioned air entering a computer room through openings that include:
• Vented floor tiles, including both perforated tiles (typically having an overall opening area of approximately 20%), and grate tiles (typically having an overall opening area greater than 50%)
• Floor tiles with unblocked openings (such as cable cutouts)
• Cold air diffusers in overhead cold air delivery systems
1700 Platform Product and Site Preparation Guide 135
Appendix C: Site Environmental Planning
Environmental Elements
Two methods for measuring air flow rate through these openings are:
• Using an Alnor meter
• Using an air flow meter and a handmade air capture hood
The Alnor flow rate meter is a specialized instrument that can be used to directly measure air flow rate. It has an air capture hood, and is instrumented to measure air flow rate in m
3
/min. However, the
Alnor meter is relatively expensive and lacks portability, even when folded.
/s or ft
3
A cost-effective and portable method to get reasonably accurate air flow rate measurements is to use a digital air velocity meter and a handmade cardboard air capture hood.
Meter and Handmade Air Capture Hood
, and an air velocity meter set to feet per minute (fpm), the flow rate in cubic feet per minute (CFM) is the velocity reading in feet per minute (fpm). The calculation is straightforward because the top opening area is exactly one square foot (ft
2
).
Because any air capture hood restricts air flow to a certain extent, thus introducing air flow impedance and associated measurement errors, an instrument calibration is required to ensure measurement accuracy. The following correction table is the result of calibration with the hood of the preferred dimensions. If a hood of different dimensions is constructed and used, a new calibration will be required.
Air Flow Velocity (ft/min)
< 200
< 400 and > 200
< 600 and > 400
Flow Rate (ft
3
/min or CFM) Correction Factor
1.10
1.18
1.25
For example, if air flow velocity measured with an air capture hood of the preferred dimensions is 250 ft/ min, the actual flow rate is estimated to be 250 x 1.18 = 295 CFM.
If the opening is too small for a hood of the preferred dimensions, flow rates can be estimated by measuring the flow velocity and multiplying it by the open area.
To derive flow rates using units other than CFM, use the following conversion table.
From Unit
CFM
To Unit
m
3
/s
Multiply by:
1/2119
CFM m
3
/hr
1.69
For detailed information on the recommended flow meter, the dimensions and fabrication of the hood, and the correction factor, contact your local Teradata Regional Technical Specialist (RTS), Teradata Customer
Support, or Teradata Engineering.
Measuring Air Flow Rate Using an Air Flow Meter and Handmade Air Capture Hood
The following illustration shows the dimensions of a recommended air capture hood.
136 1700 Platform Product and Site Preparation Guide
Figure 51: Handmade Air Capture Hood and Measurement Locations
Appendix C: Site Environmental Planning
Environmental Elements
1. Make a four-sided cardboard air hood with two open ends:
• large end: 61 cm x 61 cm (2 ft x 2 ft) (standard floor tile size)
• small end: 30.5 cm x 30.5 cm (1 ft x 1 ft)
2. Place the hood with the large open end over a vented floor tile.
Minimize air flow leakage by sealing seams on the hood, and by pressing the hood firmly against the floor.
3. Hold the air flow meter at the small open end of the hood, in the center, to get a reading of the air velocity.
4. Convert the air velocity reading to the air flow rate.
The measurement in cubic feet per minute is:
flow rate (ft
3
/min) = flow velocity (ft/min) x area (1 sq. ft on small open end of hood)
If you need to calculate air flow rate in cubic meters per second (m
3
10
4
.
/s), the conversion factor is 4.719 x
For example, to obtain air flow rate in m
3
/sec when measured air flow rate is X ft
3
/min (CFM), multiply
X ft
3
/min by 4.719 x 10
4
: X x 4.719 x 10
4
.
1700 Platform Product and Site Preparation Guide 137
Appendix C: Site Environmental Planning
Environmental Elements
Evaluating Environmental Elements Before and After an
Installation
Teradata strongly recommends that air flow measurements be performed before and after equipment installation. As soon as the site for the system installation is confirmed and accessible, perform the initial air flow evaluations. After the equipment installation is completed, repeat the air flow evaluations to verify preinstallation measurements.
Additionally, perform temperature and humidity measurements for each cabinet after the equipment is in
.
Evaluating Air Flow
1. Before installation, lay down the vented and cutout tiles according to the floor layout.
See the top box in the figure.
138
2. Request that all dedicated computer room air conditioning (CRAC) units be turned on.
1700 Platform Product and Site Preparation Guide
Appendix C: Site Environmental Planning
Environmental Elements
This ensures that airflow characteristics above and below the raised floor are consistent before and after installation.
3. Measure the flow rate from every vented tile.
Heat load differences before and after installation produce measurement differences in temperature and humidity levels. Therefore, temperature and humidity measurements taken before installation are of limited use.
4. Measure and record flow rates from tile cutouts that do not have brush seals.
This allows you to understand the extent of air leakage.
5. Compare the flow rate through vented tiles to the chilled air requirement guidelines (see About
).
If the airflow measurements do not meet the environmental requirements, it may be necessary to rearrange the floor layout , or increase the number of vented tiles per cabinet.
6. After the equipment installation is completed, as shown in the lower box in the figure, repeat the air flow measurements to verify pre-installation measurements.
Evaluating Temperature and Humidity
Once the system is in production, take temperature and humidity measurements for each cabinet, as
outlined in About Measuring Temperature and Humidity
, to ensure that environmental requirements are met.
Even if all preinstallation requirements are met, it is still possible that hot spots exist in a data center. Since rearrangement of the cabinets at this point is probably not feasible, it is recommended to switch out existing vented tiles where appropriate with vented tiles that have a higher opening percentage.
Figure 52: Floor Tiles with Low and High Opening Percentages
About Environmental Contaminants
Electronic hardware is generally sensitive to airborne contaminants. The computer room should be designed to achieve a high level of cleanliness and to minimize airborne dusts, gasses, and vapors than can potentially impact performance and reliability of the hardware within defined limits. Failure to maintain the computer room according to the standard may result in intermittent interference and/or actual component failures.
For details of the clean room standard, refer to:
• ASHRAE HVAC Applications: Chapter 16, Clean Spaces. American Society of Heating, Refrigerating and
Air Conditioning Engineers, Inc. 2003 http://www.ashrae.org/
• 2011 Gaseous and Particulate Contamination Guidelines for Data Centers
1. Go to http://www.ashrae.org/ .
1700 Platform Product and Site Preparation Guide 139
Appendix C: Site Environmental Planning
Environmental Elements
2. Search for contamination.
3. Open the 2011 Gaseous and Particulate Contamination Guidelines for Data Centers PDF file.
For particulate (dust) contamination, ASHRAE recommends that data centers be kept clean to ISO 14644-1
Class 8, which may be achieved simply by specifying the following means of filtration:
• The room air may be continuously filtered with MERV 8 filters, as recommended by ASHRAE Standard
127 (ASHRAE 2007).
• Air entering a data center may be filtered with MERV 11 or MERV 13 filters as recommended by
ASHRAE (2009b).
For gaseous contamination, ASHRAE recommends that data center operators maintain an environment with corrosion rates within the following guideline per ISA-71.04 (ISA 1985):
• Copper reactivity rate of less than 300 Å/month
Further, due to limitations from copper reactivity, ASHRAE recommends the addition of the following guideline in addition to the above copper reactivity rate:
• Silver reactivity rate of less than 200 Å/month
140 1700 Platform Product and Site Preparation Guide
Download
Advertisement
Key features
High-performance data warehouse and analytics platform
Handles large volumes of data
User-friendly interface
Powerful query engine
Scalable and flexible
Cost-effective
Reliable and secure
Industry-leading support
Frequently asked questions
The 1700 Platform has specific environmental requirements, such as temperature, humidity, and power. You can find more detailed information about these requirements in the document. It's important to ensure the site is prepared according to these requirements before installing the equipment.
The document provides a detailed list of site preparation tasks, including electrical wiring, mechanical systems, floor coverings, and environmental systems. It's important to carefully review and follow these guidelines to ensure a smooth and successful installation.
The document provides guidelines for floor layouts, including placement of cabinets and cooling systems. These layouts are designed to ensure optimal cooling and airflow, which are essential for the performance and reliability of the system.
The document provides instructions on how to safely uncrate, position, and install the 1700 Platform. It's important to follow these instructions carefully and use appropriate safety equipment.
The BYNET network is a high-speed interconnect that provides communication between the nodes of the 1700 Platform. It is essential for data transfer and system performance. The document describes the BYNET network topology and configurations.