NAMCO PAC-MAN BASKET: Get ready to experience a thrilling basketball challenge with the all-new arcade machine! With its innovative design and immersive gameplay, this machine offers an unforgettable gaming experience for players of all skill levels. Engage in exciting matches against the computer or challenge your friends to a competitive showdown on the court. The machine's user-friendly interface and intuitive controls make it easy for anyone to pick up and play, while its durable construction ensures long-lasting enjoyment.
বিজ্ঞাপন
বিজ্ঞাপন
Table of Contents
Special note .............................................................................................................................3
Maintenance and Inspection....................................................................................................3
I.Inspection ..............................................................................................................................3
1.Parts list...........................................................................................................................4
2.Half-Assembly type parts list ...........................................................................................5
II.Machine view/size and power rating .....................................................................................6
III.Component description........................................................................................................6
IV.Assembly and disassembly..................................................................................................7
1. Assembly and disassembly for Disassembly type ..........................................................7
2. Assembly and disassembly for Half-Assembly type......................................................17
3.
SET-UP Position & maintenance ............................................................................24
V.Adjustment and Inspection .................................................................................................24
1.Link adjustment .............................................................................................................25
Cable link SET-UP .....................................................................................................25
Link main board adjustment ......................................................................................26
2.Adjustment ....................................................................................................................27
SET-UP 1 SET-UP the coin entry price for each game ...........................................27
SET-UP 2 Additional tickets.....................................................................................28
SET-UP 3 Multiple of tickets....................................................................................28
SET-UP 4 Game Time SET-UP...............................................................................29
SET-UP 5 Basket motor AUTO test.........................................................................30
SET-UP 6 Ball holder motor AUTO test...................................................................30
SET-UP 7 Reset the top score 250 or keep the record ...........................................30
SET-UP 8 SET-UP DEMO music ON or OFF ...................................................30
3.LED Monitor inspection .................................................................................................31
4.AUDIT............................................................................................................................31
5.Error code......................................................................................................................32
VI.How to play........................................................................................................................33
1.There are total 4 Stages................................................................................................33
2.2 play types available ....................................................................................................33
VII.Screw and Nut list ............................................................................................................34
VIII. Wires Layout ..................................................................................................................36
IX.Expanded view ..................................................................................................................38
- 2 -
Special note
We would like to thank you for choosing our Street basketball machine,
Please read this manual before using this product to insure the security of the user.
This Manual contains the characteristics, special notes, and a simple breakdown of the product.
Maintenance and Inspection
■ Keep the machine clean by using mild types of cleaners.
■ Clean the machine regularly to maintain its appearance.
■ The appliance must not be cleaned by a water jet.
■ Treat acrylic with care by using Windex
Machine position regulation
The power must be turned off before any movement.
The brake must be released, before moving the machine.
Do not put the machine under direct sunlight, it will damage the inside parts.
I.Inspection
Before product use, please confirm the product content first, if anything is missing, please contact us right away.
NO Items Specification Total quantity
1 Chassis items Packing 1 unit
2 Basketball
3 Key
4 Key
5 AC cable line
6 Operation manual
No.5 Basketball
Maintenance door
Cash box
A4
10 unit
1 pc
1 pc
1 unit
1 set
- 3 -
1.Parts list
1A Sensor for basket
(WO-RNPW2 )
1B Basket kits 2A Basket board 2BR Back right net stander kit
2BL Back left net stander kit
2C 2 Front net stander bridge(short)
2E 2 Front net stander bridge(long)
3A Front right net stander kit
4A Base holder BF 4B Base holder FB 4C Base holder FF
4E Base holder FF
(Bottom)
5A Wooden board
A type
5B Ball holder kit
6A Ball net holder kit 6B Main part
3B Front left net stander kit
4D Base holder BB
5C Ball guide kits
6C Block wooden board for motor
6E Rubber pad
Top cover Metal Shelf (optional) Lower Side Net (Frame
Included)×4
Basketball
- 4 -
2.Half-Assembly type parts list
Main frame 4B Base holder FB
4C Base holder FF
Top cover
Lower Side Net(Frame Included)×4
5C Ball guide kits 6A Ball net holder kit
5B Ball holder kit
6B Main part
6C Block wooden board
for motor
Basketball Metal Shelf (optional)
- 5 -
II.Machine view/size and power rating
Machine Dimensions W1030×D2500×Top cover H2643mm
Weight 260 kg / 558.4 lbs (Accessories not Included )
Top cover 6.6kg
Metal Shelf 3.4kg
Lower Side Net 4.2kg×4
Voltage AC110V~120V/AC220V~240V(50/60Hz) Use Electrical
plug display as a guide Located behind the machine.
Power Consumption 200W
Fuse 3A
Token size Ø22mm~27mm
III.Component description
Left
Position direction
Back
Front
Right
Front Top Base
Basket board
Top cover(optional)
Running display board
2 Digital display board LED
Basket kit
Metal Shelf
(optional)
IC Board
Power
Test Audit
Fuse
3 Digital display board LED
Coin LED display
Ticket dispenser
Coin selector
Ticket container (inside)
Cash box(inside)
Speaker
Ball holder kit
Back Side
I/O control Board Board cover
Basket cover
Box cover
Main part
AC Cable line
Electrical plug display
Lower Side Net (Frame Included)×4
- 6 -
IV.Assembly and disassembly
1. Assembly and disassembly for Disassembly type
Step 1
1.Screw
Lower Side Net (optional) on the basket board front.
Assembly parts
2BR Back right net stander kit
2BL Back left net stander kit
3A Front right net stander kit
3B Front left net stander kit
Lower Side Net(Frame Included)
P.35 NO.32 screw(M4×10)×10
P.35 NO.32 screw(M4×10)×10
- 7 -
Step 2
1.Screw
1B Basket kits on the basket board front.
Assembly parts
1A Sensor for basket
1B Basket kits
2A Basket board
P.34 NO.13 screw(M5×15)×6
P.35 NO.21 nut(M5)×4
- 8 -
Step 3
1. Screw 2BR 2BL Back left & right net stander kits on basket board left and right.
2. Screw 2C Front net stander bridge(short) on Back left & Right net stander kits.
Assembly parts
Insert position
2A Basket board
2BR Back right net stander kit
2BL Back left net stander kit
2C Front net stander
bridge(short)
P.35 NO.33 screw (M8×70)×4
P.35 NO.19 nut (M8)×4
- 9 -
P.34 NO.10 screw (M6×48)×2
P.35 NO.20 nut (M6)×2
Step 4
Assemble 3A 3B Front right & left net stander kit on basket board left and right, connect with screw & fixed it as drawing.
Insert position
Assembly parts
3A Front right net stander kit
3B Front left net stander kit
- 10 -
P.35 NO.33 screw (M8×70)×4
P.35 NO.19 nut (M8)×4
Step 5
Screw the BF FB FF Base holders & Front net stander bridge(short) step by step as drawing.
Assembly parts
Base holder BB
Front net stander bridge(short)
BF
FB
2C Front net stander
bridge(short)
2E 2 Front net stander bridge(long)
4A Base holder BF
4B Base holder FB
4C Base holder FF
4D Base holder BB
4E Base holder FF
(Bottom)
FF
P.34 NO.10 screw (M6×48) ×9
P.35 NO.20 nut (M6)×9
P.35 NO.30 washer(M6.5×13.5)×9
P.34 NO.10 screw (M6×48)×6
P.35 NO.20 nut (M6)×6
- 11 -
P.34 NO.11 screw (M6×26)×2
P.35 NO.20 nut (M6)×2
Step 6
Screw the 5A Wooden base A type 5B Ball holder kit 5C Ball guide kits step by step as drawing.
6E Rubber pad
Wooden base A type
6E Rubber pad
Ball holder kit
Ball guide kits
Assembly parts
5A Wooden board A type
5B Ball holder kit
5C Ball guide kits
6E Rubber pad
P.34 NO.10 screw (M6×26) ×6
P.35 NO.20nut(M6) ×6
P.35 NO.30washer(M6.5×13.5) ×6
- 12 -
P.34 NO.11 screw (M6×26)×12
P.35 NO.20 nut (M6)×12
P.35 NO.30 washer(M6.5×13.5) ×12
Step 7
1. Screw 6A Ball net holder kit .
2. Screw 6B Main part Metal Shelf (optional) .
Assembly parts
6A Ball net holder kit
6B Main part
Metal Shelf (optional)
Ball net holder kit
Metal Shelf (optional)
Main part
P.35 NO.31
Hexagonal Phillips screw with 2
Washers included 2 on each side
P.34 NO.08 screw (M8×16)×4
P.35 NO.19 nut (M8)×4
P.35 NO.30 washer(M10×20)×4
- 13 -
P.34 NO.04 screw (M8×88)×4
P.35 NO.19 nut(M8)×4
P.35 NO.27 sleeve( 15×43)×4
Step 8
1.Fix the 3 main cords as the following drawing.
2.Run the IC board plug and the ball holder kit plug located underneath the front of the ball net holder, through the hole in back of the main part.
3.Now connect plugs as shown in drawing.
Main cords
Ball holder kit
Ball holder kit plug
Open main box base cover
IC board plug
Power plug
- 14 -
Step 9
Screw Top cover(optional) step by step as drawing.
Top cover(optional)
Assembly parts
Top cover(optional)
P.35 NO.28 screw (M5×38)×4
P.35 NO.29 Nut(M5)×4
Step 10
1.connect the I/O control board with Top cover.
2.Now connect plugs as shown in drawing.
I/O control Board
Top cover
Insert position
- 15 -
Step 11
Use screws to fix it then complete the assembly street basketball.
Assembly parts
6C Block wooden board
for motor
Block wooden board for motor
P.35 NO.20 nut(M6)×4
- 16 -
2. Assembly and disassembly for Half-Assembly type
Step 1
Turn the left and right frame180°to the position as drawing picture . connect with screw & fixed it as drawing.
P.35 NO.33 screw (M8×70)×4
P.35 NO.19 nut (M8)×4
- 17 -
Step 2
Screw the base frame FB and base frame FF as drawing picture.
Assembly parts
4B Base holder FB
4C Base holder FF
FB
FF
P.34 NO.11 screw (M6×26)×2
P.35 NO.20 nut (M6)×2
P.34 NO.10 screw (M6×48)×4
P.35 NO.20 nut (M6)×4
- 18 -
Step 3
Screw the 5B Ball holder kit and 5C Ball guide kits as drawing picture.
Assembly parts
5B Ball holder kit
5C Ball guide kits
Ball holder kit
Ball guide kits
- 19 -
P.34 NO.11 screw (M6×26)×12
P.35 NO.20 nut (M6)×12
P.35 NO.30 washer(M6×26)×12
Step 4
1. Screw 6A Ball net holder kit .
2. Screw 6B Main part Metal Shelf (optional) .
Assembly parts
6A Ball net holder kit
6B Main part
Metal Shelf (optional)
Ball net holder kit
Metal Shelf (optional)
Main part
P.35 NO.31
Hexagonal Phillips screw with 2
Washers included 2 on each side
P.34 NO.08 screw (M8×16)×4
P.35 NO.19 nut (M8)×4
P.35 NO.30 washer(M10×20)×4
- 20 -
P.34 NO.04 screw (M8×88)×4
P.35 NO.19 nut(M8)×4
P.35 NO.27 sleeve( 15×43)×4
Step 5
1.Fix the 3 main cords as the following drawing.
2.Run the IC board plug and the ball holder kit plug located underneath the front of the ball net holder, through the hole in back of the main part.
3.Now connect plugs as shown in drawing.
Main cords
Ball holder kit
Ball holder kit plug
Open main box base cover
IC board plug
Power plug
- 21 -
Step 6
Screw Top cover(optional) step by step as drawing.
Top cover(optional)
Assembly parts
Top cover(optional)
P.35 NO.28 screw (M5×38)×4
P.35 NO.29 Nut(M5)×4
Step 7
1.connect the I/O control board with Top cover.
2.Now connect plugs as shown in drawing.
I/O control Board
Top cover
Insert position
- 22 -
Step 8
Use screws to fix it then complete the assembly street basketball.
Assembly parts
6C Block wooden board
for motor
Block wooden board for motor
P.35 NO.20 nut(M6)×4
- 23 -
3.
SET-UP Position & maintenance
50CM(20’’)
Fix position after assembly
1.Hoist the machine from the hoist point.
2.Keep at least 50cm(20”) space from the back for maintenance and to avoid over heating.
Electrical plug display
Attention:
The power must be turned off before any movements.
Check the power rate before use AC110V~120V/AC220V~240V ,
Check Electrical plug display as a guide.
V.Adjustment and Inspection
You can find the audit system by opening the main part door.
IC board includes power fuse audit and test functions
Please see 1 Link adjustment for IC board function.
- 24 -
1.Link adjustment
Cable link SET-UP
The link set-up must follow DIP-SW-SEP-UP N0.1~15 machines.
Intermittent allowed, but cannot repeat.
A . Link up to 15 machines
B . Only one main frame is needed.
C . Any game could be used as the main frame.
Link Plug connect
Link Plug connect The link machines must stand side by side
The main part back view
Link sub-board
DIPSW
PC Board
Link sub-board
DIPSW
PC Board
Link sub-board
DIPSW
PC Board
Link PC board
Link sub-board
The link machines must stand side by side
The main part front view
P.S. If two link machines-2 PCB are connected, the main control one DIP-SW must be set as OFF OFF OFF ON.
- 25 -
Link main board adjustment
Multi-function button
1.Press and turn on the power, for TEST function.
2.In Standby mode is SERVICE function, Press once means one coin, but No record.
3.In audit mode is RESET function.
4.In ticket dispenser error mode, press is Key out function.
Link DIP-SW adjustment
SW4 SW3 SW2
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
ON
ON
ON
ON
ON
ON
ON
ON
OFF
OFF
ON
ON
OFF
OFF
ON
ON
OFF
OFF
ON
ON
OFF
OFF
ON
ON
OFF
OFF
OFF
OFF
ON
ON
ON
ON
OFF
OFF
OFF
OFF
ON
ON
ON
ON
OFF
ON
OFF
ON
OFF
ON
OFF
ON
OFF
ON
SW1
OFF
ON
OFF
ON
OFF
ON
Single mode link 1 Unit link 2 Unit link 3 Unit link 4 Unit link 5 Unit link 6 Unit link 7 Unit link 8 Unit link 9 Unit link 10 Unit link 11 Unit link 12 Unit link 13 Unit link 14 Unit link 15 Unit
Single mode starting display
_ _ _
XXXXXX
_ 0 C X X
Displays Company logo
Program type(CXX type)
Single mode(switch all DIP-SW off)
- 26 -
Link mode starting display
L I N E – T E S T
_ _ _ X X C X X
Program type(CXX type)
Link mode station NO,(XX=1-15)
When you turn on the main control machine, the other machines will link as set situation.
2.Adjustment
L I N E – T E S T after done the test can enter the set up.
Press and turn on the power, release the key after you hear the sound.
SET-UP 1 SET-UP the coin entry price for each game
Press
Press
Press
Press
1 – C O I N Alternately 1 – P L A Y
_ _ 1 _ _ _ _ 1 1 _ _ _ _ _ _ 1
then release
2 – C O I N Alternately 1 – P L A Y
_ _ 1 _ _ _ _ 2 1 _ _ _ _ _ _ 2
then release
3 – C O I N Alternately 1 – P L A Y
_ _ 1 _ _ _ _ 3 1 _ _ _ _ _ _ 3
then release
4 – C O I N Alternately 1 – P L A Y
_ _ 1 _ _ _ _ 4 1 _ _ _ _ _ _ 4
for then release to enter SET-UP 2
- 27 -
SET-UP 2 Additional tickets
Press
Press
Press
Press
M I N – O U T
_ _ 2 _ _ _ _ 0
0 ticket dispensed after every game is ended
then release
_ _ 2 _ _ _ _ 1
Each time game over
Release 1 additional tickets
then release
_ _ 2 _ _ _ _ 2
Each time game over
Release 2 additional tickets
then release
_ _ 2 _ _ _ _ 3 Each time game over
Release 3 additional tickets
for 1 second then release to enter SET-UP 3
SET-UP 3 Multiple of tickets
Press
Press
Press
Press
Press
Press
T I C K E T
_ _ 3 _ _ _ 0 0
then release
_ _ 3 _ _ _ 1 0
then release
_ _ 3 _ _ _ 2 0
then release
_ _ 3 _ _ _ 3 0
then release
_ _ 3 _ _ _ 4 0
then release
_ _ 3 _ _ _ 5 0
then release
_ _ 3 _ _ _ 6 0
No ticket, game play only
SET-UP 2 is ineffective.
10 points 1 ticket
20 points 1 ticket
30 points 1 ticket
40 points 1 ticket
50 points 1 ticket
60 points 1 ticket
- 28 -
Press
Press
then release
_ _ 3 _ _ _ 7 0
then release
_ _ 3 _ _ _ 8 0
70 points 1 ticket
80 points 1 ticket
Press then release
_ _ 3 _ _ _ 9 0 90 points 1 ticket
Press then release
_ _ 3 _ _ 1 0 0 100 points 1 ticket
The explanation
If the operator sets the game for 3____10 and the game is giving out tickets the player will receive 1 ticket for every 10 points scored . If the operator sets the game for 3____20 the player will get 1 ticket for every 20 points scored and so on.
For additional (0-3) tickets enter SET-UP 2
Press for 1 second then release to enter SET-UP 4
SET-UP 4 Game Time SET-UP
GAME - TIME
_ _ 4 _ _ _ 5 0
Stage 1 50 seconds
Stage 2 40 seconds
Stage 3 30 seconds
Stage 4 20 seconds
_ _ 4 _ _ _ 5 5
Stage 1 55 seconds
Stage 2 45 seconds
Stage 3 35 seconds
Stage 4 25 seconds
_ _ 4 _ _ _ 6 0
Stage 1 60 seconds
Stage 2 50 seconds
Stage 3 40 seconds
Stage 4 30 seconds
for 1 second then release to enter SET-UP 5 Press
- 29 -
SET-UP 5 Basket motor AUTO test
Press
Press
STE–MOT-1
_ _ 5 _ _ _ _ _
then release-Start basketball motor AUTO test
(Warning alarm will start after 5 seconds, if there is an error)
for 1 second then release to enter SET-UP 6
SET-UP 6 Ball holder motor AUTO test
Press
Press
STE–MOT-2
_ _ 6 _ _ _ _ _
then release-Start ball holder motor AUTO test
(Warning alarm will start after 5 seconds, if there is an error)
for 1 second then release to enter SET-UP 7
SET-UP 7 Reset the top score 250 or keep the record
Press
Press
XXXXXX
Displays Company logo
_ _ 7 _ _ _ _ _
Reset the top score to 250
then release
XXXXXX Displays Company logo
_ _ 7 _ _ _ _ 1
Keep the record
then release to enter SET-UP 8
SET-UP 8 SET-UP DEMO music ON or OFF
XXXXXX Displays Company logo
_ _ 8 _ _ _ _ _
DEMO music OFF
- 30 -
Press then release
XXXXXX
Displays Company logo
_ _ 8 _ _ _ _ 1
DEMO music ON
Restart the Machine to complete the SET-UP adjustment.
3.LED Monitor inspection
Testing
1. Press and turn on the power at the same time to enter LED testing mode.
Release the test button after it displays ”1” on the LED.
2.Check if the LED is displayed correctly.
3.When testing is finished you will enter the standby mode.
XXXXXXXX
LED test function display
LED displays Company logo, from right to left.
LED display 1 2 3 4 5 6 7 8 9 ,color test change from red green then orange .
Coin LED display 1 2 3 4 5 6 7 8 9 , color test red .
4.After AUTO test is finished, it will enter standby mode.
4.AUDIT
Press
Press
enter audit system in standby function only.
then release, enter audit 1
COUNT - IN
1 C X X X X X X
Record total received
Coins up to 999999 same as counter, counter reset is not allowed.
Press then release, enter audit 2
COUNT - OUT
2 C X X X X X X
Record total dispensed tickets
Tickets up to 999999 same as counter, counter reset is not allowed.
- 31 -
Press then release, enter audit 3
SHIFT - IN
3 C X X X X X X
Record total received
Coins up to 999999, counter reset is allowed.
Press
Press
then release, enter audit 4
SHIFT - OUT
3 C X X X X X X
Record total dispensed tickets up to 999999, counter reset is allowed.
then release, return back to audit function The end
XXXXXX
Displays Company logo
_ _ _ 5 5 _ _ _
Press then release, enter into standby function.
Press then release, return back to audit 3 function. And reset the audit
3 and audit 4 .
5.Error code
Every time machine is turned on it will do the AUTO test for 7 function points, before entering standby mode.
The Error specification as below,
Error 1 C O I N – 1
Warning alarm action
Left coin selector is disconnected
Left coin selector didn’t turn in to NC
Left coin selector error
Error 2 C O I N – 2
Warning alarm action
Right coin selector is disconnected
Right coin selector didn’t turn in to NC
Right coin selector error
Error 3 SET-MOT – 1
Warning alarm action
Basket motor power is disconnected
Basket SENSOR-NO
Basket is out of position
- 32 -
Error 4 SET-MOT – 2
Error 5 T I C K E T
Error 6 COUNT - IN
Error 7 COUNT-OUT
VI.How to play
Warning alarm action
Ball holder motor power is disconnected
Ball holder SENSOR-NO
Ball holder is out of position
Warning alarm action
Ticket dispenser is disconnected
Ticket dispenser adjustment error No tickets
Press for clean tickets.
Warning alarm action
Coin counter is disconnected
Coin counter error
Warning alarm action
Ticket counter is disconnected
Ticket counter error
1.There are total 4 Stages
A.Stage 1 Proceed to Stage 2,when the total scores are over 40 in the end.
B.Stage 2 Proceed to Stage 3,when the total scores are over 150 in the end.
C.Stage 3 Proceed to Stage 4,when the total scores are over 250 in the end.
D.Stage 4 Final challenge, the last game will be finished when the time is terminated.
2.2 play types available
A.Single play DIP-SW set to single play.
B.Link mode DIP-SW set to link mode, up to 15 machines can be linked.
Press link mode, display link countdown time, any other machine can be linked together during the countdown. In link mode, up to
15 machines can be linked.
When the machine is in standby mode, the SW is ineffectual.
- 33 -
VII.Screw and Nut list
NO picture Specification
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17 screw(M4×12) screw (M4×10) screw (M3×5) screw(M8×88) screw (M5×20) screw (M5×20) screw (M5) screw(M8×16) screw (M6×55) screw (M6×48) screw (M6×26) screw (M6×16) screw (M5×15) screw (M4×15) screw (M4×12) screw (M4×8) screw (M3×12)
- 34 -
Total quantity
68
21
Position set set
26
4
8 set
Knock down machine Step 7
Semi-assemble machine Step 4 set
8 set
4
4
1 set
Knock down machine Step 7
Semi-assemble machine Step 4 set
14 Knock down machine Step 3.5.6
12 Semi-assemble machine Step 2
20 Knock down machine Step 5.6
14 Semi-assemble machine Step 2.3
16 set
58
8
6 Knock down machine Step 2
4 set
2 set set set
NO picture
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
Specification screw (M3×10) nut(M8) nut (M6) nut (M5) nut (M4) nut (M6) nut (M5) nut (M4) nut (M3) sleeve 15×43) screw (M5×38) washer(M4×12) washer ( M6.5×13.5
)
Hexagonal Phillips screw will 2 Washers screw (M4×10) screw (M8×70)
- 35 -
Total quantity
1
Position set
16 Knock down machine Step 4.7
12 Semi-assemble machine Step 1.4
38 Knock down machine Step 3.5.6.11
20 Semi-assemble machine Step 2.3.8
6 Knock down machine Step 2
20
4
8
44
7 set set set set set
Knock down machine Step 7
4
Semi-assemble machine Step 4
4
4
Knock down machine Step 9
Semi-assemble machine Step 6
Knock down machine Step 9
Semi-assemble machine Step 6
24 Knock down machine Step 6.7
12 Semi-assemble machine Step 3.4
4
Knock down machine Step 7
Semi-assemble machine Step 4
48 Knock down machine Step 1
8 Knock down machine Step 3.4
4 Semi-assemble machine Step 1
VIII. Wires Layout
Basketball Wire diagram
- 36 -
- 37 -
IX.Expanded view
Item Name
1 Basket acrylic board (Namco)
2 Wooden basket board
3 Main wooden board
4 I/O control board
5 Running display board
6 3 Digital display board
7 2 Digital display board
- 38 -
Part Number
1121-13800102
2246-13800501
1134-13801701
2213-13800101
2212-13800201
2212-13800401
2212-13800301
Quantity
1
1
1
1
1
2
1
Item Name
1 Frame for main wooden board fix use
2 Board cover
3 Basket cover
4 Box cover
- 39 -
Part Number Quantity
1132-13800601 1
1134-13800402
1134-13800102
1134-13809301
1
1
1
Item Name
1 Wooden board for basket unit fix use
2 Bearing
3 Bearing (6002ZZ)
4 Sensor 1.1
5 Sliding railway for sensor
6 Bearing D-Type for Basket
7 Sliding railway for basket
8 Bearing cover
9 Basket motor holder
10 Basket holder
11 Basket left holder
12 Basket right holder
13 Connecting rod for basket unit
14 Gear motor (KGB-215-8130B1)
15 Basket position board
Part Number Quantity
1134-13801101 1
1151-13800301
1243-13800101
2213-13800301
1134-13802901
1151-13800101
9
9
1
1
1
1134-13801601
1132-13802601
1132-13801101
1132-13801431
1132-13802701
1132-13802801
1134-13801001
0912-00001061
1134-13803001
1
1
1
1
1
2
2
1
1
- 40 -
1
7
6
2
5
3
Item
1 Basket net kit
Name
2 3M reflection sticker
3 Sensor for basket (WO-RNPW2)
4 Basket sensor railway
5 Bearing
6 Bearing (6002ZZ)
7 Holder for basket sensor
4
Part Number Quantity
1134-13800741 1
1032-13800941
0955-13800001
1134-13807141
1
2
1
1151-13800301
1243-13800101
1132-13801331
2
2
1
- 41 -
Item
1 Hole type cover
Name
2 Link Sub IC Board
3 Main box base
4 The door of speaker
5 Main part (Namco)
6 Main part acrylic board (Namco)
7 1P playpush button
8 Single main IC board
9 2P playpush button
10 Transformer 220V/110V 2A
11 Transformer 110V/15V 3A*2
12 Transformer 110V/15V 3A*2
13 The knob for wooden box
14 Base for transformer fixed use
15 Castor
16 3 in 1 door (Namco)(UK)
17 Ventilation duct of speaker box
18 Speaker
19 Speaker box
20 Cover for IC board (SEGA)
21 Coin display board
- 42 -
Part Number Quantity
1121-13800201
2215-13800201
1134-13850631
1121-13800301
1
1
1
1
1112-13800102
1121-13800202
2943-18000201
2211-13800101
2943-18000201
0923-10000191
0923-10000181
0923-10000181
1119-00000001
1134-13801502
1155-00010111
2931-03000202
1
1
1
1
4
1
1
1
1
1
1
1
1294-00000202
0931-10000015
2246-13800401
1134-13850641
2212-13800101
1
1
1
1
1
Item Name
1 Coin selector – RM5
2 Coin door with hinge (Namco)(UK)
3 Variable resistor 10K 3P
4 Counter
5 Audit push button (Red)
6 Ship-Type switch
7 Socket for counter (Namco)
8 Filter YG03T5 (3A)
9 Fuse R3-11 20mm
10 Ticket control board
11 Ticket container
12 Ticket dispenser((DL-1275)SA
13 Frame of 3 in 1
14 Ticket door with hinge
15 Cash box door with hinge
16 Cash box
- 43 -
Part Number Quantity
2931-00000202 1
1634-03000101
0106-00001001
0922-00001081
0944-00000091
0944-00000141
1
1
2
2
1
1134-13801602
0924-00000101
0974-00001001
2213-13100201
1134-19300051
2331-51400101
1134-03000602
1134-03000702
1134-03000802
1134-19300081
1
1
1
1
1
1
1
1
1
1
Item Name
1 Wooden board B-type
2 Base of ball holder unit
3 Ball holder kit
4 Hinge for ball holder (650*46.6)
5 Gear Motor KGB-215-6130B1
6 Motor Frisked for ball holder kit
7 Bearing D-Type for ball holder
8 Ball holder bearing
9 Arm of ball holder
10 SENSOR 1.1
11 Bearing LF-1040
12 Bracket for ball holder sensor fixed use
Part Number Quantity
2246-13800201 1
1134-13800801
1134-13800901
1134-13803301
0912-00001061
1132-13800901
1
1
1
1
1
1151-13800201
1134-13804201
1134-13802501
2213-13800301
1243-13800301
1132-13803001
1
1
1
1
2
1
- 44 -
- 45 -
ডাউনলোড
বিজ্ঞাপন