Sight Tube Kit
(360-966-15)
WARNING
Turn off and Lockout/Tagout (LOTO) power before servicing.
Tools Required:
11/16" wrenche or adjustable wrenche
5/8" wrenche or adjustable wrenche
Procedure:
1. Remove the old sight tube by loosening and removing the 2 swaglock elbows from tank stub tubes using an 11/16 and 5/8 wrench.
2. To assemble the new tube you need to remove one side of each new swagelock elbow. The other side of the elbow you need to take apart and reassemble as follows.
a. Slide the nut portion on the tube with the threads facing the ends of the tube.
b. Install the brass back ferrule on next with the wider part on first.
c. Install the TEFLON front ferrule next with the larger end going on first. Note you are not using the brass front ferrule on the tube you are replacing it with the Teflon one.
See drawing below for an example.
d. Install brass insert into each end of tube.
e. Assemble the elbow pieces to each end of the tube until they are hand tight.
- 87 -
f. Slide the other end of the elbows onto the tank stub tubes and tighten finger tight. With the wrenches hold the elbows straight and tighten the nut about and
1/8 of a turn no more than a ¼ of a turn.
g. Tighten the nuts on the tube side 1 ¼ turns from hand tight.
Back ferrule Front ferrule
- 88 -
advertisement
* Your assessment is very important for improving the workof artificial intelligence, which forms the content of this project
Related manuals
advertisement
Table of contents
- 4 After-sale Support
- 4 Warranty
- 6 Warnings
- 7 EMO Circuit
- 7 Lockout/Tagout (LOTO)
- 8 Error Code Troubleshooting
- 21 VFD Faults
- 23 Monitoring Fluid Loss
- 24 FRU List
- 41 Electrical Components
- 43 Control Box Assembly
- 44 Keypad
- 45 Dryer Tube
- 46 Fill Port Screen
- 47 HFE Filter Bag Kit
- 52 Pump Inline Dryer
- 53 Tank Level Switch
- 58 Temperature Control Valve Assembly
- 63 Temperature Control Valve Actuator
- 64 Water Flow Transducer
- 65 HFE Side Temperature Sensor (rtd1)
- 66 Pressure Transducers
- 67 Drip Pan Level Switch Kit
- 68 Pressure Regulator
- 70 Plumbing, Pressure Regulator to Temperature Control Valve
- 71 Plumbing, Facility Inlet Pipe
- 72 H2O Side Temperature Sensor (rtd2)
- 73 Return Pipe Assembly, Process Flow
- 75 Supply Pipe Assembly, Process Flow
- 77 PRV Cartridge
- 78 VFD Filter, Contactor, Transformer
- 79 EMO Thermostat
- 81 VFD Settings
- 82 Circuit Breaker
- 83 Temp Option Board
- 84 Chip Replacement
- 85 TC-400 Controller
- 87 LON Adapter Board
- 88 Sight Tube Kit
- 90 Torque Specification Sheet
- 91 Swagelok Tube Fitting Instructions
- 94 Main Loop
- 95 Engineering Loop
- 96 Factory Reset