Commissioning
The installer must complete the installation and commissioning checklist below and make sure this guide is left with you. They must also instruct you in the use and care of the Neo, and make sure you understand the safety instructions and operation of the appliance.
WARNING
The glass dress guard fitted to this appliance reduces the risk of fire and injury and no part of it should be permanently removed.
Checklist
F
Appliance positioned in a suitable location (clearances, mantels and surrounds etc.).
F
Rinnai flue system installed and tested to ensure effective draw.
F
Gas pressure checked and set.
F Burn media installed as per instructions.
F
Glass dress guard fitted and customer advised not to remove.
F
Appliance tested for correct operation and to ensure no gas leaks.
F
Customer instructed on operating procedure and safety requirements.
F Customer advised to service the heater every two years.
20
| Neo operation guide: 11907-D 04-13