3.1.2 Checking the condensate siphon and refill with clean water to the mark.
fig. 50 Checking the condensate siphon
59970LTGBW7H0234
3 to 4 mm
>1 min fig. 51 Checking the ignition electrode
59970LTGBW7H026
3.1.3 Checking the ignition electrode
- deposits (remove any white deposits with abrasive cloth);
- the adjustment of the ignition electrode (between 3 and 4 mm);
- the quality of the gasket and condition of the porcelain
(this should not be cracked); code fl, see par. 2.10.6.
If the read-out value is lower than 3 or higher than 9μA, check cable and connections are sound if OK replace the ignition electrode.
The ignition cap is fixed on the ignition electrode and therefore cannot be removed.
40
advertisement
* Your assessment is very important for improving the workof artificial intelligence, which forms the content of this project
Related manuals
advertisement
Table of contents
- 4 INTRODUCTION
- 5 1 SAFETY
- 5 1.1 General safety
- 5 1.2 Safety during assembly and installation
- 7 2 INSTALLATION
- 7 2.1 Scope of delivery
- 7 2.2 Mounting the boiler
- 7 Installation / maintenance clearance requirements
- 8 Dimensions and connection points
- 9 Mounting the Remeha Avanta
- 9 2.3 Water-side connections
- 9 Water flow
- 9 System Pump
- 10 Pressure loss of the boiler
- 10 Open-Vented System
- 10 Sealed systems
- 10 Additional guidelines for the domestic and CH water
- 11 Water treatment
- 12 Safety valve discharge
- 12 Draining Provision
- 12 Connecting the ‘CH return
- 12 Connecting ‘CH flow
- 13 Connecting condensate drain
- 13 2.4 Gas-side connections
- 13 Additional guidelines for gas connections
- 13 Adjusting boiler to other gas-type
- 14 Connecting the gas supply
- 14 2.5 Flue terminal and air supply connections
- 14 Flue terminal positions
- 16 Room sealed flue
- 16 Connecting the flue terminal and air supply
- 17 2.6 Electrical connection
- 17 The control unit
- 18 2.7 Connecting external controls
- 21 Connecting an outside temperature sensor
- 22 Connecting the DHW sensor/thermostat
- 22 Connecting a three-way valve
- 22 Connecting a frost thermostat
- 23 Connecting an external interlock
- 24 Connecting a PC/PDA
- 24 2.8 Connecting an external pump
- 25 2.9 Wiring diagram
- 26 2.10 Commissioning
- 26 Control Panel
- 26 Additional guidelines for commissioning
- 26 Putting the boiler into operation
- 32 Normal start-up procedure
- 32 Error during the start-up procedure
- 33 Read out settings
- 34 Adjust the boiler according to the system
- 38 2.10.10 Restore factory settings
- 38 2.11 Putting the boiler out of operation
- 38 Boiler with frost protection, during longer periods of non-use
- 39 3.1 Inspection
- 40 Checking the condensate siphon
- 40 Checking the ignition electrode
- 41 Checking the combustion
- 42 3.2 Maintenance
- 46 4 ERRORS
- 46 4.1 General
- 46 4.2 Error codes
- 49 4.3 Control stop or lock-out
- 49 4.4 Error code memory
- 50 Error read outs
- 51 5 SERVICE PARTS
- 51 5.1 General
- 54 6 EC DECLARATION
- 55 7 REGULATIONS
- 55 7.1 EC regulations
- 55 7.2 Remeha factory test
- 55 7.3 Additional guidelines
- 56 8 TECHNICAL SPECIFICATIONS and working principle
- 56 8.1 Technical data
- 57 8.2 The boiler components
- 57 8.3 Working principle
- 57 Regulating
- 58 Advanced boiler control (‘abc®’-control)
- 58 Regulating the water temperature
- 58 Low flow / water protection
- 58 High Limit temperature protection
- 59 9 EFFICIENCY DATA AND GAS EFFICIENCY LABELS
- 59 9.1 Annual efficiency
- 59 9.2 Water-side efficiency