Start-Up Checklist
Unit Model Number _______________________________
(e.g. DGX-120-GH100-1600)
Unit Serial Number ________________________________
(e.g. 10111000)
Start-Up Date ____________________________________
Start-Up Personnel Name _________________________
Start-Up Company ________________________________
Phone Number ___________________________________
Pre Start-Up Checklist –
check boxes as items are completed.
o Check tightness of all factory wiring connections
o Verify control wiring wire gauge
o Hand-rotate blower to verify free rotation
o Verify supply voltage to the main disconnect
o Verify the supply gas pressure
o Verify remote controls wiring
Start-Up Blower Checklist –
refer to Blower
Start-Up section for further detail.
o L1-L2 __________
L2-L3 __________ o o o
_________ RPM o _________ Amps o _________ CFM
Optional Accessories –
refer to Blower Start-Up section, #6 for further detail.
_______ Actual Setting
Typical setting 5 minutes; 45ºF
_______ Actual Setting
Typical setting varies
Start-Up Direct Gas –
refer to Direct Gas Start-
Up section for further detail.
o Check supply gas pressure
________ Maximum
________ Minimum
________ Actual
o Set optional High Gas Pressure Switch
________ Actual Setting
Typical 8.0 in. wg
o Set optional Low Gas Pressure Switch
________ Actual Setting
Typical 3.0 in. wg
o Set Burner Pressure Differential
________ Actual Setting
Typical 0.65 in. wg
o Set the maximum firing rate
________ temp rise
o Set the minimum firing rate
________ check
o Set the unit’s operating temperature
________ ºF
DGX Industrial Space Heating 29
®
advertisement
Related manuals
advertisement
Table of contents
- 3 Clearance to Combustibles/Service Clearances
- 4 Indoor Unit
- 5 Unit Arrangement DB / HZ
- 6 Diffuser
- 6 Remote Panel (TSCP)
- 7 Electrical Wiring
- 8 Gas Piping
- 9 Blower
- 11 Direct Gas
- 11 100% Outdoor Air
- 12 50/50 Recirculation
- 15 Electrical without 7-Day Timer
- 16 Electrical with 7-Day Timer
- 17 Blower
- 18 Motor
- 19 Insufficient Airflow / Too Much Airflow
- 20 Excessive Noise or Vibration
- 21 Heater
- 24 Routine
- 27 Gas Train Layout, 400-800 MBH
- 27 Gas Train Layout, > 800 MBH
- 28 Control Center Layout / Dirty Filter Switch
- 29 Start-Up Check List
- 30 Maintenance Log