3. Evacuation (All amount of refrigerant leaked)
Part 4 Trouble Shooting
Indoor unit
Liquid side
3-Way valve
Open
Outdoor unit
Gas side
Vacuum pump
OPEN
Lo
OPEN
Vacuum
Gage
3-Way valve
Open
• Procedure
(1) Connect the vacuum pump to the center hose of charge set center hose
(2) Evacuation for approximately one hour.
– Confirm that the gauge needle has moved toward 0.8 Torr.
(3) Close the valve (Lo side) on the charge set, turn off the vacuum pump, and confirm that the gauge needle does not move (approximately 5 minutes after turning off the vacuum pump).
(4) Disconnect the charge hose from the vacuum pump.
– Vacuum pump oil.
If the vacuum pump oil becomes dirty or depleted, replenish as needed.
Copyright ©2009 LG Electronics. Inc. All right reserved.
Only for training and service purposes
- 23 -
LGE Internal Use Only
advertisement
Related manuals
advertisement
Table of contents
- 3 1. Safety Precautions
- 6 2. Nomenclature
- 8 1. List of Functions & Controls
- 9 2. Basic Mode Controls
- 11 3. Special Mode Controls
- 12 4. Utility Functions
- 16 1. Check before Test Run
- 17 2. Test Run Flow chart
- 18 3. Test Run Detail
- 20 1. 2-Way, 3-Way Valve
- 21 2. Pumping Down
- 22 3. Evacuation (All amount of refrigerant leaked)
- 23 4. Gas Charging (After Evacuation)
- 24 5. Cycle Troubleshooting Guide
- 25 6. Electric Parts Troubleshooting Guide
- 29 7. Self-diagnosis Function
- 21 1. 2-Way, 3-Way Valve
- 22 2. Pumping Down
- 23 3. Evacuation (All amount of refrigerant leaked)
- 24 4. Gas Charging (After Evacuation)
- 25 5. Cycle Troubleshooting Guide
- 26 6. Electronic Parts Troubleshooting Guide
- 30 7. Self-diagnosis Function