Operation
Connection options
Various slots are available on the connection socket of the control unit for connecting external equipment (e.g. operating hours counter).
Power supply,
230 V
Unlocking
Malfunction signals
Operating hours counter
32 02/2007 - Art. Nr. 13 021 281A
Operation
Allocation chart
Connection socket
Valve II
Connector no.
Terminals
Supply L1 Air pressure switch
Ignition Unlocking Malfunction signals
Connector no.
Terminals
Gas pressure switch
Burner motor Continuous ventilation
Connector no.
Terminals
Operating hours counter
Flame monitoring
Terminal
1
2
Designation
Terminal 5 of the control unit and terminal B4 of the 7-pin Wieland connector (counter)
Live
7
8
9
10
5
6
3
4
11
12
13
14
15
25
Earth
Live
Live
Earth
Neutral
Terminal 4 of the control unit
Terminal 7 of the control unit
Terminal 3 of the control unit
Neutral
Terminal A of the control unit
Terminal 9 of the control unit
Neutral
Terminal B of the control unit
T2
27
32
33
34
35
28
29
30
31
36
37
38
39
40
41
Terminal
26 Not assigned
Designation
Terminal 9 of the control unit via bridge (or temperature regulator) with regulator
Terminal 4 of the control unit
Earth
Neutral
Live
Earth
Neutral
Earth
Terminal 2 of the control unit
Neutral
Live
Terminal 5 of the control unit and terminal B4 of the 7-pin Wieland connector (counter)
Live
Neutral
Live
02/2007 - Art. Nr. 13 021 281A 33
advertisement
* Your assessment is very important for improving the workof artificial intelligence, which forms the content of this project
Related manuals
advertisement
Table of contents
- 3 Description du brûleur
- 5 Sélection des rampes gaz
- 5 Rampe gaz
- 8 Coffret de commande et de sécurité SG
- 10 Options de raccordement
- 12 Montage du brûleur
- 13 Contrôle / Réglage / Montage
- 16 Données de réglage du brûleur
- 17 Réglage de l'air
- 18 Contrôle du déroulement du programme
- 18 Réglage du brûleur
- 19 Réglage manostat gaz / manostat d'air
- 19 Contrôle du fonctionnement
- 19 02/2007 - Art. Nr
- 25 Burner description
- 27 Gas train selection
- 27 Gas train
- 30 SG113 automatic combustion control unit
- 32 Connection options
- 34 Burner assembly
- 35 Checking/adjusting/assembly
- 35 Burner head for natural gas/propane gas
- 37 Checks before commissioning
- 38 Burner adjustment data
- 39 Air regulation
- 40 Program sequence test
- 40 Adjusting burner output
- 41 Gas/air pressure switch adjustment
- 41 Function check
- 41 02/2007 - Art. Nr