6. Connecting Pipes to the Indoor Unit
• Preparation of Piping
Main cause of gas leakage is defect in flaring work. Carry out correct flaring work in the following procedure.
1) Cut the pipes and the cable.
■
Use the accessory piping kit or the pipes purchased locally.
■
Measure the distance between the indoor and the outdoor unit.
■
Cut the pipes a little longer than measured distance.
■
Cut the cable 1.5m longer than the pipe length.
Copper tube
Point down
90
°
2) Burrs removal
■
Completely remove all burrs from the cut cross section of pipe/tube.
■
Put the end of the copper tube/pipe to downward direction as you remove burrs in order to avoid to let burrs drop in the tubing.
3) Putting nut on
■
Remove flare nuts attached to indoor and outdoor units, than put them on pipe/tube having completed burr removal.
(Not possible to put them on after flaring work)
4) Flaring work
■
Carry out flaring work using flaring tool as shown below.
Outside diameter mm inch
Ø6.35
1/4
Ø9.52
Ø15.88
Ø19.05
3/8
5/8
3/4
A mm
0.5~0.8
0.5~0.8
0.8~1.0
0.8~1.0
Firmly hold copper tube in a bar(or die) as indicated dimension in the table above.
Bar
Copper tube
Flare nut
"A"
Bar
Slanted Uneven Rough
Pipe
Reamer
Copper pipe
Clamp handle
Handle
Yoke
Cone
Red arrow mark
Smooth all round
Inside is shining without scratches
= Improper flaring =
5) Check
■
Compare the flared work with figure below.
■
If flare is noted to be defective, cut off the flared section and do flaring work again.
Inclined Surface damaged
Cracked Uneven thickness
Even length all round
10
advertisement
Related manuals
advertisement
Table of contents
- 3 1.The following should be always observed for safety
- 4 2.Installation of Indoor, Outdoor Unit
- 4 1) Selection of the best location
- 5 bolt location(unit: mm)
- 6 3) The Indoor Unit Installation
- 6 4) Remote Controller Installation
- 8 5) Wiring Connection
- 9 ELECTRICAL WIRING
- 9 CONNECTING THE CABLE TO OUTDOOR UNIT
- 10 6) Connecting Pipes to the Indoor Unit
- 11 PIPING CONNECTION
- 12 7) Installation of Decorative Panel
- 13 8) Indoor Unit Drain Piping
- 14 HEAT INSULATION
- 14 FORM THE PIPINGS
- 15 3. Test running
- 15 1) PRECAUTIONS IN TEST RUN
- 15 INSTALLATION IS COMPLETE
- 16 2) Connection of power supply
- 16 3) Evaluation of the performance
- 17 4. Auxiliary operation
- 17 1) Two thermistor system
- 18 2) Ajusting to the height of ceiling
- 19 3) Group control (optional wiring)
- 20 4) Central control (optional)