Initial Installation. Juniper JCS 1200
Advertisement
Advertisement
Part 2
Initial Installation
■
■
■
■
■
■
Preparing the Site for JCS 1200 Platform Installation on page 33
Unpacking the JCS 1200 Platform on page 39
Installing the JCS 1200 Mounting Hardware on page 43
Installing the JCS 1200 Platform on page 49
Connecting the JCS 1200 Platform on page 59
Configuration Guidelines on page 81
Initial Installation
■ 31
Juniper Control System (JCS) 1200 Platform Hardware Guide
32 ■
Initial Installation
Chapter 3
Preparing the Site for JCS 1200 Platform
Installation
Topics include:
■
■
■
■
■
Overview of Preparing the Site for JCS 1200 Platform Installation on page 33
Site Preparation Checklist for the JCS 1200 Platform on page 33
JCS 1200 Cabinet Requirements on page 34
JCS 1200 Rack Requirements on page 35
JCS 1200 Clearance Requirements for Airflow and Hardware
Overview of Preparing the Site for JCS 1200 Platform Installation
Related Topics
■
■
To prepare your site for installation, review the guidelines and requirements in the following topics:
■
■
■
General Safety Guidelines and Warnings for the JCS 1200 Platform on page 151
JCS 1200 Cabinet Size and Clearance Requirements on page 34
JCS 1200 Cabinet Airflow Requirements on page 35
■
■
■
JCS 1200 Rack Size and Strength on page 36
JCS 1200 Connection to Building Structure on page 37
JCS 1200 Clearance Requirements for Airflow and Hardware
Site Preparation Checklist for the JCS 1200 Platform on page 33
JCS 1200 Platform Environmental Specifications on page 187
Site Preparation Checklist for the JCS 1200 Platform
The checklist in Table 16 on page 34 summarizes the tasks you need to perform
when preparing a site for platform installation.
Overview of Preparing the Site for JCS 1200 Platform Installation
■ 33
Juniper Control System (JCS) 1200 Platform Hardware Guide
Table 16: Site Preparation Checklist
Item or Task
Environment
Verify that environmental factors such as temperature and humidity do not exceed platform tolerances.
Power
Locate sites for connection of system grounding.
For More Information
“JCS 1200 Platform Environmental
Performed By Date
Calculate the power consumption and requirements.
■
■
Rack
Verify that your rack meets the minimum requirements for the installation of the platform.
■
■
Plan rack location, including required space clearances.
If a rack is used, secure rack to floor and building structure.
Related Topics
■
■
“JCS 1200 Clearance Requirements for Airflow and Hardware
“JCS 1200 Connection to Building
Overview of Preparing the Site for JCS 1200 Platform Installation on page 33
JCS 1200 Platform Environmental Specifications on page 187
JCS 1200 Cabinet Requirements
The JCS 1200 platform can be installed in a standard 800-mm (or larger) enclosed cabinet. The following topics describe cabinet requirements:
■
■
JCS 1200 Cabinet Size and Clearance Requirements on page 34
JCS 1200 Cabinet Airflow Requirements on page 35
JCS 1200 Cabinet Size and Clearance Requirements
The minimum size cabinet that can accommodate the JCS 1200 platform is 600 mm wide and 800 mm deep. A cabinet larger than the minimum requirement provides better airflow and reduces the chance of overheating. To accommodate a single
JCS 1200 platform, the cabinet must be at least 12 U (21 in. (53.34 cm)) high.
34 ■
JCS 1200 Cabinet Requirements
Chapter 3: Preparing the Site for JCS 1200 Platform Installation
The minimum front and rear clearance requirements depend on the mounting configuration you choose. The minimum total clearance inside the cabinet is 30.70 in.
between the inside of the front door and the inside of the rear door.
NOTE: If you mount the JCS 1200 platform in a cabinet, be sure that sufficient room is provided for cable management and cables.
Related Topics
■
■
■
■
Overview of Preparing the Site for JCS 1200 Platform Installation on page 33
Site Preparation Checklist for the JCS 1200 Platform on page 33
JCS 1200 Platform Environmental Specifications on page 187
JCS 1200 Cabinet Airflow Requirements on page 35
JCS 1200 Cabinet Airflow Requirements
Related Topics
■
■
■
■
When you mount the JCS 1200 platform in a cabinet, you must ensure that ventilation through the cabinet is sufficient to prevent overheating. Consider the following list of requirements when you plan for chassis cooling:
■
■
■
Ensure that the cool air supply you provide through the cabinet can adequately dissipate the thermal output of the JCS 1200 platform. For information about the JCS 1200 platform's environmental specifications, including its operating
temperature and thermal output, see “JCS 1200 Platform Environmental
Ensure that the cabinet allows the chassis hot exhaust air to exit from the cabinet without recirculating into the JCS 1200 platform. An open cabinet (without a top or doors) that employs hot air exhaust extraction from the top allows the best airflow through the chassis. If the cabinet contains a top or doors, perforations in these elements assist with removing the hot air exhaust.
Route and dress all cables to minimize the blockage of airflow to and from the chassis.
Overview of Preparing the Site for JCS 1200 Platform Installation on page 33
Site Preparation Checklist for the JCS 1200 Platform on page 33
JCS 1200 Platform Environmental Specifications on page 187
JCS 1200 Cabinet Size and Clearance Requirements on page 34
JCS 1200 Rack Requirements
The JCS 1200 platform can be installed in a rack. Many types of racks are acceptable, including four-post (telco) racks and open-frame racks. An example of an open-frame
rack appears in Figure 19 on page 37.
JCS 1200 Cabinet Airflow Requirements
■ 35
Juniper Control System (JCS) 1200 Platform Hardware Guide
The following topics describe rack requirements:
■
■
JCS 1200 Rack Size and Strength on page 36
JCS 1200 Connection to Building Structure on page 37
JCS 1200 Rack Size and Strength
The JCS 1200 platform is designed for installation in a 19-in. rack as defined in
Cabinets, Racks, Panels, and Associated Equipment (document number EIA-310-D) published by the Electronics Industry Association ( http://www.eia.org
).
With the use of adapters, the JCS 1200 platform is designed to fit into a 600-mm-wide rack or cabinet , as defined in the four-part Equipment Engineering (EE); European
telecommunications standard for equipment practice (document numbers ETS 300
119-1 through 119-4) published by the European Telecommunications Standards
Institute ( http://www.etsi.org
). Use approved wing devices to narrow the opening between the rails.
The rack rails must be spaced widely enough to accommodate the JCS 1200 chassis's external dimensions: 21 in. (53.34 cm) high, 25.64 in. (65.1 cm) deep, and
17.43 in. (44.3 cm) wide. The outer edges of the mounting brackets extend the width to 19 in. (48.3 cm). The spacing of rails and adjacent racks must also allow for the
clearances around the JCS 1200 platform and rack that are specified in “JCS 1200
Clearance Requirements for Airflow and Hardware Maintenance” on page 38.
For instructions about installing the mounting hardware, see “Installing the JCS 1200
Mounting Hardware for an Open-Frame Rack” on page 46 or “Installing the JCS 1200
Mounting Hardware for a Four-Post Rack or Cabinet” on page 44.
The chassis height of 21 in. (53.34 cm) is approximately 20 U. A U is the standard rack unit defined in Cabinets, Racks, Panels, and Associated Equipment (document number EIA-310-D) published by the Electronics Industry Association.
The rack must be strong enough to support the weight of the fully configured platform, up to 350 lb (158.8 kg). If you stack two fully configured platforms in one rack, it must be capable of supporting about 878 lb (399.1 kg).
36 ■
JCS 1200 Rack Size and Strength
Chapter 3: Preparing the Site for JCS 1200 Platform Installation
Figure 19: Typical Open-Frame Rack
Related Topics
■
■
■
■
■
Overview of Preparing the Site for JCS 1200 Platform Installation on page 33
Site Preparation Checklist for the JCS 1200 Platform on page 33
JCS 1200 Platform Environmental Specifications on page 187
JCS 1200 Connection to Building Structure on page 37
JCS 1200 Clearance Requirements for Airflow and Hardware
JCS 1200 Connection to Building Structure
Always secure the rack to the structure of the building. If your geographical area is subject to earthquakes, bolt the rack to the floor. For maximum stability, also secure the rack to ceiling brackets.
Related Topics
■
Overview of Preparing the Site for JCS 1200 Platform Installation on page 33
■
■
Site Preparation Checklist for the JCS 1200 Platform on page 33
Rack-Mounting Requirements and Warnings for the JCS 1200 Platform on page 156
JCS 1200 Connection to Building Structure
■ 37
Juniper Control System (JCS) 1200 Platform Hardware Guide
■
■
JCS 1200 Rack Size and Strength on page 36
JCS 1200 Clearance Requirements for Airflow and Hardware
JCS 1200 Clearance Requirements for Airflow and Hardware Maintenance
When planning the installation site, allow sufficient clearance around the rack (see
■
■
■
For the cooling system to function properly, the airflow around the chassis must be unrestricted.
For service personnel to remove and install hardware components, there must be adequate space at the front and back of the platform. Allow at least
30 in. (72.6 cm) in front of the rack and 24 in. (61.0 cm) behind the rack.
Airflow vents provided along the sides of the chassis must remain open and uncovered for proper cooling.
Figure 20: JCS 1200 Chassis Dimensions and Clearance Requirements
Related Topics
■
■
■
■
Overview of Preparing the Site for JCS 1200 Platform Installation on page 33
Site Preparation Checklist for the JCS 1200 Platform on page 33
Rack-Mounting Requirements and Warnings for the JCS 1200 Platform on page 156
JCS 1200 Rack Size and Strength on page 36
38 ■
JCS 1200 Clearance Requirements for Airflow and Hardware Maintenance
Chapter 4
Unpacking the JCS 1200 Platform
This chapter describes how to prepare to install the JCS 1200 platform. Topics include:
■
■
■
Tools and Parts Required to Unpack the JCS 1200 Platform on page 39
Unpacking the JCS 1200 Platform on page 40
Verifying Parts Received for the JCS 1200 Platform on page 41
Tools and Parts Required to Unpack the JCS 1200 Platform
Related Topics
■
■
To unpack the JCS 1200 platform and prepare for installation, you need the following tools:
■
■
Phillips (+) screwdriver, number 2
1/2-in. or 13-mm open-end or socket wrench to remove bracket bolts from the shipping pallet
■
Blank panels to cover any slots not occupied by a component
Unpacking the JCS 1200 Platform on page 40
Verifying Parts Received for the JCS 1200 Platform on page 41
Tools and Parts Required to Unpack the JCS 1200 Platform
■ 39
Juniper Control System (JCS) 1200 Platform Hardware Guide
Unpacking the JCS 1200 Platform
The platform is shipped in a cardboard box strapped securely to a wood pallet. Plastic straps secure the top and bottom in place. The JCS 1200 chassis is bolted to this pallet. Quick Start installation instructions and a cardboard accessory box are also included in the shipping container.
The shipping container measures 32.5 in. (82.6 cm) high, 35 in. (88.9 cm) wide, and
27 in. (68.6 cm) deep. The total weight of the container containing the JCS 1200 platform and accessories can range from 329 lb (149.6 kg) to 350 lb (158.8 kg).
NOTE: The JCS 1200 platform is maximally protected inside the shipping crate. Do not unpack it until you are ready to begin installation.
To unpack the JCS 1200 platform:
1.
Move the shipping container to a staging area as close to the installation site as possible, where you have enough room to remove the components from the chassis. While the chassis is bolted to the pallet, you can use a forklift or pallet jack to move it.
2.
3.
Position the shipping container with the wooden pallet on the bottom and the corrugated cardboard facing up.
Remove the plastic straps that hold the top and bottom of the shipping container in place.
4.
5.
6.
Remove the corrugated container cover and set it aside.
Remove the foam covering the top of the JCS 1200 platform.
Remove the accessory box and the Quick Start documentation.
7.
8.
Verify the parts received against the lists in “Verifying Parts Received for the
JCS 1200 Platform” on page 41.
Remove the vapor corrosion inhibitor (VCI) packs attached to the pallet. Be careful not to break the VCI packs open.
9.
To remove the bolts and screws from the brackets holding the chassis on the pallet, use a 1/2-in. socket wrench and a number 2 Phillips screwdriver.
10.
Store the brackets and bolts inside the accessory box.
11.
Save the corrugated shipping container cover, pallet, and packing materials in case you need to move or ship the JCS 1200 platform later. The packaging utilizes recyclable materials in the design and should be disposed of properly. Recycle packaging according to your local, state, or country specific laws and regulations.
Related Topics
To proceed with the installation, see:
■
■
Installing the JCS 1200 Mounting Hardware for a Four-Post Rack or
Installing the JCS 1200 Platform Using a Lift on page 51
40 ■
Unpacking the JCS 1200 Platform
Chapter 4: Unpacking the JCS 1200 Platform
Verifying Parts Received for the JCS 1200 Platform
A packing list is included in each shipment. Check the parts in the shipment against the items on the packing list. The packing list specifies the part numbers and descriptions of each part in your order.
If any part is missing, contact a Juniper Networks customer service representative.
A fully configured JCS 1200 platform contains the JCS 1200 platform chassis with
installed components, listed in Table 17 on page 41, and an accessory box, which
contains the parts listed in Table 18 on page 42. The parts shipped with your JCS 1200
platform can vary.
Table 17: Parts List for a Fully Configured JCS 1200 Platform
Component
Chassis
Chassis bezel
Cable management collar
Routing Engines
Management modules
Management module interposer trays
Media trays
MUX cards
Switch modules
Switch module interposer trays
Power modules
Air filters
Quick Start installation instructions
Large mounting shelf
Small mounting shelf
Blank panels for slots without components installed
Quantity
12
1
1
1
1
1
2
1
1
4
2
2
1
1
1
One blank panel for each slot not occupied by a component
Verifying Parts Received for the JCS 1200 Platform
■ 41
Juniper Control System (JCS) 1200 Platform Hardware Guide
Table 18: JCS 1200 Accessory Box Parts List
Part Quantity
Front rack-mount bracket
Mid rack-mount bracket
Rack-mount screws M5 x12 mm
Serial port breakout cable, with 14 RJ-45 jacks to female
DB-9, to connect the JCS 1200 platform through the serial port
1
RJ-45 CPU adapters for use with the serial port breakout cable
12
RJ-45 ETH adapters for use with the switch module
RJ-45 AMM adapters for use with the management module
Label, accessories contents, JCS 1200
Small rear shelf for mounting the JCS 1200 platform in a four-post rack
2
2
1
1
2
2
8
Large front shelf for mounting the JCS 1200 platform in a four-post or two-post rack
1
Bottom cable manager 1
Top cable manager
Cable manager screws
Juniper Networks Compliance Form Letter, RoHS
Worldwide
Juniper Networks Product Warranty
1
7
1
1
1 End User License Agreement
Accessory box, 19" x 12" x 3" 1
Related Topics
■
■
Tools and Parts Required to Unpack the JCS 1200 Platform on page 39
Unpacking the JCS 1200 Platform on page 40
42 ■
Verifying Parts Received for the JCS 1200 Platform
Chapter 5
Installing the JCS 1200 Mounting
Hardware
This chapter describes the procedures for installing the mounting hardware:
■
■
■
■
JCS 1200 Platform Rack-Mounting Hardware on page 43
Rack Mounting Hole Locations for the JCS 1200 Platform on page 43
Installing the JCS 1200 Mounting Hardware for a Four-Post Rack or
Installing the JCS 1200 Mounting Hardware for an Open-Frame Rack on page 46
JCS 1200 Platform Rack-Mounting Hardware
The JCS 1200 platform can be installed in a four-post rack or cabinet or an open-frame rack. Before you install the JCS 1200 platform, you install the mounting hardware on the rack. The procedure for installing the mounting hardware depends on the type of rack.
All mounting options require that you to install the supplied large mounting shelf.
The supplied small mounting shelf is needed only for a four-post rack or cabinet.
Related Topics
■
Rack Mounting Hole Locations for the JCS 1200 Platform on page 43
■
Rack-Mounting Requirements and Warnings for the JCS 1200 Platform on page 156
■
■
Installing the JCS 1200 Mounting Hardware for a Four-Post Rack or
Installing the JCS 1200 Mounting Hardware for an Open-Frame Rack on page 46
Rack Mounting Hole Locations for the JCS 1200 Platform
Table 19 on page 44 specifies the holes in which you insert mounting screws (and
cage nuts if needed) to install the mounting hardware required in a four-post or two-post open-frame rack (an X indicates a mounting hole location). The hole distances are relative to one of the standard U divisions on the rack. The bottom of all mounting shelves is at 0.04 in. (0.02 U) above a U division.
JCS 1200 Platform Rack-Mounting Hardware
■ 43
Juniper Control System (JCS) 1200 Platform Hardware Guide
Table 19: Open-Frame Rack Mounting Hole Locations
Hole
18
15
12
9
30
27
24
21
2
1
6
3
17.26 in. (43.8 cm)
15.51 in. (39.4 cm)
13.76 in. (34.9 cm)
12.01 in. (30.5 cm)
10.26 in. (26.0 cm)
8.51 in. (21.6 cm)
6.76 in. (17.1 cm)
5.01 in. (12.7 cm)
3.26 in. (8.3 cm)
1.51 in. (3.8 cm)
0.88 in. (2.2 cm)
0.25 in. (0.6 cm)
Distance Above U Division
9.86 U
8.86 U
7.86 U
6.86 U
5.86 U
4.86 U
3.86 U
2.86 U
1.86 U
0.86 U
0.50 U
0.14 U
Large
Shelf
X
X
X
X
X
X
X
X
X
X
X
Chassis
Small
Shelf
X
X
X
X
X
X
X
X
Related Topics
■
■
■
■
JCS 1200 Platform Rack-Mounting Hardware on page 43
Rack-Mounting Requirements and Warnings for the JCS 1200 Platform on page 156
Installing the JCS 1200 Mounting Hardware for a Four-Post Rack or
Installing the JCS 1200 Mounting Hardware for an Open-Frame Rack on page 46
Installing the JCS 1200 Mounting Hardware for a Four-Post Rack or Cabinet
If you are installing the JCS 1200 platform in a four-post rack or cabinet, you must first install the large mounting shelf, followed by the small mounting shelf.
To install the mounting shelves (see Figure 21 on page 45):
1.
2.
3.
4.
If the rack rails require cage nuts, install cage nuts into the holes specified in
“Rack Mounting Hole Locations for the JCS 1200 Platform” on page 43 for the
large shelf on the front side of the rack rails.
On the front of each front rack rail, partially insert a mounting screw into the hole containing the lowest cage nut.
Install the large shelf on the front rack rails. Rest the bottom slot of each ear on a mounting screw.
Partially insert a mounting screw into holes 3, 6, 9, and 30 in each ear of the large shelf.
44 ■
Installing the JCS 1200 Mounting Hardware for a Four-Post Rack or Cabinet
Chapter 5: Installing the JCS 1200 Mounting Hardware
5.
6.
7.
8.
Tighten all the screws completely.
If the rack rails require cage nuts, install cage nuts into the holes specified in
“Rack Mounting Hole Locations for the JCS 1200 Platform” on page 43 for the
small shelf on the rear side of the rack rails.
On the back of each rear rack rail, partially insert a mounting screw into the hole containing the lowest cage nut.
Install the small shelf on the back rack rails. Rest the bottom slot of each ear on a mounting screw. The small shelf installs on the back of the rear rails, extending toward the center of the rack. The bottom of the small shelf should align with the bottom of the large shelf.
Partially insert screws into the open holes in the ears of the small shelf.
9.
10.
Tighten all the screws completely.
11.
On the sides of the JCS 1200 chassis, attach the front-mounting brackets using six of the mounting screws provided.
Figure 21: Installing the JCS 1200 Mounting Hardware for a Four-Post Rack or Cabinet
Related Topics
■
■
■
JCS 1200 Platform Rack-Mounting Hardware on page 43
Rack-Mounting Requirements and Warnings for the JCS 1200 Platform on page 156
Rack Mounting Hole Locations for the JCS 1200 Platform on page 43
Installing the JCS 1200 Mounting Hardware for a Four-Post Rack or Cabinet
■ 45
Juniper Control System (JCS) 1200 Platform Hardware Guide
■
■
■
Installing the JCS 1200 Platform Using a Lift on page 51
Lifting the JCS 1200 Platform into the Rack or Cabinet on page 56
Installing the JCS 1200 Mounting Hardware for an Open-Frame Rack on page 46
Installing the JCS 1200 Mounting Hardware for an Open-Frame Rack
If you are installing the JCS 1200 platform in a front-mount or center-mount open-frame rack, you must first install the large mounting shelf on the rack. The small mounting shelf is not needed.
For information about the holes in which you insert mounting screws (and cage-nuts if needed) to install the mounting hardware in an open-frame rack (an
X
indicates a
mounting hole location), see “Rack Mounting Hole Locations for the JCS 1200
Platform” on page 43. The hole distances are relative to one of the standard U
divisions on the rack. For reference, the bottom of all mounting shelves is at
0.04 in. (0.02 U) above a U division.
5.
6.
To install the large mounting shelf (see Figure 22 on page 47):
1.
If the rack rails require cage nuts, install cage nuts into the holes specified for the large shelf on the rear side of the rack rails.
2.
3.
If the rack rails require cage nuts, install cage nuts into the holes specified for the chassis on the front side of the rack rails
On the rear of each rack rail, partially insert a mounting screw into the highest hole specified for the large shelf.
4.
7.
Install the large shelf on the rack. Hang the shelf over the mounting screws using the keyhole slots located near the top of the large shelf flanges.
Partially insert screws into the open holes in the ears of the large shelf.
Tighten all the screws completely.
Attach the mounting brackets to the sides of the chassis:
■
If you plan to front-mount the chassis in an open-frame rack, attach the front-mounting brackets using six of the mounting screws provided.
■
If you plan to center-mount the chassis in an open-frame rack, attach the center-mounting brackets using the eight mounting screws provided.
46 ■
Installing the JCS 1200 Mounting Hardware for an Open-Frame Rack
Chapter 5: Installing the JCS 1200 Mounting Hardware
Figure 22: Installing the JCS 1200 Mounting Hardware for an Open-Frame Rack
Related Topics
■
■
■
■
■
■
JCS 1200 Platform Rack-Mounting Hardware on page 43
Rack-Mounting Requirements and Warnings for the JCS 1200 Platform on page 156
Rack Mounting Hole Locations for the JCS 1200 Platform on page 43
Installing the JCS 1200 Platform Using a Lift on page 51
Lifting the JCS 1200 Platform into the Rack or Cabinet on page 56
Installing the JCS 1200 Mounting Hardware for a Four-Post Rack or
Installing the JCS 1200 Mounting Hardware for an Open-Frame Rack
■ 47
Juniper Control System (JCS) 1200 Platform Hardware Guide
48 ■
Installing the JCS 1200 Mounting Hardware for an Open-Frame Rack
Chapter 6
Installing the JCS 1200 Platform
This chapter provides instructions for installing the JCS 1200 platform into a rack and adding optional devices to your JCS 1200 platform.
■
■
■
Safety Requirements, Warnings, and Guidelines for Installing the JCS 1200
Installing the JCS 1200 Platform Using a Mechanical Lift on page 51
Installing the JCS 1200 Platform in a Rack Without a Lift on page 54
Safety Requirements, Warnings, and Guidelines for Installing the JCS 1200 Platform
To avoid harm to yourself or the platform as you install and maintain it, follow the guidelines for working with and near electrical equipment, as well as the safety procedures for working with networking equipment. However, providing an exhaustive set of guidelines for working with electrical equipment is beyond the scope of this manual.
For a discussion of how to make the installation site a safe environment, see the following topics:
■
■
■
Site Preparation Checklist for the JCS 1200 Platform on page 33
JCS 1200 Cabinet Size and Clearance Requirements on page 34
JCS 1200 Cabinet Airflow Requirements on page 35
■
■
■
JCS 1200 Rack Size and Strength on page 36
JCS 1200 Connection to Building Structure on page 37
JCS 1200 Clearance Requirements for Airflow and Hardware
For a list of safety warnings, see the following topics:
■
Definition of Safety Warning Levels on page 149
■
■
■
■
■
General Safety Guidelines and Warnings for the JCS 1200 Platform on page 151
Qualified Personnel Warning for the JCS 1200 Platform on page 152
Restricted Access Area Warning for the JCS 1200 Platform on page 152
Preventing Electrostatic Discharge Damage to the JCS 1200 Platform on page 154
Fire Safety Requirements for the JCS 1200 Platform on page 155
Safety Requirements, Warnings, and Guidelines for Installing the JCS 1200 Platform
■ 49
Juniper Control System (JCS) 1200 Platform Hardware Guide
■
■
■
■
■
■
■
■
■
■
■
■
■
JCS 1200 Chassis Lifting Guidelines on page 155
Installation Instructions Power Warning for the JCS 1200 Platform on page 156
Rack-Mounting Requirements and Warnings for the JCS 1200 Platform on page 156
Ramp Warning for the JCS 1200 Platform on page 160
Class 1 Laser Product Warning for the JCS 1200 Platform on page 160
Class 1 LED Product Warning for the JCS 1200 Platform on page 161
Laser Beam Warning for the JCS 1200 Platform on page 162
Radiation from Open Port Apertures Warning for the JCS 1200
Battery Handling Warning for the JCS 1200 Platform on page 164
Jewelry Removal Warning for the JCS 1200 Platform on page 165
Lightning Activity Warning for the JCS 1200 Platform on page 166
Operating Temperature Warning for the JCS 1200 Platform on page 167
Product Disposal Warning for the JCS 1200 Platform on page 168
Related Topics
■
■
For a list of electrical safety warnings, see the following topics:
■
In Case of an Electrical Accident on page 169
■
General Electrical Safety Guidelines and Warnings Electrical Codes for the
■
■
■
Grounded Equipment Warning for the JCS 1200 Platform on page 171
Midplane Energy Hazard Warning for the JCS 1200 Platform on page 172
Multiple Power Supplies Disconnection Warning for the JCS 1200
■
■
■
TN Power Warning for the JCS 1200 Platform on page 173
Copper Conductors Warning for the JCS 1200 Platform on page 174
JCS 1200 AC Power Electrical Safety Guidelines and Warnings on page 174
■
■
■
■
■
JCS 1200 DC Power Electrical Safety Guidelines on page 175
DC Power Disconnection Warning for the JCS 1200 Platform on page 176
JCS 1200 DC Power Grounding Requirements and Warning on page 178
DC Power Wiring Sequence Warning for the JCS 1200 Platform on page 179
DC Power Wiring Terminations Warning for the JCS 1200 Platform on page 180
Installing the JCS 1200 Platform Using a Lift on page 51
Lifting the JCS 1200 Platform into the Rack or Cabinet on page 56
50 ■
Safety Requirements, Warnings, and Guidelines for Installing the JCS 1200 Platform
Chapter 6: Installing the JCS 1200 Platform
Installing the JCS 1200 Platform Using a Mechanical Lift
Because of the JCS 1200 platform's size and weight—up to 350 lb (158.8 kg) depending on the configuration—we strongly recommend that you install the JCS 1200 platform using a mechanical lift. If you do not use a lift to install the JCS 1200
platform, see “Lifting the JCS 1200 Platform into the Rack or Cabinet” on page 56
for complete instructions to safely install the platform.
Before installing the JCS 1200 platform, you should have prepared your site and
reviewed the guidelines in “Overview of Preparing the Site for JCS 1200 Platform
Installation” on page 33. The “Site Preparation Checklist for the JCS 1200
Platform” on page 33 summarizes the tasks you need to perform when preparing a
site for platform installation. You also need to unpack the JCS 1200 platform from
the shipping container, as described in “Unpacking the JCS 1200
Topics include:
■
■
Tools Required to Install the JCS 1200 Platform Using a Mechanical Lift on page 51
Installing the JCS 1200 Platform Using a Lift on page 51
Tools Required to Install the JCS 1200 Platform Using a Mechanical Lift
Related Topics
■
■
■
To install the platform, you need the following tools:
■
■
■
Mechanical lift
Phillips (+) screwdriver, number 2
ESD grounding wrist strap
Installing the JCS 1200 Mounting Hardware for a Four-Post Rack or
Installing the JCS 1200 Mounting Hardware for an Open-Frame Rack on page 46
Installing the JCS 1200 Platform Using a Lift on page 51
Installing the JCS 1200 Platform Using a Lift
Before installing the JCS 1200 platform in the rack:
■
Read the safety information in “JCS 1200 Chassis Lifting Guidelines” on page 155.
■
Remove the JCS 1200 platform from the shipping container, as described in
“Unpacking the JCS 1200 Platform” on page 40.
■
Install the mounting hardware, as described in “Installing the JCS 1200 Mounting
Hardware for a Four-Post Rack or Cabinet” on page 44 or “Installing the JCS 1200
Mounting Hardware for an Open-Frame Rack” on page 46.
Installing the JCS 1200 Platform Using a Mechanical Lift
■ 51
Juniper Control System (JCS) 1200 Platform Hardware Guide
CAUTION: Before front mounting the JCS 1200 platform in a rack, have a qualified technician verify that the rack is strong enough to support the JCS 1200 platform's weight and is adequately supported at the installation site.
2.
3.
To install the JCS 1200 platform using a lift (see Figure 23 on page 53 and
1.
4.
5.
If you are installing the platform in an open-frame rack, ensure that the rack is in its permanent location and is secured to the building. Ensure that the installation site allows adequate clearance for both airflow and maintenance.
For details, see “Overview of Preparing the Site for JCS 1200 Platform
Load the platform onto the lift, making sure it rests securely on the lift platform.
Using the lift, position the platform in front of the rack or cabinet, centering it in front of the mounting shelves.
Lift the chassis approximately 0.75 in. (1.91 cm) above the surface of the mounting shelves and position it as close as possible to the shelves.
Carefully slide the platform onto the mounting shelves so that the bottom of the chassis and the mounting shelves overlap by approximately 2 in.
6.
7.
8.
9.
With two people pulling on the chassis from the rear of the rack or cabinet while two people push on the mounting flanges, slide the platform onto the mounting shelves until the front-mounting or center-mounting flanges contact the rack rails. The shelves ensure that the holes in the mounting flanges align with the holes in the rack rails.
Install a mounting screw into each of the open mounting holes in the rack-mounting brackets to fasten the chassis to the rack, starting from the bottom.
Move the lift away from the rack.
Visually inspect the alignment of the platform. If the platform is installed properly in the rack, all the mounting screws on one side of the rack should be aligned with the mounting screws on the opposite side, and the platform should be level.
52 ■
Installing the JCS 1200 Platform Using a Lift
Chapter 6: Installing the JCS 1200 Platform
Figure 23: Installing the JCS 1200 Platform in a Four-Post Rack
Installing the JCS 1200 Platform Using a Lift
■ 53
Juniper Control System (JCS) 1200 Platform Hardware Guide
Figure 24: Installing the JCS 1200 Platform in an Open-Frame Rack
Related Topics
■
Tools Required to Install the JCS 1200 Platform Using a Mechanical Lift on page 51
Installing the JCS 1200 Platform in a Rack Without a Lift
Because of the JCS 1200 platform's size and weight—up to 350 lb (158.8 kg) depending on the configuration—we strongly recommend that you install the JCS 1200
platform using a mechanical lift, as described in “Installing the JCS 1200 Platform
Using a Lift” on page 51. If you do not use a lift to install the platform, refer to the
following procedures:
■
■
■
■
Tools and Parts Required to Install the JCS 1200 Platform Without a Mechanical
Removing Components from the JCS 1200 Platform on page 55
Lifting the JCS 1200 Platform into the Rack or Cabinet on page 56
Reinstalling Components into the JCS 1200 Platform on page 57
54 ■
Installing the JCS 1200 Platform in a Rack Without a Lift
Chapter 6: Installing the JCS 1200 Platform
Tools and Parts Required to Install the JCS 1200 Platform Without a Mechanical Lift
■
■
■
To install the platform, you need the following tools and parts:
■
■
Phillips (+) screwdriver, number 2
ESD grounding wrist strap
Related Topics
■
Installing the JCS 1200 Mounting Hardware for a Four-Post Rack or
Installing the JCS 1200 Mounting Hardware for an Open-Frame Rack on page 46
Removing Components from the JCS 1200 Platform on page 55
Lifting the JCS 1200 Platform into the Rack or Cabinet on page 56
Removing Components from the JCS 1200 Platform
Before lifting the JCS 1200 platform, you must remove the following components:
■
Fan modules
■
■
Fan shuttle
Management modules
■
■
■
■
Media trays
Power modules
Routing Engines
Switch modules
NOTE: For detailed instructions on removing JCS 1200 components, see the removal procedures for each component.
Related Topics
■
■
To remove the components from the JCS 1200 platform:
1.
2.
Attach an electrostatic discharge (ESD) grounding strap to your bare wrist and connect the strap to one of the ESD points on the chassis.
Slide each component out of the chassis evenly so that it does not become stuck or damaged.
3.
4.
5.
Label each component as you remove it so you can reinstall it in the correct location.
Immediately store each removed component in an electrostatic bag.
Do not stack removed components. Lay each one on a flat surface.
Preventing Electrostatic Discharge Damage to the JCS 1200 Platform on page 154
Tools and Parts Required to Install the JCS 1200 Platform Without a Mechanical
Tools and Parts Required to Install the JCS 1200 Platform Without a Mechanical Lift
■ 55
Juniper Control System (JCS) 1200 Platform Hardware Guide
■
■
■
■
■
■
■
■
Removing a JCS 1200 Fan Module on page 116
Removing a JCS 1200 Fan Shuttle on page 122
Removing a JCS 1200 Management Module or Module Filler on page 124
Removing a JCS 1200 Media Tray on page 128
Removing a JCS 1200 Power Module on page 138
Removing a JCS 1200 Routing Engine on page 140
Removing a JCS 1200 Switch Module or Module Filler on page 143
Lifting the JCS 1200 Platform into the Rack or Cabinet on page 56
Lifting the JCS 1200 Platform into the Rack or Cabinet
Before you begin, see the following topics:
■
■
Tools and Parts Required to Install the JCS 1200 Platform Without a Mechanical
Removing Components from the JCS 1200 Platform on page 55
Lifting the chassis and mounting it in a rack requires four people. The empty chassis weighs approximately 329 lb (149.6 kg).
1.
Ensure the rack is in its permanent location and is secured to the building.
2.
3.
4.
5.
6.
Position the JCS 1200 platform in front of the rack or cabinet, centering it in front of the mounting shelves. Use a pallet jack if one is available.
With one person on each side and one person in the front, hold onto the bottom of the chassis and carefully lift it onto the large and small (if installed) mounting shelves.
Carefully slide the JCS 1200 platform onto the mounting shelves so that the bottom of the chassis and the mounting shelves overlap by approximately 2 in.
Install a mounting screw into each of the open mounting holes in the rack-mounting flanges to fasten the chassis to the rack, starting from the bottom.
Visually inspect the alignment of the JCS 1200 platform. If the JCS 1200 platform is installed properly in the rack, all the mounting screws on one side of the rack should be aligned with the mounting screws on the opposite side, and the platform should be level.
Related Topics
■
■
■
■
Tools and Parts Required to Install the JCS 1200 Platform Without a Mechanical
Removing Components from the JCS 1200 Platform on page 55
Installing the JCS 1200 Mounting Hardware for a Four-Post Rack or
Installing the JCS 1200 Mounting Hardware for an Open-Frame Rack on page 46
56 ■
Lifting the JCS 1200 Platform into the Rack or Cabinet
Chapter 6: Installing the JCS 1200 Platform
Reinstalling Components into the JCS 1200 Platform
NOTE: For detailed instructions on reinstalling JCS 1200 components, see the installation procedure for each component.
To reinstall components:
1.
2.
3.
Attach an electrostatic discharge (ESD) grounding strap to your bare wrist and connect the strap to one of the ESD points on the chassis.
Slide each component into the chassis evenly so that it does not become stuck or damaged.
Tighten screws, as needed, for each component.
NOTE: Make sure that all empty slots are covered with a blank panel before operating the JCS 1200 platform.
Related Topics
■
■
■
■
■
■
■
■
Preventing Electrostatic Discharge Damage to the JCS 1200 Platform on page 154
Installing a JCS 1200 Fan Module on page 118
Installing a JCS 1200 Fan Shuttle on page 123
Installing a JCS 1200 Management Module or Module Filler on page 125
Installing a JCS 1200 Media Tray on page 129
Installing a JCS 1200 Power Module on page 139
Installing a JCS 1200 Routing Engine on page 141
Installing a JCS 1200 Switch Module or Module Filler on page 143
Reinstalling Components into the JCS 1200 Platform
■ 57
Juniper Control System (JCS) 1200 Platform Hardware Guide
58 ■
Reinstalling Components into the JCS 1200 Platform
Chapter 7
Connecting the JCS 1200 Platform
This chapter discusses the following procedures:
■
■
■
■
■
■
■
■
■
■
Before you Begin Connecting the JCS 1200 Platform on page 59
Tools and Parts Required for Connecting the JCS 1200 Platform on page 60
Supplying Power to the JCS 1200 Platform on page 60
Connecting the JCS 1200 Management Module to the Network on page 68
Establishing Your JCS 1200 Management Module Connection on page 70
Connecting a Console to the JCS 1200 Routing Engines on page 72
Powering On a JCS 1200 Routing Engine on page 73
Powering Off a JCS 1200 Routing Engine on page 74
Connecting the JCS 1200 Platform to a T-series Routing Platform on page 74
Verifying that the JCS 1200 Platform is Powered On Correctly on page 79
Before you Begin Connecting the JCS 1200 Platform
Before connecting the T-series routing platform to the JCS 1200 platform, ensure that the bootROM version for all FPCs is ROM Monitor Version 6.4 or later. If an FPC bootROM version is earlier than Version 6.4, the FPC will not come online. To upgrade the firmware, you must contact your Juniper Networks customer support representative.
To determine if you need to upgrade the FPC firmware, display the version of the firmware on all FPCs by issuing the show chassis firmware
command: user@host> show chassis firmware
Part Type Version
FPC 0 ROM Juniper ROM Monitor Version 7.5b4
O/S Version 9.1-20080222.0 by builder on 2008-0
FPC 1 ROM Juniper ROM Monitor Version 6.4b18
O/S Version 9.1-20080222.0 by builder on 2008-0
FPC 2 ROM Juniper ROM Monitor Version 7.5b4
O/S Version 9.1-20080222.0 by builder on 2008-0
FPC 4 ROM Juniper ROM Monitor Version 6.4b18
O/S Version 9.1-20080222.0 by builder on 2008-0
FPC 5 ROM Juniper ROM Monitor Version 6.4b20
O/S Version 9.1-20080222.0 by builder on 2008-0
FPC 6 ROM Juniper ROM Monitor Version 7.5b4
O/S Version 9.1-20080222.0 by builder on 2008-0
Before you Begin Connecting the JCS 1200 Platform
■ 59
Juniper Control System (JCS) 1200 Platform Hardware Guide
FPC 7 ROM Juniper ROM Monitor Version 6.4b20
O/S Version 9.1-20080222.0 by builder on 2008-0
SPMB 0 ROM Juniper ROM Monitor Version 6.4b18
O/S Version 9.1-20080222.0 by builder on 2008-0
SPMB 1 ROM Juniper ROM Monitor Version 6.4b18
O/S Version 9.1-20080222.0 by builder on 2008-0
CAUTION: By default, SNMP is enabled on the management module. Do not disable
SNMP. If you disable SNMP, you might not be able to access the management module.
Related Topics
■
Connecting the JCS 1200 Platform to a T-series Routing Platform on page 74
Tools and Parts Required for Connecting the JCS 1200 Platform
To connect the JCS 1200 platform to T-series routing platforms, power, and management devices and to power on the platform, you need the following tools and parts:
■
■
2.5-mm Phillips (+) screwdriver
7/16-in. hexagonal-head external drive socket wrench, or nut driver, with a torque range between 23 lb-in. (2.6 Nm) and 25 lb-in. (2.8 Nm), for tightening nuts to terminal studs on each power supply on a DC-powered router.
CAUTION: Do not substitute a nonmetric nut driver or wrench. A tool that does not fit the nuts exactly can damage them. If a 10-mm. tool is not available, use pliers or an adjustable wrench.
Related Topics
■
■
■
■
■
■
■
■
Wire cutters
Pliers
Electrostatic discharge (ESD) grounding wrist strap
JCS 1200 Platform Power Overview on page 61
Connecting the JCS 1200 Management Module to the Network on page 68
Establishing Your JCS 1200 Management Module Connection on page 70
Connecting a Console to the JCS 1200 Routing Engines on page 72
Connecting the JCS 1200 Platform to a T-series Routing Platform on page 74
Supplying Power to the JCS 1200 Platform
Topics include:
■
■
JCS 1200 Platform Power Overview on page 61
Connecting the JCS 1200 AC Platform to AC Power on page 62
60 ■
Tools and Parts Required for Connecting the JCS 1200 Platform
Chapter 7: Connecting the JCS 1200 Platform
■
■
Connecting the JCS 1200 DC Platform to DC Power on page 63
Disconnecting Power from the JCS 1200 Platform on page 65
JCS 1200 Platform Power Overview
The JCS 1200 platform does not have a power switch. The platform has four power connectors; each powers a power module. As viewed from the rear of the JCS 1200 platform, power connector 1 (top-right connector) supplies power to power module bay 1, power connector 2 (bottom-left connector) supplies power to power module
2, power connector 3 (top-left connector) supplies power to power module 3, and power connector 4 (bottom-right connector) supplies power to power module 4 (see
Figure 25: Direction of Power from Power Connectors to Power Modules on the
JCS 1200 Platform
Power modules 1 and 2 are redundant and provide power to Routing Engine bays
1 through 6; power modules 3 and 4 are redundant and provide power to Routing
Engine bays 7 through 12. To ensure power redundancy, a typical power configuration is to supply power to power connectors 1 and 4 from one power source location while supplying power to power connectors 2 and 3 from another power source
location. The power domains are shown in Figure 26 on page 62.
JCS 1200 Platform Power Overview
■ 61
Juniper Control System (JCS) 1200 Platform Hardware Guide
Figure 26: Logical View of Power Domains on the JCS 1200 Platform
NOTE: The release handles on the fan shuttle have a safety switch that disables power output from the power boxes. If the release handles are not secured to the chassis with the thumbscrews, the JCS 1200 platform will not power on.
Related Topics
■
■
Connecting the JCS 1200 AC Platform to AC Power on page 62
Connecting the JCS 1200 DC Platform to DC Power on page 63
Connecting the JCS 1200 AC Platform to AC Power
The JCS 1200 platform has four AC power C20 input connectors. The appliance coupler at the female end of the detachable AC power cord inserts into the AC power input connector. The coupler is type C20 (right angle) as described by International
Electrotechnical Commission (IEC) standard 60320. The plug at the male end of the power cord fits into the power source receptacle that is standard for your geographical location. Use the AC power cords to connect AC power to the JCS 1200 platform.
To supply power to the JCS 1200 platform:
1.
2.
Attach an electrostatic discharge (ESD) grounding strap to your bare wrist and connect the strap to one of the ESD points on the chassis.
Connect one end of each power cord to a power connector on the rear of the
JCS 1200 platform.
3.
Connect the other end of each power cord to a 200-240 volt, 20-amp power distribution unit or appropriate electrical outlet. An external surge protective device (SPD) is not required at the AC power input of the JCS 1200 platform.
62 ■
Connecting the JCS 1200 AC Platform to AC Power
Chapter 7: Connecting the JCS 1200 Platform
The Routing Engines in the JCS 1200 platform are connected to power but are not turned on. After the JCS 1200 platform has power, depending on the configuration settings, the Routing Engines might have to be individually turned on.
Related Topics
■
JCS 1200 Platform Power Overview on page 61
■
■
■
Preventing Electrostatic Discharge Damage to the JCS 1200 Platform on page 154
Powering On a JCS 1200 Routing Engine on page 73
Connecting the JCS 1200 DC Platform to DC Power on page 63
Connecting the JCS 1200 DC Platform to DC Power
The JCS 1200 DC power inputs are configured for DC isolated return (DC-I). The DC return terminal or conductor is not connected to the equipment frame or the grounding means of the equipment.
CAUTION: Only trained service personnel other than Juniper Networks service technicians are authorized to make the connections to and disconnections from the
–48 volt DC power source. Juniper Networks service technicians are not certified or authorized to install or remove the –48 volt power cable. The customer is responsible for ensuring that only trained service personnel install or remove the –48 volt power cable.
The JCS 1200 DC platform has four DC power terminal connectors (see
Figure 27 on page 63). Each DC terminal has four M6 (0.25-inch) studs, one for –48
V DC, one for RETURN (
RTN
), and two for connecting the grounding cable (
GND
).
Each terminal has a terminal cover. Remove the terminal cover before connecting cables to each terminal, and reinstall the terminal cover on each terminal before
supplying power to the JCS 1200 platform. For more information, see “Replacing a
JCS 1200 DC Terminal Cover” on page 115.
Figure 27: JCS 1200 DC Power Terminal Connectors
Connecting the JCS 1200 DC Platform to DC Power
■ 63
Juniper Control System (JCS) 1200 Platform Hardware Guide
2.
3.
To connect the JCS 1200 DC platform to DC power:
1.
Ensure that the voltage across the DC power source cable leads is 0 V and that there is no chance that the cable leads might become active during installation.
4.
5.
6.
Verify that a licensed electrician has attached the cable lugs to the power cables.
Switch both circuit breakers on the power supply faceplate to the off position
( O ).
Attach an electrostatic discharge (ESD) grounding strap to your bare wrist and connect the strap to one of the ESD points on the chassis.
Remove the terminal cover for each terminal.
Attach the lugs on the DC source power cables to the terminal studs, making sure the cables are not touching or in the way of any JCS 1200 platform components. When connecting a cable lug to each stud, install a flat washer on the stud, install the cable lug, install a flat washer, install a split washer, and then
install a nut (see Figure 28 on page 64). Torque the wiring terminal nuts to
13.3 lb-in. (1.5 Nm).
Figure 28: Attaching the Cable Lugs to the JCS 1200 DC Power Terminal Connectors a.
Attach the positive (+) DC source power cable lugs to the RTN (return) terminals.
b.
c.
Attach the negative (–) DC source power cable lugs to the
–48V
(input) terminals.
Attach the safety ground wire to the other two terminals.
7.
8.
Verify that the power and ground cabling are correct.
Replace the terminal cover for each terminal.
64 ■
Connecting the JCS 1200 DC Platform to DC Power
Chapter 7: Connecting the JCS 1200 Platform
The Routing Engines in the JCS 1200 platform are connected to power but are not turned on. After the JCS 1200 platform has power, depending on the configuration settings, the Routing Engines might have to be individually turned on.
Related Topics
■
JCS 1200 Platform Power Overview on page 61
■
■
■
■
■
JCS 1200 DC Power Electrical Safety Guidelines on page 175
Replacing a JCS 1200 DC Terminal Cover on page 115
Preventing Electrostatic Discharge Damage to the JCS 1200 Platform on page 154
Powering On a JCS 1200 Routing Engine on page 73
Connecting the JCS 1200 AC Platform to AC Power on page 62
Disconnecting Power from the JCS 1200 Platform
You can disconnect power from the JCS 1200 platform by powering off the Routing
Engines and disconnecting the JCS 1200 platform from the power source.
To disconnect power from the JCS 1200 platform:
1.
2.
3.
Attach an electrostatic discharge (ESD) grounding strap to your bare wrist and connect the strap to one of the ESD points on the chassis.
Power off each Routing Engine (for more information, see “Powering Off a
JCS 1200 Routing Engine” on page 74).
Disconnect power from the JCS 1200 platform.
NOTE: After you disconnect the JCS 1200 platform from power, wait at least 5 seconds before you connect the JCS 1200 platform to power again.
■
JCS 1200 DC platform:
Disconnecting Power from the JCS 1200 Platform
■ 65
Juniper Control System (JCS) 1200 Platform Hardware Guide a.
Make sure the Routing Engines are powered off.
CAUTION: This device does not provide a power control button. Powering off Routing
Engines or removing power modules and switch modules does not turn off electrical current to the device. The device also might have more than one power cord. To remove all electrical current from the product, make sure that all power cords are disconnected from the power source.
CAUTION: Only trained service personnel other than Juniper Networks service technicians are authorized to make the connections to and disconnections from the
–48 volt DC power source. Juniper Networks service technicians are not certified or authorized to install or remove the –48 volt power cable. The customer is responsible for ensuring that only trained service personnel install or remove the –48 volt power cable.
b.
Turn off the power source.
c.
66 ■
Disconnecting Power from the JCS 1200 Platform
Chapter 7: Connecting the JCS 1200 Platform
Figure 29: DC Power Terminal Connectors on the JCS 1200 Platform
■ d.
Remove the nut, split washer, flat washer, and cable lug from each terminal post.
e.
Remove the power cables.
JCS 1200 AC platform: a.
Make sure the Routing Engines are powered off.
CAUTION: This device does not provide a power control button. Powering off Routing
Engines or removing power modules and switch modules does not turn off electrical current to the device. The device also might have more than one power cord. To remove all electrical current from the product, make sure that all power cords are disconnected from the power source.
b.
Disconnect all power cords on the JCS 1200 platform from the power connectors.
Related Topics
■
Preventing Electrostatic Discharge Damage to the JCS 1200 Platform on page 154
Disconnecting Power from the JCS 1200 Platform
■ 67
Juniper Control System (JCS) 1200 Platform Hardware Guide
■
■
Connecting the JCS 1200 AC Platform to AC Power on page 62
Connecting the JCS 1200 DC Platform to DC Power on page 63
Connecting the JCS 1200 Management Module to the Network
The management module supports network connection through an Ethernet connector
or a serial connector (see Figure 30 on page 68).
Figure 30: Ports on the JCS 1200 Management Module
All management module network connections to Routing Engines are made through the CLI. You can perform initial configuration of the management module after you connect it to your network; however, because some requirements are imposed by the default management module settings, it might be easier to perform these setup operations through a direct connection.
For direct connection of a computer to the management module Ethernet connector, you need a Category 5 or higher Ethernet cable.
Network connections through the serial connector may require an Advanced
Management Module (AMM) adapter.
See the JUNOS Protected System Domain Configuration Guide for information about accessing the management module CLI.
The following topics describe how to make typical network connections for a management module:
■
■
■
■
Connecting to the JCS 1200 Management Module Using a Network Ethernet
Connecting to the JCS 1200 Management Module Using a Direct Ethernet
Connecting to the JCS 1200 Management Module Using a Console Serial
Connecting to the JCS 1200 Management Module Using a Direct Serial
68 ■
Connecting the JCS 1200 Management Module to the Network
Chapter 7: Connecting the JCS 1200 Platform
Connecting to the JCS 1200 Management Module Using a Network Ethernet Connection
3.
4.
To connect the management module to the network using the Ethernet port:
1.
2.
Attach an electrostatic discharge (ESD) grounding strap to your bare wrist and connect the strap to one of the ESD points on the chassis.
Connect one end of an Ethernet cable to the Ethernet port on the management
module. See Figure 30 on page 68 for the location of input and output connectors
on the management module.
Connect the other end of the Ethernet cable to the network.
Check the Ethernet LEDs to make sure that the network connection is working.
■
■
A lit green Ethernet LINK LED indicates that there is an active connection through the port to the network.
A flashing green Ethernet activity ( TX/RX ) LED indicates that there is activity through the port over the network link.
Connecting to the JCS 1200 Management Module Using a Direct Ethernet Connection
To connect the Ethernet cable directly to the management module:
1.
Attach an electrostatic discharge (ESD) grounding strap to your bare wrist and connect the strap to one of the ESD points on the chassis.
2.
3.
4.
Connect one end of an Ethernet cable to the Ethernet port on the management
module. See Figure 30 on page 68 for the location of input and output connectors
on the management module.
Connect the other end of the Ethernet cable to the Ethernet port on the client computer.
Check the Ethernet LEDs to make sure that the network connection is working.
■
■
A lit green Ethernet
LINK
LED indicates that there is an active connection through the port to the network.
A flashing green Ethernet activity (
TX/RX
) LED indicates that there is activity through the port over the network link.
Connecting to the JCS 1200 Management Module Using a Console Serial Connection
To connect the management module to a console using a serial cable:
1.
2.
Attach an electrostatic discharge (ESD) grounding strap to your bare wrist and connect the strap to one of the ESD points on the chassis.
Plug one end of an RJ-45 serial cable into the serial connector on the management
module. See Figure 30 on page 68 for the location of input and output connectors
on the management module.
Connecting to the JCS 1200 Management Module Using a Network Ethernet Connection
■ 69
Juniper Control System (JCS) 1200 Platform Hardware Guide
NOTE: Some consoles require that you use an AMM adapter. If needed, plug an AMM adapter into the serial connector on the management module, and then connect the
serial cable. For information about the AMM adapter pinouts, see “Pinouts for the
3.
Connect the other end of the serial cable to your console.
The serial cable must have the characteristics shown in “Serial Cable
Characteristics for the JCS 1200 Management Module” on page 211.
Connecting to the JCS 1200 Management Module Using a Direct Serial Connection
To connect the management module to a client computer using a serial cable:
1.
Attach an electrostatic discharge (ESD) grounding strap to your bare wrist and connect the strap to one of the ESD points on the chassis.
2.
Plug one end of an RJ-45 serial cable into the serial connector on the management
module. See Figure 30 on page 68 for the location of input and output connectors
on the management module.
NOTE: The serial cable must have the characteristics shown in “Serial Cable
Characteristics for the JCS 1200 Management Module” on page 211.
3.
4.
Connect the other end of the serial cable to the serial connector of the client computer, such as a notebook computer.
Configure the serial port of the client computer to the following values:
■
■
Baud rate—57600
Parity—none
■
Stop bits—1
Related Topics
■
■
■
Preventing Electrostatic Discharge Damage to the JCS 1200 Platform on page 154
Tools and Parts Required for Connecting the JCS 1200 Platform on page 60
Establishing Your JCS 1200 Management Module Connection on page 70
Establishing Your JCS 1200 Management Module Connection
The management module has the following default settings:
■
■
■
■
IP address: 192.168.70.125
Subnet: 255.255.255.0
User ID: USERID (all capital letters)
Password: PASSW0RD (note the number zero, not the letter O, in PASSW0RD)
70 ■
Connecting to the JCS 1200 Management Module Using a Direct Serial Connection
Chapter 7: Connecting the JCS 1200 Platform
By default, the management module is configured to respond to DHCP first before using its static IP address.
The client computer that you connect to the management module must be configured to operate on the same subnet as the management module. The IP address of the management module must also be in the same local domain as the client computer.
To connect to the management module for the first time, you must change the IP properties on the client computer.
You can use one of two interfaces to connect to the management module for the first time. If you are connecting to the management module through an Ethernet connection, you can Telnet to the management module and use the CLI to configure the module. If you are connecting through a serial connection, you can use a terminal emulator to access the CLI.
The following topics describe how to establish a session between a client computer and the management module to perform initial configuration of the JCS 1200 platform.
■
■
Establishing Your JCS 1200 Management Module Connection Using a Direct
Ethernet Connection on page 71
Establishing Your JCS 1200 Management Module Connection Using a Direct Serial
Establishing Your JCS 1200 Management Module Connection Using a Direct Ethernet
Connection
After you connect the Ethernet cable from the management module to the client computer:
1.
Make sure that the subnet of the client computer is set to the same value as the default management module subnet (255.255.255.0).
2.
3.
Open a console window and log in to the default management module IP address
(192.168.70.125).
Enter the default user name, USERID, and the default password, PASSW0RD
(note the number zero, not the letter O, in PASSW0RD), to start the remote session.
After you connect the client computer to the management module for the first time, perform initial configuration of the JCS 1200 platform. See the JUNOS Protected System
Domain Configuration Guide for configuration instructions.
Establishing Your JCS 1200 Management Module Connection Using a Direct Serial
Connection
After you connect the serial cable from the management module to the client computer:
1.
Make sure that the serial port of the client computer is set to the following settings:
■
■
Baud rate—57600
Parity—none
Establishing Your JCS 1200 Management Module Connection Using a Direct Ethernet Connection
■ 71
Juniper Control System (JCS) 1200 Platform Hardware Guide
■
Stop bits—1
2.
3.
Open a terminal emulator window and establish a connection to the management module serial port.
Enter the default user name, USERID, and the default password, PASSW0RD
(note the number zero, not the letter O, in PASSW0RD), to start the remote session.
Related Topics
After you connect to the management module for the first time, perform initial configuration of the JCS 1200 platform. See the JUNOS Protected System Domain
Configuration Guide for CLI configuration instructions.
■
Tools and Parts Required for Connecting the JCS 1200 Platform on page 60
■
Connecting the JCS 1200 Management Module to the Network on page 68
Connecting a Console to the JCS 1200 Routing Engines
To access the Routing Engines from a console, you must use the serial port breakout cable provided with the chassis to connect the JCS 1200 platform. The breakout cable provides a direct serial interface to each Routing Engine in the JCS 1200 platform
and contains 14 RJ-45 serial cable connectors (see Figure 31 on page 72).
Figure 31: JCS 1200 Serial Port Breakout Cable
NOTE: Only 12 of the 14 RJ-45 serial cable connectors are used to connect the console to the Routing Engines. Connectors 13 and 14 are reserved for future use.
To connect the console:
1.
Attach an electrostatic discharge (ESD) grounding strap to your bare wrist and connect the strap to one of the ESD points on the chassis.
2.
3.
Connect the serial connector on the cable to the serial port connector on the alarm panel module of the JCS 1200 platform.
Connect the each of the RJ-45 connectors on the cable to your console.
72 ■
Connecting a Console to the JCS 1200 Routing Engines
Chapter 7: Connecting the JCS 1200 Platform
NOTE: Some consoles require that you use an CPU adapter. If needed, connect a
CPU adapter to each of the 12 RJ-45 connectors on the breakout cable. Then connect each CPU adapter to your console. For information about the CPU adapter pinouts,
see “Pinouts for the RJ-45 Adapters” on page 212.
Related Topics
■
■
■
■
■
■
Preventing Electrostatic Discharge Damage to the JCS 1200 Platform on page 154
Tools and Parts Required for Connecting the JCS 1200 Platform on page 60
JCS 1200 Routing Engine Description on page 24
JCS 1200 Routing Engine Control Panel Buttons and LEDs on page 25
Powering On a JCS 1200 Routing Engine on page 73
Powering Off a JCS 1200 Routing Engine on page 74
Powering On a JCS 1200 Routing Engine
After you connect the Routing Engine to power through the JCS 1200 platform, the
Routing Engine can start in any of the following ways:
■
You can press the power control button on the front of the Routing Engine behind
the control panel door (see “JCS 1200 Routing Engine Control Panel Buttons and
NOTE: Wait until the power-on LED on the Routing Engine flashes slowly before you press the power control button. While the service processor in the management module is initializing, the power-on LED does not flash, and the power control button on the Routing Engine does not respond.
While the Routing Engine is starting, the power-on LED on the front of the Routing
Engine is lit.
■
■
■
If a power failure occurs, the JCS 1200 platform and then the Routing Engine can start automatically when power is restored if the Routing Engine is configured through the management module to do so.
You can power on the Routing Engine remotely through the management module.
The wake-on-LAN feature can power on the Routing Engine if the following conditions are met:
■
The Routing Engine is connected to power (the power-on LED is flashing slowly).
■
The operating system supports the wake-on-LAN feature.
■
The wake-on-LAN feature has not been disabled through the management module.
Powering On a JCS 1200 Routing Engine
■ 73
Juniper Control System (JCS) 1200 Platform Hardware Guide
Related Topics
■
■
■
■
■
JCS 1200 Routing Engine Description on page 24
JCS 1200 Routing Engine Control Panel Buttons and LEDs on page 25
Powering Off a JCS 1200 Routing Engine on page 74
Replacing a JCS 1200 Routing Engine on page 140
Locating the JCS 1200 Routing Engine Serial Number on page 203
Powering Off a JCS 1200 Routing Engine
When you power off the Routing Engine, it is still connected to power through the
JCS 1200 platform. The Routing Engine can respond to requests from the service processor, such as a remote request to power on the Routing Engine. To remove all power from the Routing Engine, you must remove it from the JCS 1200 platform.
Issue the shutdown –T system:blade[x] command (where x is a value of 1 through 12) from the management module CLI. The command shuts down the Routing Engines cleanly, so their state information is preserved. For more information, see the JUNOS
Protected System Domain Configuration Guide.
The Routing Engine can then be powered off in any of the following ways:
■
■
You can press the power control button for more than four seconds on the
Routing Engine behind the control panel door (see “JCS 1200 Routing Engine
Control Panel Buttons and LEDs” on page 25).
If the system is not operating correctly, the management module will automatically power off the Routing Engine.
Related Topics
■
■
■
■
JCS 1200 Routing Engine Description on page 24
JCS 1200 Routing Engine Control Panel Buttons and LEDs on page 25
Powering On a JCS 1200 Routing Engine on page 73
Replacing a JCS 1200 Routing Engine on page 140
Connecting the JCS 1200 Platform to a T-series Routing Platform
You can connect up to three of the following T-series routing platforms running
JUNOS Release 9.2 or later to the JCS 1200 platform: T320 router, T640 routing node, and T1600 routing node. The following procedures describe connecting the JCS 1200 platform to a T-series routing platform:
■
■
■
Replacing the Standard CBs in the T-series Routing Platform on page 75
Connecting an Offline T-series Routing Platform to the JCS 1200
Powering On the T-series Routing Platform on page 78
74 ■
Powering Off a JCS 1200 Routing Engine
Chapter 7: Connecting the JCS 1200 Platform
Replacing the Standard CBs in the T-series Routing Platform
Before you connect an offline T-series routing platform to the JCS 1200 platform, you must replace the standard control boards (CBs) with T-CBs. To replace the CBs with T-CBs:
1.
If the routing platform is powered on, issue the request system halt both-routing-engines
operational mode command from the console or other management device connected to the routing platform. The command shuts down the Routing Engines cleanly, so their state information is preserved.
user@host> request system halt both-routing-engines
2.
3.
Wait until a message appears on the console confirming that the operating system has halted. For more information about the command, see the JUNOS System
Basics and Services Command Reference.
Attach an electrostatic discharge (ESD) grounding strap to your bare wrist and connect the strap to one of the ESD points on the chassis.
Switch all circuit breakers on the power supply faceplates to the off position ( O ).
NOTE: The CBs and T-CBs are hot-removable and hot-insertable if the routing node contains redundant host subsystems. However, we recommend that you power off the routing platform before you replace the CBs and T-CBs.
4.
Set the switches on each T-CB:
■
Set the chassis ID switch to 0. You must use the same chassis ID on each
T-CB.
■
Set the
M/S
switch on the T-CB faceplate to
S
.
5.
6.
Replace each CB with a T-CB. Use the standard replacement procedure described in the hardware guide for your routing platform.
You can optionally upgrade the Routing Engines in the routing platform. To replace each Routing Engine, follow the standard replacement procedure described in the hardware guide for your routing platform.
Connecting an Offline T-series Routing Platform to the JCS 1200 Platform
After you replace the CBs with T-CBs, you connect each T-CB on the T-series routing
platform to each switch module on the JCS 1200 platform. Figure 32 on page 76
shows the location of the switch modules on the JCS 1200 platform.
Replacing the Standard CBs in the T-series Routing Platform
■ 75
Juniper Control System (JCS) 1200 Platform Hardware Guide
Figure 32: Location of Switch Modules on the JCS 1200 Platform
To connect the T-CBs (see Figure 33 on page 77):
1.
Attach an electrostatic discharge (ESD) grounding strap to your bare wrist and connect the strap to one of the ESD points on the chassis.
2.
3.
Plug an ETH adapter into the top RJ-45 port (labeled 1 ) of switch module 1 on the JCS 1200 platform.
Connect one end of a UTP Category 5 cable to the ETH adapter.
4.
Plug the other end of the cable into the port labeled
CIP
on
T-CB-0
. Dress the cable appropriately.
NOTE: The RJ-45 port labeled AUX on a T-CB is reserved for future use.
5.
If you installed a redundant switch module into switch module bay 2: a.
Plug an ETH adapter into the top RJ-45 port (labeled on the JCS 1200 platform.
1 ) of switch module 2 b.
Connect one end of a UTP Category 5 cable to the ETH adapter.
c.
Plug the other end of the cable into the port labeled CIP on T-CB-1 . Dress the cable appropriately.
76 ■
Connecting an Offline T-series Routing Platform to the JCS 1200 Platform
Chapter 7: Connecting the JCS 1200 Platform
Figure 33: Connecting the JCS 1200 Platform to a T-series Routing Platform
6.
Repeat 2 through 5 to connect up to two additional T-series routing platforms
to RJ-45 ports labeled 2 and 3 on the JCS 1200 switch module.
NOTE: To connect more than one T-series routing platform, each routing platform must run JUNOS Release 9.2 or later.
NOTE: A switch module has six external 1000Base-T Ethernet ports for 10/100/1000
Mbps connections to external Ethernet devices, such as backbones, end stations, and servers. These ports are identified as EXT1, EXT2, EXT3, EXT4, EXT5, and EXT6 in the switch configuration menus and are labeled
1
through
6
(from top to bottom) on the JCS 1200 switch module.
NOTE: The connections between the switch modules and the T-CBs are proprietary
Ethernet connections. Do not attempt to connect these components through a switch or hub.
Connecting an Offline T-series Routing Platform to the JCS 1200 Platform
■ 77
Juniper Control System (JCS) 1200 Platform Hardware Guide
Powering On the T-series Routing Platform
After you have connected the control planes between the T-series routing platform and the JCS 1200 platform, power on the routing platform, monitor the boot process, and verify the connections. Follow this procedure:
1.
Attach an electrostatic discharge (ESD) grounding strap to your bare wrist and connect the strap to one of the ESD points on the chassis.
2.
Switch the circuit breakers on one of the power supplies to the on position (
|
) and observe the LEDs on the power supply faceplate. If the power supply is correctly installed and is functioning properly, the DC OK LED lights steadily, and the CB ON LED blinks momentarily, then lights steadily.
NOTE: After powering off a power supply, wait at least 60 seconds before powering it back on. After powering on a power supply, wait at least 60 seconds before powering it off.
If the system is completely powered off when you power on the power supply, the
Routing Engine boots as the power supply completes its startup sequence. If the
Routing Engine finishes booting and you need to power off the system again, first issue the CLI request system halt command.
After a power supply is powered on, it can take up to 60 seconds for status indicators—such as the output status LED on the power supply, the show chassis command display, and messages on the LED display on the craft interface—to indicate that the power supply is functioning normally. Ignore error indicators that appear during the first 60 seconds.
3.
4.
Repeat Step 2 for the remaining power supply.
On an external management device connected to the console or auxiliary port of the CIP, monitor the startup process to verify that the system has booted properly.
NOTE: You do not need to reboot the JCS 1200 platform after the routing platform has booted.
Related Topics
■
■
■
■
■
Preventing Electrostatic Discharge Damage to the JCS 1200 Platform on page 154
JCS 1200 Switch Module Description on page 27
JCS 1200 Switch Module Components and LEDs on page 27
Replacing the Standard CBs in the T-series Routing Platform on page 75
Verifying that the JCS 1200 Platform is Powered On Correctly on page 79
78 ■
Powering On the T-series Routing Platform
Chapter 7: Connecting the JCS 1200 Platform
Verifying that the JCS 1200 Platform is Powered On Correctly
Related Topics
■
■
■
■
■
After you connect the cables to the modules and route the cables, complete the following steps to start the JCS 1200 platform and verify that it is working correctly:
1.
Make sure that the following LEDs are lit, which indicate that the device is working correctly:
■
Input power and output power LEDs on each power module
■
OK LED on each management module
■
OK LED on each switch module
2.
3.
Make sure that the power-on LED on each Routing Engine is lit, either steady or flashing slowly.
Make sure there are no fault or error LEDs lit on any of the modules.
JCS 1200 Routing Engine Control Panel Buttons and LEDs on page 25
JCS 1200 Power Module LEDs on page 23.
JCS 1200 Management Module Connectors and LEDs on page 16
JCS 1200 Switch Module Components and LEDs on page 27
Replacing the Standard CBs in the T-series Routing Platform on page 75
Verifying that the JCS 1200 Platform is Powered On Correctly
■ 79
Juniper Control System (JCS) 1200 Platform Hardware Guide
80 ■
Verifying that the JCS 1200 Platform is Powered On Correctly
Chapter 8
Configuration Guidelines
■
Configuring the JCS 1200 Platform on page 81
Configuring the JCS 1200 Platform
CAUTION: By default, SNMP is enabled on the management module. Do not disable
SNMP. If you disable SNMP, your system might not function correctly.
Perform general configuration of the JCS 1200 platform and installed components through the management module. See the JUNOS Protected System Domain
Configuration Guide for information and instructions.
Related Topics
■
Configuring the JCS Management Module
■
■
Configuring the JCS Switch Module
Configuring an RSD and Creating PSDs