advertisement
Update Task Data
To delete a note
1. From the Project Properties, Task Properties, or the Resource Properties dialog box, click the Notes tab.
The Notes tab displays.
2. Select the note you want to delete from the History grid and click Delete.
The note is deleted from the History grid.
3. Click OK.
The dialog box closes.
Update Task Data
Use the Task Properties dialog box to define and edit task properties. To view this dialog box, double-click the header button to the left of the task you want to update.
This dialog box contains several tabs with fields that you can use to the create and edit data that you may not find available in a view. These tabs include the General,
Resources, Dependencies, Advanced, and Notes.
The availability and display of tabs in this dialog box depends on the type of task you have selected in the view:
■
If you select a phase or activity that is part of a master project or a subproject, only the General, Advanced, and Notes tabs display.
■
If you select a task or milestone that is part of a master project or a subproject, all tabs except the Subprojects tab display.
■
If you select a single task that was inserted into a master project as a subproject, all of the tabs display, including the Subprojects tab.
You can also update a task by right-clicking it in a spreadsheet view to access the shortcut menu which displays a list of task-related commands.
You can edit subproject task properties if you have Read/Write access or are saving a master project as an Open Workbench project (.rmp) file. You can also select multiple tasks and use one dialog box to edit the properties that they have in common or to define common properties. Use the Task Properties - Multiple Selections dialog box to do this.
Define Task General Properties
Use the General tab on the Task Properties dialog box to define the basic attributes of a task, such as the task name, ID, and type, and to identify the task as a key task on the project. You can also use this tab to apply properties to more than one task.
110 User Guide
Update Task Data
The following task schedules are displayed on this tab:
■
Current. The values displayed are the current values when calculating the critical path.
■
Baseline. The values displayed are automatically generated during project baselining and are read-only.
■
Early. The values displayed are automatically generated when you autoschedule your project and are read-only. An early schedule indicates the earliest a task can be completed, based on all the dependencies and constraints.
■
Late. The values displayed are automatically generated when you autoschedule your project and are read-only. A late schedule indicates the latest a task can be completed, based on all the dependencies and constraints.
To define task general properties
1. From a view that displays the task detail pane, right-click the task you want to define, and select Modify from the shortcut menu.
The General tab on the Task Properties dialog box opens.
2. Complete the following fields, and click OK:
Name
Defines the name of the task.
Category
Defines the name of the group or class to which this task belongs.
ID
Defines the unique identification code for this task.
Type
Defines the task type.
Values: Milestone, Task, Phase, or Activity
Default: Task
Key Task (Type)
Specifies whether the task is essential to the project and is a key task.
Duration
If this task is fixed, defines the length of time, in number of business days, that this task takes to complete.
Values: 1 through 20,863.
Fixed (Duration)
Specifies whether the task duration is fixed or variable.
Default: Cleared (Variable)
Chapter 5: Manage Projects 111
Update Task Data
Priority
Defines the task priority or priority inheritance if the task does not inherit the priority from parent or any higher WBS level.
Default: 10 if the parent task priority (or any higher WBS level) has not been set.
Values: 0 through 36. The lower the number, the higher the priority.
Example: If the task has a priority of 0 through 9, it is given the highest priority during scheduling. If the task has a priority of 11 through 36, it is given the lowest priority during scheduling.
Inherited (Priority)
Specifies whether you want this task to assume the priority of its parent task, or the next highest WBS level. When selected, the Priority field is not available.
Default: Selected
3. In the Schedule grid, define the following fields and click OK.
Start
Defines the task start date for the current schedule.
Default: Today's date or the next business date after today's date
Finish
Defines the task finish date for the current schedule.
Note: If you do not enter a finish date, Open Workbench calculates the date based on the tasks duration and start date.
Status
Defines the task completion status.
Values: Not Started, Started, or Completed
Default: Started
112 User Guide
Update Task Data
% Complete
Defines the progress of the task as a percentage. Regardless of the setting for the percent complete calculation method (on the Description tab of the Project
Properties dialog box), you can always edit the percent complete value for milestone tasks. This value can also be used in earned value calculations.
■
If the percent complete calculation method is set to Manual, you can edit this field for the project and for all summary and detail tasks. The status of a summary level task changes only if either the status or the % Complete value is manually modified.
■
If the percent complete calculation method is set to Effort, the value in this field is automatically calculated for the project and all summary and detail tasks.
■
If the percent complete calculation method is set to Duration, the value in this field is automatically calculated for the project and summary tasks based on the values manually entered for the detail tasks.
Values: 0 through 100.
Define Tasks as Key Tasks
Use the General tab on the Task Properties dialog box to mark tasks as key tasks. When you mark a task as a key task, the task is listed on the Key Tasks tab on the Project
Properties dialog box. You can always revert tasks to standard tasks.
To define a task as a key task
1. Right-click the task you want to define as a key task, and select Modify from the shortcut menu.
The General tab on the Task Properties dialog box opens.
2. Select the Key Task check box, and click OK.
The task is marked as a key task and the Task Properties dialog box closes.
Define Task Duration
Use the General tab on the Task Properties dialog box to enter or edit the task's duration. When you add tasks to a project, the task's default start date is today's date, or the next working date after today's date if today is a holiday or non-work day.
The maximum duration you can define can extend from present day to June 3, 2079.The duration for variable-duration tasks is automatically calculated. For fixed-duration tasks,
Open Workbench automatically calculates the task's finish date. If the task is fixed and you change the finish date, the duration is automatically calculated.
Chapter 5: Manage Projects 113
Update Task Data
During autoschedule, the duration is not changed for fixed-duration tasks, except when you enter an autoschedule start date that is greater then the task finish date. In this case, ETC is moved for resources and roles to start from the autoschedule start date and spread to the task finish date, depending on the loading pattern. If the autoschedule start date is greater than the task finish date, then the finish date is moved to the
Autoschedule start date, and all ETC is placed on that date.
To define a task's duration
1. Right-click the task you want to define duration, and select Modify from the shortcut menu.
The General tab on the Task Properties dialog box opens.
2. Complete the following field, and click OK:
Duration
Defines the number of business days for this task if this task's duration is fixed.
Values: 1 through 20,863.
Fixed (Duration)
Specifies whether the task's duration is fixed.
The Task Properties dialog box closes.
Edit Task Duration
Define Task Priority
Duration is the length of time, in business days, a task requires from conception to completion, including the start and finish dates. There are several ways you can change task duration. You can edit it directly on the desired position on the timescale in a spreadsheet view, such as the Gantt view, by using your mouse to click and drag the left or right side of the Gantt bar to the desired position on the timescale. You can also use the General tab on the Task Properties dialog box to edit task duration.
Note: For fixed-duration tasks, Open Workbench automatically calculates the task’s finish date. If the task is fixed and you change the finish date, the duration is automatically calculated.
The Task Priority controls the order in which tasks are scheduled during autoschedule, subject to dependencies and task and resources constraints. Autoschedule, therefore, schedules tasks with higher priority ahead of tasks with lower priority. Use the General tab on the Task Properties dialog box to define a task's priority. The priority value you enter in the Priority field is used when scheduling task.
If you do not define the task's priority but instead select the Inherited (Priority) check box on this tab, the priority is inherited from its parent task or the next highest WBS level. By default, this check box is selected.
114 User Guide
advertisement
* Your assessment is very important for improving the workof artificial intelligence, which forms the content of this project
Related manuals
advertisement
Table of contents
- 11 What's New in This Release
- 11 JRE Bundled with the Open Workbench Setup
- 11 Supported Languages
- 13 Introduction to Open Workbench
- 13 Installation and Upgrade
- 14 Minimum System Requirements
- 14 Before You Start
- 14 Install Open Workbench
- 16 How to Set Up Open Workbench
- 17 Define Open Workbench General Options
- 20 Define Open Workbench Default Options
- 22 Define Open Workbench File Location Options
- 23 Define Open Workbench WBS Level Labels
- 24 Define Open Workbench View Display Colors
- 24 Define Time Scales
- 26 How to Set Up Open Workbench with CA Clarity PPM
- 27 Set CA Clarity PPM Project Management Options
- 27 Install Open Workbench and CA Clarity PPM Schedule Connect
- 28 Set Microsoft Internet Explorer Web Browser Options
- 28 Uninstall Open Workbench and CA Clarity PPM Schedule Connect
- 28 Open Workbench Navigation Basics
- 28 About the File Menu
- 30 About the Ribbon Bar
- 35 About Views and the View Library
- 36 About Grid Columns and Rows
- 36 About Cutting and Copying Project Data
- 40 About Cutting and Copying Cells
- 41 Monitor Process Progress
- 41 Start Open Workbench
- 42 Quick Filter by Resources
- 42 About Calendars
- 43 Choose Calendar to Apply to Projects
- 43 Edit Calendars
- 45 Create New Calendars
- 45 Define Work Schedule and Holidays
- 46 Reset Holidays and Non-standard Workdays
- 46 Print Calendars
- 47 Delete Calendars
- 47 Access Online Help
- 50 Create Projects
- 50 Create Projects from a Command Line
- 51 Create Resources
- 52 About Resources
- 53 About Labor and Non-Labor Resource Types
- 53 Add Resources and Roles to Projects
- 55 Create Project Tasks
- 55 About Tasks
- 56 About Establishing Task and Resource Constraints
- 56 Assign Resources to Tasks
- 57 About Resource Loading Patterns
- 61 Set Resource Loading Pattern
- 62 Save Projects to Files
- 63 How Project Data is Shared Globally Across Projects
- 63 Open Projects from a File
- 64 How to Open CA Clarity PPM Projects in Open Workbench
- 65 Open Projects in Open Workbench using CA Clarity PPM
- 65 Open CA Clarity PPM Projects using Open Workbench
- 67 Open CA Clarity PPM Projects from a Command Line
- 70 How to Develop Project Schedules
- 70 How to Schedule Projects using Open Workbench
- 71 Recalculate Task Duration
- 72 Baseline Projects
- 72 Baselines and Earned Value Computations
- 73 Set Baselines
- 74 Display Baseline Data in Views
- 75 Edit Baselines
- 75 Rebaseline Projects
- 76 Multiple Baselines with Master Projects and Subprojects
- 77 Clear Baseline Values
- 78 Delete Baselines
- 78 Autoschedule Projects
- 80 Define Autoschedule Parameters
- 82 About Autoscheduling Master Projects
- 82 Autoschedule Projects from a Start Date
- 83 Autoschedule Projects from a Finish Date
- 83 Autoschedule by Task Priority
- 84 Override Task Lock during Autoschedule
- 85 Manually Schedule Projects
- 87 Schedule Subnets
- 88 Calculate Critical Path
- 88 How Critical Path is Calculated
- 91 Find Information in Projects
- 92 Define Search Criteria to Find Data
- 93 Update Project Data
- 93 Define Project Description Properties
- 94 Define Project Scheduling Properties
- 94 Define Project Resources Properties
- 97 View Tasks Marked as Key Tasks
- 98 Manage Multiple Projects
- 106 Define Project Advanced Properties
- 107 Add Notes
- 110 Update Task Data
- 110 Define Task General Properties
- 115 About Defining Task Resources Properties
- 119 About Task Dependencies Properties
- 129 Define Task Advanced Properties
- 133 Add Notes
- 135 Edit Multiple Tasks
- 136 Change Task Location in Project WBS
- 136 Shift Tasks
- 137 Delete Tasks
- 137 Update Resource Data
- 138 Define Resource or Role General Properties and Availability
- 139 Edit Resource Periodic Availability
- 140 Define Resource Advanced Properties
- 140 Define Resource Calendar
- 141 Add Notes
- 144 How to Enter Pending Estimates
- 146 Remove Resource Actual Usage on Tasks
- 146 About Editing Multiple Resources
- 147 Manage CA Clarity PPM Projects using Open Workbench
- 147 Refresh Project Data
- 149 About Resource Role Assignments
- 150 Cost Rate and Currency Data
- 151 About the CA Clarity PPM Rate Matrix
- 152 About the CA Clarity PPM Rate Matrix Extraction Job
- 152 Display Resource Billing Rates in Views
- 153 Vary Resource Billing Rates
- 153 About Multiple Baselines
- 154 How to Save Projects back to CA Clarity PPM
- 158 About CA Clarity PPM Project Locks
- 160 About Printing Project Data
- 160 Select Printer and Print Layout Options
- 161 Prepare Pages for Printing
- 162 Preview Project in a View Before Printing
- 163 Print Projects from Views
- 165 Tracking and Analysis Overview
- 166 How to Track Projects
- 166 Track Projects by Total Actual Usage
- 166 Track Projects by Periodic Actual Usage
- 167 Track Projects by Task Status
- 167 How to Track Resources
- 167 Track Resources by Total Actual Usage
- 168 Track Resources by Periodic Actual Usage
- 168 Actual Cost of Resource Task Assignments
- 169 Analyze Projects
- 169 How to Determine When and What to Analyze
- 170 Validate Project Plan Data
- 171 Analyze Projects with Earned Value Variances
- 173 About Analyzing Projects with Current Baseline
- 175 Create and Edit Filter Files
- 176 Create New Filters from Existing Filter Files
- 177 Create and Edit Sort Files
- 178 Create New Sorts from Existing Sort Files
- 178 Add View, Filter, or Sort Files to Library Groups
- 179 About Views
- 180 About Spreadsheet Views
- 180 About CPM Network Views
- 181 About the Open Workbench Library
- 182 Add New Library Groups
- 182 Change Items in Library Groups
- 183 Apply Views, Filters, Sorts to Library Groups
- 183 Define Views in Library Groups
- 183 Add Views to Library Groups
- 184 Remove Views from Library Groups
- 184 Configure Gantt Charts
- 186 Create Views
- 186 View Definition Dialog Box
- 190 About Field Names on Views
- 193 Apply Formats to Cells in Views
- 194 Apply Filters to Views
- 195 Apply Views to Projects
- 195 Insert and Delete Rows in Views
- 196 About Changing View Display Colors
- 196 Customize Colors
- 198 Define View Display Colors
- 199 Save Views
- 200 Edit Views
- 203 About Highlights
- 204 Create Highlights
- 204 Define Highlight Settings
- 205 Define Highlight Conditions
- 206 Define Highlight Formats
- 207 Change the Appearance of Fonts in Highlights
- 207 Change Gantt Symbol and Color Settings
- 208 Define Highlight Font Settings
- 209 Edit CPM Symbol and Color Settings
- 210 Save Highlights
- 210 Remove Highlights
- 211 Delete Highlights