advertisement
7. Verify furnace shut down by lowering thermostat setting below room temperature.
8. Verify that furnace restarts by raising thermostat setting above room temperature.
PRIME CONDENSATE TRAP WITH WATER
Condensate trap must be PRIMED or proper draining may not occur. The condensate trap has internal chambers which can
ONLY be primed by pouring water into the inducer drain side of condensate trap.
1. Remove upper inducer housing drain connection cap. (See
Fig. 51.)
2. Connect field-supplied 1/2-in. ID tube to upper inducer housing drain connection.
3. Insert field-supplied funnel into tube.
4. Pour 1 quart of water into funnel/tube. Water should run through inducer housing, overfill condensate trap, and flow into open field drain. (See Fig. 52.)
5. Remove funnel and tube from inducer housing and replace drain connection cap and clamp.
Fig. 52—Filling Condensate Trap
A99119
Fig. 51—Inducer Housing Drain Tube
A99118
OPERATE FURNACE
Follow procedures on operating instructions label attached to furnace.
FURNACE RESTART
With furnace operating, set thermostat below room temperature and observe that furnace goes off. Set thermostat above room temperature and observe that furnace restarts.
Step 4—Adjustments
SET GAS INPUT RATE
Furnace gas input rate on rating plate is for installations at altitudes up to 2000 ft.
44
In the U.S.A., the input ratings for altitudes above 2000 ft must be reduced by 2 percent for each 1000 ft above sea level.
In Canada, the input ratings must be derated by 5 percent for altitudes of 2001 ft to 4500 ft above sea level.
Adjust manifold pressure to obtain input rate.
Furnace input rate must be within ± 2 percent of input on furnace rating plate adjusted for altitude.
1. Determine Natural Gas Orifice Size And Manifold Pressure
For Correct Input.
a. Obtain average yearly heat value (at installed altitude) from local gas supplier.
b. Obtain average yearly specific gravity from local gas supplier.
c. Verify furnace model and size. Table 10 can only be used for furnaces with heating inputs of 20,000/13,000
(High/Low) Btuh per burner.
d. Find installation altitude in Table 10.
NOTE: For Canada altitudes of 2001 to 4500 ft, use U.S.A.
altitudes of 2001 to 3000 ft in Table 10.
e. Find closest natural gas heat value and specific gravity on
Table 10.
f. Follow heat value and specific gravity lines to point of intersection to find orifice size and manifold pressure settings for proper operation.
EXAMPLE: (0-2000 ft altitude using Table 10)
Heating value = 1050 Btu/cu ft
Specific gravity = 0.62
Therefore: Orifice No. 45
Manifold pressure 3.6-in. wc for high heat
1.5-in. wc for low heat
* Furnace is shipped with No. 45 orifices. In this example all main burner orifices are the correct size and do not need to be changed to obtain the proper input rate.
g. Check and verify burner orifice size in furnace. NEVER
ASSUME ORIFICE SIZE; ALWAYS CHECK AND
VERIFY.
2. Adjust Manifold Pressure To Obtain Input Rate.
a. Remove burner enclosure front.
NOTE: Manifold pressure MUST always be measured with burner enclosure front REMOVED.
b. Remove regulator seal caps that conceal adjustment screws for low-and high-heat gas valve pressure regulators. (See
Fig. 53.)
INLET
PRESSURE
TAP
ON/OFF
SWITCH
ON
F
F
O
LOW-FIRE
ADJUSTMENT
ALLEN SCREW
(UNDER CAP)
HIGH-FIRE
ADJUSTMENT
ALLEN SCREW
(UNDER CAP)
DO NOT bottom out gas valve regulator adjusting screw.
This can result in unregulated manifold pressure and result in excess overfire and heat exchanger failures.
NOTE: If orifice hole appears damaged or it is suspected to have been redrilled, check orifice hole with a numbered drill bit of correct size. Never redrill an orifice. A burr-free and squarely aligned orifice hole is essential for proper flame characteristics.
f. Move setup switch SW-1 to OFF position after completing low-heat adjustment.
g. Jumper R and W1 and W2 thermostat connections on control. (See Fig. 32.) This keeps furnace locked in high-heat operation.
h. Turn high-heat adjusting screw (3/32 hex Allen wrench) counterclockwise (out) to decrease input rate or clockwise
(in) to increase rate.
NOTE: DO NOT set high-heat manifold pressure less than 3.2-in.
wc or more than 3.8-in. wc for natural gas. If manifold pressure is outside this range, change main burner orifices.
i. When correct input is obtained, replace caps that conceal gas valve regulator adjustment screws. Main burner flame should be clear blue, almost transparent. (See Fig. 54.)
BURNER FLAME
BURNER
MANIFOLD
Fig. 54—Burner Flame
j. Remove jumper R-to-W1 and W2.
A89020
MANIFOLD
PRESSURE
TAP
A97358
Fig. 53—Redundant Automatic Gas Control Valve
c. Move setup switch SW-1 on control center to ON position.
This keeps furnace locked in low-heat operation.
d. Jumper R and W/W1 thermostat connections on control to start furnace.
e. Turn low-heat adjusting screw (3/32 hex Allen wrench) counterclockwise (out) to decrease input rate or clock-wise
(in) to increase input rate.
NOTE: DO NOT set low-heat manifold pressure less than 1.3-in.
wc or more than 1.7-in. wc for natural gas. If manifold pressure is outside this range, change main burner orifices.
45
DO NOT redrill orifices. Improper drilling (burrs, out-ofround holes, etc.) can cause excessive burner noise and misdirection of burner flames. This can result in flame impingement of burners and heat exchangers causing failures.
3. Verify Natural Gas Input Rate By Clocking Gas Meter.
NOTE: Be sure all pressure tubing, combustion-air and vent pipes, and burner enclosure front are in place when checking input by clocking gas meter.
a. Calculate high-altitude adjustment (if required).
UNITED STATES
At altitudes above 2000 ft, this furnace has been approved for a 2 percent derate for each 1000 ft above sea level. See
Example and Table 11 for derate multiplier factor.
CANADA
At installation altitudes from 2001 to 4500 ft, this furnace
j. Measure time (in sec) for gas meter to complete 1 revolution. Note reading.
k. Refer to Table 11 for cubic ft of gas per hr.
BURNER
ORIFICE
A93059
Fig. 55—Burner Orifice
EXAMPLE:
100,000 Btuh input furnace installed at 4300 ft.
Derate
Furnace Input Rate
X Multiplier =
at Sea Level
100,000
X
Factor
0.91
=
Furnace Input Rate at Installation
Altitude
91,000
Table 11—Altitude Derate Multiplier for U.S.A.
ALTITUDE
(FT)
0–2000
2001–3000
3001–4000
4001–5000
5001–6000
6001–7000
7001–8000
8001–9000
9001–10,000
PERCENT
OF DERATE
0
4–6
6–8
8–10
10–12
12–14
14–16
16–18
18–20
DERATE MULTIPLIER
FACTOR FOR U.S.A.*
1.00
0.95
0.93
0.91
0.89
0.87
0.85
0.83
0.81
* Derate multiplier factor is based on midpoint altitude for altitude range.
must be derated 5 percent by an authorized Gas Conversion
Station or Dealer. To determine correct input rate for altitude, see example above and use 0.95 as derate multiplier factor.
b. Reinstall burner box cover.
NOTE: Clocking gas input rate MUST always be performed with the burner box cover INSTALLED.
c. Check that gas valve adjustment caps are in place for proper input to be clocked.
d. Obtain yearly heat value average for local gas supply.
NOTE: Be sure heating value of gas used for calculations is correct for your altitude. Consult local gas utility for altitude adjustment of gas heating value.
e. Check and verify orifice size in furnace. NEVER ASSUME
THE ORIFICE SIZE. ALWAYS CHECK AND VERIFY.
f. Turn off all other gas appliances and pilots.
g. Move setup switch SW-1 to ON position. This keeps furnace locked in low-heat operation.
h. Jumper R-to-W/W1.
i. Let furnace run for 3 minutes in low-heat operation.
46
Table 12—Gas Rate (cu ft/hr)
SECONDS
FOR 1
REVOLUTION
34
35
36
37
30
31
32
33
38
39
40
45
46
47
48
49
41
42
43
44
23
24
25
26
19
20
21
22
27
28
29
14
15
16
17
18
10
11
12
13
106
103
100
97
120
116
113
109
95
92
90
80
78
76
75
73
88
86
84
82
157
150
144
138
189
180
171
164
133
129
124
257
240
225
212
200
SIZE OF TEST DIAL
1
Cu Ft
2
Cu Ft
5
Cu Ft
360
327
300
277
720
655
600
555
1800
1636
1500
1385
514 1286
480 1200
450 1125
424 1059
400 1000
379
360
343
327
313
300
288
277
267
257
248
783
750
720
692
947
900
857
818
667
643
621
212
206
200
195
240
232
225
218
189
185
180
160
157
153
150
147
176
172
167
164
529
514
500
486
600
581
563
545
474
462
450
400
391
383
375
367
439
429
419
409
SECONDS
FOR 1
REVOLUTION
88
90
92
94
80
82
84
86
96
98
100
110
112
116
120
124
102
104
106
108
66
68
70
72
59
60
62
64
74
76
78
54
55
56
57
58
50
51
52
53
41
40
39
38
45
44
43
42
38
37
36
33
32
31
30
29
35
35
34
33
54
53
51
50
61
60
58
56
48
47
46
67
65
64
63
62
SIZE OF TEST DIAL
1
Cu Ft
2
Cu Ft
5
Cu Ft
72
71
69
68
144
141
138
136
360
355
346
340
133
131
129
126
124
333
327
321
316
310
122
120
116
112
109
106
103
100
97
95
92
273
265
257
250
305
300
290
281
243
237
231
82
80
78
76
90
88
86
84
75
74
72
65
64
62
60
58
71
69
68
67
205
200
196
192
225
220
214
209
188
184
180
164
161
155
150
145
178
173
170
167 l. Multiply gas rate cu ft/hr by heating value (Btu/cu ft).
m. Move setup switch SW-1 to OFF position and jumper R and W1 and W2 thermostat connections. This keeps furnace locked in high-heat operation. Repeat items ’i’ through ’l’ for high-heat operation.
advertisement
* Your assessment is very important for improving the workof artificial intelligence, which forms the content of this project
Related manuals
advertisement
Table of contents
- 2 Safety Considerations
- 2 Introduction
- 5 Codes and Standards
- 5 Safety
- 5 General Installation
- 5 Combustion and Ventilation Air
- 5 Duct Systems
- 5 Acoustical Lining and Fibrous Glass Duct
- 5 Gas Piping and Gas Pipe Pressure Testing
- 5 Electrical Connections
- 5 Electrostatic Discharge (ESD) Precautions Procedure
- 6 Applications
- 6 General
- 6 Upflow Applications
- 6 Orientation)
- 8 Condensate Trap Field Drain Attachment
- 8 Pressure Switch Tubing
- 8 Drain Connections
- 8 Condensate Trap Freeze Protection
- 8 Downflow Applications
- 8 Condensate Trap Location
- 9 Condensate Trap Tubing
- 9 Condensate Trap Field Drain Attachment
- 9 Pressure Switch Tubing
- 10 Condensate Trap Freeze Protection
- 10 Applications
- 10 Condensate Trap Location
- 10 Condensate Trap Tubing
- 11 Condensate Trap Field Drain Attachments
- 11 Pressure Switch Tubing
- 11 Condensate Trap Freeze Protection
- 11 Construct a Working Platform
- 12 Horizontal Right (Supply-Air Discharge) Applications
- 12 Condensate Trap Location
- 12 Condensate Trap Tubing
- 13 Condensate Trap Field Drain Attachment
- 13 Pressure Switch Tubing
- 13 Condensate Trap Freeze Protection
- 13 Construct a Working Platform
- 13 Location
- 13 General
- 14 Equipment
- 14 Hazardous Locations
- 14 Installation
- 14 Leveling Legs (If Desired)
- 15 Applications
- 16 Installation in Horizontal Applications
- 16 Air Ducts
- 16 General Requirements
- 17 Ductwork Acoustical Treatment
- 17 Supply Air Connections
- 18 Return Air Connections
- 18 Filter Arrangement
- 18 Bottom Closure Panel
- 19 Gas Piping
- 20 Electrical Connections
- 20 115-V Wiring
- 21 24-V Wiring
- 22 Accessories
- 22 Direct Venting
- 25 Systems
- 25 Combustion-Air and Vent Piping
- 28 Kit Installation
- 32 Multiventing and Vent Terminations
- 32 Condensate Drain
- 32 General
- 33 Application
- 34 Condensation Drain Protection
- 34 Start-Up Adjustment and Safety Check
- 34 General
- 35 Sequence of Operation
- 36 (Adaptive Mode)
- 36 (Non-Adaptive Heating Mode)
- 37 Cooling Mode
- 39 Continuous Blower Mode
- 39 Thermidistat Mode
- 39 Continuous Blower Mode
- 40 Heat Pump
- 40 Start-Up Procedures
- 40 Purge Gas Lines
- 42 Component Self-Test
- 44 Prime Condensate Trap With Water
- 44 Operate Furnace
- 44 Furnace Restart
- 44 Adjustments
- 44 Set Gas Input Rate
- 47 Set Temperature Rise
- 47 Adjust Blower Off Delay (Heat Mode)
- 47 Set Thermostat Heat Anticipator
- 48 Check Safety Controls
- 48 Checklist