Measuring ionisation current
The ionisation current must be measured during burner start-up and maintenance or after a fault indication in the control box.
Measurement of ionisation current shortly after burner start during:
• Maintenance
• Start-up
• Fault indication.
The ionisation current can also be read out as a percentage via SatroPen.
To do so:
• Open plug connection between cable to control box and cable from ionisation electrode.
• Connect ammeter in series. Measuring range 0...200
µA DC.
l > 2 µA l < 2 µA
- OK
- Unsafe operation !
- Clean burner pipe
- Bend ionisation rod in flame area
- If necessary, replace combination electrode
- If necessary, reverse polarity on ignition transformer (induction current)
- Eliminate moisture and deposits.
Servicing air pressure monitor
• Detach silicone connecting hose and clean, check switching function.
• Replace air pressure monitor if switching function is no longer O.K.
To do so:
• Switch burner voltage-free and disconnect (7-pin connector X11).
• Unscrew cover.
• Disconnect electrical connectors.
• Release retaining screws on motor.
• Reassemble in reverse order.
"+" denotes the connecting point for pressure metering connection !
24
advertisement
Related manuals
advertisement
Table of contents
- 3 Overview
- 3 General information / safety information
- 3 Declaration of conformity
- 3 Checking scope of delivery and connection data
- 4 Operating instructions
- 4 Instruction of operating personnel
- 4 Maintenance and customer service
- 4 Key for code designation
- 4 Technical specifications
- 5 Installation
- 5 Installing flange and burner
- 5 Checking electrode setting
- 5 Installing gas assembly
- 6 Establishing electrical connections
- 7 Function
- 7 Control unit DMG
- 8 Air flow setting, dimension "A
- 9 Air flap positioning motor
- 10 Compact gas unit
- 10 Gas pressure monitor
- 11 Start-up
- 11 Adjustment tables RGN 120 / RGL
- 12 Adjustment tables RGN 120T / RGL 120T
- 13 Adjustment tables RGN 260 / RGL
- 14 Adjustment tables RGN 260T / RGL 260T
- 15 Adjusting gas burner and boiler
- 19 Calculation principle for gas burner adjustment
- 21 Design
- 21 Exploded drawing and spare parts/parts list RGN 120 / RGL
- 22 Exploded drawing and spare parts/parts list RGN 260 / RGL
- 23 Service instructions/dimensions
- 23 Service position
- 23 Reference dimensions, ignition and ionisation electrodes
- 24 Measuring ionisation current
- 24 Servicing air pressure monitor
- 25 Wiring diagrams
- 27 Troubleshooting
- 28 Burner overall dimensions / boiler connection dimensions
- 28 Working ranges