Final check and trial operation

To complete the installation, perform the following checks and tests to ensure that the air conditioner operates correctly.

Check the followings:

• Strength of the installation site

• Tightness of pipe connection to detect gas leak

• Electric wiring connection

• Heat-resistant insulation of the pipe

• Drainage

• Grounding conductor connection

• Correct operation (follow the steps below)

1. Press the Power button and check the following:

 The indicator on the indoor unit lights up.

 The airflow blade opens and the fan gears up for operation.

2. Press the Mode button to select Cool or Heat

(ARHS) mode.

In Cool mode, use Temp hr. + or button and set the temperature at 16 °C.

 In Heat mode, use Temp hr. + or button and set the temperature at 30 °C

(ARHS)

.

• Approximately 3~5 minutes later, outdoor unit will start to operate and the

Cool or Warm

(ARHS)

air will blow out.

• After 12 minutes of stationary condition check the indoor unit air treatment.

Cooling mode (indoor unit check)  Inlet air temp. - Outlet air temp:

From 10 °C to 12 °C (indicative delta T)

Heating mode (indoor unit check)

(ARHS)  Outlet air temp. - Inlet air temp:

From 11 °C to 14 °C (indicative delta T)

In heating mode, the indoor fan motor can remain off to avoid cold air blown into conditioned space

(ARHS)

.

3. Press the Air swing button and check the following:

 The airflow blades work properly.

4. Press the Power button to stop the operation.

• When you complete the installation successfully, hand over this manual to the user for storage in a handy and safe place.

Pump down procedure (when removing the product)

1. Press the Power button on the indoor unit for 5 seconds. Beep will sound immediately to let you know that the product is ready for pump down procedure. Please let the compressor run for more than 5 minutes.

2 . Release the valve caps on High and Low pressure side.

3 . Use L wrench to close the valve on the high pressure side.

4 . After approximately 2 minutes, close the valve on the low pressure side.

5 . Stop operation of the air conditioner by pressing the power button on the indoor unit or remote controller.

6 . Disconnect the pipes.