VAR8 / Variants - Installation Guide
1.2 Recommended Installation Procedure
!
!
Please read and observe the “ manual.
Safety and Precautions ” section on page 20 of this
1. If installing a VAR8 with a Network Interface Card, note that the Network Interface Card is configured, by default, for network operation using 3 audio network channels. If stand-alone operation or 1 or 2 channel only network operation is required, set the links on the Router board as described in Section “ 1.3 Link Settings for Stand-Alone, 1 or 2 Channel Only Network
Operation” on page 11 .
2. Mount the VAR8 into a 19-inch standard equipment rack.
M6 PAN HEAD POZIDRIV SCREW
M6 PLAIN WASHER
M6 CAGE NUT
DSP Audio Router power processor comms fault
SELECT BACK
FAULT
ACCEPT
FAULT
CLEAR
DEFAULT
LAMP
TEST
AUDIO
MON
!
Ensure that there is at least 1U of ventilated space between the unit and any source of heat (e.g. V400 amplifier mainframes).
3. Connect the rack and field cabling for control ports, audio inputs, audio outputs, signal monitoring,
CAN bus, RS232, and RS485, as appropriate.
!
Wiring to each VAR8 connector should be according to the diagram shown in Figure
3 on page 8 for EMC compliance.
The following drawings indicate the position of the connectors on the rear panel. Note that upper control port, A/B output, and network interface connectors may not be present, depending on the
VAR8 variant being installed.
Figure 1 on page 5 shows details of each connector. Section “ 2 Connections ” on page 12 describes the signals.
ADDITIONAL CONTROL PORTS
(ON EXP8 ONLY)
CONTROL PORTS AUDIO INPUTS
Issue: 01 complete, approved
Page 9 of 22
ENHANCED
AUDIO A OUTPUTS
(ON EXP8 ONLY)
VAR8 / Variants - Installation Guide
ENHANCED
AUDIO B OUTPUTS
(ON EXP8 ONLY)
AUDIO MONITORING
CAN BUS
RS232
STANDARD
AUDIO OUTPUTS
(See pinout in Table 1 , page 13 .)
RS485
FAULT RELAY
4. Connect the rack and field cabling for the network interface (if the ANIC8 Network Interface Card is used).
!
Wiring should be according to the diagram shown in Figure 2 on page 7 for EMC compliance.
Figure 1 on page 5 shows details of each connector. Section “ 2 Connections ” on page 12 describes the signals.
NETWORK UPSTREAM
NETWORK DOWNSTREAM
5. Connect the dual power supply (as appropriate) to the rear panel connector.
Section “ 2 Connections ” on page 12 describes the signals.
POWER SUPPLY
GND +V GND +V
6. The installation is now complete and ready for system commissioning.
Refer to the Commissioning Guide [ Table 2 - 3 ].
Issue: 01 complete, approved
Page 10 of 22
advertisement
Related manuals
advertisement
Table of contents
- 5 Installation
- 6 Installation Requirements
- 6 Cabling Requirements
- 9 Recommended Installation Procedure
- 11 Link Settings for Stand-Alone, 1 or 2 Channel Only Network Operation
- 12 Connections
- 16 Product Specification
- 19 Mechanical Dimensions
- 20 Safety and Precautions
- 20 Environmental
- 20 Electrical Safety
- 20 Lithium Battery
- 20 Unpacking and Handling
- 20 Packing for Repair
- 21 Reference Documentation
- 22 Service and Warranty
- 22 Exclusions