3 Commissioning Procedure. Huawei Technologies QISGRFU-1900

Add to My manuals
129 Pages

advertisement

3 Commissioning Procedure. Huawei Technologies QISGRFU-1900 | Manualzz

BTS3900(A) GSM

Commissioning Guide 3 Commissioning Procedure

3

Commissioning Procedure

This describes the commissioning procedure of the BTS. According to the transmission situation between the BSC and BTS, the commissioning procedure of the BTS can be classified into two types: commissioning procedure in transmission available scenario and commissioning procedure in transmission unavailable scenario.

Context l l

To solve common problems that occur during the commissioning, see

7 FAQs for BTS

Commissioning .

In this document, RFUs are classified into two types: DRFUs and GRFUs.

Procedure l Commissioning procedure in transmission available scenario

In the transmission available scenario, the transmission cables between the BSC and the

BTS are properly connected before the commissioning. Generally, the commissioning is performed on the BSC6000 LMT. If the commissioning can not be performed on the LMT independently, contact engineers on the BTS side to perform the commissioning task.

Issue 02 (2009-04-20) Huawei Proprietary and Confidential

Copyright © Huawei Technologies Co., Ltd.

3-1

3 Commissioning Procedure

Figure 3-1 Commissioning procedure (transmission available)

Run

BTS3900(A) GSM

Commissioning Guide

Remote operation

Run the BSC LMT

Check the Transmission and Networking

Check the software version

and the data configuration

Check the alarm information of the BTS

Cooperation of

local and remote operation

Commission the BTS services

Check the BTS environment alarms

End

Table 3-1 Commissioning procedure (transmission available)

No.

Operation Procedure

1 Operation on the

BSC LMT

Run the BSC LMT software. For details, see 4.1

Starting the LMT

.

Mandat ory/

Optiona l

Mandato ry

3-2 Huawei Proprietary and Confidential

Copyright © Huawei Technologies Co., Ltd.

Issue 02 (2009-04-20)

BTS3900(A) GSM

Commissioning Guide 3 Commissioning Procedure

No.

Operation Procedure Mandat ory/

Optiona l

Mandato ry

2

3

4

5 Operation on the

BTS side.

Check the transmission and networking to ensure that the transmission between the BBU and BSC, BBU and

RFU, cascaded BBUs, and cascaded RFUs is normal.

For details, see 4.2 Checking the Transmission and

Networking .

Check the software version and configuration data.

For details, see 4.3 Checking Software Version and

Data Configuration .

Check the alarm information of the BTS. For details,

see 4.4 Checking the Alarm Information of the BTS

(on the LMT)

.

Commission the antenna system. The commissioning consists of the following items: output power of the

TRXs, voltage standing wave ratio (VSWR), and connection between the antenna system and BTS. For

details, see 6.1 Commissioning the Antenna

System

.

Mandato ry

Mandato ry

Optional

6 Operation on the

BSC LMT

Perform the channel loopback test on the LMT to ensure the normal operation of the signaling channel

and service channel. For details, see 6.2 Performing the Loopback Test

.

Commission the CS services and PS services. For

details, see 4.5 Commissioning the BTS Services .

Optional

7

8

Operation requiring for the cooperatio n of the

BTS side and BSC side.

Check the environment monitoring alarm. For details,

see 4.6.2 Checking the Environment Monitoring

Alarms on the LMT

.

Mandato ry

Mandato ry l Commissioning procedure in transmission unavailable scenario

In transmission unavailable scenario, the BTS commissioning consists of two phases: In the initial phase of the commissioning, the transmission cables between the BSC and the

BTS are not properly connected. Commission the BTS at the local end. In the later phase of the commissioning, the transmission cable between the BSC and the BTS is properly connected. Commission the BTS on the LMT.

Issue 02 (2009-04-20) Huawei Proprietary and Confidential

Copyright © Huawei Technologies Co., Ltd.

3-3

3 Commissioning Procedure

Figure 3-2 Commissioning procedure (transmission unavailable)

Run

BTS3900(A) GSM

Commissioning Guide

Local operation before the transmission is available

Run the Site Maintenance Terminal

Configure the basic data of the site

Check the active software version

Check the transmission

between the BBU and the RFU locally

Check the operation of the BTS

Check the hardware connections of the BTS

Wait till the transmission is available

Remote operation after the transmission is available

Run the BSC LMT

Check the transmission and networking

Check the consistency between hardware installation and data configuration

Check the alarm information of the BTS

Cooperation of the local and remote operation after the transmission is available

Commission the BTS services

Check the BTS environment alarms

End

3-4 Huawei Proprietary and Confidential

Copyright © Huawei Technologies Co., Ltd.

Issue 02 (2009-04-20)

BTS3900(A) GSM

Commissioning Guide 3 Commissioning Procedure

Table 3-2 Commissioning procedure (transmission unavailable)

No.

1

2

3

4

5

6

7

8

9

10

Operation on the

BTS side.

Operation on the

BSC LMT

Operation Procedure

Run the Site Maintenance Terminal. For details, see

5.1 Starting the Site Maintenance Terminal .

Configure the basic data of the BTS such as boards of the BTS and logical objects of the site to ensure that the SMT can support the local commissioning tasks.

For details, see 5.2 Configuring the Basic Data of the BTS

.

Check the active software version. For details, see 5.3

Checking the Active Software Version on the

SMT .

Check the transmission between the BBU and RFU.

For details, see 5.4 Checking the Transmission

Between the BBU and RFU on the BTS Side

.

Check the running status of the BTS. The procedure for checking the running status of the BTS involves checking the state of LEDs and alarm information. For

details, see 5.5 Checking the Running Status of the

BTS

.

Check the hardware connection of the BTS. For

details, see 5.6 Checking the Hardware Connection of the BTS

.

Commission the antenna system. The commissioning consists of the following items: output power of the

TRXs, VSWR, and connection between the antenna system and the BTS. For details, see

6.1

Commissioning the Antenna System

.

Wait till the transmission is available.

Run the BSC LMT software. For details, see

4.1

Starting the LMT

.

Check the transmission and networking to ensure that the transmission between the BBU and BSC, BBU and

RFU, cascaded BBUs, and cascaded RFUs is normal.

For details, see

4.2 Checking the Transmission and

Networking

.

Check the software version and configuration data.

For details, see 4.3 Checking Software Version and

Data Configuration

.

Mandat ory/

Optiona l

Mandato ry

Mandato ry

Mandato ry

Mandato ry

Mandato ry

Mandato ry

Optional

Mandato ry

Mandato ry

Mandato ry

Issue 02 (2009-04-20) Huawei Proprietary and Confidential

Copyright © Huawei Technologies Co., Ltd.

3-5

3 Commissioning Procedure

BTS3900(A) GSM

Commissioning Guide

----End

No.

11

12

13 Operation requiring

14 for the cooperatio n of the

BTS side and BSC side.

Operation Procedure

Check the alarm information of the BTS. For details,

see 4.4 Checking the Alarm Information of the BTS

(on the LMT)

.

Perform the channel loopback test on the LMT to ensure the normal operation of the signaling channel

and service channel. For details, see 6.2 Performing the Loopback Test .

Commission the CS services and PS services. For details, see

4.5 Commissioning the BTS Services

.

Check the environment monitoring alarm. For details, see

4.6.2 Checking the Environment Monitoring

Alarms on the LMT .

Mandat ory/

Optiona l

Mandato ry

Optional

Mandato ry

Mandato ry

3-6 Huawei Proprietary and Confidential

Copyright © Huawei Technologies Co., Ltd.

Issue 02 (2009-04-20)

advertisement

Related manuals

advertisement

Table of contents