Step 11: The underside of the rail must be at least 2” above the stair tread nose to provide clearance for the footrest. T o achieve this 2” clearance move the rail and bracket forward. Once the clearance is 2” tighten all bracket nuts to hold the brackets in position. To maintain the 2” clearance, and to hold the rail in place, secure the bottom bracket to the first step from the floor with 2-2” wood screws, using a 3/8 nut driver on a 6-10” extension of a cordless drill.
C. CHASSIS INSTALLATION
Step 1: Remove plastic bag from chassis box. Lift the chassis with the manual override hole (on bottom) facing the downhill side of the stairs and gently slide the chassis onto the rail until it makes contact with the plastic rack. DO NOT LET THE CHASSIS
FREE FALL DOWN THE RAIL.
CAUTION! Be careful not to trap fingers between the rail and the chassis.
Step 2: Remove the safety tie and turn the red “ON/OFF” switch to the “ON” position (I).
Step 3: Use the installation switch (the black switch on the top of the chassis) to move the chassis at least two (2) feet down the rail, pushing gently on the chassis to ensure the chassis does not pull any rack to the top.
Step 4: Loosen, but do not remove, the four (4) seat-leveling bolts two (2) on each side of the chassis) and then align them vertically using a level. Firmly tighten the two
(2) bolts on the side of the chassis facing the wall.
CAUTION! Do not ride on the chassis or lift until the install is complete.
Pinnacle Stair Lift manual | | www.Harmar.com | 866-351-2776 7