Selecting the place of installation
Select a place which gives a true picture of the environment or process; also select a place that is as clean as possible. Air should circulate freely around the sensor.
It is recommended that the sensor head is installed directly in the process through the ball valve assembly. When the ball valve assembly is used, the chamber or the duct does not have to be emptied or shut down for installation or removal of the probe. Install the sensor head transversely against the direction of the process flow.
If the probe head has to be installed aside of the process gas flow or the process is very hot or particularly dirty, the probe can be installed in a “leak-through” position. In this installation, the probe is mounted behind the ball valve assembly and if necessary, a cooling coil and/or a filter can be mounted in between. The flow passes through the sensor head and leaks out through a vent hole in the fitting body enabling a reasonable response time. In hot and dirty processes, a sample system can also be used.
Mounting the transmitter
In F IGURE 3-1 and F IGURE 3-2 , you can see the dimensions of the
DMP248 transmitter:
V AISALA __________________________________________________________________________ 7
OPERATING MANUAL _______________________________________________________________
104
CL ENT
120
NOTE
ø6.5
65
F IGURE 3-1
133
145
Dimensions of the DMP248 electronics housing (in mm).
1.
Always mount the transmitter housing with the cable bushings pointing downwards to ensure IP65 (NEMA4) rating
2.
Make sure that the connection cable has the right thickness
( ∅ 7...10 mm) and that the cable bushing is carefully tightened.
3.
Pay always special attention to closing the transmitter cover carefully and remember to tighten all four screws.
PROBE
PUSHED
DOWN
ø5.5
178
149 cable length
2, 5 or 10 m
PROBE UP clasp nut fitting body adjustment range120 mm non leaking screw (A)
(factory setting) or leak screw (B)
(included in the package)
31
F
IGURE
3-2
ø13.5
Probe dimensions (in mm).
29
R1/2 ISO 7/1
8 _____________________________________________________________________M210492 EN A
advertisement
Related manuals
advertisement
Table of contents
- 5 CHAPTER 1 GENERAL INFORMATION
- 7 CHAPTER 2 PRODUCT DESCRIPTION
- 10 Use in high pressure
- 11 CHAPTER 3 INSTALLATION
- 13 Mounting; overview
- 14 Mounting the probe directly to the process
- 15 Installing the probe through the ball valve assembly
- 21 Mounting the probe with a quick connect
- 22 Sample cell
- 24 Grounding
- 26 Connections
- 27 Connection to an AC supply
- 29 CHAPTER 4 COMMISSIONING
- 37 CHAPTER 5 COMMANDS
- 59 CHAPTER 6 CALIBRATION AND ADJUSTMENT
- 60 Two-point calibration and adjustment adjustment procedure
- 60 Using serial commands
- 61 Using display/keypad commands
- 62 Using LED commands
- 63 Humidity calibration table
- 63 One point offset correction
- 63 Using serial commands
- 64 Using display/keypad commands
- 64 Using LED commands
- 65 Two-point temperature calibration and adjustement
- 65 Using serial commands
- 66 Using display/keypad commands
- 66 Using LED commands
- 67 Using serial commands
- 67 Using display/keypad commands
- 68 Using LED commands
- 71 CHAPTER 7 MAINTENANCE
- 76 CHAPTER 8 TECHNICAL DATA
- 80 CHAPTER 9 OPTIONS
- 81 CHAPTER 10 SPARE PARTS AND ACCESSORIES
- 83 APPENDIX 1 SERIAL COMMANDS
- 105 APPENDIX 2 POWER SUPPLY MODULE
- 109 APPENDIX 3 INSTALLING AND USING THE RS 485/422 SERIAL PORT MODULE
- 119 APPENDIX 4 INSTALLING AND USING THE CURRENT LOOP MODULE
- 129 APPENDIX 5 ERROR MESSAGES
- 133 APPENDIX 6 WIRING DIAGRAM
- 135 APPENDIX 7 ALARM OUTPUT UNIT
- 141 APPENDIX 8 PRESSURE CONVERSION CHART
- 141 Multiplication factors