advertisement
short-circuit protection. PD380/630AFH-A-Y1 AC distribution cabinet is not supposed to be directly connected to the secondary side of a transformer with capacity greater than 1000kVA. An extra distribution cabinet should be used between PD380/630AFH-A-Y1 AC distribution cabinet and the transformer for short-circuit protection.
2. Generator
If the load of the power supply system is more than 50% of the generator capacity, when the higher harmonic current generated by the rectifiers passes the stator winding of the synchronous generator, the voltage waveform will be severely distorted, which will have two effects. One is, it will cause unstable running and mechanical vibration of the generator; and the other is, the harmonic current will make the generator overheat, thus accelerating the insulation ageing of the generator. This is not only harmful to the generator, but also affects the stable running of the power supply system. Therefore, the load of the power supply system should not exceed 50% of the generator capacity. It should be calculated based on the apparent power. A simple calculation of the generator capacity is: output voltage (taken as 60V) × output current (take the final configuration) × 2.
The power factor and excitation model of the generator should also be taken into consideration when selecting a generator. Brushless generator of fundamental wave excitation model should be used with caution.
Safety Protection
Lightning protection & surge protection
The lightning protection and earthing system of telecom stations should comply with relevant standards.
The power supply system is equipped with a Class- C SPD. To achieve better surge protection, it is recommended to mount Class-B SPD before the AC mains is connected to the system. The mounting of Class-B SPD is shown in Figure 20 .
Class-B SPD should be purchased and mounted by the user. If condition permits, it is recommended that the cable length between the Class-B SPD and the AC distribution unit of the power supply system range between 5 ~ 10m. And this section of cable should be routed indoors to avoid direct lightning strike. When mounting the Class-B SPD, attention should be paid to the sectional area and length of the cable connecting the Class-B SPD: the sectional area should be no less than 25mm 2 , the cable should be as short as possible, and so is the earth cable of the Class-B SPD. The SPDs should be inspected periodically to ensure their normal operation.
Figure 20: Diagram of SPD mounting & system earthing
Vertiv | NetSure 801 CAA Series Power Supply System Instruction Manual 33
advertisement
Related manuals
advertisement
Table of contents
- 5 Safety Precautions
- 5 Electrical Safety
- 6 Battery
- 7 Others
- 8 OVERVIEW
- 8 Model Information
- 8 Overview
- 9 Components
- 9 Rectifier
- 11 Controller
- 11 AC Distribution Cabinet
- 16 DC Distribution Cabinet
- 24 Rectifier Cabinet
- 29 installation preparation
- 29 Installation Requirements
- 29 Environmental Requirements
- 29 Layout Requirements of The Equipment Room
- 32 Power Supply
- 33 Safety Protection
- 34 Equipment Running Environment Checklist
- 36 Storage Conditions
- 36 Installation Preparation
- 40 Unpacking Inspection
- 42 Installation
- 42 Cabinet Installation
- 42 Cabinet Placement
- 43 Mounting Large Side Door And Small Side Door
- 43 Installation on The Floor
- 45 Installation on Supporting Rack
- 46 Parallel Connection Between Cabinets
- 46 Parallel Connection with Copper Bars
- 49 Connecting Power Cables
- 50 Connecting Earth Cable
- 52 Distribution Cabinet
- 55 Connecting AC Input Cables
- 57 Connecting DC Emergency Lighting Cables (Optional)
- 58 Connecting DC Load Cables
- 59 Connecting Battery Cables
- 60 Installation Checklist
- 61 Installing Rectifier and Controller
- 61 Installing Rectifier
- 62 Installing Controller
- 63 Board
- 66 Cable
- 66 Connecting Rectifier Cabinet Communication Cable
- 68 Cabinet
- 69 Connecting Communication Cable of Distribution Cabinet
- 71 Installing Options
- 71 Installing Temperature Sensor
- 73 Testing
- 73 Note on Testing
- 73 Power-on
- 75 Setting Basic Parameters
- 75 Setting DIP Switch
- 76 Setting Basic Parameters for Controller
- 82 Checking Alarm and Operation Status
- 82 Testing Controller
- 84 Testing AC Distribution
- 85 Testing DC Distribution
- 86 Access Controller Through Web
- 94 Operation
- 94 Power Distribution LCD Operation
- 96 Controller Operation of Rectifier Cabinet
- 96 System Alarm and Status
- 96 Distribution Parameters Setting
- 96 Setting the Position Number of The Rectifier Manually
- 100 Adding Load
- 100 Adding Rectifier
- 101 Maintenance
- 101 Maintenance Requirements
- 101 General
- 101 Maintenance Tools and Equipment
- 102 Reference Technical Specification for Maintenance
- 104 Routine Maintenance Items
- 107 Routine Maintenance
- 108 Basic Inspection
- 108 Handling Controller Fault
- 108 Handling Rectifier Fault
- 110 Replacing Rectifier
- 111 Emergency Treatment
- 113 Appendix 1 Technical Parameters
- 116 Appendix 2 Alarm list
- 122 Appendix 3 ENGINEERING DESIGN DIAGRAM
- 138 APPENDIX 4 WIRING DIAGRAM
- 156 Appendix 5 SPARE PARTS