A er all previous steps have been completed, the unit is ready to be placed into operation. Follow these steps carefully.
1. Remove control valve cover by fi rst releasing the plastic clip from the back of the cover. Pull back of cover slightly outward and li up.
Note: The following steps will require turning the indicator knob ( and ) to various positions. Manually rotate the camsha
COUNTERCLOCKWISE
only until indicator knob points to desired position. (See manual regeneration sections for each control’s manual operation.)
2. Rotate indicator knob
COUNTERCLOCKWISE
until it points directly to the word
BACKWASH
.
3. Fill media tank with water.
a. With water supply off , place the bypass valve(s) into the “not in bypass” position.
b. Open water supply valve very slowly to approximately the 1/4 open position.
IMPORTANT
: If opened too rapidly or too far, media may be lost. In the 1/4 open position, you should hear air escaping slowly from the drain line.
c. When all of the air has been purged from the tank
(water begins to fl ow steadily from the drain), open the main supply valve all the way.
d. Allow water to run to drain until clear.
about fi ve minutes. This will allow all trapped air to escape from the tank.
4, Add water to brine tank (initial fi ll).
With a bucket or hose, add approximately
4 gallons (15 liters) of water to brine tank. If the tank has a salt platform above the bo om of the tank, add water until the level is approximately 1 inch (25 mm) above the platform.
5 Place the conditioner into operation.
a. With the water supply valve completely open, carefully advance the indicator knob
COUNTERCLOCKWISE
to the center of the
BRINE REFILL
position. Hold at this position until water starts to fl ow through the brine line into the brine tank. Do not run for more than one or two minutes.
b. Advance the indicator knob
COUNTERCLOCKWISE
until it points to the center of the
BRINE/SLOW RINSE
position.
c. With the conditioner in this position, check to see if water is being drawn from the brine tank.
The water level in the brine tank will recede very slowly. Observe water level for at least three minutes. If the water level does not recede, or if it goes up, reference the
Troubleshooting
section.
d. Advance the indicator knob
COUNTERCLOCKWISE
to the
SERVICE
position and run water from a nearby faucet until the water is clear and so .
Electrical Connection
100 VAC, 115 VAC, and 230 VAC units
: Remove twist tie from the power cord and extend cord to its full length.
Make sure power source matches the rating printed on the control. Be certain a wall switch does not control the outlet.
12 VAC
: Connect the plug of the transformer (supplied) secondary cable to the mating socket at the rear or bo om of the timer housing. Be certain the transformer is secure and is plugged into a power source of correct voltage that is not controlled by a wall switch.
Ion Exchange
Cation resin is used to create the ion-exchange process wherein dissolved minerals are removed and replaced with sodium ions.
| 6 | ProFlow Eliminator